SlideShare a Scribd company logo
ID            Task      Task Name                     Duration   Start        Finish            05 Nov '12                   12 Nov '12                    19 Nov '12
              Mode                                                                              M T W        T   F   S   S   M T W         T   F   S   S   M T W        T   F   S   S   M
     1                  Start Unit 4, 5 & 62          66 days    Tue 06/11/12 Tue 05/02/13
                        Assignment 2
     2                    Task 1                      8 days     Tue 06/11/12 Thu 15/11/12
     3                       A - Gant Chart           4 days     Tue 06/11/12 Fri 09/11/12
     4                       B - Schedule             2 days     Mon 12/11/12Tue 13/11/12
     5                       C - Risk Assessment      2 days     Wed          Thu 15/11/12
                                                                 14/11/12
     6                    Task 2                      19 days    Fri 16/11/12 Wed 12/12/12
     7                      A - Research              6 days     Fri 16/11/12 Fri 23/11/12
     8                      B - Primary Content       6 days     Mon          Mon
                            Research                             26/11/12     03/12/12
     9                      C - Planning              8 days     Mon 03/12/12Wed 12/12/12
     10                   Task 3                      20 days    Thu 13/12/12 Wed 09/01/13
     11                     A - Proposal              6 days     Thu 13/12/12 Thu 20/12/12
     12                     B - Pitch                 3 days     Mon 07/01/13Wed 09/01/13
     13                   Task 4                      3 days     Thu 10/01/13 Mon 14/01/13
     14                     A - Production            3 days     Thu 10/01/13 Mon
                            Meeting                                           14/01/13
     15                   Task 5                      5 days     Tue 15/01/13 Mon 21/01/13
     16                     A - Video Assets          5 days     Tue 15/01/13 Mon 21/01/13
     17                   Task 6                      7 days     Tue 22/01/13 Wed 30/01/13
     18                     A - Shoot Video           7 days     Tue 22/01/13 Wed 30/01/13
     19
     20                 Additional Buffer Time        2 days     Thu 31/01/13 Fri 01/02/13


                                    Task                                     External Milestone                              Manual Summary Rollup
                                    Split                                    Inactive Task                                   Manual Summary

Project: Project Plan               Milestone                                Inactive Milestone                              Start-only
Date: Wed 07/11/12                  Summary                                  Inactive Summary                                Finish-only
                                    Project Summary                          Manual Task                                     Deadline
                                    External Tasks                           Duration-only                                   Progress

                                                                                       Page 1
ID            Task      Task Name                     Duration   Start        Finish            05 Nov '12                   12 Nov '12                    19 Nov '12
              Mode                                                                              M T W        T   F   S   S   M T W         T   F   S   S   M T W        T   F   S   S   M
     21                 End Unit 4, 5, & 62           2 days     Mon          Tue 05/02/13
                        Assignment 2                             04/02/13
     22
     23                 Start Unit 4, 5, & 62         66 days    Mon          Mon
                        Assignment 3                             18/02/13     20/05/13
     24                   Task 1                      2 days     Mon 18/02/13Tue 19/02/13
     25                      A - Import Video         2 days     Mon          Tue 19/02/13
                             with Diary                          18/02/13
     26                   Task 2                      15 days    Wed 20/02/13Tue 12/03/13
     27                      A - Edit Video           15 days    Wed 20/02/13Tue 12/03/13
     28                   Task 3                      11 days    Wed 13/03/13Wed 27/03/13
     29                      A - Export Video         2 days     Wed 13/03/13Thu 14/03/13
     30                      B - Gather Feedback      4 days     Fri 15/03/13 Wed
                                                                              20/03/13
     31                     C - Create a Report       5 days     Thu 21/03/13 Wed 27/03/13
     32                   Task 4                      7 days     Thu 28/03/13 Fri 05/04/13
     33                     A - Create a              4 days     Thu 28/03/13 Tue 02/04/13
                            Questionnaire
     34                     B - End of Project        3 days     Wed          Fri 05/04/13
                            Meeting with Client                  03/04/13

     35                   Task 5                      10 days    Mon 08/04/13Fri 19/04/13
     36                     Evaluation                10 days    Mon 08/04/13Fri 19/04/13
     37


                                    Task                                     External Milestone                              Manual Summary Rollup
                                    Split                                    Inactive Task                                   Manual Summary

Project: Project Plan               Milestone                                Inactive Milestone                              Start-only
Date: Wed 07/11/12                  Summary                                  Inactive Summary                                Finish-only
                                    Project Summary                          Manual Task                                     Deadline
                                    External Tasks                           Duration-only                                   Progress

                                                                                       Page 2
ID            Task      Task Name                     Duration   Start       Finish            05 Nov '12                   12 Nov '12                    19 Nov '12
              Mode                                                                             M T W        T   F   S   S   M T W         T   F   S   S   M T W        T   F   S   S   M
     38                 End Unit 4, 5, & 62           2 days     Mon         Tue 23/04/13
                        Assignment 3                             22/04/13




                                    Task                                    External Milestone                              Manual Summary Rollup
                                    Split                                   Inactive Task                                   Manual Summary

Project: Project Plan               Milestone                               Inactive Milestone                              Start-only
Date: Wed 07/11/12                  Summary                                 Inactive Summary                                Finish-only
                                    Project Summary                         Manual Task                                     Deadline
                                    External Tasks                          Duration-only                                   Progress

                                                                                      Page 3
26 Nov '12                      03 Dec '12                     10 Dec '12                   17 Dec '12                   24 Dec '12                      31 Dec '12                   07 Jan '13
M T W        T   F      S   S   M T W          T   F   S   S   M T W        T   F   S   S   M T W        T   F   S   S   M T W        T   F      S   S   M T W        T   F   S   S   M T W        T




                                       Task                                             External Milestone                            Manual Summary Rollup
                                       Split                                            Inactive Task                                 Manual Summary

Project: Project Plan                  Milestone                                        Inactive Milestone                            Start-only
Date: Wed 07/11/12                     Summary                                          Inactive Summary                              Finish-only
                                       Project Summary                                  Manual Task                                   Deadline
                                       External Tasks                                   Duration-only                                 Progress

                                                                                               Page 4
26 Nov '12                      03 Dec '12                     10 Dec '12                   17 Dec '12                   24 Dec '12                      31 Dec '12                   07 Jan '13
M T W        T   F      S   S   M T W          T   F   S   S   M T W        T   F   S   S   M T W        T   F   S   S   M T W        T   F      S   S   M T W        T   F   S   S   M T W        T




                                       Task                                             External Milestone                            Manual Summary Rollup
                                       Split                                            Inactive Task                                 Manual Summary

Project: Project Plan                  Milestone                                        Inactive Milestone                            Start-only
Date: Wed 07/11/12                     Summary                                          Inactive Summary                              Finish-only
                                       Project Summary                                  Manual Task                                   Deadline
                                       External Tasks                                   Duration-only                                 Progress

                                                                                               Page 5
26 Nov '12                      03 Dec '12                     10 Dec '12                   17 Dec '12                   24 Dec '12                      31 Dec '12                   07 Jan '13
M T W        T   F      S   S   M T W          T   F   S   S   M T W        T   F   S   S   M T W        T   F   S   S   M T W        T   F      S   S   M T W        T   F   S   S   M T W        T




                                       Task                                             External Milestone                            Manual Summary Rollup
                                       Split                                            Inactive Task                                 Manual Summary

Project: Project Plan                  Milestone                                        Inactive Milestone                            Start-only
Date: Wed 07/11/12                     Summary                                          Inactive Summary                              Finish-only
                                       Project Summary                                  Manual Task                                   Deadline
                                       External Tasks                                   Duration-only                                 Progress

                                                                                               Page 6
n '13                    14 Jan '13                       21 Jan '13                   28 Jan '13                     04 Feb '13                   11 Feb '13                   18 Feb '13
        T   F   S    S   M T W        T   F   S       S   M T W        T   F   S   S   M T W        T    F    S   S   M T W        T   F   S   S   M T W        T   F   S   S   M T W        T   F   S   S




                                              Task                                            External Milestone                               Manual Summary Rollup
                                              Split                                           Inactive Task                                    Manual Summary

        Project: Project Plan                 Milestone                                       Inactive Milestone                               Start-only
        Date: Wed 07/11/12                    Summary                                         Inactive Summary                                 Finish-only
                                              Project Summary                                 Manual Task                                      Deadline
                                              External Tasks                                  Duration-only                                    Progress

                                                                                                        Page 7
n '13                    14 Jan '13                       21 Jan '13                   28 Jan '13                     04 Feb '13                   11 Feb '13                   18 Feb '13
        T   F   S    S   M T W        T   F   S       S   M T W        T   F   S   S   M T W        T    F    S   S   M T W        T   F   S   S   M T W        T   F   S   S   M T W        T   F   S   S




                                              Task                                            External Milestone                               Manual Summary Rollup
                                              Split                                           Inactive Task                                    Manual Summary

        Project: Project Plan                 Milestone                                       Inactive Milestone                               Start-only
        Date: Wed 07/11/12                    Summary                                         Inactive Summary                                 Finish-only
                                              Project Summary                                 Manual Task                                      Deadline
                                              External Tasks                                  Duration-only                                    Progress

                                                                                                        Page 8
n '13                    14 Jan '13                       21 Jan '13                   28 Jan '13                     04 Feb '13                   11 Feb '13                   18 Feb '13
        T   F   S    S   M T W        T   F   S       S   M T W        T   F   S   S   M T W        T    F    S   S   M T W        T   F   S   S   M T W        T   F   S   S   M T W        T   F   S   S




                                              Task                                            External Milestone                               Manual Summary Rollup
                                              Split                                           Inactive Task                                    Manual Summary

        Project: Project Plan                 Milestone                                       Inactive Milestone                               Start-only
        Date: Wed 07/11/12                    Summary                                         Inactive Summary                                 Finish-only
                                              Project Summary                                 Manual Task                                      Deadline
                                              External Tasks                                  Duration-only                                    Progress

                                                                                                        Page 9
25 Feb '13                      04 Mar '13                   11 Mar '13                    18 Mar '13                   25 Mar '13                    01 Apr '13                   08 Apr '13
S   M T W        T      F   S   S   M T W        T   F   S   S   M T W        T   F   S   S    M T W        T   F   S   S   M T W        T    F   S   S   M T W        T   F   S   S   M T W




                                       Task                                           External Milestone                           Manual Summary Rollup
                                       Split                                          Inactive Task                                Manual Summary

Project: Project Plan                  Milestone                                      Inactive Milestone                           Start-only
Date: Wed 07/11/12                     Summary                                        Inactive Summary                             Finish-only
                                       Project Summary                                Manual Task                                  Deadline
                                       External Tasks                                 Duration-only                                Progress

                                                                                              Page 10
25 Feb '13                      04 Mar '13                   11 Mar '13                    18 Mar '13                   25 Mar '13                    01 Apr '13                   08 Apr '13
S   M T W        T      F   S   S   M T W        T   F   S   S   M T W        T   F   S   S    M T W        T   F   S   S   M T W        T    F   S   S   M T W        T   F   S   S   M T W




                                       Task                                           External Milestone                           Manual Summary Rollup
                                       Split                                          Inactive Task                                Manual Summary

Project: Project Plan                  Milestone                                      Inactive Milestone                           Start-only
Date: Wed 07/11/12                     Summary                                        Inactive Summary                             Finish-only
                                       Project Summary                                Manual Task                                  Deadline
                                       External Tasks                                 Duration-only                                Progress

                                                                                              Page 11
25 Feb '13                      04 Mar '13                   11 Mar '13                    18 Mar '13                   25 Mar '13                    01 Apr '13                   08 Apr '13
S   M T W        T      F   S   S   M T W        T   F   S   S   M T W        T   F   S   S    M T W        T   F   S   S   M T W        T    F   S   S   M T W        T   F   S   S   M T W




                                       Task                                           External Milestone                           Manual Summary Rollup
                                       Split                                          Inactive Task                                Manual Summary

Project: Project Plan                  Milestone                                      Inactive Milestone                           Start-only
Date: Wed 07/11/12                     Summary                                        Inactive Summary                             Finish-only
                                       Project Summary                                Manual Task                                  Deadline
                                       External Tasks                                 Duration-only                                Progress

                                                                                              Page 12
8 Apr '13                   15 Apr '13                       22 Apr '13                   29 Apr '13                     06 May '13               13 May '13                  20 May '13
        W   T   F   S   S   M T W        T   F       S   S   M T W        T   F   S   S   M T W        T     F   S   S   M T W T      F   S   S   M T W T         F   S   S   M T W T      F   S




                                             Task                                            External Milestone                           Manual Summary Rollup
                                             Split                                           Inactive Task                                Manual Summary

       Project: Project Plan                 Milestone                                       Inactive Milestone                           Start-only
       Date: Wed 07/11/12                    Summary                                         Inactive Summary                             Finish-only
                                             Project Summary                                 Manual Task                                  Deadline
                                             External Tasks                                  Duration-only                                Progress

                                                                                                   Page 13
8 Apr '13                   15 Apr '13                       22 Apr '13                   29 Apr '13                     06 May '13               13 May '13                  20 May '13
        W   T   F   S   S   M T W        T   F       S   S   M T W        T   F   S   S   M T W        T     F   S   S   M T W T      F   S   S   M T W T         F   S   S   M T W T      F   S




                                             Task                                            External Milestone                           Manual Summary Rollup
                                             Split                                           Inactive Task                                Manual Summary

       Project: Project Plan                 Milestone                                       Inactive Milestone                           Start-only
       Date: Wed 07/11/12                    Summary                                         Inactive Summary                             Finish-only
                                             Project Summary                                 Manual Task                                  Deadline
                                             External Tasks                                  Duration-only                                Progress

                                                                                                   Page 14
8 Apr '13                   15 Apr '13                       22 Apr '13                   29 Apr '13                     06 May '13               13 May '13                  20 May '13
        W   T   F   S   S   M T W        T   F       S   S   M T W        T   F   S   S   M T W        T     F   S   S   M T W T      F   S   S   M T W T         F   S   S   M T W T      F   S




                                             Task                                            External Milestone                           Manual Summary Rollup
                                             Split                                           Inactive Task                                Manual Summary

       Project: Project Plan                 Milestone                                       Inactive Milestone                           Start-only
       Date: Wed 07/11/12                    Summary                                         Inactive Summary                             Finish-only
                                             Project Summary                                 Manual Task                                  Deadline
                                             External Tasks                                  Duration-only                                Progress

                                                                                                   Page 15

More Related Content

Viewers also liked

Financial Education Services Un Mundo De Oportunidad
Financial Education Services Un Mundo De OportunidadFinancial Education Services Un Mundo De Oportunidad
Financial Education Services Un Mundo De Oportunidad
guestc13de1d1
 
Sessió Cloud a Microblau
Sessió Cloud a MicroblauSessió Cloud a Microblau
Sessió Cloud a Microblau
Microblau
 
Bike Anjo Brasil. Formas de atuação em rede para a discussão das bicicletas
Bike Anjo Brasil. Formas de atuação em rede para a discussão das bicicletasBike Anjo Brasil. Formas de atuação em rede para a discussão das bicicletas
Bike Anjo Brasil. Formas de atuação em rede para a discussão das bicicletas
ongciclourbano
 
L'hort de l'escola mtm
L'hort de l'escola  mtmL'hort de l'escola  mtm
L'hort de l'escola mtm
GarciaFossas
 
La salud y el deporte neli
La salud y el deporte neliLa salud y el deporte neli
La salud y el deporte neliluis
 
Jacobo Ochoa Velasquez
Jacobo Ochoa VelasquezJacobo Ochoa Velasquez
Jacobo Ochoa Velasquezyako89
 
Letter of Thanks_Artic Coop
Letter of Thanks_Artic CoopLetter of Thanks_Artic Coop
Letter of Thanks_Artic CoopKurt Santos
 
Definicion De Fuerza
Definicion De FuerzaDefinicion De Fuerza
Definicion De Fuerzajordin
 
DEMOSTRACION EDUCATIVA I "D" 28JUN2011
DEMOSTRACION EDUCATIVA I "D"  28JUN2011DEMOSTRACION EDUCATIVA I "D"  28JUN2011
DEMOSTRACION EDUCATIVA I "D" 28JUN2011Om Seto
 
Boletim Fique Por Dentro n.01
Boletim Fique Por Dentro n.01Boletim Fique Por Dentro n.01
Boletim Fique Por Dentro n.01
Centro Universitário do Norte
 
Aden assuncao dissertacao
Aden assuncao dissertacaoAden assuncao dissertacao
Aden assuncao dissertacao
moratonoise
 
Órganos de los sentidos
Órganos de los sentidos Órganos de los sentidos
Órganos de los sentidos
gualalupe1980
 
ICN No To The Exploitation of Child Labour Webinar
ICN No To The Exploitation of Child Labour WebinarICN No To The Exploitation of Child Labour Webinar
ICN No To The Exploitation of Child Labour Webinar
icn-rcc
 
Body Memory and Affectivity
Body Memory and AffectivityBody Memory and Affectivity
Body Memory and Affectivity
TheHumanMindProject
 

Viewers also liked (19)

Schedule
ScheduleSchedule
Schedule
 
Financial Education Services Un Mundo De Oportunidad
Financial Education Services Un Mundo De OportunidadFinancial Education Services Un Mundo De Oportunidad
Financial Education Services Un Mundo De Oportunidad
 
Sessió Cloud a Microblau
Sessió Cloud a MicroblauSessió Cloud a Microblau
Sessió Cloud a Microblau
 
Bike Anjo Brasil. Formas de atuação em rede para a discussão das bicicletas
Bike Anjo Brasil. Formas de atuação em rede para a discussão das bicicletasBike Anjo Brasil. Formas de atuação em rede para a discussão das bicicletas
Bike Anjo Brasil. Formas de atuação em rede para a discussão das bicicletas
 
L'hort de l'escola mtm
L'hort de l'escola  mtmL'hort de l'escola  mtm
L'hort de l'escola mtm
 
La salud y el deporte neli
La salud y el deporte neliLa salud y el deporte neli
La salud y el deporte neli
 
Jacobo Ochoa Velasquez
Jacobo Ochoa VelasquezJacobo Ochoa Velasquez
Jacobo Ochoa Velasquez
 
Friohielo
FriohieloFriohielo
Friohielo
 
Fisica ii
Fisica iiFisica ii
Fisica ii
 
Letter of Thanks_Artic Coop
Letter of Thanks_Artic CoopLetter of Thanks_Artic Coop
Letter of Thanks_Artic Coop
 
Definicion De Fuerza
Definicion De FuerzaDefinicion De Fuerza
Definicion De Fuerza
 
Testimonials 2.1
Testimonials 2.1Testimonials 2.1
Testimonials 2.1
 
DEMOSTRACION EDUCATIVA I "D" 28JUN2011
DEMOSTRACION EDUCATIVA I "D"  28JUN2011DEMOSTRACION EDUCATIVA I "D"  28JUN2011
DEMOSTRACION EDUCATIVA I "D" 28JUN2011
 
Boletim Fique Por Dentro n.01
Boletim Fique Por Dentro n.01Boletim Fique Por Dentro n.01
Boletim Fique Por Dentro n.01
 
Aden assuncao dissertacao
Aden assuncao dissertacaoAden assuncao dissertacao
Aden assuncao dissertacao
 
Órganos de los sentidos
Órganos de los sentidos Órganos de los sentidos
Órganos de los sentidos
 
ICN No To The Exploitation of Child Labour Webinar
ICN No To The Exploitation of Child Labour WebinarICN No To The Exploitation of Child Labour Webinar
ICN No To The Exploitation of Child Labour Webinar
 
Body Memory and Affectivity
Body Memory and AffectivityBody Memory and Affectivity
Body Memory and Affectivity
 
Marimar
MarimarMarimar
Marimar
 

Similar to Gant chart

Project outline
Project outlineProject outline
Project outlineCrashin
 
Project schedule
Project scheduleProject schedule
Project schedulems72527
 
Project plan
Project planProject plan
Project planLS66731
 
Project plan
Project planProject plan
Project planinwill12
 
Gnatt chart outlining project
Gnatt chart outlining projectGnatt chart outlining project
Gnatt chart outlining projectms72527
 
Project1gantt
Project1ganttProject1gantt
Project1gantt
jmo46
 
High level project plan with dependencies
High level project plan with dependenciesHigh level project plan with dependencies
High level project plan with dependencies
MADS Board
 
Verbe planning v1
Verbe planning v1Verbe planning v1
Verbe planning v1vudt1990
 
Verbe planning
Verbe planningVerbe planning
Verbe planning
vudt1990
 
Verbe planning
Verbe planningVerbe planning
Verbe planning
dangtuanvu1990
 
Engineering and Permitting Schedule
Engineering and Permitting ScheduleEngineering and Permitting Schedule
Engineering and Permitting ScheduleHonolulu Civil Beat
 
Town School for Boys Master Schedule
Town School for Boys Master ScheduleTown School for Boys Master Schedule
Town School for Boys Master ScheduleMKThink Strategy
 
Task 2 schedule all
Task 2   schedule allTask 2   schedule all
Task 2 schedule allMrrrjones
 
Microsoft project tugas 1
Microsoft project   tugas 1Microsoft project   tugas 1
Microsoft project tugas 1
Tri Atsumori
 
Task 2 schedule all
Task 2   schedule allTask 2   schedule all
Task 2 schedule allMrrrjones
 
Shneha single page
Shneha single pageShneha single page
Shneha single pageshneha patel
 
- Project.pdf
- Project.pdf- Project.pdf
- Project.pdf
Hemin Refiq
 

Similar to Gant chart (20)

Project outline
Project outlineProject outline
Project outline
 
Project schedule
Project scheduleProject schedule
Project schedule
 
Project plan
Project planProject plan
Project plan
 
Project plan
Project planProject plan
Project plan
 
Gnatt chart outlining project
Gnatt chart outlining projectGnatt chart outlining project
Gnatt chart outlining project
 
Project10.mpp
Project10.mppProject10.mpp
Project10.mpp
 
Gant chart
Gant chartGant chart
Gant chart
 
Project1gantt
Project1ganttProject1gantt
Project1gantt
 
High level project plan with dependencies
High level project plan with dependenciesHigh level project plan with dependencies
High level project plan with dependencies
 
Verbe planning v1
Verbe planning v1Verbe planning v1
Verbe planning v1
 
Verbe planning
Verbe planningVerbe planning
Verbe planning
 
Verbe planning
Verbe planningVerbe planning
Verbe planning
 
Engineering and Permitting Schedule
Engineering and Permitting ScheduleEngineering and Permitting Schedule
Engineering and Permitting Schedule
 
Town School for Boys Master Schedule
Town School for Boys Master ScheduleTown School for Boys Master Schedule
Town School for Boys Master Schedule
 
Task 2 schedule all
Task 2   schedule allTask 2   schedule all
Task 2 schedule all
 
Complete schedule
Complete scheduleComplete schedule
Complete schedule
 
Microsoft project tugas 1
Microsoft project   tugas 1Microsoft project   tugas 1
Microsoft project tugas 1
 
Task 2 schedule all
Task 2   schedule allTask 2   schedule all
Task 2 schedule all
 
Shneha single page
Shneha single pageShneha single page
Shneha single page
 
- Project.pdf
- Project.pdf- Project.pdf
- Project.pdf
 

More from heather1405

Exporting digital video for interactive media products
Exporting digital video for interactive media productsExporting digital video for interactive media products
Exporting digital video for interactive media productsheather1405
 
Post production workspace
Post production workspacePost production workspace
Post production workspaceheather1405
 
Post production workspace
Post production workspacePost production workspace
Post production workspaceheather1405
 
Shooting video assets
Shooting video assetsShooting video assets
Shooting video assetsheather1405
 
Team meeting two minutes (1)
Team meeting two   minutes (1)Team meeting two   minutes (1)
Team meeting two minutes (1)heather1405
 
Team meeting two agenda (2)
Team meeting two   agenda (2)Team meeting two   agenda (2)
Team meeting two agenda (2)heather1405
 
Short report of our pitch presentation meeting
Short report of our pitch presentation meetingShort report of our pitch presentation meeting
Short report of our pitch presentation meetingheather1405
 
Client pitch minutes
Client pitch   minutesClient pitch   minutes
Client pitch minutesheather1405
 
Client pitch agenda
Client pitch   agendaClient pitch   agenda
Client pitch agendaheather1405
 

More from heather1405 (20)

Exporting digital video for interactive media products
Exporting digital video for interactive media productsExporting digital video for interactive media products
Exporting digital video for interactive media products
 
Evaluation
EvaluationEvaluation
Evaluation
 
Post production workspace
Post production workspacePost production workspace
Post production workspace
 
Post production workspace
Post production workspacePost production workspace
Post production workspace
 
Questionnaire
QuestionnaireQuestionnaire
Questionnaire
 
Final minutes
Final minutesFinal minutes
Final minutes
 
Final agenda
Final agendaFinal agenda
Final agenda
 
Diary
DiaryDiary
Diary
 
Shot log
Shot logShot log
Shot log
 
Shooting video assets
Shooting video assetsShooting video assets
Shooting video assets
 
Shot log
Shot logShot log
Shot log
 
The pitch
The pitchThe pitch
The pitch
 
Team meeting two minutes (1)
Team meeting two   minutes (1)Team meeting two   minutes (1)
Team meeting two minutes (1)
 
Team meeting two agenda (2)
Team meeting two   agenda (2)Team meeting two   agenda (2)
Team meeting two agenda (2)
 
Short report of our pitch presentation meeting
Short report of our pitch presentation meetingShort report of our pitch presentation meeting
Short report of our pitch presentation meeting
 
Proposal
ProposalProposal
Proposal
 
Client pitch minutes
Client pitch   minutesClient pitch   minutes
Client pitch minutes
 
Client pitch agenda
Client pitch   agendaClient pitch   agenda
Client pitch agenda
 
Assets table
Assets tableAssets table
Assets table
 
Proposal
ProposalProposal
Proposal
 

Gant chart

  • 1. ID Task Task Name Duration Start Finish 05 Nov '12 12 Nov '12 19 Nov '12 Mode M T W T F S S M T W T F S S M T W T F S S M 1 Start Unit 4, 5 & 62 66 days Tue 06/11/12 Tue 05/02/13 Assignment 2 2 Task 1 8 days Tue 06/11/12 Thu 15/11/12 3 A - Gant Chart 4 days Tue 06/11/12 Fri 09/11/12 4 B - Schedule 2 days Mon 12/11/12Tue 13/11/12 5 C - Risk Assessment 2 days Wed Thu 15/11/12 14/11/12 6 Task 2 19 days Fri 16/11/12 Wed 12/12/12 7 A - Research 6 days Fri 16/11/12 Fri 23/11/12 8 B - Primary Content 6 days Mon Mon Research 26/11/12 03/12/12 9 C - Planning 8 days Mon 03/12/12Wed 12/12/12 10 Task 3 20 days Thu 13/12/12 Wed 09/01/13 11 A - Proposal 6 days Thu 13/12/12 Thu 20/12/12 12 B - Pitch 3 days Mon 07/01/13Wed 09/01/13 13 Task 4 3 days Thu 10/01/13 Mon 14/01/13 14 A - Production 3 days Thu 10/01/13 Mon Meeting 14/01/13 15 Task 5 5 days Tue 15/01/13 Mon 21/01/13 16 A - Video Assets 5 days Tue 15/01/13 Mon 21/01/13 17 Task 6 7 days Tue 22/01/13 Wed 30/01/13 18 A - Shoot Video 7 days Tue 22/01/13 Wed 30/01/13 19 20 Additional Buffer Time 2 days Thu 31/01/13 Fri 01/02/13 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 1
  • 2. ID Task Task Name Duration Start Finish 05 Nov '12 12 Nov '12 19 Nov '12 Mode M T W T F S S M T W T F S S M T W T F S S M 21 End Unit 4, 5, & 62 2 days Mon Tue 05/02/13 Assignment 2 04/02/13 22 23 Start Unit 4, 5, & 62 66 days Mon Mon Assignment 3 18/02/13 20/05/13 24 Task 1 2 days Mon 18/02/13Tue 19/02/13 25 A - Import Video 2 days Mon Tue 19/02/13 with Diary 18/02/13 26 Task 2 15 days Wed 20/02/13Tue 12/03/13 27 A - Edit Video 15 days Wed 20/02/13Tue 12/03/13 28 Task 3 11 days Wed 13/03/13Wed 27/03/13 29 A - Export Video 2 days Wed 13/03/13Thu 14/03/13 30 B - Gather Feedback 4 days Fri 15/03/13 Wed 20/03/13 31 C - Create a Report 5 days Thu 21/03/13 Wed 27/03/13 32 Task 4 7 days Thu 28/03/13 Fri 05/04/13 33 A - Create a 4 days Thu 28/03/13 Tue 02/04/13 Questionnaire 34 B - End of Project 3 days Wed Fri 05/04/13 Meeting with Client 03/04/13 35 Task 5 10 days Mon 08/04/13Fri 19/04/13 36 Evaluation 10 days Mon 08/04/13Fri 19/04/13 37 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 2
  • 3. ID Task Task Name Duration Start Finish 05 Nov '12 12 Nov '12 19 Nov '12 Mode M T W T F S S M T W T F S S M T W T F S S M 38 End Unit 4, 5, & 62 2 days Mon Tue 23/04/13 Assignment 3 22/04/13 Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 3
  • 4. 26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12 07 Jan '13 M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 4
  • 5. 26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12 07 Jan '13 M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 5
  • 6. 26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12 07 Jan '13 M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 6
  • 7. n '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13 18 Feb '13 T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 7
  • 8. n '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13 18 Feb '13 T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 8
  • 9. n '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13 18 Feb '13 T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 9
  • 10. 25 Feb '13 04 Mar '13 11 Mar '13 18 Mar '13 25 Mar '13 01 Apr '13 08 Apr '13 S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 10
  • 11. 25 Feb '13 04 Mar '13 11 Mar '13 18 Mar '13 25 Mar '13 01 Apr '13 08 Apr '13 S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 11
  • 12. 25 Feb '13 04 Mar '13 11 Mar '13 18 Mar '13 25 Mar '13 01 Apr '13 08 Apr '13 S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 12
  • 13. 8 Apr '13 15 Apr '13 22 Apr '13 29 Apr '13 06 May '13 13 May '13 20 May '13 W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 13
  • 14. 8 Apr '13 15 Apr '13 22 Apr '13 29 Apr '13 06 May '13 13 May '13 20 May '13 W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 14
  • 15. 8 Apr '13 15 Apr '13 22 Apr '13 29 Apr '13 06 May '13 13 May '13 20 May '13 W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Project Plan Milestone Inactive Milestone Start-only Date: Wed 07/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 15