ID            Task      Task Name                     Duration   Start        Finish            Predecessors   05 Nov '12                  12 Nov '12               19 Nov '12
              Mode                                                                                             M T W T      F      S   S   M T W T      F   S   S   M T W T
     1                  Start Unit 4, 5 & 62          66 days    Tue 06/11/12 Tue 05/02/13
                        Assignment 2
     2                    Task 1                      8 days     Tue 06/11/12 Thu 15/11/12
     3                       A - Gant Chart           4 days     Tue 06/11/12 Fri 09/11/12
     4                       B - Schedule             2 days     Mon 12/11/12Tue 13/11/12 3
     5                       C - Risk Assessment      2 days     Wed          Thu 15/11/12 4
                                                                 14/11/12
     6                    Task 2                      19 days    Fri 16/11/12 Wed 12/12/12
     7                      A - Research              6 days     Fri 16/11/12 Fri 23/11/12
     8                      B - Primary Content       6 days     Mon          Mon          7
                            Research                             26/11/12     03/12/12
     9                      C - Planning              8 days     Mon 03/12/12Wed 12/12/12
     10                   Task 3                      20 days    Thu 13/12/12 Wed 09/01/13
     11                     A - Proposal              6 days     Thu 13/12/12 Thu 20/12/12
     12                     B - Pitch                 3 days     Mon 07/01/13Wed 09/01/13
     13                   Task 4                      3 days     Thu 10/01/13 Mon 14/01/13
     14                     A - Production            3 days     Thu 10/01/13 Mon
                            Meeting                                           14/01/13
     15                   Task 5                      5 days     Tue 15/01/13 Mon 21/01/13
     16                     A - Video Assets          5 days     Tue 15/01/13 Mon 21/01/13
     17                   Task 6                      7 days     Tue 22/01/13 Wed 30/01/13
     18                     A - Shoot Video           7 days     Tue 22/01/13 Wed 30/01/13
     19
     20                 Additional Buffer Time        2 days     Thu 31/01/13 Fri 01/02/13


                                    Task                                     External Milestone                       Manual Summary Rollup
                                    Split                                    Inactive Task                            Manual Summary

Project: Project Plan               Milestone                                Inactive Milestone                       Start-only
Date: Wed 07/11/12                  Summary                                  Inactive Summary                         Finish-only
                                    Project Summary                          Manual Task                              Deadline
                                    External Tasks                           Duration-only                            Progress

                                                                                       Page 1
ID            Task      Task Name                     Duration   Start        Finish            Predecessors   05 Nov '12                  12 Nov '12               19 Nov '12
              Mode                                                                                             M T W T      F      S   S   M T W T      F   S   S   M T W T
     21                 End Unit 4, 5, & 62           2 days     Mon          Tue 05/02/13
                        Assignment 2                             04/02/13
     22
     23                 Start Unit 4, 5, & 62         66 days    Mon          Mon
                        Assignment 3                             18/02/13     20/05/13
     24                   Task 1                      2 days     Mon 18/02/13Tue 19/02/13
     25                      A - Import Video         2 days     Mon          Tue 19/02/13
                             with Diary                          18/02/13
     26                   Task 2                      15 days    Wed 20/02/13Tue 12/03/13
     27                      A - Edit Video           15 days    Wed 20/02/13Tue 12/03/13
     28                   Task 3                      11 days    Wed 13/03/13Wed 27/03/13
     29                      A - Export Video         2 days     Wed 13/03/13Thu 14/03/13
     30                      B - Gather Feedback      4 days     Fri 15/03/13 Wed
                                                                              20/03/13
     31                     C - Create a Report       5 days     Thu 21/03/13 Wed 27/03/13
     32                   Task 4                      7 days     Thu 28/03/13 Fri 05/04/13
     33                     A - Create a              4 days     Thu 28/03/13 Tue 02/04/13
                            Questionnaire
     34                     B - End of Project        3 days     Wed          Fri 05/04/13
                            Meeting with Client                  03/04/13

     35                   Task 5                      10 days    Mon 08/04/13Fri 19/04/13
     36                     Evaluation                10 days    Mon 08/04/13Fri 19/04/13
     37


                                    Task                                     External Milestone                       Manual Summary Rollup
                                    Split                                    Inactive Task                            Manual Summary

Project: Project Plan               Milestone                                Inactive Milestone                       Start-only
Date: Wed 07/11/12                  Summary                                  Inactive Summary                         Finish-only
                                    Project Summary                          Manual Task                              Deadline
                                    External Tasks                           Duration-only                            Progress

                                                                                       Page 2
ID            Task      Task Name                     Duration   Start       Finish            Predecessors   05 Nov '12                  12 Nov '12               19 Nov '12
              Mode                                                                                            M T W T      F      S   S   M T W T      F   S   S   M T W T
     38                 End Unit 4, 5, & 62           2 days     Mon         Tue 23/04/13
                        Assignment 3                             22/04/13




                                    Task                                    External Milestone                       Manual Summary Rollup
                                    Split                                   Inactive Task                            Manual Summary

Project: Project Plan               Milestone                               Inactive Milestone                       Start-only
Date: Wed 07/11/12                  Summary                                 Inactive Summary                         Finish-only
                                    Project Summary                         Manual Task                              Deadline
                                    External Tasks                          Duration-only                            Progress

                                                                                      Page 3
ov '12                   26 Nov '12               03 Dec '12               10 Dec '12                    17 Dec '12                24 Dec '12                  31 Dec '12
         T   F   S   S   M T W T      F   S   S   M T W T      F   S   S   M T W        T   F   S    S   M T W T      F   S   S    M T W T         F   S   S   M T W T      F   S   S   M




                                          Task                                      External Milestone                            Manual Summary Rollup
                                          Split                                     Inactive Task                                 Manual Summary

         Project: Project Plan            Milestone                                 Inactive Milestone                            Start-only
         Date: Wed 07/11/12               Summary                                   Inactive Summary                              Finish-only
                                          Project Summary                           Manual Task                                   Deadline
                                          External Tasks                            Duration-only                                 Progress

                                                                                            Page 4
ov '12                   26 Nov '12               03 Dec '12               10 Dec '12                    17 Dec '12                24 Dec '12                  31 Dec '12
         T   F   S   S   M T W T      F   S   S   M T W T      F   S   S   M T W        T   F   S    S   M T W T      F   S   S    M T W T         F   S   S   M T W T      F   S   S   M




                                          Task                                      External Milestone                            Manual Summary Rollup
                                          Split                                     Inactive Task                                 Manual Summary

         Project: Project Plan            Milestone                                 Inactive Milestone                            Start-only
         Date: Wed 07/11/12               Summary                                   Inactive Summary                              Finish-only
                                          Project Summary                           Manual Task                                   Deadline
                                          External Tasks                            Duration-only                                 Progress

                                                                                            Page 5
ov '12                   26 Nov '12               03 Dec '12               10 Dec '12                    17 Dec '12                24 Dec '12                  31 Dec '12
         T   F   S   S   M T W T      F   S   S   M T W T      F   S   S   M T W        T   F   S    S   M T W T      F   S   S    M T W T         F   S   S   M T W T      F   S   S   M




                                          Task                                      External Milestone                            Manual Summary Rollup
                                          Split                                     Inactive Task                                 Manual Summary

         Project: Project Plan            Milestone                                 Inactive Milestone                            Start-only
         Date: Wed 07/11/12               Summary                                   Inactive Summary                              Finish-only
                                          Project Summary                           Manual Task                                   Deadline
                                          External Tasks                            Duration-only                                 Progress

                                                                                            Page 6
07 Jan '13                      14 Jan '13                 21 Jan '13               28 Jan '13                   04 Feb '13                    11 Feb '13               18 Feb '13
M T W T          F      S   S   M T W T       F   S    S   M T W T      F   S   S   M T W T          F   S   S   M T W T        F   S      S   M T W T      F   S   S   M T W T      F




                                      Task                                      External Milestone                            Manual Summary Rollup
                                      Split                                     Inactive Task                                 Manual Summary

Project: Project Plan                 Milestone                                 Inactive Milestone                            Start-only
Date: Wed 07/11/12                    Summary                                   Inactive Summary                              Finish-only
                                      Project Summary                           Manual Task                                   Deadline
                                      External Tasks                            Duration-only                                 Progress

                                                                                       Page 7
07 Jan '13                      14 Jan '13                 21 Jan '13               28 Jan '13                   04 Feb '13                    11 Feb '13               18 Feb '13
M T W T          F      S   S   M T W T       F   S    S   M T W T      F   S   S   M T W T          F   S   S   M T W T        F   S      S   M T W T      F   S   S   M T W T      F




                                      Task                                      External Milestone                            Manual Summary Rollup
                                      Split                                     Inactive Task                                 Manual Summary

Project: Project Plan                 Milestone                                 Inactive Milestone                            Start-only
Date: Wed 07/11/12                    Summary                                   Inactive Summary                              Finish-only
                                      Project Summary                           Manual Task                                   Deadline
                                      External Tasks                            Duration-only                                 Progress

                                                                                       Page 8
07 Jan '13                      14 Jan '13                 21 Jan '13               28 Jan '13                   04 Feb '13                    11 Feb '13               18 Feb '13
M T W T          F      S   S   M T W T       F   S    S   M T W T      F   S   S   M T W T          F   S   S   M T W T        F   S      S   M T W T      F   S   S   M T W T      F




                                      Task                                      External Milestone                            Manual Summary Rollup
                                      Split                                     Inactive Task                                 Manual Summary

Project: Project Plan                 Milestone                                 Inactive Milestone                            Start-only
Date: Wed 07/11/12                    Summary                                   Inactive Summary                              Finish-only
                                      Project Summary                           Manual Task                                   Deadline
                                      External Tasks                            Duration-only                                 Progress

                                                                                       Page 9
3               25 Feb '13               04 Mar '13                11 Mar '13                 18 Mar '13               25 Mar '13                 01 Apr '13                   08 Apr '13
    F   S   S   M T W T      F   S   S   M T W T       F   S   S   M T W T      F   S   S     M T W T      F   S   S   M T W T        F   S   S   M T W        T   F   S   S   M T




                                     Task                                   External Milestone                          Manual Summary Rollup
                                     Split                                  Inactive Task                               Manual Summary

    Project: Project Plan            Milestone                              Inactive Milestone                          Start-only
    Date: Wed 07/11/12               Summary                                Inactive Summary                            Finish-only
                                     Project Summary                        Manual Task                                 Deadline
                                     External Tasks                         Duration-only                               Progress

                                                                                    Page 10
3               25 Feb '13               04 Mar '13                11 Mar '13                 18 Mar '13               25 Mar '13                 01 Apr '13                   08 Apr '13
    F   S   S   M T W T      F   S   S   M T W T       F   S   S   M T W T      F   S   S     M T W T      F   S   S   M T W T        F   S   S   M T W        T   F   S   S   M T




                                     Task                                   External Milestone                          Manual Summary Rollup
                                     Split                                  Inactive Task                               Manual Summary

    Project: Project Plan            Milestone                              Inactive Milestone                          Start-only
    Date: Wed 07/11/12               Summary                                Inactive Summary                            Finish-only
                                     Project Summary                        Manual Task                                 Deadline
                                     External Tasks                         Duration-only                               Progress

                                                                                    Page 11
3               25 Feb '13               04 Mar '13                11 Mar '13                 18 Mar '13               25 Mar '13                 01 Apr '13                   08 Apr '13
    F   S   S   M T W T      F   S   S   M T W T       F   S   S   M T W T      F   S   S     M T W T      F   S   S   M T W T        F   S   S   M T W        T   F   S   S   M T




                                     Task                                   External Milestone                          Manual Summary Rollup
                                     Split                                  Inactive Task                               Manual Summary

    Project: Project Plan            Milestone                              Inactive Milestone                          Start-only
    Date: Wed 07/11/12               Summary                                Inactive Summary                            Finish-only
                                     Project Summary                        Manual Task                                 Deadline
                                     External Tasks                         Duration-only                               Progress

                                                                                    Page 12
08 Apr '13                     15 Apr '13                22 Apr '13               29 Apr '13                    06 May '13                  13 May '13               20 May '13
    T W T      F    S      S   M T W T      F   S   S    M T W T      F   S   S   M T W T          F    S   S   M T W T      F     S   S    M T W T      F   S   S   M T W T      F   S




                                        Task                                       External Milestone                            Manual Summary Rollup
                                        Split                                      Inactive Task                                 Manual Summary

   Project: Project Plan                Milestone                                  Inactive Milestone                            Start-only
   Date: Wed 07/11/12                   Summary                                    Inactive Summary                              Finish-only
                                        Project Summary                            Manual Task                                   Deadline
                                        External Tasks                             Duration-only                                 Progress

                                                                                         Page 13
08 Apr '13                     15 Apr '13                22 Apr '13               29 Apr '13                    06 May '13                  13 May '13               20 May '13
    T W T      F    S      S   M T W T      F   S   S    M T W T      F   S   S   M T W T          F    S   S   M T W T      F     S   S    M T W T      F   S   S   M T W T      F   S




                                        Task                                       External Milestone                            Manual Summary Rollup
                                        Split                                      Inactive Task                                 Manual Summary

   Project: Project Plan                Milestone                                  Inactive Milestone                            Start-only
   Date: Wed 07/11/12                   Summary                                    Inactive Summary                              Finish-only
                                        Project Summary                            Manual Task                                   Deadline
                                        External Tasks                             Duration-only                                 Progress

                                                                                         Page 14
08 Apr '13                     15 Apr '13                22 Apr '13               29 Apr '13                    06 May '13                  13 May '13               20 May '13
    T W T      F    S      S   M T W T      F   S   S    M T W T      F   S   S   M T W T          F    S   S   M T W T      F     S   S    M T W T      F   S   S   M T W T      F   S




                                        Task                                       External Milestone                            Manual Summary Rollup
                                        Split                                      Inactive Task                                 Manual Summary

   Project: Project Plan                Milestone                                  Inactive Milestone                            Start-only
   Date: Wed 07/11/12                   Summary                                    Inactive Summary                              Finish-only
                                        Project Summary                            Manual Task                                   Deadline
                                        External Tasks                             Duration-only                                 Progress

                                                                                         Page 15

Gant chart

  • 1.
    ID Task Task Name Duration Start Finish Predecessors 05 Nov '12 12 Nov '12 19 Nov '12 Mode M T W T F S S M T W T F S S M T W T 1 Start Unit 4, 5 & 62 66 days Tue 06/11/12 Tue 05/02/13 Assignment 2 2 Task 1 8 days Tue 06/11/12 Thu 15/11/12 3 A - Gant Chart 4 days Tue 06/11/12 Fri 09/11/12 4 B - Schedule 2 days Mon 12/11/12Tue 13/11/12 3 5 C - Risk Assessment 2 days Wed Thu 15/11/12 4 14/11/12 6 Task 2 19 days Fri 16/11/12 Wed 12/12/12 7 A - Research 6 days Fri 16/11/12 Fri 23/11/12 8 B - Primary Content 6 days Mon Mon 7 Research 26/11/12 03/12/12 9 C - Planning 8 days Mon 03/12/12Wed 12/12/12 10 Task 3 20 days Thu 13/12/12 Wed 09/01/13 11 A - Proposal 6 days Thu 13/12/12 Thu 20/12/12 12 B - Pitch 3 days Mon 07/01/13Wed 09/01/13 13 Task 4 3 days Thu 10/01/13 Mon 14/01/13 14 A - Production 3 days Thu 10/01/13 Mon Meeting 14/01/13 15 Task 5 5 days Tue 15/01/13 Mon 21/01/13 16 A - Video Assets 5 days Tue 15/01/13 Mon 21/01/13 17 Task 6 7 days Tue 22/01/13 Wed 30/01/13 18 A - Shoot Video 7 days Tue 22/01/13 Wed 30/01/13 19 20 Additional Buffer Time 2 days Thu 31/01/13 Fri 01/02/13 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 1
  • 2.
    ID Task Task Name Duration Start Finish Predecessors 05 Nov '12 12 Nov '12 19 Nov '12 Mode M T W T F S S M T W T F S S M T W T 21 End Unit 4, 5, & 62 2 days Mon Tue 05/02/13 Assignment 2 04/02/13 22 23 Start Unit 4, 5, & 62 66 days Mon Mon Assignment 3 18/02/13 20/05/13 24 Task 1 2 days Mon 18/02/13Tue 19/02/13 25 A - Import Video 2 days Mon Tue 19/02/13 with Diary 18/02/13 26 Task 2 15 days Wed 20/02/13Tue 12/03/13 27 A - Edit Video 15 days Wed 20/02/13Tue 12/03/13 28 Task 3 11 days Wed 13/03/13Wed 27/03/13 29 A - Export Video 2 days Wed 13/03/13Thu 14/03/13 30 B - Gather Feedback 4 days Fri 15/03/13 Wed 20/03/13 31 C - Create a Report 5 days Thu 21/03/13 Wed 27/03/13 32 Task 4 7 days Thu 28/03/13 Fri 05/04/13 33 A - Create a 4 days Thu 28/03/13 Tue 02/04/13 Questionnaire 34 B - End of Project 3 days Wed Fri 05/04/13 Meeting with Client 03/04/13 35 Task 5 10 days Mon 08/04/13Fri 19/04/13 36 Evaluation 10 days Mon 08/04/13Fri 19/04/13 37 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 2
  • 3.
    ID Task Task Name Duration Start Finish Predecessors 05 Nov '12 12 Nov '12 19 Nov '12 Mode M T W T F S S M T W T F S S M T W T 38 End Unit 4, 5, & 62 2 days Mon Tue 23/04/13 Assignment 3 22/04/13 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 3
  • 4.
    ov '12 26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12 T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 4
  • 5.
    ov '12 26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12 T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 5
  • 6.
    ov '12 26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12 T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 6
  • 7.
    07 Jan '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13 18 Feb '13 M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 7
  • 8.
    07 Jan '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13 18 Feb '13 M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 8
  • 9.
    07 Jan '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13 18 Feb '13 M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 9
  • 10.
    3 25 Feb '13 04 Mar '13 11 Mar '13 18 Mar '13 25 Mar '13 01 Apr '13 08 Apr '13 F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 10
  • 11.
    3 25 Feb '13 04 Mar '13 11 Mar '13 18 Mar '13 25 Mar '13 01 Apr '13 08 Apr '13 F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 11
  • 12.
    3 25 Feb '13 04 Mar '13 11 Mar '13 18 Mar '13 25 Mar '13 01 Apr '13 08 Apr '13 F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 12
  • 13.
    08 Apr '13 15 Apr '13 22 Apr '13 29 Apr '13 06 May '13 13 May '13 20 May '13 T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 13
  • 14.
    08 Apr '13 15 Apr '13 22 Apr '13 29 Apr '13 06 May '13 13 May '13 20 May '13 T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 14
  • 15.
    08 Apr '13 15 Apr '13 22 Apr '13 29 Apr '13 06 May '13 13 May '13 20 May '13 T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 15