SlideShare a Scribd company logo
Establishing the Performance Measurement Baseline (PMB) The Performance Measurement Baseline is a time–phased schedule of all the work to be performed, the budgeted cost for this work, and the organizational elements that produce the deliverables from this work.  Glen B. Alleman Vice President, Strategy and Performance Management Lewis & Fowler 8310 South Valley Highway Suite 300 Englewood, Colorado 80112 www.lewisandfowler.com [email_address]
The Processes Surrounding the Performance Measurement Baseline PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Identify Needed Business Capabilities Establish a Performance Measurement Baseline Execute the Performance Measurement Baseline Capabilities Based Plan Business Value Stream Earned Value Performance Technical Performance Measures Business Value Stream Technical Requirements Establish a Requirements Baseline Technical Performance Measures PMB
There are 3 PMBs on Every Project ,[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Establish Cost Baseline Establish Schedule Baseline Establish Technical Baseline Perform Functional Analysis Determine Scope and Approach Develop Technical Logic Develop Technical Baseline Develop WBS Define Activities Estimate Time Durations Sequence Activities Finalize Schedule Identify Apportioned Milestones Determine Resource Requirements Prepare Cost Estimate Resource Load Schedule Finalize Apportioned Milestones Determine Funding Constraints Approve PMB
The Six Steps to Build the Performance Measurement Baseline PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Decompose the Project Scope into a product based Work Breakdown Structure and then into Work Packages which describe the production of all deliverables Decompose Scope Assign Responsibility for Work Packages to named owners who are accountable for the management of resource allocation and cost baseline, and technical performance Assign Responsibility Arrange the Work Packages in a well formed network with explicitly defined deliverables, milestones and internal and external dependencies Arrange Work Packages Develop Time–Phased Budget (BCWS) from labor spreads in each Work Package and balance these BCWS spreads across the Project. Develop BCWS Assign Objective Performance Measures for each Work Package and summarize these for the Project as a whole. Use the 0%/100% measurement of complete whenever possible. Assign Performance Measures Establish a Performance Measurement Baseline to be used forecasting Work Package and Project ongoing and completion metrics. Set Performance Baseline
These Definitions Will Help Clarify What We’re Talking About ,[object Object],[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Critical Success Factors For The Performance Measurement Baseline ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Success Of The PMB Depends On Identifying Measureable Results PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. What gets measured gets done 1 If you don’t measure results, you can’t tell success from failure 2 If you can’t see success, you can’t reward it 3 If you can’t reward success, you’re probably rewarding failure 4 If you can demonstrate results, you can remain credible 7 If you can’t see success, you can’t learn from it 5 If you can’t see failure, you can’t correct it 6
Decompose The Scope Into A Proper “Tree” PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Business Capability Process Invoices for Top Tier Suppliers 1 st  Level Electronic Invoice Submittal  1 st  Level Routing to Payables Department 2 nd  Level Payables Account Verification  2nd Level Payment Scheduling  2 nd  Level Material receipt verification 2nd Level “ On hand” balance Updates
Use This “Tree” To Decompose The  Project Scope Into Work Packages ,[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc.
What Does A Good Work Package  “NOT” Look Like? PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. What NOT to do Instead Think About It’s NOT a laundry list of work to be done It’s a decomposition of the products, services, and data generated by those It’s NOT a functional decomposition That’s the role of the Organizational Breakdown Structure (OBS) It’s NOT a direct map of the requirements Requirements produce products and services, but are not one for one with the WBS It’s NOT a reflection of the underlying product or service partitioning This is done later in the program strategy It’s NOT the first structure you might think of… Build the WBS several times, assess its usefulness in describing the products and services
What Is “NOT” In A Work Package? ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Some Attributes Of A Good Work Package ,[object Object],[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc.
A Deliverables Focused Work Breakdown Structure (WBS) ,[object Object],[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc.
The Work Breakdown Structure  Connections With The Work Packages ,[object Object],[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. The WBS becomes the framework for Cost, Schedule, and Technical Performance Measurement. The WBS is the organizational structure for the Work Packages
Connect The WBS To Work Packages And Then Define The Tasks To Produce The Deliverables PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Deliverables WBS Tasks and Schedule Business Need Process Invoices for Top Tier Suppliers 1 st  Level Electronic Invoice Submittal  1 st  Level Routing to Payables Department 2 nd  Level Payables Account Verification  2nd Level Payment Scheduling  2 nd  Level Material receipt verification 2nd Level “ On hand” balance Updates Work  Package 1 2 3 4 6 5 A B Deliverables defined in WP Terminal Node in the WBS defines the products or services of the project Terminal node of the WBS defined by a Work Package Tasks within the Work Package produce the Deliverables 100% Completion of deliverables is the measure of performance for the Work Package Management of the Work Package Tasks is the responsibility of the WP Manager. These are not held in the master plan A decomposition of the work needed to fulfill the business requirements
Steps In Building The Work Packages ,[object Object],[object Object],[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Decompose Business Capabilities Into Deliverables, Then Work Packages, Then Measurable Outcomes PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Business Capabilities Capability Number 1 Capability Number 2 Deliverable Number 1.1 Deliverable Number 1.2 Deliverable Number 1.3 Deliverable Number 1.4 Work Package Number 1 Work Package Number 2 Work Package Number 3 50% Milestone 50% Milestone 100% Milestone 100% Milestone Deliverable Number 2.1 Work Package Number 4 100% Milestone Deliverable Number 2.1 Deliverable Number 2.1 Work Package Number 5 25% Milestone 75% Milestone Increasing Detail of the Planning Outcomes Increasing Value to the Customer
Step 1: Define The Deliverables And Their Apportioned Value PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Description Deliverable(s) Apportioned Milestones Transaction processing integration test complete ,[object Object],[object Object],[object Object],Define integration testing environment ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Business processes defined and approved ,[object Object],[object Object],User acceptance testing defined ,[object Object],[object Object],User Acceptance Testing Conducted ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Step 2: Define The Effort, Duration, And Confidence Intervals PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Baseline Contents of a Work Package ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. In theory there is no difference between theory and practice. In practice there is.
Use Word Or Excel, It Doesn’t Matter  Just Capture The Contents In One Place PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. No matter what  form  is used, the  function  of the Work Package must communicate to the participants the baseline information described in the Table of Contents of the previous page.
Naming Work Packages May Seem Simple –  But What’s In A Name? ,[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Maturity Action Product Product State Adjective Verb Noun Verb Demonstrates Maturity A step in the process End Item Final Status Preliminary Design Processes Complete Preliminary design of transaction processes complete
Work Package Description ,[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. If you can’t tell the story between the lobby and the 9 th  floor, then you haven't got a clear picture of what “done” looks like.
Assumptions ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Assumptions are repulsive, especially to gravity.
Earned Value Method ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Earned Value is how physical progress is measured in the Performance Measurement Baseline. Only delivered value to the customer is important.
Responsibilities ,[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. WBS OBS The Work Packages are where the work and the people come together
Assign The Responsibilities And Make A Single Person Accountable PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Arrange The Work Packages Into A “Well Formed” Network PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. 2 nd  Level Payables Account Verification 2 nd  Level Payment Scheduling 2 nd  Level Material receipt verification 2 nd  Level “ On hand” balance Updates
A “Well Formed” Network Has Specific Attributes ,[object Object],[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc.
“ Arranging” the Work Packages Is Iterative And Incremental PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. In the example above, the Work Package Managers collectively come to an agreement on how the sequence of how the work will be performed.  The result is a collective ownership of the outcome. This ownership comes from the collective development of the project plan. This process is a Product Development Kaizen (PDK)
Develop A Time–Phased Budget PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. 2 nd  Level System Payables Account Verification 2 nd  Level System Payment Scheduling 2 nd  Level System Material receipt verification 2 nd  Level System “ On hand” balance Updates Duration of the Work Package BCWS Duration of the Work Package BCWS Duration of the Work Package BCWS Duration of the Work Package BCWS
Balance All The Work Across The Project Before Setting The Baseline PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Identify Objective Measures Of Performance For Each Work Package ,[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Set The Performance Baseline ,[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. There are two phases of any complex project …  Too early to tell and too late to stop
Build The Apportioned Milestones And Assign Physical Percent Complete ,[object Object],[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. 1 mile = 1,000 (mille) paces  = 1,640 yards .  Introduced to Britain by the Romans The passage of a milestone meant progress to the destination. But it is critical to pre-assign value to each milestone and record this value as the milestone is passed
Assemble The Work Packages Into A Credible Schedule ,[object Object],[object Object],[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Henry Laurence Gantt, A.B., M.E 1861–1919
Project Maturity Flow Is The Incremental Delivery Of Business Capabilities  PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Pilot Data Enrollment Integrators Quality Monitor Internal Router External Interfaces Finance Loss Data Store Lookup Data Warehouse Data Marts Data Marts Portals and others Billing Resale's Emulations Demo conversion process, member reconciliation Shared group matrix reports and interfaces Shared member crosswalk and members to ERP Integrators in ERP converted to inventory Status and trigger conversions Data in Marts for ERP Material Master Converted from legacy External Vendors converted to ERP TBD Vendors from legacy Material converted end–to–end
Analyzing And Assessing The Network Of Work Packages Requires Understanding ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. A credible schedule cannot be just a list of activities. It must be an accurate model of the project strategy and execution that can be analyzed, assessed, and used to answer risk based questions.
A “Very” Simple Risk Management Process Is Needed To Establish Credibility PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Planning Identification Analysis Handling Communication and  Tracking ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],“ Risk Analysis Techniques, Schedule, Cost and Other Aspects, INCOSE Heartland Chapter October 24, 2001, Futon Corporation
Integrating Cost, Schedule, And Technical Performance PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Cost, Schedule, Technical Model † WBS Task 100 Task 101 Task 102 Task 103 Task 104 Task 105 Task 106 † This is a Key concept. This is the part of the process that integrates the cost and schedule risk impacts to provide the basis of a credible schedule. Probability Density Function ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],Monte Carlo Simulation Tool is Mandatory 1.0 .8 .6 .4 .2 0 Days, Facilities, Parts, People Cumulative Distribution Function Days, Facilities, Parts and People
There Is Technical And Programmatic Risk – Both Must Be Addressed ,[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. So much for our strategy of winning through technical dominance
Wrap Up PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. A good plan, violently executed now is better than a perfect plan executed next week –  General George S. Patton
In The End Its All About The Schedule ,[object Object],[object Object],[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc.
Troubled Projects Always Have A Common Set Of Attributes ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],PMI  College of  Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. A ship on the beach is a lighthouse to the sea – Dutch Proverb

More Related Content

What's hot

Project management
Project managementProject management
Project management
Yasir Afzal Rajput
 
Introduction to Project Management.pdf
Introduction to Project Management.pdfIntroduction to Project Management.pdf
Introduction to Project Management.pdf
GourhariBiswas1
 
Preparing for pmi ba exam
Preparing for pmi ba examPreparing for pmi ba exam
Preparing for pmi ba exam
MAX Technical Training
 
Program management audit checklist
Program management audit checklistProgram management audit checklist
Program management audit checklist
Bob Prieto
 
Project Initiation and Scoping
Project Initiation and ScopingProject Initiation and Scoping
Project Initiation and Scoping
Ciprian Rusen
 
PMO (Project Management Office)
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)
Dilawar Abbas
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS project
Samir Paralikar
 
Introduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardIntroduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid Hamdard
Javid Hamdard
 
PMO 101
PMO 101PMO 101
PMO 101
shailsood
 
The Modern PMO
The Modern PMOThe Modern PMO
The Modern PMO
PMI-Montréal
 
3. Project Management A Case Study Of A Successful Erp Implementation
3. Project Management A Case Study Of A Successful Erp Implementation3. Project Management A Case Study Of A Successful Erp Implementation
3. Project Management A Case Study Of A Successful Erp ImplementationDonovan Mulder
 
How to Start a Project
How to Start a ProjectHow to Start a Project
How to Start a Project
Craig Brown
 
The pmo strategy discipline execution value
The pmo   strategy discipline execution valueThe pmo   strategy discipline execution value
The pmo strategy discipline execution valueOrlando Lugo
 
Setting up a pmo
Setting up a pmoSetting up a pmo
Setting up a pmo
crmackenzie
 
Pmp slide share
Pmp slide sharePmp slide share
Pmp slide share
saleem54
 
An Introduction to Benefits Realization Management
An Introduction to Benefits Realization ManagementAn Introduction to Benefits Realization Management
An Introduction to Benefits Realization Management
Craig Letavec
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
Soe Naing Win
 
How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)
Insaf Ali Soomro PMP
 
Introduction to project management( framework and processes )
Introduction to project management( framework and processes )Introduction to project management( framework and processes )
Introduction to project management( framework and processes )
Qussay Karam
 

What's hot (20)

Project management
Project managementProject management
Project management
 
Introduction to Project Management.pdf
Introduction to Project Management.pdfIntroduction to Project Management.pdf
Introduction to Project Management.pdf
 
Preparing for pmi ba exam
Preparing for pmi ba examPreparing for pmi ba exam
Preparing for pmi ba exam
 
Program management audit checklist
Program management audit checklistProgram management audit checklist
Program management audit checklist
 
Project Initiation and Scoping
Project Initiation and ScopingProject Initiation and Scoping
Project Initiation and Scoping
 
PMO (Project Management Office)
PMO (Project Management Office)PMO (Project Management Office)
PMO (Project Management Office)
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS project
 
Introduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid HamdardIntroduction to Project Management by Javid Hamdard
Introduction to Project Management by Javid Hamdard
 
PMO 101
PMO 101PMO 101
PMO 101
 
The Modern PMO
The Modern PMOThe Modern PMO
The Modern PMO
 
3. Project Management A Case Study Of A Successful Erp Implementation
3. Project Management A Case Study Of A Successful Erp Implementation3. Project Management A Case Study Of A Successful Erp Implementation
3. Project Management A Case Study Of A Successful Erp Implementation
 
How to Start a Project
How to Start a ProjectHow to Start a Project
How to Start a Project
 
The pmo strategy discipline execution value
The pmo   strategy discipline execution valueThe pmo   strategy discipline execution value
The pmo strategy discipline execution value
 
Setting up a pmo
Setting up a pmoSetting up a pmo
Setting up a pmo
 
Pmp slide share
Pmp slide sharePmp slide share
Pmp slide share
 
PMP
PMPPMP
PMP
 
An Introduction to Benefits Realization Management
An Introduction to Benefits Realization ManagementAn Introduction to Benefits Realization Management
An Introduction to Benefits Realization Management
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)
 
Introduction to project management( framework and processes )
Introduction to project management( framework and processes )Introduction to project management( framework and processes )
Introduction to project management( framework and processes )
 

Similar to Establishing the Performance Measurement Baseline

Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement Baseline
Glen Alleman
 
Deliverables based planning
Deliverables based planning Deliverables based planning
Deliverables based planning
Glen Alleman
 
Establishing the performance measurement baseline (pmi northern utah)(v1)
Establishing the performance measurement baseline (pmi northern utah)(v1)Establishing the performance measurement baseline (pmi northern utah)(v1)
Establishing the performance measurement baseline (pmi northern utah)(v1)
Glen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
Glen Alleman
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baseline
guest9da059
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baseline
Glen Alleman
 
IIBA Basel Event March 2016 - Case Study Agile Waterfall.pptx
IIBA Basel Event March 2016 - Case Study Agile Waterfall.pptxIIBA Basel Event March 2016 - Case Study Agile Waterfall.pptx
IIBA Basel Event March 2016 - Case Study Agile Waterfall.pptx
ssuser991a01
 
Sameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle itSameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle it
Sameer Mitter
 
Pmp Five Sample Questions
Pmp Five Sample QuestionsPmp Five Sample Questions
Pmp Five Sample Questions
OSP International LLC
 
Pm0011 project planning and scheduling
Pm0011 project planning and schedulingPm0011 project planning and scheduling
Pm0011 project planning and scheduling
consult4solutions
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value Management
Glen Alleman
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
Glen Alleman
 
Kenneth Luster resume 2016
Kenneth Luster resume 2016Kenneth Luster resume 2016
Kenneth Luster resume 2016
Kenneth Luster
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure Cycle
Glen Alleman
 
The Power of Business Process Improvement
The Power of Business Process ImprovementThe Power of Business Process Improvement
The Power of Business Process Improvement
Business Book Summaries
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement Baseline
Glen Alleman
 
Earned Value + Agile = Success
Earned Value + Agile = SuccessEarned Value + Agile = Success
Earned Value + Agile = Success
Glen Alleman
 

Similar to Establishing the Performance Measurement Baseline (20)

Establishing the Performance Measurement Baseline
Establishing the Performance Measurement BaselineEstablishing the Performance Measurement Baseline
Establishing the Performance Measurement Baseline
 
Deliverables based planning
Deliverables based planning Deliverables based planning
Deliverables based planning
 
Establishing the performance measurement baseline (pmi northern utah)(v1)
Establishing the performance measurement baseline (pmi northern utah)(v1)Establishing the performance measurement baseline (pmi northern utah)(v1)
Establishing the performance measurement baseline (pmi northern utah)(v1)
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baseline
 
How To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement BaselineHow To Build A Credible Performance Measurement Baseline
How To Build A Credible Performance Measurement Baseline
 
IIBA Basel Event March 2016 - Case Study Agile Waterfall.pptx
IIBA Basel Event March 2016 - Case Study Agile Waterfall.pptxIIBA Basel Event March 2016 - Case Study Agile Waterfall.pptx
IIBA Basel Event March 2016 - Case Study Agile Waterfall.pptx
 
Sameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle itSameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle it
 
BAs IIBA and the BABOK
BAs IIBA and the BABOKBAs IIBA and the BABOK
BAs IIBA and the BABOK
 
PMP Exam Sample Questions
PMP Exam Sample QuestionsPMP Exam Sample Questions
PMP Exam Sample Questions
 
Pmp Five Sample Questions
Pmp Five Sample QuestionsPmp Five Sample Questions
Pmp Five Sample Questions
 
Pm0011 project planning and scheduling
Pm0011 project planning and schedulingPm0011 project planning and scheduling
Pm0011 project planning and scheduling
 
Integrating Agile and Earned Value Management
Integrating Agile and Earned Value ManagementIntegrating Agile and Earned Value Management
Integrating Agile and Earned Value Management
 
Earned Value Management and Agile
Earned Value Management and AgileEarned Value Management and Agile
Earned Value Management and Agile
 
PMP Exam Sample Questions Set 6
PMP Exam Sample Questions Set 6PMP Exam Sample Questions Set 6
PMP Exam Sample Questions Set 6
 
Kenneth Luster resume 2016
Kenneth Luster resume 2016Kenneth Luster resume 2016
Kenneth Luster resume 2016
 
Breaking the Project Failure Cycle
Breaking the Project Failure CycleBreaking the Project Failure Cycle
Breaking the Project Failure Cycle
 
The Power of Business Process Improvement
The Power of Business Process ImprovementThe Power of Business Process Improvement
The Power of Business Process Improvement
 
Building A Credible Measurement Baseline
Building A Credible Measurement BaselineBuilding A Credible Measurement Baseline
Building A Credible Measurement Baseline
 
Earned Value + Agile = Success
Earned Value + Agile = SuccessEarned Value + Agile = Success
Earned Value + Agile = Success
 

More from Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
Glen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
Glen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
Glen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
Glen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
Glen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
Glen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
Glen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
Glen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
Glen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
Glen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
Glen Alleman
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
Glen Alleman
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
Glen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
Glen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
Glen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
Glen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
Glen Alleman
 

More from Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 

Recently uploaded

GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
Sri Ambati
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Inflectra
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
UiPathCommunity
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
Product School
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
Product School
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
Product School
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
Safe Software
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
Alison B. Lowndes
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
Product School
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
DianaGray10
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
ThousandEyes
 
Elevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object CalisthenicsElevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object Calisthenics
Dorra BARTAGUIZ
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
Paul Groth
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
OnBoard
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Thierry Lestable
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
Thijs Feryn
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Jeffrey Haguewood
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
DianaGray10
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 

Recently uploaded (20)

GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
 
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
De-mystifying Zero to One: Design Informed Techniques for Greenfield Innovati...
 
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdfFIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
FIDO Alliance Osaka Seminar: Passkeys and the Road Ahead.pdf
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
 
Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........Bits & Pixels using AI for Good.........
Bits & Pixels using AI for Good.........
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
 
UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4UiPath Test Automation using UiPath Test Suite series, part 4
UiPath Test Automation using UiPath Test Suite series, part 4
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
 
Elevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object CalisthenicsElevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object Calisthenics
 
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMsTo Graph or Not to Graph Knowledge Graph Architectures and LLMs
To Graph or Not to Graph Knowledge Graph Architectures and LLMs
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 

Establishing the Performance Measurement Baseline

  • 1. Establishing the Performance Measurement Baseline (PMB) The Performance Measurement Baseline is a time–phased schedule of all the work to be performed, the budgeted cost for this work, and the organizational elements that produce the deliverables from this work. Glen B. Alleman Vice President, Strategy and Performance Management Lewis & Fowler 8310 South Valley Highway Suite 300 Englewood, Colorado 80112 www.lewisandfowler.com [email_address]
  • 2. The Processes Surrounding the Performance Measurement Baseline PMI College of Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Identify Needed Business Capabilities Establish a Performance Measurement Baseline Execute the Performance Measurement Baseline Capabilities Based Plan Business Value Stream Earned Value Performance Technical Performance Measures Business Value Stream Technical Requirements Establish a Requirements Baseline Technical Performance Measures PMB
  • 3.
  • 4. The Six Steps to Build the Performance Measurement Baseline PMI College of Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Decompose the Project Scope into a product based Work Breakdown Structure and then into Work Packages which describe the production of all deliverables Decompose Scope Assign Responsibility for Work Packages to named owners who are accountable for the management of resource allocation and cost baseline, and technical performance Assign Responsibility Arrange the Work Packages in a well formed network with explicitly defined deliverables, milestones and internal and external dependencies Arrange Work Packages Develop Time–Phased Budget (BCWS) from labor spreads in each Work Package and balance these BCWS spreads across the Project. Develop BCWS Assign Objective Performance Measures for each Work Package and summarize these for the Project as a whole. Use the 0%/100% measurement of complete whenever possible. Assign Performance Measures Establish a Performance Measurement Baseline to be used forecasting Work Package and Project ongoing and completion metrics. Set Performance Baseline
  • 5.
  • 6.
  • 7. Success Of The PMB Depends On Identifying Measureable Results PMI College of Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. What gets measured gets done 1 If you don’t measure results, you can’t tell success from failure 2 If you can’t see success, you can’t reward it 3 If you can’t reward success, you’re probably rewarding failure 4 If you can demonstrate results, you can remain credible 7 If you can’t see success, you can’t learn from it 5 If you can’t see failure, you can’t correct it 6
  • 8. Decompose The Scope Into A Proper “Tree” PMI College of Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Business Capability Process Invoices for Top Tier Suppliers 1 st Level Electronic Invoice Submittal 1 st Level Routing to Payables Department 2 nd Level Payables Account Verification 2nd Level Payment Scheduling 2 nd Level Material receipt verification 2nd Level “ On hand” balance Updates
  • 9.
  • 10. What Does A Good Work Package “NOT” Look Like? PMI College of Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. What NOT to do Instead Think About It’s NOT a laundry list of work to be done It’s a decomposition of the products, services, and data generated by those It’s NOT a functional decomposition That’s the role of the Organizational Breakdown Structure (OBS) It’s NOT a direct map of the requirements Requirements produce products and services, but are not one for one with the WBS It’s NOT a reflection of the underlying product or service partitioning This is done later in the program strategy It’s NOT the first structure you might think of… Build the WBS several times, assess its usefulness in describing the products and services
  • 11.
  • 12.
  • 13.
  • 14.
  • 15. Connect The WBS To Work Packages And Then Define The Tasks To Produce The Deliverables PMI College of Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Deliverables WBS Tasks and Schedule Business Need Process Invoices for Top Tier Suppliers 1 st Level Electronic Invoice Submittal 1 st Level Routing to Payables Department 2 nd Level Payables Account Verification 2nd Level Payment Scheduling 2 nd Level Material receipt verification 2nd Level “ On hand” balance Updates Work Package 1 2 3 4 6 5 A B Deliverables defined in WP Terminal Node in the WBS defines the products or services of the project Terminal node of the WBS defined by a Work Package Tasks within the Work Package produce the Deliverables 100% Completion of deliverables is the measure of performance for the Work Package Management of the Work Package Tasks is the responsibility of the WP Manager. These are not held in the master plan A decomposition of the work needed to fulfill the business requirements
  • 16.
  • 17. Decompose Business Capabilities Into Deliverables, Then Work Packages, Then Measurable Outcomes PMI College of Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Business Capabilities Capability Number 1 Capability Number 2 Deliverable Number 1.1 Deliverable Number 1.2 Deliverable Number 1.3 Deliverable Number 1.4 Work Package Number 1 Work Package Number 2 Work Package Number 3 50% Milestone 50% Milestone 100% Milestone 100% Milestone Deliverable Number 2.1 Work Package Number 4 100% Milestone Deliverable Number 2.1 Deliverable Number 2.1 Work Package Number 5 25% Milestone 75% Milestone Increasing Detail of the Planning Outcomes Increasing Value to the Customer
  • 18.
  • 19. Step 2: Define The Effort, Duration, And Confidence Intervals PMI College of Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 20.
  • 21. Use Word Or Excel, It Doesn’t Matter Just Capture The Contents In One Place PMI College of Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. No matter what form is used, the function of the Work Package must communicate to the participants the baseline information described in the Table of Contents of the previous page.
  • 22.
  • 23.
  • 24.
  • 25.
  • 26.
  • 27. Assign The Responsibilities And Make A Single Person Accountable PMI College of Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 28. Arrange The Work Packages Into A “Well Formed” Network PMI College of Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. 2 nd Level Payables Account Verification 2 nd Level Payment Scheduling 2 nd Level Material receipt verification 2 nd Level “ On hand” balance Updates
  • 29.
  • 30. “ Arranging” the Work Packages Is Iterative And Incremental PMI College of Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. In the example above, the Work Package Managers collectively come to an agreement on how the sequence of how the work will be performed. The result is a collective ownership of the outcome. This ownership comes from the collective development of the project plan. This process is a Product Development Kaizen (PDK)
  • 31. Develop A Time–Phased Budget PMI College of Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. 2 nd Level System Payables Account Verification 2 nd Level System Payment Scheduling 2 nd Level System Material receipt verification 2 nd Level System “ On hand” balance Updates Duration of the Work Package BCWS Duration of the Work Package BCWS Duration of the Work Package BCWS Duration of the Work Package BCWS
  • 32. Balance All The Work Across The Project Before Setting The Baseline PMI College of Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc.
  • 33.
  • 34.
  • 35.
  • 36.
  • 37. Project Maturity Flow Is The Incremental Delivery Of Business Capabilities PMI College of Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. Pilot Data Enrollment Integrators Quality Monitor Internal Router External Interfaces Finance Loss Data Store Lookup Data Warehouse Data Marts Data Marts Portals and others Billing Resale's Emulations Demo conversion process, member reconciliation Shared group matrix reports and interfaces Shared member crosswalk and members to ERP Integrators in ERP converted to inventory Status and trigger conversions Data in Marts for ERP Material Master Converted from legacy External Vendors converted to ERP TBD Vendors from legacy Material converted end–to–end
  • 38.
  • 39.
  • 40.
  • 41.
  • 42. Wrap Up PMI College of Scheduling “ PMI” is a registered trade and service mark of the Project Management Institute, Inc. A good plan, violently executed now is better than a perfect plan executed next week – General George S. Patton
  • 43.
  • 44.

Editor's Notes

  1. Thank you for the invitation to speak today. The topic of a Performance Measurement Baseline may sound a bit arcane to some parts of the project management community. In the defense and aerospace community is contractually obligated to manage programs using the Performance Measurement Baseline. So how can we learn from experiences outside of defense and aerospace? This talk is a very quick tour of a larger problem found in all projects – “how do we know when we are done?” and “how can we tell we are actually making progress toward the ‘getting done’ part of the project?” In the 44 slides today we will cover the six steps in defining the performance measurement baseline and a description of what to do with the baseline once you have it. Our Learning Objectives today include: The development of the Performance Measurement Baseline (PMB) is a Practice based on Principles . The Principles come first, then the Practice . Without the Principles a PM might be able to produce a PMB, but with the Principles the PMB can produce a better PMB. The key to success in the Practice of PMB is to know the difference between doing something and doing something for the right reasons. The role of a Principle is to guide the development of Practice . With Principles the Practice becomes clear and can be generalized to broader situations, improved on to make the Practice better, while maintaining the core Principles.