SlideShare a Scribd company logo
Table of contents 
1. General. 
2. Management Organization Chart 
3. Sequence of works (beam & slab). 
4. Formwork design. 
5. Construction joint treatment. 
6. Re bars fabrication & setting. 
7. Installation of embed item. 
8. Placing of concrete. 
9. Compaction of concrete. 
10.Removal of formworks 
11.Curing 
12.Protecting against raining 
13.Electricity 
14.Equipment & Manpower 
15.Safety measure 
Appendix 
A. General plan and elevation 
B. Typical formworks & Scaffolding arrangement. 
C. Calculation for formwork and support systems 
D. Safety Procedure 
1. General
This method statement describes how we carry out the concrete works of superstructure 
in building works. 
Concrete class shall be approved ready-mix concrete Grade 35MN/m2 
Please refer to Appendix A for general plan and elevation of three main building. 
2. Management Organization Chart 
Mr. N.N.Hai 
HSE Manager 
Mr. Tran Thanh Minh 
Site Engineer 
Mr. Hoang Hung 
Site Engineer 
Sub Contractor Sub Contractor 
2.1 Project Manager 
Mr. T. UCHIDA 
Project Manager 
Mr. A . IKEGAMI 
Construction 
Manager 
Mr. A.M. Cabonce 
QA/QC Manager 
Mr. K.Miyara 
Chief Engineer 
Mr. P. C. TRUNG 
Chief site Engineer 
Mr. Dang Trong Dung 
Site Engineer 
Sub Contractor 
· To oversee and control all aspects of the Piling activities, and dictate schedule 
requirements 
· To ensure that all field staff are fully aware of the requirements of this method 
statement, and that these requirements, in all respects, are fully implemented. 
· To ensure that Safety and Environmental procedures, particularly, are in place 
before activity commences, and strictly complied with, throughout the duration 
of concreting works.
2.2 Construction Managers, directly reports to Project Manager. 
· To oversee all construction works, with respect to schedule. 
· To ensure that all field staff follow the requirements of this method statement, 
including quality control and HSE. 
2.3 Chief Engineer, reports to Construction Manager 
· To ensure that all relevant preparations have been made. 
· To ensure that all provisions of this method statement are followed. 
· To ensure that all quality inspection is carried out and record taken, if 
required. 
· To ensure that all necessary safety and environmental precautions are in 
place and that all workers under their direct control are fully aware of all 
procedure requirements 
· To control execution of the entire activity 
2.4 Site Engineer 
· To assist Chief Engineer to control the Subcontractor for all activities relative 
to this method statement. 
· To ensure safe working environment at all times, during Subcontractor 
execution of concreting works. 
2.5 Surveyor 
· To give control points & grid line to Subcontractor for concreting works. 
· To supervise Subcontractor and conduct survey checks from time to time. 
· To carry out all surveying work and to ensure all required records are taken 
and maintained. 
2.6 QA/QC department 
· To oversee construction activity with respect to quality control. 
· To ensure quality procedures has been followed.
· To ensure that all required inspections have been carried out and that 
records, if required have been taken and properly stored. 
· Advise the laboratory and Site Engineers to control the quality of works. 
2.7 Health, Safety & Environmental department 
· To monitor that all the working activities are executed in accordance with site 
safety procedures. 
· To ensure that precautions with respect to Environmental matters have been 
implemented on site. 
3. Sequence of works (beam & slab). 
Setting Staging for Construction 
Area 
Setting Support & Bottom 
Formwork 
Construction Joint Treatment 
Inspection for Construction 
Joint 
Assembling re bar 
Inspection of re bar 
Setting Side Formwork
Inspection for casting 
concrete 
Placing Concrete 
Curing 
Stripping of Form 
Stripping Support and Prop after 
Getting Design Strength 100% 
4. Formworks Design 
Formwork shall be set in correct position following specification and the approved 
structure drawings. 
Please refer to Appendix B for Typical formworks & support for 2nd floor slab. 
Formworks and support is calculated as shown in Attachment C 
Approved form oil will be applied to form surface prior to installation of form. 
5. Construction joint treatment 
All construction joints will be chipped to remove cement sand surface to make rough 
surface.
In some cases, approved retarder for concrete surface will be used as another method 
to make construction joint properly. 
6. Rebar fabrication & setting 
Approved re-bar type will be delivered to site and it will be inspected & tested prior to 
use. 
Re-bar shall be cut and bent according to the approved schedule at the site workshop 
and transported to site by truck. After delivery to the site re-bars shall be fixed according 
to specification and approved drawings by Engineer or Consultant. 
Rebar shall be inspected by Engineer or Consultant prior to install of next layer or 
formworks. 
Any mistake rebar will be replaced or repaired by approved method. 
Approved concrete spacer shall be used; its concrete grade shall be 35 MN/m2. 
7. Installation of embed item 
All the embed item showing in the drawings shall be firmly installed in correct position. 
8. Placing of Concrete 
Approved ready-mix concrete will be transported from batching plant to the site by mixer 
truck. During transportation & waiting time the concrete shall be kept continuously 
agitated. 
From mixer truck concrete will be poured to casting location by concrete pump or by 
bucket. The height from discharge position to casting level shall not be over 1.5m. 
On each concreting day and for each grade of concrete mix, samples shall be taken. 
When samples are taken at sites, samples shall be taken for every 24m3 of concrete or 
part thereof, of each grade of concrete. 
Minimum requirement of sample
- Each concreting day 
- Each part of structure (each building) 
- After filling above condition, samples shall be taken for every four mixer or 
agitating truck (20~24m2). 
9. Compaction of Concrete. 
Concrete after pouring to position shall be compacted by immersion vibrator. Proper 
staging for vibration works will be arranged. 
Wooden or rubber hammer also will be used as external vibrator in some cases. 
10. Removal of formworks 
Form works removal shall be accordance with specification Clause 4.20 or as proposal 
hereunder. 
- All vertical or side formworks : 12 hrs (The period shall commence from the time 
of last pour of concrete) 
- Soffit formworks to slabs & beams : 3 days ((The period shall commence from the 
time of last pour of concrete) 
- Props to slabs & beams: Requirement in Specification is 14 days. We propose 
that before remove props we will carry out testing for cube sample, whenever if 
we get 100% designed strength of concrete we will remove props (After skirting of 
formworks, props shall be immediately put up to support the structure) 
- Props to cantilever slabs & cantilever beams: Requirement in Specification is 21 
days. We propose that before remove props we will carry out testing for cube 
sample, whenever if we get 100% designed strength of concrete we will remove 
props (After skirting of formworks, props shall be immediately put up to support 
the structure)
* Testing for purpose of removal formworks will be carried out at 7th days after finish 
casting concrete. 
All tie rod holes & defects on surface will be repaired following approved method. 
11. Curing. 
After removal of form works, concrete shall be cured minimum of 6 days according to 
TCXDVN 391:2007– Requirements for Natural Moist Curing, apply for Area C of Viet 
Nam. 
Curing of concrete will be carried out by spraying water periodically to the surface of the 
newly placed concrete. Jute bag or nylon sheet shall be used to cover the concrete 
surface for keeping wet. 
Water to be used for curing and cleaning works is portable water from local authority. 
Approved curing compound also will be used in several cases. 
12. Protecting against raining. 
Against raining, plastic sheet shall be prepared to cover over the concrete area before 
concreting. 
13. Electricity 
Electricity will be supplied by generators on site. 
14. Equipment & Manpower 
a)Equipment 
Equipment Unit Quantity 
Mixer truck Nos 04 
Vibrator Nos 03 
Concrete Pump No 01 
Generator 15KVA No 01 
Generator 10KVA Nos 02 
Bucket Nos 10 
Showel Nos 05 
Trowel Nos 05
b)Manpower 
Description Unit Quantity 
Supervisor No 01 
Surveyor Nos 02 
Foreman No 01 
Electrician No 01 
Worker Nos 10 
15. Safety measure 
Please refer to Appendix D for Safety Procedure when working at high position
APPENDIX A 
GENERAL PLAN & ELEVATION
APPENDIX B 
FORMWORKS & 
SCAFFOLDING ARRANGEMENT
APPENDIX C 
CALCULATION FOR FORMWORKS & SUPPORT
APPENDIX D 
SAFETY PROCEDURE

More Related Content

What's hot

Method of Statement - Pavement works
Method of Statement - Pavement worksMethod of Statement - Pavement works
Method of Statement - Pavement works
Mohd Nizam Mohd Zan
 
Method statement for civil works
Method statement for civil worksMethod statement for civil works
Method statement for civil works
Muhammad Shahid
 
Erection of structural components in precast constructions
Erection of structural components in precast constructionsErection of structural components in precast constructions
Erection of structural components in precast constructions
ParamaAthmeka
 
Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequenceRanjith Kumar
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001Minh Bui Si
 
Method stm lean concrete
Method stm lean concreteMethod stm lean concrete
Method stm lean concreteMinh Bui Si
 
Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015
HaGun Gunawan
 
Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paintMinh Bui Si
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
Mereia Kali
 
Method statement for expansion joint
Method statement for expansion jointMethod statement for expansion joint
Method statement for expansion joint
akash yadav
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTmustafa hussain
 
Erection method statement
Erection method statementErection method statement
Erection method statement
kanalbiru
 
Method aluminum door & window
Method aluminum door & windowMethod aluminum door & window
Method aluminum door & windowMinh Bui Si
 
Construction phases
Construction phasesConstruction phases
Construction phases
Meesum Zaidi
 
Construction activities and Process
Construction activities and ProcessConstruction activities and Process
Construction activities and ProcessIbrahim Adhnan
 
Site visit report qs semester 1
Site visit report   qs semester 1Site visit report   qs semester 1
Site visit report qs semester 1
KhangWei Chin
 
Demolition of Structures.
Demolition of Structures.Demolition of Structures.
Demolition of Structures.
Chintan Varia
 

What's hot (20)

Method of Statement - Pavement works
Method of Statement - Pavement worksMethod of Statement - Pavement works
Method of Statement - Pavement works
 
Casting yard
Casting yardCasting yard
Casting yard
 
Method statement for civil works
Method statement for civil worksMethod statement for civil works
Method statement for civil works
 
Erection of structural components in precast constructions
Erection of structural components in precast constructionsErection of structural components in precast constructions
Erection of structural components in precast constructions
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Demolition methods and its sequence
Demolition methods and its sequenceDemolition methods and its sequence
Demolition methods and its sequence
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
Method stm lean concrete
Method stm lean concreteMethod stm lean concrete
Method stm lean concrete
 
Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015Method of works install stator generator+strand jack + 07 july2015
Method of works install stator generator+strand jack + 07 july2015
 
Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paint
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 
Column & beam
Column & beamColumn & beam
Column & beam
 
Method statement for expansion joint
Method statement for expansion jointMethod statement for expansion joint
Method statement for expansion joint
 
ERECTION METHOD STATEMENT
ERECTION METHOD STATEMENTERECTION METHOD STATEMENT
ERECTION METHOD STATEMENT
 
Erection method statement
Erection method statementErection method statement
Erection method statement
 
Method aluminum door & window
Method aluminum door & windowMethod aluminum door & window
Method aluminum door & window
 
Construction phases
Construction phasesConstruction phases
Construction phases
 
Construction activities and Process
Construction activities and ProcessConstruction activities and Process
Construction activities and Process
 
Site visit report qs semester 1
Site visit report   qs semester 1Site visit report   qs semester 1
Site visit report qs semester 1
 
Demolition of Structures.
Demolition of Structures.Demolition of Structures.
Demolition of Structures.
 

Similar to Concreting of super structure

Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphbhlksd
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016Ali Issa
 
Concreting work
Concreting workConcreting work
Concreting work
QualityConstruction1
 
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for  Haris & Co Civil Team.pdfCivil Works Site Construction Guidelines for  Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
usamazahoor159
 
6 pavement quality concrete
6 pavement quality concrete6 pavement quality concrete
6 pavement quality concrete
thamand7
 
1008 caissons-specification
1008 caissons-specification1008 caissons-specification
1008 caissons-specification
Dr Fereidoun Dejahang
 
Abhishek presentation.pptx
Abhishek presentation.pptxAbhishek presentation.pptx
Abhishek presentation.pptx
RAKESHPANDEY754083
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
Bharatha Rathnayke
 
PPT_MoRT&H Section 900 - FINAL.pptx
PPT_MoRT&H Section 900 - FINAL.pptxPPT_MoRT&H Section 900 - FINAL.pptx
PPT_MoRT&H Section 900 - FINAL.pptx
gthpmc
 
Developers Transflex Installation
Developers Transflex InstallationDevelopers Transflex Installation
Developers Transflex Installation
guest470ea8
 
HCB Manual gtz 2008.doc
HCB Manual gtz 2008.docHCB Manual gtz 2008.doc
HCB Manual gtz 2008.doc
FeteneBefekadu
 
Metroppt
MetropptMetroppt
Engineering quality version 2014 for construction projects
Engineering quality version 2014 for construction projectsEngineering quality version 2014 for construction projects
Engineering quality version 2014 for construction projects
meetgiannis
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)AJAY SHAHU
 
Advanced Building Measurement
Advanced Building MeasurementAdvanced Building Measurement
Advanced Building Measurement
Sultan M Muzahir
 
Delhi metro presention
Delhi   metro presentionDelhi   metro presention
Delhi metro presention
Dharmendra Kumar
 
Precast
PrecastPrecast
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
AKASHGARG131
 

Similar to Concreting of super structure (20)

Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
 
Concreting work
Concreting workConcreting work
Concreting work
 
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for  Haris & Co Civil Team.pdfCivil Works Site Construction Guidelines for  Haris & Co Civil Team.pdf
Civil Works Site Construction Guidelines for Haris & Co Civil Team.pdf
 
6 pavement quality concrete
6 pavement quality concrete6 pavement quality concrete
6 pavement quality concrete
 
1008 caissons-specification
1008 caissons-specification1008 caissons-specification
1008 caissons-specification
 
Abhishek presentation.pptx
Abhishek presentation.pptxAbhishek presentation.pptx
Abhishek presentation.pptx
 
Concrete repair
Concrete repairConcrete repair
Concrete repair
 
Method statement tank base concrete pouring
Method statement  tank base concrete pouringMethod statement  tank base concrete pouring
Method statement tank base concrete pouring
 
PPT_MoRT&H Section 900 - FINAL.pptx
PPT_MoRT&H Section 900 - FINAL.pptxPPT_MoRT&H Section 900 - FINAL.pptx
PPT_MoRT&H Section 900 - FINAL.pptx
 
Developers Transflex Installation
Developers Transflex InstallationDevelopers Transflex Installation
Developers Transflex Installation
 
HCB Manual gtz 2008.doc
HCB Manual gtz 2008.docHCB Manual gtz 2008.doc
HCB Manual gtz 2008.doc
 
Metroppt
MetropptMetroppt
Metroppt
 
Engineering quality version 2014 for construction projects
Engineering quality version 2014 for construction projectsEngineering quality version 2014 for construction projects
Engineering quality version 2014 for construction projects
 
Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)Industrial Training Report-(2012-13)
Industrial Training Report-(2012-13)
 
Advanced Building Measurement
Advanced Building MeasurementAdvanced Building Measurement
Advanced Building Measurement
 
Delhi metro presention
Delhi   metro presentionDelhi   metro presention
Delhi metro presention
 
Precast
PrecastPrecast
Precast
 
Dda training presentation
Dda training presentationDda training presentation
Dda training presentation
 
AH15019
AH15019AH15019
AH15019
 

Concreting of super structure

  • 1. Table of contents 1. General. 2. Management Organization Chart 3. Sequence of works (beam & slab). 4. Formwork design. 5. Construction joint treatment. 6. Re bars fabrication & setting. 7. Installation of embed item. 8. Placing of concrete. 9. Compaction of concrete. 10.Removal of formworks 11.Curing 12.Protecting against raining 13.Electricity 14.Equipment & Manpower 15.Safety measure Appendix A. General plan and elevation B. Typical formworks & Scaffolding arrangement. C. Calculation for formwork and support systems D. Safety Procedure 1. General
  • 2. This method statement describes how we carry out the concrete works of superstructure in building works. Concrete class shall be approved ready-mix concrete Grade 35MN/m2 Please refer to Appendix A for general plan and elevation of three main building. 2. Management Organization Chart Mr. N.N.Hai HSE Manager Mr. Tran Thanh Minh Site Engineer Mr. Hoang Hung Site Engineer Sub Contractor Sub Contractor 2.1 Project Manager Mr. T. UCHIDA Project Manager Mr. A . IKEGAMI Construction Manager Mr. A.M. Cabonce QA/QC Manager Mr. K.Miyara Chief Engineer Mr. P. C. TRUNG Chief site Engineer Mr. Dang Trong Dung Site Engineer Sub Contractor · To oversee and control all aspects of the Piling activities, and dictate schedule requirements · To ensure that all field staff are fully aware of the requirements of this method statement, and that these requirements, in all respects, are fully implemented. · To ensure that Safety and Environmental procedures, particularly, are in place before activity commences, and strictly complied with, throughout the duration of concreting works.
  • 3. 2.2 Construction Managers, directly reports to Project Manager. · To oversee all construction works, with respect to schedule. · To ensure that all field staff follow the requirements of this method statement, including quality control and HSE. 2.3 Chief Engineer, reports to Construction Manager · To ensure that all relevant preparations have been made. · To ensure that all provisions of this method statement are followed. · To ensure that all quality inspection is carried out and record taken, if required. · To ensure that all necessary safety and environmental precautions are in place and that all workers under their direct control are fully aware of all procedure requirements · To control execution of the entire activity 2.4 Site Engineer · To assist Chief Engineer to control the Subcontractor for all activities relative to this method statement. · To ensure safe working environment at all times, during Subcontractor execution of concreting works. 2.5 Surveyor · To give control points & grid line to Subcontractor for concreting works. · To supervise Subcontractor and conduct survey checks from time to time. · To carry out all surveying work and to ensure all required records are taken and maintained. 2.6 QA/QC department · To oversee construction activity with respect to quality control. · To ensure quality procedures has been followed.
  • 4. · To ensure that all required inspections have been carried out and that records, if required have been taken and properly stored. · Advise the laboratory and Site Engineers to control the quality of works. 2.7 Health, Safety & Environmental department · To monitor that all the working activities are executed in accordance with site safety procedures. · To ensure that precautions with respect to Environmental matters have been implemented on site. 3. Sequence of works (beam & slab). Setting Staging for Construction Area Setting Support & Bottom Formwork Construction Joint Treatment Inspection for Construction Joint Assembling re bar Inspection of re bar Setting Side Formwork
  • 5. Inspection for casting concrete Placing Concrete Curing Stripping of Form Stripping Support and Prop after Getting Design Strength 100% 4. Formworks Design Formwork shall be set in correct position following specification and the approved structure drawings. Please refer to Appendix B for Typical formworks & support for 2nd floor slab. Formworks and support is calculated as shown in Attachment C Approved form oil will be applied to form surface prior to installation of form. 5. Construction joint treatment All construction joints will be chipped to remove cement sand surface to make rough surface.
  • 6. In some cases, approved retarder for concrete surface will be used as another method to make construction joint properly. 6. Rebar fabrication & setting Approved re-bar type will be delivered to site and it will be inspected & tested prior to use. Re-bar shall be cut and bent according to the approved schedule at the site workshop and transported to site by truck. After delivery to the site re-bars shall be fixed according to specification and approved drawings by Engineer or Consultant. Rebar shall be inspected by Engineer or Consultant prior to install of next layer or formworks. Any mistake rebar will be replaced or repaired by approved method. Approved concrete spacer shall be used; its concrete grade shall be 35 MN/m2. 7. Installation of embed item All the embed item showing in the drawings shall be firmly installed in correct position. 8. Placing of Concrete Approved ready-mix concrete will be transported from batching plant to the site by mixer truck. During transportation & waiting time the concrete shall be kept continuously agitated. From mixer truck concrete will be poured to casting location by concrete pump or by bucket. The height from discharge position to casting level shall not be over 1.5m. On each concreting day and for each grade of concrete mix, samples shall be taken. When samples are taken at sites, samples shall be taken for every 24m3 of concrete or part thereof, of each grade of concrete. Minimum requirement of sample
  • 7. - Each concreting day - Each part of structure (each building) - After filling above condition, samples shall be taken for every four mixer or agitating truck (20~24m2). 9. Compaction of Concrete. Concrete after pouring to position shall be compacted by immersion vibrator. Proper staging for vibration works will be arranged. Wooden or rubber hammer also will be used as external vibrator in some cases. 10. Removal of formworks Form works removal shall be accordance with specification Clause 4.20 or as proposal hereunder. - All vertical or side formworks : 12 hrs (The period shall commence from the time of last pour of concrete) - Soffit formworks to slabs & beams : 3 days ((The period shall commence from the time of last pour of concrete) - Props to slabs & beams: Requirement in Specification is 14 days. We propose that before remove props we will carry out testing for cube sample, whenever if we get 100% designed strength of concrete we will remove props (After skirting of formworks, props shall be immediately put up to support the structure) - Props to cantilever slabs & cantilever beams: Requirement in Specification is 21 days. We propose that before remove props we will carry out testing for cube sample, whenever if we get 100% designed strength of concrete we will remove props (After skirting of formworks, props shall be immediately put up to support the structure)
  • 8. * Testing for purpose of removal formworks will be carried out at 7th days after finish casting concrete. All tie rod holes & defects on surface will be repaired following approved method. 11. Curing. After removal of form works, concrete shall be cured minimum of 6 days according to TCXDVN 391:2007– Requirements for Natural Moist Curing, apply for Area C of Viet Nam. Curing of concrete will be carried out by spraying water periodically to the surface of the newly placed concrete. Jute bag or nylon sheet shall be used to cover the concrete surface for keeping wet. Water to be used for curing and cleaning works is portable water from local authority. Approved curing compound also will be used in several cases. 12. Protecting against raining. Against raining, plastic sheet shall be prepared to cover over the concrete area before concreting. 13. Electricity Electricity will be supplied by generators on site. 14. Equipment & Manpower a)Equipment Equipment Unit Quantity Mixer truck Nos 04 Vibrator Nos 03 Concrete Pump No 01 Generator 15KVA No 01 Generator 10KVA Nos 02 Bucket Nos 10 Showel Nos 05 Trowel Nos 05
  • 9. b)Manpower Description Unit Quantity Supervisor No 01 Surveyor Nos 02 Foreman No 01 Electrician No 01 Worker Nos 10 15. Safety measure Please refer to Appendix D for Safety Procedure when working at high position
  • 10. APPENDIX A GENERAL PLAN & ELEVATION
  • 11. APPENDIX B FORMWORKS & SCAFFOLDING ARRANGEMENT
  • 12. APPENDIX C CALCULATION FOR FORMWORKS & SUPPORT
  • 13.
  • 14. APPENDIX D SAFETY PROCEDURE