SlideShare a Scribd company logo
1 of 6
ID            Task       Task Name                                Duration   Start 29 Oct '12Finish          05 Nov '12                      12 Nov '12                   19 Nov '12
              Mode                                                                                       S   M T W        T      F   S   S   M T W        T   F   S   S   M T
     1                   Start Assignment 2                         1 day    Mon 05/11/12Mon 05/11/12
     2                   Create Project Plan - The project plan 1 day        Tue 06/11/12 Tue 06/11/12
                         will show all of the tasks that I will
                         need to complete and will even show
                         the dates in which I will talk to the
                         client and have sqedueled meetings
                         with them.
     3                   Create Gnatt Chart of the project - This 1 day      Wed             Wed
                         outlines the key tasks that I will have to          07/11/12        07/11/12
                         complete and some of the risks that I
                         will have to face in the project
     4                   Complete the risk assessment -A risk 1 day          Wed             Wed
                         assessment should be completed                      07/11/12        07/11/12
                         showing back up plans and any health
                         and safety issues to ensure the project
                         is completed on time
     5                   Target Research - In order to have an 3 days        Mon             Wed
                         understanding of your target audience,              12/11/12        14/11/12
                         competitors, where your product
                         would be situated in the market place
                         etc you need to do a broad range of the
                         following: Identify the target audience,
                         look at other colleges etc.




                                     Task                                    External Milestone                     Manual Summary Rollup
                                     Split                                   Inactive Task                          Manual Summary

Project: Gnatt Chart Outlining Pro   Milestone                               Inactive Milestone                     Start-only
Date: Tue 27/11/12                   Summary                                 Inactive Summary                       Finish-only
                                     Project Summary                         Manual Task                            Deadline
                                     External Tasks                          Duration-only                          Progress

                                                                                    Page 1
ID            Task       Task Name                                 Duration   Start 29 Oct '12Finish             05 Nov '12                      12 Nov '12                   19 Nov '12
              Mode                                                                                           S   M T W        T      F   S   S   M T W        T   F   S   S   M T
     6                   Discuss with client how the                1 day     Wed             Wed
                         questionnaire will be layed out and                  14/11/12        14/11/12
                         what will happen during the
                         pre-production planning on the
                         advertisement
     7                   Design and produce a questionnaire         4 days    Mon             Thu 22/11/12
                         and gather the results                               19/11/12
     8                   Pre‐production planning for your           6 days    Mon             Mon
                         advert.                                              26/11/12        03/12/12
      9                  produce an outline (proposal)              2 days    Tue 04/12/12    Wed 05/12/12
     10                  Hold a preliminary team/group              1 day     Mon             Mon
                         meeting to discuss the progress                      10/12/12        10/12/12
                         through your project.
     11                  Agree individual roles within the          1 day     Wed             Wed
                         project and allocate jobs within the                 12/12/12        12/12/12
                         team/group.
     12                  Complete the pre-production phase          3 days    Mon 07/01/13Wed 09/01/13
     13                  Complete Production Phase                  16 days   Mon 14/01/13Mon 04/02/13
     14                    Begin Filming for the infomational
                           DVD
     15                    Keep up to date with the client
     16                    (If bad weather or a full team is not in 21 days   Mon             Mon
                           then production maybe delayed a                    14/01/13        11/02/13
                           week)



                                     Task                                     External Milestone                        Manual Summary Rollup
                                     Split                                    Inactive Task                             Manual Summary

Project: Gnatt Chart Outlining Pro   Milestone                                Inactive Milestone                        Start-only
Date: Tue 27/11/12                   Summary                                  Inactive Summary                          Finish-only
                                     Project Summary                          Manual Task                               Deadline
                                     External Tasks                           Duration-only                             Progress

                                                                                     Page 2
19 Nov '12                    26 Nov '12                      03 Dec '12                   10 Dec '12                     17 Dec '12                     24 Dec '12                   31 Dec '12
     T W     T   F    S   S   M T W         T    F   S    S   M T W        T   F   S   S   M T W          T   F   S   S   M T W        T   F     S   S   M T W        T   F   S   S   M T W




                                         Task                                          External Milestone                          Manual Summary Rollup
                                         Split                                         Inactive Task                               Manual Summary

    Project: Gnatt Chart Outlining Pro   Milestone                                     Inactive Milestone                          Start-only
    Date: Tue 27/11/12                   Summary                                       Inactive Summary                            Finish-only
                                         Project Summary                               Manual Task                                 Deadline
                                         External Tasks                                Duration-only                               Progress

                                                                                              Page 3
19 Nov '12                    26 Nov '12                      03 Dec '12                   10 Dec '12                     17 Dec '12                     24 Dec '12                   31 Dec '12
     T W     T   F    S   S   M T W         T    F   S    S   M T W        T   F   S   S   M T W          T   F   S   S   M T W        T   F     S   S   M T W        T   F   S   S   M T W




                                         Task                                          External Milestone                          Manual Summary Rollup
                                         Split                                         Inactive Task                               Manual Summary

    Project: Gnatt Chart Outlining Pro   Milestone                                     Inactive Milestone                          Start-only
    Date: Tue 27/11/12                   Summary                                       Inactive Summary                            Finish-only
                                         Project Summary                               Manual Task                                 Deadline
                                         External Tasks                                Duration-only                               Progress

                                                                                              Page 4
Dec '12                    07 Jan '13                          14 Jan '13                   21 Jan '13                      28 Jan '13                         04 Feb '13                   11 Feb '13
      W   T   F   S    S   M T W          T      F    S   S    M T W        T   F   S   S   M T W           T   F   S   S   M T W        T      F   S      S   M T W        T   F   S   S   M T W        T




                                              Task                                          External Milestone                               Manual Summary Rollup
                                              Split                                         Inactive Task                                    Manual Summary

     Project: Gnatt Chart Outlining Pro       Milestone                                     Inactive Milestone                               Start-only
     Date: Tue 27/11/12                       Summary                                       Inactive Summary                                 Finish-only
                                              Project Summary                               Manual Task                                      Deadline
                                              External Tasks                                Duration-only                                    Progress

                                                                                                   Page 5
Dec '12                    07 Jan '13                          14 Jan '13                   21 Jan '13                      28 Jan '13                         04 Feb '13                   11 Feb '13
      W   T   F   S    S   M T W          T      F    S   S    M T W        T   F   S   S   M T W           T   F   S   S   M T W        T      F   S      S   M T W        T   F   S   S   M T W        T




                                              Task                                          External Milestone                               Manual Summary Rollup
                                              Split                                         Inactive Task                                    Manual Summary

     Project: Gnatt Chart Outlining Pro       Milestone                                     Inactive Milestone                               Start-only
     Date: Tue 27/11/12                       Summary                                       Inactive Summary                                 Finish-only
                                              Project Summary                               Manual Task                                      Deadline
                                              External Tasks                                Duration-only                                    Progress

                                                                                                   Page 6

More Related Content

Viewers also liked

Production and Operatiosn management
Production and Operatiosn managementProduction and Operatiosn management
Production and Operatiosn managementPratik Lahiri
 
Project management 101
Project management 101Project management 101
Project management 101Sujatha TS
 
Meeting Planner Tool
Meeting Planner ToolMeeting Planner Tool
Meeting Planner ToolJason Bargent
 
WHO - AMR Global Overview and Action Plan
WHO - AMR Global Overview and Action PlanWHO - AMR Global Overview and Action Plan
WHO - AMR Global Overview and Action Planmarkovingian
 
From Idea to Market. How to build a hardware startup
From Idea to Market. How to build a hardware startupFrom Idea to Market. How to build a hardware startup
From Idea to Market. How to build a hardware startupAgnieszka Nazaruk
 
PROJECT MANAGEMENT [ARC 3164]- Project: 2 DOCUMENTATION OF A MEDIUM-SIZED PRO...
PROJECT MANAGEMENT [ARC 3164]- Project: 2 DOCUMENTATION OF A MEDIUM-SIZED PRO...PROJECT MANAGEMENT [ARC 3164]- Project: 2 DOCUMENTATION OF A MEDIUM-SIZED PRO...
PROJECT MANAGEMENT [ARC 3164]- Project: 2 DOCUMENTATION OF A MEDIUM-SIZED PRO...Angeline KH
 
Sales Call Planner Tool
Sales Call Planner ToolSales Call Planner Tool
Sales Call Planner ToolJason Bargent
 
Paretos the business opportunity 07112010
Paretos   the business opportunity 07112010Paretos   the business opportunity 07112010
Paretos the business opportunity 07112010stewart_gary
 
5 circular arrows as steps in business process powerpoint templates 0812
5 circular arrows as steps in business process powerpoint templates 08125 circular arrows as steps in business process powerpoint templates 0812
5 circular arrows as steps in business process powerpoint templates 0812SlideTeam.net
 
Business Requirements Gathering - Current & Future State
Business Requirements Gathering - Current & Future StateBusiness Requirements Gathering - Current & Future State
Business Requirements Gathering - Current & Future StateJason Bargent
 
Project Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, FranceProject Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, FranceRakibul Hasan,MEng,EIT
 
Prevalence of malnutrition among under five children of RukaminiNagar, Belgaum
Prevalence of malnutrition among under five children of RukaminiNagar, BelgaumPrevalence of malnutrition among under five children of RukaminiNagar, Belgaum
Prevalence of malnutrition among under five children of RukaminiNagar, BelgaumSawan Kumar
 
Malnutrition project proposal ( Increasing knowlege about importance of a bal...
Malnutrition project proposal ( Increasing knowlege about importance of a bal...Malnutrition project proposal ( Increasing knowlege about importance of a bal...
Malnutrition project proposal ( Increasing knowlege about importance of a bal...Oriba Dan Langoya
 
Six thinking hats exercise
Six thinking hats exerciseSix thinking hats exercise
Six thinking hats exerciseShmuel Gershon
 
Ishikawa's Fish Bone
Ishikawa's Fish BoneIshikawa's Fish Bone
Ishikawa's Fish BonePrithvi Ghag
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
Six Thinking Hats
Six Thinking HatsSix Thinking Hats
Six Thinking HatsJegan Sekar
 

Viewers also liked (19)

Production and Operatiosn management
Production and Operatiosn managementProduction and Operatiosn management
Production and Operatiosn management
 
Project1
Project1Project1
Project1
 
Project management 101
Project management 101Project management 101
Project management 101
 
Meeting Planner Tool
Meeting Planner ToolMeeting Planner Tool
Meeting Planner Tool
 
WHO - AMR Global Overview and Action Plan
WHO - AMR Global Overview and Action PlanWHO - AMR Global Overview and Action Plan
WHO - AMR Global Overview and Action Plan
 
From Idea to Market. How to build a hardware startup
From Idea to Market. How to build a hardware startupFrom Idea to Market. How to build a hardware startup
From Idea to Market. How to build a hardware startup
 
PROJECT MANAGEMENT [ARC 3164]- Project: 2 DOCUMENTATION OF A MEDIUM-SIZED PRO...
PROJECT MANAGEMENT [ARC 3164]- Project: 2 DOCUMENTATION OF A MEDIUM-SIZED PRO...PROJECT MANAGEMENT [ARC 3164]- Project: 2 DOCUMENTATION OF A MEDIUM-SIZED PRO...
PROJECT MANAGEMENT [ARC 3164]- Project: 2 DOCUMENTATION OF A MEDIUM-SIZED PRO...
 
Sales Call Planner Tool
Sales Call Planner ToolSales Call Planner Tool
Sales Call Planner Tool
 
Paretos the business opportunity 07112010
Paretos   the business opportunity 07112010Paretos   the business opportunity 07112010
Paretos the business opportunity 07112010
 
5 circular arrows as steps in business process powerpoint templates 0812
5 circular arrows as steps in business process powerpoint templates 08125 circular arrows as steps in business process powerpoint templates 0812
5 circular arrows as steps in business process powerpoint templates 0812
 
Business Requirements Gathering - Current & Future State
Business Requirements Gathering - Current & Future StateBusiness Requirements Gathering - Current & Future State
Business Requirements Gathering - Current & Future State
 
Project Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, FranceProject Planning and Management of Millau Viaduct Bridge, France
Project Planning and Management of Millau Viaduct Bridge, France
 
Prevalence of malnutrition among under five children of RukaminiNagar, Belgaum
Prevalence of malnutrition among under five children of RukaminiNagar, BelgaumPrevalence of malnutrition among under five children of RukaminiNagar, Belgaum
Prevalence of malnutrition among under five children of RukaminiNagar, Belgaum
 
Malnutrition project proposal ( Increasing knowlege about importance of a bal...
Malnutrition project proposal ( Increasing knowlege about importance of a bal...Malnutrition project proposal ( Increasing knowlege about importance of a bal...
Malnutrition project proposal ( Increasing knowlege about importance of a bal...
 
Six thinking hats exercise
Six thinking hats exerciseSix thinking hats exercise
Six thinking hats exercise
 
Ishikawa's Fish Bone
Ishikawa's Fish BoneIshikawa's Fish Bone
Ishikawa's Fish Bone
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Six Thinking Hats
Six Thinking HatsSix Thinking Hats
Six Thinking Hats
 
Fish bone examples ppt
Fish bone examples pptFish bone examples ppt
Fish bone examples ppt
 

Similar to Plan and schedule marketing project tasks

Project outline
Project outlineProject outline
Project outlineCrashin
 
Verbe planning v1
Verbe planning v1Verbe planning v1
Verbe planning v1vudt1990
 
Verbe planning
Verbe planningVerbe planning
Verbe planningvudt1990
 
Microsoft project tugas 1
Microsoft project   tugas 1Microsoft project   tugas 1
Microsoft project tugas 1Tri Atsumori
 
High level project plan with dependencies
High level project plan with dependenciesHigh level project plan with dependencies
High level project plan with dependenciesMADS Board
 
Chapter 2
Chapter 2Chapter 2
Chapter 2Mr SMAK
 
Chapter 2 ASE
Chapter 2 ASEChapter 2 ASE
Chapter 2 ASEMr SMAK
 
Task 2 schedule all
Task 2   schedule allTask 2   schedule all
Task 2 schedule allMrrrjones
 
App concept schedule
App concept scheduleApp concept schedule
App concept schedulehamza_123456
 
App concept schedule
App concept scheduleApp concept schedule
App concept schedulehamza_123456
 
Plan proyecto final- Jimmy Bedoya
Plan proyecto final- Jimmy BedoyaPlan proyecto final- Jimmy Bedoya
Plan proyecto final- Jimmy BedoyaJimmy Bedoya
 
Senior Semar Calendar 2011 Semester 1
Senior Semar Calendar 2011 Semester 1Senior Semar Calendar 2011 Semester 1
Senior Semar Calendar 2011 Semester 1clover66
 
Time unit 2012 nov part 2
Time unit 2012 nov part 2 Time unit 2012 nov part 2
Time unit 2012 nov part 2 Skript
 
Microsoft office project grand paper ismud-2b
Microsoft office project   grand paper ismud-2bMicrosoft office project   grand paper ismud-2b
Microsoft office project grand paper ismud-2bIskandar Muda
 

Similar to Plan and schedule marketing project tasks (20)

Gant chart
Gant chartGant chart
Gant chart
 
Gant chart
Gant chartGant chart
Gant chart
 
Project outline
Project outlineProject outline
Project outline
 
Project10.mpp
Project10.mppProject10.mpp
Project10.mpp
 
Verbe planning v1
Verbe planning v1Verbe planning v1
Verbe planning v1
 
Verbe planning
Verbe planningVerbe planning
Verbe planning
 
Verbe planning
Verbe planningVerbe planning
Verbe planning
 
Microsoft project tugas 1
Microsoft project   tugas 1Microsoft project   tugas 1
Microsoft project tugas 1
 
Carta gantt
Carta ganttCarta gantt
Carta gantt
 
Team schedule media
Team schedule   mediaTeam schedule   media
Team schedule media
 
High level project plan with dependencies
High level project plan with dependenciesHigh level project plan with dependencies
High level project plan with dependencies
 
Chapter 2
Chapter 2Chapter 2
Chapter 2
 
Chapter 2 ASE
Chapter 2 ASEChapter 2 ASE
Chapter 2 ASE
 
Task 2 schedule all
Task 2   schedule allTask 2   schedule all
Task 2 schedule all
 
App concept schedule
App concept scheduleApp concept schedule
App concept schedule
 
App concept schedule
App concept scheduleApp concept schedule
App concept schedule
 
Plan proyecto final- Jimmy Bedoya
Plan proyecto final- Jimmy BedoyaPlan proyecto final- Jimmy Bedoya
Plan proyecto final- Jimmy Bedoya
 
Senior Semar Calendar 2011 Semester 1
Senior Semar Calendar 2011 Semester 1Senior Semar Calendar 2011 Semester 1
Senior Semar Calendar 2011 Semester 1
 
Time unit 2012 nov part 2
Time unit 2012 nov part 2 Time unit 2012 nov part 2
Time unit 2012 nov part 2
 
Microsoft office project grand paper ismud-2b
Microsoft office project   grand paper ismud-2bMicrosoft office project   grand paper ismud-2b
Microsoft office project grand paper ismud-2b
 

More from ms72527

Questionnaire results feedback
Questionnaire results feedbackQuestionnaire results feedback
Questionnaire results feedbackms72527
 
Team proposal presentation
Team proposal presentationTeam proposal presentation
Team proposal presentationms72527
 
Mood board for Media Advert
Mood board for Media AdvertMood board for Media Advert
Mood board for Media Advertms72527
 
Unit 32 diary
Unit 32 diaryUnit 32 diary
Unit 32 diaryms72527
 
Wesbsite screenshots
Wesbsite screenshotsWesbsite screenshots
Wesbsite screenshotsms72527
 
Unit 32 task 2
Unit 32 task 2Unit 32 task 2
Unit 32 task 2ms72527
 
Questionnaire for creative media
Questionnaire for creative mediaQuestionnaire for creative media
Questionnaire for creative mediams72527
 
Unit 32 task 2 Presentation
Unit 32 task 2 PresentationUnit 32 task 2 Presentation
Unit 32 task 2 Presentationms72527
 
About us page storyboard
About us page storyboardAbout us page storyboard
About us page storyboardms72527
 
Pack page storyboard
Pack page storyboardPack page storyboard
Pack page storyboardms72527
 
Presentation Test Upload
Presentation Test UploadPresentation Test Upload
Presentation Test Uploadms72527
 

More from ms72527 (11)

Questionnaire results feedback
Questionnaire results feedbackQuestionnaire results feedback
Questionnaire results feedback
 
Team proposal presentation
Team proposal presentationTeam proposal presentation
Team proposal presentation
 
Mood board for Media Advert
Mood board for Media AdvertMood board for Media Advert
Mood board for Media Advert
 
Unit 32 diary
Unit 32 diaryUnit 32 diary
Unit 32 diary
 
Wesbsite screenshots
Wesbsite screenshotsWesbsite screenshots
Wesbsite screenshots
 
Unit 32 task 2
Unit 32 task 2Unit 32 task 2
Unit 32 task 2
 
Questionnaire for creative media
Questionnaire for creative mediaQuestionnaire for creative media
Questionnaire for creative media
 
Unit 32 task 2 Presentation
Unit 32 task 2 PresentationUnit 32 task 2 Presentation
Unit 32 task 2 Presentation
 
About us page storyboard
About us page storyboardAbout us page storyboard
About us page storyboard
 
Pack page storyboard
Pack page storyboardPack page storyboard
Pack page storyboard
 
Presentation Test Upload
Presentation Test UploadPresentation Test Upload
Presentation Test Upload
 

Recently uploaded

How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 

Recently uploaded (20)

How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 

Plan and schedule marketing project tasks

  • 1. ID Task Task Name Duration Start 29 Oct '12Finish 05 Nov '12 12 Nov '12 19 Nov '12 Mode S M T W T F S S M T W T F S S M T 1 Start Assignment 2 1 day Mon 05/11/12Mon 05/11/12 2 Create Project Plan - The project plan 1 day Tue 06/11/12 Tue 06/11/12 will show all of the tasks that I will need to complete and will even show the dates in which I will talk to the client and have sqedueled meetings with them. 3 Create Gnatt Chart of the project - This 1 day Wed Wed outlines the key tasks that I will have to 07/11/12 07/11/12 complete and some of the risks that I will have to face in the project 4 Complete the risk assessment -A risk 1 day Wed Wed assessment should be completed 07/11/12 07/11/12 showing back up plans and any health and safety issues to ensure the project is completed on time 5 Target Research - In order to have an 3 days Mon Wed understanding of your target audience, 12/11/12 14/11/12 competitors, where your product would be situated in the market place etc you need to do a broad range of the following: Identify the target audience, look at other colleges etc. Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Gnatt Chart Outlining Pro Milestone Inactive Milestone Start-only Date: Tue 27/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 1
  • 2. ID Task Task Name Duration Start 29 Oct '12Finish 05 Nov '12 12 Nov '12 19 Nov '12 Mode S M T W T F S S M T W T F S S M T 6 Discuss with client how the 1 day Wed Wed questionnaire will be layed out and 14/11/12 14/11/12 what will happen during the pre-production planning on the advertisement 7 Design and produce a questionnaire 4 days Mon Thu 22/11/12 and gather the results 19/11/12 8 Pre‐production planning for your 6 days Mon Mon advert. 26/11/12 03/12/12 9 produce an outline (proposal) 2 days Tue 04/12/12 Wed 05/12/12 10 Hold a preliminary team/group 1 day Mon Mon meeting to discuss the progress 10/12/12 10/12/12 through your project. 11 Agree individual roles within the 1 day Wed Wed project and allocate jobs within the 12/12/12 12/12/12 team/group. 12 Complete the pre-production phase 3 days Mon 07/01/13Wed 09/01/13 13 Complete Production Phase 16 days Mon 14/01/13Mon 04/02/13 14 Begin Filming for the infomational DVD 15 Keep up to date with the client 16 (If bad weather or a full team is not in 21 days Mon Mon then production maybe delayed a 14/01/13 11/02/13 week) Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Gnatt Chart Outlining Pro Milestone Inactive Milestone Start-only Date: Tue 27/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 2
  • 3. 19 Nov '12 26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12 T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Gnatt Chart Outlining Pro Milestone Inactive Milestone Start-only Date: Tue 27/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 3
  • 4. 19 Nov '12 26 Nov '12 03 Dec '12 10 Dec '12 17 Dec '12 24 Dec '12 31 Dec '12 T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Gnatt Chart Outlining Pro Milestone Inactive Milestone Start-only Date: Tue 27/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 4
  • 5. Dec '12 07 Jan '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13 W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Gnatt Chart Outlining Pro Milestone Inactive Milestone Start-only Date: Tue 27/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 5
  • 6. Dec '12 07 Jan '13 14 Jan '13 21 Jan '13 28 Jan '13 04 Feb '13 11 Feb '13 W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T Task External Milestone Manual Summary Rollup Split Inactive Task Manual Summary Project: Gnatt Chart Outlining Pro Milestone Inactive Milestone Start-only Date: Tue 27/11/12 Summary Inactive Summary Finish-only Project Summary Manual Task Deadline External Tasks Duration-only Progress Page 6