![Example:(Max 2 slot)
Jobs J1 J2 J3 J4
Profit 100 40 20 3
Deadline 2 1 2 1
Job Slot Solution Profit Status
J1 [1,2] {J1} 100 Can do
J2 [0,1] [1,2] {j2 , J1} 100+40 Can do
J3 [0,1] [1,2] {j2 , J1} 140 Can not do
J4 [0,1] [1,2] {j2 , J1} 140 Can not do
Total profit: 140
0 1 2
j2 j1
5 out of 6](https://image.slidesharecdn.com/jobsequencing-190303094340/85/Job-sequencing-with-deadline-5-320.jpg)


This document discusses the job sequencing problem, where the goal is to schedule jobs to be completed by their deadlines to maximize total profit. It provides an example problem with 4 jobs, their profits, deadlines, and the optimal solution of scheduling jobs J1 and J2 to earn a total profit of 140.




![Example:(Max 2 slot)
Jobs J1 J2 J3 J4
Profit 100 40 20 3
Deadline 2 1 2 1
Job Slot Solution Profit Status
J1 [1,2] {J1} 100 Can do
J2 [0,1] [1,2] {j2 , J1} 100+40 Can do
J3 [0,1] [1,2] {j2 , J1} 140 Can not do
J4 [0,1] [1,2] {j2 , J1} 140 Can not do
Total profit: 140
0 1 2
j2 j1
5 out of 6](https://image.slidesharecdn.com/jobsequencing-190303094340/85/Job-sequencing-with-deadline-5-320.jpg)