SlideShare a Scribd company logo
London Ambulance Service
      System Failure
           1992

     Craig Houston   Fraser Hall
Overview
• On 26th October 1992 the London Ambulance Service
  started using a new Computer Aided Dispatch system.
   – Aims:
      • Improve efficiency
      • Control resources efficiently
      • Decrease personnel requirements
• The system failed:
   – The system could not cope with the load placed on it by
     normal use;
   – The response to emergency calls was several hours;
   – Ambulance communications failed and ambulances were
     lost from the system.
Time Line of Events



1.   Need Discovered – Early 1980’s
2.   Anderson Report Produced – Autumn 1990
3.   Project Put to tender - 7 February 1991
4.   Contractor decided – August 1991
5.   Project Development – June 1991 -> 8th January 1992
6.   System Integration - October 1992
7.   System Fails – 26th October 1992 – 4th November 1992
London Ambulance Service
                              LAS


• Largest Ambulance Service in the world
• Around 4,000 staff at over 70 stations
• Carries over 5,000 patients every day.
• Receives 2,000-2,500 calls each day
   – Only 1,300 to 1,600 are emergency calls

• Area covers 620 miles2
Manual System
• Call taking
   – Recorded on form
   – Location identified on map
   – Form sent to central collection point
• Resource identification
   –   Form Collected – duplicates removed
   –   Passed onto region assigned resource allocator
   –   Resource allocator decides on crew to be mobilised
   –   Form updated – passed to dispatcher
• Resource mobilisation
   – Dispatcher contacts ambulance station
   – Or passed onto radio operator if ambulance is already mobile
• Whole process meant to take < 3 minutes
Computer Aided Dispatch
• Existing systems dismissed as inadequate and impossible to
  modify to meet LAS’s needs
   – Intended functionality was more than manual system could cope with.
• Desired system:
   – To consist of Computer Aided Dispatch; Computer map display;
     Automatic Vehicle Location System (AVLS);
   – Must integrate with existing Mobile Data Terminals and the Radio
     Interface System.
• Success dependent upon:
   – Near 100% accuracy and reliability of technology;
   – Absolute cooperation from all parties including CAC staff and
     ambulance crews.
Communication Infrastructure




                 *Taken from Report of the Inquiry Into The London Ambulance Service
What Went Wrong?
• When the system was adopted several issues
  arose from its first use:
  – Ambulance locations were incorrect or not shown
  – Call taking created exceptions which created a greater
    work load
  – Ambulance response time became unacceptable
• Many reports have been produced on what went
  wrong:
  – From its conception to its integration the project
    management and process were doomed to fail.
Project Assignment
• How it was done
  – The project was put out to tender.
  – Report by Arthur Andersen
     • Suggested budget of £1.5Million and time-frame for
       development & testing 19 months, longer if a
       consortium was given project.
     • Report was mostly ignored
        – Cheapest bidder chosen
        – Consortium given strict deadline of 6 months development
            » Significantly less than the 19 months set as industry
              standard
Project Assignment
                             Continued


• A consortium consisting of Apricot, Systems
  Options and Datatrak given the project
  – Their proposal of £937k was £700k cheaper than next
    bidder
     • No questions were asked as to this figure.
  – Systems Options were to develop the CAD software
     • Previous experience of emergency service systems was
       limited to an administrative system
     • No experience of high integrity systems
  – There was no official designation of who were to
    manage the project.
System Design
• System requirements:
  – Need for 100% reliability
     • System was never 100% reliable.
     • Strict deadline meant testing was unacceptable.
     • Fail safe measures never tested.
  – Must be able to cope with unexpected events/data
     • System never expected incomplete information
         – Exceptions when this occurred took up vital computation time
     • Exceptions were not prioritised and took up vital processing
  – Efficiency is key to system
     • System could not cope with volume of traffic
     • Never tested to full capacity
         – Failed to achieve suitable level of performance for normal work load
System Design
                              Continued

– Must be able to de-duplicate calls
   • System failed to identify duplicate calls
   • More traffic within the system caused:
       – resource allocation issues
       – Processing performance diminution
– Communication of information is vital
   • Communication channels expected to be 100% reliable by system
       – Passed back incomplete information which system failed to handle
         correctly
   • Poor interface between Ambulance crew, MDTs & the system
– Must be easy to use for staff
   • Staff were used to old system and had to be trained to use new
     system
System Implementation
• Problems:
  – Time-frame too short
     • Developers saw deadlines as rigid
        – Rush to complete software liable to generate problems
     • Testing time was inadequate for critical system
     • Development team had doubts on feasibility of system
        – They did not reflect their feelings onto management
System Integration
• Problems:
  – Adoption too soon
      • Users not ready
            – Changed control room layout confusing to staff
            – Complete change from original system without significant training
            – Two groups of users:
                  » Separate training left users unsure of each others roles
      • System not ready
            – Backup server not tested properly.
            – Inadequate full load testing
            – Data transmission problems
  – Staff
      • Opposed to new system
            – Unwilling to learn/use new system
            – Lack of trust in new system
      • Not consulted over the new system
            – Development missed out on meeting staff needs.
            – Limited involvement in testing therefore testing of typical use not fulfilled
Project Management
• Problems:
  – Break down in relationship between staff and management following new
    initiatives introduced
      • Lack of trust in any new system.
      • Little communication between management and staff meant issues were unresolved
  – Contractor
      • Board of management were misled into the lead contractors ability and pass experience
        of emergency service systems
      • High risk by management in offering project to small software house company with little
        experience of high integrity systems.
  – project management throughout the development and implementation
    process was inadequate and at times ambiguous.
      •   A major systems integration project such as CAD requires full time. professional,
          experienced project management. This was lacking;
  – Scale of change and speed of change were too aggressive for the
    circumstances
Project Management
                          Continued


– Poorly defined Management structure
   • No party took ownership from start
       – Systems Options assumed to be responsible
       – Became too busy and London Ambulance Service management took
         over
   • Executive Directors took control of minor problems
       – Should have been left to lower level management
   • Evaluation team:
       – Systems Manager – Ambulance crewman with many years
         experience: No IT knowledge
           » Replaced by IT expert – too late
       – Analyst – Contractor with 5 years experience with LAS
   • Structure inflexible from structure before project lead to problems
     in communication
Project Management
                          Continued



– Lack of defined communication channels
   • Concerns Raised at meetings never followed up
   • Staff unable to reflect issues on to management
   • Development team issues unresolved due to strict deadlines
Assignment To Integration                          What Should Have Been Done?

•   Assignment
     – The project should have been assigned to a consortium or company with prior
       experience
     – Lowest cost should not have been deciding factor
     – More attention should have been made on Anderson report.
•   Implementation
     –   Timetable should have been better calculated
     –   Testing should not have been passed by
     –   Independent testing should have been carried out
     –   Development teams concerns should have been raised earlier
•   Integration
     – Training should have been more focused
     – Mixed training (i.e. users from all parts of process) should have been carried out
          • Highlight the role of different teams so user knows the whole system
     – User issues never addressed.
     – Backup should have been tested
     – Manual fallback system should have been in place.
Project Management                    What Should Have Been Done?


• Project Management
   – Management and staff issues prior to the new system development should
     have been resolved to gain staff’s trust and support
   – Communication channels should have been setup between staff and
     management.
       • Staff delegate to raise concerns of staff
   – Better definition of project ownership
       • LAS should not have to own project as they have little experience of system
         development
   – Project management should have outlined to development teams that
     deadlines were not strict in the interest of better system
   – Formal recording of concerns should have been used
       • Concerns should be followed up.
       • Delegation of ownership of concern to member of management would ensure
         concern is addressed
       • Problems not given thorough analysis.
Project Management                 What Should Have Been Done?


– Project should have been split into phases instead of a single process
    • Ensure that each phase is complete before next is begun
    • Creates quality assurance at each stage
    • Clearly defined structure more likely to achieve system targets.
– An IT manager should be appointed to sit on LAS board
    • It is their role to coordinate between LAS board and the system
      development contractor
    • Experience in IT is essential to allow good project management and
      communication between non IT board members and the project team.
    • Separate Executive Directors from the project team to restrict
      interference.
– A report should have been commissioned to be completed before
  adoption which could have outlined the problems before they
  occurred.
Project Management                 What Should Have Been Done?

– LAS Board failed to follow PRINCE Project Management method
    • Projects in Controlled Environments
    • Shows Corporate and Project Management separation.




– Management had little/no training over the years to prepare them for such a
  project.
– Ambiguity over project management
– High Integrity system projects should have full-time professional management.
Summary
• Project was doomed from the start:
   – Assignment of project to contractor was riddled with issues
   – Development of the project was too aggressive and quick for the
     circumstances
   – Integration of the system was unstructured and completed too soon.
• Management Problems
   – Management was unstructured
   – Too ambiguous at every level
   – Communication channels were unclear
• Many issues could have been avoided through better project
  management.
• Questions.
References

• Report of the Inquiry Into The London Ambulance Service - Anthony
   Finkelstein
• A Comedy of Errors: the London Ambulance Service case study – Anthony
   Finkelstein
• Overview of LAS Failure – Ian Sommerville
• CAD Failure LAS – ambulance.freeuk
• Software failure: management failure – Stephen Flowers

More Related Content

What's hot

New 7 QC Tools Module 2 | Interrelationship Digraph
New 7 QC Tools Module 2 | Interrelationship DigraphNew 7 QC Tools Module 2 | Interrelationship Digraph
New 7 QC Tools Module 2 | Interrelationship Digraph
Shakehand with Life
 
8 Wastes of Lean
8 Wastes of Lean8 Wastes of Lean
8 Wastes of Lean
Praneet Surti
 
Continuous improvement & pdca
Continuous improvement & pdcaContinuous improvement & pdca
Continuous improvement & pdca
Shoilen Sannamat
 
Process improvement
Process improvementProcess improvement
Process improvement
aolrac
 
Value Stream Mapping Process
Value Stream Mapping ProcessValue Stream Mapping Process
Value Stream Mapping Process
Anand Subramaniam
 
Principles of logistics_information
Principles of logistics_informationPrinciples of logistics_information
Principles of logistics_information
MuthuPandi100
 
Lean Six Sigma methodology
Lean Six Sigma methodologyLean Six Sigma methodology
Lean Six Sigma methodology
Ramiro Cid
 
Gemba Walk
Gemba WalkGemba Walk
FedEx
FedExFedEx
Lean Leadership: Part 1 of 3
Lean Leadership: Part 1 of 3Lean Leadership: Part 1 of 3
Lean Leadership: Part 1 of 3
TKMG, Inc.
 
Fundamentals of Lean
Fundamentals of LeanFundamentals of Lean
Fundamentals of Lean
Kirk Hazen, P.E.
 
" Gemba walk for Lean Leaders. ; by Zeeshan Syed LSSGB "
 " Gemba walk for Lean Leaders.  ; by Zeeshan Syed LSSGB " " Gemba walk for Lean Leaders.  ; by Zeeshan Syed LSSGB "
" Gemba walk for Lean Leaders. ; by Zeeshan Syed LSSGB "
Zeeshan Syed
 
LeanCor Consulting Webinar: The PFEP – How to Create Standardization in Mater...
LeanCor Consulting Webinar: The PFEP – How to Create Standardization in Mater...LeanCor Consulting Webinar: The PFEP – How to Create Standardization in Mater...
LeanCor Consulting Webinar: The PFEP – How to Create Standardization in Mater...
LeanCor Supply Chain Group
 
5S For The Office by Operational Excellence Consulting
5S For The Office by Operational Excellence Consulting5S For The Office by Operational Excellence Consulting
5S For The Office by Operational Excellence Consulting
Operational Excellence Consulting
 
Management information systems in DHL
Management information systems in DHLManagement information systems in DHL
Management information systems in DHL
Vishnu V S
 
Six Sigma DMAIC Case Study
Six Sigma DMAIC Case StudySix Sigma DMAIC Case Study
Six Sigma DMAIC Case Study
Body of Knowledge
 
Lean ppt
Lean pptLean ppt
Lean ppt
shoban44
 
Business process modelling
Business process modellingBusiness process modelling
Business process modelling
Kiito25
 
Value Steam Mapping
Value Steam MappingValue Steam Mapping
Value Steam Mapping
antiquealterego
 
Types of waste - lean Concept Krishna Heda
Types of waste - lean Concept Krishna HedaTypes of waste - lean Concept Krishna Heda
Types of waste - lean Concept Krishna Heda
krishnaheda
 

What's hot (20)

New 7 QC Tools Module 2 | Interrelationship Digraph
New 7 QC Tools Module 2 | Interrelationship DigraphNew 7 QC Tools Module 2 | Interrelationship Digraph
New 7 QC Tools Module 2 | Interrelationship Digraph
 
8 Wastes of Lean
8 Wastes of Lean8 Wastes of Lean
8 Wastes of Lean
 
Continuous improvement & pdca
Continuous improvement & pdcaContinuous improvement & pdca
Continuous improvement & pdca
 
Process improvement
Process improvementProcess improvement
Process improvement
 
Value Stream Mapping Process
Value Stream Mapping ProcessValue Stream Mapping Process
Value Stream Mapping Process
 
Principles of logistics_information
Principles of logistics_informationPrinciples of logistics_information
Principles of logistics_information
 
Lean Six Sigma methodology
Lean Six Sigma methodologyLean Six Sigma methodology
Lean Six Sigma methodology
 
Gemba Walk
Gemba WalkGemba Walk
Gemba Walk
 
FedEx
FedExFedEx
FedEx
 
Lean Leadership: Part 1 of 3
Lean Leadership: Part 1 of 3Lean Leadership: Part 1 of 3
Lean Leadership: Part 1 of 3
 
Fundamentals of Lean
Fundamentals of LeanFundamentals of Lean
Fundamentals of Lean
 
" Gemba walk for Lean Leaders. ; by Zeeshan Syed LSSGB "
 " Gemba walk for Lean Leaders.  ; by Zeeshan Syed LSSGB " " Gemba walk for Lean Leaders.  ; by Zeeshan Syed LSSGB "
" Gemba walk for Lean Leaders. ; by Zeeshan Syed LSSGB "
 
LeanCor Consulting Webinar: The PFEP – How to Create Standardization in Mater...
LeanCor Consulting Webinar: The PFEP – How to Create Standardization in Mater...LeanCor Consulting Webinar: The PFEP – How to Create Standardization in Mater...
LeanCor Consulting Webinar: The PFEP – How to Create Standardization in Mater...
 
5S For The Office by Operational Excellence Consulting
5S For The Office by Operational Excellence Consulting5S For The Office by Operational Excellence Consulting
5S For The Office by Operational Excellence Consulting
 
Management information systems in DHL
Management information systems in DHLManagement information systems in DHL
Management information systems in DHL
 
Six Sigma DMAIC Case Study
Six Sigma DMAIC Case StudySix Sigma DMAIC Case Study
Six Sigma DMAIC Case Study
 
Lean ppt
Lean pptLean ppt
Lean ppt
 
Business process modelling
Business process modellingBusiness process modelling
Business process modelling
 
Value Steam Mapping
Value Steam MappingValue Steam Mapping
Value Steam Mapping
 
Types of waste - lean Concept Krishna Heda
Types of waste - lean Concept Krishna HedaTypes of waste - lean Concept Krishna Heda
Types of waste - lean Concept Krishna Heda
 

Viewers also liked

Las Failure
Las FailureLas Failure
Las Failure
guestc990b6
 
Las Failure
Las FailureLas Failure
Las Failure
guestc990b6
 
London Ambulance Problems
London Ambulance ProblemsLondon Ambulance Problems
London Ambulance Problems
KennyBHS
 
Pci lecture 2 software it failures (1)
Pci lecture 2 software it failures (1)Pci lecture 2 software it failures (1)
Pci lecture 2 software it failures (1)
cooper0236
 
Ppt on datalogger+digital modulation english
Ppt on datalogger+digital modulation englishPpt on datalogger+digital modulation english
Ppt on datalogger+digital modulation english
Bhupesh Jha
 
AOL - Time Warner Merger And Its Failure
AOL - Time Warner Merger And Its FailureAOL - Time Warner Merger And Its Failure
AOL - Time Warner Merger And Its Failure
Vivek Vadakkuppattu
 
intelligent ambulance system idea
intelligent ambulance system idea intelligent ambulance system idea
intelligent ambulance system idea
Nishanth Smartboy
 
intelligence Ambulance project report
intelligence Ambulance project reportintelligence Ambulance project report
intelligence Ambulance project report
Ritesh Kumar
 
Digital Communication ppt
Digital Communication pptDigital Communication ppt
Digital Communication ppt
BZU lahore
 
Etude de marché
Etude de marchéEtude de marché
Etude de marché
Patrice Lumu Mussinga
 
Digital communication systems
Digital communication systemsDigital communication systems
Digital communication systems
Nisreen Bashar
 
What Makes Great Infographics
What Makes Great InfographicsWhat Makes Great Infographics
What Makes Great Infographics
SlideShare
 
Masters of SlideShare
Masters of SlideShareMasters of SlideShare
Masters of SlideShare
Kapost
 
STOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
STOP! VIEW THIS! 10-Step Checklist When Uploading to SlideshareSTOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
STOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
Empowered Presentations
 
You Suck At PowerPoint!
You Suck At PowerPoint!You Suck At PowerPoint!
You Suck At PowerPoint!
Jesse Desjardins - @jessedee
 
10 Ways to Win at SlideShare SEO & Presentation Optimization
10 Ways to Win at SlideShare SEO & Presentation Optimization10 Ways to Win at SlideShare SEO & Presentation Optimization
10 Ways to Win at SlideShare SEO & Presentation Optimization
Oneupweb
 
How To Get More From SlideShare - Super-Simple Tips For Content Marketing
How To Get More From SlideShare - Super-Simple Tips For Content MarketingHow To Get More From SlideShare - Super-Simple Tips For Content Marketing
How To Get More From SlideShare - Super-Simple Tips For Content Marketing
Content Marketing Institute
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & Tricks
SlideShare
 

Viewers also liked (18)

Las Failure
Las FailureLas Failure
Las Failure
 
Las Failure
Las FailureLas Failure
Las Failure
 
London Ambulance Problems
London Ambulance ProblemsLondon Ambulance Problems
London Ambulance Problems
 
Pci lecture 2 software it failures (1)
Pci lecture 2 software it failures (1)Pci lecture 2 software it failures (1)
Pci lecture 2 software it failures (1)
 
Ppt on datalogger+digital modulation english
Ppt on datalogger+digital modulation englishPpt on datalogger+digital modulation english
Ppt on datalogger+digital modulation english
 
AOL - Time Warner Merger And Its Failure
AOL - Time Warner Merger And Its FailureAOL - Time Warner Merger And Its Failure
AOL - Time Warner Merger And Its Failure
 
intelligent ambulance system idea
intelligent ambulance system idea intelligent ambulance system idea
intelligent ambulance system idea
 
intelligence Ambulance project report
intelligence Ambulance project reportintelligence Ambulance project report
intelligence Ambulance project report
 
Digital Communication ppt
Digital Communication pptDigital Communication ppt
Digital Communication ppt
 
Etude de marché
Etude de marchéEtude de marché
Etude de marché
 
Digital communication systems
Digital communication systemsDigital communication systems
Digital communication systems
 
What Makes Great Infographics
What Makes Great InfographicsWhat Makes Great Infographics
What Makes Great Infographics
 
Masters of SlideShare
Masters of SlideShareMasters of SlideShare
Masters of SlideShare
 
STOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
STOP! VIEW THIS! 10-Step Checklist When Uploading to SlideshareSTOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
STOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
 
You Suck At PowerPoint!
You Suck At PowerPoint!You Suck At PowerPoint!
You Suck At PowerPoint!
 
10 Ways to Win at SlideShare SEO & Presentation Optimization
10 Ways to Win at SlideShare SEO & Presentation Optimization10 Ways to Win at SlideShare SEO & Presentation Optimization
10 Ways to Win at SlideShare SEO & Presentation Optimization
 
How To Get More From SlideShare - Super-Simple Tips For Content Marketing
How To Get More From SlideShare - Super-Simple Tips For Content MarketingHow To Get More From SlideShare - Super-Simple Tips For Content Marketing
How To Get More From SlideShare - Super-Simple Tips For Content Marketing
 
How to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & TricksHow to Make Awesome SlideShares: Tips & Tricks
How to Make Awesome SlideShares: Tips & Tricks
 

Similar to Lascas Failure Learn A Big Lession From The Most Terrible Problems In The World

Proj Mgmt.ppt
Proj Mgmt.pptProj Mgmt.ppt
Proj Mgmt.ppt
NikhilDudka
 
Hi Maturity in the CMMI Services Context
Hi Maturity in the CMMI Services Context Hi Maturity in the CMMI Services Context
Hi Maturity in the CMMI Services Context
SPIN Chennai
 
10 - Project Management
10 - Project Management10 - Project Management
10 - Project Management
Raymond Gao
 
Adaptive case study on setting up of PMO for large it organization
Adaptive case study on setting up of PMO for large it organizationAdaptive case study on setting up of PMO for large it organization
Adaptive case study on setting up of PMO for large it organization
LN Mishra CBAP
 
Bse 3105 lecture 3-software evolution planning
Bse 3105  lecture 3-software evolution planningBse 3105  lecture 3-software evolution planning
Bse 3105 lecture 3-software evolution planning
Alonzee Tash
 
Manish tripathi-se-failure stories-12feb2017
Manish tripathi-se-failure stories-12feb2017Manish tripathi-se-failure stories-12feb2017
Manish tripathi-se-failure stories-12feb2017
A P
 
Leveraging IT Service Catalog to Transform Services Delivery - Argonne Nation...
Leveraging IT Service Catalog to Transform Services Delivery - Argonne Nation...Leveraging IT Service Catalog to Transform Services Delivery - Argonne Nation...
Leveraging IT Service Catalog to Transform Services Delivery - Argonne Nation...
Evergreen Systems
 
Systems Life Cycle
Systems Life CycleSystems Life Cycle
Systems Life Cycle
Nirmal PR
 
Replacing obsolete ERP software systems with Genio
Replacing obsolete ERP software systems with GenioReplacing obsolete ERP software systems with Genio
Replacing obsolete ERP software systems with Genio
Ricardo Marques
 
Christian Bk Hansen - Agile on Huge Banking Mainframe Legacy Systems - EuroST...
Christian Bk Hansen - Agile on Huge Banking Mainframe Legacy Systems - EuroST...Christian Bk Hansen - Agile on Huge Banking Mainframe Legacy Systems - EuroST...
Christian Bk Hansen - Agile on Huge Banking Mainframe Legacy Systems - EuroST...
TEST Huddle
 
Gac presentation
Gac presentationGac presentation
Gac presentation
JISC's Green ICT Programme
 
Major Pitfalls of ERP Implementation in Big Companies
Major Pitfalls of ERP Implementation in Big CompaniesMajor Pitfalls of ERP Implementation in Big Companies
Major Pitfalls of ERP Implementation in Big Companies
Mohammed Khaiata
 
Pulse2012 Trm Battelle Final
Pulse2012 Trm Battelle FinalPulse2012 Trm Battelle Final
Pulse2012 Trm Battelle Final
brockj
 
Proposal dms for dwf v2
Proposal   dms for dwf v2Proposal   dms for dwf v2
Proposal dms for dwf v2
Media-Mosaic
 
Sadchap04
Sadchap04Sadchap04
Chapter 04
Chapter 04Chapter 04
Chapter 04
andyburghardt
 
Software that truly supports good decisions
Software that truly supports good decisionsSoftware that truly supports good decisions
Software that truly supports good decisions
Utkan Uluçay, MSc., CDDP
 
Richard.laws
Richard.lawsRichard.laws
Richard.laws
NASAPMC
 
BTEC National in ICT: Unit 3 - Operational Issues
BTEC National in ICT: Unit 3 - Operational IssuesBTEC National in ICT: Unit 3 - Operational Issues
BTEC National in ICT: Unit 3 - Operational Issues
mrcox
 
Chap013.pptx
Chap013.pptxChap013.pptx
Chap013.pptx
FilizMizrak
 

Similar to Lascas Failure Learn A Big Lession From The Most Terrible Problems In The World (20)

Proj Mgmt.ppt
Proj Mgmt.pptProj Mgmt.ppt
Proj Mgmt.ppt
 
Hi Maturity in the CMMI Services Context
Hi Maturity in the CMMI Services Context Hi Maturity in the CMMI Services Context
Hi Maturity in the CMMI Services Context
 
10 - Project Management
10 - Project Management10 - Project Management
10 - Project Management
 
Adaptive case study on setting up of PMO for large it organization
Adaptive case study on setting up of PMO for large it organizationAdaptive case study on setting up of PMO for large it organization
Adaptive case study on setting up of PMO for large it organization
 
Bse 3105 lecture 3-software evolution planning
Bse 3105  lecture 3-software evolution planningBse 3105  lecture 3-software evolution planning
Bse 3105 lecture 3-software evolution planning
 
Manish tripathi-se-failure stories-12feb2017
Manish tripathi-se-failure stories-12feb2017Manish tripathi-se-failure stories-12feb2017
Manish tripathi-se-failure stories-12feb2017
 
Leveraging IT Service Catalog to Transform Services Delivery - Argonne Nation...
Leveraging IT Service Catalog to Transform Services Delivery - Argonne Nation...Leveraging IT Service Catalog to Transform Services Delivery - Argonne Nation...
Leveraging IT Service Catalog to Transform Services Delivery - Argonne Nation...
 
Systems Life Cycle
Systems Life CycleSystems Life Cycle
Systems Life Cycle
 
Replacing obsolete ERP software systems with Genio
Replacing obsolete ERP software systems with GenioReplacing obsolete ERP software systems with Genio
Replacing obsolete ERP software systems with Genio
 
Christian Bk Hansen - Agile on Huge Banking Mainframe Legacy Systems - EuroST...
Christian Bk Hansen - Agile on Huge Banking Mainframe Legacy Systems - EuroST...Christian Bk Hansen - Agile on Huge Banking Mainframe Legacy Systems - EuroST...
Christian Bk Hansen - Agile on Huge Banking Mainframe Legacy Systems - EuroST...
 
Gac presentation
Gac presentationGac presentation
Gac presentation
 
Major Pitfalls of ERP Implementation in Big Companies
Major Pitfalls of ERP Implementation in Big CompaniesMajor Pitfalls of ERP Implementation in Big Companies
Major Pitfalls of ERP Implementation in Big Companies
 
Pulse2012 Trm Battelle Final
Pulse2012 Trm Battelle FinalPulse2012 Trm Battelle Final
Pulse2012 Trm Battelle Final
 
Proposal dms for dwf v2
Proposal   dms for dwf v2Proposal   dms for dwf v2
Proposal dms for dwf v2
 
Sadchap04
Sadchap04Sadchap04
Sadchap04
 
Chapter 04
Chapter 04Chapter 04
Chapter 04
 
Software that truly supports good decisions
Software that truly supports good decisionsSoftware that truly supports good decisions
Software that truly supports good decisions
 
Richard.laws
Richard.lawsRichard.laws
Richard.laws
 
BTEC National in ICT: Unit 3 - Operational Issues
BTEC National in ICT: Unit 3 - Operational IssuesBTEC National in ICT: Unit 3 - Operational Issues
BTEC National in ICT: Unit 3 - Operational Issues
 
Chap013.pptx
Chap013.pptxChap013.pptx
Chap013.pptx
 

More from guestc990b6

Qc Vs Qa
Qc Vs QaQc Vs Qa
Qc Vs Qa
guestc990b6
 
Sigma Table
Sigma TableSigma Table
Sigma Table
guestc990b6
 
Monte Carlo
Monte CarloMonte Carlo
Monte Carlo
guestc990b6
 
Action Research - David Avison
Action Research  - David AvisonAction Research  - David Avison
Action Research - David Avison
guestc990b6
 
Software Engineering The Multiview Approach And Wisdm
Software Engineering   The Multiview Approach And WisdmSoftware Engineering   The Multiview Approach And Wisdm
Software Engineering The Multiview Approach And Wisdm
guestc990b6
 
Comparative Development Methodologies
Comparative Development MethodologiesComparative Development Methodologies
Comparative Development Methodologies
guestc990b6
 
Review Of Mutiview
Review Of MutiviewReview Of Mutiview
Review Of Mutiview
guestc990b6
 
Career Hub Rich Picture
Career Hub Rich PictureCareer Hub Rich Picture
Career Hub Rich Picture
guestc990b6
 
IED Classification Avison & Taylor
IED Classification   Avison & TaylorIED Classification   Avison & Taylor
IED Classification Avison & Taylor
guestc990b6
 
Comparison Of Methodologies
Comparison Of MethodologiesComparison Of Methodologies
Comparison Of Methodologies
guestc990b6
 
Rich Picture One Of The Tools
Rich Picture   One Of The ToolsRich Picture   One Of The Tools
Rich Picture One Of The Tools
guestc990b6
 
The Rich Picture A Tool For Reasoning About Work Context
The Rich Picture   A Tool For Reasoning About Work ContextThe Rich Picture   A Tool For Reasoning About Work Context
The Rich Picture A Tool For Reasoning About Work Context
guestc990b6
 

More from guestc990b6 (12)

Qc Vs Qa
Qc Vs QaQc Vs Qa
Qc Vs Qa
 
Sigma Table
Sigma TableSigma Table
Sigma Table
 
Monte Carlo
Monte CarloMonte Carlo
Monte Carlo
 
Action Research - David Avison
Action Research  - David AvisonAction Research  - David Avison
Action Research - David Avison
 
Software Engineering The Multiview Approach And Wisdm
Software Engineering   The Multiview Approach And WisdmSoftware Engineering   The Multiview Approach And Wisdm
Software Engineering The Multiview Approach And Wisdm
 
Comparative Development Methodologies
Comparative Development MethodologiesComparative Development Methodologies
Comparative Development Methodologies
 
Review Of Mutiview
Review Of MutiviewReview Of Mutiview
Review Of Mutiview
 
Career Hub Rich Picture
Career Hub Rich PictureCareer Hub Rich Picture
Career Hub Rich Picture
 
IED Classification Avison & Taylor
IED Classification   Avison & TaylorIED Classification   Avison & Taylor
IED Classification Avison & Taylor
 
Comparison Of Methodologies
Comparison Of MethodologiesComparison Of Methodologies
Comparison Of Methodologies
 
Rich Picture One Of The Tools
Rich Picture   One Of The ToolsRich Picture   One Of The Tools
Rich Picture One Of The Tools
 
The Rich Picture A Tool For Reasoning About Work Context
The Rich Picture   A Tool For Reasoning About Work ContextThe Rich Picture   A Tool For Reasoning About Work Context
The Rich Picture A Tool For Reasoning About Work Context
 

Recently uploaded

Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Jeffrey Haguewood
 
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdfUnlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Malak Abu Hammad
 
Nordic Marketo Engage User Group_June 13_ 2024.pptx
Nordic Marketo Engage User Group_June 13_ 2024.pptxNordic Marketo Engage User Group_June 13_ 2024.pptx
Nordic Marketo Engage User Group_June 13_ 2024.pptx
MichaelKnudsen27
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
innovationoecd
 
Serial Arm Control in Real Time Presentation
Serial Arm Control in Real Time PresentationSerial Arm Control in Real Time Presentation
Serial Arm Control in Real Time Presentation
tolgahangng
 
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Speck&Tech
 
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
saastr
 
Best 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERPBest 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERP
Pixlogix Infotech
 
How to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For FlutterHow to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For Flutter
Daiki Mogmet Ito
 
How to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptxHow to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptx
danishmna97
 
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdfMonitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Tosin Akinosho
 
Choosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptxChoosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptx
Brandon Minnick, MBA
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
panagenda
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc
 
UI5 Controls simplified - UI5con2024 presentation
UI5 Controls simplified - UI5con2024 presentationUI5 Controls simplified - UI5con2024 presentation
UI5 Controls simplified - UI5con2024 presentation
Wouter Lemaire
 
Taking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdfTaking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdf
ssuserfac0301
 
Ocean lotus Threat actors project by John Sitima 2024 (1).pptx
Ocean lotus Threat actors project by John Sitima 2024 (1).pptxOcean lotus Threat actors project by John Sitima 2024 (1).pptx
Ocean lotus Threat actors project by John Sitima 2024 (1).pptx
SitimaJohn
 
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing InstancesEnergy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
Alpen-Adria-Universität
 
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development ProvidersYour One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
akankshawande
 
Recommendation System using RAG Architecture
Recommendation System using RAG ArchitectureRecommendation System using RAG Architecture
Recommendation System using RAG Architecture
fredae14
 

Recently uploaded (20)

Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
Salesforce Integration for Bonterra Impact Management (fka Social Solutions A...
 
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdfUnlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
Unlock the Future of Search with MongoDB Atlas_ Vector Search Unleashed.pdf
 
Nordic Marketo Engage User Group_June 13_ 2024.pptx
Nordic Marketo Engage User Group_June 13_ 2024.pptxNordic Marketo Engage User Group_June 13_ 2024.pptx
Nordic Marketo Engage User Group_June 13_ 2024.pptx
 
Presentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of GermanyPresentation of the OECD Artificial Intelligence Review of Germany
Presentation of the OECD Artificial Intelligence Review of Germany
 
Serial Arm Control in Real Time Presentation
Serial Arm Control in Real Time PresentationSerial Arm Control in Real Time Presentation
Serial Arm Control in Real Time Presentation
 
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
Cosa hanno in comune un mattoncino Lego e la backdoor XZ?
 
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
Deep Dive: AI-Powered Marketing to Get More Leads and Customers with HyperGro...
 
Best 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERPBest 20 SEO Techniques To Improve Website Visibility In SERP
Best 20 SEO Techniques To Improve Website Visibility In SERP
 
How to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For FlutterHow to use Firebase Data Connect For Flutter
How to use Firebase Data Connect For Flutter
 
How to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptxHow to Get CNIC Information System with Paksim Ga.pptx
How to Get CNIC Information System with Paksim Ga.pptx
 
Monitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdfMonitoring and Managing Anomaly Detection on OpenShift.pdf
Monitoring and Managing Anomaly Detection on OpenShift.pdf
 
Choosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptxChoosing The Best AWS Service For Your Website + API.pptx
Choosing The Best AWS Service For Your Website + API.pptx
 
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAUHCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
HCL Notes und Domino Lizenzkostenreduzierung in der Welt von DLAU
 
TrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy SurveyTrustArc Webinar - 2024 Global Privacy Survey
TrustArc Webinar - 2024 Global Privacy Survey
 
UI5 Controls simplified - UI5con2024 presentation
UI5 Controls simplified - UI5con2024 presentationUI5 Controls simplified - UI5con2024 presentation
UI5 Controls simplified - UI5con2024 presentation
 
Taking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdfTaking AI to the Next Level in Manufacturing.pdf
Taking AI to the Next Level in Manufacturing.pdf
 
Ocean lotus Threat actors project by John Sitima 2024 (1).pptx
Ocean lotus Threat actors project by John Sitima 2024 (1).pptxOcean lotus Threat actors project by John Sitima 2024 (1).pptx
Ocean lotus Threat actors project by John Sitima 2024 (1).pptx
 
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing InstancesEnergy Efficient Video Encoding for Cloud and Edge Computing Instances
Energy Efficient Video Encoding for Cloud and Edge Computing Instances
 
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development ProvidersYour One-Stop Shop for Python Success: Top 10 US Python Development Providers
Your One-Stop Shop for Python Success: Top 10 US Python Development Providers
 
Recommendation System using RAG Architecture
Recommendation System using RAG ArchitectureRecommendation System using RAG Architecture
Recommendation System using RAG Architecture
 

Lascas Failure Learn A Big Lession From The Most Terrible Problems In The World

  • 1. London Ambulance Service System Failure 1992 Craig Houston Fraser Hall
  • 2. Overview • On 26th October 1992 the London Ambulance Service started using a new Computer Aided Dispatch system. – Aims: • Improve efficiency • Control resources efficiently • Decrease personnel requirements • The system failed: – The system could not cope with the load placed on it by normal use; – The response to emergency calls was several hours; – Ambulance communications failed and ambulances were lost from the system.
  • 3. Time Line of Events 1. Need Discovered – Early 1980’s 2. Anderson Report Produced – Autumn 1990 3. Project Put to tender - 7 February 1991 4. Contractor decided – August 1991 5. Project Development – June 1991 -> 8th January 1992 6. System Integration - October 1992 7. System Fails – 26th October 1992 – 4th November 1992
  • 4. London Ambulance Service LAS • Largest Ambulance Service in the world • Around 4,000 staff at over 70 stations • Carries over 5,000 patients every day. • Receives 2,000-2,500 calls each day – Only 1,300 to 1,600 are emergency calls • Area covers 620 miles2
  • 5. Manual System • Call taking – Recorded on form – Location identified on map – Form sent to central collection point • Resource identification – Form Collected – duplicates removed – Passed onto region assigned resource allocator – Resource allocator decides on crew to be mobilised – Form updated – passed to dispatcher • Resource mobilisation – Dispatcher contacts ambulance station – Or passed onto radio operator if ambulance is already mobile • Whole process meant to take < 3 minutes
  • 6. Computer Aided Dispatch • Existing systems dismissed as inadequate and impossible to modify to meet LAS’s needs – Intended functionality was more than manual system could cope with. • Desired system: – To consist of Computer Aided Dispatch; Computer map display; Automatic Vehicle Location System (AVLS); – Must integrate with existing Mobile Data Terminals and the Radio Interface System. • Success dependent upon: – Near 100% accuracy and reliability of technology; – Absolute cooperation from all parties including CAC staff and ambulance crews.
  • 7. Communication Infrastructure *Taken from Report of the Inquiry Into The London Ambulance Service
  • 8. What Went Wrong? • When the system was adopted several issues arose from its first use: – Ambulance locations were incorrect or not shown – Call taking created exceptions which created a greater work load – Ambulance response time became unacceptable • Many reports have been produced on what went wrong: – From its conception to its integration the project management and process were doomed to fail.
  • 9. Project Assignment • How it was done – The project was put out to tender. – Report by Arthur Andersen • Suggested budget of £1.5Million and time-frame for development & testing 19 months, longer if a consortium was given project. • Report was mostly ignored – Cheapest bidder chosen – Consortium given strict deadline of 6 months development » Significantly less than the 19 months set as industry standard
  • 10. Project Assignment Continued • A consortium consisting of Apricot, Systems Options and Datatrak given the project – Their proposal of £937k was £700k cheaper than next bidder • No questions were asked as to this figure. – Systems Options were to develop the CAD software • Previous experience of emergency service systems was limited to an administrative system • No experience of high integrity systems – There was no official designation of who were to manage the project.
  • 11. System Design • System requirements: – Need for 100% reliability • System was never 100% reliable. • Strict deadline meant testing was unacceptable. • Fail safe measures never tested. – Must be able to cope with unexpected events/data • System never expected incomplete information – Exceptions when this occurred took up vital computation time • Exceptions were not prioritised and took up vital processing – Efficiency is key to system • System could not cope with volume of traffic • Never tested to full capacity – Failed to achieve suitable level of performance for normal work load
  • 12. System Design Continued – Must be able to de-duplicate calls • System failed to identify duplicate calls • More traffic within the system caused: – resource allocation issues – Processing performance diminution – Communication of information is vital • Communication channels expected to be 100% reliable by system – Passed back incomplete information which system failed to handle correctly • Poor interface between Ambulance crew, MDTs & the system – Must be easy to use for staff • Staff were used to old system and had to be trained to use new system
  • 13. System Implementation • Problems: – Time-frame too short • Developers saw deadlines as rigid – Rush to complete software liable to generate problems • Testing time was inadequate for critical system • Development team had doubts on feasibility of system – They did not reflect their feelings onto management
  • 14. System Integration • Problems: – Adoption too soon • Users not ready – Changed control room layout confusing to staff – Complete change from original system without significant training – Two groups of users: » Separate training left users unsure of each others roles • System not ready – Backup server not tested properly. – Inadequate full load testing – Data transmission problems – Staff • Opposed to new system – Unwilling to learn/use new system – Lack of trust in new system • Not consulted over the new system – Development missed out on meeting staff needs. – Limited involvement in testing therefore testing of typical use not fulfilled
  • 15. Project Management • Problems: – Break down in relationship between staff and management following new initiatives introduced • Lack of trust in any new system. • Little communication between management and staff meant issues were unresolved – Contractor • Board of management were misled into the lead contractors ability and pass experience of emergency service systems • High risk by management in offering project to small software house company with little experience of high integrity systems. – project management throughout the development and implementation process was inadequate and at times ambiguous. • A major systems integration project such as CAD requires full time. professional, experienced project management. This was lacking; – Scale of change and speed of change were too aggressive for the circumstances
  • 16. Project Management Continued – Poorly defined Management structure • No party took ownership from start – Systems Options assumed to be responsible – Became too busy and London Ambulance Service management took over • Executive Directors took control of minor problems – Should have been left to lower level management • Evaluation team: – Systems Manager – Ambulance crewman with many years experience: No IT knowledge » Replaced by IT expert – too late – Analyst – Contractor with 5 years experience with LAS • Structure inflexible from structure before project lead to problems in communication
  • 17. Project Management Continued – Lack of defined communication channels • Concerns Raised at meetings never followed up • Staff unable to reflect issues on to management • Development team issues unresolved due to strict deadlines
  • 18. Assignment To Integration What Should Have Been Done? • Assignment – The project should have been assigned to a consortium or company with prior experience – Lowest cost should not have been deciding factor – More attention should have been made on Anderson report. • Implementation – Timetable should have been better calculated – Testing should not have been passed by – Independent testing should have been carried out – Development teams concerns should have been raised earlier • Integration – Training should have been more focused – Mixed training (i.e. users from all parts of process) should have been carried out • Highlight the role of different teams so user knows the whole system – User issues never addressed. – Backup should have been tested – Manual fallback system should have been in place.
  • 19. Project Management What Should Have Been Done? • Project Management – Management and staff issues prior to the new system development should have been resolved to gain staff’s trust and support – Communication channels should have been setup between staff and management. • Staff delegate to raise concerns of staff – Better definition of project ownership • LAS should not have to own project as they have little experience of system development – Project management should have outlined to development teams that deadlines were not strict in the interest of better system – Formal recording of concerns should have been used • Concerns should be followed up. • Delegation of ownership of concern to member of management would ensure concern is addressed • Problems not given thorough analysis.
  • 20. Project Management What Should Have Been Done? – Project should have been split into phases instead of a single process • Ensure that each phase is complete before next is begun • Creates quality assurance at each stage • Clearly defined structure more likely to achieve system targets. – An IT manager should be appointed to sit on LAS board • It is their role to coordinate between LAS board and the system development contractor • Experience in IT is essential to allow good project management and communication between non IT board members and the project team. • Separate Executive Directors from the project team to restrict interference. – A report should have been commissioned to be completed before adoption which could have outlined the problems before they occurred.
  • 21. Project Management What Should Have Been Done? – LAS Board failed to follow PRINCE Project Management method • Projects in Controlled Environments • Shows Corporate and Project Management separation. – Management had little/no training over the years to prepare them for such a project. – Ambiguity over project management – High Integrity system projects should have full-time professional management.
  • 22. Summary • Project was doomed from the start: – Assignment of project to contractor was riddled with issues – Development of the project was too aggressive and quick for the circumstances – Integration of the system was unstructured and completed too soon. • Management Problems – Management was unstructured – Too ambiguous at every level – Communication channels were unclear • Many issues could have been avoided through better project management. • Questions.
  • 23. References • Report of the Inquiry Into The London Ambulance Service - Anthony Finkelstein • A Comedy of Errors: the London Ambulance Service case study – Anthony Finkelstein • Overview of LAS Failure – Ian Sommerville • CAD Failure LAS – ambulance.freeuk • Software failure: management failure – Stephen Flowers