Week 1
           Monday      Tuesday   Wednesday Thursday   Friday      Saturday   Sunday
w/b                                                   Task 1      Task 4
05.11.12                                              Task 2
w/b
12.11.12
w/b                              Task 5
19.11.12
w/b                              Task 6
26.11.12
w/b                              Task 7
03.12.12
w/b                              Tasks
10.12.12                         Check up              Deadline



Task 1 – Complete

Task 2 – Complete

Task 3 – Complete

Task 4 – Almost Complete

Task 5 – Not Started

Task 6 – Not Started

Task 7 – Not Started


Week 3
           Monday      Tuesday   Wednesday Thursday   Friday      Saturday   Sunday
w/b                                                   Task 1      Task 4
05.11.12                                              Task 2
w/b
12.11.12
w/b                              Task 5
19.11.12
w/b                              Task 6
26.11.12
w/b                              Task 7
03.12.12
w/b                              Tasks
10.12.12                         Check up              Deadline



Task 1 – Complete
Task 2 – Complete

Task 3 – Complete

Task 4 – Almost Complete

Task 5 – Almost complete

Task 6 – Not Started

Task 7 – Not Started


Week 4
           Monday      Tuesday   Wednesday Thursday   Friday      Saturday   Sunday
w/b                                                   Task 1      Task 4
05.11.12                                              Task 2
w/b
12.11.12
w/b                              Task 5
19.11.12
w/b                              Task 6
26.11.12
w/b                              Task 7
03.12.12
w/b                              Tasks
10.12.12                         Check up              Deadline



Task 1 – Complete

Task 2 – Complete

Task 3 – Complete

Task 4 – Almost Complete

Task 5 – Almost complete

Task 6 – Not Started

Task 7 – Not Started


Week 5
           Monday      Tuesday   Wednesday Thursday   Friday      Saturday   Sunday
w/b                                                   Task 1      Task 4
05.11.12                                              Task 2
w/b
12.11.12
w/b                              Task 5
19.11.12
w/b                              Task 6
26.11.12
w/b                              Task 7
03.12.12
w/b                              Tasks
10.12.12                         Check up              Deadline



Task 1 – Complete

Task 2 – Complete

Task 3 – Complete

Task 4 – Almost Complete

Task 5 – Almost complete

Task 6 – Not Started

Task 7 – Not Started


Week 6
           Monday      Tuesday   Wednesday Thursday   Friday      Saturday   Sunday
w/b                                                   Task 1      Task 4
05.11.12                                              Task 2
w/b
12.11.12
w/b                              Task 5
19.11.12
w/b                              Task 6
26.11.12
w/b                              Task 7
03.12.12
w/b                              Tasks
10.12.12                         Check up              Deadline



Task 1 – Complete

Task 2 – Complete

Task 3 – Complete

Task 4 – Almost Complete

Task 5 – Almost complete
Task 6 – Not Started

Task 7 – Not Started


Week 7
                  Monday                 Tuesday                Wednesday Thursday                               Friday                      Saturday               Sunday
w/b                                                                                                              Task 1                      Task 4
05.11.12                                                                                                         Task 2
w/b
12.11.12
w/b                                                             Task 5
19.11.12
w/b                                                             Task 6
26.11.12
w/b                                                             Task 7
03.12.12
w/b                                                             Tasks
10.12.12                                                        Check up                                             Deadline
w/b                                                             Task Left                 Instant
17/12/12                                                                                  Deadline



Task 1 – Complete

Task 2 – Complete

Task 3 – Complete

Task 4 – Complete

Task 5 – Complete

Task 6 – Complete

Task 7 – In progress
Date and Task   Comment
16/11/2012      I have stood up and presented my character
23/11/2012      I have carried out and finished drawing the digital art of my game character.
28/11/2012      I have added detail to my character making the lines more smooth and have shadowing.
29/11/2012      I have finished adding the final details I had used the select tool to make the lines more smoother and drawn boxes at one side of the character and make it a
                darker colour to give it a shadow effect.
30/11/2012      I have made an animation to show how my character will jump in the game.
05/12/2012      I have animated my character to look like he is breathing.
06/12/2012      I have made the animation for my characters breathing longer and also gave him a waiting animation and I have also given him a blinking animation.
12/12/2012      I have made the breathing and waiting animation on their own scene and began the make a running animation.
19/12/2012      I have started to add buttons to the flash
20/12/2012      I have finished adding the buttons and have added another scene showing more information about banana ram

Task 2 schedule all

  • 1.
    Week 1 Monday Tuesday Wednesday Thursday Friday Saturday Sunday w/b Task 1 Task 4 05.11.12 Task 2 w/b 12.11.12 w/b Task 5 19.11.12 w/b Task 6 26.11.12 w/b Task 7 03.12.12 w/b Tasks 10.12.12 Check up Deadline Task 1 – Complete Task 2 – Complete Task 3 – Complete Task 4 – Almost Complete Task 5 – Not Started Task 6 – Not Started Task 7 – Not Started Week 3 Monday Tuesday Wednesday Thursday Friday Saturday Sunday w/b Task 1 Task 4 05.11.12 Task 2 w/b 12.11.12 w/b Task 5 19.11.12 w/b Task 6 26.11.12 w/b Task 7 03.12.12 w/b Tasks 10.12.12 Check up Deadline Task 1 – Complete
  • 2.
    Task 2 –Complete Task 3 – Complete Task 4 – Almost Complete Task 5 – Almost complete Task 6 – Not Started Task 7 – Not Started Week 4 Monday Tuesday Wednesday Thursday Friday Saturday Sunday w/b Task 1 Task 4 05.11.12 Task 2 w/b 12.11.12 w/b Task 5 19.11.12 w/b Task 6 26.11.12 w/b Task 7 03.12.12 w/b Tasks 10.12.12 Check up Deadline Task 1 – Complete Task 2 – Complete Task 3 – Complete Task 4 – Almost Complete Task 5 – Almost complete Task 6 – Not Started Task 7 – Not Started Week 5 Monday Tuesday Wednesday Thursday Friday Saturday Sunday w/b Task 1 Task 4 05.11.12 Task 2 w/b 12.11.12
  • 3.
    w/b Task 5 19.11.12 w/b Task 6 26.11.12 w/b Task 7 03.12.12 w/b Tasks 10.12.12 Check up Deadline Task 1 – Complete Task 2 – Complete Task 3 – Complete Task 4 – Almost Complete Task 5 – Almost complete Task 6 – Not Started Task 7 – Not Started Week 6 Monday Tuesday Wednesday Thursday Friday Saturday Sunday w/b Task 1 Task 4 05.11.12 Task 2 w/b 12.11.12 w/b Task 5 19.11.12 w/b Task 6 26.11.12 w/b Task 7 03.12.12 w/b Tasks 10.12.12 Check up Deadline Task 1 – Complete Task 2 – Complete Task 3 – Complete Task 4 – Almost Complete Task 5 – Almost complete
  • 4.
    Task 6 –Not Started Task 7 – Not Started Week 7 Monday Tuesday Wednesday Thursday Friday Saturday Sunday w/b Task 1 Task 4 05.11.12 Task 2 w/b 12.11.12 w/b Task 5 19.11.12 w/b Task 6 26.11.12 w/b Task 7 03.12.12 w/b Tasks 10.12.12 Check up Deadline w/b Task Left Instant 17/12/12 Deadline Task 1 – Complete Task 2 – Complete Task 3 – Complete Task 4 – Complete Task 5 – Complete Task 6 – Complete Task 7 – In progress Date and Task Comment 16/11/2012 I have stood up and presented my character 23/11/2012 I have carried out and finished drawing the digital art of my game character. 28/11/2012 I have added detail to my character making the lines more smooth and have shadowing. 29/11/2012 I have finished adding the final details I had used the select tool to make the lines more smoother and drawn boxes at one side of the character and make it a darker colour to give it a shadow effect. 30/11/2012 I have made an animation to show how my character will jump in the game. 05/12/2012 I have animated my character to look like he is breathing. 06/12/2012 I have made the animation for my characters breathing longer and also gave him a waiting animation and I have also given him a blinking animation. 12/12/2012 I have made the breathing and waiting animation on their own scene and began the make a running animation. 19/12/2012 I have started to add buttons to the flash 20/12/2012 I have finished adding the buttons and have added another scene showing more information about banana ram