SlideShare a Scribd company logo
(Field Experiences)
Installation of Advanced Composite Core Conductors:
a growing part of capacity expansion and reliability at PLN
Indera Arifianto
PT. PLN (Persero)
P3B Jawa Bali
National Seminar on
New Generation High Performance Conductors
December 4, 2014 – New Delhi, India
PLN manages a transmission network spread across hundreds of islands with a
population of almost 250 million people and over 50 million customers.
70kV 150kV 275kV 500kV
Java-Bali 3.136 13.401 - 5.053
Sumatera 318 9.069 1.374 -
East Indonesia 658 6.381 - -
TOTAL 4.112 28.851 1.374 5.053
Length of Transmission Lines (kmc)
The toughest challenge faced by PLN is maintaining transmission capacity and
meeting the rapid growth of demand and generation of new power.
• Growth on transmission lines (1,99%) and power transformer (11,91%) is still not
covering the load growth (7,5%).
• Indonesian Electrification ratio : 78%  challenge and opportunity.
PLN require a growing solution used to upgrade the existing transmission lines and
rapidly add capacity before new lines can be installed.
Only reconductoring
existing assets with new
tech. conductors can
alternatively keep pace
with PLN plans to add
5 – 10 GW per year.
Social problem:
Public resistant to new OHTL
Composite core conductors were selected by PLN as HTLS conductors:
(1) higher temp and (2) more Aluminum.
ACSR “Lion”
238mm2
AAAC “Upas”
362mm2
Al Equivalent 305
mm2
ACSS “Hen”
242mm2
1.
2.
3a.
GAP
265mm2
Steel reinforced
Various mm2
ACCR
322mm2
3b. Composite Core
360 mm2
Al Equivalent 381 mm2
High Temperature
with Low Sag
Maximize
Conductive
Material for
Lowest Losses
1
2
3Increase Operating Temperature
= Increased Ampacity
Add more conductive material
with lower conductivity,
= net improvement over ACSR
After 30 projects and almost 6,000 kilometers of installations, PLN is now have
more experiences on composite core conductor installation and performance.
No Project Name
Total
CCTs
Line
Length
Ex Upgraded New Conductor Status
1 Bukit Asam - Lahat (Sumatera) 2 44.7 ACSR Hawk Comp/Core 310 Lisbon Energized on October 2010
2 New Tangerang – Cengkareng 2 6.2 2 x ACSR Zebra 2 x Comp/Core 520 Dublin Energized on April 2011
3 Angke – Ancol 2 4.7 ACSR Drake Comp/Core 510 Warsaw Energized June 2011
4 Kota Bumi - Bukit Kemuning (Sumatera) 2 34.3 ACSR Hawk Comp/Core 310 Lisbon Energized June 2011
5 Bandung Selatan - Cigereleng 2 13.26 2 x ACSR Dove 2 x Comp/Core 310 Lisbon Energized on October 2011
6 Cibinong - Sentul - Bogor Baru 2 23 ACSR Dove Comp/Core 360 Amsterdam Energized Feb 2012
7 Mranggen Incomer 2 4.3 2 x ACSR Hawk 2 x Comp/Core Amsterdam Energized 2012
8 Pedan - Klaten 2 12.7 1 x ACSR Hawk Comp/Core 310 Lisbon Energized on April 2012
9 Langsa – Pangkalan Brandan (Sumatera) 1 78 ACSR Hawk Comp/Core 310 Lisbon 1cct energized Sept 2012
10 Langsa – Pangkalan Brandan (Sumatera) 1 78 ACSR Hawk Comp/Core 310 Lisbon 2cct energized Sept 2012
11 Pagelaran – Tegineneng (Sumatera) 2 38.5 1 x ACSR Hawk Comp/Core 310 Lisbon Energized on Sept 2012
12 Mandai-Pangkep (Makassar) 1 39.5 ACSR 150/50 Comp/Core 150 Helsinki Energized on Sept 2012
13 Kediri-Kediri Baru 2 0.7 2 x ACSR Zebra 2 x Comp/Core 520 Dublin Energized Oct 2012
14 Gilimanuk – Celukan Bawang (Bali) 2 43 2 x ACSR Hawk 2 x Comp/Core 310 Lisbon Energized Jan 2013
15 Kapal - Padang Sambian - Pesanggaran (Bali) 2 17.28 ACSR Hawk Comp/Core 310 Lisbon Energized Jan 2013
16 Probolinggo - Lumajang 2 50.5 ACSR Comp/Core 415 Brussels Energized on Mei 2013
17 Natar-Sutami 2 26.4 ACSR HAWK Comp/Core 310 Lisbon Energized on May 2013
18 Mandai – Pangkep 1 39.5 ACSR 150/50 Comp/Core 150 Helsinki Energized June 2013
19 Cibinong – ITP 2 8.5 ACSR Hawk Comp/Core 310 Lisbon 1cct energized on Oct 2013
20 PLTGU Duri – Garuda Sakti 2 80.3 ACSR HAWK Comp/Core 360 Amsterdam Energized on Dec 2013
21 Surabaya Barat – Babatan 2 15.6 ACSR Hawk Comp/Core 310 Lisbon Energized on January 2014
22 PLTGU Duri – Duri 2 42 ACSR Hawk Comp/Core 310 Lisbon Energized on April 2014
23 Baturaja - Bukit Kemuning 2 98.5 ACSR Hawk Comp/Core 310 Lisbon Energized on July 2014
24 GI Sei Harapan - GI Baloi - GI Batu Besar (Batam) 2 16.72 1x ACSR Hawk Comp/Core 310 Lisbon Energized October 2014
25 Borang - Seduduk Putih 2 13 ACSR 120/25 Comp/Core 150 Helsinki 1 cct energized Oct 2014
26 Cilegon Baru – Serang 2 22.7 ACSR Zebra Comp/Core 550 Hamburg Under Construction
27 Dumai – Duri 2 55.8 ACSR Hawk Comp/Core 310 Lisbon Under Construction
28 Baturaja – Bukit Asam 2 72.74 ACSR Hawk Comp/Core 310 Lisbon Under Construction
29 Binjai - Paya geli 2 13.7 2x ACSR Hawk 2 x Comp/Core 310 Lisbon Under Construction
30 Padalarang - Cibabat 2 9.2 2x ACSR Hawk 2 x Comp/Core 310 Lisbon Under Construction
Almost doubled ampacity
(726 amp to 1350 amp)
Without any changes to tower
constructions
Composite core have delivered on the promise of higher capacity, low I2R losses
and maintaining sag clearance without tower modifications.
Expectation Performance Results
Capacity Increase Double capacity versus installed ACSR
conductor of the same diameter.
Meets expectations. Composite core
conductors that use trapezoidal strands
of pure aluminum have matched
performance models for capacity.
Low Losses 40% reduction lower I2R losses versus ACSR
of same diameter. (~50% capacity increase
with the same I2R losses.)
Meets expectations. Composite core
conductors that use trapezoidal strands
of pure aluminum meet resistance target.
Low Sag Provide up to two times capacity while
matching the clearance of the initial ACSR
conductor.
Meets expectations. Low thermal
expansion of composite core conductors
has been proven in the field.
Ease and Speed of
Installation
Install at least 10km circuit in 2 weeks with
standard equipment/techniques to allow for
open bid with multiple bidders.
Exceeds expectations. After three years
of experience, local contactors can beat
this target of installation speed.
Cost of Project Less than ACSR conductor size increase (or
twin conductor) and tower expansion.
Meets expectations. The cost of
conductor is offset by the speed and
elimination of tower improvements.
Metal core HTLS conductors struggle to meet project capacity increases while
maintaining sag without significant tower modifications increasing time/costs.
Composite core conductors have had installation issues, but on whole it has been
identified and solved to be reliable and consistent as any conductor.
2010 2011 2012 2013 2014
# of Projects 1 4 8 7 10
KM of HTLS 268 468 1,092 1,732 2,297
# of DE/MSJ 126 / 60 912 / 112 1398 / 219 3042 / 291 3762 / 645
Small Issues 1 1 1
Large Issues 1
Case 1
Unreported installation
error while deadending.
Case 2
Puller location during stringing
led to bad installation technique
during deadending.
Case 4
Unreported installation issue during
mid span joint completion.
Case 3
Poorly manufactured conductor was delivered
to the field and decided by all parties (including
core manufacturer) to be installed with
techniques that deviated from standard.
2010: Issue #1
Installation crew did not report conductor drop during deadending process.
The Facts:
• During the deadend process,
the conductor was not
properly secured and dropped
causing damage to the core at
the grip.
• The crew did not report the
incident to the supervisor and
the damage was not repaired
until after initial energization.
Lessons Learned
• No matter how good the procedures and training are, communication is the key to
identifying damage and making repairs in the field.
• Training was changed to emphasize that reporting mistakes in not an issue.
2012: Issue #2
Unnoticed bad angle on tensioned conductor during deadending process.
The Facts:
• Excellent control of angles
were used by the contractor
on a difficult puller placement
• Damage was caused pulling
the grip to deadend.
• A repair was made and the
line has operated as expected.
Lessons Learned
• Pre-planning is important to identify areas that require non-standard techniques.
• Supervisors and Master Installers should be involved early in the project planning in
order to focus on the exceptions during a project.
2013: Issue #3
Tensioned control line during mid-span joint installation.
The Facts:
• A control line was not released
in a timely fashion after
installing a mid-span joint.
• The damage was repaired and
the line is operating as
expected.
Lessons Learned
• Trained crews and supervisors can still make mistakes during installation, but
following techniques and reporting errors can fix problems before installation.
2012: Issue #4
“Keystoned” conductor was not rejected at the factory and led to field issues.
Three examples of extreme keystoning
during installation illustrate the extent and
variability of the issue. Resulting in the
need to adjust the sagging technique.
Well made composite core conductor has
good contact between all layers of aluminum
strands and composite core.
2012: Issue #4
Systematic use of core crushing clamp to adjust for poorly made conductor.
The Facts:
• Poorly stranded conductor
resulted in grips not being able
to hold during deadending, to
avoid slippage a non-standard
technique using a wavy clamp
(deadend shoe) was
employed.
• Details of the damage and
repairs to follow.
2012: Issue #4
Extensive laboratory testing confirmed the cause of damage.
Areas under crests
Clamp with wave seat
• On all samples examined in the lab, there was an exact correlation
of the damaged areas and the waves of the deadend shoe.
• The exact amount of damaged varied by the “heaviness” of the
crimp, and perhaps by the amount of keystoning, but the sample
size was too small to confirm an exact correlation.
2012: Issue #4
Repairs were made with the support of the core and conductor supplier.
The line is now operating at ±80% of maximum capacity (±150% ACSR).
In 2010, before the first installation in Indonesia, PLN and the core and conductor
suppliers met to establish training and supervision procedures for projects.
PT PLN
Installation
EPC
Contractor
Conductor
Supplier
Composite
Core Supplier
Maintenance
1
2
4
3
5 6 7
1
2 4
3
5
6
7
Submit core and conductor
information to allow PLN to
create specifications.
Submit samples and qualify to
the PLN specification.
Supply core to manufacturer.
Supply conductor to contractor.
Training of contractor in a classroom
environment prior to job.
Field training of the installation crew
and introduction of supervisors.
Supervise in the field to ensure good
technique, make recommendations,
and troubleshoot as needed.
In 2014, after four years and 30 projects, PLN and the core and conductor
suppliers met to recommend improvements to training and supervision.
PT PLN
Installation
EPC
Contractor
Conductor
Supplier
Composite
Core Supplier
Maintenance
Training Center
1 2
3
1
2
3
The core supplier or designated
company will sign off on conductor
quality before delivery to the
jobsite.
PLN is taking a more active role in
the training and certification of
contractors to the guidelines and
techniques of all suppliers.
The core supplier or designated
company will sign off on the
installation, indicating that best
practices were followed and the
conductor is properly installed.
Example of installation training slides using pictures as well as words.
 Store the reels with flanges
upright.
 Never lay or transport the reels
on their side. Only exception is
when the reels are transported by
air freight.
 Lift reels with spreader bar/cradle
sling.
 Lift reels using ‘fork truck’
approaching from side of reel so
the weight is lifted on reel
flanges.
 Never lift reels with short slings
that cave in the sides of the reel.
Example of installation training slides using pictures as well as words.
• Do not lift the conductor with the hook
of a strap hoist or chain hoist. Lifting in
this way could damage the
conductor/core.
• Use a wide nylon strap or other lifting
device that doesn’t put a sharp angle
on the conductor/core.
• Lift on the armor rod wires to distribute
the force being applied on the
conductor.
Lifting the Conductor
Example of installation training slides using pictures as well as words.
By dropping down the insulator and hooking
the deadend to the insulator, there is very
little chance of damaging the conductor. For
higher voltages the insulators are heavy.
Use an alternate method for lifting the
conductor.
BEST PRACTICE
Acceptable but not preferred.
Birdcages are possible and the
conductor is more likely to be
damaged.
Lifting the Deadend and Conductor
Example of installation training slides using pictures as well as words.
Sagging the conductor
Control the conductor at all times from the grip back to the structure. Protect the conductor
from being damaged near the hoist hook at the grip. (See orange hose below). If the conductor
were to fall from the grip, the core could likely be damaged.
Good people and good training are the keys to all success. PLN has incorporated
composite core installation and maintenance training into standard practice.
Since 2010 there are:
• 4 Master Installers
• 11 Contractors
• 48 Supervisor
• 155 Trained linesmen
An increased focus on training began in 2014,
and will continue with PLN Corporate Univ.
Composite core conductors have proven themselves a valuable part of the PLN
solution to rapidly add transmission capacity and maintain efficiency.
Expanded use of composite core conductors on 275kv and 500kv transmission will
reduce the need for new lines to move power to critical load centers.
1. PLN General Managers, engineers, project and asset managers, and maintenance
managers have developed confidence in composite core conductors
2. Multiple suppliers of composite core conductor provide high quality and pricing
competition.
3. To meet PLN and Government plans for 5-10 GW per year, composite core
conductors are expected to be a much larger part of transmission grid expansion
in the next 5 years.
4. No other HTLS conductor can be used as effectively and quickly to add capacity
and maintain system efficiency as composite core conductors.
1. Any experienced contractor can successfully install composite core conductors if
the guidelines provided by suppliers are followed.
2. To minimize the learning curve for contractors, PLN has focused on reinforcing
the three steps of (1) planning, (2) training and (3) supervision for each project.
3. PLN support for “Master Installers” to have authority in the field during
installation has created a positive avenue to communicate questions or incidents
and continue training and troubleshooting during the job.
4. After four years of installation, composite core conductors have become a
alternative product option for PLN with multiple experienced contractors bidding
on every project.
5. Composite core conductors have proven safe and reliable on thirty projects since
2010, and PLN is considering to use composite core conductors on higher voltage
transmission lines up to 500kv in the future.
Composite core conductors have become an alternative solution for transmission
line congestion in Indonesia with 4years and 30projects of proven reliability.
Thank You

More Related Content

What's hot

Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground Resistance
Power System Operation
 
Cable
CableCable
Electrical wiring
Electrical wiringElectrical wiring
Electrical wiring
Patel Mit
 
Cables in ducts and tunnels
Cables in ducts and tunnelsCables in ducts and tunnels
Cables in ducts and tunnels
Leonardo ENERGY
 
Overload capacity of power transformers
Overload capacity of power transformersOverload capacity of power transformers
Overload capacity of power transformers
Leonardo ENERGY
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
SARAVANAN A
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
SMRITI KESHARWANI
 
Cable sizing.pptx
Cable sizing.pptxCable sizing.pptx
Cable sizing.pptx
ssuser1f60f6
 
Substation grounding
Substation groundingSubstation grounding
Substation grounding
Syed Ubaid
 
Electrical Wiring:Types of wires and Cables and the circuit control on domest...
Electrical Wiring:Types of wires and Cables and the circuit control on domest...Electrical Wiring:Types of wires and Cables and the circuit control on domest...
Electrical Wiring:Types of wires and Cables and the circuit control on domest...
maharshi solanki
 
Iec 60364 4-442
Iec 60364 4-442Iec 60364 4-442
Iec 60364 4-442
Maria Jimenez
 
Power cables
Power cablesPower cables
Power cables
ahmdfurkan
 
SERVICE MAINS.pdf
SERVICE MAINS.pdfSERVICE MAINS.pdf
SERVICE MAINS.pdf
vaasuchetu
 
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power Plant
Transmission Loss Calculation on 33 / 66 / 132 KV  Lines for Solar Power PlantTransmission Loss Calculation on 33 / 66 / 132 KV  Lines for Solar Power Plant
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power Plant
Gensol Engineering Limited
 
1.Electrical Accidents PPT - Vskp RAJESH CEA.pdf
1.Electrical Accidents PPT - Vskp RAJESH CEA.pdf1.Electrical Accidents PPT - Vskp RAJESH CEA.pdf
1.Electrical Accidents PPT - Vskp RAJESH CEA.pdf
ssuser4bcf3b
 
530009996-As-4041-Pressure-Piping.pdf
530009996-As-4041-Pressure-Piping.pdf530009996-As-4041-Pressure-Piping.pdf
530009996-As-4041-Pressure-Piping.pdf
moumo1
 
Electrical Lessons learned
Electrical Lessons learnedElectrical Lessons learned
Electrical Lessons learned
michaeljmack
 
Cable and laying
Cable and layingCable and laying
Cable and laying
BHAGWAN PRASAD
 
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEWEHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
Dr. Babasaheb Ambedkar Technological University
 
Grounding pad mounted transformers
Grounding   pad mounted transformersGrounding   pad mounted transformers
Grounding pad mounted transformers
Jimmy Chaparro
 

What's hot (20)

Principles & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground ResistancePrinciples & Testing Methods Of Earth Ground Resistance
Principles & Testing Methods Of Earth Ground Resistance
 
Cable
CableCable
Cable
 
Electrical wiring
Electrical wiringElectrical wiring
Electrical wiring
 
Cables in ducts and tunnels
Cables in ducts and tunnelsCables in ducts and tunnels
Cables in ducts and tunnels
 
Overload capacity of power transformers
Overload capacity of power transformersOverload capacity of power transformers
Overload capacity of power transformers
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Cable sizing.pptx
Cable sizing.pptxCable sizing.pptx
Cable sizing.pptx
 
Substation grounding
Substation groundingSubstation grounding
Substation grounding
 
Electrical Wiring:Types of wires and Cables and the circuit control on domest...
Electrical Wiring:Types of wires and Cables and the circuit control on domest...Electrical Wiring:Types of wires and Cables and the circuit control on domest...
Electrical Wiring:Types of wires and Cables and the circuit control on domest...
 
Iec 60364 4-442
Iec 60364 4-442Iec 60364 4-442
Iec 60364 4-442
 
Power cables
Power cablesPower cables
Power cables
 
SERVICE MAINS.pdf
SERVICE MAINS.pdfSERVICE MAINS.pdf
SERVICE MAINS.pdf
 
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power Plant
Transmission Loss Calculation on 33 / 66 / 132 KV  Lines for Solar Power PlantTransmission Loss Calculation on 33 / 66 / 132 KV  Lines for Solar Power Plant
Transmission Loss Calculation on 33 / 66 / 132 KV Lines for Solar Power Plant
 
1.Electrical Accidents PPT - Vskp RAJESH CEA.pdf
1.Electrical Accidents PPT - Vskp RAJESH CEA.pdf1.Electrical Accidents PPT - Vskp RAJESH CEA.pdf
1.Electrical Accidents PPT - Vskp RAJESH CEA.pdf
 
530009996-As-4041-Pressure-Piping.pdf
530009996-As-4041-Pressure-Piping.pdf530009996-As-4041-Pressure-Piping.pdf
530009996-As-4041-Pressure-Piping.pdf
 
Electrical Lessons learned
Electrical Lessons learnedElectrical Lessons learned
Electrical Lessons learned
 
Cable and laying
Cable and layingCable and laying
Cable and laying
 
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEWEHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
EHVAC TRANSMISSION LINE MAINTENANCE TECHNIQUES IN INDIAN PERSPECTIVE-A REVIEW
 
Grounding pad mounted transformers
Grounding   pad mounted transformersGrounding   pad mounted transformers
Grounding pad mounted transformers
 

Viewers also liked

CTC Global ACCC conductor overview august 2016
CTC Global ACCC conductor overview august 2016CTC Global ACCC conductor overview august 2016
CTC Global ACCC conductor overview august 2016
Dave Bryant
 
ACCC Engineering Manual
ACCC Engineering ManualACCC Engineering Manual
ACCC Engineering Manual
Dave Bryant
 
Characteristics of overhead conductors
Characteristics of overhead conductorsCharacteristics of overhead conductors
Characteristics of overhead conductors
ilyas_ghumman
 
Conductors
ConductorsConductors
Conductors
mohammed rida
 
Electrical conductors & insulators
Electrical conductors & insulatorsElectrical conductors & insulators
Electrical conductors & insulators
thompsonj1064
 
New generation of copper conductors for overhead lines
New generation of copper conductors for overhead linesNew generation of copper conductors for overhead lines
New generation of copper conductors for overhead lines
Leonardo ENERGY
 
Hard-Drawn Copper Conductors for Over Head Power Transmission
Hard-Drawn Copper Conductors for Over Head Power TransmissionHard-Drawn Copper Conductors for Over Head Power Transmission
Hard-Drawn Copper Conductors for Over Head Power Transmission
Chirag vasava
 
AST 406 Conductors
AST 406 ConductorsAST 406 Conductors
AST 406 Conductors
Neil MacIntosh
 
Conductors and Insulators-quiz
Conductors and Insulators-quizConductors and Insulators-quiz
Conductors and Insulators-quiz
neelusis5
 
insulators, conductors, transformer and ac motors
insulators, conductors, transformer and ac motorsinsulators, conductors, transformer and ac motors
insulators, conductors, transformer and ac motors
Chippa Srikanth
 
Conductors and insulators
Conductors and insulatorsConductors and insulators
Conductors and insulators
johnron16
 
Conductors and insulators
Conductors and insulatorsConductors and insulators
Conductors and insulators
Mr. M
 
transmission line
transmission line transmission line
transmission line
singh1515
 
INSULATORS AND ITS TYPES
INSULATORS AND ITS TYPESINSULATORS AND ITS TYPES
INSULATORS AND ITS TYPES
Raviteja Damerla
 

Viewers also liked (14)

CTC Global ACCC conductor overview august 2016
CTC Global ACCC conductor overview august 2016CTC Global ACCC conductor overview august 2016
CTC Global ACCC conductor overview august 2016
 
ACCC Engineering Manual
ACCC Engineering ManualACCC Engineering Manual
ACCC Engineering Manual
 
Characteristics of overhead conductors
Characteristics of overhead conductorsCharacteristics of overhead conductors
Characteristics of overhead conductors
 
Conductors
ConductorsConductors
Conductors
 
Electrical conductors & insulators
Electrical conductors & insulatorsElectrical conductors & insulators
Electrical conductors & insulators
 
New generation of copper conductors for overhead lines
New generation of copper conductors for overhead linesNew generation of copper conductors for overhead lines
New generation of copper conductors for overhead lines
 
Hard-Drawn Copper Conductors for Over Head Power Transmission
Hard-Drawn Copper Conductors for Over Head Power TransmissionHard-Drawn Copper Conductors for Over Head Power Transmission
Hard-Drawn Copper Conductors for Over Head Power Transmission
 
AST 406 Conductors
AST 406 ConductorsAST 406 Conductors
AST 406 Conductors
 
Conductors and Insulators-quiz
Conductors and Insulators-quizConductors and Insulators-quiz
Conductors and Insulators-quiz
 
insulators, conductors, transformer and ac motors
insulators, conductors, transformer and ac motorsinsulators, conductors, transformer and ac motors
insulators, conductors, transformer and ac motors
 
Conductors and insulators
Conductors and insulatorsConductors and insulators
Conductors and insulators
 
Conductors and insulators
Conductors and insulatorsConductors and insulators
Conductors and insulators
 
transmission line
transmission line transmission line
transmission line
 
INSULATORS AND ITS TYPES
INSULATORS AND ITS TYPESINSULATORS AND ITS TYPES
INSULATORS AND ITS TYPES
 

Similar to Installation of Advanced Composite Core Conductors in Indonesia

New project report
New project reportNew project report
New project report
Sai Printers
 
ACCC Conductor Overview August 2019
ACCC Conductor Overview August 2019ACCC Conductor Overview August 2019
ACCC Conductor Overview August 2019
Dave Bryant
 
Optical fibre testing mahendra singh
Optical fibre testing mahendra singhOptical fibre testing mahendra singh
Optical fibre testing mahendra singh
Mahendra Singh
 
PECO Co-op Presentation-Final
PECO Co-op Presentation-FinalPECO Co-op Presentation-Final
PECO Co-op Presentation-Final
Jithin Thenasseril
 
WHO final
WHO  finalWHO  final
WHO final
Qasim Muhammad
 
Jeevan1
Jeevan1Jeevan1
Indian Railway
Indian Railway Indian Railway
Indian Railway
Vinayak Prabhutendolkar
 
NAREN RESUME (1)
NAREN RESUME (1)NAREN RESUME (1)
NAREN RESUME (1)
Narendran B
 
2012 offshore wind cables
2012 offshore wind cables2012 offshore wind cables
2012 offshore wind cables
MEC Intelligence
 
Brief Profile_Aug-15
Brief Profile_Aug-15Brief Profile_Aug-15
Brief Profile_Aug-15
JASHO MONDAL
 
Final Report -Group-41
Final Report -Group-41Final Report -Group-41
Final Report -Group-41
Habib Ali Khan
 
Curriculum vitae meganathan n e-16302
Curriculum vitae  meganathan n  e-16302Curriculum vitae  meganathan n  e-16302
Curriculum vitae meganathan n e-16302
MeganathanNagaraj
 
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
AbdalmoedAlaiashy2
 
Three core extra high voltage cable – a global innovation
Three core extra high voltage cable – a global innovationThree core extra high voltage cable – a global innovation
Three core extra high voltage cable – a global innovation
Tata Power Delhi Distribution Limited
 
A thesis on pi robot
A thesis on pi robotA thesis on pi robot
A thesis on pi robot
Nitesh Prasad
 
PEL Report
PEL ReportPEL Report
PEL Report
Numan Ameer Nizami
 
4330903.pdf
4330903.pdf4330903.pdf
4330903.pdf
shwetaprajapati6
 
Industrial trainning r_gemco
Industrial trainning r_gemcoIndustrial trainning r_gemco
Industrial trainning r_gemco
ET181010SheikErfanAh
 
Jmv presentation smart process plant
Jmv  presentation  smart process plantJmv  presentation  smart process plant
Jmv presentation smart process plant
Mahesh Chandra Manav
 
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
Thorne & Derrick International
 

Similar to Installation of Advanced Composite Core Conductors in Indonesia (20)

New project report
New project reportNew project report
New project report
 
ACCC Conductor Overview August 2019
ACCC Conductor Overview August 2019ACCC Conductor Overview August 2019
ACCC Conductor Overview August 2019
 
Optical fibre testing mahendra singh
Optical fibre testing mahendra singhOptical fibre testing mahendra singh
Optical fibre testing mahendra singh
 
PECO Co-op Presentation-Final
PECO Co-op Presentation-FinalPECO Co-op Presentation-Final
PECO Co-op Presentation-Final
 
WHO final
WHO  finalWHO  final
WHO final
 
Jeevan1
Jeevan1Jeevan1
Jeevan1
 
Indian Railway
Indian Railway Indian Railway
Indian Railway
 
NAREN RESUME (1)
NAREN RESUME (1)NAREN RESUME (1)
NAREN RESUME (1)
 
2012 offshore wind cables
2012 offshore wind cables2012 offshore wind cables
2012 offshore wind cables
 
Brief Profile_Aug-15
Brief Profile_Aug-15Brief Profile_Aug-15
Brief Profile_Aug-15
 
Final Report -Group-41
Final Report -Group-41Final Report -Group-41
Final Report -Group-41
 
Curriculum vitae meganathan n e-16302
Curriculum vitae  meganathan n  e-16302Curriculum vitae  meganathan n  e-16302
Curriculum vitae meganathan n e-16302
 
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
04-Fiber-Optic-Test-Enhancement-Project-Update-Meeting-08-10-2022.pptx
 
Three core extra high voltage cable – a global innovation
Three core extra high voltage cable – a global innovationThree core extra high voltage cable – a global innovation
Three core extra high voltage cable – a global innovation
 
A thesis on pi robot
A thesis on pi robotA thesis on pi robot
A thesis on pi robot
 
PEL Report
PEL ReportPEL Report
PEL Report
 
4330903.pdf
4330903.pdf4330903.pdf
4330903.pdf
 
Industrial trainning r_gemco
Industrial trainning r_gemcoIndustrial trainning r_gemco
Industrial trainning r_gemco
 
Jmv presentation smart process plant
Jmv  presentation  smart process plantJmv  presentation  smart process plant
Jmv presentation smart process plant
 
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
ABB Kabeldon - HV High Voltage Cable Joints, Cable Terminations & Separable C...
 

More from Dave Bryant

Learn about CTC Global and ACCC Conductor
Learn about CTC Global and ACCC ConductorLearn about CTC Global and ACCC Conductor
Learn about CTC Global and ACCC Conductor
Dave Bryant
 
How AEP leveraged CTC Global ACCC Conductor to improve transmission line effi...
How AEP leveraged CTC Global ACCC Conductor to improve transmission line effi...How AEP leveraged CTC Global ACCC Conductor to improve transmission line effi...
How AEP leveraged CTC Global ACCC Conductor to improve transmission line effi...
Dave Bryant
 
ACCC conductor overview December 2016
ACCC conductor overview December 2016ACCC conductor overview December 2016
ACCC conductor overview December 2016
Dave Bryant
 
SCS Global Certification of CTC Global ACCC Conductor
SCS Global Certification of CTC Global ACCC ConductorSCS Global Certification of CTC Global ACCC Conductor
SCS Global Certification of CTC Global ACCC Conductor
Dave Bryant
 
CTC Global ACCC conductor newsletter May 2016
CTC Global ACCC conductor newsletter May 2016CTC Global ACCC conductor newsletter May 2016
CTC Global ACCC conductor newsletter May 2016
Dave Bryant
 
CTC Global ACCC conductor update June 2016
CTC Global ACCC conductor update June 2016CTC Global ACCC conductor update June 2016
CTC Global ACCC conductor update June 2016
Dave Bryant
 
CTC Global ACCC conductor update July 2016
CTC Global ACCC conductor update July 2016CTC Global ACCC conductor update July 2016
CTC Global ACCC conductor update July 2016
Dave Bryant
 
AEP texas project edison award winner
AEP texas project edison award winnerAEP texas project edison award winner
AEP texas project edison award winner
Dave Bryant
 
Installing ACCC conductor in Congo Africa
Installing ACCC conductor in Congo AfricaInstalling ACCC conductor in Congo Africa
Installing ACCC conductor in Congo Africa
Dave Bryant
 
CTC Global ACCC Conductor efficiency presentation 2016
CTC Global ACCC Conductor efficiency presentation 2016CTC Global ACCC Conductor efficiency presentation 2016
CTC Global ACCC Conductor efficiency presentation 2016
Dave Bryant
 
How ACCC Conductor can help meet the Clean Power Plan mandate
How ACCC Conductor can help meet the Clean Power Plan mandateHow ACCC Conductor can help meet the Clean Power Plan mandate
How ACCC Conductor can help meet the Clean Power Plan mandate
Dave Bryant
 
CTC Global's ACCC conductor reduces CO2 emissions
CTC Global's ACCC conductor reduces CO2 emissionsCTC Global's ACCC conductor reduces CO2 emissions
CTC Global's ACCC conductor reduces CO2 emissions
Dave Bryant
 
CTC Global - Economic & Environmental Impact of Power Line Loss Reductions
CTC Global - Economic & Environmental Impact of Power Line Loss ReductionsCTC Global - Economic & Environmental Impact of Power Line Loss Reductions
CTC Global - Economic & Environmental Impact of Power Line Loss Reductions
Dave Bryant
 
CTC Global ISO Certification
CTC Global ISO CertificationCTC Global ISO Certification
CTC Global ISO Certification
Dave Bryant
 

More from Dave Bryant (14)

Learn about CTC Global and ACCC Conductor
Learn about CTC Global and ACCC ConductorLearn about CTC Global and ACCC Conductor
Learn about CTC Global and ACCC Conductor
 
How AEP leveraged CTC Global ACCC Conductor to improve transmission line effi...
How AEP leveraged CTC Global ACCC Conductor to improve transmission line effi...How AEP leveraged CTC Global ACCC Conductor to improve transmission line effi...
How AEP leveraged CTC Global ACCC Conductor to improve transmission line effi...
 
ACCC conductor overview December 2016
ACCC conductor overview December 2016ACCC conductor overview December 2016
ACCC conductor overview December 2016
 
SCS Global Certification of CTC Global ACCC Conductor
SCS Global Certification of CTC Global ACCC ConductorSCS Global Certification of CTC Global ACCC Conductor
SCS Global Certification of CTC Global ACCC Conductor
 
CTC Global ACCC conductor newsletter May 2016
CTC Global ACCC conductor newsletter May 2016CTC Global ACCC conductor newsletter May 2016
CTC Global ACCC conductor newsletter May 2016
 
CTC Global ACCC conductor update June 2016
CTC Global ACCC conductor update June 2016CTC Global ACCC conductor update June 2016
CTC Global ACCC conductor update June 2016
 
CTC Global ACCC conductor update July 2016
CTC Global ACCC conductor update July 2016CTC Global ACCC conductor update July 2016
CTC Global ACCC conductor update July 2016
 
AEP texas project edison award winner
AEP texas project edison award winnerAEP texas project edison award winner
AEP texas project edison award winner
 
Installing ACCC conductor in Congo Africa
Installing ACCC conductor in Congo AfricaInstalling ACCC conductor in Congo Africa
Installing ACCC conductor in Congo Africa
 
CTC Global ACCC Conductor efficiency presentation 2016
CTC Global ACCC Conductor efficiency presentation 2016CTC Global ACCC Conductor efficiency presentation 2016
CTC Global ACCC Conductor efficiency presentation 2016
 
How ACCC Conductor can help meet the Clean Power Plan mandate
How ACCC Conductor can help meet the Clean Power Plan mandateHow ACCC Conductor can help meet the Clean Power Plan mandate
How ACCC Conductor can help meet the Clean Power Plan mandate
 
CTC Global's ACCC conductor reduces CO2 emissions
CTC Global's ACCC conductor reduces CO2 emissionsCTC Global's ACCC conductor reduces CO2 emissions
CTC Global's ACCC conductor reduces CO2 emissions
 
CTC Global - Economic & Environmental Impact of Power Line Loss Reductions
CTC Global - Economic & Environmental Impact of Power Line Loss ReductionsCTC Global - Economic & Environmental Impact of Power Line Loss Reductions
CTC Global - Economic & Environmental Impact of Power Line Loss Reductions
 
CTC Global ISO Certification
CTC Global ISO CertificationCTC Global ISO Certification
CTC Global ISO Certification
 

Recently uploaded

Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
PuktoonEngr
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
Madhumitha Jayaram
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
Ratnakar Mikkili
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 

Recently uploaded (20)

Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt2. Operations Strategy in a Global Environment.ppt
2. Operations Strategy in a Global Environment.ppt
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Wearable antenna for antenna applications
Wearable antenna for antenna applicationsWearable antenna for antenna applications
Wearable antenna for antenna applications
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 

Installation of Advanced Composite Core Conductors in Indonesia

  • 1. (Field Experiences) Installation of Advanced Composite Core Conductors: a growing part of capacity expansion and reliability at PLN Indera Arifianto PT. PLN (Persero) P3B Jawa Bali National Seminar on New Generation High Performance Conductors December 4, 2014 – New Delhi, India
  • 2. PLN manages a transmission network spread across hundreds of islands with a population of almost 250 million people and over 50 million customers. 70kV 150kV 275kV 500kV Java-Bali 3.136 13.401 - 5.053 Sumatera 318 9.069 1.374 - East Indonesia 658 6.381 - - TOTAL 4.112 28.851 1.374 5.053 Length of Transmission Lines (kmc)
  • 3. The toughest challenge faced by PLN is maintaining transmission capacity and meeting the rapid growth of demand and generation of new power. • Growth on transmission lines (1,99%) and power transformer (11,91%) is still not covering the load growth (7,5%). • Indonesian Electrification ratio : 78%  challenge and opportunity.
  • 4. PLN require a growing solution used to upgrade the existing transmission lines and rapidly add capacity before new lines can be installed. Only reconductoring existing assets with new tech. conductors can alternatively keep pace with PLN plans to add 5 – 10 GW per year. Social problem: Public resistant to new OHTL
  • 5. Composite core conductors were selected by PLN as HTLS conductors: (1) higher temp and (2) more Aluminum. ACSR “Lion” 238mm2 AAAC “Upas” 362mm2 Al Equivalent 305 mm2 ACSS “Hen” 242mm2 1. 2. 3a. GAP 265mm2 Steel reinforced Various mm2 ACCR 322mm2 3b. Composite Core 360 mm2 Al Equivalent 381 mm2 High Temperature with Low Sag Maximize Conductive Material for Lowest Losses 1 2 3Increase Operating Temperature = Increased Ampacity Add more conductive material with lower conductivity, = net improvement over ACSR
  • 6. After 30 projects and almost 6,000 kilometers of installations, PLN is now have more experiences on composite core conductor installation and performance. No Project Name Total CCTs Line Length Ex Upgraded New Conductor Status 1 Bukit Asam - Lahat (Sumatera) 2 44.7 ACSR Hawk Comp/Core 310 Lisbon Energized on October 2010 2 New Tangerang – Cengkareng 2 6.2 2 x ACSR Zebra 2 x Comp/Core 520 Dublin Energized on April 2011 3 Angke – Ancol 2 4.7 ACSR Drake Comp/Core 510 Warsaw Energized June 2011 4 Kota Bumi - Bukit Kemuning (Sumatera) 2 34.3 ACSR Hawk Comp/Core 310 Lisbon Energized June 2011 5 Bandung Selatan - Cigereleng 2 13.26 2 x ACSR Dove 2 x Comp/Core 310 Lisbon Energized on October 2011 6 Cibinong - Sentul - Bogor Baru 2 23 ACSR Dove Comp/Core 360 Amsterdam Energized Feb 2012 7 Mranggen Incomer 2 4.3 2 x ACSR Hawk 2 x Comp/Core Amsterdam Energized 2012 8 Pedan - Klaten 2 12.7 1 x ACSR Hawk Comp/Core 310 Lisbon Energized on April 2012 9 Langsa – Pangkalan Brandan (Sumatera) 1 78 ACSR Hawk Comp/Core 310 Lisbon 1cct energized Sept 2012 10 Langsa – Pangkalan Brandan (Sumatera) 1 78 ACSR Hawk Comp/Core 310 Lisbon 2cct energized Sept 2012 11 Pagelaran – Tegineneng (Sumatera) 2 38.5 1 x ACSR Hawk Comp/Core 310 Lisbon Energized on Sept 2012 12 Mandai-Pangkep (Makassar) 1 39.5 ACSR 150/50 Comp/Core 150 Helsinki Energized on Sept 2012 13 Kediri-Kediri Baru 2 0.7 2 x ACSR Zebra 2 x Comp/Core 520 Dublin Energized Oct 2012 14 Gilimanuk – Celukan Bawang (Bali) 2 43 2 x ACSR Hawk 2 x Comp/Core 310 Lisbon Energized Jan 2013 15 Kapal - Padang Sambian - Pesanggaran (Bali) 2 17.28 ACSR Hawk Comp/Core 310 Lisbon Energized Jan 2013 16 Probolinggo - Lumajang 2 50.5 ACSR Comp/Core 415 Brussels Energized on Mei 2013 17 Natar-Sutami 2 26.4 ACSR HAWK Comp/Core 310 Lisbon Energized on May 2013 18 Mandai – Pangkep 1 39.5 ACSR 150/50 Comp/Core 150 Helsinki Energized June 2013 19 Cibinong – ITP 2 8.5 ACSR Hawk Comp/Core 310 Lisbon 1cct energized on Oct 2013 20 PLTGU Duri – Garuda Sakti 2 80.3 ACSR HAWK Comp/Core 360 Amsterdam Energized on Dec 2013 21 Surabaya Barat – Babatan 2 15.6 ACSR Hawk Comp/Core 310 Lisbon Energized on January 2014 22 PLTGU Duri – Duri 2 42 ACSR Hawk Comp/Core 310 Lisbon Energized on April 2014 23 Baturaja - Bukit Kemuning 2 98.5 ACSR Hawk Comp/Core 310 Lisbon Energized on July 2014 24 GI Sei Harapan - GI Baloi - GI Batu Besar (Batam) 2 16.72 1x ACSR Hawk Comp/Core 310 Lisbon Energized October 2014 25 Borang - Seduduk Putih 2 13 ACSR 120/25 Comp/Core 150 Helsinki 1 cct energized Oct 2014 26 Cilegon Baru – Serang 2 22.7 ACSR Zebra Comp/Core 550 Hamburg Under Construction 27 Dumai – Duri 2 55.8 ACSR Hawk Comp/Core 310 Lisbon Under Construction 28 Baturaja – Bukit Asam 2 72.74 ACSR Hawk Comp/Core 310 Lisbon Under Construction 29 Binjai - Paya geli 2 13.7 2x ACSR Hawk 2 x Comp/Core 310 Lisbon Under Construction 30 Padalarang - Cibabat 2 9.2 2x ACSR Hawk 2 x Comp/Core 310 Lisbon Under Construction Almost doubled ampacity (726 amp to 1350 amp) Without any changes to tower constructions
  • 7. Composite core have delivered on the promise of higher capacity, low I2R losses and maintaining sag clearance without tower modifications. Expectation Performance Results Capacity Increase Double capacity versus installed ACSR conductor of the same diameter. Meets expectations. Composite core conductors that use trapezoidal strands of pure aluminum have matched performance models for capacity. Low Losses 40% reduction lower I2R losses versus ACSR of same diameter. (~50% capacity increase with the same I2R losses.) Meets expectations. Composite core conductors that use trapezoidal strands of pure aluminum meet resistance target. Low Sag Provide up to two times capacity while matching the clearance of the initial ACSR conductor. Meets expectations. Low thermal expansion of composite core conductors has been proven in the field. Ease and Speed of Installation Install at least 10km circuit in 2 weeks with standard equipment/techniques to allow for open bid with multiple bidders. Exceeds expectations. After three years of experience, local contactors can beat this target of installation speed. Cost of Project Less than ACSR conductor size increase (or twin conductor) and tower expansion. Meets expectations. The cost of conductor is offset by the speed and elimination of tower improvements. Metal core HTLS conductors struggle to meet project capacity increases while maintaining sag without significant tower modifications increasing time/costs.
  • 8. Composite core conductors have had installation issues, but on whole it has been identified and solved to be reliable and consistent as any conductor. 2010 2011 2012 2013 2014 # of Projects 1 4 8 7 10 KM of HTLS 268 468 1,092 1,732 2,297 # of DE/MSJ 126 / 60 912 / 112 1398 / 219 3042 / 291 3762 / 645 Small Issues 1 1 1 Large Issues 1 Case 1 Unreported installation error while deadending. Case 2 Puller location during stringing led to bad installation technique during deadending. Case 4 Unreported installation issue during mid span joint completion. Case 3 Poorly manufactured conductor was delivered to the field and decided by all parties (including core manufacturer) to be installed with techniques that deviated from standard.
  • 9. 2010: Issue #1 Installation crew did not report conductor drop during deadending process. The Facts: • During the deadend process, the conductor was not properly secured and dropped causing damage to the core at the grip. • The crew did not report the incident to the supervisor and the damage was not repaired until after initial energization. Lessons Learned • No matter how good the procedures and training are, communication is the key to identifying damage and making repairs in the field. • Training was changed to emphasize that reporting mistakes in not an issue.
  • 10. 2012: Issue #2 Unnoticed bad angle on tensioned conductor during deadending process. The Facts: • Excellent control of angles were used by the contractor on a difficult puller placement • Damage was caused pulling the grip to deadend. • A repair was made and the line has operated as expected. Lessons Learned • Pre-planning is important to identify areas that require non-standard techniques. • Supervisors and Master Installers should be involved early in the project planning in order to focus on the exceptions during a project.
  • 11. 2013: Issue #3 Tensioned control line during mid-span joint installation. The Facts: • A control line was not released in a timely fashion after installing a mid-span joint. • The damage was repaired and the line is operating as expected. Lessons Learned • Trained crews and supervisors can still make mistakes during installation, but following techniques and reporting errors can fix problems before installation.
  • 12. 2012: Issue #4 “Keystoned” conductor was not rejected at the factory and led to field issues. Three examples of extreme keystoning during installation illustrate the extent and variability of the issue. Resulting in the need to adjust the sagging technique. Well made composite core conductor has good contact between all layers of aluminum strands and composite core.
  • 13. 2012: Issue #4 Systematic use of core crushing clamp to adjust for poorly made conductor. The Facts: • Poorly stranded conductor resulted in grips not being able to hold during deadending, to avoid slippage a non-standard technique using a wavy clamp (deadend shoe) was employed. • Details of the damage and repairs to follow.
  • 14. 2012: Issue #4 Extensive laboratory testing confirmed the cause of damage. Areas under crests Clamp with wave seat • On all samples examined in the lab, there was an exact correlation of the damaged areas and the waves of the deadend shoe. • The exact amount of damaged varied by the “heaviness” of the crimp, and perhaps by the amount of keystoning, but the sample size was too small to confirm an exact correlation.
  • 15. 2012: Issue #4 Repairs were made with the support of the core and conductor supplier. The line is now operating at ±80% of maximum capacity (±150% ACSR).
  • 16. In 2010, before the first installation in Indonesia, PLN and the core and conductor suppliers met to establish training and supervision procedures for projects. PT PLN Installation EPC Contractor Conductor Supplier Composite Core Supplier Maintenance 1 2 4 3 5 6 7 1 2 4 3 5 6 7 Submit core and conductor information to allow PLN to create specifications. Submit samples and qualify to the PLN specification. Supply core to manufacturer. Supply conductor to contractor. Training of contractor in a classroom environment prior to job. Field training of the installation crew and introduction of supervisors. Supervise in the field to ensure good technique, make recommendations, and troubleshoot as needed.
  • 17. In 2014, after four years and 30 projects, PLN and the core and conductor suppliers met to recommend improvements to training and supervision. PT PLN Installation EPC Contractor Conductor Supplier Composite Core Supplier Maintenance Training Center 1 2 3 1 2 3 The core supplier or designated company will sign off on conductor quality before delivery to the jobsite. PLN is taking a more active role in the training and certification of contractors to the guidelines and techniques of all suppliers. The core supplier or designated company will sign off on the installation, indicating that best practices were followed and the conductor is properly installed.
  • 18. Example of installation training slides using pictures as well as words.  Store the reels with flanges upright.  Never lay or transport the reels on their side. Only exception is when the reels are transported by air freight.  Lift reels with spreader bar/cradle sling.  Lift reels using ‘fork truck’ approaching from side of reel so the weight is lifted on reel flanges.  Never lift reels with short slings that cave in the sides of the reel.
  • 19. Example of installation training slides using pictures as well as words. • Do not lift the conductor with the hook of a strap hoist or chain hoist. Lifting in this way could damage the conductor/core. • Use a wide nylon strap or other lifting device that doesn’t put a sharp angle on the conductor/core. • Lift on the armor rod wires to distribute the force being applied on the conductor. Lifting the Conductor
  • 20. Example of installation training slides using pictures as well as words. By dropping down the insulator and hooking the deadend to the insulator, there is very little chance of damaging the conductor. For higher voltages the insulators are heavy. Use an alternate method for lifting the conductor. BEST PRACTICE Acceptable but not preferred. Birdcages are possible and the conductor is more likely to be damaged. Lifting the Deadend and Conductor
  • 21. Example of installation training slides using pictures as well as words. Sagging the conductor Control the conductor at all times from the grip back to the structure. Protect the conductor from being damaged near the hoist hook at the grip. (See orange hose below). If the conductor were to fall from the grip, the core could likely be damaged.
  • 22. Good people and good training are the keys to all success. PLN has incorporated composite core installation and maintenance training into standard practice. Since 2010 there are: • 4 Master Installers • 11 Contractors • 48 Supervisor • 155 Trained linesmen An increased focus on training began in 2014, and will continue with PLN Corporate Univ.
  • 23. Composite core conductors have proven themselves a valuable part of the PLN solution to rapidly add transmission capacity and maintain efficiency. Expanded use of composite core conductors on 275kv and 500kv transmission will reduce the need for new lines to move power to critical load centers. 1. PLN General Managers, engineers, project and asset managers, and maintenance managers have developed confidence in composite core conductors 2. Multiple suppliers of composite core conductor provide high quality and pricing competition. 3. To meet PLN and Government plans for 5-10 GW per year, composite core conductors are expected to be a much larger part of transmission grid expansion in the next 5 years. 4. No other HTLS conductor can be used as effectively and quickly to add capacity and maintain system efficiency as composite core conductors.
  • 24. 1. Any experienced contractor can successfully install composite core conductors if the guidelines provided by suppliers are followed. 2. To minimize the learning curve for contractors, PLN has focused on reinforcing the three steps of (1) planning, (2) training and (3) supervision for each project. 3. PLN support for “Master Installers” to have authority in the field during installation has created a positive avenue to communicate questions or incidents and continue training and troubleshooting during the job. 4. After four years of installation, composite core conductors have become a alternative product option for PLN with multiple experienced contractors bidding on every project. 5. Composite core conductors have proven safe and reliable on thirty projects since 2010, and PLN is considering to use composite core conductors on higher voltage transmission lines up to 500kv in the future. Composite core conductors have become an alternative solution for transmission line congestion in Indonesia with 4years and 30projects of proven reliability.