The Flatlick Sewer Rehabilitation Project included rehabilitation of approximately 2,500 linear feet of existing 24-inch diameter pipe and 650 linear feet of existing 15-inch diameter pipe using the Cured in Place Pipe (CIPP) lining method. The lining was cured using UV Light. In addition, 11 manholes were rehabilitated throughout the Flatlick Branch stream valley in Chantilly, Virginia. This project was substantially complete on January 4, 2021.