Flatlick Sewer Rehabilitation Project
Phase 1 and 2
Project Details
Flatlick Sewer Rehabilitation Project Phase 1 & 2
Capital Facilities/Wastewater Design and Construction Division/Collections Branch
Description:
The Flatlick Sewer Rehabilitation Project included rehabilitation of approximately 2,500 linear feet of existing 24-inch
diameter pipe and 650 linear feet of existing 15-inch diameter pipe using the Cured in Place Pipe (CIPP) lining
method. The lining was cured using UV Light. In addition, 11 manholes were rehabilitated throughout the Flatlick
Branch stream valley in Chantilly, Virginia. This project was substantially complete on January 4, 2021.
Project Overview:
• Cured-in-place pipe lining (cured using UV light)
• Manhole rehabilitation using cementitious and epoxy coatings
• Bypass pumping system
• 3,000 linear feet of access road
• Permitting: US Army Corps of Engineers Nationwide Permit #12, Virginia Department of Transportation Land Use
Permit, Fairfax County Park Authority
• Challenge – maintaining access roads and bypass pumping operations during flooding events
Project Team:
• Matt Doyle, P.E. - Wastewater Design and Construction Division
• Suzy Harding, P.E. - Wastewater Design and Construction Division
• Colleen Block, P. E. - Wastewater Design and Construction Division
• Tom Richardson, P.E. - Wastewater Collection Division
• Shwan Fatah, P.E. - Wastewater Collection Division
• Arcadis - Engineer
• Flippo Construction Company - Contractor
Flatlick Sewer Rehabilitation Project Phase 1 & 2
Capital Facilities/Wastewater Design and Construction Division/Collections Branch
Sully District, Tax Map No. 44-2
Project is located along
Flatlick Branch from
Lee Jackson Memorial
Highway to Walney
Road.
Flatlick Sewer Rehabilitation Project Phase 1 & 2
Capital Facilities/Wastewater Design and Construction Division/Collections Branch
Construction of Mulch & Mat Access Roads
Mulch and timber-mat access roads
were installed to reach the sewers in
the Flatlick Branch stream valley.
Flatlick Sewer Rehabilitation Project Phase 1 & 2
Capital Facilities/Wastewater Design and Construction Division/Collections Branch
Tree Protection
Tree protection
Flatlick Sewer Rehabilitation Project Phase 1 & 2
Capital Facilities/Wastewater Design and Construction Division/Collections Branch
Jersey Barriers and Steel Plates to Control Flooding
Various measures
were used to
mitigate effects of
flooding on the
construction site,
including Jersey
Barriers and steel
plates to hold
matting in place.
Flatlick Sewer Rehabilitation Project Phase 1 & 2
Capital Facilities/Wastewater Design and Construction Division/Collections Branch
Bypass Pumping System
Laying out bypass piping
at Phase 1 Construction
Entrance
Bypass pumps and piping
configuration at Phase 1
Construction Entrance
Flatlick Sewer Rehabilitation Project Phase 1 & 2
Capital Facilities/Wastewater Design and Construction Division/Collections Branch
Bypass Pumping System
Pressure testing the
bypass pumping system
Piping in discharge manhole.
Piping in suction manhole.
Flatlick Sewer Rehabilitation Project Phase 1 & 2
Capital Facilities/Wastewater Design and Construction Division/Collections Branch
Bypass Pumping System: Bypass Piping
Bypass piping laid out along Phase 2 access road
Flatlick Sewer Rehabilitation Project Phase 1 & 2
Capital Facilities/Wastewater Design and Construction Division/Collections Branch
Manhole Rehabilitation
MH 006 epoxy coating and new steps Backfilled phase 1 suction manhole
Surface
preparation of
MH for lining
Flatlick Sewer Rehabilitation Project Phase 1 & 2
Capital Facilities/Wastewater Design and Construction Division/Collections Branch
UV Cured-in-Place Pipe Lining Equipment
UV light train
Video
monitoring
during lining
operation
Unloading liner
Before After
Capital Facilities/Wastewater Design and Construction Division/Collections Branch
Flatlick Sewer Rehabilitation Project Phase 1 & 2
Manholes Before and after Lining
Brick manhole channel
Deteriorating manhole steps and concrete
Rehabilitated manhole with epoxy coating of entire interior
and new steps (plastic-wrap removed after epoxy application)
Before After
Capital Facilities/Wastewater Design and Construction Division/Collections Branch
Flatlick Sewer Rehabilitation Project Phase 1 & 2
Sewer Pipes Before and after Lining
Mild offset joints and cracks
Infiltration
Infiltration
Deteriorated concrete: Aggregate
and reinforcement visible
Cured-in-place pipe: Addresses the “before” defects
Additional Information
For additional Information, please call
www.fairfaxcounty.gov/publicworks
Flatlick Sewer Rehabilitation Project Phase 1 & 2
Capital Facilities/Wastewater Design and Construction Division/Collections Branch
Sharon North, M.A., Section Chief, Communications
703-324-8455, TTY 711
Sharon.North@fairfaxcounty.gov
or
Irene Haske, Communications Specialist
703-324-5821, TTY 711
Irene.Haske@fairfaxcounty.gov

More Related Content

What's hot

Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3
Fairfax County
 
Substantial completion flatlick branch iii stream restoration
Substantial completion   flatlick branch iii stream restorationSubstantial completion   flatlick branch iii stream restoration
Substantial completion flatlick branch iii stream restoration
Fairfax County
 
Historic Jail Roof Replacement
Historic Jail Roof ReplacementHistoric Jail Roof Replacement
Historic Jail Roof Replacement
Fairfax County
 
Green Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairGreen Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer Repair
Fairfax County
 
Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020
Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020
Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020
Fairfax County
 
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Fairfax County
 
Paul Springs Segment 1 & 2 Stream Restoration
Paul Springs Segment 1 & 2 Stream RestorationPaul Springs Segment 1 & 2 Stream Restoration
Paul Springs Segment 1 & 2 Stream Restoration
Fairfax County
 
Summerton Way Pond Retrofit
Summerton Way Pond RetrofitSummerton Way Pond Retrofit
Summerton Way Pond Retrofit
Fairfax County
 
Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1
Fairfax County
 
Emergency Repair of Sanitary Sewer Line Crossing Lake Thoreau January 2016
Emergency Repair of Sanitary Sewer Line Crossing Lake Thoreau January 2016Emergency Repair of Sanitary Sewer Line Crossing Lake Thoreau January 2016
Emergency Repair of Sanitary Sewer Line Crossing Lake Thoreau January 2016
Fairfax County
 
Peyton Run POD Presentation_5_12_21
 Peyton Run POD Presentation_5_12_21 Peyton Run POD Presentation_5_12_21
Peyton Run POD Presentation_5_12_21
Fairfax County
 
Crisis Care Facility
Crisis Care FacilityCrisis Care Facility
Crisis Care Facility
Fairfax County
 
Belle View Pump Station Rehabilitation
Belle View Pump Station RehabilitationBelle View Pump Station Rehabilitation
Belle View Pump Station Rehabilitation
Fairfax County
 
Accotink Creek Watershed Project Wakefield Park North
Accotink Creek Watershed Project  Wakefield Park NorthAccotink Creek Watershed Project  Wakefield Park North
Accotink Creek Watershed Project Wakefield Park North
Fairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
Fairfax County
 
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016
Fairfax County
 
Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust”
Fairfax County
 
Crook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectCrook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration Project
Fairfax County
 
Waynewood II Force Main Replacement
Waynewood II Force Main ReplacementWaynewood II Force Main Replacement
Waynewood II Force Main Replacement
Fairfax County
 
Barker.R.CV.
Barker.R.CV.Barker.R.CV.
Barker.R.CV.
Richard Barker
 

What's hot (20)

Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3Pohick Stream Stabilization Phase II - Areas 2 and 3
Pohick Stream Stabilization Phase II - Areas 2 and 3
 
Substantial completion flatlick branch iii stream restoration
Substantial completion   flatlick branch iii stream restorationSubstantial completion   flatlick branch iii stream restoration
Substantial completion flatlick branch iii stream restoration
 
Historic Jail Roof Replacement
Historic Jail Roof ReplacementHistoric Jail Roof Replacement
Historic Jail Roof Replacement
 
Green Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairGreen Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer Repair
 
Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020
Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020
Pimmit Run Tributary at George Marshall High School Stream Restoration 9/29/2020
 
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
Annual Contract for Stream and Water Quality Improvements: Golden Woods Pond ...
 
Paul Springs Segment 1 & 2 Stream Restoration
Paul Springs Segment 1 & 2 Stream RestorationPaul Springs Segment 1 & 2 Stream Restoration
Paul Springs Segment 1 & 2 Stream Restoration
 
Summerton Way Pond Retrofit
Summerton Way Pond RetrofitSummerton Way Pond Retrofit
Summerton Way Pond Retrofit
 
Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1
 
Emergency Repair of Sanitary Sewer Line Crossing Lake Thoreau January 2016
Emergency Repair of Sanitary Sewer Line Crossing Lake Thoreau January 2016Emergency Repair of Sanitary Sewer Line Crossing Lake Thoreau January 2016
Emergency Repair of Sanitary Sewer Line Crossing Lake Thoreau January 2016
 
Peyton Run POD Presentation_5_12_21
 Peyton Run POD Presentation_5_12_21 Peyton Run POD Presentation_5_12_21
Peyton Run POD Presentation_5_12_21
 
Crisis Care Facility
Crisis Care FacilityCrisis Care Facility
Crisis Care Facility
 
Belle View Pump Station Rehabilitation
Belle View Pump Station RehabilitationBelle View Pump Station Rehabilitation
Belle View Pump Station Rehabilitation
 
Accotink Creek Watershed Project Wakefield Park North
Accotink Creek Watershed Project  Wakefield Park NorthAccotink Creek Watershed Project  Wakefield Park North
Accotink Creek Watershed Project Wakefield Park North
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016
 
Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust” Huntsman Lake “Pardon Our Dust”
Huntsman Lake “Pardon Our Dust”
 
Crook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration ProjectCrook Branch at Mantua Elementary School Stream Restoration Project
Crook Branch at Mantua Elementary School Stream Restoration Project
 
Waynewood II Force Main Replacement
Waynewood II Force Main ReplacementWaynewood II Force Main Replacement
Waynewood II Force Main Replacement
 
Barker.R.CV.
Barker.R.CV.Barker.R.CV.
Barker.R.CV.
 

Similar to Flatlick Sewer Rehabilitation Project Phase 1 and 2

Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
Fairfax County
 
Flatlick Branch III Stream Restoration June 6, 2020
Flatlick Branch III Stream Restoration June 6, 2020Flatlick Branch III Stream Restoration June 6, 2020
Flatlick Branch III Stream Restoration June 6, 2020
Fairfax County
 
Slipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway DriveSlipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway Drive
Fairfax County
 
Flatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration ProjectFlatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration Project
Fairfax County
 
Flatlick Branch-Phase 1 Stream Restoration
Flatlick Branch-Phase 1 Stream RestorationFlatlick Branch-Phase 1 Stream Restoration
Flatlick Branch-Phase 1 Stream Restoration
Fairfax County
 
Flatlick Branch - Phase 1 Stream Restoration
Flatlick Branch - Phase 1 Stream RestorationFlatlick Branch - Phase 1 Stream Restoration
Flatlick Branch - Phase 1 Stream Restoration
Fairfax County
 
Oakton Community Park Phase 2A
Oakton Community Park Phase 2AOakton Community Park Phase 2A
Oakton Community Park Phase 2A
Fairfax County
 
Pohick Creek Restoration Project Phase I June 2016
Pohick Creek Restoration Project Phase I June 2016Pohick Creek Restoration Project Phase I June 2016
Pohick Creek Restoration Project Phase I June 2016
Fairfax County
 
Green Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairGreen Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer Repair
Fairfax County
 
Newington Commons Pond Improvement
Newington Commons Pond ImprovementNewington Commons Pond Improvement
Newington Commons Pond Improvement
Fairfax County
 
Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016
Fairfax County
 
Pohick Creek Tributary Stream Restoration Project
Pohick Creek Tributary Stream Restoration ProjectPohick Creek Tributary Stream Restoration Project
Pohick Creek Tributary Stream Restoration Project
Fairfax County
 
Towlston Meadows Restoration Project
Towlston Meadows Restoration ProjectTowlston Meadows Restoration Project
Towlston Meadows Restoration Project
Fairfax County
 
Fort Hunt Road Emergency Gravity Sewer Project
Fort Hunt Road Emergency Gravity Sewer ProjectFort Hunt Road Emergency Gravity Sewer Project
Fort Hunt Road Emergency Gravity Sewer Project
Fairfax County
 
South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration Ja...
South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration Ja...South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration Ja...
South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration Ja...
Fairfax County
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Fairfax County
 
Colfax Ave Emergency Sewer Rehabilitation Project
Colfax Ave Emergency Sewer Rehabilitation ProjectColfax Ave Emergency Sewer Rehabilitation Project
Colfax Ave Emergency Sewer Rehabilitation Project
Fairfax County
 
Bradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit ProjectBradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit Project
Fairfax County
 
Oakton Swim and Racquet Water Quality Retrofit
Oakton Swim and Racquet Water Quality RetrofitOakton Swim and Racquet Water Quality Retrofit
Oakton Swim and Racquet Water Quality Retrofit
Fairfax County
 
Peppercorn Drive Outfall Restoration
Peppercorn Drive Outfall RestorationPeppercorn Drive Outfall Restoration
Peppercorn Drive Outfall Restoration
Fairfax County
 

Similar to Flatlick Sewer Rehabilitation Project Phase 1 and 2 (20)

Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
Little River Turnpike, Backlick Rd. Emergency Sewer Repair Sept 2020
 
Flatlick Branch III Stream Restoration June 6, 2020
Flatlick Branch III Stream Restoration June 6, 2020Flatlick Branch III Stream Restoration June 6, 2020
Flatlick Branch III Stream Restoration June 6, 2020
 
Slipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway DriveSlipline Replacement #2 - Waterway Drive
Slipline Replacement #2 - Waterway Drive
 
Flatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration ProjectFlatlick Branch Phase II Stream Restoration Project
Flatlick Branch Phase II Stream Restoration Project
 
Flatlick Branch-Phase 1 Stream Restoration
Flatlick Branch-Phase 1 Stream RestorationFlatlick Branch-Phase 1 Stream Restoration
Flatlick Branch-Phase 1 Stream Restoration
 
Flatlick Branch - Phase 1 Stream Restoration
Flatlick Branch - Phase 1 Stream RestorationFlatlick Branch - Phase 1 Stream Restoration
Flatlick Branch - Phase 1 Stream Restoration
 
Oakton Community Park Phase 2A
Oakton Community Park Phase 2AOakton Community Park Phase 2A
Oakton Community Park Phase 2A
 
Pohick Creek Restoration Project Phase I June 2016
Pohick Creek Restoration Project Phase I June 2016Pohick Creek Restoration Project Phase I June 2016
Pohick Creek Restoration Project Phase I June 2016
 
Green Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairGreen Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer Repair
 
Newington Commons Pond Improvement
Newington Commons Pond ImprovementNewington Commons Pond Improvement
Newington Commons Pond Improvement
 
Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016Potomac Meadow Water Quality Improvement July 2016
Potomac Meadow Water Quality Improvement July 2016
 
Pohick Creek Tributary Stream Restoration Project
Pohick Creek Tributary Stream Restoration ProjectPohick Creek Tributary Stream Restoration Project
Pohick Creek Tributary Stream Restoration Project
 
Towlston Meadows Restoration Project
Towlston Meadows Restoration ProjectTowlston Meadows Restoration Project
Towlston Meadows Restoration Project
 
Fort Hunt Road Emergency Gravity Sewer Project
Fort Hunt Road Emergency Gravity Sewer ProjectFort Hunt Road Emergency Gravity Sewer Project
Fort Hunt Road Emergency Gravity Sewer Project
 
South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration Ja...
South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration Ja...South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration Ja...
South Van Dorn Sanitary Sewer Emergency Replacement and Stream Restoration Ja...
 
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream RestorationScotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
Scotts Run at Old Meadow Road Park Phase I and Phase II Stream Restoration
 
Colfax Ave Emergency Sewer Rehabilitation Project
Colfax Ave Emergency Sewer Rehabilitation ProjectColfax Ave Emergency Sewer Rehabilitation Project
Colfax Ave Emergency Sewer Rehabilitation Project
 
Bradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit ProjectBradley Acres Pond Retrofit Project
Bradley Acres Pond Retrofit Project
 
Oakton Swim and Racquet Water Quality Retrofit
Oakton Swim and Racquet Water Quality RetrofitOakton Swim and Racquet Water Quality Retrofit
Oakton Swim and Racquet Water Quality Retrofit
 
Peppercorn Drive Outfall Restoration
Peppercorn Drive Outfall RestorationPeppercorn Drive Outfall Restoration
Peppercorn Drive Outfall Restoration
 

More from Fairfax County

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
Fairfax County
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
Fairfax County
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
Fairfax County
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Fairfax County
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
Fairfax County
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
Fairfax County
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Fairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
Fairfax County
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
Fairfax County
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
Fairfax County
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
Fairfax County
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Fairfax County
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
Fairfax County
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
Fairfax County
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Fairfax County
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Fairfax County
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
Fairfax County
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Fairfax County
 
Reston Fire Station #25
Reston Fire Station #25Reston Fire Station #25
Reston Fire Station #25
Fairfax County
 
Reston Arts Center Community Meeting 02-28-22
Reston Arts Center Community Meeting 02-28-22Reston Arts Center Community Meeting 02-28-22
Reston Arts Center Community Meeting 02-28-22
Fairfax County
 

More from Fairfax County (20)

Merrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer ReplacementMerrifield Nursery Emergency Gravity Sewer Replacement
Merrifield Nursery Emergency Gravity Sewer Replacement
 
SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS SULLY BASINS STORMWATER POND RETROFITS
SULLY BASINS STORMWATER POND RETROFITS
 
Clarks Crossing Road Improvements 05-13-22
 Clarks Crossing Road Improvements 05-13-22 Clarks Crossing Road Improvements 05-13-22
Clarks Crossing Road Improvements 05-13-22
 
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptxTysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
Tysons West Wastewater Conveyance Systems Modifications Project 05-22.pptx
 
Lorton Volunteer Fire Station #19
Lorton Volunteer Fire Station  #19 Lorton Volunteer Fire Station  #19
Lorton Volunteer Fire Station #19
 
Sully Community Center Construction Progress
Sully Community Center Construction ProgressSully Community Center Construction Progress
Sully Community Center Construction Progress
 
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptxRiverwood Community Meeting - 04-14-2022- Presentation.pptx
Riverwood Community Meeting - 04-14-2022- Presentation.pptx
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022Long Branch Public Meeting - FINAL - 04-11-2022
Long Branch Public Meeting - FINAL - 04-11-2022
 
Workhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick OffpptxWorkhouse Arts Stakeholder Kick Offpptx
Workhouse Arts Stakeholder Kick Offpptx
 
Workhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing CouncilWorkhouse Arts Affordable Housing Council
Workhouse Arts Affordable Housing Council
 
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
Rabbit Branch at Collingham Drive Stream Restoration - March 28, 2022.pptx
 
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
LAKE BARTON DREDGING, RESTORATION AND RISER MODIFICATION PROJECT
 
Reston Arts Community Center Feasibility - Wrap Up
 Reston Arts Community Center Feasibility - Wrap Up Reston Arts Community Center Feasibility - Wrap Up
Reston Arts Community Center Feasibility - Wrap Up
 
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
Stormwater Wastewater Facility Virtual Community Meeting, March 29, 2022
 
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022Reston Arts Center Feasibility Study Focus Group - March 28, 2022
Reston Arts Center Feasibility Study Focus Group - March 28, 2022
 
Reston Arts Center Feasibility - Focus Group Visual Arts
Reston Arts Center Feasibility -  Focus Group Visual ArtsReston Arts Center Feasibility -  Focus Group Visual Arts
Reston Arts Center Feasibility - Focus Group Visual Arts
 
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
Reston Arts Center Feasibility Focus Groups Visual, March 14, 2022
 
Reston Fire Station #25
Reston Fire Station #25Reston Fire Station #25
Reston Fire Station #25
 
Reston Arts Center Community Meeting 02-28-22
Reston Arts Center Community Meeting 02-28-22Reston Arts Center Community Meeting 02-28-22
Reston Arts Center Community Meeting 02-28-22
 

Recently uploaded

Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
PKavitha10
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
LAXMAREDDY22
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
Roger Rozario
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
sachin chaurasia
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
UReason
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
21UME003TUSHARDEB
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
cnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classicationcnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classication
SakkaravarthiShanmug
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
Anant Corporation
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
Nada Hikmah
 

Recently uploaded (20)

Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
BRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdfBRAIN TUMOR DETECTION for seminar ppt.pdf
BRAIN TUMOR DETECTION for seminar ppt.pdf
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
Data Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason WebinarData Driven Maintenance | UReason Webinar
Data Driven Maintenance | UReason Webinar
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
cnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classicationcnn.pptx Convolutional neural network used for image classication
cnn.pptx Convolutional neural network used for image classication
 
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by AnantLLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
LLM Fine Tuning with QLoRA Cassandra Lunch 4, presented by Anant
 
Curve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods RegressionCurve Fitting in Numerical Methods Regression
Curve Fitting in Numerical Methods Regression
 

Flatlick Sewer Rehabilitation Project Phase 1 and 2

  • 1. A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! Project No. WW-000007-014 C & D Sully District February 8, 2021 Flatlick Sewer Rehabilitation Project Phase 1 and 2
  • 2. Project Details Flatlick Sewer Rehabilitation Project Phase 1 & 2 Capital Facilities/Wastewater Design and Construction Division/Collections Branch Description: The Flatlick Sewer Rehabilitation Project included rehabilitation of approximately 2,500 linear feet of existing 24-inch diameter pipe and 650 linear feet of existing 15-inch diameter pipe using the Cured in Place Pipe (CIPP) lining method. The lining was cured using UV Light. In addition, 11 manholes were rehabilitated throughout the Flatlick Branch stream valley in Chantilly, Virginia. This project was substantially complete on January 4, 2021. Project Overview: • Cured-in-place pipe lining (cured using UV light) • Manhole rehabilitation using cementitious and epoxy coatings • Bypass pumping system • 3,000 linear feet of access road • Permitting: US Army Corps of Engineers Nationwide Permit #12, Virginia Department of Transportation Land Use Permit, Fairfax County Park Authority • Challenge – maintaining access roads and bypass pumping operations during flooding events Project Team: • Matt Doyle, P.E. - Wastewater Design and Construction Division • Suzy Harding, P.E. - Wastewater Design and Construction Division • Colleen Block, P. E. - Wastewater Design and Construction Division • Tom Richardson, P.E. - Wastewater Collection Division • Shwan Fatah, P.E. - Wastewater Collection Division • Arcadis - Engineer • Flippo Construction Company - Contractor
  • 3. Flatlick Sewer Rehabilitation Project Phase 1 & 2 Capital Facilities/Wastewater Design and Construction Division/Collections Branch Sully District, Tax Map No. 44-2 Project is located along Flatlick Branch from Lee Jackson Memorial Highway to Walney Road.
  • 4. Flatlick Sewer Rehabilitation Project Phase 1 & 2 Capital Facilities/Wastewater Design and Construction Division/Collections Branch Construction of Mulch & Mat Access Roads Mulch and timber-mat access roads were installed to reach the sewers in the Flatlick Branch stream valley.
  • 5. Flatlick Sewer Rehabilitation Project Phase 1 & 2 Capital Facilities/Wastewater Design and Construction Division/Collections Branch Tree Protection Tree protection
  • 6. Flatlick Sewer Rehabilitation Project Phase 1 & 2 Capital Facilities/Wastewater Design and Construction Division/Collections Branch Jersey Barriers and Steel Plates to Control Flooding Various measures were used to mitigate effects of flooding on the construction site, including Jersey Barriers and steel plates to hold matting in place.
  • 7. Flatlick Sewer Rehabilitation Project Phase 1 & 2 Capital Facilities/Wastewater Design and Construction Division/Collections Branch Bypass Pumping System Laying out bypass piping at Phase 1 Construction Entrance Bypass pumps and piping configuration at Phase 1 Construction Entrance
  • 8. Flatlick Sewer Rehabilitation Project Phase 1 & 2 Capital Facilities/Wastewater Design and Construction Division/Collections Branch Bypass Pumping System Pressure testing the bypass pumping system Piping in discharge manhole. Piping in suction manhole.
  • 9. Flatlick Sewer Rehabilitation Project Phase 1 & 2 Capital Facilities/Wastewater Design and Construction Division/Collections Branch Bypass Pumping System: Bypass Piping Bypass piping laid out along Phase 2 access road
  • 10. Flatlick Sewer Rehabilitation Project Phase 1 & 2 Capital Facilities/Wastewater Design and Construction Division/Collections Branch Manhole Rehabilitation MH 006 epoxy coating and new steps Backfilled phase 1 suction manhole Surface preparation of MH for lining
  • 11. Flatlick Sewer Rehabilitation Project Phase 1 & 2 Capital Facilities/Wastewater Design and Construction Division/Collections Branch UV Cured-in-Place Pipe Lining Equipment UV light train Video monitoring during lining operation Unloading liner
  • 12. Before After Capital Facilities/Wastewater Design and Construction Division/Collections Branch Flatlick Sewer Rehabilitation Project Phase 1 & 2 Manholes Before and after Lining Brick manhole channel Deteriorating manhole steps and concrete Rehabilitated manhole with epoxy coating of entire interior and new steps (plastic-wrap removed after epoxy application)
  • 13. Before After Capital Facilities/Wastewater Design and Construction Division/Collections Branch Flatlick Sewer Rehabilitation Project Phase 1 & 2 Sewer Pipes Before and after Lining Mild offset joints and cracks Infiltration Infiltration Deteriorated concrete: Aggregate and reinforcement visible Cured-in-place pipe: Addresses the “before” defects
  • 14. Additional Information For additional Information, please call www.fairfaxcounty.gov/publicworks Flatlick Sewer Rehabilitation Project Phase 1 & 2 Capital Facilities/Wastewater Design and Construction Division/Collections Branch Sharon North, M.A., Section Chief, Communications 703-324-8455, TTY 711 Sharon.North@fairfaxcounty.gov or Irene Haske, Communications Specialist 703-324-5821, TTY 711 Irene.Haske@fairfaxcounty.gov