The document presents an economic feasibility study comparing two alternatives for Highway 640:
1) A traditional highway design
2) A sustainable highway design
It provides initial cost estimates and annual operation and maintenance cost projections for 30 years for each alternative. The sustainable highway design has higher initial costs but lower projected annual costs, resulting in it being the recommended option.
There are two main types of joints in rigid pavement: longitudinal joints and transverse joints. Longitudinal joints run parallel to traffic flow, while transverse joints run perpendicular. Transverse joints include construction joints, contraction joints, and expansion joints. Construction joints define the boundaries of individual concrete placements. Contraction joints relieve tensile stresses from shrinkage. Expansion joints allow for expansion of the concrete due to rising temperatures.
Civil engineering involves planning, designing, constructing, and maintaining structures and facilities. It addresses areas like transportation, water resources, environmental protection, and more. The main tasks of civil engineers are planning, estimating, supervising construction, and managing projects. Civil engineering works encompass buildings, roads, bridges, dams, and other structures. It has many branches including surveying, construction, geotechnical engineering, transportation, environmental engineering, and town planning. Civil engineers ensure structures are built safely and effectively to serve societal needs.
The document provides an introduction to transportation engineering. It discusses key topics including:
- Transportation engineering deals with planning, design, operation and management of various transportation modes to provide safe, efficient movement of people and goods.
- Key aspects covered include highway engineering, traffic engineering, transportation networks and systems, roles of transportation, history of road development in India, functional classification of roads, and administration of roads.
- It also summarizes India's road development plans over the decades including the landmark Nagpur Plan from 1943 which was the first long-term road development plan for India.
This document discusses vertical alignment in road design. It defines vertical alignment as the vertical aspect of the road profile, including crest and sag curves. It describes the basic components of vertical alignment as grade and vertical curves. Grade is the slope of the road expressed as a percentage, while vertical curves are parabolic curves that provide gradual transitions between different grades to allow comfortable driving. The document discusses types of vertical curves such as sag curves at the bottom of hills and crest curves at the tops of hills, as well as symmetrical and unsymmetrical curves. It provides the equations used to design different types of vertical curves.
Curves are used in transportation infrastructure to provide gradual turns rather than sharp angles. There are two main types of curves: horizontal curves, which provide transitions between sections of roadway; and vertical curves, which provide transitions between changes in elevation. Horizontal curves are further classified as simple, compound, reverse, or spiral curves depending on their design. Vertical curves similarly provide a gradual grade transition. Proper curve design considers factors like design speed, drainage, and sight distance to ensure safety.
The document discusses airport obstructions and imaginary surfaces. It defines obstructions as objects that interfere with aircraft movement and lists different types of imaginary surfaces like approach, takeoff, horizontal, and conical surfaces established around airports and runways. These surfaces define the heights and areas where no obstructions are allowed based on factors like runway length and type of landings. The document also discusses zoning laws that govern land use and height of developments near airports to ensure safety of aircraft operations.
There are two main types of joints in rigid pavement: longitudinal joints and transverse joints. Longitudinal joints run parallel to traffic flow, while transverse joints run perpendicular. Transverse joints include construction joints, contraction joints, and expansion joints. Construction joints define the boundaries of individual concrete placements. Contraction joints relieve tensile stresses from shrinkage. Expansion joints allow for expansion of the concrete due to rising temperatures.
Civil engineering involves planning, designing, constructing, and maintaining structures and facilities. It addresses areas like transportation, water resources, environmental protection, and more. The main tasks of civil engineers are planning, estimating, supervising construction, and managing projects. Civil engineering works encompass buildings, roads, bridges, dams, and other structures. It has many branches including surveying, construction, geotechnical engineering, transportation, environmental engineering, and town planning. Civil engineers ensure structures are built safely and effectively to serve societal needs.
The document provides an introduction to transportation engineering. It discusses key topics including:
- Transportation engineering deals with planning, design, operation and management of various transportation modes to provide safe, efficient movement of people and goods.
- Key aspects covered include highway engineering, traffic engineering, transportation networks and systems, roles of transportation, history of road development in India, functional classification of roads, and administration of roads.
- It also summarizes India's road development plans over the decades including the landmark Nagpur Plan from 1943 which was the first long-term road development plan for India.
This document discusses vertical alignment in road design. It defines vertical alignment as the vertical aspect of the road profile, including crest and sag curves. It describes the basic components of vertical alignment as grade and vertical curves. Grade is the slope of the road expressed as a percentage, while vertical curves are parabolic curves that provide gradual transitions between different grades to allow comfortable driving. The document discusses types of vertical curves such as sag curves at the bottom of hills and crest curves at the tops of hills, as well as symmetrical and unsymmetrical curves. It provides the equations used to design different types of vertical curves.
Curves are used in transportation infrastructure to provide gradual turns rather than sharp angles. There are two main types of curves: horizontal curves, which provide transitions between sections of roadway; and vertical curves, which provide transitions between changes in elevation. Horizontal curves are further classified as simple, compound, reverse, or spiral curves depending on their design. Vertical curves similarly provide a gradual grade transition. Proper curve design considers factors like design speed, drainage, and sight distance to ensure safety.
The document discusses airport obstructions and imaginary surfaces. It defines obstructions as objects that interfere with aircraft movement and lists different types of imaginary surfaces like approach, takeoff, horizontal, and conical surfaces established around airports and runways. These surfaces define the heights and areas where no obstructions are allowed based on factors like runway length and type of landings. The document also discusses zoning laws that govern land use and height of developments near airports to ensure safety of aircraft operations.
The document discusses reasons for laying new railway lines and the process of railway surveys. It outlines six main reasons for proposing new railway lines: 1) strategic connections, 2) linking trade centers, 3) connecting ports to inland areas, 4) shortening existing routes, 5) laying branch lines, and 6) developing undeveloped areas. It then describes the three main types of railway surveys - reconnaissance, preliminary, and location surveys - conducted to determine the optimal route. The reconnaissance survey gathers initial data, preliminary survey evaluates alternative routes, and location survey establishes the final track centerline.
Rigid pavements are constructed using reinforced concrete slabs that provide a strong wearing surface and base course. They are used in areas with adverse conditions like heavy rainfall, poor soil/drainage, or extreme climate. Materials for rigid pavements include Portland cement, coarse and fine aggregates, and water. Reinforcement includes dowel bars at joints. Rigid pavements have longitudinal and transverse joints, including contraction joints to relieve stresses, expansion joints to allow for expansion, and construction joints. They can be constructed using slipform pavers, fixed form pavers, or manual methods. Quality control ensures the concrete meets specifications. Traffic is only allowed after a minimum 28-day curing period.
This document provides information on the design of flexible pavements according to IRC: 37-2001 guidelines. It discusses the design criteria of fatigue cracking and rutting failures. The design approach involves selecting design inputs, performing a trial thickness design using layered elastic theory, and comparing the critical responses to failure criteria. Design tables and charts provide pavement thickness designs for different subgrade CBR values and traffic loads. The recommended pavement compositions specify material properties and minimum thicknesses for sub-base, base and surface courses. An example problem demonstrates the estimation of design traffic over the design period.
Transition curve and Super-elevation
Transition Curve
Objectives of Transition Curve
Properties Of Transition Curve
Types Of Transition Curve
Length Of Transition Curve
Superelevation
Objective of providing superelevation
Advantages of providing superelevation
Superelevation Formula
Numerical
This document discusses various aspects of airport engineering and design. It begins by outlining the history of air transport development in India. It then defines key terms like airport, airfield, aerodrome and describes important airport components such as runways, terminals, taxiways, and control towers. The document also discusses factors that influence airport site selection and layout, including aircraft characteristics, wind patterns, and safety. It provides examples of different types of airports and concludes by covering topics like runway orientation, design, lighting and signage.
This document is a project report on the geometric design of railway tracks submitted by Mohit M. Jain to Gujarat Technological University in India. It introduces the topic of geometric design and its importance for ensuring safe and efficient train operation. The following chapters discuss geometric cross sections, gradients including different types, curves, superelevation, and gauge widening on curves. The report provides information on the key design considerations for railway tracks.
Surveying Engineering
Traversing Practical part 1
Plane and Applied surveying 2
Report number(2)
• Report name :Gales Traverse Table(Horizontal angle
measurement (FL)of closed traversing
• Apparatus
• Theodolite Instrument
• Tripod
• Compass
• Pin
• Tape
• Range pole
Object
• To conducted survey work in a closed traversing and calculate
in depend coordinates and area calculation by coordinate rule.
Procedure Traverse;
Calculations Traverse .Dada Sheet and Table method work clock wise surveying
-Gales Traverse Table.
*Traverse Calculations
-Traverse Calculation.
-Coordinate conversions.
-Signs of Departures and Latitudes.
*Balancing latitude and departure
-Correction for ∆E& ∆N:
Bowditch adjustment or compass method
-The example…
-Vector components (pre-adjustment)
*The adjustment components
Prepared by:
Asst. Prof. Salar K.Hussein
Mr. Kamal Y.Abdullah
Asst.Lecturer. Dilveen H. Omar
Erbil Polytechnic University
Technical Engineering College
Civil Engineering Department
Pavement materials in Road Constructionsrinivas2036
Different pavement materials used in the road construction. Importance of soil, aggregate pavement materials. Tests on Soil for pavement construction. Tests on aggregate for pavement construction.
Requirements of soil and aggregates in pavement.
5.track or permanent way and track stressesMani Vel
The document discusses the components and stresses acting on railroad tracks. It describes the main parts of a track including the rails, sleepers, ballast, and formation. The rails are joined by fish plates and bolts and fastened to sleepers. Sleepers are embedded in ballast which provides drainage and load distribution. A good track requires proper gauge, cross-leveling, alignment, gradient, and resilience to provide a comfortable ride while withstanding forces from train movement and varying temperatures. Wheels are coned rather than flat to reduce wear on flanges and rails and allow for lateral movement.
in this presentation, we should discuss what is the need for a survey in bridge construction site and what are the needed equipment use in construction. in this presentation, you should learn about how to locate activity of bridge construction.the different method should be learning in this presentation and it more effectively. it is more helpful in your career growth.
thank you
ASWINI & SAGAR
This document discusses factors to consider in airport site selection. Key factors include:
- Air traffic potential and adequate access to the site
- Sufficient land for facilities, expansion, and utilities
- Favorable atmospheric, meteorological, and soil conditions
- Availability of land and utilities for future expansion
- Consideration of surrounding development, obstructions, and other airports
Structural Analysis And Design is a structural analysis and design software. It includes tools for 3D modeling, analysis, and design of structures according to various international codes. The software was originally developed by Research Engineers International and later acquired by Bentley Systems. It allows engineers to generate models using different elements like frames, plates, and solids. Various types of structures like trusses, planes, and spaces can be modeled and analyzed. The software provides tools for assigning properties, loads, boundary conditions, and performing analysis to calculate member forces and deflections. The results can then be used for structural design of elements like beams, columns, slabs, and foundations.
A project report on flyover internship bihar rajya pul nirman nigam limited p...Prashant Shaurabh
This document summarizes a project report on the construction of a flyover in Bihar, India. It discusses the reasons for constructing the flyover to reduce travel time from 45 minutes to 15 minutes due to increasing traffic. It then outlines the various sections of the report, including the stages of the project like surveys, traffic analysis, and design. It describes the key components of the flyover like foundations, substructures, superstructures and provides technical details. It also lists the various machines and equipment used in the construction process and explains the construction procedures and dimensions of piles, pile caps, piers etc. through images.
In transport engineering, subgrade is the native material underneath a constructed road, pavement or railway track. It is also called formation level.
The term can also refer to imported material that has been used to build an embankment.
Transportation plays a vital role in a country's economic and social development by enabling the movement of goods, services, and people. Road transportation in particular is critical for India given that over 75% of its population lives in rural areas. Historically, India began developing roads as early as 3500 BC but larger scale construction began under the Romans and further improved under Mughal rule to facilitate administration, military operations, and commerce. Today, a well-planned road network connecting villages to markets is essential to improve rural livelihoods and drive overall economic growth.
This document discusses lateral earth pressure and provides details on Rankine's theory and graphical methods for determining active and passive earth pressures. It explains that lateral earth pressure is exerted by soil on retaining structures and depends on whether the structure is stationary or moving towards/away from the soil mass. Rankine's theory assumes dry, homogeneous soil and a vertical wall. Rebhann and Culmann's graphical methods can be used to locate the failure plane and determine the magnitude and direction of lateral earth pressures based on the soil's friction angle and the structure's orientation.
This document provides a cost estimate for a proposed development comprising 2 blocks of 31-storey residential towers above a 7-storey podium and 2-storey basement on a site in Kuala Lumpur. It includes estimates for substructure, structure, architectural components, M&E services, and external works. The total estimated construction cost is RM194,999,403.72 or RM2,195/sqft, including preliminaries, contingencies and cost escalation over one year. The highest cost components are structure, architectural works, and M&E services.
PROJECT 8th SEM - DEVELOPMENT OF SOME INTEGRATED DECISION-MAKING FRAMEWORK FO...Swagatam Mitra
Multiple-criteria decision-making (MCDM) or multiple-criteria decision analysis (MCDA) is a sub-discipline of operations research that explicitly evaluates multiple conflicting criteria in decision making (both in daily life or in professional settings). Conflicting criteria are typical in evaluating options: cost or price is usually one of the main criteria, and some measure of quality is typically another criterion, easily in conflict with the cost. In order to survive in the present day global competitive environment, it now becomes essential for the manufacturing organisations to take timely and accurate decisions regarding effective use of their scarce resources. Various multicriteria decision-making (MCDM) methods are now available to help those organisations in choosing the best decisive course of actions. In this project work, the applicability of some newly developed MCDM methods will be explored while solving some discrete manufacturing decision making problems. Integrated decision-making framework will also be developed for effective decision-making. Ranking performances of these methods will also be compared. Decision making that deals with several aspects of a finite set of available alternatives in a given situation is often referred to as multi criteria analysis.
The document discusses reasons for laying new railway lines and the process of railway surveys. It outlines six main reasons for proposing new railway lines: 1) strategic connections, 2) linking trade centers, 3) connecting ports to inland areas, 4) shortening existing routes, 5) laying branch lines, and 6) developing undeveloped areas. It then describes the three main types of railway surveys - reconnaissance, preliminary, and location surveys - conducted to determine the optimal route. The reconnaissance survey gathers initial data, preliminary survey evaluates alternative routes, and location survey establishes the final track centerline.
Rigid pavements are constructed using reinforced concrete slabs that provide a strong wearing surface and base course. They are used in areas with adverse conditions like heavy rainfall, poor soil/drainage, or extreme climate. Materials for rigid pavements include Portland cement, coarse and fine aggregates, and water. Reinforcement includes dowel bars at joints. Rigid pavements have longitudinal and transverse joints, including contraction joints to relieve stresses, expansion joints to allow for expansion, and construction joints. They can be constructed using slipform pavers, fixed form pavers, or manual methods. Quality control ensures the concrete meets specifications. Traffic is only allowed after a minimum 28-day curing period.
This document provides information on the design of flexible pavements according to IRC: 37-2001 guidelines. It discusses the design criteria of fatigue cracking and rutting failures. The design approach involves selecting design inputs, performing a trial thickness design using layered elastic theory, and comparing the critical responses to failure criteria. Design tables and charts provide pavement thickness designs for different subgrade CBR values and traffic loads. The recommended pavement compositions specify material properties and minimum thicknesses for sub-base, base and surface courses. An example problem demonstrates the estimation of design traffic over the design period.
Transition curve and Super-elevation
Transition Curve
Objectives of Transition Curve
Properties Of Transition Curve
Types Of Transition Curve
Length Of Transition Curve
Superelevation
Objective of providing superelevation
Advantages of providing superelevation
Superelevation Formula
Numerical
This document discusses various aspects of airport engineering and design. It begins by outlining the history of air transport development in India. It then defines key terms like airport, airfield, aerodrome and describes important airport components such as runways, terminals, taxiways, and control towers. The document also discusses factors that influence airport site selection and layout, including aircraft characteristics, wind patterns, and safety. It provides examples of different types of airports and concludes by covering topics like runway orientation, design, lighting and signage.
This document is a project report on the geometric design of railway tracks submitted by Mohit M. Jain to Gujarat Technological University in India. It introduces the topic of geometric design and its importance for ensuring safe and efficient train operation. The following chapters discuss geometric cross sections, gradients including different types, curves, superelevation, and gauge widening on curves. The report provides information on the key design considerations for railway tracks.
Surveying Engineering
Traversing Practical part 1
Plane and Applied surveying 2
Report number(2)
• Report name :Gales Traverse Table(Horizontal angle
measurement (FL)of closed traversing
• Apparatus
• Theodolite Instrument
• Tripod
• Compass
• Pin
• Tape
• Range pole
Object
• To conducted survey work in a closed traversing and calculate
in depend coordinates and area calculation by coordinate rule.
Procedure Traverse;
Calculations Traverse .Dada Sheet and Table method work clock wise surveying
-Gales Traverse Table.
*Traverse Calculations
-Traverse Calculation.
-Coordinate conversions.
-Signs of Departures and Latitudes.
*Balancing latitude and departure
-Correction for ∆E& ∆N:
Bowditch adjustment or compass method
-The example…
-Vector components (pre-adjustment)
*The adjustment components
Prepared by:
Asst. Prof. Salar K.Hussein
Mr. Kamal Y.Abdullah
Asst.Lecturer. Dilveen H. Omar
Erbil Polytechnic University
Technical Engineering College
Civil Engineering Department
Pavement materials in Road Constructionsrinivas2036
Different pavement materials used in the road construction. Importance of soil, aggregate pavement materials. Tests on Soil for pavement construction. Tests on aggregate for pavement construction.
Requirements of soil and aggregates in pavement.
5.track or permanent way and track stressesMani Vel
The document discusses the components and stresses acting on railroad tracks. It describes the main parts of a track including the rails, sleepers, ballast, and formation. The rails are joined by fish plates and bolts and fastened to sleepers. Sleepers are embedded in ballast which provides drainage and load distribution. A good track requires proper gauge, cross-leveling, alignment, gradient, and resilience to provide a comfortable ride while withstanding forces from train movement and varying temperatures. Wheels are coned rather than flat to reduce wear on flanges and rails and allow for lateral movement.
in this presentation, we should discuss what is the need for a survey in bridge construction site and what are the needed equipment use in construction. in this presentation, you should learn about how to locate activity of bridge construction.the different method should be learning in this presentation and it more effectively. it is more helpful in your career growth.
thank you
ASWINI & SAGAR
This document discusses factors to consider in airport site selection. Key factors include:
- Air traffic potential and adequate access to the site
- Sufficient land for facilities, expansion, and utilities
- Favorable atmospheric, meteorological, and soil conditions
- Availability of land and utilities for future expansion
- Consideration of surrounding development, obstructions, and other airports
Structural Analysis And Design is a structural analysis and design software. It includes tools for 3D modeling, analysis, and design of structures according to various international codes. The software was originally developed by Research Engineers International and later acquired by Bentley Systems. It allows engineers to generate models using different elements like frames, plates, and solids. Various types of structures like trusses, planes, and spaces can be modeled and analyzed. The software provides tools for assigning properties, loads, boundary conditions, and performing analysis to calculate member forces and deflections. The results can then be used for structural design of elements like beams, columns, slabs, and foundations.
A project report on flyover internship bihar rajya pul nirman nigam limited p...Prashant Shaurabh
This document summarizes a project report on the construction of a flyover in Bihar, India. It discusses the reasons for constructing the flyover to reduce travel time from 45 minutes to 15 minutes due to increasing traffic. It then outlines the various sections of the report, including the stages of the project like surveys, traffic analysis, and design. It describes the key components of the flyover like foundations, substructures, superstructures and provides technical details. It also lists the various machines and equipment used in the construction process and explains the construction procedures and dimensions of piles, pile caps, piers etc. through images.
In transport engineering, subgrade is the native material underneath a constructed road, pavement or railway track. It is also called formation level.
The term can also refer to imported material that has been used to build an embankment.
Transportation plays a vital role in a country's economic and social development by enabling the movement of goods, services, and people. Road transportation in particular is critical for India given that over 75% of its population lives in rural areas. Historically, India began developing roads as early as 3500 BC but larger scale construction began under the Romans and further improved under Mughal rule to facilitate administration, military operations, and commerce. Today, a well-planned road network connecting villages to markets is essential to improve rural livelihoods and drive overall economic growth.
This document discusses lateral earth pressure and provides details on Rankine's theory and graphical methods for determining active and passive earth pressures. It explains that lateral earth pressure is exerted by soil on retaining structures and depends on whether the structure is stationary or moving towards/away from the soil mass. Rankine's theory assumes dry, homogeneous soil and a vertical wall. Rebhann and Culmann's graphical methods can be used to locate the failure plane and determine the magnitude and direction of lateral earth pressures based on the soil's friction angle and the structure's orientation.
This document provides a cost estimate for a proposed development comprising 2 blocks of 31-storey residential towers above a 7-storey podium and 2-storey basement on a site in Kuala Lumpur. It includes estimates for substructure, structure, architectural components, M&E services, and external works. The total estimated construction cost is RM194,999,403.72 or RM2,195/sqft, including preliminaries, contingencies and cost escalation over one year. The highest cost components are structure, architectural works, and M&E services.
PROJECT 8th SEM - DEVELOPMENT OF SOME INTEGRATED DECISION-MAKING FRAMEWORK FO...Swagatam Mitra
Multiple-criteria decision-making (MCDM) or multiple-criteria decision analysis (MCDA) is a sub-discipline of operations research that explicitly evaluates multiple conflicting criteria in decision making (both in daily life or in professional settings). Conflicting criteria are typical in evaluating options: cost or price is usually one of the main criteria, and some measure of quality is typically another criterion, easily in conflict with the cost. In order to survive in the present day global competitive environment, it now becomes essential for the manufacturing organisations to take timely and accurate decisions regarding effective use of their scarce resources. Various multicriteria decision-making (MCDM) methods are now available to help those organisations in choosing the best decisive course of actions. In this project work, the applicability of some newly developed MCDM methods will be explored while solving some discrete manufacturing decision making problems. Integrated decision-making framework will also be developed for effective decision-making. Ranking performances of these methods will also be compared. Decision making that deals with several aspects of a finite set of available alternatives in a given situation is often referred to as multi criteria analysis.
The document summarizes the design of an electrically assisted human powered vehicle. It includes sections on the center of gravity calculation, bill of materials and mass table, cost analysis, performance analysis, assembly specifications, CAD assembly files, and project timeline. The key details are the vehicle will have a total mass of 184.7kg, cost $9,450 to produce, and be able to reach speeds of up to 40kph with electric assist while accommodating a single rider weighing up to 120kg.
The document provides specifications for various long stroke ball screw linear actuators including:
- Force ratings from 400 to 2,000 lbs
- Velocities up to 40 in/sec
- IP54 sealing from contamination
- Adjustable limit switch positions
- Pistons with rugged anti-rotation features
This document compares the cost estimates of a railway doubling project from the initial Detailed Project Report (DPR) to two subsequent revised estimates. The total estimated cost increased from ₹750.56 billion in the DPR to ₹1293.72 billion in the first revised estimate, an increase of 72.37%. It further increased to ₹2018.23 billion in the second revised estimate, up another 15.12% from the first. Most of the increase was due to price escalation, though some was also attributed to changes in project scope.
StrAuto is an automated structural design and optimization software. It provides an iterative design process to generate and evaluate thousands of design alternatives to find the optimal solution that meets design targets like lowest cost. It was used to optimize the design of several large-scale building projects. For one project, a super tall tower, StrAuto optimized the outrigger levels, concrete strengths, and core wall thicknesses, analyzing over 4,600 design variations to minimize weight and lateral drift within limits. This led to a 7.8% reduction in weight from the initial design.
1. The document provides information on modeling and analyzing various components used in rotor systems, including shafts, drive shafts, clamping plates, and tie bolts. Dimensional data and results from balance testing, spin testing, and FEA analyses are presented.
2. Modal, static, and harmonic analyses were performed on a hall rail model under different load and geometry conditions. Safety factors were calculated based on maximum stresses.
3. Static structural, modal, and harmonic analyses of the hall rail were performed and compared using ANSYS, SOLIDWORKS, and ABAQUS. Results for maximum stress and safety factors using different software are shown in a table.
IRJET-Estimating the Vehicle Operating Cost through Railway Over BridgeIRJET Journal
This document summarizes the design of a railway over bridge (ROB) being built in Sitapura, Jaipur to ease traffic congestion. Key details include:
- The ROB will be 925 meters long and Y-shaped, with one wing extending north towards Sitapura.
- Design tables show parameters like sight distances, curve radii, and transition lengths for speeds of 100-120 kmph.
- Vehicle operating costs are estimated using World Bank and Indian Road Congress models based on road and vehicle characteristics.
- Cost of the ROB is estimated to be 116 crore rupees. Geometric design elements are analyzed to estimate vehicle operating costs at different speeds.
Francesco Boscolo, member of Tecnalia Offshore Energy Area, presents at FOWT 2018 conference in Marseille a methodology for the design of an umbilical cable for floating offshore platforms, based on static and dynamic analysis in a time domain approach, in order to get a significative time-consuming reduction in the design stage.
The document discusses a study on improving the surface roughness of parts manufactured by selective laser melting (SLM). The study examines the effects of process parameters on surface roughness, including laser power, scan speed, hatch distance, and contour offset. Experiments were designed using Taguchi and full factorial methods with different parameter levels for the contour and upskin areas. Surface roughness was measured and statistical analysis was performed to identify significant factors and optimal parameters. The Taguchi method achieved a surface roughness of 3.5 μm for the upskin, while the full factorial method achieved 4.06 μm.
This document provides standard dimensions, sectional properties, and characteristics of H-steel sections. It includes dimensions such as depth, width, thickness, radius, and area. Sectional properties included are sectional area, unit weight, moment of inertia, radius of gyration, and compactness criteria. Characteristics such as yield strength are also provided, varying based on thickness of the steel. Over 50 H-steel section dimensions are defined.
The document proposes constructing a funicular railway system at Haji Malang Gad in Ambernath, Thane district, Maharashtra, India. It would transport devotees and luggage up a 400m elevation gain over 5km that currently takes 4-5 hours on foot. The proposed system would have two passenger trolleys carrying 60 passengers each, departing every 10 minutes, and an optional goods trolley. The total projected cost is Rs. 4591 lakhs. An economic analysis estimates the project would have a 13.3% internal rate of return over 23 years 10 months.
The document summarizes key points about the GLIO Index, which is designed to enable clearer comparisons between listed and unlisted infrastructure by focusing on companies that provide mission critical infrastructure. It is based on the EDHECInfra Infrastructure classification system and includes companies that derive at least 75% of EBITDA from eligible infrastructure groups like regulated utilities, renewables, energy transportation and storage, transportation, and communications infrastructure. Breakdowns of the index by group, sector, and other metrics are also provided. Plans for a GLIO/GRESB ESG Index and Infrastructure Investment Trust model are briefly outlined.
This document provides information on Tehran's metro system including:
- Tehran's metro network consists of 12 lines totaling 430km in length serving over 5 billion passengers.
- The network includes 4 express lines and 8 urban lines, with 276 stations. Future plans aim to increase daily ridership to 10 million passengers through expansion.
- Funding has come from various government sources as well as private developers, with construction costs totaling over $18.5 billion.
- Ridership has grown tremendously over time from 3.3 million passengers in 1999 to over 1 billion in 2012, relieving road congestion and reducing environmental impacts.
This document discusses proposals to increase water production for a local water utility to address increasing demand. It analyzes 4 options: maintaining the status quo, rehabilitating an old water treatment plant, constructing a new water treatment plant, or purchasing bulk water. Key details include projected demand outpacing supply by 2022 under the status quo. Rehabilitating the old plant would increase supply but take over 3 years and cost $878 million. Building a new 15 MLD plant would meet demand until 2027 at a lower cost and faster completion time than rehabilitation. Purchasing bulk water is also considered. Charts show the projected impact of each option on meeting demand.
This document provides a preliminary cost appraisal and cost plan for the construction of two 31-story residential tower blocks with 7-story podium and 2-story basement on a site with an area of 160,000 square feet. It includes estimated costs for various elements of the structure, architectural, mechanical and electrical works. The total estimated construction cost is RM336,568,652.15 or RM3,750.93 per square meter of construction floor area. The document further breaks down the estimated costs by cost per square meter for the basement, podium and each tower block.
This document provides a summary of the key plan for a highway project in India. The 45.38 km project has a cost of 920 Cr and involves bypass lanes, realignments, and widening. It is scheduled for completion by March 2023. Physical and financial progress are tracked monthly, with physical work over 77% complete as of September 2022. The status of highway and structure works is also summarized.
Esriuk_track3_bruce mc-daniel - highways englandEsri UK
The document discusses Highways England's methods for prioritizing locations for improved cycling facilities on the Strategic Road Network. ArcGIS was used to analyze connectivity, economic, and safety data to score and rank potential scheme locations. This included analyzing population within 2.5km, deprivation levels, distance from public transport, accident rates, and traffic levels. The prioritization process has led to £100 million being allocated over 5 years to implement 200 new cycling facilities and crossings to help cyclists.
This document summarizes research optimizing pulsed current gas tungsten arc welding (PC-GTAW) parameters for welding AISI 304L stainless steel pipe. The researchers used ANOVA and Taguchi methods to analyze how welding current, position, and other PC-GTAW parameters affect outer bead width, depth of penetration, and ultimate tensile strength. They conducted experiments using a Taguchi L16 orthogonal array and found welding current had the greatest influence, contributing 65-95% to responses, while position contributed 6-35%. The optimal parameters were identified as a 100-C current and 180 degree position for maximum tensile strength with suitable bead geometry.
Similar to Economic Feasibility Study for Highway 640 (20)
2. Objective of Study
to provide a decision-making tool between our two investment alternatives
to study and analyze alternatives and recommend the best choice of
investment. Finally to perform an assessment analysis for the alternative
through sensitivity analysis.
Moreover, the objective of choosing the Sustainable Highway as one of the
alternatives is to play a leading role in a sustainable future. In addition, to
improve the quality of highway design and so reduce to the cost of operations
on the long term.
4. Alternative Consideration
Alternative 1
Regular Asphalt Pavement
Electric Lightning Poles
No Environmental landscaping
Regular Tolls Machines
Alternative 2
Concrete PCCP Pavement
Solar Panel Lightning poles
Environmental landscaping
Electronic Toll Collection System
Higher useful life
Higher traffic capacity
Lower O&M costs
5. Data & Assumptions- Alternative 1
Initial Cost = $407,176,368 CAD
Alternative 1- INTIAL
COSTS Description Unit
Unit
cost ($) Cost ($)
Clearing of vegetation Clearing and grubbing m^2 3 9720000
Grading; Earth works
Earth excavation or fill
m^3
27.06 14650000
%
Landscaping
Sodding and top soil m^2 3.52 11404800
Top soil m^3 2.67 2560000
Drainage of the right of
the way
Curb and Gutter m 360 38880000
500 mm pipe culvert + end
sections m
249 26892000
1500 mm wide box culvert m 350 37800000
storm water sweres m 65 7020000
Guard rails and safety
appurtenant
Concrete median m 313 33804000
Steel guardrail at shoulder m 56 6048000
3 cable guard rail at
shoulder m
10 1080000
Fencing and gates Chain link fence m 15 1620000
Wire fence m 9.03 975240
Lighting Poles
Hight mast Piece 3000 600000
Standard Piece 1300 10920000
Toll Booth and Gates
Traffic control
Painting of taraffic control
lines Km 576 62208
TOTAL 204036248
Pavement
layers
Description of payment
layer
Amount
Quantit
y per
Km
Price per
unit per
2 lane
8 lane
total in
HIGHWAY
407
Cost/ Km Total cost
surface H1-1. Mm(t) 40 750 84.75 339 254250 27459000
Binder
Medium Binder Duty,
mm(t)
60 1125 66.2 264.8 297900
32173200
Extra
layer
Medium Binder Duty,
mm(t)
60 1125 66.2 264.8 297900
32173200
Base Granular A, mm(t) 150 6991 16.04 64.16 448542.56
48442596.4
8
Subbase Granular A, mm(t) 450 15206 8.27 33.08 503014.48
54325563.8
4
Shoulder H1-1 . Mm(t) 40 100 84.75 339 33900 3661200
Shoulder
Medium Binder Duty,
mm(t)
50 125 66.2 264.8 33100
3574800
Subgrade
subgrade improvement,
% area(m^2)
500 6.16 24.64 12320
1330560
TOTAL
203140120.
3
6. Data & Assumptions- Alternative 2
Initial Cost = $459,123,752 CAD
Pavement
layers
Description of payment layer,
Amount ( quantity)
Quantity
per Km
Price per
unit per
2 lane
8 lane
total in
HIGHWAY
407
Cost per Km Total cost Total cost
surface PCCP ( 120mm ) (t) 750 94.92 379.68 284760 30754080 27459000
Binder Medium Binder Duty, mm(t) 1125 66.2 264.8 297900
32173200 32173200
Extra layer Medium Binder Duty, mm(t) 1125 66.2 264.8 297900
32173200 32173200
Base Granular A, mm(t) 6991 16.04 64.16 448542.56
48442596 48442596.48
Subbase Granular A, mm(t) 15206 8.27 33.08 503014.48
54325564 54325563.84
Shoulder PCCP ( 120mm ) (t) 100 94.92 379.68 37968 4100544 3661200
Shoulder Medium Binder Duty, mm(t) 125 66.2 264.8 33100
3574800 3574800
Subgrade
subgrade improvement, %
area(m^2)
500 6.16 24.64 12320
1330560 1330560
TOTAL 206874544 203140120.3
INTIAL COSTS Description Unit
unit cost
($)
quantity Cost
Cleraring of
vegeterian
Clearing and grubbing m^2 3 9720000
Grading; Earth
works
Earth excavation or fill m^3 27.06 14650000
Percent of rock excavation or
fill
%
Landscaping
Sodding and top soil m^2 4.22 13685760
Top soil m^3 3.2 3072000
Drainage of the
right of the way
Curb and Gutter m 360 108000 38880000
500 mm pipe culvert + end
sections
m 249 108000 26892000
1500 mm wide box culvert m 350 108000 37800000
bioretention swale drain km 50000 108 5400000
Guard rails and
safety appurtenats
Concrete median m 313 108000 33804000
Steel guardrail at shoulder m 56 108000 6048000
3 cable guard rail at shoulder m 10 108000 1080000
Fencicng and gates
Chain link fence m 15 108000 1620000
Wire fence m 9.03 108000 975240
Lighting Solar Panel Lights Piece 1700 16800 28560000
Electronic Tolling
System
Piece 50 600000 30000000
Traffic control
Painting of taraffic control
lines
Km 576 108 62208
TOTAL 252249208
9. Revenues- Alternative 1
Alternative 1 Alternative 2
0
50000000
100000000
150000000
200000000
250000000
300000000
350000000
400000000
450000000
500000000
AnnualRevenues($)
Year
TOTAL REVENU Over Life Cycle of
Project- Traditional Highway
0
100000000
200000000
300000000
400000000
500000000
600000000
700000000
AnnualRevenues($)
Year
TOTAL REVENU Over Life Cycle of
Project- Sustainable Highway
10. General Project Assumptions
Assumption Reference
MARR 3.95%
Based on the Inflation rate & Real
interest rate
Inflation Rate 1.07 Inflation Canada
Depreciation Rate 8% CCA Classes- Canada Revenue Agency
Corporate Tax
Rate 26.5%
Canada Revenue Agency
ATMARR 3% Based on MARR
Planning Horizon 30 years -
Bank Loan Interest
Rate
6% Highway 407 Ontario
11. Methods of Evaluation
The 8 Steps of a Systematic Economic Analysis
Technique:
1. Identify the alternatives
2. Define the planning horizon
3. Specify the discount rate
4. Estimate the cash flows (BTCF)
5. Determine the After Tax Cash Flow (ATCF)
6. Compare the alternatives
7. Perform supplementary analyses
8. Select the preferred investment
12. 2. Defining The Planning Horizon
The planning horizon is the amount of time an organization will look into the future
when preparing a strategic plan.
Four methods:
1. LCM
2. Longest Life
3. Shortest Life
4. Organizational needs
The planning horizon is estimated according to our “Firm’s need” decision based on
our contract duration period of 30 years, rather than the “Longest Life” planning
horizon which equals to 60 years.
13. 3. Specify the discount rate
The minimum attractive rate of return (MARR) is the interest rate that a firm
wished to earn on its investment
In order to calculate the value of MARR, the following equation is used:
(1 + MARR) = (1 + r) * (1+ f) where,
r = Real Interest rate
f = Inflation Rate
Real Interest Rate = 2.85% Annual Inflation Rate = 1.07% (Inflation Canada 2015(CPI))
From the equation, MARR = 3.95%
14. 4. Estimate The Before Tax Cash Flow (BTCF)
Bank Loan Cash Flow Project Cash Flow
16. BANK Loan Repayment Plans
Four loan repayment plans are evaluated:
1. Pay interest due at end of each year, and principal at end of year 30.
2. Make equal end-of-period principal payments of $10,179,409.21 and pay
interest each period on the unpaid balance at the beginning of the period.
3. Make 30 equal end-of-period payments over the loan period.
4. Make no payment until the end of the loan period.
Corporate interest rate of 6% compounded annually.
Method #2 has been chosen: Make equal end-of-period principal payments of
$10,179,409.21 and pay interest due at the end of each period. The interest
of each period is the interest on the unpaid balance at the beginning of the
year.
17. Tabular Method- Alternative 1
Using the Tabular Method,
the annual payment
(includes the principal &
interest) is calculated
using the annual worth
equation
Using The Tabular method,
the loan payment schedule
is constructed showing the
remaining balance at the
end of each year, Interest
payment and Principal
payment.
The payment will start
after the first year when
the construction phase is
over.
18. Loan Repayment Cash Flow- Alternative 1
(50,000,000.00)
-
50,000,000.00
100,000,000.00
150,000,000.00
200,000,000.00
250,000,000.00
300,000,000.00
350,000,000.00
BankLoanCashFlow($)
Year
19. Tabular Method- Alternative 2
Using the Tabular Method,
the annual payment
(includes the principal &
interest) is calculated
using the annual worth
equation
Using The Tabular method,
the loan payment schedule
is constructed showing the
remaining balance at the
end of each year, Interest
payment and Principal
payment.
The payment will start
after the first year when
the construction phase is
over.
21. Project Cash Flow
Cash flows are key to discounted cash flow valuations. To measure cash flows,
the following parameters have to be taken into consideration:
1. Specify the initial investment.
2. Specify the discount rate
3. Determine the salvage value
4. Determine the annual operating & maintenance expenses.
5. Determine the annual net income.
6. Determine the net cash flow in each year.
22. Project Cash Flow
Alternative 1 Alternative 2
(500,000,000.00)
(400,000,000.00)
(300,000,000.00)
(200,000,000.00)
(100,000,000.00)
-
100,000,000.00
200,000,000.00
300,000,000.00
400,000,000.00
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30
NetBeforeTaxCashFlow($)
End Of Year (EOY)
BTCF Traditional Highway-Alternative 1
(600,000,000.00)
(400,000,000.00)
(200,000,000.00)
-
200,000,000.00
400,000,000.00
600,000,000.00
800,000,000.00
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30
NetBeforeTaxCashFlow($)
End Of Year (EOY)
BTCF Sustainable Highway
23. 5. After Tax Cash Flow Analysis (ATCF)
INCOME TAX =Taxable income * Tax Rate
ATCF = Before Tax CF – income tax
MARR = ATMARR/ (1 – tax rate)
4% = ATMARR/ (1-26.5%)
ATMARR= 3%
CAA Depreciation Method
24. CAA Depreciation
The CCA rate for
highways is 8% in
class 17
Planning horizon =
30 years
26. 6. Compare Between Alternatives
Single project- Investment Worth Measurement:
1. Payback Period (PBP)
2. Present Worth (PW)
3. Annual Worth (AW)
4. Future Worth (FW)
5. Internal Rate of Return (IRR)
6. External Rate of Return (ERR)
7. Capitalized worth method (CW)
Accept the investment if:
PW >= 0$
FW >= 0$
AW >= 0$
IRR >= ATMARR
ERR >= ATMARR
27. 6. Compare Between Alternatives
PW analysis results:
The Present Worth (PW) of alternative 2 is $1,954,306,928 CAD and bigger than 0. The PW for Alternative 1
is $544,853,106 CAD and bigger than 0. The two investments are accepted.
AW analysis results:
Based on the Annual Worth analysis (AW) for each alternative, alternatives 1&2 are accepted.
FW analysis results:
Based on the Future Worth analysis (FW), FW1= $ 1 284 519 418,31 > 0, and FW2 =4,607,379,805 > 0, both
alternatives are accepted.
IRR analysis:
IRR for Alternative 1- Simple investment (one sign change) is 10.92%
IRR for Alternative 2- Simple investment (one sign change) is 35%
Both alternative IRR’s value are bigger than that of the ATMARR, but IRR Alternative B is higher and so the
Sustainable Highway investment is more attractive, since the higher the IRR on a project and the greater
the amount by which it exceeds the cost of capital.
28. Ranking Approach
In order to compare
between
alternatives using
the ranking
approach:
Find PW, of
Alternatives 1&2
Select the one with
the highest positive
PW value. Where;
Present worth (PW)
= F*(1+i) n
Consider the option
of “Doing Nothing”
= not to invest in
either alternatives.
Alternative B - Sustainable highway
is selected; PW(B) is the highest.
29. Incremental Approach
PW (B-A) > 0 select alternative B If IRR (B-A) > ATMARR
PW (B-A) = 0 select either one If IRR (B-A) = ATMARR
PW (B-A) < 0 select alternative A If IRR (B-A) < ATMARRT
PW (A-0) = $497,746,362.54 > 0
Alternative A is better than “do nothing”
PW (B- A) = $1,509,677,166.62 > 0
Alternative (B) is better than Alternative (A)
Alternative B is the best.
30. Supplementary Analysis
1. Sensitivity Analysis
Case 1
All parameters are fixed except for “ATMARR”.
Shows how change in ATMARR affect PW, AW, FW, and IRR.
$-
$200,000,000.00
$400,000,000.00
$600,000,000.00
$800,000,000.00
$1,000,000,000.00
$1,200,000,000.00
$1,400,000,000.00
Valuein$
% Error ATMARR
Sensitivity - % Error ATMARR -
Alternative 1
PW Traditional
FW Traditional
AW Traditional
IRR Traditional
31. Supplementary Analysis
1. Sensitivity Analysis
Case 2
All parameters are fixed except for “The total number of highway user”, which
directly affect the revenues.
Shows how change in the Revenue affect on “PW”, “AW”, “FW”, and “IRR”.
$(2,000,000,000.00)
$-
$2,000,000,000.00
$4,000,000,000.00
$6,000,000,000.00
$8,000,000,000.00
$10,000,000,000.00
$12,000,000,000.00
Valuein$
% Error No. of Users
Sensitivity - % Error No. of Users -
Sustainable
PW Sustainable
FW Sustainable
AW Sustainable
IRR Sustainable
32. Supplementary Analysis
Depreciation Methods Comparison-Alternative 1
0
50000000
100000000
150000000
200000000
250000000
300000000
350000000
400000000
450000000
1 2 3 4 5 6 7 8 9 10111213141516171819202122232425262728293031
ANNUALBOOKVALUE($)
YEAR
Comparision between Depreciation Methods
streight line
SOYD
CCA
34. 8.Select Preferred Investment
The two alternatives have been evaluated using the 8 Economic Methods of
Evaluation, Alternative 2, the Sustainable Highway design for Highway 640 is
selected, since it best meets the objectives of the study.