AEP’s Energized Reconductior Project for the Lower Rio Grande Valley
Edison Award Entry I April 2016
2
AEP’s Energized Reconductior Project for the Lower Rio Grande Valley
Edison Award Entry I April 2016
OVERVIEW
The Energized Reconductor Project of the Lower Rio Grande
Valley (LRGV) is a landmark accomplishment for American
Electric Power (AEP) and the utility industry. The 240 mile
project capitalized on multiple innovative technologies from
across the industry, allowing AEP to provide an immediate
solution to the problem of reliable electricity while addressing
future load growth.
The LRGV is served by two 345-kV transmission lines that
originate from Corpus Christi, 120 miles to the north, and
account for the bulk of the electricity carried into the LRGV.
The lines are in a vulnerable position due to the LRGV’s
dependency on them to supply the majority of the power to
South Texas, as well as their proximity to the Texas Gulf
Coast exposing them to corrosive salt spray and making them
susceptible to storm outages.
In February 2011 South Texas experienced record winter
temperatures which dropped as low as 20 degrees Fahrenheit.
For a region accustomed to average February temperatures in
the mid 60’s, these temperatures were crippling. Panicked
residents flooded the stores in search of portable heaters.
This immediate increase in demand for electricity coupled with
downed generation due to prescheduled maintenance resulted
in rolling blackouts throughout the region due to the limitations
of the transmission system.
3
AEP’s Energized Reconductior Project for the Lower Rio Grande Valley
Edison Award Entry I April 2016
CHALLENGES
Summer highs in the LRGV routinely hit triple digits. This, coupled with a 30% population growth from 2000-2010,
resulted in AEP’s peak electric demand increasing from 1000 MW in the summer of 2000 to a summer record peak
demand of 2220 MW in 2010. While an increase in load over a decade is to be expected, the 514 MW jump from the
previous summer during the 2011 winter storm (2220 MW to 2734 MW) was outside all modeled projections.
Furthermore, due to continued growth, the projected 2016 summer peak load is expected to reach 2800 MW with a
forecasted summer 2020 peak load of over 3000 MW.
An immediate plan was needed to supply relief to the circuits most affected by the short term seasonal spikes.
However, this plan also had to offer a long term solution to address the load increases for 2016, 2020 and beyond.
AEP, as well as the Electric Reliability Council of Texas (ERCOT), needed a solution that could meet the pressing
demands and provide reliability while safely maintaining an aggressive schedule. ERCOT was presented with a
number of traditional cold construction options for increasing capacity on these circuits, running the gamut of
temporary upgrades to complete overhauls. As AEP looked into permitting, right of way (ROW) acquisition and
various customer disruptions, it became apparent that these variables had a very real chance of interrupting their
customer’s service or adding unforeseen costs to the project. However, the biggest area of concern for AEP was that
ERCOT could only grant outages clearances in the spring and summer months, if at all, and the lines would be
required to be restored to full service whenever system anomalies warranted.
AEP chose the energized solution because it allowed them to use the existing right of ways and structures, limiting property
disruptions and reducing the overall cost to their customer.
4
AEP’s Energized Reconductior Project for the Lower Rio Grande Valley
Edison Award Entry I April 2016
AN INNOVATIVE
SOLUTION
Taking the list of challenges into account, it was apparent to
AEP that a traditional construction solution would only add
additional delays to an already time sensitive project and
therefore could not be counted on as a viable option to meet
the 2016 completion schedule.
AEP approached Quanta Energized Services, an entity of
Quanta Services, to discuss their live-line planning and
construction expertise. While smaller energized projects had
been successfully completed in the past, an energized
reconductor project of this size and length (240 mi.) had never
been attempted. To ensure that construction of the project
was completed by the mandated 2016 in service date, AEP
concluded that no new structures or right-of-away could be
purchased. Under this plan a lightweight, high capacity
conductor was needed and cable manufacturer CTC Global,
with their revolutionary ACCC Composite Core Conductor,
were brought onboard the project team. AEP, confident that
the issues associated with traditional transmission line
construction had been averted. A joint work plan with Quanta
Energized Services technical advisors to reconductor the
entire 240 miles while keeping the lines in-service and
energized. In early spring 2011, AEP’s plan to perform the
energized reconductor of the existing 345-kV transmission
lines was approved by the regional planning group at ERCOT.
Above: Quanta Energized Services Linemaster Robotic Arm
chosen for AEP LRGV Reconductor.
Below: Aluminum Conductor Composite Core (ACCC) a lighter
alternative to conventional conductor, reduces sag while
doubling the capacity. This project was the longest installation
of advanced conductor in North America.
5
AEP’s Energized Reconductior Project for the Lower Rio Grande Valley
Edison Award Entry I April 2016
STATE-OF-THE-ART TECHNOLOGIES
Through the innovative partnerships with Quanta and CTC Global, AEP was able to capitalize on several 21st century
technologies that not only accelerated the work schedule to ensure that the required in service date for the upgraded
line was achieved but also benefit the environment and increase the level of safety for all involved. The two
technological advances that made this project possible were:
Aluminum Conductor Composite Core (ACCC)
• The use of Aluminum Conductor Composite Core (ACCC) to replace the existing conductor. While the same
diameter as the original conductor, ACCC, due to the reduced size composite core, is comprised of 28%
more aluminum.
• The extra aluminum and higher temperature rating allows for twice the capacity of conventional conductor.
The composite core reduces thermal sag. Replacing the old conductor with one of the same diameter and
weight but more capacity meant that AEP could replace the old conductor without widening clearances or
causing tower modifications and rebuilds.
• Due to the added aluminum, line losses were reduced by up to 40%, equaling a savings of over $30 million
dollars in the first year alone.
• The lower emission from the CO2 reductions in the first year is equivalent to removing 34,000 cars from the
road.
• Also of great importance, due to the location of the job, the ACCC is more resistant to corrosion and has the
ability to handle future increases in load.
Energized Barehand Work Methods & Linemaster Robotic Arm
• The Energized Barehand work methods and proprietary LineMaster Robotic Arm made it possible for all 240
miles of 345kV conductor to be removed and replaced without interrupting the flow of electricity.
• Attached to a boom on a ground-based vehicle, the LineMaster Robotic Arm safely moves and securely
holds energized power lines while the conductors, insulators and structures are maintained, replaced or
rebuilt.
• The LineMaster Robotic Arm allowed the construction team to safely work without any outages on the
project.
• Its all weather capabilities allowed for it to remain in place during poor weather while the crew found shelter
and then continue work once the weather had passed.
• In addition to the robotic arm, barehand work methods and proprietary energized reconductoring procedures
were developed by a team which collectively has more than 400 years of energized work experience, starting
with the first-ever energized reconductor project in 1990.
• These methods, tools and equipment have been and continue to be tested and improved in the field and at
the world renown STRI lab in Sweden.
6
AEP’s Energized Reconductior Project for the Lower Rio Grande Valley
Edison Award Entry I April 2016
PROJECT EXECUTION
Once AEP identified the technology needed to
complete this project and received approval from
ERCOT to proceed, they went about coordinating the
various complexities and components related to a
project of this size. Constructing the project safely
while not sacrificing the reliable power AEP’s
customers expect on a daily basis were key drivers.
Due to the vulnerability of the system, the key areas
that needed to be upgraded were identified and
prioritized. The difficulty of this task was multiplied by
the fact that a segment of conductor needing to be
upgraded often times was not connected to a
substation that needed to be upgraded first. AEP
closely managed all of these variables to ensure that
there were no delays, work stoppages, or power
outages.
A year before the first lineman hit the right-of-way,
AEP and the Quanta Energized Services technical
advisors went about developing detailed, project-
specific work procedures with calculated man-hours,
sequencing, schedules and anticipated resources.
The project called for an aggressive schedule to
ensure that the line would be upgraded by the
required date. The project was divided into five
segments between the substations. Doing so
resulted in several strategic, as well as, financial
benefits:
• It reduced the risk on the entire system
serving the LRGV;
• It prioritized the line sections between the
substations, so that the completed areas
could immediately reap the benefits of the
system upgrade;
• It created five smaller projects, which
increased the efficiency of scheduling
materials, equipment and crews, as well as
minimizing the project costs.
This is a temporary D Phase structure that has been
installed inside of a three pole angle, allowing the outside
phase to be transferred. This creates an open position on
the existing pole to pull the new wire in. When the new
wire is in, loads are transferred to deengerize another
phase and pull another wire.
An energized reconductor of this size required careful
planning. Work procedures for each task had to be
developed. A group of technical advisors collaborated
together to produce these procedures. As the project
progressed, lessons were learned and these
procedures were further refined and revised.
The barehand work method was instrumental to the
work that was performed on the energized conductors.
When working barehand, the lineman wear conductive
suits and are bonded to the conductor, putting them at
the same potential as the energized conductor
allowing them to physically touch and work on the
energized conductor and equipment. To support
conductors while unclipping or clipping, the
LineMaster Single Point Lifter robotic arm was used.
This tool provided safe, secure and controlled support
of the energized conductors.
In order to replace conductors in an energized state, a
temporary support for a phase conductor needed to be
established. This was done by installing temporary
structures along the edge of the right of way next to
the existing line. Since the temporary structures were
installed within the ROW, no additional land or the
timely permits associated with land acquisition were
required.
7
AEP’s Energized Reconductior Project for the Lower Rio Grande Valley
Edison Award Entry I April 2016
The new conductor was then installed in its permanent
position, clipped in and sagged. Electrical load from
another phase was transferred to this new conductor
and the old conductor was de-energized. The old
conductor was then reconductored. This was repeated,
until all the conductors were replaced, without any
interruption to the electrical supply. This was performed
section by section, on average 20 to 30 miles. This plan
allowed for the reuse of existing structures, therefore
minimizing the impact on landowners and negating any
of the timely permits associated with land acquisition and
construction.
Other realized cost savings during construction were the
energized crews’ ability to perform out of the scope
upgrades and maintenance, such as replacing damaged
V-string insulators and the upgrade of existing shield
wire with OPGW fiber. This type of work often requires
months of planning to get the necessary outages, which
can be cancelled at any time. This is one of the factors
that led ERCOT to be able to take back every scheduled
outage because construction and repairs were made
while the line remained energized. The state-of-the-art
and proprietary technology used on the energized
reconductoring, led to ahead of schedule completion of
the project, despite record-setting inclement weather.
Among the unique aspects of these one-of-a-kind work
procedures was the ability to adapt to job irregularities.
A necessary adaptation that occurred early in the project
was related to the bundled conductor, which sat in a
vertical configuration rather than the tradition horizontal
configuration. To most efficiently tackle this issue the
team needed to tailor both the equipment and the
procedures to accommodate the vertical configuration.
This first test proved to be a calling card for the entire
project as procedures were continually updated to make
the project safer and more efficient.
While numerous factors played an important part in the
success of this project, from state of the art equipment,
to extensive training, none were as important as the
detailed work procedures. The work procedures,
developed by the technical advisors, were developed
specifically for each part of this project. Making the
scope even more unique, was the fact that it was under
continuous evolution. Methods of success and failure
from the field, were used to further refine these
procedures. As work procedures were refined and the
crews became experienced in these procedures and
work methods the result was a gradual to substantial
improvement in productivity, allowing the project to be
finished eight months ahead of schedule and millions
of dollars under budget.
The suit worn by barehand linemen consists of a
hooded jacket, bib style pants, socks, and gloves.
The suit is made of 75% Nomex and 25%
stainless-steel fibers. The Nomex content of the
suit qualifies as the outer fire-retardant clothing
layer. The steel mesh woven into the suit serves as
a Faraday Cage, shielding the lineman from the
electric field.
While wearing the barehand suit, the electric
charge flows around the outside of the suit (the
charged cage) and not through the lineman's body
(the interior of the charged cage). With the metallic
mesh clothing bonded to the conductor, the
lineman can work inside the electrical field.
BAREHAND SUIT
8
AEP’s Energized Reconductior Project for the Lower Rio Grande Valley
Edison Award Entry I April 2016
SUBSTATION CHALLENGES
As construction continued on the two 345 kV lines, the AEP project management team turned their attention to the
five substations that tied into the lines. With the upgraded reconductor nearly doubling the electric capacity of the two
345 kV lines, AEP needed to upgrade the substations as they had not been built for the higher capacity. AEP’s
concerns centered on the continuous current, as well as the fault current. This meant that additional bus supports
needed to be added and everything that carried current had to be upgraded and replaced. Unlike the transmission
line, an upgrade to the substations would require outage clearances from ERCOT to take the power out while
working in the substation. Raising the level of complexity was the issue that for every outage AEP took on an already
strained system, they would also be competing with other utilities and generators for these outage clearances.
The traditional timeframe to upgrade a substation is six to eight months, however, with the new conductor being
installed every day and a lack of outage clearances available from ERCOT, AEP was given a shortened window to
complete each substation. In addition to the shortened construction timeline, the vulnerability of the system dictated
that ERCOT attach a restoration time on every outage clearance given. The mandated restoration time was normally
shorter than the ERCOT approved outage clearance time and dictated how AEP could do the work on each
substation during the outage clearance. This meant that instead of a complete demolition of the substation, AEP had
to approach each substation work plan in a unique way, so that they could return the clearance if needed. In order to
return the clearance by the ERCOT mandated restoration time a substation had to be rebuilt and upgraded one piece
at a time. An example of this unique request is the construction of the control houses. As the breakers and
conductor were changed out in the substation, the control cables were moved to the new control house until the
original control house was empty and could be demolished. AEP, while working around the energized construction
portion of the project, was able to safely upgrade each of the five substations in the allotted timeframe, without
jeopardizing the grid and subsequently electric power to their customers in the LRGV.
COST SAVINGS ANALYSIS
The inability to get outage clearances and the lengthy process of acquiring right of way pushed AEP toward the
energized reconductor option. Another cost issue that is often overlooked in the overall construction budget is the
ability to source generation to supplement the transmission lines that have been taken out of service. In areas where
ample amounts of generation are not prevalent, less efficient generation sources must be used. This results in costly
expenditures to the utility and their customers. By working in an energized state, alternative generation sources were
not needed. Based on local generation costs, the combined savings for 2014 and 2015 was approximately
$43,377,129.
9
AEP’s Energized Reconductior Project for the Lower Rio Grande Valley
Edison Award Entry I April 2016
AEP Simulation Lab
The idea to reconductor the line in 20-25 mile segments, one
phase at a time was a deviation from the conventional method of
reconductoring all three phases at once, but necessary when
completing a project in an energized state, while using the
Linemaster Robotic Arm ™.
This unconventional way of reconductoring brought about
questions that had to be answered. For example, when do you
replace the relay settings for the reconductored line? Also, would
the inrush current trip the line if the single phase breakers were
utilized to move load on a phase in the 20-25 mile segment?
To answer these questions, simulations were run and studied in
AEP Transmission’s Gahanna, Ohio simulation lab. These unique
lab simulations led AEP to replace the relay settings before the
Pictured Yiyan “Spark” Xue, principal
engineer over RTDS testing in AEP’s
Gahanna, Ohio simulation lab.
line was reconductored. As well as determine that the relay settings would not trip the line during a single phase
breaker operation.
AEP’s simulation lab minimized the risk on the project while avoiding delays and costs associated with
conventional field test.
10
AEP’s Energized Reconductior Project for the Lower Rio Grande Valley
Edison Award Entry I April 2016
AEP completed the longest energized reconductor project eight months ahead of schedule and significantly under
budget. The upgrade to the 345 kV ACCC conductor will allow for future clean energy generation to power the Lower Rio
Grande Valley for the next several decades.
CONCLUSION
The Future of Transmission Construction
This project not only strengthened the transmission system in the Lower Rio Grande Valley, it demonstrated that
with collaboration and careful planning long distances can efficiently and safely be reconductored in an
energized state. In an outage-constrained industry with heavy workloads and condensed time frames, this
project demonstrates the industry has a viable option.
In South Texas with the completion of the 240 mile Energized Reconductor Project, AEP has ensured numerous
communities in the LRGV that their need for reliable power today, tomorrow and well into the future will be met.
Lights will stay on, homes will be cooled and heated, schools will stay in session and hospitals will continue to
save people. AEP has shown that with the use of innovative technology and the lessons learned from the
project they are prepared and more than ready to tackle all future issues in the LRGV.
During the course of the project AEP hosted nearly 20 utilities, including several international utilities, providing
field tours and detailed classroom analysis. Throughout every visit, senior management from AEP was onsite to
discuss and answer questions about project specifics. In doing so AEP ensured that the foundation built from
the world’s longest energized project will continue to benefit future utility customers around the globe.
11
AEP’s Energized Reconductior Project for the Lower Rio Grande Valley
Edison Award Entry I April 2016
• Voltages up to 345kV
• Supports up to
2,250lbs per phase
• Vertical and horizontal
applications
LINEMASTER ROBOTIC ARM ™
Quanta Energized Services’ Linemaster ™ Robotic Arm and Single Point Lifter create a safer and more efficient work
environment for powerline construction, maintenance or upgrades. The LineMaster Robotic Arms provide temporary
secure conductor support to existing conductors, while they remain in service.
SINGLE PICK THREE PHASE
THE PROCESS
• The LineMaster Robotic Arm ™ operates by hydraulic actuators and attaches to conventional crane or boom trucks.
• When moved into position it captures the conductors, and can be operated to provide safe working clearances.
• The conductors are secured in wire holders on station class all weather insulators
• .An aging or damaged structure is removed and new structure is put in its place.
• Electricity continues to flow and the LineMaster Robotic Arm ™ is moved back into position so the conductor can be
connected to the new structure.
• Voltages up to 765kV
• Supports up to
10,000lbs.
• Vertical and horizontal
applications

More Related Content

What's hot

Bob Bach: Energy Efficiency in the Ontario Building Code
Bob Bach: Energy Efficiency in the Ontario Building CodeBob Bach: Energy Efficiency in the Ontario Building Code
Bob Bach: Energy Efficiency in the Ontario Building CodeToronto 2030 District
 
Vanadium Redox Flow Battery
Vanadium Redox Flow Battery Vanadium Redox Flow Battery
Vanadium Redox Flow Battery Rajkumar Tondare
 
Power+Generation+Project+-+Melbourne
Power+Generation+Project+-+MelbournePower+Generation+Project+-+Melbourne
Power+Generation+Project+-+MelbourneJohn Rimac
 
A high density, high-efficiency, isolated on-board vehicle battery charger ut...
A high density, high-efficiency, isolated on-board vehicle battery charger ut...A high density, high-efficiency, isolated on-board vehicle battery charger ut...
A high density, high-efficiency, isolated on-board vehicle battery charger ut...EG TECHNOLOGIES
 
Integrated Renewable H2 Utility Systems
Integrated Renewable H2 Utility SystemsIntegrated Renewable H2 Utility Systems
Integrated Renewable H2 Utility SystemsGlenn Rambach
 
Clean Air Zones- big models for big questions
Clean Air Zones- big models for big questionsClean Air Zones- big models for big questions
Clean Air Zones- big models for big questionsScott Hamilton
 
Redox flow battery - Power Sector
Redox flow battery - Power SectorRedox flow battery - Power Sector
Redox flow battery - Power SectorIrish Pereira
 
Sabien M2G Client Endorsements & Case Studies
Sabien M2G Client Endorsements & Case StudiesSabien M2G Client Endorsements & Case Studies
Sabien M2G Client Endorsements & Case StudiesGSimmers
 
Edward tony ranson gcc 2016
Edward tony ranson gcc 2016Edward tony ranson gcc 2016
Edward tony ranson gcc 2016GWT
 
The Ins & Outs of Energy Efficiency in the Building Code - Bob Bach, P.Eng.
The Ins & Outs of Energy Efficiency in the Building Code - Bob Bach, P.Eng.The Ins & Outs of Energy Efficiency in the Building Code - Bob Bach, P.Eng.
The Ins & Outs of Energy Efficiency in the Building Code - Bob Bach, P.Eng.SBCBreakfastSessions
 
Larry Hebert Resume
Larry Hebert ResumeLarry Hebert Resume
Larry Hebert ResumeLarry Hebert
 
Advanced Energy Storage 10-2010
Advanced Energy Storage 10-2010Advanced Energy Storage 10-2010
Advanced Energy Storage 10-2010Larry Stapleton
 
Building Grid Resilience
Building Grid ResilienceBuilding Grid Resilience
Building Grid ResilienceAdvisian
 

What's hot (20)

Bob Bach: Energy Efficiency in the Ontario Building Code
Bob Bach: Energy Efficiency in the Ontario Building CodeBob Bach: Energy Efficiency in the Ontario Building Code
Bob Bach: Energy Efficiency in the Ontario Building Code
 
Vanadium Redox Flow Battery
Vanadium Redox Flow Battery Vanadium Redox Flow Battery
Vanadium Redox Flow Battery
 
Michael%20Weir-3
Michael%20Weir-3Michael%20Weir-3
Michael%20Weir-3
 
Power+Generation+Project+-+Melbourne
Power+Generation+Project+-+MelbournePower+Generation+Project+-+Melbourne
Power+Generation+Project+-+Melbourne
 
A high density, high-efficiency, isolated on-board vehicle battery charger ut...
A high density, high-efficiency, isolated on-board vehicle battery charger ut...A high density, high-efficiency, isolated on-board vehicle battery charger ut...
A high density, high-efficiency, isolated on-board vehicle battery charger ut...
 
Integrated Renewable H2 Utility Systems
Integrated Renewable H2 Utility SystemsIntegrated Renewable H2 Utility Systems
Integrated Renewable H2 Utility Systems
 
Clean Air Zones- big models for big questions
Clean Air Zones- big models for big questionsClean Air Zones- big models for big questions
Clean Air Zones- big models for big questions
 
Redox flow battery - Power Sector
Redox flow battery - Power SectorRedox flow battery - Power Sector
Redox flow battery - Power Sector
 
Sabien M2G Client Endorsements & Case Studies
Sabien M2G Client Endorsements & Case StudiesSabien M2G Client Endorsements & Case Studies
Sabien M2G Client Endorsements & Case Studies
 
Update on CCS Activities in Canada and Possible Topics for European Collabora...
Update on CCS Activities in Canada and Possible Topics for European Collabora...Update on CCS Activities in Canada and Possible Topics for European Collabora...
Update on CCS Activities in Canada and Possible Topics for European Collabora...
 
08 waldren sandia-epri ider planning case study_waldren 10 may 2016 - final
08 waldren sandia-epri ider planning case study_waldren 10 may 2016 - final08 waldren sandia-epri ider planning case study_waldren 10 may 2016 - final
08 waldren sandia-epri ider planning case study_waldren 10 may 2016 - final
 
Edward tony ranson gcc 2016
Edward tony ranson gcc 2016Edward tony ranson gcc 2016
Edward tony ranson gcc 2016
 
C.v. p maidens
C.v. p maidensC.v. p maidens
C.v. p maidens
 
The Ins & Outs of Energy Efficiency in the Building Code - Bob Bach, P.Eng.
The Ins & Outs of Energy Efficiency in the Building Code - Bob Bach, P.Eng.The Ins & Outs of Energy Efficiency in the Building Code - Bob Bach, P.Eng.
The Ins & Outs of Energy Efficiency in the Building Code - Bob Bach, P.Eng.
 
Larry Hebert Resume
Larry Hebert ResumeLarry Hebert Resume
Larry Hebert Resume
 
MGoutho_Res_0816
MGoutho_Res_0816MGoutho_Res_0816
MGoutho_Res_0816
 
Ballard Technology Solutions
Ballard Technology SolutionsBallard Technology Solutions
Ballard Technology Solutions
 
0415 RECV
0415 RECV0415 RECV
0415 RECV
 
Advanced Energy Storage 10-2010
Advanced Energy Storage 10-2010Advanced Energy Storage 10-2010
Advanced Energy Storage 10-2010
 
Building Grid Resilience
Building Grid ResilienceBuilding Grid Resilience
Building Grid Resilience
 

Viewers also liked

CTC Global ACCC conductor overview august 2016
CTC Global ACCC conductor overview august 2016CTC Global ACCC conductor overview august 2016
CTC Global ACCC conductor overview august 2016Dave Bryant
 
How ACCC Conductor can help meet the Clean Power Plan mandate
How ACCC Conductor can help meet the Clean Power Plan mandateHow ACCC Conductor can help meet the Clean Power Plan mandate
How ACCC Conductor can help meet the Clean Power Plan mandateDave Bryant
 
CTC Global ACCC conductor update June 2016
CTC Global ACCC conductor update June 2016CTC Global ACCC conductor update June 2016
CTC Global ACCC conductor update June 2016Dave Bryant
 
CTC Global ACCC Conductor efficiency presentation 2016
CTC Global ACCC Conductor efficiency presentation 2016CTC Global ACCC Conductor efficiency presentation 2016
CTC Global ACCC Conductor efficiency presentation 2016Dave Bryant
 
CTC Global ACCC conductor update July 2016
CTC Global ACCC conductor update July 2016CTC Global ACCC conductor update July 2016
CTC Global ACCC conductor update July 2016Dave Bryant
 
CTC Global ACCC conductor newsletter May 2016
CTC Global ACCC conductor newsletter May 2016CTC Global ACCC conductor newsletter May 2016
CTC Global ACCC conductor newsletter May 2016Dave Bryant
 
CTC Global ISO Certification
CTC Global ISO CertificationCTC Global ISO Certification
CTC Global ISO CertificationDave Bryant
 
Installing ACCC conductor in Congo Africa
Installing ACCC conductor in Congo AfricaInstalling ACCC conductor in Congo Africa
Installing ACCC conductor in Congo AfricaDave Bryant
 
CTC Global's ACCC conductor reduces CO2 emissions
CTC Global's ACCC conductor reduces CO2 emissionsCTC Global's ACCC conductor reduces CO2 emissions
CTC Global's ACCC conductor reduces CO2 emissionsDave Bryant
 
Installation of Advanced Composite Core Conductors in Indonesia
Installation of Advanced Composite Core Conductors in IndonesiaInstallation of Advanced Composite Core Conductors in Indonesia
Installation of Advanced Composite Core Conductors in IndonesiaDave Bryant
 
ACCC Engineering Manual
ACCC Engineering ManualACCC Engineering Manual
ACCC Engineering ManualDave Bryant
 
SCS Global Certification of CTC Global ACCC Conductor
SCS Global Certification of CTC Global ACCC ConductorSCS Global Certification of CTC Global ACCC Conductor
SCS Global Certification of CTC Global ACCC ConductorDave Bryant
 

Viewers also liked (12)

CTC Global ACCC conductor overview august 2016
CTC Global ACCC conductor overview august 2016CTC Global ACCC conductor overview august 2016
CTC Global ACCC conductor overview august 2016
 
How ACCC Conductor can help meet the Clean Power Plan mandate
How ACCC Conductor can help meet the Clean Power Plan mandateHow ACCC Conductor can help meet the Clean Power Plan mandate
How ACCC Conductor can help meet the Clean Power Plan mandate
 
CTC Global ACCC conductor update June 2016
CTC Global ACCC conductor update June 2016CTC Global ACCC conductor update June 2016
CTC Global ACCC conductor update June 2016
 
CTC Global ACCC Conductor efficiency presentation 2016
CTC Global ACCC Conductor efficiency presentation 2016CTC Global ACCC Conductor efficiency presentation 2016
CTC Global ACCC Conductor efficiency presentation 2016
 
CTC Global ACCC conductor update July 2016
CTC Global ACCC conductor update July 2016CTC Global ACCC conductor update July 2016
CTC Global ACCC conductor update July 2016
 
CTC Global ACCC conductor newsletter May 2016
CTC Global ACCC conductor newsletter May 2016CTC Global ACCC conductor newsletter May 2016
CTC Global ACCC conductor newsletter May 2016
 
CTC Global ISO Certification
CTC Global ISO CertificationCTC Global ISO Certification
CTC Global ISO Certification
 
Installing ACCC conductor in Congo Africa
Installing ACCC conductor in Congo AfricaInstalling ACCC conductor in Congo Africa
Installing ACCC conductor in Congo Africa
 
CTC Global's ACCC conductor reduces CO2 emissions
CTC Global's ACCC conductor reduces CO2 emissionsCTC Global's ACCC conductor reduces CO2 emissions
CTC Global's ACCC conductor reduces CO2 emissions
 
Installation of Advanced Composite Core Conductors in Indonesia
Installation of Advanced Composite Core Conductors in IndonesiaInstallation of Advanced Composite Core Conductors in Indonesia
Installation of Advanced Composite Core Conductors in Indonesia
 
ACCC Engineering Manual
ACCC Engineering ManualACCC Engineering Manual
ACCC Engineering Manual
 
SCS Global Certification of CTC Global ACCC Conductor
SCS Global Certification of CTC Global ACCC ConductorSCS Global Certification of CTC Global ACCC Conductor
SCS Global Certification of CTC Global ACCC Conductor
 

Similar to AEP texas project edison award winner

Res Sher Chauhan general est Nov 2016
Res  Sher Chauhan general est Nov 2016Res  Sher Chauhan general est Nov 2016
Res Sher Chauhan general est Nov 2016Sher Chuhan
 
Reasons utilities are switching to high-performance overhead conductors
Reasons utilities are switching to high-performance overhead conductorsReasons utilities are switching to high-performance overhead conductors
Reasons utilities are switching to high-performance overhead conductorsctcglobal
 
Ultra High Voltage AC Transmission UHVAC
Ultra High Voltage AC Transmission UHVACUltra High Voltage AC Transmission UHVAC
Ultra High Voltage AC Transmission UHVACAravind Panasa
 
MEC - COMPANY PROFILE
MEC - COMPANY PROFILEMEC - COMPANY PROFILE
MEC - COMPANY PROFILECarlos Camino
 
Renewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectRenewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectPartha Deb
 
Mike Koons - Resume_Linkedin 2016_
Mike Koons - Resume_Linkedin 2016_Mike Koons - Resume_Linkedin 2016_
Mike Koons - Resume_Linkedin 2016_Mike Koons
 
Earth_Renewed_CNRGH2.1
Earth_Renewed_CNRGH2.1Earth_Renewed_CNRGH2.1
Earth_Renewed_CNRGH2.1dCORE
 
Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015Dennis Kehoe
 
Learn about CTC Global and ACCC Conductor
Learn about CTC Global and ACCC ConductorLearn about CTC Global and ACCC Conductor
Learn about CTC Global and ACCC ConductorDave Bryant
 
Reasons why utilities are switching to high performance overhead conductors
Reasons why utilities are switching to high performance overhead conductorsReasons why utilities are switching to high performance overhead conductors
Reasons why utilities are switching to high performance overhead conductorsctcglobal
 
CV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASATCV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASATRommel Siasat
 
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...AMI GE International
 
KinetIQ Solutions Capability Statement
KinetIQ Solutions Capability StatementKinetIQ Solutions Capability Statement
KinetIQ Solutions Capability StatementRay Salmons
 
Long-Duration Energy Storage and PV: Renewable Energy’s BFFs
Long-Duration Energy Storage and PV: Renewable Energy’s BFFsLong-Duration Energy Storage and PV: Renewable Energy’s BFFs
Long-Duration Energy Storage and PV: Renewable Energy’s BFFsCraig Horne
 

Similar to AEP texas project edison award winner (20)

Res Sher Chauhan general est Nov 2016
Res  Sher Chauhan general est Nov 2016Res  Sher Chauhan general est Nov 2016
Res Sher Chauhan general est Nov 2016
 
Reasons utilities are switching to high-performance overhead conductors
Reasons utilities are switching to high-performance overhead conductorsReasons utilities are switching to high-performance overhead conductors
Reasons utilities are switching to high-performance overhead conductors
 
Ultra High Voltage AC Transmission UHVAC
Ultra High Voltage AC Transmission UHVACUltra High Voltage AC Transmission UHVAC
Ultra High Voltage AC Transmission UHVAC
 
MEC - COMPANY PROFILE
MEC - COMPANY PROFILEMEC - COMPANY PROFILE
MEC - COMPANY PROFILE
 
Engr. Asim Mahmood CV
Engr. Asim Mahmood CVEngr. Asim Mahmood CV
Engr. Asim Mahmood CV
 
Wind Power EPCM
Wind Power EPCMWind Power EPCM
Wind Power EPCM
 
Renewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot ProjectRenewable Integration & Energy Strage Smart Grid Pilot Project
Renewable Integration & Energy Strage Smart Grid Pilot Project
 
Mike Koons - Resume_Linkedin 2016_
Mike Koons - Resume_Linkedin 2016_Mike Koons - Resume_Linkedin 2016_
Mike Koons - Resume_Linkedin 2016_
 
Earth_Renewed_CNRGH2.1
Earth_Renewed_CNRGH2.1Earth_Renewed_CNRGH2.1
Earth_Renewed_CNRGH2.1
 
OES PPT
OES PPTOES PPT
OES PPT
 
Cv of mr.Jefferson Tomas Tulabot
Cv of mr.Jefferson Tomas TulabotCv of mr.Jefferson Tomas Tulabot
Cv of mr.Jefferson Tomas Tulabot
 
Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015Resume Dennis Kehoe 2015
Resume Dennis Kehoe 2015
 
Satham Mohamed.A-CV..
Satham Mohamed.A-CV..Satham Mohamed.A-CV..
Satham Mohamed.A-CV..
 
Learn about CTC Global and ACCC Conductor
Learn about CTC Global and ACCC ConductorLearn about CTC Global and ACCC Conductor
Learn about CTC Global and ACCC Conductor
 
Reasons why utilities are switching to high performance overhead conductors
Reasons why utilities are switching to high performance overhead conductorsReasons why utilities are switching to high performance overhead conductors
Reasons why utilities are switching to high performance overhead conductors
 
Eskom - Grid Connectivity
Eskom - Grid ConnectivityEskom - Grid Connectivity
Eskom - Grid Connectivity
 
CV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASATCV-Engineering Manager-Lead Electrical Eng_RFSIASAT
CV-Engineering Manager-Lead Electrical Eng_RFSIASAT
 
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...Results of DigitArc Electrode Regulator and SmartArc power input optimization...
Results of DigitArc Electrode Regulator and SmartArc power input optimization...
 
KinetIQ Solutions Capability Statement
KinetIQ Solutions Capability StatementKinetIQ Solutions Capability Statement
KinetIQ Solutions Capability Statement
 
Long-Duration Energy Storage and PV: Renewable Energy’s BFFs
Long-Duration Energy Storage and PV: Renewable Energy’s BFFsLong-Duration Energy Storage and PV: Renewable Energy’s BFFs
Long-Duration Energy Storage and PV: Renewable Energy’s BFFs
 

Recently uploaded

(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...ranjana rawat
 
Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)RaviPrajapat11
 
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130Suhani Kapoor
 
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts ServicesBOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Servicesdollysharma2066
 
Call Girls Service Nagpur Aditi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Aditi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Aditi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Aditi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
VIP Call Girls Service Bandlaguda Hyderabad Call +91-8250192130
VIP Call Girls Service Bandlaguda Hyderabad Call +91-8250192130VIP Call Girls Service Bandlaguda Hyderabad Call +91-8250192130
VIP Call Girls Service Bandlaguda Hyderabad Call +91-8250192130Suhani Kapoor
 
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...ranjana rawat
 
Spiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsSpiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsprasan26
 
VIP Call Girl Gorakhpur Aashi 8250192130 Independent Escort Service Gorakhpur
VIP Call Girl Gorakhpur Aashi 8250192130 Independent Escort Service GorakhpurVIP Call Girl Gorakhpur Aashi 8250192130 Independent Escort Service Gorakhpur
VIP Call Girl Gorakhpur Aashi 8250192130 Independent Escort Service GorakhpurSuhani Kapoor
 
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...Delhi Escorts
 
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...Suhani Kapoor
 
Horizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben AbrahamHorizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben Abrahamssuserbb03ff
 
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Yamuna Vihar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(AISHA) Wagholi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
(PARI) Viman Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune ...
 
Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)Environmental Toxicology (environmental biology)
Environmental Toxicology (environmental biology)
 
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
VIP Call Girls Service Chaitanyapuri Hyderabad Call +91-8250192130
 
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts ServicesBOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
BOOK Call Girls in (Dwarka) CALL | 8377087607 Delhi Escorts Services
 
Call Girls Service Nagpur Aditi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Aditi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Aditi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Aditi Call 7001035870 Meet With Nagpur Escorts
 
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
(DIYA) Call Girls Sinhagad Road ( 7001035870 ) HI-Fi Pune Escorts Service
 
VIP Call Girls Service Bandlaguda Hyderabad Call +91-8250192130
VIP Call Girls Service Bandlaguda Hyderabad Call +91-8250192130VIP Call Girls Service Bandlaguda Hyderabad Call +91-8250192130
VIP Call Girls Service Bandlaguda Hyderabad Call +91-8250192130
 
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service
(ANIKA) Call Girls Wagholi ( 7001035870 ) HI-Fi Pune Escorts Service
 
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Shirwal 8250192130 Will You Miss This Cha...
 
Spiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnidsSpiders by Slidesgo - an introduction to arachnids
Spiders by Slidesgo - an introduction to arachnids
 
Call Girls In Pratap Nagar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Pratap Nagar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCeCall Girls In Pratap Nagar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
Call Girls In Pratap Nagar꧁❤ 🔝 9953056974🔝❤꧂ Escort ServiCe
 
Call Girls In { Delhi } South Extension Whatsup 9873940964 Enjoy Unlimited Pl...
Call Girls In { Delhi } South Extension Whatsup 9873940964 Enjoy Unlimited Pl...Call Girls In { Delhi } South Extension Whatsup 9873940964 Enjoy Unlimited Pl...
Call Girls In { Delhi } South Extension Whatsup 9873940964 Enjoy Unlimited Pl...
 
VIP Call Girl Gorakhpur Aashi 8250192130 Independent Escort Service Gorakhpur
VIP Call Girl Gorakhpur Aashi 8250192130 Independent Escort Service GorakhpurVIP Call Girl Gorakhpur Aashi 8250192130 Independent Escort Service Gorakhpur
VIP Call Girl Gorakhpur Aashi 8250192130 Independent Escort Service Gorakhpur
 
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
(ANAYA) Call Girls Hadapsar ( 7001035870 ) HI-Fi Pune Escorts Service
 
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...9873940964 High Profile  Call Girls  Delhi |Defence Colony ( MAYA CHOPRA ) DE...
9873940964 High Profile Call Girls Delhi |Defence Colony ( MAYA CHOPRA ) DE...
 
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
VIP Call Girls Saharanpur Aaradhya 8250192130 Independent Escort Service Saha...
 
Horizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben AbrahamHorizon Net Zero Dawn – keynote slides by Ben Abraham
Horizon Net Zero Dawn – keynote slides by Ben Abraham
 
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(RIYA) Kalyani Nagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

AEP texas project edison award winner

  • 1. 1 AEP’s Energized Reconductior Project for the Lower Rio Grande Valley Edison Award Entry I April 2016
  • 2. 2 AEP’s Energized Reconductior Project for the Lower Rio Grande Valley Edison Award Entry I April 2016 OVERVIEW The Energized Reconductor Project of the Lower Rio Grande Valley (LRGV) is a landmark accomplishment for American Electric Power (AEP) and the utility industry. The 240 mile project capitalized on multiple innovative technologies from across the industry, allowing AEP to provide an immediate solution to the problem of reliable electricity while addressing future load growth. The LRGV is served by two 345-kV transmission lines that originate from Corpus Christi, 120 miles to the north, and account for the bulk of the electricity carried into the LRGV. The lines are in a vulnerable position due to the LRGV’s dependency on them to supply the majority of the power to South Texas, as well as their proximity to the Texas Gulf Coast exposing them to corrosive salt spray and making them susceptible to storm outages. In February 2011 South Texas experienced record winter temperatures which dropped as low as 20 degrees Fahrenheit. For a region accustomed to average February temperatures in the mid 60’s, these temperatures were crippling. Panicked residents flooded the stores in search of portable heaters. This immediate increase in demand for electricity coupled with downed generation due to prescheduled maintenance resulted in rolling blackouts throughout the region due to the limitations of the transmission system.
  • 3. 3 AEP’s Energized Reconductior Project for the Lower Rio Grande Valley Edison Award Entry I April 2016 CHALLENGES Summer highs in the LRGV routinely hit triple digits. This, coupled with a 30% population growth from 2000-2010, resulted in AEP’s peak electric demand increasing from 1000 MW in the summer of 2000 to a summer record peak demand of 2220 MW in 2010. While an increase in load over a decade is to be expected, the 514 MW jump from the previous summer during the 2011 winter storm (2220 MW to 2734 MW) was outside all modeled projections. Furthermore, due to continued growth, the projected 2016 summer peak load is expected to reach 2800 MW with a forecasted summer 2020 peak load of over 3000 MW. An immediate plan was needed to supply relief to the circuits most affected by the short term seasonal spikes. However, this plan also had to offer a long term solution to address the load increases for 2016, 2020 and beyond. AEP, as well as the Electric Reliability Council of Texas (ERCOT), needed a solution that could meet the pressing demands and provide reliability while safely maintaining an aggressive schedule. ERCOT was presented with a number of traditional cold construction options for increasing capacity on these circuits, running the gamut of temporary upgrades to complete overhauls. As AEP looked into permitting, right of way (ROW) acquisition and various customer disruptions, it became apparent that these variables had a very real chance of interrupting their customer’s service or adding unforeseen costs to the project. However, the biggest area of concern for AEP was that ERCOT could only grant outages clearances in the spring and summer months, if at all, and the lines would be required to be restored to full service whenever system anomalies warranted. AEP chose the energized solution because it allowed them to use the existing right of ways and structures, limiting property disruptions and reducing the overall cost to their customer.
  • 4. 4 AEP’s Energized Reconductior Project for the Lower Rio Grande Valley Edison Award Entry I April 2016 AN INNOVATIVE SOLUTION Taking the list of challenges into account, it was apparent to AEP that a traditional construction solution would only add additional delays to an already time sensitive project and therefore could not be counted on as a viable option to meet the 2016 completion schedule. AEP approached Quanta Energized Services, an entity of Quanta Services, to discuss their live-line planning and construction expertise. While smaller energized projects had been successfully completed in the past, an energized reconductor project of this size and length (240 mi.) had never been attempted. To ensure that construction of the project was completed by the mandated 2016 in service date, AEP concluded that no new structures or right-of-away could be purchased. Under this plan a lightweight, high capacity conductor was needed and cable manufacturer CTC Global, with their revolutionary ACCC Composite Core Conductor, were brought onboard the project team. AEP, confident that the issues associated with traditional transmission line construction had been averted. A joint work plan with Quanta Energized Services technical advisors to reconductor the entire 240 miles while keeping the lines in-service and energized. In early spring 2011, AEP’s plan to perform the energized reconductor of the existing 345-kV transmission lines was approved by the regional planning group at ERCOT. Above: Quanta Energized Services Linemaster Robotic Arm chosen for AEP LRGV Reconductor. Below: Aluminum Conductor Composite Core (ACCC) a lighter alternative to conventional conductor, reduces sag while doubling the capacity. This project was the longest installation of advanced conductor in North America.
  • 5. 5 AEP’s Energized Reconductior Project for the Lower Rio Grande Valley Edison Award Entry I April 2016 STATE-OF-THE-ART TECHNOLOGIES Through the innovative partnerships with Quanta and CTC Global, AEP was able to capitalize on several 21st century technologies that not only accelerated the work schedule to ensure that the required in service date for the upgraded line was achieved but also benefit the environment and increase the level of safety for all involved. The two technological advances that made this project possible were: Aluminum Conductor Composite Core (ACCC) • The use of Aluminum Conductor Composite Core (ACCC) to replace the existing conductor. While the same diameter as the original conductor, ACCC, due to the reduced size composite core, is comprised of 28% more aluminum. • The extra aluminum and higher temperature rating allows for twice the capacity of conventional conductor. The composite core reduces thermal sag. Replacing the old conductor with one of the same diameter and weight but more capacity meant that AEP could replace the old conductor without widening clearances or causing tower modifications and rebuilds. • Due to the added aluminum, line losses were reduced by up to 40%, equaling a savings of over $30 million dollars in the first year alone. • The lower emission from the CO2 reductions in the first year is equivalent to removing 34,000 cars from the road. • Also of great importance, due to the location of the job, the ACCC is more resistant to corrosion and has the ability to handle future increases in load. Energized Barehand Work Methods & Linemaster Robotic Arm • The Energized Barehand work methods and proprietary LineMaster Robotic Arm made it possible for all 240 miles of 345kV conductor to be removed and replaced without interrupting the flow of electricity. • Attached to a boom on a ground-based vehicle, the LineMaster Robotic Arm safely moves and securely holds energized power lines while the conductors, insulators and structures are maintained, replaced or rebuilt. • The LineMaster Robotic Arm allowed the construction team to safely work without any outages on the project. • Its all weather capabilities allowed for it to remain in place during poor weather while the crew found shelter and then continue work once the weather had passed. • In addition to the robotic arm, barehand work methods and proprietary energized reconductoring procedures were developed by a team which collectively has more than 400 years of energized work experience, starting with the first-ever energized reconductor project in 1990. • These methods, tools and equipment have been and continue to be tested and improved in the field and at the world renown STRI lab in Sweden.
  • 6. 6 AEP’s Energized Reconductior Project for the Lower Rio Grande Valley Edison Award Entry I April 2016 PROJECT EXECUTION Once AEP identified the technology needed to complete this project and received approval from ERCOT to proceed, they went about coordinating the various complexities and components related to a project of this size. Constructing the project safely while not sacrificing the reliable power AEP’s customers expect on a daily basis were key drivers. Due to the vulnerability of the system, the key areas that needed to be upgraded were identified and prioritized. The difficulty of this task was multiplied by the fact that a segment of conductor needing to be upgraded often times was not connected to a substation that needed to be upgraded first. AEP closely managed all of these variables to ensure that there were no delays, work stoppages, or power outages. A year before the first lineman hit the right-of-way, AEP and the Quanta Energized Services technical advisors went about developing detailed, project- specific work procedures with calculated man-hours, sequencing, schedules and anticipated resources. The project called for an aggressive schedule to ensure that the line would be upgraded by the required date. The project was divided into five segments between the substations. Doing so resulted in several strategic, as well as, financial benefits: • It reduced the risk on the entire system serving the LRGV; • It prioritized the line sections between the substations, so that the completed areas could immediately reap the benefits of the system upgrade; • It created five smaller projects, which increased the efficiency of scheduling materials, equipment and crews, as well as minimizing the project costs. This is a temporary D Phase structure that has been installed inside of a three pole angle, allowing the outside phase to be transferred. This creates an open position on the existing pole to pull the new wire in. When the new wire is in, loads are transferred to deengerize another phase and pull another wire. An energized reconductor of this size required careful planning. Work procedures for each task had to be developed. A group of technical advisors collaborated together to produce these procedures. As the project progressed, lessons were learned and these procedures were further refined and revised. The barehand work method was instrumental to the work that was performed on the energized conductors. When working barehand, the lineman wear conductive suits and are bonded to the conductor, putting them at the same potential as the energized conductor allowing them to physically touch and work on the energized conductor and equipment. To support conductors while unclipping or clipping, the LineMaster Single Point Lifter robotic arm was used. This tool provided safe, secure and controlled support of the energized conductors. In order to replace conductors in an energized state, a temporary support for a phase conductor needed to be established. This was done by installing temporary structures along the edge of the right of way next to the existing line. Since the temporary structures were installed within the ROW, no additional land or the timely permits associated with land acquisition were required.
  • 7. 7 AEP’s Energized Reconductior Project for the Lower Rio Grande Valley Edison Award Entry I April 2016 The new conductor was then installed in its permanent position, clipped in and sagged. Electrical load from another phase was transferred to this new conductor and the old conductor was de-energized. The old conductor was then reconductored. This was repeated, until all the conductors were replaced, without any interruption to the electrical supply. This was performed section by section, on average 20 to 30 miles. This plan allowed for the reuse of existing structures, therefore minimizing the impact on landowners and negating any of the timely permits associated with land acquisition and construction. Other realized cost savings during construction were the energized crews’ ability to perform out of the scope upgrades and maintenance, such as replacing damaged V-string insulators and the upgrade of existing shield wire with OPGW fiber. This type of work often requires months of planning to get the necessary outages, which can be cancelled at any time. This is one of the factors that led ERCOT to be able to take back every scheduled outage because construction and repairs were made while the line remained energized. The state-of-the-art and proprietary technology used on the energized reconductoring, led to ahead of schedule completion of the project, despite record-setting inclement weather. Among the unique aspects of these one-of-a-kind work procedures was the ability to adapt to job irregularities. A necessary adaptation that occurred early in the project was related to the bundled conductor, which sat in a vertical configuration rather than the tradition horizontal configuration. To most efficiently tackle this issue the team needed to tailor both the equipment and the procedures to accommodate the vertical configuration. This first test proved to be a calling card for the entire project as procedures were continually updated to make the project safer and more efficient. While numerous factors played an important part in the success of this project, from state of the art equipment, to extensive training, none were as important as the detailed work procedures. The work procedures, developed by the technical advisors, were developed specifically for each part of this project. Making the scope even more unique, was the fact that it was under continuous evolution. Methods of success and failure from the field, were used to further refine these procedures. As work procedures were refined and the crews became experienced in these procedures and work methods the result was a gradual to substantial improvement in productivity, allowing the project to be finished eight months ahead of schedule and millions of dollars under budget. The suit worn by barehand linemen consists of a hooded jacket, bib style pants, socks, and gloves. The suit is made of 75% Nomex and 25% stainless-steel fibers. The Nomex content of the suit qualifies as the outer fire-retardant clothing layer. The steel mesh woven into the suit serves as a Faraday Cage, shielding the lineman from the electric field. While wearing the barehand suit, the electric charge flows around the outside of the suit (the charged cage) and not through the lineman's body (the interior of the charged cage). With the metallic mesh clothing bonded to the conductor, the lineman can work inside the electrical field. BAREHAND SUIT
  • 8. 8 AEP’s Energized Reconductior Project for the Lower Rio Grande Valley Edison Award Entry I April 2016 SUBSTATION CHALLENGES As construction continued on the two 345 kV lines, the AEP project management team turned their attention to the five substations that tied into the lines. With the upgraded reconductor nearly doubling the electric capacity of the two 345 kV lines, AEP needed to upgrade the substations as they had not been built for the higher capacity. AEP’s concerns centered on the continuous current, as well as the fault current. This meant that additional bus supports needed to be added and everything that carried current had to be upgraded and replaced. Unlike the transmission line, an upgrade to the substations would require outage clearances from ERCOT to take the power out while working in the substation. Raising the level of complexity was the issue that for every outage AEP took on an already strained system, they would also be competing with other utilities and generators for these outage clearances. The traditional timeframe to upgrade a substation is six to eight months, however, with the new conductor being installed every day and a lack of outage clearances available from ERCOT, AEP was given a shortened window to complete each substation. In addition to the shortened construction timeline, the vulnerability of the system dictated that ERCOT attach a restoration time on every outage clearance given. The mandated restoration time was normally shorter than the ERCOT approved outage clearance time and dictated how AEP could do the work on each substation during the outage clearance. This meant that instead of a complete demolition of the substation, AEP had to approach each substation work plan in a unique way, so that they could return the clearance if needed. In order to return the clearance by the ERCOT mandated restoration time a substation had to be rebuilt and upgraded one piece at a time. An example of this unique request is the construction of the control houses. As the breakers and conductor were changed out in the substation, the control cables were moved to the new control house until the original control house was empty and could be demolished. AEP, while working around the energized construction portion of the project, was able to safely upgrade each of the five substations in the allotted timeframe, without jeopardizing the grid and subsequently electric power to their customers in the LRGV. COST SAVINGS ANALYSIS The inability to get outage clearances and the lengthy process of acquiring right of way pushed AEP toward the energized reconductor option. Another cost issue that is often overlooked in the overall construction budget is the ability to source generation to supplement the transmission lines that have been taken out of service. In areas where ample amounts of generation are not prevalent, less efficient generation sources must be used. This results in costly expenditures to the utility and their customers. By working in an energized state, alternative generation sources were not needed. Based on local generation costs, the combined savings for 2014 and 2015 was approximately $43,377,129.
  • 9. 9 AEP’s Energized Reconductior Project for the Lower Rio Grande Valley Edison Award Entry I April 2016 AEP Simulation Lab The idea to reconductor the line in 20-25 mile segments, one phase at a time was a deviation from the conventional method of reconductoring all three phases at once, but necessary when completing a project in an energized state, while using the Linemaster Robotic Arm ™. This unconventional way of reconductoring brought about questions that had to be answered. For example, when do you replace the relay settings for the reconductored line? Also, would the inrush current trip the line if the single phase breakers were utilized to move load on a phase in the 20-25 mile segment? To answer these questions, simulations were run and studied in AEP Transmission’s Gahanna, Ohio simulation lab. These unique lab simulations led AEP to replace the relay settings before the Pictured Yiyan “Spark” Xue, principal engineer over RTDS testing in AEP’s Gahanna, Ohio simulation lab. line was reconductored. As well as determine that the relay settings would not trip the line during a single phase breaker operation. AEP’s simulation lab minimized the risk on the project while avoiding delays and costs associated with conventional field test.
  • 10. 10 AEP’s Energized Reconductior Project for the Lower Rio Grande Valley Edison Award Entry I April 2016 AEP completed the longest energized reconductor project eight months ahead of schedule and significantly under budget. The upgrade to the 345 kV ACCC conductor will allow for future clean energy generation to power the Lower Rio Grande Valley for the next several decades. CONCLUSION The Future of Transmission Construction This project not only strengthened the transmission system in the Lower Rio Grande Valley, it demonstrated that with collaboration and careful planning long distances can efficiently and safely be reconductored in an energized state. In an outage-constrained industry with heavy workloads and condensed time frames, this project demonstrates the industry has a viable option. In South Texas with the completion of the 240 mile Energized Reconductor Project, AEP has ensured numerous communities in the LRGV that their need for reliable power today, tomorrow and well into the future will be met. Lights will stay on, homes will be cooled and heated, schools will stay in session and hospitals will continue to save people. AEP has shown that with the use of innovative technology and the lessons learned from the project they are prepared and more than ready to tackle all future issues in the LRGV. During the course of the project AEP hosted nearly 20 utilities, including several international utilities, providing field tours and detailed classroom analysis. Throughout every visit, senior management from AEP was onsite to discuss and answer questions about project specifics. In doing so AEP ensured that the foundation built from the world’s longest energized project will continue to benefit future utility customers around the globe.
  • 11. 11 AEP’s Energized Reconductior Project for the Lower Rio Grande Valley Edison Award Entry I April 2016 • Voltages up to 345kV • Supports up to 2,250lbs per phase • Vertical and horizontal applications LINEMASTER ROBOTIC ARM ™ Quanta Energized Services’ Linemaster ™ Robotic Arm and Single Point Lifter create a safer and more efficient work environment for powerline construction, maintenance or upgrades. The LineMaster Robotic Arms provide temporary secure conductor support to existing conductors, while they remain in service. SINGLE PICK THREE PHASE THE PROCESS • The LineMaster Robotic Arm ™ operates by hydraulic actuators and attaches to conventional crane or boom trucks. • When moved into position it captures the conductors, and can be operated to provide safe working clearances. • The conductors are secured in wire holders on station class all weather insulators • .An aging or damaged structure is removed and new structure is put in its place. • Electricity continues to flow and the LineMaster Robotic Arm ™ is moved back into position so the conductor can be connected to the new structure. • Voltages up to 765kV • Supports up to 10,000lbs. • Vertical and horizontal applications