Construction of elevated road corridor/Bridge/flyover from AIIMS to Digha at Patna in the state of Bihar for Bihar State Road Development Corporation Ltd.(BSRDCL) By Gammon India Ltd.
The document provides a training report for a bridge construction project in Jaipur, India during May-June 2016. It summarizes the key components of the bridge, including pile foundations, substructures like piers and pedestals, and superstructures such as prestressed concrete girders and deck slabs. The training helped the author gain practical knowledge of bridge construction techniques and management that supplemented their theoretical classroom learning.
Grillage Analysis of T-Beam bridge, Box culvert and their Limit State Design; components of Bridges and loads acting on bridges are presented in this slide.
The document provides details about the construction of a two-lane bridge over a railway crossing in Moradabad, India by UP State Bridge Corporation Limited. It summarizes the key components of the bridge, including pile foundations with friction piles, pier foundations, pier caps, pedestals, bearings, abutments, girders, deck slabs, and crash barriers. It also provides details on the materials used, such as concrete grades between M30-M40 and rebar sizes from 6mm to 32mm. Construction testing methods like slump tests, sieve tests, and cube tests are also summarized.
The document summarizes the construction of a flyover project in Patna, Bihar, India. It discusses the various stages of the project, including topographic and traffic surveys, geotechnical analysis, planning and design, and construction. The construction involves building the substructure with pile foundations and pile caps, and the superstructure, which consists of piers and precast concrete deck segments connected by post-tensioning. Once completed, the flyover will help reduce traffic congestion in the city.
this report is helpful for highway work or road construction, its also useful for pavement works or pavement design. this report told about bitumen road work construction, in this report cement used for work in side of road.its helpful for those civil engineers who want to submit there training report or seminar report.
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTIONVed Jangid
This document provides a summer internship report for a civil engineering student's internship at the Public Works Department in Ajmer, Rajasthan, India from May 10th to July 10th, 2018. The internship involved working on the construction of a 10-room and 2-store building at the Revenue Research and Training Institute campus in Ajmer. The report details the project overview, building components, construction materials used, construction processes and the intern's weekly progress and conclusions.
A RCC bridge is a monolithic structure that is poured in place. Forms are placed, the reinforcing steel is placed into the forms and a concrete mix is poured into the forms. The rebar extends beyond the form to allow connection to the next section to be poured. In a PSC structure the elements are precast either in a yard or onsite. They are cast with longitudinal holes to allow the prestressing strands to be extended between them. These strands use their tension to pull the units together and to act as reinforcement by prestreeing the entirety of the structure to make it stronger.
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTIONAbhishek Singh
This document appears to be an internship report submitted by four students - Abhishek Singh, Naval Tej Singh Ahuja, Sahil Thakur, and Swapnil Singh - to their supervisor Mr. Kapil Bhardwaj at Universal Buildwell Pvt. Ltd. in Gurgaon, Haryana, India. The report provides details about a residential construction project called Universal Aura, including project specifications, building materials used, and work ongoing at the site during the students' summer internship from June 13 to July 13, 2016.
The document provides a training report for a bridge construction project in Jaipur, India during May-June 2016. It summarizes the key components of the bridge, including pile foundations, substructures like piers and pedestals, and superstructures such as prestressed concrete girders and deck slabs. The training helped the author gain practical knowledge of bridge construction techniques and management that supplemented their theoretical classroom learning.
Grillage Analysis of T-Beam bridge, Box culvert and their Limit State Design; components of Bridges and loads acting on bridges are presented in this slide.
The document provides details about the construction of a two-lane bridge over a railway crossing in Moradabad, India by UP State Bridge Corporation Limited. It summarizes the key components of the bridge, including pile foundations with friction piles, pier foundations, pier caps, pedestals, bearings, abutments, girders, deck slabs, and crash barriers. It also provides details on the materials used, such as concrete grades between M30-M40 and rebar sizes from 6mm to 32mm. Construction testing methods like slump tests, sieve tests, and cube tests are also summarized.
The document summarizes the construction of a flyover project in Patna, Bihar, India. It discusses the various stages of the project, including topographic and traffic surveys, geotechnical analysis, planning and design, and construction. The construction involves building the substructure with pile foundations and pile caps, and the superstructure, which consists of piers and precast concrete deck segments connected by post-tensioning. Once completed, the flyover will help reduce traffic congestion in the city.
this report is helpful for highway work or road construction, its also useful for pavement works or pavement design. this report told about bitumen road work construction, in this report cement used for work in side of road.its helpful for those civil engineers who want to submit there training report or seminar report.
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTIONVed Jangid
This document provides a summer internship report for a civil engineering student's internship at the Public Works Department in Ajmer, Rajasthan, India from May 10th to July 10th, 2018. The internship involved working on the construction of a 10-room and 2-store building at the Revenue Research and Training Institute campus in Ajmer. The report details the project overview, building components, construction materials used, construction processes and the intern's weekly progress and conclusions.
A RCC bridge is a monolithic structure that is poured in place. Forms are placed, the reinforcing steel is placed into the forms and a concrete mix is poured into the forms. The rebar extends beyond the form to allow connection to the next section to be poured. In a PSC structure the elements are precast either in a yard or onsite. They are cast with longitudinal holes to allow the prestressing strands to be extended between them. These strands use their tension to pull the units together and to act as reinforcement by prestreeing the entirety of the structure to make it stronger.
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTIONAbhishek Singh
This document appears to be an internship report submitted by four students - Abhishek Singh, Naval Tej Singh Ahuja, Sahil Thakur, and Swapnil Singh - to their supervisor Mr. Kapil Bhardwaj at Universal Buildwell Pvt. Ltd. in Gurgaon, Haryana, India. The report provides details about a residential construction project called Universal Aura, including project specifications, building materials used, and work ongoing at the site during the students' summer internship from June 13 to July 13, 2016.
DESIGN OF BOX CULVERT AS PER IRC-112: 2011, INTERNSHIP PROJECT REPORT.
INCLUDES:
1) BASIC DETAILS
2) DESIGN OF 2 CELL BOX CULVERT
3) DESIGN OF WING WALLS (RETAINING WALLS) AS PER IRC
The document is an internship report on Bharat Pride Park, a residential and commercial development project in Kalaburagi, India. It provides details about the project, including an overview of the consulting firm and the intern's responsibilities. The internship involved taking measurements to calculate quantities of materials, interpreting drawings, and assisting engineers and supervisors. The intern gained experience in construction processes and project documentation during the one-month internship.
This document provides a training report on the construction of the Mithapur to Chiraiyatad flyover project in Bihar, India. It includes three sections: components of a bridge, construction procedures and dimensions, and quality control tests. The report describes the various components of the bridge, including foundations, substructures, and superstructures. It provides details on constructing piles, pile caps, piers, pier caps, I-girders, decks, bearings, and crash barriers. Dimensional details and construction procedures are outlined for each component. Finally, the report discusses quality control tests for aggregates, cement, and load testing of the completed structures.
The document discusses the balanced cantilever method of bridge construction. It begins by explaining that this method is used for bridges with spans between 50-250m, and involves attaching precast or cast-in-place segments in an alternating manner from each end of cantilevers supported by piers. This method is well-suited for irregular spans, congested sites, and environmentally sensitive areas. It also discusses advantages like determinacy and reduced cracking risks. The document then goes into detail about construction sequences, member proportioning, superstructure types, and analysis of a specific balanced cantilever bridge in Kochi, India.
CONSTRUCTION OF DISTRICT CONTROL BUILDING, CENTRAL STORE BUILDING & 33/11KV POWER SUBSTATION CONTROL ROOM AT CHAPRA,BIHAR
An Internship Report submitted in partial fulfilment of the
requirements for the degree
of
B.Tech (Civil Engineering)
by
VIJAY KUMAR SINGH
13BCL0001
VIT UNIVERSITY
VELLORE – 632 014, TAMILNADU
Summer Internship Report of Civil Engineering in Construction SiteRAVI KUMAR
The document provides details about the internship completed by Ravi Kumar at Fidesto Projects Private Limited from June 17 to July 30, 2019. It includes an acknowledgement, information about the organization and the proposed residential project in Pune on which Ravi Kumar worked. Safety protocols at construction sites like use of safety equipment and formwork are also summarized. The key steps involved in building construction are outlined.
Seismic Analysis of G 10 Storey Building with Various Locations of Shear Wall...ijtsrd
Shear walls are specially designed structural members provided in the multi storey buildings to resist lateral forces. These walls have very high in plane strength and stiffness, which can resist large horizontal forces and can support gravity loads. There are lots of literatures available to design and analyse the shear wall. Ravi Kumar Vishwakarma | Vipin Kumar Tiwari "Seismic Analysis of G+10 Storey Building with Various Locations of Shear Walls using Etabs" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-5 | Issue-4 , June 2021, URL: https://www.ijtsrd.compapers/ijtsrd43646.pdf Paper URL: https://www.ijtsrd.comengineering/structural-engineering/43646/seismic-analysis-of-g10-storey-building-with-various-locations-of-shear-walls-using-etabs/ravi-kumar-vishwakarma
This document discusses box culverts and their components and construction. It begins by defining a culvert as a cross-drainage structure less than 6 meters long. It then describes box culverts, noting they consist of rectangular or square openings constructed monolithically with abutments and piers. Box culverts are typically constructed where soil is soft to distribute load over a wider area. They are made of concrete and can redirect water flow. The document outlines the wet cast and dry cast construction methods and lists the typical components of a box culvert. It also discusses the loads box culverts are subject to and their applications, advantages, and thank you.
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTssuser5fea8f
The document is a summer training report submitted by Sudhanshu Kumar to the Uttar Pradesh Public Works Department about bituminous (asphalt) roads. It includes an introduction to bitumen and bituminous roads, descriptions of the different layers in a flexible bituminous pavement including sub-grade, sub-base, base, binder and wearing courses. It also details test procedures for determining the Marshall stability of bituminous mixtures and the key steps for constructing a bituminous road which include preparing the base with a water bound macadam layer, applying a tack coat, constructing layers from bottom to top, and compacting each layer.
The document discusses the design and estimation of an Intze tank. It includes an abstract that describes the need for water storage and supply. It then covers various topics related to designing water tanks such as estimating water demand based on population and consumption rates, classifying different types of water tanks, design requirements for concrete water tanks, and the design of specific elements like domes and overhead tanks. The document aims to provide theory and guidelines for designing a reinforced concrete elevated circular water tank with a domed roof and conical base using the working stress method.
This document provides guidelines for the fourth revision of the design of flexible pavements in India. It outlines the history and progression of flexible pavement design guidelines in India, from the initial empirical approach to current semi-mechanistic and mechanistic-empirical approaches. The key updates in the fourth revision include recommendations for better performing bituminous mixes and binders, guidelines for selecting elastic moduli for bituminous mixes, and performance models and criteria for various pavement distresses. Design charts are provided to help determine pavement layer thicknesses based on traffic levels and other factors.
Experimental Study on Partial Replacement of Cement with Nano Silica in the C...ijtsrd
The main objective of this work is to study the mechanical strength and durability of the concrete when the particular cement dosage in concrete in replaced with Nano silica powder. However it is expected that the use of Nano-silica in concrete improve the strength properties of concrete. Also it is an attempt made to develop the concrete using Nano sized particles as a partial replacement of cement, which satisfies the various structural properties of concrete like compressive strength and tensile strength. It is expected that the final outcome of the project will have an overall beneficial effect on the utility of Nano-silica concrete in the field of civil engineering construction work. Rahul K | Andavan S"Experimental Study on Partial Replacement of Cement with Nano Silica in the Concrete" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-2 | Issue-1 , December 2017, URL: http://www.ijtsrd.com/papers/ijtsrd7032.pdf http://www.ijtsrd.com/engineering/civil-engineering/7032/experimental-study-on-partial-replacement-of-cement--with-nano-silica-in-the-concrete/rahul-k
This document is a summer intern project report on bituminous (asphalt) roads submitted by Shubham Paliwal to GLA University. It discusses the key steps in bituminous road construction including preparing the base, applying a tack coat, laying down the asphalt concrete layer, and compacting it. It also covers materials used like aggregates, asphalt, and tests performed on samples like flakiness index and bitumen extraction tests. The report provides an overview of bituminous road technology and construction methods.
Summer Training Report =Bihar Rajya pul Nirman NigamRaju kumar Gautam
This document provides details about a summer training project conducted at Bihar Rajya Pul Nirman Nigam Limited (BRPNNL) from June 6 to July 7, 2017. It describes the construction of a flyover from Mithapur to Chiriyantand in Patna, including surveying, foundations involving pile boring and concrete pile construction, substructures like pile caps, pier shafts and pier caps, and superstructures such as segments, girders, and their launching. The flyover is being built to reduce traffic problems in Patna due to increasing vehicles and poor road infrastructure.
This document discusses approximate analysis methods for multi-storey frames under vertical and lateral loads. It introduces the substitute frame method, portal method, and cantilever method for analyzing frames. An example problem demonstrates using the substitute frame method to analyze a frame for vertical loads, distributing fixed end moments using distribution factors. Homework is assigned to analyze another frame using the cantilever method under given loading conditions.
Industrial Summer Training Report at Construction Site of CPWD Alok Mishra
Construction of Police Station Khajuri Khas, Near Sonia Vihar, Delhi (SH: C/o Police Station Building, Electric sub Station & External Development Work i.e. Internal Electrical Installations)
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PROAli Meer
This document discusses the design and analysis of a multi-storied residential building using STAAD Pro software. It includes details on the building specifications, applicable codes, loads on the structure, and the design of structural elements like slabs, beams, columns, and footings. The analysis involves assigning materials, loads, properties and performing RCC design in STAAD Pro to verify the safety and serviceability of the building according to codes. The results show the design is safe and meets code requirements. References include design codes and textbooks.
Construction Of A Viaduct/Bridge: An OverviewSourav Goswami
This document is a submission by Sourav Goswami describing his 7-day internship project focused on the construction of a metro rail bridge. The project was conducted under Rail Vikas Nigam Limited and Gammon India Limited. Sourav thanks the project guides and staff who provided guidance and knowledge about bridge construction activities including piling, pile caps, piers, bearings and segments.
Undergraduate major project_-_design_ofVijay Singh
This document describes the design of a T-beam rail-over-bridge submitted by 9 students for their Bachelor of Technology degree in Civil Engineering. It includes an introduction to bridge types and T-beam bridges. It then outlines the contents which will cover the design of the deck slab, cantilever slab, longitudinal and cross girders, and bearings. Design calculations and reinforcement details will be provided for each component.
DESIGN OF BOX CULVERT AS PER IRC-112: 2011, INTERNSHIP PROJECT REPORT.
INCLUDES:
1) BASIC DETAILS
2) DESIGN OF 2 CELL BOX CULVERT
3) DESIGN OF WING WALLS (RETAINING WALLS) AS PER IRC
The document is an internship report on Bharat Pride Park, a residential and commercial development project in Kalaburagi, India. It provides details about the project, including an overview of the consulting firm and the intern's responsibilities. The internship involved taking measurements to calculate quantities of materials, interpreting drawings, and assisting engineers and supervisors. The intern gained experience in construction processes and project documentation during the one-month internship.
This document provides a training report on the construction of the Mithapur to Chiraiyatad flyover project in Bihar, India. It includes three sections: components of a bridge, construction procedures and dimensions, and quality control tests. The report describes the various components of the bridge, including foundations, substructures, and superstructures. It provides details on constructing piles, pile caps, piers, pier caps, I-girders, decks, bearings, and crash barriers. Dimensional details and construction procedures are outlined for each component. Finally, the report discusses quality control tests for aggregates, cement, and load testing of the completed structures.
The document discusses the balanced cantilever method of bridge construction. It begins by explaining that this method is used for bridges with spans between 50-250m, and involves attaching precast or cast-in-place segments in an alternating manner from each end of cantilevers supported by piers. This method is well-suited for irregular spans, congested sites, and environmentally sensitive areas. It also discusses advantages like determinacy and reduced cracking risks. The document then goes into detail about construction sequences, member proportioning, superstructure types, and analysis of a specific balanced cantilever bridge in Kochi, India.
CONSTRUCTION OF DISTRICT CONTROL BUILDING, CENTRAL STORE BUILDING & 33/11KV POWER SUBSTATION CONTROL ROOM AT CHAPRA,BIHAR
An Internship Report submitted in partial fulfilment of the
requirements for the degree
of
B.Tech (Civil Engineering)
by
VIJAY KUMAR SINGH
13BCL0001
VIT UNIVERSITY
VELLORE – 632 014, TAMILNADU
Summer Internship Report of Civil Engineering in Construction SiteRAVI KUMAR
The document provides details about the internship completed by Ravi Kumar at Fidesto Projects Private Limited from June 17 to July 30, 2019. It includes an acknowledgement, information about the organization and the proposed residential project in Pune on which Ravi Kumar worked. Safety protocols at construction sites like use of safety equipment and formwork are also summarized. The key steps involved in building construction are outlined.
Seismic Analysis of G 10 Storey Building with Various Locations of Shear Wall...ijtsrd
Shear walls are specially designed structural members provided in the multi storey buildings to resist lateral forces. These walls have very high in plane strength and stiffness, which can resist large horizontal forces and can support gravity loads. There are lots of literatures available to design and analyse the shear wall. Ravi Kumar Vishwakarma | Vipin Kumar Tiwari "Seismic Analysis of G+10 Storey Building with Various Locations of Shear Walls using Etabs" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-5 | Issue-4 , June 2021, URL: https://www.ijtsrd.compapers/ijtsrd43646.pdf Paper URL: https://www.ijtsrd.comengineering/structural-engineering/43646/seismic-analysis-of-g10-storey-building-with-various-locations-of-shear-walls-using-etabs/ravi-kumar-vishwakarma
This document discusses box culverts and their components and construction. It begins by defining a culvert as a cross-drainage structure less than 6 meters long. It then describes box culverts, noting they consist of rectangular or square openings constructed monolithically with abutments and piers. Box culverts are typically constructed where soil is soft to distribute load over a wider area. They are made of concrete and can redirect water flow. The document outlines the wet cast and dry cast construction methods and lists the typical components of a box culvert. It also discusses the loads box culverts are subject to and their applications, advantages, and thank you.
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTssuser5fea8f
The document is a summer training report submitted by Sudhanshu Kumar to the Uttar Pradesh Public Works Department about bituminous (asphalt) roads. It includes an introduction to bitumen and bituminous roads, descriptions of the different layers in a flexible bituminous pavement including sub-grade, sub-base, base, binder and wearing courses. It also details test procedures for determining the Marshall stability of bituminous mixtures and the key steps for constructing a bituminous road which include preparing the base with a water bound macadam layer, applying a tack coat, constructing layers from bottom to top, and compacting each layer.
The document discusses the design and estimation of an Intze tank. It includes an abstract that describes the need for water storage and supply. It then covers various topics related to designing water tanks such as estimating water demand based on population and consumption rates, classifying different types of water tanks, design requirements for concrete water tanks, and the design of specific elements like domes and overhead tanks. The document aims to provide theory and guidelines for designing a reinforced concrete elevated circular water tank with a domed roof and conical base using the working stress method.
This document provides guidelines for the fourth revision of the design of flexible pavements in India. It outlines the history and progression of flexible pavement design guidelines in India, from the initial empirical approach to current semi-mechanistic and mechanistic-empirical approaches. The key updates in the fourth revision include recommendations for better performing bituminous mixes and binders, guidelines for selecting elastic moduli for bituminous mixes, and performance models and criteria for various pavement distresses. Design charts are provided to help determine pavement layer thicknesses based on traffic levels and other factors.
Experimental Study on Partial Replacement of Cement with Nano Silica in the C...ijtsrd
The main objective of this work is to study the mechanical strength and durability of the concrete when the particular cement dosage in concrete in replaced with Nano silica powder. However it is expected that the use of Nano-silica in concrete improve the strength properties of concrete. Also it is an attempt made to develop the concrete using Nano sized particles as a partial replacement of cement, which satisfies the various structural properties of concrete like compressive strength and tensile strength. It is expected that the final outcome of the project will have an overall beneficial effect on the utility of Nano-silica concrete in the field of civil engineering construction work. Rahul K | Andavan S"Experimental Study on Partial Replacement of Cement with Nano Silica in the Concrete" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-2 | Issue-1 , December 2017, URL: http://www.ijtsrd.com/papers/ijtsrd7032.pdf http://www.ijtsrd.com/engineering/civil-engineering/7032/experimental-study-on-partial-replacement-of-cement--with-nano-silica-in-the-concrete/rahul-k
This document is a summer intern project report on bituminous (asphalt) roads submitted by Shubham Paliwal to GLA University. It discusses the key steps in bituminous road construction including preparing the base, applying a tack coat, laying down the asphalt concrete layer, and compacting it. It also covers materials used like aggregates, asphalt, and tests performed on samples like flakiness index and bitumen extraction tests. The report provides an overview of bituminous road technology and construction methods.
Summer Training Report =Bihar Rajya pul Nirman NigamRaju kumar Gautam
This document provides details about a summer training project conducted at Bihar Rajya Pul Nirman Nigam Limited (BRPNNL) from June 6 to July 7, 2017. It describes the construction of a flyover from Mithapur to Chiriyantand in Patna, including surveying, foundations involving pile boring and concrete pile construction, substructures like pile caps, pier shafts and pier caps, and superstructures such as segments, girders, and their launching. The flyover is being built to reduce traffic problems in Patna due to increasing vehicles and poor road infrastructure.
This document discusses approximate analysis methods for multi-storey frames under vertical and lateral loads. It introduces the substitute frame method, portal method, and cantilever method for analyzing frames. An example problem demonstrates using the substitute frame method to analyze a frame for vertical loads, distributing fixed end moments using distribution factors. Homework is assigned to analyze another frame using the cantilever method under given loading conditions.
Industrial Summer Training Report at Construction Site of CPWD Alok Mishra
Construction of Police Station Khajuri Khas, Near Sonia Vihar, Delhi (SH: C/o Police Station Building, Electric sub Station & External Development Work i.e. Internal Electrical Installations)
DESIGN AND ANALAYSIS OF MULTI STOREY BUILDING USING STAAD PROAli Meer
This document discusses the design and analysis of a multi-storied residential building using STAAD Pro software. It includes details on the building specifications, applicable codes, loads on the structure, and the design of structural elements like slabs, beams, columns, and footings. The analysis involves assigning materials, loads, properties and performing RCC design in STAAD Pro to verify the safety and serviceability of the building according to codes. The results show the design is safe and meets code requirements. References include design codes and textbooks.
Construction Of A Viaduct/Bridge: An OverviewSourav Goswami
This document is a submission by Sourav Goswami describing his 7-day internship project focused on the construction of a metro rail bridge. The project was conducted under Rail Vikas Nigam Limited and Gammon India Limited. Sourav thanks the project guides and staff who provided guidance and knowledge about bridge construction activities including piling, pile caps, piers, bearings and segments.
Undergraduate major project_-_design_ofVijay Singh
This document describes the design of a T-beam rail-over-bridge submitted by 9 students for their Bachelor of Technology degree in Civil Engineering. It includes an introduction to bridge types and T-beam bridges. It then outlines the contents which will cover the design of the deck slab, cantilever slab, longitudinal and cross girders, and bearings. Design calculations and reinforcement details will be provided for each component.
This document provides information about a bridge engineering course taught by Prof. Dr. Azlan Abdul Rahman. The 12-week course covers various topics related to bridge design and analysis including bridge types, structural forms, design process, load calculations, finite element analysis using LUSAS software, prestressed concrete bridge design, and bridge substructure elements. The course objectives are to teach students to identify bridge types and design processes, perform bridge load calculations, use LUSAS for bridge analysis, and design prestressed concrete bridge beams, abutments and piers.
This document provides an overview of the course MAB1053 Bridge Engineering. The course objectives are to teach students about concrete bridge types, bridge loading calculations, and basic bridge design and analysis using finite element software. The content is delivered over 15 weeks and covers topics such as bridge substructures, loading, deck analysis methods, and prestressed concrete bridge design. The course aims to provide students with the fundamental knowledge needed for basic bridge design and analysis.
This document provides an overview of the course MAB1053 Bridge Engineering. The course objectives are to teach students about concrete bridge types, bridge loading calculations, and basic bridge design and analysis using finite element software. The content is delivered over 15 weeks and covers topics such as bridge substructures, loading, deck analysis methods, and prestressed concrete bridge design. The course aims to provide students with the fundamental knowledge needed for basic bridge design and analysis.
This document provides an overview of bridge engineering. It defines a bridge as a structure that allows passage over an obstacle without blocking the way underneath. Bridges are critical infrastructure for transportation. The document outlines the key components of bridges, including the substructure (abutments, piers, foundations), superstructure (decking, parapets, bearings), and different classifications of bridges based on materials, purpose, lifespan, spans and loads. It provides examples of different bridge types like beam, cantilever, arch, truss and suspension bridges. Finally, it highlights some landmark bridges in India like the Dhola Sadiya, Pamban and Bandra-Worli sea link bridges.
challanges made for construction of bridge in hilly areasSwapnali Kunjir
This document discusses the challenges of constructing bridges in hilly areas. Key challenges include constructing bridges across deep gorges with large height differences, on rivers with unstable beds, in areas with extreme temperatures or landslides. Proper site selection and bridge type choice are important considering geological and weather conditions. Foundations can be difficult to build in areas with mixed soil types. Management of construction activities, materials, quality, safety, and equipment are also discussed. Common bridge types for hilly areas described include beam, truss, cantilever, arch, tied arch, suspension, and cable-stayed bridges.
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxtoddr4
Running Head: BRIDGE DESIGN 1
BRIDGE DESIGN 31
Title:
Student Name:
Institution:
Course:
Date:
BRIDGE DESIGN FOR THE MOTOR WAY BELOW
8m
Embankment
A
Motorway
16m
10m
Central Reservation
Motorway
16m
Grass Verge
Existing Factory Units
Footway
A
Carriagewaym
Existing Factory Units
Fixed Factory Entrance
Fixed Factory Entrance
3m
2m
3m
2m
10mm
Existing Highway to Proposed Bridge
Existing Development
Proposed Development
Existing Development
Existing Retaining Wall – 500mm thick rc construction indicated by old record drawings
Central Reservation
10m
10m
Section A-A
2m footway
1.2m high parapets
10m carriageway
Bridge Deck Section
Figure 1
Bridge design
Most suitable bridge forms
· Beam bridge
· Arch bridge
The beam bridge: Beam and slab with ladder decks
This form of bridges comprises of slab which sits on top of steel I-beams. This form is mostly used for mid span highway bridge which is where our required bridge falls in.
Slab in this system is supported on tow main girders with a spacing of about 3.5m and it lies longitudinally between the girders as per the below diagram.
Figure 1
The bridge will use plate girders giving us a scope to vary the flange and web sizes to fit and suit the bridge load carrying capabilities. In the design process, ability of the bridge to carry the maximum load expected and the loading at the various stages of construction will guide on the proportion of girders that is their depth, width of tension and compression flanges and web thickness.
The girders are erected firmly on the ground and have stud connectors welded on the top flange to provide composite action between the slab and girder. The number of studs and spacing vary depending on expected level of shear flow between steel girder and concrete slab.
The girders rest on bearings fastened to the bottom flange. The girders are stiffened to carry the bearing loads at these points. Some cases apply bracing between the girders at support to carry lateral forces and provide torsional restraint.
Bridge description
· The bridge will have a span of 50m.
· The bridge will be raised to a height of 10m on both sides to be in level with the existing highway. The girders will have constant height.
· The bridge cross section will have the reinforced concrete slab sitting on top of two main abutment substructures and an extra substructure which will be on the central reservation. The main substructure will be located at the embarkment of the road.
Construction sequence
Abutment substructure construction
Girder construction
The bridge will consist of two main girder I beams. The girders will be of the same height. To make the I-beam, steel plates will be used. The steel plate is cut into the required sizes for the bottom flange and top flange and for the web. The cut pieces are then fillet welded into the I-section. This is done either by machine manual assembling in jig or through improved pressing machine .
This document provides an overview of the course MAB1053 Bridge Engineering Introduction. The key points are:
1. The course objectives are to identify types of bridges, perform basic calculations for bridge loading and analysis, and perform basic design of prestressed concrete bridge elements.
2. The course content includes introduction to bridges, bridge substructure elements, bridge loading, bridge superstructure analysis methods, and prestressed concrete bridge design.
3. The course schedule outlines the topics to be covered each week by the lecturers, including bridge types, loading, substructure, superstructure analysis, and prestressed concrete design.
The document provides information on the construction and erection of bridge elements such as prestressed concrete girders and deck slabs. It discusses casting of bridge girders using steel molds, various launching methods for erecting girders including using launching girders, and the balanced cantilever method of construction where bridge segments are constructed in a balanced manner from each pier until the two halves are joined. It also covers different types of bridge decks and systems used for structural steel girder bridges.
The document discusses various methods for constructing and erecting bridge elements. It describes the construction of prestressed concrete girders including casting them on site and using precast panels. Common bridge girder erection methods are also summarized, such as using launching girders to shift girders into place span by span. Balanced cantilever construction is explained as building out cantilever segments from each pier until the two halves meet in the middle.
Summer traning report BRPNNL by Amit Raj 14CE10005Amit Raj
The document provides a training report on the construction of the Mithapur to Chiraiyatad flyover project in Bihar, India. It includes three sections: components of a bridge, construction procedures and dimensions, and quality control. The first section describes the foundation, substructure, and superstructure components. The second section details the construction process and specifications of piles, pile caps, piers, pier caps, I-girders, decks, bearings, and crash barriers. The third section discusses quality control tests for aggregates, cement, and performance testing of the bridge structures.
This document provides a certificate for students who completed practical training on the construction of a hospital building. It summarizes the key aspects of the construction project, including that it was located in Delhi and involved building two towers totaling 22 floors to house 1,500 beds. The building structure utilized both reinforced concrete and mild steel in a composite design. Foundations were raft foundations due to soil conditions. Masonry work included various brick types, and scaffolding was used for tasks like masonry and plastering.
This document discusses reinforced concrete (RC) girder bridges. It begins by defining girder bridges as the simplest bridge type, consisting of horizontal beams supported at each end. RC girder bridges are comprised of deck slabs that vehicles drive on, supported by main girders. There are three main types of girder bridges: box girders, which can handle twisting forces and are suitable for longer spans; concrete girders made of pre-stressed concrete; and I-beam girders made of steel. RC girder bridges must be designed to support dead loads from the structure itself, live loads from traffic, and dynamic loads from wind and weather.
The document discusses precast concrete construction. It defines precast concrete as concrete that is cast in reusable molds and cured in a controlled environment off-site before being transported to the construction site. Benefits of precast construction include better quality control during curing, less weather dependence, faster construction time, and lower costs. Examples of precast concrete applications include buildings, bridges, retaining walls, and transportation products. The document also discusses design considerations, formwork, casting, handling, transportation and erection of precast concrete elements.
This document summarizes a seminar presentation on stress ribbon bridges. It defines a stress ribbon bridge as a tension structure similar to a simple suspension bridge, where the suspension cables are embedded in the deck which follows a catenary arc between supports. This provides stiffness to prevent excessive swaying. Such bridges use pre-tensioned concrete reinforced by steel cables. The document outlines the history and theory behind stress ribbon bridges, describes their construction process, and provides examples of existing stress ribbon bridges along with their advantages and disadvantages.
A bridge is the key element in a transportation system; it controls both the volume and weight of the traffic. Balance must be achieved between handling future traffic volume and loads and the cost of heavier and wider bridge structure. Economic Analysis and comparisons against competing alternatives is required as Bridges are the most expensive part of a road transportation network. Monetized & Non-Monetized Benefits that will accrue like time savings to road users, benefits to business activities (and to the economy in general) and salvage value benefits like Right-of-Way and substructure use need to be assessed as well.
The document discusses the construction stage analysis of a segmental cantilever bridge. It describes the bridge as having three spans totaling 200 meters constructed using the balanced cantilever method. In this method, cantilever segments are constructed on both sides of the pier and joined together. During construction, the bending moment on the pier increases with each added segment as the structure changes from a cantilever to a continuous bridge. Considering only the final operational stage could cause failure if intermediate stage stresses are not addressed. The document presents modeling the bridge construction in stages to analyze stresses, deflections, and reactions at each stage.
This is just an overview about the Reinforced Concrete Deck Girder Bridge
(RCDG Bridge)
the Presentation includes:
Materials for Construction,
Parts of a typical RCDG bridge,
The Forces Acting on the bridge, etc.
Properties of Fluids, Fluid Statics, Pressure MeasurementIndrajeet sahu
Properties of Fluids: Density, viscosity, surface tension, compressibility, and specific gravity define fluid behavior.
Fluid Statics: Studies pressure, hydrostatic pressure, buoyancy, and fluid forces on surfaces.
Pressure at a Point: In a static fluid, the pressure at any point is the same in all directions. This is known as Pascal's principle. The pressure increases with depth due to the weight of the fluid above.
Hydrostatic Pressure: The pressure exerted by a fluid at rest due to the force of gravity. It can be calculated using the formula P=ρghP=ρgh, where PP is the pressure, ρρ is the fluid density, gg is the acceleration due to gravity, and hh is the height of the fluid column above the point in question.
Buoyancy: The upward force exerted by a fluid on a submerged or partially submerged object. This force is equal to the weight of the fluid displaced by the object, as described by Archimedes' principle. Buoyancy explains why objects float or sink in fluids.
Fluid Pressure on Surfaces: The analysis of pressure forces on surfaces submerged in fluids. This includes calculating the total force and the center of pressure, which is the point where the resultant pressure force acts.
Pressure Measurement: Manometers, barometers, pressure gauges, and differential pressure transducers measure fluid pressure.
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...PriyankaKilaniya
Energy efficiency has been important since the latter part of the last century. The main object of this survey is to determine the energy efficiency knowledge among consumers. Two separate districts in Bangladesh are selected to conduct the survey on households and showrooms about the energy and seller also. The survey uses the data to find some regression equations from which it is easy to predict energy efficiency knowledge. The data is analyzed and calculated based on five important criteria. The initial target was to find some factors that help predict a person's energy efficiency knowledge. From the survey, it is found that the energy efficiency awareness among the people of our country is very low. Relationships between household energy use behaviors are estimated using a unique dataset of about 40 households and 20 showrooms in Bangladesh's Chapainawabganj and Bagerhat districts. Knowledge of energy consumption and energy efficiency technology options is found to be associated with household use of energy conservation practices. Household characteristics also influence household energy use behavior. Younger household cohorts are more likely to adopt energy-efficient technologies and energy conservation practices and place primary importance on energy saving for environmental reasons. Education also influences attitudes toward energy conservation in Bangladesh. Low-education households indicate they primarily save electricity for the environment while high-education households indicate they are motivated by environmental concerns.
This study Examines the Effectiveness of Talent Procurement through the Imple...DharmaBanothu
In the world with high technology and fast
forward mindset recruiters are walking/showing interest
towards E-Recruitment. Present most of the HRs of
many companies are choosing E-Recruitment as the best
choice for recruitment. E-Recruitment is being done
through many online platforms like Linkedin, Naukri,
Instagram , Facebook etc. Now with high technology E-
Recruitment has gone through next level by using
Artificial Intelligence too.
Key Words : Talent Management, Talent Acquisition , E-
Recruitment , Artificial Intelligence Introduction
Effectiveness of Talent Acquisition through E-
Recruitment in this topic we will discuss about 4important
and interlinked topics which are
Blood finder application project report (1).pdfKamal Acharya
Blood Finder is an emergency time app where a user can search for the blood banks as
well as the registered blood donors around Mumbai. This application also provide an
opportunity for the user of this application to become a registered donor for this user have
to enroll for the donor request from the application itself. If the admin wish to make user
a registered donor, with some of the formalities with the organization it can be done.
Specialization of this application is that the user will not have to register on sign-in for
searching the blood banks and blood donors it can be just done by installing the
application to the mobile.
The purpose of making this application is to save the user’s time for searching blood of
needed blood group during the time of the emergency.
This is an android application developed in Java and XML with the connectivity of
SQLite database. This application will provide most of basic functionality required for an
emergency time application. All the details of Blood banks and Blood donors are stored
in the database i.e. SQLite.
This application allowed the user to get all the information regarding blood banks and
blood donors such as Name, Number, Address, Blood Group, rather than searching it on
the different websites and wasting the precious time. This application is effective and
user friendly.
We have designed & manufacture the Lubi Valves LBF series type of Butterfly Valves for General Utility Water applications as well as for HVAC applications.
Build the Next Generation of Apps with the Einstein 1 Platform.
Rejoignez Philippe Ozil pour une session de workshops qui vous guidera à travers les détails de la plateforme Einstein 1, l'importance des données pour la création d'applications d'intelligence artificielle et les différents outils et technologies que Salesforce propose pour vous apporter tous les bénéfices de l'IA.
Supermarket Management System Project Report.pdfKamal Acharya
Supermarket management is a stand-alone J2EE using Eclipse Juno program.
This project contains all the necessary required information about maintaining
the supermarket billing system.
The core idea of this project to minimize the paper work and centralize the
data. Here all the communication is taken in secure manner. That is, in this
application the information will be stored in client itself. For further security the
data base is stored in the back-end oracle and so no intruders can access it.
Impartiality as per ISO /IEC 17025:2017 StandardMuhammadJazib15
This document provides basic guidelines for imparitallity requirement of ISO 17025. It defines in detial how it is met and wiudhwdih jdhsjdhwudjwkdbjwkdddddddddddkkkkkkkkkkkkkkkkkkkkkkkwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwioiiiiiiiiiiiii uwwwwwwwwwwwwwwwwhe wiqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqq gbbbbbbbbbbbbb owdjjjjjjjjjjjjjjjjjjjj widhi owqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqq uwdhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhwqiiiiiiiiiiiiiiiiiiiiiiiiiiiiw0pooooojjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjjj whhhhhhhhhhh wheeeeeeee wihieiiiiii wihe
e qqqqqqqqqqeuwiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiqw dddddddddd cccccccccccccccv s w c r
cdf cb bicbsad ishd d qwkbdwiur e wetwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwwww w
dddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddddfffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffffw
uuuuhhhhhhhhhhhhhhhhhhhhhhhhe qiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiiii iqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqq eeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeeee qqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqqccccccccccccccccccccccccccccccccccccccccccccccccccccccccccccc ccccccccccccccccccccccccccccccccccc bbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbbu uuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuum
m
m mmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmmm m i
g i dijsd sjdnsjd ndjajsdnnsa adjdnawddddddddddddd uw
2. TRAINING/INTERNSHIP REPORT ON
Construction of Elevated Road Corridor from AIIMS to Digha
at Patna in the State of Bihar
For
Bihar State Road Development Corporation Ltd.
By
GAMMON INDIA LIMITED
[EPC CONTRACTOR]
AECOM Asia Company Ltd.
in JV with
Rodic Consultants Pvt. Ltd.
[CONSULTANT]
3. ABOUT THE AUTHOR
AMIT KUMAR
I was born in Sept,1998 in Samastipur, Bihar.
I am doing Bachelor of Technology in Civil
Engineering at RRSDCE Begusarai, Bihar.
Currently I am in 3rd Year 2016-2020 Batch.
CONTACT INFORMATION
Amit Kumar
email :- i.amitkumar.001@gmail.com
Mob :- +918809141855
COLLEGE ID
Roll No. :- 16-C-08
Reg. No. :- 16101125011
Department of Civil Engineering
RRSDCE Begusarai
Department of Science and Technology
Government of Bihar
4. TRAINING/INTERNSHIP REPORT ON
Construction of Elevated Road Corridor from AIIMS to Digha
at Patna in the State of Bihar
UNDER GUIDANCE OF
Amarendra Kumar (Asst. Bridge Engg.)
Amit Kumar (Asst. Bridge Engg.)
Ashok Kumar Gupta (Asst. Highway Engg.)
Ashok Kumar Sinha (AQME)
5. ACKNOWLEDGMENTS
The internship opportunity I had with Bihar State Road Development Corporation Ltd. was a great chance for learning and
professional development. Therefore, I consider myself as a very lucky individual as I was provided with an opportunity to be
a part of it. I am also grateful for having a chance to meet so many wonderful people and professionals who led me though
this internship period.
Bearing in mind previous I am using this opportunity to express my deepest gratitude and special thanks to the MD of Bihar
State Road Development Corporation Ltd. who in spite of being extraordinarily busy with her/his duties, took time out to
hear, guide and keep me on the correct path and allowing me to carry out my project at their esteemed organization and
extending during the training.
It is my radiant sentiment to place on record my best regards, deepest sense of gratitude to Mr. Amarendra Kumar (Asst.
Bridge Engg.), Mr. Amit Kumar (Asst. Bridge Engg.), Mr. Ashok Kumar Gupta (Asst. Highway Engg.), Mr. Ashok Kumar Sinha
(AQME) for their careful and precious guidance which were extremely valuable for my study both theoretically and
practically.
I perceive as this opportunity as a big milestone in my career development. I will strive to use gained skills and knowledge in
the best possible way, and I will continue to work on their improvement, in order to attain desired career objectives. Hope to
continue cooperation with all of you in the future,
Sincerely,
AMIT KUMAR
6. INDEX
About The Author
Acknowledgments
Index
Project Information
Execution of Project
Location on Map and Satellite Images
Components of Bridge
Pile and Pile Cap
Pier and Pier Cap
Abutment
Pedestal
Bearing
Seismic Stopper
Girder
Deck
Crash Barrier
Expansion Joint
QA/QC Lab
Casting Yard
Batching Plant
Some Machines and Equipments
Some Images at Plant and
Construction Site
Safety Measures in Construction
Conclusion
Ask Any Query
7. PROJECT INFORMATION
PROJECT NAME : Construction of Elevated Road Corridor from AIIMS to Digha at Patna in the
State of Bihar
AUTHORITY : Bihar State Road Development Corporation Ltd.
AUTHORITY'S ENGINEER : M/s AECOM Asia Company Ltd. in JV with Rodic Consultants Pvt. Ltd.
PROOF CONSULTANT : B&S Engineering Consultants Pvt. Ltd.
EPC CONTRACTOR : GAMMON INDIA LIMITED
LENGTH :- 12.27 Kms [11.9 Km. + Additional south approach of Digha Rail-cum-Road Bridge at Chainage
12.27Km]
Starting Point : Km. 6.8 of NH-98 (Near AIIMS)
End Point : Digha Rail-cum-Road Bridge(At the Junction of Ganga Path)
8.
9. EXECUTION OF PROJECT
Sequence of Construction
1. Surveying
2. Analysis and design of the construction
3. Piling
a. Drilling
b. Pile cap construction
4. Construction of pier shaft and pier cap
5. Construction of pedestal and seismic stopper
6. Construction of segments and/or girders
7. Launching and gluing of segments
8. Construction of road over bridge
10.
11.
12. COMPONENTS OF BRIDGE
[A] FOUNDATION
PILE AND PILE CAP
[B] SUBSTRUCTURE
PIER AND PIER CAP
ABUTMENT
[C] SUPERSTRUCTURE
PEDESTAL
BEARING
SEISMIC STOPPER
GIRDER
DECK
CRASH BARRIER
EXPANSION JOINT
13. PILE AND PILE CAP
PILE
A pile is basically a long cylinder of a strong material such as concrete that is
pushed into the ground to act as a steady support for structures built on top of
it.Pile foundations are used in the following situations: When there is a layer of
weak soil at the surface. This layer cannot support the weight of the structure, so
the loads of the structure have to bypass this layer and be transferred to the layer
of stronger soil or rock that is below the weak layer. When a structure has very
heavy, concentrated loads, such as in a high rise buildings, bridge, or water tank
pile foundation are used. Pile foundations are capable of taking higher loads than
spread footings.
PILE CAP
A pile cap is a thick concrete mat that rests on concrete that have been driven into
soft or unstable ground to provide a suitable stable foundation. It usually forms
part of the foundation of a building, typically a multi-story building, structure or
support base for heavy equipment. The cast concrete pile cap distributes the load
of the building into the piles.
14.
15.
16. PIER AND PIER CAP
PIER
A pier is a raised structure typically supported by
well-spaced piles or pillars. Bridges, buildings, and
walkways may all be supported by piers.
PIER CAP
The upper or bearing part of a bridge pier; usually
made of concrete or hard stone; designed to
distribute concentrated loads evenly over the area of
the pier.
19. ABUTMENT
Abutment refers to the substructure at the ends of a
bridge span or dam whereon the structure's
superstructure rests or contacts. Single-span bridges
have abutments at each end which provide vertical and
lateral support for the bridge, as well as acting as
retaining walls to resist lateral movement of the
earthen fill of the bridge approach. Multi-span bridges
require piers to support ends of spans unsupported by
abutments.
21. PEDESTAL
A concrete pedestal is a compression element provided to
carry the loads from supported elements like columns,
statues etc. It is generally provided below the metal
columns. In general pedestal width is greater than its
height.
The main functions of pedestal provision are as follows.
To avoid contact between soil and metal elements.
To offer support for elements at some elevation
To allow thinner foundation footing.
23. BEARING
A bridge bearing is a component of a bridge which typically
provides a resting surface between bridge piers and the bridge
deck. The purpose of a bearing is to allow controlled movement
and thereby reduce the stresses involved. Movement could be
thermal expansion or contraction, or movement from other sources
such as seismic activity.
There are several different types of bridge bearings which are used
depending on a number of different factors including the bridge
span. The oldest form of bridge bearing is simply two plates resting
on top of each other. A common form of modern bridge bearing is
the elastomeric bridge bearing. Another type of bridge bearing is
the mechanical bridge bearing.
There are several types of mechanical bridge bearing, such as the
pinned bearing, which in turn includes specific types such as the
rocker bearing, and the roller bearing. Another type of mechanical
bearing is the fixed bearing, which allows rotation, but not other
forms of movement.
25. SEISMIC STOPPER
Seismic stopper are mainly based on the concept of
vibration control device (VCD) with capability of
giving stable stage to the bridge and mainly it
absorbs the vibrations and prevent the collapse of
the structure.
Despite the fact that the stoppers, which restrain the
transverse seismic movements of the deck, are
frequently used in seismically isolated bridge, the use
of longitudinal stopper is relatively rare, mainly due
to the large in-service constraint movements of
bridges.
26. GIRDER
A girder is a support beam used in construction. It is
the main horizontal support of a structure which
supports smaller beams.
Girders often have an I-beam cross section
composed of two load-bearing flanges separated by
a stabilizing web, but may also have a Box shape,Z-
shape, or other forms. A girder is commonly used to
build bridges.
30. DECK
A deck is the surface of a bridge. A structural element
of its superstructure, it may be constructed of
concrete, steel, open grating, or wood. Sometimes the
deck is covered a railroad bed and track, asphalt
concrete, or other form of pavement for ease of
vehicle crossing. A concrete deck may be an integral
part of the bridge structure (T-beam or double tee
structure) or it may be supported with I-beams or steel
girders.
31. CRASH BARRIER
Crash/Traffic barriers keep vehicles within their
roadway and prevent them from colliding with
dangerous obstacles such as boulders, sign supports,
trees, bridge abutments, buildings, walls, and large
storm drains, or from traversing steep (non-
recoverable) slopes or entering deep water. They are
also installed within medians of divided highways to
prevent errant vehicles from entering the opposing
carriageway of traffic and help to reduce head-on
collisions.
32. EXPANSION JOINT
An expansion joint or movement joint is an assembly
designed to safely absorb the temperature-induced
expansion and contraction of construction materials,
to absorb vibration, to hold parts together, or to
allow movement due to ground settlement or
earthquakes. They are commonly found between
sections of buildings, bridges, sidewalks, railway
tracks, piping systems, ships, and other structures.
34. QA/QC LAB
CTM MACHINE
LOS ANGELES ABRASION APPARATUS
HOT AIR OVEN
CONCRETE FLOW TEST
SLUMP CONE
RAPID MOISTURE METER
FLAKINESS AND ELONGATION GAUGE
THIN FILM OVEN
IS SIEVE
PYCNOMETER
DUCTILITY APPARATUS
AIV APPARATUS
WATER BATH
CBR APPARATUS
MARSHAL STABILITY TEST
MARSHAL MOULD
MARSHAL PEDESTAL BIG SIZE
MARSHAL PEDESTAL SMALL SIZE
BITUMEN EXTRACTOR APPARATUS
CASAGRANDE APPARATUS
35.
36.
37.
38.
39. CASTING YARD
A casting yard is a confined place where all the concrete structures like segments,
I-girders/ beams etc are casted. The casting yard brings factory-controlled
production techniques, efficiency, quality control, and time savings to bridge
construction. Fabricating bridge segments in a separate area also removes casting
operations from the construction critical path and reduces overall construction
time.
Regardless of the project location or size, a contractor's casting yard for bridge
segments has several essential features.
These include:
-delivery and storage areas,
-a concrete batch plant,
-a rebar cage assembly area,
-one or more casting cells,
-steam curing facilities,
-geometric control stations, and
-segment storage and handling facilities.
40.
41. BATCHING PLANT
A concrete plant, also known as a batch plant or batching
plant or a concrete batching plant, is equipment that
combines various ingredients to form concrete. Some of these
inputs include water, air, admixtures, sand, aggregate (rocks,
gravel, etc.), fly ash, silica fume, slag, and cement.
There are two main types of concrete plants: Dry mix plants
and Wet mix plants, and also plants that contain both a transit
mix side and a central mix side while utilizing common
material storage points. A concrete plant can have a variety of
parts and accessories, including: mixers (either tilt drum or
horizontal or in some cases both), cement batchers, aggregate
batchers, conveyors, radial stackers, aggregate bins, cement
bins, heaters, chillers, cement silos, batch plant controls, and
dust collectors.
48. CONCLUSION
In conclusion, the training that I had already gone through is very interesting,
instructive and somehow challenging for someone that has zero-working
experience. It gave me lots of benefit and positive changes that enable me to
enter the working environment. Through this training I was able to gain new
insights and more comprehensive understanding about the real working
condition and practice.
The training has provided me the opportunities to develop and improve my
soft and functional skills. All of this valuable experience knowledge that I have
gained were not only acquired through the direct involvement in task given
but also through other aspect of the training such as work observation,
interaction with the staffs and local people.
From what I have undergone, I am hundred percent agree that the training
program have achieve its primary objective. It is the platform to prepare for
the students to face to real working life. As a result of the program, I am more
confident to enter the working world and build my future career.