SlideShare a Scribd company logo
Earth Mat Design for Metro
Station
Subhendu Bikash Santra
SE/RVNL/KOLKATA
contents
 Introduction.
 Standards.
 Design Procedure.
 Example.
Introduction
 Earthing means connecting one conducting wire from
neutral point to ground [System Grounding] or from
equipment body to ground [ Equipment grounding].
 Earthing system is necessary to ensure safety of
equipment and personnel, continuity, protection and
reliability of overall system.
 Separate Earth or Clean Earth.
 Earth Mat.
Standard
 IS 3043:1989.
 IEEE 80:2000.
Purpose of Earth-MAT
 Provides easy and shortest path to flow the earth fault
current without adversely affecting the continuity of
service.
 Safe touch and step voltage for personnel nearby the
station area.
 Protection of costly devices from unbalanced voltage
during fault.
Design Procedure of Earth
Mat
 Determination of maximum L-G fault current and L-L-G
fault current at LT side. Take the larger one as fault
current for MAT design.
 Determine the grid current by using current split factor.
 Buried conductor size selection .
 Select Design according to the space availability.
Design Procedure of Earth
Mat
 Symmetrical [1:1 to 1:3 Mesh size]-IEEE Imperial
Formulae 80:2000 std.
 Non-Symmetrical- Finite Element Analysis using ETAP
software.
 For symmetrical-Minimum spacing between parallel
conductor is 2.5 m. and max-22.2m
 Perfect soil resistivity data is required for calculating
allowable step and touch voltage.
Design Procedure of Earth
Mat
 A high soil resistivity of crust layer is required where soil
resistivity is very high and fault current is large.
 Where soil resistivity is low there is no need of giving
high resistivity crust layer.
 Crust layer resistivity directly increases the allowable
touch and step potential without actually reducing
calculated touch and step voltage.
 Two layer soil model is required where soil resistivity is
non-uniform.
Design Procedure of Earth
Mat
 Increase in horizontal conductor length actually
reduces touch potential.
 Increase in no of down rod reduces step potential.
 Increase in no of mesh in mat reduces the touch
potential but beyond certain limit the MAT is said to be
saturated.
 So, we have to effectively use conductor and down-
rod to minimize the step and touch potential within
MAT zone and beyond of at least 2m from edge.
 IEEE 80: 2000 is particularly important for symmetrical
MAT design where space is not a problem.
Symmetrical Mat
Unsymmetrical MAT
Example : JOKA Station
 Space Availability : Non-Uniform
 Soil Resistivity: Non-Uniform. (7.60 ohm-m[6M] and
12.88 ohm-m (beyond 6M).
 Fault Current: 7.5 KA (max)
 Split Factor: 75%
 Crust layer treatment : Nothing is required as soil
resistivity is less and also fault current.
Example : JOKA Station
 Method : Finite Element Analysis Method.
 Analysis: ETAP software.
Proposed Drawing at JOKA
Simulation Result
Software
Window:
Software
Window:
Simulation Result
MAT Model
Corelated
with space
availability
Simulation Result
Result
Summery
Showing no
warning
Simulation Result
Step
Potential
Profile.
Simulation Result
Touch
Potential
Profile.
Simulation Result
Grid
Potential
Rise
Simulation Result
 Allowable Step: 231.8 V ; Calculated Step: 41.6 V
 Allowable Touch: 224.5 V ; Calculated Touch: 103 V
 Resistance : 0.09 Ohm (less than 1 ohm)
 GPR: 510.8 V which is considerably low for a remote
ended person. (transferred potential)
Thus the MAT design is safe and Acceptable.
Thank You

More Related Content

What's hot

Site selection for a harbour
Site selection for a harbourSite selection for a harbour
Site selection for a harbour
Latif Hyder Wadho
 
Guide lines bridge_design
Guide lines bridge_designGuide lines bridge_design
Guide lines bridge_design
Pralhad Kore
 
Prestressed concrete continuous beam
Prestressed concrete continuous beamPrestressed concrete continuous beam
Prestressed concrete continuous beam
PraveenKumar Shanmugam
 
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
Ratnesh Kushwaha
 
Rcc member design steps
Rcc member design stepsRcc member design steps
Rcc member design steps
DYPCET
 
staad pro
staad prostaad pro
staad pro
Jaspreet singh
 
Aircraft characteristics
Aircraft characteristicsAircraft characteristics
Aircraft characteristics
srinivas2036
 
Problems on bearing capacity of soil
Problems on bearing capacity of soilProblems on bearing capacity of soil
Problems on bearing capacity of soil
Latif Hyder Wadho
 
Marshall Mix Design: Lab Report
Marshall Mix Design: Lab ReportMarshall Mix Design: Lab Report
Marshall Mix Design: Lab Report
Priyansh Singh
 
Components of railway track
Components of railway trackComponents of railway track
Components of railway track
gayathrysatheesan1
 
Tunnel Engineering Report (VJTI MUMBAI)
Tunnel Engineering Report (VJTI MUMBAI)Tunnel Engineering Report (VJTI MUMBAI)
Tunnel Engineering Report (VJTI MUMBAI)
Mayur Rahangdale
 
Presentation on Summer internship on Road Construction
Presentation on Summer internship on Road ConstructionPresentation on Summer internship on Road Construction
Presentation on Summer internship on Road Construction
Self-employed
 
Construction of a New Railway Track
Construction of a New  Railway TrackConstruction of a New  Railway Track
Construction of a New Railway Track
Arbaz Kazi
 
1st Semester M Tech Structural Engineering (Dec-2013) Question Papers
1st Semester M Tech Structural Engineering  (Dec-2013) Question Papers 1st Semester M Tech Structural Engineering  (Dec-2013) Question Papers
1st Semester M Tech Structural Engineering (Dec-2013) Question Papers
BGS Institute of Technology, Adichunchanagiri University (ACU)
 
Construction of telecommunication towers
Construction of telecommunication towersConstruction of telecommunication towers
Construction of telecommunication towers
snookala
 
Laboratory Vane Shear Test
Laboratory Vane Shear TestLaboratory Vane Shear Test
Laboratory Vane Shear Test
A K
 
Structural analysis 2
Structural analysis   2Structural analysis   2
Structural analysis 2
R VIJAYAKUMAR
 
Design of a channel Reach
Design of a channel ReachDesign of a channel Reach
Design of a channel Reach
Latif Hyder Wadho
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavement
Bhavik A Shah
 
Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)
Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)
Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)
Hossam Shafiq I
 

What's hot (20)

Site selection for a harbour
Site selection for a harbourSite selection for a harbour
Site selection for a harbour
 
Guide lines bridge_design
Guide lines bridge_designGuide lines bridge_design
Guide lines bridge_design
 
Prestressed concrete continuous beam
Prestressed concrete continuous beamPrestressed concrete continuous beam
Prestressed concrete continuous beam
 
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
 
Rcc member design steps
Rcc member design stepsRcc member design steps
Rcc member design steps
 
staad pro
staad prostaad pro
staad pro
 
Aircraft characteristics
Aircraft characteristicsAircraft characteristics
Aircraft characteristics
 
Problems on bearing capacity of soil
Problems on bearing capacity of soilProblems on bearing capacity of soil
Problems on bearing capacity of soil
 
Marshall Mix Design: Lab Report
Marshall Mix Design: Lab ReportMarshall Mix Design: Lab Report
Marshall Mix Design: Lab Report
 
Components of railway track
Components of railway trackComponents of railway track
Components of railway track
 
Tunnel Engineering Report (VJTI MUMBAI)
Tunnel Engineering Report (VJTI MUMBAI)Tunnel Engineering Report (VJTI MUMBAI)
Tunnel Engineering Report (VJTI MUMBAI)
 
Presentation on Summer internship on Road Construction
Presentation on Summer internship on Road ConstructionPresentation on Summer internship on Road Construction
Presentation on Summer internship on Road Construction
 
Construction of a New Railway Track
Construction of a New  Railway TrackConstruction of a New  Railway Track
Construction of a New Railway Track
 
1st Semester M Tech Structural Engineering (Dec-2013) Question Papers
1st Semester M Tech Structural Engineering  (Dec-2013) Question Papers 1st Semester M Tech Structural Engineering  (Dec-2013) Question Papers
1st Semester M Tech Structural Engineering (Dec-2013) Question Papers
 
Construction of telecommunication towers
Construction of telecommunication towersConstruction of telecommunication towers
Construction of telecommunication towers
 
Laboratory Vane Shear Test
Laboratory Vane Shear TestLaboratory Vane Shear Test
Laboratory Vane Shear Test
 
Structural analysis 2
Structural analysis   2Structural analysis   2
Structural analysis 2
 
Design of a channel Reach
Design of a channel ReachDesign of a channel Reach
Design of a channel Reach
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavement
 
Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)
Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)
Lec 05 Horizontal Alignment (Transportation Engineering Dr.Lina Shbeeb)
 

Viewers also liked

Building lightning protection for Metro Railway
Building lightning protection for Metro RailwayBuilding lightning protection for Metro Railway
Building lightning protection for Metro Railway
Subhendu Bikash Santra
 
Earth MAT design for Metro Station
Earth MAT design for Metro StationEarth MAT design for Metro Station
Earth MAT design for Metro Station
Subhendu Bikash Santra
 
(3.4.1.2)station design guidelines final 122309
(3.4.1.2)station design guidelines final 122309(3.4.1.2)station design guidelines final 122309
(3.4.1.2)station design guidelines final 122309
Avtansh Ghai
 
Earthing fault
Earthing faultEarthing fault
Earthing fault
Hossam Zein
 
Electrical Design calculations
Electrical Design calculationsElectrical Design calculations
Electrical Design calculations
Pankaj Chavan
 
practical earth measure
practical earth measurepractical earth measure
practical earth measure
Rakesh Singh
 
Tp metro
Tp metroTp metro
2014 Kingsmill Product Catalogue (Edition 6)
2014 Kingsmill Product Catalogue (Edition 6)2014 Kingsmill Product Catalogue (Edition 6)
2014 Kingsmill Product Catalogue (Edition 6)
Thorne & Derrick International
 
ECNG 3015- System Earthing
ECNG 3015- System EarthingECNG 3015- System Earthing
ECNG 3015- System Earthing
Chandrabhan Sharma
 
Resistance Measurement instruments
Resistance Measurement instrumentsResistance Measurement instruments
Resistance Measurement instruments
Chandan Singh
 
Earthing Syatem
Earthing SyatemEarthing Syatem
Earthing Syatem
Noman Khan
 
Insulation Testing
Insulation TestingInsulation Testing
Insulation Testing
Powerpoint Engineering Ltd
 
Chapter 7
Chapter 7Chapter 7
Chapter 7
snoshoesam
 
Earth Resistance Testing
Earth Resistance TestingEarth Resistance Testing
Earth Resistance Testing
Powerpoint Engineering Ltd
 
Megger (mega-ohm-meter)
Megger (mega-ohm-meter)Megger (mega-ohm-meter)
Megger (mega-ohm-meter)
Kausik das
 
Fundamentals of Fire Alarm System
Fundamentals of Fire Alarm SystemFundamentals of Fire Alarm System
Fundamentals of Fire Alarm System
Subhendu Bikash Santra
 
Earthing
EarthingEarthing
Earthing
AKANSHA GURELE
 
Insulation Resistance Testing / Megger
Insulation Resistance Testing / Megger Insulation Resistance Testing / Megger
Insulation Resistance Testing / Megger
Roland Manansala
 
Earthing
EarthingEarthing
Earthing
vijay9213
 
Measurement of Resistance
Measurement of ResistanceMeasurement of Resistance
Measurement of Resistance
NIT Puducherry
 

Viewers also liked (20)

Building lightning protection for Metro Railway
Building lightning protection for Metro RailwayBuilding lightning protection for Metro Railway
Building lightning protection for Metro Railway
 
Earth MAT design for Metro Station
Earth MAT design for Metro StationEarth MAT design for Metro Station
Earth MAT design for Metro Station
 
(3.4.1.2)station design guidelines final 122309
(3.4.1.2)station design guidelines final 122309(3.4.1.2)station design guidelines final 122309
(3.4.1.2)station design guidelines final 122309
 
Earthing fault
Earthing faultEarthing fault
Earthing fault
 
Electrical Design calculations
Electrical Design calculationsElectrical Design calculations
Electrical Design calculations
 
practical earth measure
practical earth measurepractical earth measure
practical earth measure
 
Tp metro
Tp metroTp metro
Tp metro
 
2014 Kingsmill Product Catalogue (Edition 6)
2014 Kingsmill Product Catalogue (Edition 6)2014 Kingsmill Product Catalogue (Edition 6)
2014 Kingsmill Product Catalogue (Edition 6)
 
ECNG 3015- System Earthing
ECNG 3015- System EarthingECNG 3015- System Earthing
ECNG 3015- System Earthing
 
Resistance Measurement instruments
Resistance Measurement instrumentsResistance Measurement instruments
Resistance Measurement instruments
 
Earthing Syatem
Earthing SyatemEarthing Syatem
Earthing Syatem
 
Insulation Testing
Insulation TestingInsulation Testing
Insulation Testing
 
Chapter 7
Chapter 7Chapter 7
Chapter 7
 
Earth Resistance Testing
Earth Resistance TestingEarth Resistance Testing
Earth Resistance Testing
 
Megger (mega-ohm-meter)
Megger (mega-ohm-meter)Megger (mega-ohm-meter)
Megger (mega-ohm-meter)
 
Fundamentals of Fire Alarm System
Fundamentals of Fire Alarm SystemFundamentals of Fire Alarm System
Fundamentals of Fire Alarm System
 
Earthing
EarthingEarthing
Earthing
 
Insulation Resistance Testing / Megger
Insulation Resistance Testing / Megger Insulation Resistance Testing / Megger
Insulation Resistance Testing / Megger
 
Earthing
EarthingEarthing
Earthing
 
Measurement of Resistance
Measurement of ResistanceMeasurement of Resistance
Measurement of Resistance
 

Similar to earth mat design for metro station

Ieee depth
Ieee depthIeee depth
PRESTO POWER
PRESTO POWERPRESTO POWER
PRESTO POWER
Piero Belforte
 
PRESTO POWER
PRESTO POWERPRESTO POWER
PRESTO POWER
Piero Belforte
 
10.1.1.192.9435(1)
10.1.1.192.9435(1)10.1.1.192.9435(1)
10.1.1.192.9435(1)
Mohammad Ahmad
 
Design of Earthing System for 230 kV High Voltage Substation by ETAP 12.6 Sof...
Design of Earthing System for 230 kV High Voltage Substation by ETAP 12.6 Sof...Design of Earthing System for 230 kV High Voltage Substation by ETAP 12.6 Sof...
Design of Earthing System for 230 kV High Voltage Substation by ETAP 12.6 Sof...
ijtsrd
 
Six-port Interferometer for W-band Transceivers: Design and Characterization
Six-port Interferometer for W-band Transceivers: Design and CharacterizationSix-port Interferometer for W-band Transceivers: Design and Characterization
Six-port Interferometer for W-band Transceivers: Design and Characterization
IJECEIAES
 
High Speed Edge Card Transitions
High Speed Edge Card TransitionsHigh Speed Edge Card Transitions
High Speed Edge Card Transitions
Premier Farnell
 
Optimization of Empirical Modelling of Advanced Highly Strained In 0.7 Ga 0.3...
Optimization of Empirical Modelling of Advanced Highly Strained In 0.7 Ga 0.3...Optimization of Empirical Modelling of Advanced Highly Strained In 0.7 Ga 0.3...
Optimization of Empirical Modelling of Advanced Highly Strained In 0.7 Ga 0.3...
IJECEIAES
 
55tmtt05-pfeiffer-proof
55tmtt05-pfeiffer-proof55tmtt05-pfeiffer-proof
55tmtt05-pfeiffer-proof
David Goren
 
Design And Analysis Of Low Power High Performance Single Bit Full Adder
Design And Analysis Of Low Power High Performance Single Bit Full AdderDesign And Analysis Of Low Power High Performance Single Bit Full Adder
Design And Analysis Of Low Power High Performance Single Bit Full Adder
IJTET Journal
 
Design of Grounding System for Substation
Design of Grounding System for SubstationDesign of Grounding System for Substation
Design of Grounding System for Substation
ijtsrd
 
OPTIMIZATION OF WIRE EDM PARAMETERS TO ACHIEVE A FINE SURFACE FINISH
OPTIMIZATION OF WIRE EDM PARAMETERS TO ACHIEVE A FINE SURFACE FINISHOPTIMIZATION OF WIRE EDM PARAMETERS TO ACHIEVE A FINE SURFACE FINISH
OPTIMIZATION OF WIRE EDM PARAMETERS TO ACHIEVE A FINE SURFACE FINISH
Ijripublishers Ijri
 
IRJET- A Study on the Leakage Mechanism of Standard 6T Sram Cell
IRJET- A Study on the Leakage Mechanism of Standard 6T Sram CellIRJET- A Study on the Leakage Mechanism of Standard 6T Sram Cell
IRJET- A Study on the Leakage Mechanism of Standard 6T Sram Cell
IRJET Journal
 
grad project IEEE paper
grad project IEEE papergrad project IEEE paper
grad project IEEE paper
Akash Patel, EIT
 
IRJET- The Process of Edm Cutting Parameters Optimizing by using Taguchi Meth...
IRJET- The Process of Edm Cutting Parameters Optimizing by using Taguchi Meth...IRJET- The Process of Edm Cutting Parameters Optimizing by using Taguchi Meth...
IRJET- The Process of Edm Cutting Parameters Optimizing by using Taguchi Meth...
IRJET Journal
 
FORCED STACK SLEEP TRANSISTOR (FORTRAN): A NEW LEAKAGE CURRENT REDUCTION APPR...
FORCED STACK SLEEP TRANSISTOR (FORTRAN): A NEW LEAKAGE CURRENT REDUCTION APPR...FORCED STACK SLEEP TRANSISTOR (FORTRAN): A NEW LEAKAGE CURRENT REDUCTION APPR...
FORCED STACK SLEEP TRANSISTOR (FORTRAN): A NEW LEAKAGE CURRENT REDUCTION APPR...
VIT-AP University
 
MERITA PROJECT:METHODOLOGY TO EVALUATE RADIATED EMISSION FROM HIGH DENSITY MU...
MERITA PROJECT:METHODOLOGY TO EVALUATE RADIATED EMISSION FROM HIGH DENSITY MU...MERITA PROJECT:METHODOLOGY TO EVALUATE RADIATED EMISSION FROM HIGH DENSITY MU...
MERITA PROJECT:METHODOLOGY TO EVALUATE RADIATED EMISSION FROM HIGH DENSITY MU...
Piero Belforte
 
Performance Study of Wire Cut Electric Discharge Machining Process by Using T...
Performance Study of Wire Cut Electric Discharge Machining Process by Using T...Performance Study of Wire Cut Electric Discharge Machining Process by Using T...
Performance Study of Wire Cut Electric Discharge Machining Process by Using T...
International Journal of Engineering Inventions www.ijeijournal.com
 
Investigation of overvoltage on square, rectangular and L-shaped ground grid...
Investigation of overvoltage on square, rectangular and  L-shaped ground grid...Investigation of overvoltage on square, rectangular and  L-shaped ground grid...
Investigation of overvoltage on square, rectangular and L-shaped ground grid...
IJECEIAES
 
Implementation of cmos 3
Implementation of cmos 3Implementation of cmos 3
Implementation of cmos 3
IAEME Publication
 

Similar to earth mat design for metro station (20)

Ieee depth
Ieee depthIeee depth
Ieee depth
 
PRESTO POWER
PRESTO POWERPRESTO POWER
PRESTO POWER
 
PRESTO POWER
PRESTO POWERPRESTO POWER
PRESTO POWER
 
10.1.1.192.9435(1)
10.1.1.192.9435(1)10.1.1.192.9435(1)
10.1.1.192.9435(1)
 
Design of Earthing System for 230 kV High Voltage Substation by ETAP 12.6 Sof...
Design of Earthing System for 230 kV High Voltage Substation by ETAP 12.6 Sof...Design of Earthing System for 230 kV High Voltage Substation by ETAP 12.6 Sof...
Design of Earthing System for 230 kV High Voltage Substation by ETAP 12.6 Sof...
 
Six-port Interferometer for W-band Transceivers: Design and Characterization
Six-port Interferometer for W-band Transceivers: Design and CharacterizationSix-port Interferometer for W-band Transceivers: Design and Characterization
Six-port Interferometer for W-band Transceivers: Design and Characterization
 
High Speed Edge Card Transitions
High Speed Edge Card TransitionsHigh Speed Edge Card Transitions
High Speed Edge Card Transitions
 
Optimization of Empirical Modelling of Advanced Highly Strained In 0.7 Ga 0.3...
Optimization of Empirical Modelling of Advanced Highly Strained In 0.7 Ga 0.3...Optimization of Empirical Modelling of Advanced Highly Strained In 0.7 Ga 0.3...
Optimization of Empirical Modelling of Advanced Highly Strained In 0.7 Ga 0.3...
 
55tmtt05-pfeiffer-proof
55tmtt05-pfeiffer-proof55tmtt05-pfeiffer-proof
55tmtt05-pfeiffer-proof
 
Design And Analysis Of Low Power High Performance Single Bit Full Adder
Design And Analysis Of Low Power High Performance Single Bit Full AdderDesign And Analysis Of Low Power High Performance Single Bit Full Adder
Design And Analysis Of Low Power High Performance Single Bit Full Adder
 
Design of Grounding System for Substation
Design of Grounding System for SubstationDesign of Grounding System for Substation
Design of Grounding System for Substation
 
OPTIMIZATION OF WIRE EDM PARAMETERS TO ACHIEVE A FINE SURFACE FINISH
OPTIMIZATION OF WIRE EDM PARAMETERS TO ACHIEVE A FINE SURFACE FINISHOPTIMIZATION OF WIRE EDM PARAMETERS TO ACHIEVE A FINE SURFACE FINISH
OPTIMIZATION OF WIRE EDM PARAMETERS TO ACHIEVE A FINE SURFACE FINISH
 
IRJET- A Study on the Leakage Mechanism of Standard 6T Sram Cell
IRJET- A Study on the Leakage Mechanism of Standard 6T Sram CellIRJET- A Study on the Leakage Mechanism of Standard 6T Sram Cell
IRJET- A Study on the Leakage Mechanism of Standard 6T Sram Cell
 
grad project IEEE paper
grad project IEEE papergrad project IEEE paper
grad project IEEE paper
 
IRJET- The Process of Edm Cutting Parameters Optimizing by using Taguchi Meth...
IRJET- The Process of Edm Cutting Parameters Optimizing by using Taguchi Meth...IRJET- The Process of Edm Cutting Parameters Optimizing by using Taguchi Meth...
IRJET- The Process of Edm Cutting Parameters Optimizing by using Taguchi Meth...
 
FORCED STACK SLEEP TRANSISTOR (FORTRAN): A NEW LEAKAGE CURRENT REDUCTION APPR...
FORCED STACK SLEEP TRANSISTOR (FORTRAN): A NEW LEAKAGE CURRENT REDUCTION APPR...FORCED STACK SLEEP TRANSISTOR (FORTRAN): A NEW LEAKAGE CURRENT REDUCTION APPR...
FORCED STACK SLEEP TRANSISTOR (FORTRAN): A NEW LEAKAGE CURRENT REDUCTION APPR...
 
MERITA PROJECT:METHODOLOGY TO EVALUATE RADIATED EMISSION FROM HIGH DENSITY MU...
MERITA PROJECT:METHODOLOGY TO EVALUATE RADIATED EMISSION FROM HIGH DENSITY MU...MERITA PROJECT:METHODOLOGY TO EVALUATE RADIATED EMISSION FROM HIGH DENSITY MU...
MERITA PROJECT:METHODOLOGY TO EVALUATE RADIATED EMISSION FROM HIGH DENSITY MU...
 
Performance Study of Wire Cut Electric Discharge Machining Process by Using T...
Performance Study of Wire Cut Electric Discharge Machining Process by Using T...Performance Study of Wire Cut Electric Discharge Machining Process by Using T...
Performance Study of Wire Cut Electric Discharge Machining Process by Using T...
 
Investigation of overvoltage on square, rectangular and L-shaped ground grid...
Investigation of overvoltage on square, rectangular and  L-shaped ground grid...Investigation of overvoltage on square, rectangular and  L-shaped ground grid...
Investigation of overvoltage on square, rectangular and L-shaped ground grid...
 
Implementation of cmos 3
Implementation of cmos 3Implementation of cmos 3
Implementation of cmos 3
 

earth mat design for metro station

  • 1. Earth Mat Design for Metro Station Subhendu Bikash Santra SE/RVNL/KOLKATA
  • 2. contents  Introduction.  Standards.  Design Procedure.  Example.
  • 3. Introduction  Earthing means connecting one conducting wire from neutral point to ground [System Grounding] or from equipment body to ground [ Equipment grounding].  Earthing system is necessary to ensure safety of equipment and personnel, continuity, protection and reliability of overall system.  Separate Earth or Clean Earth.  Earth Mat.
  • 5. Purpose of Earth-MAT  Provides easy and shortest path to flow the earth fault current without adversely affecting the continuity of service.  Safe touch and step voltage for personnel nearby the station area.  Protection of costly devices from unbalanced voltage during fault.
  • 6. Design Procedure of Earth Mat  Determination of maximum L-G fault current and L-L-G fault current at LT side. Take the larger one as fault current for MAT design.  Determine the grid current by using current split factor.  Buried conductor size selection .  Select Design according to the space availability.
  • 7. Design Procedure of Earth Mat  Symmetrical [1:1 to 1:3 Mesh size]-IEEE Imperial Formulae 80:2000 std.  Non-Symmetrical- Finite Element Analysis using ETAP software.  For symmetrical-Minimum spacing between parallel conductor is 2.5 m. and max-22.2m  Perfect soil resistivity data is required for calculating allowable step and touch voltage.
  • 8. Design Procedure of Earth Mat  A high soil resistivity of crust layer is required where soil resistivity is very high and fault current is large.  Where soil resistivity is low there is no need of giving high resistivity crust layer.  Crust layer resistivity directly increases the allowable touch and step potential without actually reducing calculated touch and step voltage.  Two layer soil model is required where soil resistivity is non-uniform.
  • 9. Design Procedure of Earth Mat  Increase in horizontal conductor length actually reduces touch potential.  Increase in no of down rod reduces step potential.  Increase in no of mesh in mat reduces the touch potential but beyond certain limit the MAT is said to be saturated.  So, we have to effectively use conductor and down- rod to minimize the step and touch potential within MAT zone and beyond of at least 2m from edge.  IEEE 80: 2000 is particularly important for symmetrical MAT design where space is not a problem.
  • 12. Example : JOKA Station  Space Availability : Non-Uniform  Soil Resistivity: Non-Uniform. (7.60 ohm-m[6M] and 12.88 ohm-m (beyond 6M).  Fault Current: 7.5 KA (max)  Split Factor: 75%  Crust layer treatment : Nothing is required as soil resistivity is less and also fault current.
  • 13. Example : JOKA Station  Method : Finite Element Analysis Method.  Analysis: ETAP software.
  • 21. Simulation Result  Allowable Step: 231.8 V ; Calculated Step: 41.6 V  Allowable Touch: 224.5 V ; Calculated Touch: 103 V  Resistance : 0.09 Ohm (less than 1 ohm)  GPR: 510.8 V which is considerably low for a remote ended person. (transferred potential) Thus the MAT design is safe and Acceptable.