Energy Capture from Waves: Final PresentationRobert Kaiser: Project ManagerJoseph Gorton: Electrical EngineerGeoffrey Hoffmann: Mechanical EngineerKyle Steets: Mechanical EngineerPeter Wassel: Mechanical Engineer
OutlineDesignsDetailed Design: Buoy Testing & AnalysisProject Management
Fall 2008 Semester
Spring 2009 Semester
Designs
“Pandora’s Box”
Buoy
Buoy: Mechanical Design
Buoy: Mechanical Design
Buoy: Mechanical Design
Buoy: Mechanical Design
Buoy: Electrical Design
Manufacturing
Wire Wrapping
Pipe Caps and Springs
Inner Pipe Spacers
Testing and analysis
Early Test ResultsTested magnets with two of Dr. Orehotsky’s coils in the Physics II LabOne (1) Magnet was able to produce approximately 1 VoltsTwo (2) Magnets were able to produce approximately 2 Volts
Demonstration Test Results: One Coil
Current Electrical Test Results:Three Coils
Mechanical Test Results
Analysis
Comparison to Solar and Wind Power
Program Management
BudgetOriginal BudgetCurrent Budget
Comparing what was budgeted and what was spentCurrent BudgetActual Money Spent
WBS Structure
Materials
Thank You! – Any Questions?

Senior Project Powerpoint