JEEVAN.KANNADASAN
248/4 B, Main Road, Ammapalayam post,
Perambalur DT-621101, Tamilnadu,India.
Mob: 0091-9994811152
Mob: 0091-9566535340
E-mail: jiivan.k@gmail.com
FIELD EXPERIENCE: +4YEAR 3MONTHS:
PROFESSIONAL EXPERIENCE:
1) Tuv Sud Asia pvt.ltd (India, Singapore)
Designation : Electrical Engineer
Nature of Job : QC/QA , Testing & Commissioning
Duration : July’2012 to Sep’2013
2) Tamil nadu Electricity Board (Govt of TN).
Designation : Tr.Electrical Engineer
Nature of Job : Substation Erection, Testing Commissioning
Duration : Oct’2013 to Oct’2014
4)) Amp power India (India).
Designation : Sr.Electrical(Commissioning) Engineer
Nature of Job : GIS substation Testing Commissioning
ORGANIZATION DURATION
IKE Electric Pvt.ltd (India) June’2008 to June’2009
Tuv Sud Asia pvt.ltd (India, Singapore)
July’2012 to Sep’2013
Tamil nadu Electricity Board (Govt of TN) Oct’2013 to Oct’2014
Amp power India (India) Nov’2014 to Nov’2015
Harsha Abakus solar Pvt.Ltd (India, Oman) DEC’2015 to Till Date
Duration : Nov’2014 to Nov’2015
5) Harsha Abakus solar Pvt.Ltd (India, Oman).
Designation : Sr.Electrical Engineer
Nature of Job : Substation Erection, Testing Commissioning
(AC And DC Supply)
Duration : Dec’2015 to Till date
QUALIFICATION SUMMARY:
 Background in the principles and practices of Electrical
Substation and Power plants .
 Excellent supervisory experience, including setting goals and
objectives, project development, planning and organization.
 Focused on work quality and excellence in client service.
 Experienced in Electrical Engineering respectively- SUPPORTING
WITH TESTING TEAM.
 Erection And testing commissioning for Solar ON GRID 2MWp in
Singapore Phase-1 project’s
 Testing commissioning for GIS 33KV 2*20MW in Oman (MEDC)
project’s
 Implementing safety standards and ensuring adherence to
safety norms throughout the project lifecycle from
construction to commissioning.
Harsha Abakus solar Pvt.Ltd (India, Oman).
Sr.Electrical Engineer: Dec’2015 to Till date
PROJECT/CONTRACT NAME: SunEdison Solar Energy Pvt.ltd
ROLES AND RESPONSIBILITIES:
• Design & Maintenance of Electrical Equipments.
• Troubleshooting of control and Feeder panel wiring.
• Feeder Protection system relay testing and Pre-Commissioning at
plant.
• Tracker &PV solar plates installation
Monitoring the inventory and ensured availability of all equipments prior to the installation.
Interface with Regional Dealers, Authorized Service centre & customers.
Track & resolve Customer Complaints.
Installation & Commissioning of AC And DC
Handling Complaints of Solar Photovoltaic Projects (12MWpto 60MWp).
Handling of Solar Photovoltaic Projects, Large Inverters & UPS.
Installation & Commissioning of Multi Purpose Solar power Systems.
Routine maintenance of UPS System.
Monitoring and executing the mounting racks and modules and fitting all the electrical
equipment.
• Performed troubleshoot on all the PV equipments and ensured the smooth working
Installed various mounted equipments such as rooftop and photovoltaic.
Amp power India (India)
Senior Commissioning Engineer: Oct.2014 to Oct.2015
PROJECT/CONTRACT NAME: Magala Well Pad (OIL AND GAS)India
1. C1- 33/415V GIS indoor SS (Primary)
2. C2-10*33/11/415v GIS Indoor SS
Handled the Pre-commissioning and commissioning of electrical
equipment’s
• 10*5MVA Power transformers, 33KV GIS Switchgear, 6.6KV
Switchgear, 415V MCC, AC UPS, DC UPS Systems and Battery Banks.
• Testing of Protection system include Microprocessor based relay
• Differential stability test for motor, generator, transformer
and line and HT Power Cables
• Testing and commissioning of soft starters for 3.831MW motors
• Planning for resources and manpower for planned shutdown of the
plant and execution including start-up
• Hookup the new synchronizing panel with existing synchronizing
panel
• Punch listing of completed works and monitoring nonconformities.
• Supervise and manage vendor engineering and equipment
deliverable to ensure compliance with project standards and
specifications
Experience with NR Relays:
• Motor Management relay RCS-9626CN
• Transformer Management Relay RCS-9622CN, RCS-9624CN
• Feeder Management Relay RCS-9625CN
• SID-409Reserve Supply Auto-Transfer change over Relay
• Current operated relay
• Under voltage & over voltage relay
• Restricted earth fault relay
•
Experience with SEL Relays:
• SEL787 - Transformer Protection Relay
• SEL 751A - Feeder Protection Relay
• SEL 751 - O/C & E/F Relay
• SEL 710 - Motor Protection Relay
•
Testing Equipment Handled:
• Transformer winding resistance kit.(Scope,tinsely)
• Transformer Ratio Kit(Udey Raj, tinsely)
• Primary injection kit.(Sakova)
• 1 ΦRelay test kit (Sudharsan)
• Hi-Pot test kit(0-300KV AC, 0-70KV DC).(Sakova)
• Contact Resistance Measurement Kit.(Scope)
• 3 Phase Breaker Timer Kit.(Scope)
• Knee Point Kit.(Udey Raj)
• SFRA Kit (MEGGER)
• Break oil voltage tester
• Dc Earth fault tester
• Cable fault detector.
Tamil nadu Electricity Board (Govt of TN)
 Electrical installation works of Power distribution Sub-
station respectively Gas Insulated Switchgear(110,33 and
22kv), HV Switchgear (11kv), power Transformer, station
transformer, Neutral earthing resister, Control and Relay
panels, AVR panels, Capacitors Banks, SCS panels, LVAC
panels, DCDB panels, Battery charger panels, Battery bank,
small power and lighting, small power and lighting
distribution board, indoor and outdoor earthing, lightning
protection, cable tray, truncking, GI conduits installation
for small power and lighting, Indoor and outdoor earthing.
Outdoor Switchyard erection works: Steel structure
assembling, Current Transformer, Voltage Transformer,
Isolator with and without Earth switch, Circuit breakers
post insulator, Air core line trap and lightning arrester
installation and Etc.,)
 Cable Laying of LV power and control cable. Meggering the power
and control cable and continuity test. While cable laying proper
protection for the cable and proper dressing.
 LV power cable, control cable glanding and termination for it.
Proper glanding for the cable. Determine type of cable, armoured
or non-armoured, determine type of armoured and cable overall
diameter, determine whether there is any potential for the
coupling of dissimilar (e.g. brass and aluminium).
Responsibilities:-
 Overall responsibility for site work and installation.
 Responsible for on-site work, including Electrical construction
administration and electrical engineering consultation.
 Performed site mobilization, supervision, inspections, quality
assurance, material control and site reconciliation.
 Conduct site visit and collect information required for tie-in
projects with existing facility and expansion.
 Maintained effective working relationships with field crews,
clients and consultants.
 Arranging safety meetings to the workers and suggesting them to
maintain safety measures at work area.
 Attending meeting with Clients & Consultants about the technical
problems and solve them.
 Reviewing drawings and necessary co-ordinations.
 Preparation of Technical submittal schedule, Submission and
follow-up for approval.
 Co-ordination with civil construction team.
 Additionally municipal documents preparation for the applying
building permit.
TEST EUIPMENTS HANDLED:
 DET-5 / 4R Earthing Megger
 Megger S1-5001 Insulation Tester
 Digital low resistance ohmmeter-Megger DLRO10
 Digital resistance ohmmeter-ARABCAL/DLRO 10 HD
 Micro-ohmmeter megabras MPK253
 Oil Test Kit (BDV) Megger-OTS100AF/2
 Oil Test Kit (BDV) Megger-OTS80AF/2
 Step and touch potential and Earth impedance test.
Tuv Sud Asia pvt.ltd (India, Singapore)
Electrical Engineer: Dec. July’2012 to Sep’2013
PROJECT/CONTRACT NAME: GreenE-house ( TN, Singapore)
ROLES AND RESPONSIBILITIES:
• Maintenance of Electrical Equipments.
• Troubleshooting of control and Feeder panel wiring.
• Feeder Protection system relay testing and Pre-Commissioning at
plant.
Monitoring the inventory and ensured availability of all
equipments prior to the installation.
Interface with Regional Dealers, Authorized Service centre &
customers.
Track & resolve Customer Complaints.
Installation & Commissioning of Solar Photovoltaic Projects &
Domestic Products.
Handling Complaints of Solar Photovoltaic Projects (1,10KW &5MW).
Handling of Solar Photovoltaic Projects, Large Inverters & UPS.
Installation & Commissioning of Multi Purpose Solar power Systems.
Routine maintenance of UPS System.
Monitoring and executing the mounting racks and modules and
fitting all the electrical equipment.
• Performed troubleshoot on all the PV equipments and ensured the smooth working
Installed various mounted equipments such as rooftop and photovoltaic.
PROFESSIONAL/EDUCATIONAL QUALIFICATION
EDUCATIONAL QUALIFICATION:
• B.E in Electrical & Electronics Engineering from PERIYAR
MANIAMMAI University, THANJORE. Completed in 2012 With 87.25%
• Diploma in Electrical & Electronics Engineering from Thanthai Hans
roever polytechnic college, Perambalur completed in 2008
TECHNICAL SKILL:
Programs: Microsoft Word, Excel, Power Point, Outlook.
Platforms: Windows Vista/XP/2000/2003/2008/Windows 7.
PERSIONAL DETAILS:
NAME : JEEVAN.K
DATE OF BIRTH : 30th
May 1990
FATHER’S NAME : KANNADASAN.R
MARITAL STATUS : SINGLE
PERMENANT ADDRESS : 248/4B Main road,
Ammapalayam post,
perambalur District,
Tamilnadu-625009, India.
E-mail : jiivan.k@gmail.com
PASSPORT DETAILS:
Passport Number : L4672508
Date of issue : 18/10/2013
Date of Expiry : 17/10/2023
Place of issue : Tiruchirappalli
I declare that the above information given by
me is true to the best of my knowledge and belief.
Place :
Date : Jeevan.kannadasan

Jeevan1

  • 1.
    JEEVAN.KANNADASAN 248/4 B, MainRoad, Ammapalayam post, Perambalur DT-621101, Tamilnadu,India. Mob: 0091-9994811152 Mob: 0091-9566535340 E-mail: jiivan.k@gmail.com FIELD EXPERIENCE: +4YEAR 3MONTHS: PROFESSIONAL EXPERIENCE: 1) Tuv Sud Asia pvt.ltd (India, Singapore) Designation : Electrical Engineer Nature of Job : QC/QA , Testing & Commissioning Duration : July’2012 to Sep’2013 2) Tamil nadu Electricity Board (Govt of TN). Designation : Tr.Electrical Engineer Nature of Job : Substation Erection, Testing Commissioning Duration : Oct’2013 to Oct’2014 4)) Amp power India (India). Designation : Sr.Electrical(Commissioning) Engineer Nature of Job : GIS substation Testing Commissioning ORGANIZATION DURATION IKE Electric Pvt.ltd (India) June’2008 to June’2009 Tuv Sud Asia pvt.ltd (India, Singapore) July’2012 to Sep’2013 Tamil nadu Electricity Board (Govt of TN) Oct’2013 to Oct’2014 Amp power India (India) Nov’2014 to Nov’2015 Harsha Abakus solar Pvt.Ltd (India, Oman) DEC’2015 to Till Date
  • 2.
    Duration : Nov’2014to Nov’2015 5) Harsha Abakus solar Pvt.Ltd (India, Oman). Designation : Sr.Electrical Engineer Nature of Job : Substation Erection, Testing Commissioning (AC And DC Supply) Duration : Dec’2015 to Till date QUALIFICATION SUMMARY:  Background in the principles and practices of Electrical Substation and Power plants .  Excellent supervisory experience, including setting goals and objectives, project development, planning and organization.  Focused on work quality and excellence in client service.  Experienced in Electrical Engineering respectively- SUPPORTING WITH TESTING TEAM.  Erection And testing commissioning for Solar ON GRID 2MWp in Singapore Phase-1 project’s  Testing commissioning for GIS 33KV 2*20MW in Oman (MEDC) project’s  Implementing safety standards and ensuring adherence to safety norms throughout the project lifecycle from construction to commissioning. Harsha Abakus solar Pvt.Ltd (India, Oman). Sr.Electrical Engineer: Dec’2015 to Till date PROJECT/CONTRACT NAME: SunEdison Solar Energy Pvt.ltd ROLES AND RESPONSIBILITIES: • Design & Maintenance of Electrical Equipments. • Troubleshooting of control and Feeder panel wiring. • Feeder Protection system relay testing and Pre-Commissioning at plant. • Tracker &PV solar plates installation Monitoring the inventory and ensured availability of all equipments prior to the installation. Interface with Regional Dealers, Authorized Service centre & customers. Track & resolve Customer Complaints. Installation & Commissioning of AC And DC Handling Complaints of Solar Photovoltaic Projects (12MWpto 60MWp).
  • 3.
    Handling of SolarPhotovoltaic Projects, Large Inverters & UPS. Installation & Commissioning of Multi Purpose Solar power Systems. Routine maintenance of UPS System. Monitoring and executing the mounting racks and modules and fitting all the electrical equipment. • Performed troubleshoot on all the PV equipments and ensured the smooth working Installed various mounted equipments such as rooftop and photovoltaic. Amp power India (India) Senior Commissioning Engineer: Oct.2014 to Oct.2015 PROJECT/CONTRACT NAME: Magala Well Pad (OIL AND GAS)India 1. C1- 33/415V GIS indoor SS (Primary) 2. C2-10*33/11/415v GIS Indoor SS Handled the Pre-commissioning and commissioning of electrical equipment’s • 10*5MVA Power transformers, 33KV GIS Switchgear, 6.6KV Switchgear, 415V MCC, AC UPS, DC UPS Systems and Battery Banks. • Testing of Protection system include Microprocessor based relay • Differential stability test for motor, generator, transformer and line and HT Power Cables • Testing and commissioning of soft starters for 3.831MW motors • Planning for resources and manpower for planned shutdown of the plant and execution including start-up • Hookup the new synchronizing panel with existing synchronizing panel • Punch listing of completed works and monitoring nonconformities. • Supervise and manage vendor engineering and equipment deliverable to ensure compliance with project standards and specifications Experience with NR Relays: • Motor Management relay RCS-9626CN • Transformer Management Relay RCS-9622CN, RCS-9624CN • Feeder Management Relay RCS-9625CN • SID-409Reserve Supply Auto-Transfer change over Relay • Current operated relay • Under voltage & over voltage relay • Restricted earth fault relay • Experience with SEL Relays: • SEL787 - Transformer Protection Relay
  • 4.
    • SEL 751A- Feeder Protection Relay • SEL 751 - O/C & E/F Relay • SEL 710 - Motor Protection Relay • Testing Equipment Handled: • Transformer winding resistance kit.(Scope,tinsely) • Transformer Ratio Kit(Udey Raj, tinsely) • Primary injection kit.(Sakova) • 1 ΦRelay test kit (Sudharsan) • Hi-Pot test kit(0-300KV AC, 0-70KV DC).(Sakova) • Contact Resistance Measurement Kit.(Scope) • 3 Phase Breaker Timer Kit.(Scope) • Knee Point Kit.(Udey Raj) • SFRA Kit (MEGGER) • Break oil voltage tester • Dc Earth fault tester • Cable fault detector. Tamil nadu Electricity Board (Govt of TN)  Electrical installation works of Power distribution Sub- station respectively Gas Insulated Switchgear(110,33 and 22kv), HV Switchgear (11kv), power Transformer, station transformer, Neutral earthing resister, Control and Relay panels, AVR panels, Capacitors Banks, SCS panels, LVAC panels, DCDB panels, Battery charger panels, Battery bank, small power and lighting, small power and lighting distribution board, indoor and outdoor earthing, lightning protection, cable tray, truncking, GI conduits installation for small power and lighting, Indoor and outdoor earthing. Outdoor Switchyard erection works: Steel structure assembling, Current Transformer, Voltage Transformer, Isolator with and without Earth switch, Circuit breakers post insulator, Air core line trap and lightning arrester installation and Etc.,)  Cable Laying of LV power and control cable. Meggering the power and control cable and continuity test. While cable laying proper protection for the cable and proper dressing.  LV power cable, control cable glanding and termination for it. Proper glanding for the cable. Determine type of cable, armoured or non-armoured, determine type of armoured and cable overall diameter, determine whether there is any potential for the coupling of dissimilar (e.g. brass and aluminium). Responsibilities:-  Overall responsibility for site work and installation.  Responsible for on-site work, including Electrical construction administration and electrical engineering consultation.  Performed site mobilization, supervision, inspections, quality
  • 5.
    assurance, material controland site reconciliation.  Conduct site visit and collect information required for tie-in projects with existing facility and expansion.  Maintained effective working relationships with field crews, clients and consultants.  Arranging safety meetings to the workers and suggesting them to maintain safety measures at work area.  Attending meeting with Clients & Consultants about the technical problems and solve them.  Reviewing drawings and necessary co-ordinations.  Preparation of Technical submittal schedule, Submission and follow-up for approval.  Co-ordination with civil construction team.  Additionally municipal documents preparation for the applying building permit. TEST EUIPMENTS HANDLED:  DET-5 / 4R Earthing Megger  Megger S1-5001 Insulation Tester  Digital low resistance ohmmeter-Megger DLRO10  Digital resistance ohmmeter-ARABCAL/DLRO 10 HD  Micro-ohmmeter megabras MPK253  Oil Test Kit (BDV) Megger-OTS100AF/2  Oil Test Kit (BDV) Megger-OTS80AF/2  Step and touch potential and Earth impedance test. Tuv Sud Asia pvt.ltd (India, Singapore) Electrical Engineer: Dec. July’2012 to Sep’2013 PROJECT/CONTRACT NAME: GreenE-house ( TN, Singapore) ROLES AND RESPONSIBILITIES: • Maintenance of Electrical Equipments. • Troubleshooting of control and Feeder panel wiring. • Feeder Protection system relay testing and Pre-Commissioning at plant. Monitoring the inventory and ensured availability of all equipments prior to the installation. Interface with Regional Dealers, Authorized Service centre & customers.
  • 6.
    Track & resolveCustomer Complaints. Installation & Commissioning of Solar Photovoltaic Projects & Domestic Products. Handling Complaints of Solar Photovoltaic Projects (1,10KW &5MW). Handling of Solar Photovoltaic Projects, Large Inverters & UPS. Installation & Commissioning of Multi Purpose Solar power Systems. Routine maintenance of UPS System. Monitoring and executing the mounting racks and modules and fitting all the electrical equipment. • Performed troubleshoot on all the PV equipments and ensured the smooth working Installed various mounted equipments such as rooftop and photovoltaic. PROFESSIONAL/EDUCATIONAL QUALIFICATION EDUCATIONAL QUALIFICATION: • B.E in Electrical & Electronics Engineering from PERIYAR MANIAMMAI University, THANJORE. Completed in 2012 With 87.25% • Diploma in Electrical & Electronics Engineering from Thanthai Hans roever polytechnic college, Perambalur completed in 2008 TECHNICAL SKILL: Programs: Microsoft Word, Excel, Power Point, Outlook. Platforms: Windows Vista/XP/2000/2003/2008/Windows 7. PERSIONAL DETAILS: NAME : JEEVAN.K DATE OF BIRTH : 30th May 1990 FATHER’S NAME : KANNADASAN.R MARITAL STATUS : SINGLE PERMENANT ADDRESS : 248/4B Main road, Ammapalayam post, perambalur District, Tamilnadu-625009, India. E-mail : jiivan.k@gmail.com PASSPORT DETAILS: Passport Number : L4672508 Date of issue : 18/10/2013 Date of Expiry : 17/10/2023 Place of issue : Tiruchirappalli
  • 7.
    I declare thatthe above information given by me is true to the best of my knowledge and belief. Place : Date : Jeevan.kannadasan