SlideShare a Scribd company logo
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
Innovative Ratemaking –
Multiyear Rate Plans
February 2014
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
This document:
◼ Discusses the current business and regulatory environment that is resulting in the increased use of innovative ratemaking techniques,
including the consideration by some utilities and jurisdictions of a multiyear rate plan (MYRP) filing
◼ Provides an overview of the different MYRP approaches being utilized, including case studies in selected states and key takeaways
from each approach
◼ Summarizes future trends regarding the use of MYRP filings
Outline
◼ Current Environment
◼ Overview of Multiyear Rate Plans
◼ Case Studies
◼ Issues for Utilities Considering MYRPs
◼ Conclusions
Introduction
1
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
The current business environment is creating challenges for utilities
◼ Electric utility costs are increasing more rapidly than retail sales
 Utilities are actively modernizing and enhancing their delivery infrastructure
 Sales growth, which enabled utilities to finance new investments in the past, has not bounced back from pre-recession lows, and
in some areas is declining
Current Environment
Sources: SNL Financial; U.S. Energy Information Administration
$0
$40
$80
$120
$160
$200
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
TotalExpenditures($Billions)
Total Capital Expenditures 2003–2012
3,250,000
3,500,000
3,750,000
4,000,000
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
GigawattHours
Total Retail Sales 2003–2012
2
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
Traditional regulatory mechanisms are also impacting financial performance
◼ Regulatory lag makes timely cost recovery difficult
◼ Consistent “under-earning” impacts utility credit ratings, increases cost of capital, and may discourage needed investment
Utilities have responded by filing rate cases more frequently, which leads to additional challenges
◼ Requires significant resources that could otherwise be used to run the business
◼ Contributes to increased uncertainty of revenues and ROE and puts upward pressure on financing costs
◼ Creates an additional burden and resource requirements for regulators and interveners
Current Environment (Cont’d)
8%
9%
10%
11%
12%
13%
14%
15%
0% 20% 40% 60% 80% 100% 120% 140% 160% 180%
AuthorizedROE
Earned ROE as a % of Authorized ROE
Earned vs. Authorized ROE for Electric Utilities
Electric utilities are
struggling to earn
their authorized
return
Median = 10.3%
Median = 86.6%
Sources: SNL Financial; Regulatory Research Associates
0
10
20
30
40
50
60
70
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012
Number of Rate Cases Approved 2003-2012
3
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
In light of the challenges associated with traditional regulatory approaches, some utilities and public utility commissions are
experimenting with alternative approaches
◼ Various methods have been introduced across many states including:
 Cost trackers
 Inclusion of construction work in progress (CWIP) in the rate base
 Revenue decoupling
 Forward test years
 Formula rates
 MYRPs
Current Environment (Cont’d)
MYRPs represent one alternative regulatory approach to addressing the limitations of traditional regulatory mechanisms
in the current business environment.
4
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
Characteristics
◼ Originally utilized in the railroad, telecommunications, and oil pipeline industries
◼ Typically designed for a three- to five-year period
◼ Attrition relief mechanisms (ARMs) define annual rate escalations
◼ ARMs are usually capped either in terms of rates or total revenue
◼ Typical ARM designs include:
 Stairsteps – predetermined increases in rates or revenues based on cost growth forecasts
 Indexing – variable increases tied to an index like the CPI inflation rate
 Hybrids – indexing for O&M and stairsteps for CapEx
◼ Additional provisions sometimes included in MYRP structure include:
 Cost trackers
 Earnings sharing mechanisms to distribute excess earnings between utility and customers (when allowed ROE is exceeded)
 “Off-ramps” to allow for plan suspension in the event of unusually high or low earnings
Benefits
◼ Produces more predictable revenue stream and certainty for utility to make investments (reduces cost of capital)
◼ Reduces regulatory costs
◼ Incents utility to manage costs
◼ Enables utility to allocate resources to running the business rather than rate case administration
Overview
5
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
◼ 17 states have implemented MYRPs in
one form or another
◼ California and the states in the
Northeast have the most experience
with MYRPs
◼ Indexing is more common with
distributors than with vertically
integrated utilities
◼ MYRPs with rate freezes are most often
accompanied by extensive
supplemental funding through trackers
MYRP Adoption by State
Source: “Alternative Regulation for Evolving Utility Challenges: An Updated Survey,” EEI, January 2013
Recent U.S. Multiyear Rate Cap Precedents by State
6
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
* Award levelized across three-year plan. Individual year increases calculated at $540.8M, $306.6M, $280.2M for 2010, 2011, 2012
Sources: New York State Public Service Commission; SNL
Consolidated Edison
Case Study – New York:
Background
Utility Consolidated Edison (ConEd)
Rate Year 2010
MYRP Type Levelized Stairsteps
Length of Plan Three Years
Terms
Component Requested Awarded*
Award
Rate Year $854.4M* $420.4M
Year 2 6% on Total Bill Basis $420.4M
Year 3 6% on Total Bill Basis $420.4M
ROE 10.90% 10.15%
Profit
Sharing
ROE Threshold →
Percent Shared with
Customers
11.15% → 50%
12.149% → 75%
Compliance Reporting
Computation and Disposition of Earnings Report (Annual)
◼ Filed within 60 days after the rate year is complete
◼ Includes detailed computations of ROE for the year to be
submitted to the secretary
◼ Calculation determines profit-sharing levels as specified in plan
Capital Expenditures Report (Annual)
◼ Filed with the secretary by February 28. Provides list of new
projects, canceled projects, and explanations for variances in
actuals versus budget
◼ Review meeting: Meet with commission staff on or before
December 15 prior to Year 2 and Year 3 to review capital
spending plans
Key Takeaways from the Order
◼ ConEd required to reduce O&M by a set amount annually
◼ Net plant targets established for three categories
• If actual net plant in service is less than targets, ConEd must
defer carrying costs for the benefit of customers
• If actual net plant exceeds targets, ConEd must absorb costs
during term of plan
• Any overages must be justified
◼ Plan includes 2% annual productivity adjustment to revenue
requirement
◼ ConEd encouraged to consider the rate impacts on customers in their
capital budgeting and planning
◼ Commission’s order specifies significant requirements related to
improving corporate culture with an emphasis on increased
effectiveness and accountability to customers and other stakeholders
◼ Commission finds that three-year plan is beneficial by providing rate
payers with certainty for budgeting purposes and providing utility with
clarity of revenue expectations for the next three years
◼ Order includes a reliability performance mechanism that penalizes
revenue allowance if performance on certain metrics is not achieved
7
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
Georgia Power Company
Case Study – Georgia:
Background
Utility Georgia Power Company
Rate Year 2011
MYRP Type Stairstep
Length of Plan Three Years
Terms
Component Requested Awarded
Award
Rate Year $615M $562.3M
Year 2 Unable to Discern $189.7M
Year 3 Unable to Discern $92.6M
ROE 11.95%
11.15%
(Dead band = 10.25%
to 12.25%)
Profit
Sharing
ROE Threshold →
Percent Shared with
Customers
Above 12.25% → 66%
Sources: Georgia Public Service Commission; SNL
Compliance Reporting
Retail Surveillance Report (Annual)
◼ Includes detailed calculations for ROE and supporting
documentation
◼ Also includes company financials and actuals vs. budgeted
non-fuel O&M
Retail Base Revenue and Electricity Sales Forecast
◼ Forecast of base rate revenue and megawatt-hour sales
◼ Redacted for “trade-secret status”
Key Takeaways from the Order
◼ If earnings fall below 10.25% ROE, GA Power may petition the
commission for a interim cost recovery (ICR) tariff
◼ ICR process will involve minimum filing requirements established by
the commission and subject to public input
8
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
Public Service Company of Colorado
Case Study – Colorado:
Background
Utility
Public Service Company of
Colorado
Rate Year 2012
MYRP Type Stairstep
Length of Plan Three Years
Terms
Component Requested Awarded
Award $141.9M $114M
Rate Year $141.9M 73
Year 2 Unable to Discern 16
Year 3 Unable to Discern 25
ROE 10.75% 10.0%
Profit
Sharing
ROE Threshold →
Percent Shared with
Customers
Above 10.0% → 60%
Above 10.2% → 50%
Above 10.5% → 100%
Sources: Colorado Public Utilities Commission; SNL
Key Takeaways from the Order
◼ PSCo agrees not to file a new rate case unless the revenue shortfall
for a 12-month period is more than 2% of the targeted revenue for the
year (“stay out” provision)
◼ Proposed plan would have increased base rates by $281M but be
offset by $139.1M in reductions to riders currently in the tariff
◼ PSCo filed both future test year (FTY) and historical test year (HTY)
calculations. HTY calculations resulted in $160.8M revenue
deficiency due to the effects of accelerated depreciation (compared to
$141.9M for FTY)
◼ All interveners (except one) urged the use of the HTY rather than the
FTY
◼ Staff recommended a lower ROE, lower cost of debt, and a different
capital structure which resulted in a reduction of the revenue
deficiency of $125.7M
◼ Commission accepted the settlement agreement without revisions or
modifications
Compliance Reporting
Earnings Sharing Mechanism Report
◼ Presents ROE performance with supporting calculations.
Based on ROE level, revenue sharing agreement may be
triggered
◼ Report includes:
• Common Plant Allocation and supporting documentation
• Calculation of Earnings Sharing and supporting
documentation
• Information related to CWIP and allowance for funds
used during construction (AFUDC)
◼ Report does not include:
• Capital project execution information (actuals versus
budget with variance explanations)
9
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
San Diego Gas & Electric
Case Study – California:
Background
Utility San Diego Gas & Electric
Rate Year 2012
MYRP Type
Hybrid – Fixed % Based on Cost
Projections Tied to an Index
Length of Plan Four Years
Terms
Component Requested Awarded
Award
Rate Year $237.5M $123.4M
Year 2 Unable to Discern 2.65% Increase
Year 3 Unable to Discern 2.75% Increase
Year 4 Unable to Discern 2.75% Increase
ROE N/A* 10.7%
Profit
Sharing
60/40 for RD&D
Revenues
(Cust./Utility)
75/25 for RD&D
Revenues
(Cust./Utility)
Key Takeaways from the Order
◼ SDG&E required to update reliability performance metrics and targets
◼ Includes allowances for two-way accounts in a number of categories,
e.g., compliance with certain EPA rules, energy storage, transmission
and distribution integrity management programs
◼ SDG&E must provide detailed accounting of and justification for
AFUDC in next case
◼ SDG&E used a five-year average (2005–2009) as the basis for all
cost forecasting
• Opponents suggested the use of the most recent recorded data
is more appropriate
• Commission ruled that it depends on the cost center and each
should be considered separately
◼ SDG&E proposed post-test year (PTY) adjustment mechanism that
included six components: O&M adjustment, capital-related cost
adjustment, medical cost adjustment, Z-factor adjustment if
applicable, earnings sharing mechanism, and productivity investment
sharing mechanism
• The Commission elected to simplify and use one PTY
adjustment mechanism established ahead of time and based on
CPI – Urban index
* ROE is settled in a separate proceeding in California
Sources: California Public Utilities Commission; SNL
10
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
Legislation Leads to Commission Order
◼ Minnesota legislature authorized the commission to approve MYRPs in 2011 with Minn. Stat. 216B.16, subd. 19
◼ Commission solicited and received comments on appropriate terms and conditions for MYRPs
◼ Commission met to consider the motion on April 4, 2013
◼ Final order issued June 17, 2013 (Docket No. E,G-999/M-12-587)
 Benefits and concerns associated with MYRPs (as noted in the order):
◼ The commission’s goal is to permit plans that generate sufficient benefits to outweigh concerns and justify the burdens of plan
administration
Minnesota PUC Authorizes MYRPs
Case Study – Minnesota:
Source: Order Establishing Terms, Conditions, and Procedures for Multiyear Rate Plans: MNPUC, June 17, 2013
Benefits Concerns
◼ Reduced regulatory lag
◼ Reduced financing costs
◼ Reduced need for rate cases and other riders
◼ More predictable utility bills (gradual rate changes)
◼ Reduced rate shock
◼ Difficulty of accurately forecasting costs and
revenues
◼ Mismatch of relevant costs to relevant revenues
◼ Challenges associated with evaluation and
administration of plans
11
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
◼ The following table summarizes the outcome of MPUC deliberations on the various parameters of MYRPs under consideration:
Key Structural Decisions
Case Study – Minnesota:
Item Options Proposed Commission Decision Rationale
Procedural Context ◼ File MYRP within context of
general rate case
◼ File shortly after rate case when
factual record is still fresh
◼ File plan to coincide with capital
project
File MYRP within context of general
rate case
Evaluation of MYRP presents same
challenges as general rate case and
more. General rate case process
provides best foundation for meeting
challenges
Subsequent Rate Cases ◼ Utilities seeking approval of
MYRP must agree to forego any
rate case filings throughout
duration of MYRP
Utilities will not be permitted to file a
new rate case until MYRP has
expired
Evaluation of MYRP creates
additional challenges in exchange for
reduced regulatory burden. Filing a
new rate case would force
commission to incur the burdens
without the benefits
Formula Rates ◼ Specific rates for each year of
plan
◼ Automatic formulas for annual
rate adjustment
Plans will specify fixed rates for each
year of the plan. MYRPs that
propose formula rates will not be
approved
Fixed multiyear rates allow prices to
adjust over time but are based on
fact-driven rate-making process and
substantial evidence. Formulaic rates
automatically pass through utility
costs to customers and reduce
incentive to manage costs
Return on Equity ◼ Reduce ROE in each year of the
plan
◼ Maintain same ROE throughout
term of plan
◼ Address ROE on a case-by-case
basis
The established ROE will be used to
determine rates for all years of
MYRP
Difficult to forecast changes in ROE
over time. Doubtful benefits
outweighed by burden of generating
estimates
Source: Order Establishing Terms, Conditions, and Procedures for Multiyear Rate Plans: MNPUC, June 17, 2013
12
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
Key Structural Decisions (Cont’d)
Case Study – Minnesota:
Item Options Proposed Commission Decision Rationale
Rate Riders and Differed
Accounting
◼ Eliminate all riders (no longer
necessary as need is met
through MYRP)
◼ Consider riders on case-by-case
basis
Allow some riders on case-by-case
basis. Push utilities to consolidate
where possible, and under no
circumstances allow double-dip
recovery
Not all supplemental cost-recovery
categories are addressed in an
MYRP (e.g., energy costs,
emissions, conservation). Utilities
should seize efficiencies where they
can and prove in the filing that no
costs are being recovered through
both the MYRP and a rate rider
Rates at Plan Expiration ◼ Require new rate case filing No decision. Commission will not
specify how to determine rates, but
the utility will be required to propose
what those rates will be or how they
will be calculated as part of the
MYRP filing. The utility is certainly
permitted to file a new rate case
Commission Initiated
Rate Change
◼ Imprudent rate increases should
be subject to refund and utilities
should waive any claim that such
a decision would constitute
retroactive rate making
Imprudent rate increases will be
subject to refund and utilities must
waive any claim that such a decision
would constitute retroactive rate
making
Follows from language of Minn. Stat.
216B.16
Plan Duration ◼ Two-year maximum (until
experience is gained)
◼ Three-year maximum or even
longer
Three-year maximum (term will begin
on effective date of new rates)
Commission sees no reason to
preclude consideration of three-year
plans as specified in the statute.
Further, given the administrative
burdens, commission sees no reason
to limit the period over which parties
hope to reap the benefits of MYRP
Source: Order Establishing Terms, Conditions, and Procedures for Multiyear Rate Plans: MNPUC, June 17, 2013
13
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
◼ Additional scrutiny
 MYRPs involve setting rates based on planned capital expenditures rather than reimbursing investments already made.
Therefore, utilities must be prepared to provide more detailed information than what has been required in the past
◼ Budgeting and project management skills
 Utilities must be able to show that investments were made according to the plan submitted at the time of the filing. Failure to
adhere to the plan may result in refunds or other costly regulatory issues. Ability to budget properly and execute projects to plan is
critical with MYRPs
◼ Project selection
 Determining which projects to include in the plan can be challenging. Utilities should consider:
– Size of projects (impact on revenue requirement)
– Execution risk associated with projects (scope, schedule, and budget)
◼ Compliance
 Compliance mechanisms will play a significant role in whether a MYRP is the best solution for a utility
 Some specific issues that must be addressed include:
– Threshold for determining rate refunds
– Aggregate versus project-by-project approach
– Internal surveillance
– Reporting mechanisms
Issues for Utilities Considering MYRPs
14
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
We believe the use of MYRPs will continue to grow as utilities and commissions work to overcome the limitations of traditional
ratemaking in order to balance the needs of the ratepayers and shareholders with the realities of operating and maintaining a
safe, reliable, and sustainable power delivery system
◼ Business as usual is not sustainable in the current business environment
◼ MYRPs provide a promising strategy for addressing some of the regulatory challenges facing the industry
◼ Additional scrutiny associated with MYRPs means utilities will have to improve their budgeting and project management practices in
order to be compliant and successfully earn the maximum allowable rate of return
◼ The success of early adopters will influence the direction of ratemaking across the country—utilities and commissions will be watching
closely
Conclusions
Alternative regulatory mechanisms are in the early stages of development, and utilities have an opportunity to help
shape the regulatory construct going forward.
15
Copyright © 2014 by ScottMadden, Inc. All rights reserved.
Richard D. Starkweather
Partner and Regulatory Practice
Leader
ScottMadden, Inc.
2626 Glenwood Avenue
Suite 480
Raleigh, NC 27608
rstarkweather@scottmadden.com
O: 919-781-4191 M: 919-345-9871
ScottMadden, Inc.
2626 Glenwood Avenue
Suite 480
Raleigh, NC 27608
pfowler@scottmadden.com
O: 919-781-4191 M: 404-558-1609
Preston Fowler
Director
Contact Us
16
ScottMadden has helped several utilities develop the tools necessary to successfully develop and defend a multiyear rate plan
filing. Please let us show you how we can help.

More Related Content

What's hot

Finance Technologies: Buy or Rent
Finance Technologies: Buy or RentFinance Technologies: Buy or Rent
Finance Technologies: Buy or Rent
ScottMadden, Inc.
 
Strategic Cybersecurity
Strategic CybersecurityStrategic Cybersecurity
Strategic Cybersecurity
ScottMadden, Inc.
 
Designing a Program that Increases Your Intelligent Automation “Velocity”
Designing a Program that Increases Your Intelligent Automation “Velocity”Designing a Program that Increases Your Intelligent Automation “Velocity”
Designing a Program that Increases Your Intelligent Automation “Velocity”
ScottMadden, Inc.
 
Coal Combustion Residuals: Understanding the Final Rule and Next Steps for El...
Coal Combustion Residuals: Understanding the Final Rule and Next Steps for El...Coal Combustion Residuals: Understanding the Final Rule and Next Steps for El...
Coal Combustion Residuals: Understanding the Final Rule and Next Steps for El...
ScottMadden, Inc.
 
The Electric Vehicle Market: Utility Perspective and Considerations for Utili...
The Electric Vehicle Market: Utility Perspective and Considerations for Utili...The Electric Vehicle Market: Utility Perspective and Considerations for Utili...
The Electric Vehicle Market: Utility Perspective and Considerations for Utili...
ScottMadden, Inc.
 
Value of Strategic Direction
Value of Strategic DirectionValue of Strategic Direction
Value of Strategic Direction
ScottMadden, Inc.
 
Combined Cycles
Combined CyclesCombined Cycles
Combined Cycles
ScottMadden, Inc.
 
Benchmarking for Natural Gas LDCs
Benchmarking for Natural Gas LDCsBenchmarking for Natural Gas LDCs
Benchmarking for Natural Gas LDCs
ScottMadden, Inc.
 
Miami University 2018 Cleveland Research Company Stock Pitch Competition
Miami University 2018 Cleveland Research Company Stock Pitch CompetitionMiami University 2018 Cleveland Research Company Stock Pitch Competition
Miami University 2018 Cleveland Research Company Stock Pitch Competition
Nhat Pham
 
Credit Suisse Global Industrials Conference Dec 4, 2013
Credit Suisse Global Industrials Conference Dec 4, 2013Credit Suisse Global Industrials Conference Dec 4, 2013
Credit Suisse Global Industrials Conference Dec 4, 2013ProgressiveWaste
 
Cibc presentation feb 27, 2014
Cibc presentation feb 27, 2014Cibc presentation feb 27, 2014
Cibc presentation feb 27, 2014ProgressiveWaste
 
Bin ir presentation feb 27, 2014 final
Bin ir presentation feb 27, 2014 finalBin ir presentation feb 27, 2014 final
Bin ir presentation feb 27, 2014 finalProgressiveWaste
 
Investor presentation april 2014
Investor presentation april 2014Investor presentation april 2014
Investor presentation april 2014ProgressiveWaste
 
Credit Suisse Environmental and Industrial Services Conference 2014
 Credit Suisse Environmental and Industrial Services Conference 2014 Credit Suisse Environmental and Industrial Services Conference 2014
Credit Suisse Environmental and Industrial Services Conference 2014
ProgressiveWaste
 
Investor presentation march 2016 v final
Investor presentation march 2016 v finalInvestor presentation march 2016 v final
Investor presentation march 2016 v final
CrestwoodCorporate
 
air products & chemicals 7 May 2008 Bankof America BASics
air products & chemicals 7 May 2008 Bankof America BASicsair products & chemicals 7 May 2008 Bankof America BASics
air products & chemicals 7 May 2008 Bankof America BASicsfinance26
 
Cs conference slides march 10, 2014
Cs conference slides march 10, 2014Cs conference slides march 10, 2014
Cs conference slides march 10, 2014ProgressiveWaste
 
Fossil Benchmarking Analysis
Fossil Benchmarking AnalysisFossil Benchmarking Analysis
Fossil Benchmarking Analysis
ScottMadden, Inc.
 
Celp investor presentation march 2016
Celp investor presentation march 2016Celp investor presentation march 2016
Celp investor presentation march 2016
CypressEnergy
 

What's hot (20)

Finance Technologies: Buy or Rent
Finance Technologies: Buy or RentFinance Technologies: Buy or Rent
Finance Technologies: Buy or Rent
 
Strategic Cybersecurity
Strategic CybersecurityStrategic Cybersecurity
Strategic Cybersecurity
 
Designing a Program that Increases Your Intelligent Automation “Velocity”
Designing a Program that Increases Your Intelligent Automation “Velocity”Designing a Program that Increases Your Intelligent Automation “Velocity”
Designing a Program that Increases Your Intelligent Automation “Velocity”
 
Coal Combustion Residuals: Understanding the Final Rule and Next Steps for El...
Coal Combustion Residuals: Understanding the Final Rule and Next Steps for El...Coal Combustion Residuals: Understanding the Final Rule and Next Steps for El...
Coal Combustion Residuals: Understanding the Final Rule and Next Steps for El...
 
The Electric Vehicle Market: Utility Perspective and Considerations for Utili...
The Electric Vehicle Market: Utility Perspective and Considerations for Utili...The Electric Vehicle Market: Utility Perspective and Considerations for Utili...
The Electric Vehicle Market: Utility Perspective and Considerations for Utili...
 
Value of Strategic Direction
Value of Strategic DirectionValue of Strategic Direction
Value of Strategic Direction
 
Six sigma
Six sigmaSix sigma
Six sigma
 
Combined Cycles
Combined CyclesCombined Cycles
Combined Cycles
 
Benchmarking for Natural Gas LDCs
Benchmarking for Natural Gas LDCsBenchmarking for Natural Gas LDCs
Benchmarking for Natural Gas LDCs
 
Miami University 2018 Cleveland Research Company Stock Pitch Competition
Miami University 2018 Cleveland Research Company Stock Pitch CompetitionMiami University 2018 Cleveland Research Company Stock Pitch Competition
Miami University 2018 Cleveland Research Company Stock Pitch Competition
 
Credit Suisse Global Industrials Conference Dec 4, 2013
Credit Suisse Global Industrials Conference Dec 4, 2013Credit Suisse Global Industrials Conference Dec 4, 2013
Credit Suisse Global Industrials Conference Dec 4, 2013
 
Cibc presentation feb 27, 2014
Cibc presentation feb 27, 2014Cibc presentation feb 27, 2014
Cibc presentation feb 27, 2014
 
Bin ir presentation feb 27, 2014 final
Bin ir presentation feb 27, 2014 finalBin ir presentation feb 27, 2014 final
Bin ir presentation feb 27, 2014 final
 
Investor presentation april 2014
Investor presentation april 2014Investor presentation april 2014
Investor presentation april 2014
 
Credit Suisse Environmental and Industrial Services Conference 2014
 Credit Suisse Environmental and Industrial Services Conference 2014 Credit Suisse Environmental and Industrial Services Conference 2014
Credit Suisse Environmental and Industrial Services Conference 2014
 
Investor presentation march 2016 v final
Investor presentation march 2016 v finalInvestor presentation march 2016 v final
Investor presentation march 2016 v final
 
air products & chemicals 7 May 2008 Bankof America BASics
air products & chemicals 7 May 2008 Bankof America BASicsair products & chemicals 7 May 2008 Bankof America BASics
air products & chemicals 7 May 2008 Bankof America BASics
 
Cs conference slides march 10, 2014
Cs conference slides march 10, 2014Cs conference slides march 10, 2014
Cs conference slides march 10, 2014
 
Fossil Benchmarking Analysis
Fossil Benchmarking AnalysisFossil Benchmarking Analysis
Fossil Benchmarking Analysis
 
Celp investor presentation march 2016
Celp investor presentation march 2016Celp investor presentation march 2016
Celp investor presentation march 2016
 

Similar to Innovative Ratemaking- Multiyear Rate Plans

CaribNews Exclusive: PREPA Transformation - June 1,2015
CaribNews Exclusive: PREPA Transformation - June 1,2015CaribNews Exclusive: PREPA Transformation - June 1,2015
CaribNews Exclusive: PREPA Transformation - June 1,2015
caribnews
 
The Economic Consequences of New Models
The Economic Consequences of New ModelsThe Economic Consequences of New Models
The Economic Consequences of New Models
ScottMadden, Inc.
 
SolarCity Investors _ Nov 2015
SolarCity  Investors _ Nov 2015SolarCity  Investors _ Nov 2015
SolarCity Investors _ Nov 2015
Dmitry Tseitlin
 
The 51st State Initiative
The 51st State InitiativeThe 51st State Initiative
The 51st State Initiative
ScottMadden, Inc.
 
ScottMadden's 51st State Roadmap
ScottMadden's 51st State RoadmapScottMadden's 51st State Roadmap
ScottMadden's 51st State Roadmap
ScottMadden, Inc.
 
Energy Efficiency Incentives
Energy Efficiency IncentivesEnergy Efficiency Incentives
Energy Efficiency Incentiveswayneshirley
 
Edison International - Business Update November 2016
Edison International - Business Update November 2016Edison International - Business Update November 2016
Edison International - Business Update November 2016EdisonInternational
 
3 q2016 earnings_ppt_final
3 q2016 earnings_ppt_final3 q2016 earnings_ppt_final
3 q2016 earnings_ppt_final
InfraREIT
 
Edison International Business Update - July 2017
Edison International Business Update - July 2017Edison International Business Update - July 2017
Edison International Business Update - July 2017
EdisonInternational
 
Dec 2014 investor deck
Dec 2014 investor deckDec 2014 investor deck
Dec 2014 investor deck
broadwind
 
Delta air lines deutsche bank presentation 2018
Delta air lines deutsche bank presentation 2018Delta air lines deutsche bank presentation 2018
Delta air lines deutsche bank presentation 2018
Delta_Airlines
 
1 q2017 earnings_ppt_final
1 q2017 earnings_ppt_final1 q2017 earnings_ppt_final
1 q2017 earnings_ppt_final
InfraREIT
 
Access Midstream Partners Investor Presentation - July 2013
Access Midstream Partners Investor Presentation - July 2013 Access Midstream Partners Investor Presentation - July 2013
Access Midstream Partners Investor Presentation - July 2013
Kprelosky
 
4 q2016 earnings_ppt_final
4 q2016 earnings_ppt_final4 q2016 earnings_ppt_final
4 q2016 earnings_ppt_final
InfraREIT
 
Awk red chip slides final without notes
Awk red chip slides final without notesAwk red chip slides final without notes
Awk red chip slides final without notes
RedChip Companies, Inc.
 
Trc q1 2014 earnings slides final
Trc q1 2014 earnings slides finalTrc q1 2014 earnings slides final
Trc q1 2014 earnings slides finaltrcsolutions
 
Prepaid OCS Convergence Model
Prepaid OCS Convergence ModelPrepaid OCS Convergence Model
Prepaid OCS Convergence ModelKarthik Ethirajan
 
India - Renewables - eligible overseas capital markets candidate 2015
India - Renewables - eligible overseas capital markets candidate 2015India - Renewables - eligible overseas capital markets candidate 2015
India - Renewables - eligible overseas capital markets candidate 2015
Varun Sethi
 
India Renewables-Eligible Overseas Capital Markets Candidate
India Renewables-Eligible Overseas Capital Markets CandidateIndia Renewables-Eligible Overseas Capital Markets Candidate
India Renewables-Eligible Overseas Capital Markets Candidate
Varun Sethi
 
XYZ solar power Global IPO
XYZ solar power   Global IPOXYZ solar power   Global IPO
XYZ solar power Global IPO
Varun Sethi
 

Similar to Innovative Ratemaking- Multiyear Rate Plans (20)

CaribNews Exclusive: PREPA Transformation - June 1,2015
CaribNews Exclusive: PREPA Transformation - June 1,2015CaribNews Exclusive: PREPA Transformation - June 1,2015
CaribNews Exclusive: PREPA Transformation - June 1,2015
 
The Economic Consequences of New Models
The Economic Consequences of New ModelsThe Economic Consequences of New Models
The Economic Consequences of New Models
 
SolarCity Investors _ Nov 2015
SolarCity  Investors _ Nov 2015SolarCity  Investors _ Nov 2015
SolarCity Investors _ Nov 2015
 
The 51st State Initiative
The 51st State InitiativeThe 51st State Initiative
The 51st State Initiative
 
ScottMadden's 51st State Roadmap
ScottMadden's 51st State RoadmapScottMadden's 51st State Roadmap
ScottMadden's 51st State Roadmap
 
Energy Efficiency Incentives
Energy Efficiency IncentivesEnergy Efficiency Incentives
Energy Efficiency Incentives
 
Edison International - Business Update November 2016
Edison International - Business Update November 2016Edison International - Business Update November 2016
Edison International - Business Update November 2016
 
3 q2016 earnings_ppt_final
3 q2016 earnings_ppt_final3 q2016 earnings_ppt_final
3 q2016 earnings_ppt_final
 
Edison International Business Update - July 2017
Edison International Business Update - July 2017Edison International Business Update - July 2017
Edison International Business Update - July 2017
 
Dec 2014 investor deck
Dec 2014 investor deckDec 2014 investor deck
Dec 2014 investor deck
 
Delta air lines deutsche bank presentation 2018
Delta air lines deutsche bank presentation 2018Delta air lines deutsche bank presentation 2018
Delta air lines deutsche bank presentation 2018
 
1 q2017 earnings_ppt_final
1 q2017 earnings_ppt_final1 q2017 earnings_ppt_final
1 q2017 earnings_ppt_final
 
Access Midstream Partners Investor Presentation - July 2013
Access Midstream Partners Investor Presentation - July 2013 Access Midstream Partners Investor Presentation - July 2013
Access Midstream Partners Investor Presentation - July 2013
 
4 q2016 earnings_ppt_final
4 q2016 earnings_ppt_final4 q2016 earnings_ppt_final
4 q2016 earnings_ppt_final
 
Awk red chip slides final without notes
Awk red chip slides final without notesAwk red chip slides final without notes
Awk red chip slides final without notes
 
Trc q1 2014 earnings slides final
Trc q1 2014 earnings slides finalTrc q1 2014 earnings slides final
Trc q1 2014 earnings slides final
 
Prepaid OCS Convergence Model
Prepaid OCS Convergence ModelPrepaid OCS Convergence Model
Prepaid OCS Convergence Model
 
India - Renewables - eligible overseas capital markets candidate 2015
India - Renewables - eligible overseas capital markets candidate 2015India - Renewables - eligible overseas capital markets candidate 2015
India - Renewables - eligible overseas capital markets candidate 2015
 
India Renewables-Eligible Overseas Capital Markets Candidate
India Renewables-Eligible Overseas Capital Markets CandidateIndia Renewables-Eligible Overseas Capital Markets Candidate
India Renewables-Eligible Overseas Capital Markets Candidate
 
XYZ solar power Global IPO
XYZ solar power   Global IPOXYZ solar power   Global IPO
XYZ solar power Global IPO
 

More from ScottMadden, Inc.

Creating IT Value-A Better Way to Make IT Investment Decisions
Creating IT Value-A Better Way to Make IT Investment DecisionsCreating IT Value-A Better Way to Make IT Investment Decisions
Creating IT Value-A Better Way to Make IT Investment Decisions
ScottMadden, Inc.
 
Benchmarking for Natural Gas LDCs
Benchmarking for Natural Gas LDCsBenchmarking for Natural Gas LDCs
Benchmarking for Natural Gas LDCs
ScottMadden, Inc.
 
ScottMadden Fossil Benchmarking Analysis
ScottMadden Fossil Benchmarking Analysis ScottMadden Fossil Benchmarking Analysis
ScottMadden Fossil Benchmarking Analysis
ScottMadden, Inc.
 
Overcoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsOvercoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/Projects
ScottMadden, Inc.
 
ScottMadden HR Shared Services Benchmarking Study Highlights 2019
ScottMadden HR Shared Services Benchmarking Study Highlights 2019ScottMadden HR Shared Services Benchmarking Study Highlights 2019
ScottMadden HR Shared Services Benchmarking Study Highlights 2019
ScottMadden, Inc.
 
ScottMadden Fossil Benchmarking Analysis
ScottMadden Fossil Benchmarking Analysis ScottMadden Fossil Benchmarking Analysis
ScottMadden Fossil Benchmarking Analysis
ScottMadden, Inc.
 
ScottMadden Finance Shared Services Benchmark Highlights 2020
ScottMadden Finance Shared Services Benchmark Highlights 2020ScottMadden Finance Shared Services Benchmark Highlights 2020
ScottMadden Finance Shared Services Benchmark Highlights 2020
ScottMadden, Inc.
 
The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...
The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...
The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...
ScottMadden, Inc.
 
ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...
ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...
ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...
ScottMadden, Inc.
 
Energy Industry Update Webcast: Don't Stop Believin'
Energy Industry Update Webcast: Don't Stop Believin'Energy Industry Update Webcast: Don't Stop Believin'
Energy Industry Update Webcast: Don't Stop Believin'
ScottMadden, Inc.
 
Technology for HR Shared Services
Technology for HR Shared ServicesTechnology for HR Shared Services
Technology for HR Shared Services
ScottMadden, Inc.
 
Building a Business Case for Shared Services
Building a Business Case for Shared ServicesBuilding a Business Case for Shared Services
Building a Business Case for Shared Services
ScottMadden, Inc.
 
Fundamentals of Designing, Building, & Implementing a Service Delivery Center
Fundamentals of Designing, Building, & Implementing a Service Delivery CenterFundamentals of Designing, Building, & Implementing a Service Delivery Center
Fundamentals of Designing, Building, & Implementing a Service Delivery Center
ScottMadden, Inc.
 
Next Generation Shared Services Centers
Next Generation Shared Services CentersNext Generation Shared Services Centers
Next Generation Shared Services Centers
ScottMadden, Inc.
 
Capital Program Assessment Overview
Capital Program Assessment OverviewCapital Program Assessment Overview
Capital Program Assessment Overview
ScottMadden, Inc.
 
Generation Trends: What are the Impacts on Transmission?
Generation Trends: What are the Impacts on Transmission? Generation Trends: What are the Impacts on Transmission?
Generation Trends: What are the Impacts on Transmission?
ScottMadden, Inc.
 
Overcoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsOvercoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/Projects
ScottMadden, Inc.
 
Shared Services Customer Satisfaction
Shared Services Customer SatisfactionShared Services Customer Satisfaction
Shared Services Customer Satisfaction
ScottMadden, Inc.
 
Shared Services Technologies
Shared Services TechnologiesShared Services Technologies
Shared Services Technologies
ScottMadden, Inc.
 
HR Shared Service Expansion
HR Shared Service ExpansionHR Shared Service Expansion
HR Shared Service Expansion
ScottMadden, Inc.
 

More from ScottMadden, Inc. (20)

Creating IT Value-A Better Way to Make IT Investment Decisions
Creating IT Value-A Better Way to Make IT Investment DecisionsCreating IT Value-A Better Way to Make IT Investment Decisions
Creating IT Value-A Better Way to Make IT Investment Decisions
 
Benchmarking for Natural Gas LDCs
Benchmarking for Natural Gas LDCsBenchmarking for Natural Gas LDCs
Benchmarking for Natural Gas LDCs
 
ScottMadden Fossil Benchmarking Analysis
ScottMadden Fossil Benchmarking Analysis ScottMadden Fossil Benchmarking Analysis
ScottMadden Fossil Benchmarking Analysis
 
Overcoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsOvercoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/Projects
 
ScottMadden HR Shared Services Benchmarking Study Highlights 2019
ScottMadden HR Shared Services Benchmarking Study Highlights 2019ScottMadden HR Shared Services Benchmarking Study Highlights 2019
ScottMadden HR Shared Services Benchmarking Study Highlights 2019
 
ScottMadden Fossil Benchmarking Analysis
ScottMadden Fossil Benchmarking Analysis ScottMadden Fossil Benchmarking Analysis
ScottMadden Fossil Benchmarking Analysis
 
ScottMadden Finance Shared Services Benchmark Highlights 2020
ScottMadden Finance Shared Services Benchmark Highlights 2020ScottMadden Finance Shared Services Benchmark Highlights 2020
ScottMadden Finance Shared Services Benchmark Highlights 2020
 
The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...
The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...
The ScottMadden Energy Industry Update Webcast: Everything Counts ... In Larg...
 
ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...
ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...
ScottMadden's Energy Industry Update for the 2019 Utility Supply Chain Confer...
 
Energy Industry Update Webcast: Don't Stop Believin'
Energy Industry Update Webcast: Don't Stop Believin'Energy Industry Update Webcast: Don't Stop Believin'
Energy Industry Update Webcast: Don't Stop Believin'
 
Technology for HR Shared Services
Technology for HR Shared ServicesTechnology for HR Shared Services
Technology for HR Shared Services
 
Building a Business Case for Shared Services
Building a Business Case for Shared ServicesBuilding a Business Case for Shared Services
Building a Business Case for Shared Services
 
Fundamentals of Designing, Building, & Implementing a Service Delivery Center
Fundamentals of Designing, Building, & Implementing a Service Delivery CenterFundamentals of Designing, Building, & Implementing a Service Delivery Center
Fundamentals of Designing, Building, & Implementing a Service Delivery Center
 
Next Generation Shared Services Centers
Next Generation Shared Services CentersNext Generation Shared Services Centers
Next Generation Shared Services Centers
 
Capital Program Assessment Overview
Capital Program Assessment OverviewCapital Program Assessment Overview
Capital Program Assessment Overview
 
Generation Trends: What are the Impacts on Transmission?
Generation Trends: What are the Impacts on Transmission? Generation Trends: What are the Impacts on Transmission?
Generation Trends: What are the Impacts on Transmission?
 
Overcoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/ProjectsOvercoming the Challenges of Large Capital Programs/Projects
Overcoming the Challenges of Large Capital Programs/Projects
 
Shared Services Customer Satisfaction
Shared Services Customer SatisfactionShared Services Customer Satisfaction
Shared Services Customer Satisfaction
 
Shared Services Technologies
Shared Services TechnologiesShared Services Technologies
Shared Services Technologies
 
HR Shared Service Expansion
HR Shared Service ExpansionHR Shared Service Expansion
HR Shared Service Expansion
 

Recently uploaded

A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
thanhdowork
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
Peter Windle
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
vaibhavrinwa19
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
Vivekanand Anglo Vedic Academy
 
Chapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdfChapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdf
Kartik Tiwari
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
Best Digital Marketing Institute In NOIDA
Best Digital Marketing Institute In NOIDABest Digital Marketing Institute In NOIDA
Best Digital Marketing Institute In NOIDA
deeptiverma2406
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Atul Kumar Singh
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
Marketing internship report file for MBA
Marketing internship report file for MBAMarketing internship report file for MBA
Marketing internship report file for MBA
gb193092
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
Group Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana BuscigliopptxGroup Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana Buscigliopptx
ArianaBusciglio
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
chanes7
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 

Recently uploaded (20)

A Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptxA Survey of Techniques for Maximizing LLM Performance.pptx
A Survey of Techniques for Maximizing LLM Performance.pptx
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
 
The French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free downloadThe French Revolution Class 9 Study Material pdf free download
The French Revolution Class 9 Study Material pdf free download
 
Chapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdfChapter -12, Antibiotics (One Page Notes).pdf
Chapter -12, Antibiotics (One Page Notes).pdf
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
Best Digital Marketing Institute In NOIDA
Best Digital Marketing Institute In NOIDABest Digital Marketing Institute In NOIDA
Best Digital Marketing Institute In NOIDA
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
Guidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th SemesterGuidance_and_Counselling.pdf B.Ed. 4th Semester
Guidance_and_Counselling.pdf B.Ed. 4th Semester
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
Marketing internship report file for MBA
Marketing internship report file for MBAMarketing internship report file for MBA
Marketing internship report file for MBA
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
Group Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana BuscigliopptxGroup Presentation 2 Economics.Ariana Buscigliopptx
Group Presentation 2 Economics.Ariana Buscigliopptx
 
Digital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion DesignsDigital Artifact 2 - Investigating Pavilion Designs
Digital Artifact 2 - Investigating Pavilion Designs
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 

Innovative Ratemaking- Multiyear Rate Plans

  • 1. Copyright © 2014 by ScottMadden, Inc. All rights reserved. Innovative Ratemaking – Multiyear Rate Plans February 2014
  • 2. Copyright © 2014 by ScottMadden, Inc. All rights reserved. This document: ◼ Discusses the current business and regulatory environment that is resulting in the increased use of innovative ratemaking techniques, including the consideration by some utilities and jurisdictions of a multiyear rate plan (MYRP) filing ◼ Provides an overview of the different MYRP approaches being utilized, including case studies in selected states and key takeaways from each approach ◼ Summarizes future trends regarding the use of MYRP filings Outline ◼ Current Environment ◼ Overview of Multiyear Rate Plans ◼ Case Studies ◼ Issues for Utilities Considering MYRPs ◼ Conclusions Introduction 1
  • 3. Copyright © 2014 by ScottMadden, Inc. All rights reserved. The current business environment is creating challenges for utilities ◼ Electric utility costs are increasing more rapidly than retail sales  Utilities are actively modernizing and enhancing their delivery infrastructure  Sales growth, which enabled utilities to finance new investments in the past, has not bounced back from pre-recession lows, and in some areas is declining Current Environment Sources: SNL Financial; U.S. Energy Information Administration $0 $40 $80 $120 $160 $200 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 TotalExpenditures($Billions) Total Capital Expenditures 2003–2012 3,250,000 3,500,000 3,750,000 4,000,000 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 GigawattHours Total Retail Sales 2003–2012 2
  • 4. Copyright © 2014 by ScottMadden, Inc. All rights reserved. Traditional regulatory mechanisms are also impacting financial performance ◼ Regulatory lag makes timely cost recovery difficult ◼ Consistent “under-earning” impacts utility credit ratings, increases cost of capital, and may discourage needed investment Utilities have responded by filing rate cases more frequently, which leads to additional challenges ◼ Requires significant resources that could otherwise be used to run the business ◼ Contributes to increased uncertainty of revenues and ROE and puts upward pressure on financing costs ◼ Creates an additional burden and resource requirements for regulators and interveners Current Environment (Cont’d) 8% 9% 10% 11% 12% 13% 14% 15% 0% 20% 40% 60% 80% 100% 120% 140% 160% 180% AuthorizedROE Earned ROE as a % of Authorized ROE Earned vs. Authorized ROE for Electric Utilities Electric utilities are struggling to earn their authorized return Median = 10.3% Median = 86.6% Sources: SNL Financial; Regulatory Research Associates 0 10 20 30 40 50 60 70 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 Number of Rate Cases Approved 2003-2012 3
  • 5. Copyright © 2014 by ScottMadden, Inc. All rights reserved. In light of the challenges associated with traditional regulatory approaches, some utilities and public utility commissions are experimenting with alternative approaches ◼ Various methods have been introduced across many states including:  Cost trackers  Inclusion of construction work in progress (CWIP) in the rate base  Revenue decoupling  Forward test years  Formula rates  MYRPs Current Environment (Cont’d) MYRPs represent one alternative regulatory approach to addressing the limitations of traditional regulatory mechanisms in the current business environment. 4
  • 6. Copyright © 2014 by ScottMadden, Inc. All rights reserved. Characteristics ◼ Originally utilized in the railroad, telecommunications, and oil pipeline industries ◼ Typically designed for a three- to five-year period ◼ Attrition relief mechanisms (ARMs) define annual rate escalations ◼ ARMs are usually capped either in terms of rates or total revenue ◼ Typical ARM designs include:  Stairsteps – predetermined increases in rates or revenues based on cost growth forecasts  Indexing – variable increases tied to an index like the CPI inflation rate  Hybrids – indexing for O&M and stairsteps for CapEx ◼ Additional provisions sometimes included in MYRP structure include:  Cost trackers  Earnings sharing mechanisms to distribute excess earnings between utility and customers (when allowed ROE is exceeded)  “Off-ramps” to allow for plan suspension in the event of unusually high or low earnings Benefits ◼ Produces more predictable revenue stream and certainty for utility to make investments (reduces cost of capital) ◼ Reduces regulatory costs ◼ Incents utility to manage costs ◼ Enables utility to allocate resources to running the business rather than rate case administration Overview 5
  • 7. Copyright © 2014 by ScottMadden, Inc. All rights reserved. ◼ 17 states have implemented MYRPs in one form or another ◼ California and the states in the Northeast have the most experience with MYRPs ◼ Indexing is more common with distributors than with vertically integrated utilities ◼ MYRPs with rate freezes are most often accompanied by extensive supplemental funding through trackers MYRP Adoption by State Source: “Alternative Regulation for Evolving Utility Challenges: An Updated Survey,” EEI, January 2013 Recent U.S. Multiyear Rate Cap Precedents by State 6
  • 8. Copyright © 2014 by ScottMadden, Inc. All rights reserved. * Award levelized across three-year plan. Individual year increases calculated at $540.8M, $306.6M, $280.2M for 2010, 2011, 2012 Sources: New York State Public Service Commission; SNL Consolidated Edison Case Study – New York: Background Utility Consolidated Edison (ConEd) Rate Year 2010 MYRP Type Levelized Stairsteps Length of Plan Three Years Terms Component Requested Awarded* Award Rate Year $854.4M* $420.4M Year 2 6% on Total Bill Basis $420.4M Year 3 6% on Total Bill Basis $420.4M ROE 10.90% 10.15% Profit Sharing ROE Threshold → Percent Shared with Customers 11.15% → 50% 12.149% → 75% Compliance Reporting Computation and Disposition of Earnings Report (Annual) ◼ Filed within 60 days after the rate year is complete ◼ Includes detailed computations of ROE for the year to be submitted to the secretary ◼ Calculation determines profit-sharing levels as specified in plan Capital Expenditures Report (Annual) ◼ Filed with the secretary by February 28. Provides list of new projects, canceled projects, and explanations for variances in actuals versus budget ◼ Review meeting: Meet with commission staff on or before December 15 prior to Year 2 and Year 3 to review capital spending plans Key Takeaways from the Order ◼ ConEd required to reduce O&M by a set amount annually ◼ Net plant targets established for three categories • If actual net plant in service is less than targets, ConEd must defer carrying costs for the benefit of customers • If actual net plant exceeds targets, ConEd must absorb costs during term of plan • Any overages must be justified ◼ Plan includes 2% annual productivity adjustment to revenue requirement ◼ ConEd encouraged to consider the rate impacts on customers in their capital budgeting and planning ◼ Commission’s order specifies significant requirements related to improving corporate culture with an emphasis on increased effectiveness and accountability to customers and other stakeholders ◼ Commission finds that three-year plan is beneficial by providing rate payers with certainty for budgeting purposes and providing utility with clarity of revenue expectations for the next three years ◼ Order includes a reliability performance mechanism that penalizes revenue allowance if performance on certain metrics is not achieved 7
  • 9. Copyright © 2014 by ScottMadden, Inc. All rights reserved. Georgia Power Company Case Study – Georgia: Background Utility Georgia Power Company Rate Year 2011 MYRP Type Stairstep Length of Plan Three Years Terms Component Requested Awarded Award Rate Year $615M $562.3M Year 2 Unable to Discern $189.7M Year 3 Unable to Discern $92.6M ROE 11.95% 11.15% (Dead band = 10.25% to 12.25%) Profit Sharing ROE Threshold → Percent Shared with Customers Above 12.25% → 66% Sources: Georgia Public Service Commission; SNL Compliance Reporting Retail Surveillance Report (Annual) ◼ Includes detailed calculations for ROE and supporting documentation ◼ Also includes company financials and actuals vs. budgeted non-fuel O&M Retail Base Revenue and Electricity Sales Forecast ◼ Forecast of base rate revenue and megawatt-hour sales ◼ Redacted for “trade-secret status” Key Takeaways from the Order ◼ If earnings fall below 10.25% ROE, GA Power may petition the commission for a interim cost recovery (ICR) tariff ◼ ICR process will involve minimum filing requirements established by the commission and subject to public input 8
  • 10. Copyright © 2014 by ScottMadden, Inc. All rights reserved. Public Service Company of Colorado Case Study – Colorado: Background Utility Public Service Company of Colorado Rate Year 2012 MYRP Type Stairstep Length of Plan Three Years Terms Component Requested Awarded Award $141.9M $114M Rate Year $141.9M 73 Year 2 Unable to Discern 16 Year 3 Unable to Discern 25 ROE 10.75% 10.0% Profit Sharing ROE Threshold → Percent Shared with Customers Above 10.0% → 60% Above 10.2% → 50% Above 10.5% → 100% Sources: Colorado Public Utilities Commission; SNL Key Takeaways from the Order ◼ PSCo agrees not to file a new rate case unless the revenue shortfall for a 12-month period is more than 2% of the targeted revenue for the year (“stay out” provision) ◼ Proposed plan would have increased base rates by $281M but be offset by $139.1M in reductions to riders currently in the tariff ◼ PSCo filed both future test year (FTY) and historical test year (HTY) calculations. HTY calculations resulted in $160.8M revenue deficiency due to the effects of accelerated depreciation (compared to $141.9M for FTY) ◼ All interveners (except one) urged the use of the HTY rather than the FTY ◼ Staff recommended a lower ROE, lower cost of debt, and a different capital structure which resulted in a reduction of the revenue deficiency of $125.7M ◼ Commission accepted the settlement agreement without revisions or modifications Compliance Reporting Earnings Sharing Mechanism Report ◼ Presents ROE performance with supporting calculations. Based on ROE level, revenue sharing agreement may be triggered ◼ Report includes: • Common Plant Allocation and supporting documentation • Calculation of Earnings Sharing and supporting documentation • Information related to CWIP and allowance for funds used during construction (AFUDC) ◼ Report does not include: • Capital project execution information (actuals versus budget with variance explanations) 9
  • 11. Copyright © 2014 by ScottMadden, Inc. All rights reserved. San Diego Gas & Electric Case Study – California: Background Utility San Diego Gas & Electric Rate Year 2012 MYRP Type Hybrid – Fixed % Based on Cost Projections Tied to an Index Length of Plan Four Years Terms Component Requested Awarded Award Rate Year $237.5M $123.4M Year 2 Unable to Discern 2.65% Increase Year 3 Unable to Discern 2.75% Increase Year 4 Unable to Discern 2.75% Increase ROE N/A* 10.7% Profit Sharing 60/40 for RD&D Revenues (Cust./Utility) 75/25 for RD&D Revenues (Cust./Utility) Key Takeaways from the Order ◼ SDG&E required to update reliability performance metrics and targets ◼ Includes allowances for two-way accounts in a number of categories, e.g., compliance with certain EPA rules, energy storage, transmission and distribution integrity management programs ◼ SDG&E must provide detailed accounting of and justification for AFUDC in next case ◼ SDG&E used a five-year average (2005–2009) as the basis for all cost forecasting • Opponents suggested the use of the most recent recorded data is more appropriate • Commission ruled that it depends on the cost center and each should be considered separately ◼ SDG&E proposed post-test year (PTY) adjustment mechanism that included six components: O&M adjustment, capital-related cost adjustment, medical cost adjustment, Z-factor adjustment if applicable, earnings sharing mechanism, and productivity investment sharing mechanism • The Commission elected to simplify and use one PTY adjustment mechanism established ahead of time and based on CPI – Urban index * ROE is settled in a separate proceeding in California Sources: California Public Utilities Commission; SNL 10
  • 12. Copyright © 2014 by ScottMadden, Inc. All rights reserved. Legislation Leads to Commission Order ◼ Minnesota legislature authorized the commission to approve MYRPs in 2011 with Minn. Stat. 216B.16, subd. 19 ◼ Commission solicited and received comments on appropriate terms and conditions for MYRPs ◼ Commission met to consider the motion on April 4, 2013 ◼ Final order issued June 17, 2013 (Docket No. E,G-999/M-12-587)  Benefits and concerns associated with MYRPs (as noted in the order): ◼ The commission’s goal is to permit plans that generate sufficient benefits to outweigh concerns and justify the burdens of plan administration Minnesota PUC Authorizes MYRPs Case Study – Minnesota: Source: Order Establishing Terms, Conditions, and Procedures for Multiyear Rate Plans: MNPUC, June 17, 2013 Benefits Concerns ◼ Reduced regulatory lag ◼ Reduced financing costs ◼ Reduced need for rate cases and other riders ◼ More predictable utility bills (gradual rate changes) ◼ Reduced rate shock ◼ Difficulty of accurately forecasting costs and revenues ◼ Mismatch of relevant costs to relevant revenues ◼ Challenges associated with evaluation and administration of plans 11
  • 13. Copyright © 2014 by ScottMadden, Inc. All rights reserved. ◼ The following table summarizes the outcome of MPUC deliberations on the various parameters of MYRPs under consideration: Key Structural Decisions Case Study – Minnesota: Item Options Proposed Commission Decision Rationale Procedural Context ◼ File MYRP within context of general rate case ◼ File shortly after rate case when factual record is still fresh ◼ File plan to coincide with capital project File MYRP within context of general rate case Evaluation of MYRP presents same challenges as general rate case and more. General rate case process provides best foundation for meeting challenges Subsequent Rate Cases ◼ Utilities seeking approval of MYRP must agree to forego any rate case filings throughout duration of MYRP Utilities will not be permitted to file a new rate case until MYRP has expired Evaluation of MYRP creates additional challenges in exchange for reduced regulatory burden. Filing a new rate case would force commission to incur the burdens without the benefits Formula Rates ◼ Specific rates for each year of plan ◼ Automatic formulas for annual rate adjustment Plans will specify fixed rates for each year of the plan. MYRPs that propose formula rates will not be approved Fixed multiyear rates allow prices to adjust over time but are based on fact-driven rate-making process and substantial evidence. Formulaic rates automatically pass through utility costs to customers and reduce incentive to manage costs Return on Equity ◼ Reduce ROE in each year of the plan ◼ Maintain same ROE throughout term of plan ◼ Address ROE on a case-by-case basis The established ROE will be used to determine rates for all years of MYRP Difficult to forecast changes in ROE over time. Doubtful benefits outweighed by burden of generating estimates Source: Order Establishing Terms, Conditions, and Procedures for Multiyear Rate Plans: MNPUC, June 17, 2013 12
  • 14. Copyright © 2014 by ScottMadden, Inc. All rights reserved. Key Structural Decisions (Cont’d) Case Study – Minnesota: Item Options Proposed Commission Decision Rationale Rate Riders and Differed Accounting ◼ Eliminate all riders (no longer necessary as need is met through MYRP) ◼ Consider riders on case-by-case basis Allow some riders on case-by-case basis. Push utilities to consolidate where possible, and under no circumstances allow double-dip recovery Not all supplemental cost-recovery categories are addressed in an MYRP (e.g., energy costs, emissions, conservation). Utilities should seize efficiencies where they can and prove in the filing that no costs are being recovered through both the MYRP and a rate rider Rates at Plan Expiration ◼ Require new rate case filing No decision. Commission will not specify how to determine rates, but the utility will be required to propose what those rates will be or how they will be calculated as part of the MYRP filing. The utility is certainly permitted to file a new rate case Commission Initiated Rate Change ◼ Imprudent rate increases should be subject to refund and utilities should waive any claim that such a decision would constitute retroactive rate making Imprudent rate increases will be subject to refund and utilities must waive any claim that such a decision would constitute retroactive rate making Follows from language of Minn. Stat. 216B.16 Plan Duration ◼ Two-year maximum (until experience is gained) ◼ Three-year maximum or even longer Three-year maximum (term will begin on effective date of new rates) Commission sees no reason to preclude consideration of three-year plans as specified in the statute. Further, given the administrative burdens, commission sees no reason to limit the period over which parties hope to reap the benefits of MYRP Source: Order Establishing Terms, Conditions, and Procedures for Multiyear Rate Plans: MNPUC, June 17, 2013 13
  • 15. Copyright © 2014 by ScottMadden, Inc. All rights reserved. ◼ Additional scrutiny  MYRPs involve setting rates based on planned capital expenditures rather than reimbursing investments already made. Therefore, utilities must be prepared to provide more detailed information than what has been required in the past ◼ Budgeting and project management skills  Utilities must be able to show that investments were made according to the plan submitted at the time of the filing. Failure to adhere to the plan may result in refunds or other costly regulatory issues. Ability to budget properly and execute projects to plan is critical with MYRPs ◼ Project selection  Determining which projects to include in the plan can be challenging. Utilities should consider: – Size of projects (impact on revenue requirement) – Execution risk associated with projects (scope, schedule, and budget) ◼ Compliance  Compliance mechanisms will play a significant role in whether a MYRP is the best solution for a utility  Some specific issues that must be addressed include: – Threshold for determining rate refunds – Aggregate versus project-by-project approach – Internal surveillance – Reporting mechanisms Issues for Utilities Considering MYRPs 14
  • 16. Copyright © 2014 by ScottMadden, Inc. All rights reserved. We believe the use of MYRPs will continue to grow as utilities and commissions work to overcome the limitations of traditional ratemaking in order to balance the needs of the ratepayers and shareholders with the realities of operating and maintaining a safe, reliable, and sustainable power delivery system ◼ Business as usual is not sustainable in the current business environment ◼ MYRPs provide a promising strategy for addressing some of the regulatory challenges facing the industry ◼ Additional scrutiny associated with MYRPs means utilities will have to improve their budgeting and project management practices in order to be compliant and successfully earn the maximum allowable rate of return ◼ The success of early adopters will influence the direction of ratemaking across the country—utilities and commissions will be watching closely Conclusions Alternative regulatory mechanisms are in the early stages of development, and utilities have an opportunity to help shape the regulatory construct going forward. 15
  • 17. Copyright © 2014 by ScottMadden, Inc. All rights reserved. Richard D. Starkweather Partner and Regulatory Practice Leader ScottMadden, Inc. 2626 Glenwood Avenue Suite 480 Raleigh, NC 27608 rstarkweather@scottmadden.com O: 919-781-4191 M: 919-345-9871 ScottMadden, Inc. 2626 Glenwood Avenue Suite 480 Raleigh, NC 27608 pfowler@scottmadden.com O: 919-781-4191 M: 404-558-1609 Preston Fowler Director Contact Us 16 ScottMadden has helped several utilities develop the tools necessary to successfully develop and defend a multiyear rate plan filing. Please let us show you how we can help.