SlideShare a Scribd company logo
1 of 26
Download to read offline
Sheath Bonding Method in Underground cables
Ahmed Adel - Project Manager (Brugg Cables)
Introduction
Now days, the underground cables became the fastest solution for electric
transmission in urban areas or crowded cities when the overhead transmission
line can’t be installed. In the 21 centauries, The HV cables industry in the world
wide had taken a lead in the commercial market offering a reasonable cable
prices with the suitable HV accessories and proper earthing methods. HV
companies had proven through years their ability to compete against each other
with a longer life XLPE cables and high quality cable accessories.
Before designing HV cable, many aspects should be taken into consideration
like: Cable voltage, short circuit calculation, cable ampacity many questions
should be asked like: cable laid in trench or buried in sand? Cable length? Is
there any cable sections? What is the earthing method used...?
Cable grounding is a very important aspect, without it, induced voltage will be
generated in the cable sheath causing over heat and leading to decrease the
cable ampacity. To overcome this issue, a lot of grounding methods had been
implemented just to choose the proper one to be compatible with the installed
cable system.
1. Cable components
Fig (1)
Shown in Fig (1):
- The main conductor which is responsible for current transferring could be
stranded or segmented depending on the conductor cross section.
- The conductor screen is a semiconducting screen to achieve homogeneous
field within insulation.
- The insulation is XLPE (cross-linked poly ethylene) with dielectric properties
surrounding the cable conductor, the surface of the insulation should be clean
from any dust or voids which can cause partial discharge leading to complete
breakdown.
- The insulation screen is a semiconductor screen to achieve homogenous
electric field within insulation.
- The metallic screen is the moisture barrier and provides the main grounding for
the cable against short circuit current in case of faults or the capacitive charging
current.
Sheath type Moisture
Protection
Mechanical
protection
Corrosion
Protection
Diameter Costs
Lead Sheath Excellent Good Excellent + ==
Lead Sheath
& copper
wires
Excellent Good
Excellent
+ =
CU
corrugated
Sheath
good Excellent Good o =
AL
corrugated
Sheath
good Good Good o o
Cu wires &
laminated
Sheath
fair Fair Good ++ o
Al wires &
laminated
Sheath
fair Fair Good ++ +
Table (1)
- Outer protective jacket is the mechanical protection for the metallic sheath and
anticorrosion layer, usually it consist of polymeric material PE (Polyethylene) or
PVC (poly vinyl chloride).
2. Faradays law
According to the basic theory of faradays law in fig(2) that: if an AC current flow
in any wire it will produce magnetic field which rotates around the wire and the
rate of change of the magnetic field will induce voltage generating electric
current, if there is a path, flows in the opposite direction of the main current.
Fig (2)
In case of the high voltage cable in fig (3), the cable conductor are surrounded by
insulation and metallic sheath, when the current flow in the main conductor the
produced magnetic field will induce voltage on the metallic sheath and if the
sheath is grounded from both ends a circulating current will start to flow which is
will affect the cable ampacity and can cause harm to personal maintenances
Fig (3)
3. Sheath losses
Applying faradays law on the high voltage cable, we will find that the sheath of
the cable acts as a secondary of a transformer; where the current in the
conductor induces voltage in the sheath.
The induced voltage depends on:
- The mutual inductance between core & sheath
- The conductor current
- The length of the cable
Assuming there is no proper grounding method for the cable, the induced e.m.f
will generate two types of losses: circulating current losses (λ1’) and eddy
current losses (λ1’’), so the total losses in cable metallic sheath:
λ 1 = λ 1’ + λ 1’’
3.1 The eddy current (λ 1’’):
Is generated on similar principle of skin and proximity effect; i.e. they are induced
by the conductor current, sheath circulating current and by current circulating in
close proximity current carrying conductor.
The induced voltage is maximum in the internal side of the sheath and minimum
in its external side. This situation induces the circulation of eddy currents in the
sheath as shown in fig (4).
Fig (4)
The eddy currents are generally of smaller magnitude when comparing with
circulating currents of solidly bonded cable sheaths and may be neglected in
case of large segmental conductors.
3.2 Circulating current (λ 1’):
Is generated when the cable sheath is forming a closed loop and grounded from
either ends or intermediate points along the cable route fig (5).
Fig 5
The value of the circulating current can be determined by the magnitude of
current in cable conductor, frequency, mean diameter, the resistance of cable
sheath and the distance between single-core cables; i.e. the mutual inductance.
As a consequence the calculation of the circulating current and the induced
voltage is done by using specialized computer program (Power cable current
Analyzer).
4. Sheath losses effect
According to IEC 287, the permissible current of an AC cable is written as
Equation in buried cables where drying out of the soil does not occur on cables
installed in the air
- Δθ: permissible temperature rise of conductor above ambient temperature.
- Wd: dielectric losses per unit length per phase.
- n: number of conductors in a cable.
- λ1,λ2: ratio of the total losses in metallic sheaths and armour respectively to the
total conductor losses.
- R: alternating current resistance of conductor at its maximum operating
temperature.
- T1: thermal resistance per core between conductor and sheath.
- T2: thermal resistance of between conductor and cable armour.
- T3: thermal resistance of external serving
- T4: thermal resistance of surrounding medium.
By computing Δθ which is the conductor maximum temperature rises above the
ambient temperature:
Δθ = (I²R + ½ Wd) T1 + [I²R (1 + λ1) + Wd] nT2 + [I²R (1+ λ1 + λ2) +
Wd) n (T3 +T4)
However in the case of a simplified cable circuit consisting of single-core cables
(n=1) provided with metallic sheath and no metallic armour (λ2 = 0 and T2 =0) and
ignoring the environmental thermal resistance (T4) the temperature rise between
conductor and cable outer surface is given with the following equation:
Δθ = I²R [T1+ T3 (1 + λ1)] + Wd (½T1 +T3)
From the above relation its clear that λ1 (losses generated due to circulating
current) is increasing the temperature rise which will reduce the cable ampacity.
as shown in fig (6) the relation between sheath current and the temperature rise
affecting the cable permissible current.
Fig (6)
Therefore, the sheath circulating current must be reduced for the increment of
transmission capacity. In addition, the high sheath current has an effect on
individuals and may cause the fault by the breakdown of insulation.
4. Sheath bonding methods
Various methods of bonding may be used for the purpose of minimizing sheath
losses. Formerly, where special bonding was employed for the prevention of
sheath losses on lead-sheathed cables without an insulating jacket, the sheaths
were subjected to ac voltages, and the bonding was designed to keep the
magnitude of the induced voltages within small limits so as to prevent the
possibility of sheath corrosion due to ac electrolysis.
Any sheath bonding or grounding method must perform the following functions:
(1) Reduce or eliminate the sheath losses
(2) Limit sheath voltages as required by the sheath sectionalizing joints.
(3) Maintain a continuous sheath circuit to permit fault-current return, and
adequate lighting and switching surge protection
4.1. Both ends bonding
- The metallic sheaths are grounded at least at the two extremes of the cable.
- This system doesn’t allow high values of the induced voltages in the metallic
sheaths. When dealing with both ends bonding cables, sheath circulating current
loss occurs because there is a closed circuit current.
- This type is applied for MV and LV cable system with short distance.
Fig (7)
Advantage:
- The two cable ends are directly connected to earth with no sheath voltage
limiter
- No need for parallel continuity earthing cable
- No stand voltage at the end of the cable
Fig (8)
Disadvantage:
- Establishing a closed circuit for the induced current causing over heat and
consequent reduction in the cable ampacity as discussed before.
Recommended:
In order to minimize the losses caused by both ends bonding, cables
should be laid in a trefoil formation and a proper balance of cable spacing for
good heat dissipation.
4.2. Single point bonding
- The simplest form of special bonding consists in arranging for the sheaths of the
three cables to be connected and grounded at one point only along their length.
- At all other points, a voltage will appear from sheath to ground that will be a
maximum at the farthest point from the ground bond. The sheaths must therefore
be adequately insulated from ground. Since there is no closed sheath circuit,
except through the sheath voltage limiter (if any), current does not normally flow
longitudinally along the sheaths and no sheath circulating current loss occurs
(sheath eddy loss will still be present) shown in fig (9).
Fig (9)
Types of single point bonding
- Types are divided according to cable length in fig (10), if the cable length is less
than 500 m or one drum length then one side bonding is applied, but if the cable
length is from 300m to 1000m long cable section then split bonded system is
applied.
Fig (10)
Advantage:
- The ampacity is higher compared with both sides bonding, as there are
practically no circulating current in cable sheath.
Disadvantage:
-
- As the screen is open, there are no circulating currents, but there is an induced
voltage appearing at the open cable screen, where sheath voltage limiters must
be installed in order to protect the cable outer jacket against transient
overvoltage.
- The length of one section is limited as the magnitude of the induced voltage is
increasing with length.
Recommended
- During a ground fault on the power system, the zero-sequence current carried by
the cable conductors could return by whatever external paths are available. A
ground fault in the immediate vicinity of the cable can cause a large difference in
ground potential rise between the two ends of the cable system, posing hazards
to personnel and equipment.
- For this reason, single-point bonded cable installations need a parallel ground
conductor, grounded at both ends of the cable route and installed very close to
the cable conductors, to carry the fault current during ground faults and to limit
the voltage rise of the sheath during ground faults to an acceptable level.
Fig (11)
- The parallel ground continuity conductor (PGCC) is usually insulated to avoid
corrosion and transposed, if the cables are not transposed, to avoid circulating
currents and losses during normal operating conditions.
- The sheath voltage reduction rate of transposed PGCC is compared with no
transposed PGCC. As shown in Fig. 11, the effect of transposed PGCC is better
than no transposed PGCC. The average reduction rate in the sheath voltage of
transposed PGCC is 70.8 %, about 8.7 % better than no transposed PGCC.
Consequently, the difference is not big compared with duct formation or directly
buried formation because the spacing between phase conductors is closer than
duct or directly buried formation fig (12).
Fig (12)
5. Cross-bonding method
- For underground circuits, longer than 1 km, the losses on the metallic sheaths
can be minimized making in each joint a cross bonding of the cable shields.
- The most basic form of cross bonding consists of sectionalizing the cable into
three minor sections of equal length and cross connecting the sheaths between
each two-minor section. Three minor cable sections form a major section fig (13).
- The natural points to establish the crossings are the joints, where appropriate
cross bonding boxes connected to the sheaths, these boxes include SVL. This
method provides balanced induced voltages at a vectorial angle of 120°of no
resultant circulating current when phasorial summation was applied.
Fig (13)
5.1. Laying formation:
5.1.1 Flat formation
a) Un Transposed:
If the single-core cables are installed in flat formation un transposed the
voltages induced in the cable sheaths of outer cables are higher than the
induced voltage in the middle cable and the vectorial (phasor) summation is
not zero fig (14). As a consequence, it is not possible to eliminate the
circulating currents in a cable circuit where only the cable sheaths are cross-
bonded. The imbalanced phasorial voltage is generating a residual voltage
which, in return would generate circulating currents.
Ub (smaller induced voltage leading to imbalance)
Uc
Ua
Fig (14)
b) Transposed:
When the cable sheaths of transposed cables occupying the same position in
circuit configuration are straight connected, the vectorial summation of
induced voltage would be zero if the system would be of balanced
parameters: currents, spacing and length.
Fig (15)
- By connecting in series the cable sheath of the three phases (120° phasor
displacement) the circulating currents could be eliminated; the phasor sum of
induced voltages could be zero if the geometrical data of cable circuit is uniform
along the three cable sections as fig (16).
Uc Ub
Ua
Fig (16)
- So, it is obvious that in order to significantly reduce or to eliminate the circulating
current losses the cable and cable sheaths must be transposed at every joint bay
position and the sheaths cross-connected with phase rotation in opposition to
that of cable transposition.
- The maximum induced voltage in respect to earth depends on the position of
each minor transposition section within the major transposition section. At the
ends of major transposition sections the cable sheaths are at earth potential as
shown in fig (17) ,while at all other points along the cable the voltage is
proportional to cable length in respect to earthing points or, for the median (2nd)
minor section, of measuring point in respect to the other two minor sections.
Fig (17)
5.1.2.Trefoil formation
- When the cables are laid in trefoil formation, the induced voltage in the sheath of
the three cables is similar so the cross-bonding method will be applied like the
flat type system with transposition. As in fig (17).
5.2. CROSS BONDING COMPONENTS
To a cross bonding system implementation the following equipments are applied:
a) Cross bonding boxes to execute the crossing of the sheaths. These boxes
include SVL and each box should have an earth electrode itself for create an
earth return circuit in each divided section of the line. These boxes should be
watertight and capable of containing the effects of the thermal or electrical
failures of any element inside the box, including a possible internal short circuit.
To facilitate its maintenance, these boxes should be installed in joints boxes with
easy access (for example through the placement of manholes) and they should
not be at more than one meter below the ground level [3].
b) Direct bonding boxes to connect the sheath directly to earth. These boxes
include earth electrode but, unlike cross bonding boxes, they do not include SVL.
c) Kits for shield interruption: it is necessary for each phase joint to introduce an
additional kit to remove the shield outside the respective box and to connect a
concentric cable.
d) Cables to the sheaths connection to cross bonding boxes: should be coaxial
cables insulated with XLPE (cross linked polyethylene) or flexible monopole
conductors. The section of these cables is determined by the maximum value of
short circuit current of the power line. Thus, the monopole conductors are directly
connected to the cross bonding boxes. The sheaths connections should be
designed to minimize the cable length, which should not exceed the 10 meters
5.3. Un balanced Conditions
In cross-bonded cable system, there are so many unbalanced conditions. These
unbalanced condition cause circulating current along the metallic sheath. Various
unbalanced conditions are considered:
- Length of minor sections
- Mixed cable arrangement in same major section
- Multiple circuits
- earthing resistance
- etc
5.3.1 Correlation of the sheath current and length imbalance
We consider unified burying formation, which is constructed by the same
formation as trefoil or duct. When the cables in each minor section have the
same length, the cables are referred to balance and the length imbalance rate is
zero. In trefoil and duct formation like Fig 18. Supposing the normal length of the
cable is 300 meters, and the lengths of the cables in the first minor section are
changing, then the imbalance rate of the system and the sheath circulating
currents are indicated in Fig 19.
Fig 19
Fig 20
The current marked with square represent the cable in trefoil formation and the
other is the duct formation:
- Its obvious that the circulating current are nearly the same in the both formation.
- The circulating current reaches Zero when all the minor sections are equal in
length which means balanced system.
- The change in length of the minor section affect the circulating current leading to
un balanced conditions.
5.4 Scenarios of Cross-bonding:
The basic form of the cross-bonding system is each major section consists of
3 minor section equal in length, and between the three minors sections the
sheath is connected to a sheath voltage limiter and earthed at the beginning
and at the end of the major section.
It is not generally possible to divide the route length into exactly matched
minor section lengths, nor is it always possible to maintain a constant spacing
of the cables throughout the route, Due to the different site situations, other
scenarios had been applied to the cross-bonding achieving the same results,
and reducing the induced sheath voltage as well.
5.4.1 Modified Cross-bonding:
In this modified version of the sectionalized cross-bonding system, it is not
necessary to have the number of minor sections exactly divisible by three.
Balanced voltage conditions within a given major section consisting of four minor
sections can be achieved by subdividing one minor section into two subsections,
as follows:
(1) One short length (or subsection) followed by two equal lengths (or
minor sections) with another short length (or subsection)
completing the major section; the combined length of the two
subsections should be equal to the length of one minor section as
shown
Fig 21
(2) One short length (or subsection) followed by one longer length
(or minor section) then another short length (or subsection)
followed by one longer length (or minor section) to complete the
major section; the two longer lengths (or minor sections) should be
equal and the combined length of the two subsections should be
equal to the length of one minor section as shown on Fig 22. In this
case, the first cross bonding must be reversed
Fig 22
5.4.2 Continuous Cross Bonding.
In this system the sheaths are cross bonded at the end of each minor section
throughout the whole cable route. The three sheaths are bonded and grounded
at the two ends of the route only, as shown in Fig 23. It is again generally
desirable that the cables are transposed so that each conductor occupies each of
the three positions for one third of the total length. The number of matched minor
sections should preferably be exactly divisible by three, but this becomes less
important as the total number of minor sections increases.
Its preferable to apply this system when there is large number of minor sections
with unequal lengths.
5.4.3 Mixed Systems.
When the number of minor sections is not exactly divisible by three, the system
may consist of a mixture of (regular or modified) cross-bonded system and
single-point bonded lengths. When necessary, on account of a large number of
minor sections having unequal lengths, the cross bonding may be of the
continuous type. Figure 24 shows the arrangement of a final single point bonded
length at the end of a cross-bonded system.
Fig 24
References:
[1] IEC 287-1-1: “Electric cables-calculation of the current rating, part 1: current rating equations (100%
load factor) and calculation of losses, section 1: general”. IEC publication 287, 1994.
[2] ANSI/IEEE Std 575-1 988, IEEE Guide for the Application of Sheath-Bonding Methods for Single
Conductor Cables and the Calculation of Induced Voltages and Currents in Cable Sheaths.
[3] J.S. Barrett, G.J.Anders. “Circulating current and hysteresis losses in screens, sheaths and armour of
electric power cables-mathematical models and comparison with IEC Standard 287”. IEE Proc.-Sei.
Meas. Technol., Vol. 144, No. 3, pp. 101-110, May 1997
[4] Peter Graneau. “Underground power transmission. The science, technology & economics of high
voltage cables”. Ed. John Wiley & Sons, 1979.
[5] Manuel Llorente Antón. “Cables eléctricos aislados. Descripción y aplicaciones practices”. Editorial
Paraninfo, 1994..
[6] Víctor Sierra Madrigal, Alfonso Sansores Escalante. “Manual técnico de cables de energía”. Ed. Mc
Graw Hill, 2ª Edición, 1984
[7] Enrique Ras. “Teoría de líneas eléctricas”. Ed. Marcombo 1986
[8] Jordi-Roger Riba, Xavier Alabern. “Experimental behavior of a magneticfield shield for an underground
power line”. Internacional Conference on Renewable Energy and Power Quality. Zaragoza, 2005.

More Related Content

What's hot

Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level CalculationDinesh Sarda
 
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINESSAG-TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINESPower System Operation
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)J. FR
 
Underground Cables
Underground Cables Underground Cables
Underground Cables Parth Pawar
 
Underground cables
Underground cablesUnderground cables
Underground cablesAnu71
 
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?Power System Operation
 
Mixed Bonding Method of High Voltage Cable
Mixed Bonding Method of High Voltage CableMixed Bonding Method of High Voltage Cable
Mixed Bonding Method of High Voltage Cableijtsrd
 
Construction EHV Transmission Line
Construction EHV Transmission LineConstruction EHV Transmission Line
Construction EHV Transmission LineSURESH GOPAL
 
Presentation1
Presentation1Presentation1
Presentation1darshanaf
 
Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601SARAVANAN A
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear johny renoald
 
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREUNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREPremanandDesai
 
Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guideSlides Hub
 

What's hot (20)

Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINESSAG-TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG-TENSION CALCULATION METHODS FOR OVERHEAD LINES
 
Load list calculation
Load list calculationLoad list calculation
Load list calculation
 
Testing of Transformer (AREVA)
Testing of Transformer (AREVA)Testing of Transformer (AREVA)
Testing of Transformer (AREVA)
 
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
ABB - TRANSFORMERS-PROTECTION-COURSE (2001)
 
Dog Conductor
Dog ConductorDog Conductor
Dog Conductor
 
Underground Cables
Underground Cables Underground Cables
Underground Cables
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
Short Circuit Calculation Symmetrical & Asymmetrical Fault Currents ?
 
Cable Sizing Calculations
Cable Sizing CalculationsCable Sizing Calculations
Cable Sizing Calculations
 
Mixed Bonding Method of High Voltage Cable
Mixed Bonding Method of High Voltage CableMixed Bonding Method of High Voltage Cable
Mixed Bonding Method of High Voltage Cable
 
Construction EHV Transmission Line
Construction EHV Transmission LineConstruction EHV Transmission Line
Construction EHV Transmission Line
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Presentation1
Presentation1Presentation1
Presentation1
 
Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601Relay Setting Calculation For REF615/ REJ601
Relay Setting Calculation For REF615/ REJ601
 
Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTREUNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
UNIT - 05 DISTRIBUTION LINES AND TRANSFORMER CENTRE
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guide
 

Viewers also liked

Examples of Some Cable Ampacity Projects Led by Dr Anders
Examples of Some Cable Ampacity Projects Led by Dr AndersExamples of Some Cable Ampacity Projects Led by Dr Anders
Examples of Some Cable Ampacity Projects Led by Dr AndersGeorge Anders
 
Tape Tile - Underground Cable Protection For HV High Voltage Cables
Tape Tile - Underground Cable Protection For HV High Voltage CablesTape Tile - Underground Cable Protection For HV High Voltage Cables
Tape Tile - Underground Cable Protection For HV High Voltage CablesThorne & Derrick International
 
Ocean Thermal Energy Conversion
Ocean Thermal Energy ConversionOcean Thermal Energy Conversion
Ocean Thermal Energy ConversionSuman Sourabh
 
Under ground cables presention
Under ground cables presentionUnder ground cables presention
Under ground cables presentionRazu Khan
 

Viewers also liked (6)

Examples of Some Cable Ampacity Projects Led by Dr Anders
Examples of Some Cable Ampacity Projects Led by Dr AndersExamples of Some Cable Ampacity Projects Led by Dr Anders
Examples of Some Cable Ampacity Projects Led by Dr Anders
 
Tape Tile - Underground Cable Protection For HV High Voltage Cables
Tape Tile - Underground Cable Protection For HV High Voltage CablesTape Tile - Underground Cable Protection For HV High Voltage Cables
Tape Tile - Underground Cable Protection For HV High Voltage Cables
 
Ug cables
Ug cablesUg cables
Ug cables
 
Ocean Thermal Energy Conversion
Ocean Thermal Energy ConversionOcean Thermal Energy Conversion
Ocean Thermal Energy Conversion
 
Cable and laying
Cable and layingCable and laying
Cable and laying
 
Under ground cables presention
Under ground cables presentionUnder ground cables presention
Under ground cables presention
 

Similar to Sheath bonding method for underground cables

Power System I Chapt 3.pdf
Power System I Chapt 3.pdfPower System I Chapt 3.pdf
Power System I Chapt 3.pdfArifeAbdulkerim
 
Simulation and detection of transients on a 150kV HV Cable-paper
Simulation and detection of transients on a 150kV HV Cable-paperSimulation and detection of transients on a 150kV HV Cable-paper
Simulation and detection of transients on a 150kV HV Cable-paperThomas Mathew
 
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...nak maneth
 
Capacitance and Cable Testing
Capacitance and Cable TestingCapacitance and Cable Testing
Capacitance and Cable TestingHussein Kassem
 
IRJET-Sensitivity Analysis of Maximum Overvoltage on Cables with Considering ...
IRJET-Sensitivity Analysis of Maximum Overvoltage on Cables with Considering ...IRJET-Sensitivity Analysis of Maximum Overvoltage on Cables with Considering ...
IRJET-Sensitivity Analysis of Maximum Overvoltage on Cables with Considering ...IRJET Journal
 
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Ivan Rojas Soliz
 
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhj
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhjCableshjtuy uifchgnhmj,kuytdfghjytfgkuhj
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhjKamalMohamed47
 
Underground Cables.pdf
Underground Cables.pdfUnderground Cables.pdf
Underground Cables.pdfAdhithyaS5
 
Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...
Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...
Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...Leonardo ENERGY
 
Basics of electrical engineering
Basics of electrical engineeringBasics of electrical engineering
Basics of electrical engineeringNishkam Dhiman
 

Similar to Sheath bonding method for underground cables (20)

Chapter 8N.pptx
Chapter 8N.pptxChapter 8N.pptx
Chapter 8N.pptx
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
B011120723
B011120723B011120723
B011120723
 
Power System I Chapt 3.pdf
Power System I Chapt 3.pdfPower System I Chapt 3.pdf
Power System I Chapt 3.pdf
 
Hv chap5
Hv chap5Hv chap5
Hv chap5
 
f2001_landinger.ppt
f2001_landinger.pptf2001_landinger.ppt
f2001_landinger.ppt
 
Simulation and detection of transients on a 150kV HV Cable-paper
Simulation and detection of transients on a 150kV HV Cable-paperSimulation and detection of transients on a 150kV HV Cable-paper
Simulation and detection of transients on a 150kV HV Cable-paper
 
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
System design-engineering-j jicable11-0279_final-evolution-in-method-performa...
 
Capacitance and Cable Testing
Capacitance and Cable TestingCapacitance and Cable Testing
Capacitance and Cable Testing
 
IRJET-Sensitivity Analysis of Maximum Overvoltage on Cables with Considering ...
IRJET-Sensitivity Analysis of Maximum Overvoltage on Cables with Considering ...IRJET-Sensitivity Analysis of Maximum Overvoltage on Cables with Considering ...
IRJET-Sensitivity Analysis of Maximum Overvoltage on Cables with Considering ...
 
CMOS Topic 4 -_the_wire
CMOS Topic 4 -_the_wireCMOS Topic 4 -_the_wire
CMOS Topic 4 -_the_wire
 
H046044147
H046044147H046044147
H046044147
 
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
Undergrounding high voltage_electricity_transmission_lines_the_technical_issu...
 
power cable1.ppt
power cable1.pptpower cable1.ppt
power cable1.ppt
 
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhj
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhjCableshjtuy uifchgnhmj,kuytdfghjytfgkuhj
Cableshjtuy uifchgnhmj,kuytdfghjytfgkuhj
 
Underground cables
Underground cablesUnderground cables
Underground cables
 
Underground Cables.pdf
Underground Cables.pdfUnderground Cables.pdf
Underground Cables.pdf
 
Unit I.pdf
Unit I.pdfUnit I.pdf
Unit I.pdf
 
Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...
Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...
Micro-alloyed copper overhead line conductors - Wire & Cable Technology Inter...
 
Basics of electrical engineering
Basics of electrical engineeringBasics of electrical engineering
Basics of electrical engineering
 

Recently uploaded

Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 

Recently uploaded (20)

Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 

Sheath bonding method for underground cables

  • 1. Sheath Bonding Method in Underground cables Ahmed Adel - Project Manager (Brugg Cables) Introduction Now days, the underground cables became the fastest solution for electric transmission in urban areas or crowded cities when the overhead transmission line can’t be installed. In the 21 centauries, The HV cables industry in the world wide had taken a lead in the commercial market offering a reasonable cable prices with the suitable HV accessories and proper earthing methods. HV companies had proven through years their ability to compete against each other with a longer life XLPE cables and high quality cable accessories. Before designing HV cable, many aspects should be taken into consideration like: Cable voltage, short circuit calculation, cable ampacity many questions should be asked like: cable laid in trench or buried in sand? Cable length? Is there any cable sections? What is the earthing method used...? Cable grounding is a very important aspect, without it, induced voltage will be generated in the cable sheath causing over heat and leading to decrease the cable ampacity. To overcome this issue, a lot of grounding methods had been implemented just to choose the proper one to be compatible with the installed cable system.
  • 2. 1. Cable components Fig (1) Shown in Fig (1): - The main conductor which is responsible for current transferring could be stranded or segmented depending on the conductor cross section. - The conductor screen is a semiconducting screen to achieve homogeneous field within insulation. - The insulation is XLPE (cross-linked poly ethylene) with dielectric properties surrounding the cable conductor, the surface of the insulation should be clean from any dust or voids which can cause partial discharge leading to complete breakdown. - The insulation screen is a semiconductor screen to achieve homogenous electric field within insulation. - The metallic screen is the moisture barrier and provides the main grounding for the cable against short circuit current in case of faults or the capacitive charging current.
  • 3. Sheath type Moisture Protection Mechanical protection Corrosion Protection Diameter Costs Lead Sheath Excellent Good Excellent + == Lead Sheath & copper wires Excellent Good Excellent + = CU corrugated Sheath good Excellent Good o = AL corrugated Sheath good Good Good o o Cu wires & laminated Sheath fair Fair Good ++ o Al wires & laminated Sheath fair Fair Good ++ + Table (1) - Outer protective jacket is the mechanical protection for the metallic sheath and anticorrosion layer, usually it consist of polymeric material PE (Polyethylene) or PVC (poly vinyl chloride). 2. Faradays law According to the basic theory of faradays law in fig(2) that: if an AC current flow in any wire it will produce magnetic field which rotates around the wire and the rate of change of the magnetic field will induce voltage generating electric current, if there is a path, flows in the opposite direction of the main current.
  • 4. Fig (2) In case of the high voltage cable in fig (3), the cable conductor are surrounded by insulation and metallic sheath, when the current flow in the main conductor the produced magnetic field will induce voltage on the metallic sheath and if the sheath is grounded from both ends a circulating current will start to flow which is will affect the cable ampacity and can cause harm to personal maintenances Fig (3)
  • 5. 3. Sheath losses Applying faradays law on the high voltage cable, we will find that the sheath of the cable acts as a secondary of a transformer; where the current in the conductor induces voltage in the sheath. The induced voltage depends on: - The mutual inductance between core & sheath - The conductor current - The length of the cable Assuming there is no proper grounding method for the cable, the induced e.m.f will generate two types of losses: circulating current losses (λ1’) and eddy current losses (λ1’’), so the total losses in cable metallic sheath: λ 1 = λ 1’ + λ 1’’ 3.1 The eddy current (λ 1’’): Is generated on similar principle of skin and proximity effect; i.e. they are induced by the conductor current, sheath circulating current and by current circulating in close proximity current carrying conductor. The induced voltage is maximum in the internal side of the sheath and minimum in its external side. This situation induces the circulation of eddy currents in the sheath as shown in fig (4).
  • 6. Fig (4) The eddy currents are generally of smaller magnitude when comparing with circulating currents of solidly bonded cable sheaths and may be neglected in case of large segmental conductors. 3.2 Circulating current (λ 1’): Is generated when the cable sheath is forming a closed loop and grounded from either ends or intermediate points along the cable route fig (5).
  • 7. Fig 5 The value of the circulating current can be determined by the magnitude of current in cable conductor, frequency, mean diameter, the resistance of cable sheath and the distance between single-core cables; i.e. the mutual inductance. As a consequence the calculation of the circulating current and the induced voltage is done by using specialized computer program (Power cable current Analyzer). 4. Sheath losses effect According to IEC 287, the permissible current of an AC cable is written as Equation in buried cables where drying out of the soil does not occur on cables installed in the air
  • 8. - Δθ: permissible temperature rise of conductor above ambient temperature. - Wd: dielectric losses per unit length per phase. - n: number of conductors in a cable. - λ1,λ2: ratio of the total losses in metallic sheaths and armour respectively to the total conductor losses. - R: alternating current resistance of conductor at its maximum operating temperature. - T1: thermal resistance per core between conductor and sheath. - T2: thermal resistance of between conductor and cable armour. - T3: thermal resistance of external serving - T4: thermal resistance of surrounding medium. By computing Δθ which is the conductor maximum temperature rises above the ambient temperature: Δθ = (I²R + ½ Wd) T1 + [I²R (1 + λ1) + Wd] nT2 + [I²R (1+ λ1 + λ2) + Wd) n (T3 +T4) However in the case of a simplified cable circuit consisting of single-core cables (n=1) provided with metallic sheath and no metallic armour (λ2 = 0 and T2 =0) and ignoring the environmental thermal resistance (T4) the temperature rise between conductor and cable outer surface is given with the following equation:
  • 9. Δθ = I²R [T1+ T3 (1 + λ1)] + Wd (½T1 +T3) From the above relation its clear that λ1 (losses generated due to circulating current) is increasing the temperature rise which will reduce the cable ampacity. as shown in fig (6) the relation between sheath current and the temperature rise affecting the cable permissible current. Fig (6) Therefore, the sheath circulating current must be reduced for the increment of transmission capacity. In addition, the high sheath current has an effect on individuals and may cause the fault by the breakdown of insulation.
  • 10. 4. Sheath bonding methods Various methods of bonding may be used for the purpose of minimizing sheath losses. Formerly, where special bonding was employed for the prevention of sheath losses on lead-sheathed cables without an insulating jacket, the sheaths were subjected to ac voltages, and the bonding was designed to keep the magnitude of the induced voltages within small limits so as to prevent the possibility of sheath corrosion due to ac electrolysis. Any sheath bonding or grounding method must perform the following functions: (1) Reduce or eliminate the sheath losses (2) Limit sheath voltages as required by the sheath sectionalizing joints. (3) Maintain a continuous sheath circuit to permit fault-current return, and adequate lighting and switching surge protection 4.1. Both ends bonding - The metallic sheaths are grounded at least at the two extremes of the cable. - This system doesn’t allow high values of the induced voltages in the metallic sheaths. When dealing with both ends bonding cables, sheath circulating current loss occurs because there is a closed circuit current. - This type is applied for MV and LV cable system with short distance.
  • 11. Fig (7) Advantage: - The two cable ends are directly connected to earth with no sheath voltage limiter - No need for parallel continuity earthing cable - No stand voltage at the end of the cable Fig (8) Disadvantage: - Establishing a closed circuit for the induced current causing over heat and consequent reduction in the cable ampacity as discussed before.
  • 12. Recommended: In order to minimize the losses caused by both ends bonding, cables should be laid in a trefoil formation and a proper balance of cable spacing for good heat dissipation. 4.2. Single point bonding - The simplest form of special bonding consists in arranging for the sheaths of the three cables to be connected and grounded at one point only along their length. - At all other points, a voltage will appear from sheath to ground that will be a maximum at the farthest point from the ground bond. The sheaths must therefore be adequately insulated from ground. Since there is no closed sheath circuit, except through the sheath voltage limiter (if any), current does not normally flow longitudinally along the sheaths and no sheath circulating current loss occurs (sheath eddy loss will still be present) shown in fig (9). Fig (9)
  • 13. Types of single point bonding - Types are divided according to cable length in fig (10), if the cable length is less than 500 m or one drum length then one side bonding is applied, but if the cable length is from 300m to 1000m long cable section then split bonded system is applied. Fig (10) Advantage: - The ampacity is higher compared with both sides bonding, as there are practically no circulating current in cable sheath. Disadvantage: - - As the screen is open, there are no circulating currents, but there is an induced voltage appearing at the open cable screen, where sheath voltage limiters must be installed in order to protect the cable outer jacket against transient overvoltage.
  • 14. - The length of one section is limited as the magnitude of the induced voltage is increasing with length. Recommended - During a ground fault on the power system, the zero-sequence current carried by the cable conductors could return by whatever external paths are available. A ground fault in the immediate vicinity of the cable can cause a large difference in ground potential rise between the two ends of the cable system, posing hazards to personnel and equipment. - For this reason, single-point bonded cable installations need a parallel ground conductor, grounded at both ends of the cable route and installed very close to the cable conductors, to carry the fault current during ground faults and to limit the voltage rise of the sheath during ground faults to an acceptable level. Fig (11)
  • 15. - The parallel ground continuity conductor (PGCC) is usually insulated to avoid corrosion and transposed, if the cables are not transposed, to avoid circulating currents and losses during normal operating conditions. - The sheath voltage reduction rate of transposed PGCC is compared with no transposed PGCC. As shown in Fig. 11, the effect of transposed PGCC is better than no transposed PGCC. The average reduction rate in the sheath voltage of transposed PGCC is 70.8 %, about 8.7 % better than no transposed PGCC. Consequently, the difference is not big compared with duct formation or directly buried formation because the spacing between phase conductors is closer than duct or directly buried formation fig (12). Fig (12)
  • 16. 5. Cross-bonding method - For underground circuits, longer than 1 km, the losses on the metallic sheaths can be minimized making in each joint a cross bonding of the cable shields. - The most basic form of cross bonding consists of sectionalizing the cable into three minor sections of equal length and cross connecting the sheaths between each two-minor section. Three minor cable sections form a major section fig (13). - The natural points to establish the crossings are the joints, where appropriate cross bonding boxes connected to the sheaths, these boxes include SVL. This method provides balanced induced voltages at a vectorial angle of 120°of no resultant circulating current when phasorial summation was applied. Fig (13)
  • 17. 5.1. Laying formation: 5.1.1 Flat formation a) Un Transposed: If the single-core cables are installed in flat formation un transposed the voltages induced in the cable sheaths of outer cables are higher than the induced voltage in the middle cable and the vectorial (phasor) summation is not zero fig (14). As a consequence, it is not possible to eliminate the circulating currents in a cable circuit where only the cable sheaths are cross- bonded. The imbalanced phasorial voltage is generating a residual voltage which, in return would generate circulating currents. Ub (smaller induced voltage leading to imbalance) Uc Ua Fig (14)
  • 18. b) Transposed: When the cable sheaths of transposed cables occupying the same position in circuit configuration are straight connected, the vectorial summation of induced voltage would be zero if the system would be of balanced parameters: currents, spacing and length. Fig (15) - By connecting in series the cable sheath of the three phases (120° phasor displacement) the circulating currents could be eliminated; the phasor sum of induced voltages could be zero if the geometrical data of cable circuit is uniform along the three cable sections as fig (16). Uc Ub Ua Fig (16)
  • 19. - So, it is obvious that in order to significantly reduce or to eliminate the circulating current losses the cable and cable sheaths must be transposed at every joint bay position and the sheaths cross-connected with phase rotation in opposition to that of cable transposition. - The maximum induced voltage in respect to earth depends on the position of each minor transposition section within the major transposition section. At the ends of major transposition sections the cable sheaths are at earth potential as shown in fig (17) ,while at all other points along the cable the voltage is proportional to cable length in respect to earthing points or, for the median (2nd) minor section, of measuring point in respect to the other two minor sections. Fig (17) 5.1.2.Trefoil formation - When the cables are laid in trefoil formation, the induced voltage in the sheath of the three cables is similar so the cross-bonding method will be applied like the flat type system with transposition. As in fig (17).
  • 20. 5.2. CROSS BONDING COMPONENTS To a cross bonding system implementation the following equipments are applied: a) Cross bonding boxes to execute the crossing of the sheaths. These boxes include SVL and each box should have an earth electrode itself for create an earth return circuit in each divided section of the line. These boxes should be watertight and capable of containing the effects of the thermal or electrical failures of any element inside the box, including a possible internal short circuit. To facilitate its maintenance, these boxes should be installed in joints boxes with easy access (for example through the placement of manholes) and they should not be at more than one meter below the ground level [3]. b) Direct bonding boxes to connect the sheath directly to earth. These boxes include earth electrode but, unlike cross bonding boxes, they do not include SVL. c) Kits for shield interruption: it is necessary for each phase joint to introduce an additional kit to remove the shield outside the respective box and to connect a concentric cable. d) Cables to the sheaths connection to cross bonding boxes: should be coaxial cables insulated with XLPE (cross linked polyethylene) or flexible monopole conductors. The section of these cables is determined by the maximum value of short circuit current of the power line. Thus, the monopole conductors are directly connected to the cross bonding boxes. The sheaths connections should be designed to minimize the cable length, which should not exceed the 10 meters 5.3. Un balanced Conditions In cross-bonded cable system, there are so many unbalanced conditions. These unbalanced condition cause circulating current along the metallic sheath. Various unbalanced conditions are considered: - Length of minor sections - Mixed cable arrangement in same major section - Multiple circuits - earthing resistance - etc
  • 21. 5.3.1 Correlation of the sheath current and length imbalance We consider unified burying formation, which is constructed by the same formation as trefoil or duct. When the cables in each minor section have the same length, the cables are referred to balance and the length imbalance rate is zero. In trefoil and duct formation like Fig 18. Supposing the normal length of the cable is 300 meters, and the lengths of the cables in the first minor section are changing, then the imbalance rate of the system and the sheath circulating currents are indicated in Fig 19. Fig 19
  • 22. Fig 20 The current marked with square represent the cable in trefoil formation and the other is the duct formation: - Its obvious that the circulating current are nearly the same in the both formation. - The circulating current reaches Zero when all the minor sections are equal in length which means balanced system. - The change in length of the minor section affect the circulating current leading to un balanced conditions. 5.4 Scenarios of Cross-bonding: The basic form of the cross-bonding system is each major section consists of 3 minor section equal in length, and between the three minors sections the sheath is connected to a sheath voltage limiter and earthed at the beginning and at the end of the major section. It is not generally possible to divide the route length into exactly matched minor section lengths, nor is it always possible to maintain a constant spacing of the cables throughout the route, Due to the different site situations, other scenarios had been applied to the cross-bonding achieving the same results, and reducing the induced sheath voltage as well.
  • 23. 5.4.1 Modified Cross-bonding: In this modified version of the sectionalized cross-bonding system, it is not necessary to have the number of minor sections exactly divisible by three. Balanced voltage conditions within a given major section consisting of four minor sections can be achieved by subdividing one minor section into two subsections, as follows: (1) One short length (or subsection) followed by two equal lengths (or minor sections) with another short length (or subsection) completing the major section; the combined length of the two subsections should be equal to the length of one minor section as shown Fig 21 (2) One short length (or subsection) followed by one longer length (or minor section) then another short length (or subsection) followed by one longer length (or minor section) to complete the major section; the two longer lengths (or minor sections) should be equal and the combined length of the two subsections should be equal to the length of one minor section as shown on Fig 22. In this case, the first cross bonding must be reversed
  • 24. Fig 22 5.4.2 Continuous Cross Bonding. In this system the sheaths are cross bonded at the end of each minor section throughout the whole cable route. The three sheaths are bonded and grounded at the two ends of the route only, as shown in Fig 23. It is again generally desirable that the cables are transposed so that each conductor occupies each of the three positions for one third of the total length. The number of matched minor sections should preferably be exactly divisible by three, but this becomes less important as the total number of minor sections increases. Its preferable to apply this system when there is large number of minor sections with unequal lengths.
  • 25. 5.4.3 Mixed Systems. When the number of minor sections is not exactly divisible by three, the system may consist of a mixture of (regular or modified) cross-bonded system and single-point bonded lengths. When necessary, on account of a large number of minor sections having unequal lengths, the cross bonding may be of the continuous type. Figure 24 shows the arrangement of a final single point bonded length at the end of a cross-bonded system. Fig 24 References: [1] IEC 287-1-1: “Electric cables-calculation of the current rating, part 1: current rating equations (100% load factor) and calculation of losses, section 1: general”. IEC publication 287, 1994. [2] ANSI/IEEE Std 575-1 988, IEEE Guide for the Application of Sheath-Bonding Methods for Single Conductor Cables and the Calculation of Induced Voltages and Currents in Cable Sheaths. [3] J.S. Barrett, G.J.Anders. “Circulating current and hysteresis losses in screens, sheaths and armour of electric power cables-mathematical models and comparison with IEC Standard 287”. IEE Proc.-Sei. Meas. Technol., Vol. 144, No. 3, pp. 101-110, May 1997 [4] Peter Graneau. “Underground power transmission. The science, technology & economics of high voltage cables”. Ed. John Wiley & Sons, 1979. [5] Manuel Llorente Antón. “Cables eléctricos aislados. Descripción y aplicaciones practices”. Editorial Paraninfo, 1994..
  • 26. [6] Víctor Sierra Madrigal, Alfonso Sansores Escalante. “Manual técnico de cables de energía”. Ed. Mc Graw Hill, 2ª Edición, 1984 [7] Enrique Ras. “Teoría de líneas eléctricas”. Ed. Marcombo 1986 [8] Jordi-Roger Riba, Xavier Alabern. “Experimental behavior of a magneticfield shield for an underground power line”. Internacional Conference on Renewable Energy and Power Quality. Zaragoza, 2005.