International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 09 | Sep 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 295
Design of Flexible Pavements for an Existing Road
Dr. S. S. Saraf1, Mr. Aniket D. Dhoke2, Mr. M. R. Vyawhare3, Mr. A. R. Bijwe4.
¹ First Author, Assistance Professor, Department of Civil Engineering, P. R. Pote ( Patil ) College of Engineering and
Management, Amravati
² - Second Author, PG Student, M.E Transportation Engineering and Management, Dr. Rajendra Gode Institute of
Technology and Research, (SGBAU) Amravati
³ - Third Author, Professor and Head, Civil Engineering Department, Dr. Rajendra Gode Institute of Technology and
Research, (SGBAU) Amravati
4 – Fourth Author, Assistant Professor, Civil Engineering Department, Dr. Rajendra Gode Institute of Technology
and Research, (SGBAU) Amravati
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract - Pavements are expected for the smooth,
protected and orderly entry of traffic, Pavements are by and
large named adaptable and unbending Pavements.
Adaptable Pavements are those which have are for the most
part named adaptable and unbending Pavements.
Adaptable Pavements are those which have low flexural
strength and are adaptable in their primary activity under
loads. Unbending Pavements are low flexural strength and
are adaptable in their primary activity those which have
essential flexural strength and flexural inflexibility. The
significant advancement in the auto versatile innovation has
come about weighty moving burdens on the current
expressways for streamlining of the vehicle cost. The current
streets which are planned in view of the thumb rules can't
take special care of the weighty wheel loads bringing about
the crumbling of the current streets. In the venture report,
an endeavor is made to plan a street at Paratwada, in light
of the standards of Pavement plan. On the current
arrangement of the street, soil tests are gathered for the
assurance of soil attributes like consistency limit, strainer
examination, CBR values and so on, Based on this the
thickness of Pavement (flexible)is planned. The
arrangement of the streets is likewise planned and fixed by
studying and evening out. The absolute street length being
497 meters of which, on segment is 247m, other is 200m and
the third area is 50m.
1. INTRODUCTION
For financial and effective development of interstates,
right plan of the thickness of Pavements for various states
of traffic and sub-grades is fundamental. The study of
Pavement configuration is moderately new. In India,
already street outside was planned on a few level headed
information however more on the experience of the street
engineer. A few erratic thicknesses of the Pavements were
utilized which lead to exorbitant disappointments and
wastage as at times, the thickness of Pavements was
lacking and in different cases costly. As there could be no
legitimate plan measures, the development of streets was
pretty much uneconomical in practically all cases.
Consequently sensible strategy for planning and
ascertaining the outside layer thickness based on
assessment of traffic loads and bearing limit of sub-grade
and so on.
2. PAVEMENT
Pavement is a planned design laid on an area, expected to
support vehicular traffic. The capability of Pavement is to
communicate burdens to the sub-base and under lying
soil. Presently a day's Flexible Pavements contain sand
and rock or squashed stone compacted with a cover of
bituminous material, like Pavementic tar or Pavementic
oil. Such Pavement has sufficient versatility to retain
shocks.
Types of Pavements:
Based on the structural behavior, pavements are generally
classified into the following three categories:
1. Flexible pavement
2. Rigid pavement
3. Semi-rigid pavement.
2.1 Flexible Pavement:
Figure 1: Flexible Pavement
Adaptable Pavements are those which are adaptable in
their primary activity under the heaps. A few significant
elements of these Pavements are:
1.It has no flexural strength,
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 09 | Sep 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 296
2.It reflects the deformation of lower layers,
3.It will transmit the vertical compressive stress to
bottom layers by grain to grain transfer, Design
procedure of Flexible pavement using IRC method.
Flexible pavements consist of the following components:
1.Soil sub grade
2.Sub base course
3.Base course
4.Surface course
2.2 Rigid Pavement:
Figure 2: Rigid Pavement
Rigid pavements are those which possess noteworthy
flexural rigidity.
1.It possesses flexural strength
2. Load transfer is by the way of slab action and it
distributes the wheel load to a wider area below
3. Flexural stresses will be developed due to wheel load
temperature changes Survey.
Rigid pavement consists of the following components:
1. Cement Concrete slab
2. Base course
3. Soil sub grade
2.3 Semi-Rigid Pavement:
1. At the point when fortified materials like
pozzolanic concrete, lean cement or soil concrete
are utilized, then the Pavement layer has
impressively high flexural strength than the
normal adaptable Pavement is known as a semi-
inflexible Pavement.
2. These materials have low protection from effect
and scraped spot and are in this manner utilized
with adaptable Pavement surface course.
Figure 3: Functions of Pavement
2.4 Functions Of Pavement Components
2.4.1 Soil Subgrade:
1. The Pavement load is at last taken by soil sub grade
and thus for no situation it ought to be over focused
and top 50cm layer of soil sub grade ought to be all
around compacted at O.M.C.
2. Common strength tests used for evaluation of soil
sub grade are:
a. California Bearing Ratio test
b. California resistance value test
c. Tri-axial compression test
d. Plate bearing test
2.4.2 Sub base and Base Courses:
These are broken stone totals. It is alluring to utilize
more modest size evaluated totals at sub base course
rather than rock stones. Base and sub base courses are
utilized under adaptable Pavements principally to
further develop load supporting limit by dissemination
of burden through a limited thickness.
Base courses are used under rigid pavements for :
a.Preventing pumping
b. Protecting the sub grade
2.4.3 Wearing Course:
Purpose behind this course is to give smooth riding
surface. It opposes pressure applied by tires and takes
up mileage because of traffic. It additionally offers
water snugness.
The dependability of wearing course is assessed by
Marshaling solidness test where in ideal percent of
bituminous material is worked out in light of
steadiness thickness, voids in mineral total (V M A) and
voids loaded up with bitumen (V F B). Plate Bearing
test are likewise in some cases made use for hoisting
the wearing course and the Pavement in general.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 09 | Sep 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 297
2.5 Factors to be considered in the design of
pavements
Pavement configuration comprises of two sections:
1. Mix plan of material to be utilized in every
Pavement part layer
2. Thickness plan of the Pavement and the part layer
The different variables to be considered for the plan of
Pavement are:
1. Design wheel load
2. Sub grade soil
3. Climatic factors
4. Pavement component material
5. Environmental factors
2.5.1 Traffic & Loads acting on pavement
Traffic and Loads following up on Pavement are thought
about while planning an Pavement. Loads cause stresses,
distortions, and removals in structures Analysis of their
belongings is done by the strategies for primary
examination. Over-burdening might cause primary
disappointment, and consequently underlying
disappointment ought to be either viewed as in the plan or
stringently controlled. The various sorts of burdens
following up on streets are as per the following:
1. Contact pressure.
2. Repetition of loads.
3. Wheel load.
4. Axle configuration.
2.5.2 Contact Pressure:
The tire pressure is a significant element, as it decides the
contact region of the wheel to the Pavement surface.
Despite the fact that the state of the contact region is
curved, a round region is frequently considered for
purpose of effortlessness in examination.
2.5.3 Repetition of Loads:
The impact of traffic on Pavement, not just rely upon the
size of the wheel load, yet additionally on the recurrence
of the heap application. Each heap application cause a few
distortion and the complete twisting is the summation of
every one of these. Consequently, present day plan
depends on all out number of standard axles.
2.5.4 Wheel load:
The following significant variable is the wheel load it
decides the profundity of the Pavement expected to
guarantee that the sub grade soil isn't fizzled. The
pressure dissemination and diversion inside an Pavement
are affected by wheel design.
2.5.5 Axle configuration:
The Standard Axle thought about is Single Axle with Dual
wheel 80 KN, where Single wheel load is 20 KN.
3. LITERATURE REVIEW
Adaptable Pavements are liked over concrete substantial
streets as they enjoy an extraordinary benefit that these
can be reinforced and worked on in stages with the
development of traffic and furthermore their surfaces can
be processed and reused for restoration. The adaptable
Pavements are more affordable additionally concerning
introductory venture and upkeep. Albeit Rigid Pavement is
costly yet have less upkeep and having great plan period.
The monetary part is completed for the plan Pavement of a
segment by utilizing the outcomes got by plan strategy and
their relating part layer thickness.
Saurabh Jain, Dr. Y. P. Joshi, S. S. Goliya: This paper talks
about the plan techniques that are generally being followed
and inspects the "Plan of inflexible and adaptable
Pavements by different strategies and their expense
investigation by every strategy"
D. S. V. Prasad and G. V. R. Prasada Raju : This paper
examines the exhibition of adaptable Pavement on far
reaching soil sub grade utilizing rock/fly debris as sub base
course with squander tire elastic as a building up material.
It was seen that from the research center test aftereffects of
direct shear and CBR, the rock sub base shows better
execution when contrasted with fly debris sub base with
various rates of waste tire elastic as supporting material.
Cyclic burden tests are likewise completed in the research
center by putting a roundabout metal plate on the model
adaptable Pavements. It was seen that the greatest burden
conveying limit related with less worth of bounce back
avoidance got for rock supported sub base contrasted with
fly debris built up sub base.
4. METHODOLOGY
The three soil tests are utilized in the review. For these Soil
samples1,2,3 are the Index and Engineering properties are
resolved are organized in the Table.1.The soil
protuberances were broken into pieces and sieved through
4.75mm sifter and afterward dried in broiler at 1050c for
24 hours. The dirt are named I.S Classification system(IS
1498-1970).
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 09 | Sep 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 298
Description Sample
1
Sample2 Sample3
D10 0.18 0.075 0.09
D30 0.4 0.22 0.26
D60 0.65 0.89 0.9
Uniform
Coefficient(CU)
3.61 11.86 10
Coefficient of
Curvature(CC)
1.367 0.725 0.834
Liquid limit 38.5 26.5 25.5
Plastic limit 22.2 21.05 19.32
Plasticity index 16.3 5.45 6.18
Free swell index 80 80 72
Specific gravity 2.2 2.2 2
Maximum Dry
Density
(g/cc)
1.678 1.91 2.05
Optimum Moisture
Content
(%)
10.63 8.1 11.5
Table 1: Properties of Soil
4.1 Experimental Programme & Discussion
4.1.1 Collection of Samples:
Three samples of soils had been collected in the
location ofthe Paratwada site (work).
4.1.2 Types of Soil Test:
The different types of tests conducted on the samples
are;
1. Index properties
2. Specific gravity
3. Compaction characteristics
4. California bearing ratio
Type of material Suggested CBR value(%)
Gravel 25
Road metal 55
Table 2: CBR values of
Sample A, Sample B, Sample C (Soaking)
Graph 1: CBR values of Sample A, Sample B,Sample C
(Soaking)
4.2 Design of Pavement Thickness by CBR
Method:
1. The soil tests are taken and their ideal dampness still
up in the air by Proctor's thickness test for light compaction.
2. The soil test is then compacted in CBR shape for ideal
thickness and the form is drenched for 3 days.
3. The CBR test is then performed to get the CBR values
for the dirt sub grade
Figure 4: CBR Design chart
Sample 1:
CBR corresponding to 2.5mm penetration
=(74.4/1370) × 100 = 5.4%
Assume, Average Daily Traffic (ADT) = 300Annual rate
of growth of traffic (r) = 8%
Time taken for pavement construction (n) = 1 yearNo.
of vehicles for design (A) = P (1 + r )(n +10)
325
300
275
250
225
200
175
150
125
Sample 1
Sample 2
Sample 3
0 1 2 3 4 5 6 7 8 9 10 11
Penetration in (mm)
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 09 | Sep 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 299
= 300(1 +8/ 100 )(1 + 10)
= 699.49 vehicles/day
= 700 vehicles/day
 Thus 40cm of pavement materials is required to
cover thenatural soil subgrade having 5.4% CBR
value. Therefore, the thickness of base and sub base
courses are12.5cm and 22cm having CBR value 55%
and 25% usingthe design chart.
 The CBR values for the gravel and road metal are
assumedas follows
Description Sample1 Sample2 Sample3
CBR value of
2.5mm
14.36% 13.59% 14.756%
CBR value of
5.0mm
11.13% 12.426% 11.12%
Table 3: The Suggested CBR Values of Sample 1 for Type
of material
Sample 2:
CBR corresponding to 5 mm penetration = 4.91%
Assume, Average Daily Traffic (ADT) = 300 Annual rate
of growth of traffic (r) = 8%
Time taken for pavement construction (n) = 1 year
No. ofvehicles for design (A) = P (1 + r )(n + 10)
= 300(1 +8/100) (1 + 10)
= 699.49 vehicles/day
= 700 vehicles/day
 Thus 45cm of pavement materials is required to cover
thenatural soil sub grade having 4.9% CBR value.
 Therefore, the thickness of base and sub base courses
are 13cm and 25cm having CBR value 50% and 25%
using the design chart.
The CBR values for the gravel and road metal are
assumedas follows:
Type of material Suggested CBR value(%)
Gravel 25
Road metal 50
Sample 3:
CBR corresponding to 2.5mm penetration
=(77.8/1370) ×100 = 5.8%
Assume, Average Daily Traffic (ADT) = 300 Annual
rate of growth of traffic (r) = 8%
Time taken for pavement construction (n) = 1 yearNo. of
vehicles for design (A) = P (1 + r )(n + 10)
= 300(1 +8/100 )(1 + 10)
= 699.49 vehicles/day
= 700 vehicles/day
 Thus 38cm of pavement materials is required to cover
thenatural soil subgrade having 5.8% CBR value.
 Therefore, the thickness of base and sub base courses
are 11cm and 22cm having CBR value 47% and 25%
using thedesign chart.
The CBR values for the gravel and road metal are
assumedas follows:
Type of material Suggested CBR value (%)
Gravel 25
Road metal 47
Table 5: The Suggested CBR Values of Sample 3for Type of
material
5. CONCLUSION
In this task work, an endeavor is made to consolidate most
recent methods of mathematical plan, Pavement plan for a
street for a current state which 2 km away from
Paratwada.
• The IRC details depend on levelheaded reasoning, the
proposed street is protected in both geometrics as well as
Pavement plan. It is likewise proposed to plan an
adaptable Pavement by Group Index technique and CBR
strategy.
• A few additional techniques are accessible in the plan of
adaptable Pavement, which are greatly exceptional like
California opposing worth strategy, Mc leod technique,
Tri-pivotal strategy and Burnister strategy. In light of the
limits of time and degree, just GI technique and CBR
strategy are embraced.
Table 4: The Suggested CBR Values of Sample 2 for
Type of material
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 09 | Sep 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 300
6. REFERENCES
[1] “Highway Engineering” by S.K.Khanna and C.E.G.Justo
[2] “ Highway Engineering” by T.D.Ahuja
[3] “Estimation and costing in civil engineering” by
B.N.Dutta
[4] “Soil mechanics and foundation engineering” by
K.R.Arora
[5] “Surveying” by K.R.Arora
[6] “Surveying” by B.C.Punmia
[7] “IRC 37-2001”: Guidelines for the design of flexible
pavements.

More Related Content

Similar to Design of Flexible Pavements for an Existing Road

IRJET- Study on Flexible Pavement Failures and it’s Remedial Measures
IRJET- Study on Flexible Pavement Failures and it’s Remedial MeasuresIRJET- Study on Flexible Pavement Failures and it’s Remedial Measures
IRJET- Study on Flexible Pavement Failures and it’s Remedial Measures
IRJET Journal
 
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET Journal
 
Experimental Study on Pavement Stabilization Using Geosynthetic Solution
Experimental Study on Pavement Stabilization Using Geosynthetic SolutionExperimental Study on Pavement Stabilization Using Geosynthetic Solution
Experimental Study on Pavement Stabilization Using Geosynthetic Solution
IRJET Journal
 
Metro Work
Metro WorkMetro Work
Metro Work
Rajendra Kumar
 
IRJET- Study on Partial Replacement of Plastic Waste Material with Coarse...
IRJET-  	  Study on Partial Replacement of Plastic Waste Material with Coarse...IRJET-  	  Study on Partial Replacement of Plastic Waste Material with Coarse...
IRJET- Study on Partial Replacement of Plastic Waste Material with Coarse...
IRJET Journal
 
Utilization of industrial waste materials in the construction of interlocking...
Utilization of industrial waste materials in the construction of interlocking...Utilization of industrial waste materials in the construction of interlocking...
Utilization of industrial waste materials in the construction of interlocking...
IRJET Journal
 
IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...
IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...
IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...
IRJET Journal
 
Ch 9
Ch 9Ch 9
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
Patel Tapan
 
A Review Paper on Analysis and Design of Precast Box Culvert Bridge
A Review Paper on Analysis and Design of Precast Box Culvert BridgeA Review Paper on Analysis and Design of Precast Box Culvert Bridge
A Review Paper on Analysis and Design of Precast Box Culvert Bridge
IRJET Journal
 
PPT FINAL.pptx
PPT FINAL.pptxPPT FINAL.pptx
PPT FINAL.pptx
Beipazilaikibby
 
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESProject:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Malay Talaviya
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck Level
IRJET Journal
 
presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)
alamrintu
 
Bituminous Pavement Failures
Bituminous Pavement FailuresBituminous Pavement Failures
Bituminous Pavement Failures
IJERA Editor
 
Highway Pavement
Highway PavementHighway Pavement
Highway Pavement
Moses Payma Dukuly
 
Design and construction of highway (flexible pavement
Design and construction of highway (flexible pavementDesign and construction of highway (flexible pavement
Design and construction of highway (flexible pavement
suraj vishwakarma
 
Flexible pavement
Flexible pavement  Flexible pavement
Flexible pavement
AmitKumar8089
 
Pavement design
Pavement designPavement design
Pavement design
Garvit Goyal
 
Usage of geogrids in flexible pavement
Usage of geogrids in flexible pavementUsage of geogrids in flexible pavement
Usage of geogrids in flexible pavement
Aglaia Connect
 

Similar to Design of Flexible Pavements for an Existing Road (20)

IRJET- Study on Flexible Pavement Failures and it’s Remedial Measures
IRJET- Study on Flexible Pavement Failures and it’s Remedial MeasuresIRJET- Study on Flexible Pavement Failures and it’s Remedial Measures
IRJET- Study on Flexible Pavement Failures and it’s Remedial Measures
 
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...IRJET-  	  Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
IRJET- Design and Analysis of Flexible Pavement in Amaravati Governemnt C...
 
Experimental Study on Pavement Stabilization Using Geosynthetic Solution
Experimental Study on Pavement Stabilization Using Geosynthetic SolutionExperimental Study on Pavement Stabilization Using Geosynthetic Solution
Experimental Study on Pavement Stabilization Using Geosynthetic Solution
 
Metro Work
Metro WorkMetro Work
Metro Work
 
IRJET- Study on Partial Replacement of Plastic Waste Material with Coarse...
IRJET-  	  Study on Partial Replacement of Plastic Waste Material with Coarse...IRJET-  	  Study on Partial Replacement of Plastic Waste Material with Coarse...
IRJET- Study on Partial Replacement of Plastic Waste Material with Coarse...
 
Utilization of industrial waste materials in the construction of interlocking...
Utilization of industrial waste materials in the construction of interlocking...Utilization of industrial waste materials in the construction of interlocking...
Utilization of industrial waste materials in the construction of interlocking...
 
IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...
IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...
IRJET- Study on Causes of Cracks and its Remedial Measures in Reinforced Conc...
 
Ch 9
Ch 9Ch 9
Ch 9
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
 
A Review Paper on Analysis and Design of Precast Box Culvert Bridge
A Review Paper on Analysis and Design of Precast Box Culvert BridgeA Review Paper on Analysis and Design of Precast Box Culvert Bridge
A Review Paper on Analysis and Design of Precast Box Culvert Bridge
 
PPT FINAL.pptx
PPT FINAL.pptxPPT FINAL.pptx
PPT FINAL.pptx
 
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURESProject:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
Project:- SURVEY AND ANALYSIS OF ROAD PAVEMENT FAILURES
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck Level
 
presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)
 
Bituminous Pavement Failures
Bituminous Pavement FailuresBituminous Pavement Failures
Bituminous Pavement Failures
 
Highway Pavement
Highway PavementHighway Pavement
Highway Pavement
 
Design and construction of highway (flexible pavement
Design and construction of highway (flexible pavementDesign and construction of highway (flexible pavement
Design and construction of highway (flexible pavement
 
Flexible pavement
Flexible pavement  Flexible pavement
Flexible pavement
 
Pavement design
Pavement designPavement design
Pavement design
 
Usage of geogrids in flexible pavement
Usage of geogrids in flexible pavementUsage of geogrids in flexible pavement
Usage of geogrids in flexible pavement
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
IRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
IRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
IRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
IRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
IRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
IRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
IRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
PauloRodrigues104553
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
Ratnakar Mikkili
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
RadiNasr
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
ihlasbinance2003
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
Madan Karki
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
University of Maribor
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 

Recently uploaded (20)

New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Series of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.pptSeries of visio cisco devices Cisco_Icons.ppt
Series of visio cisco devices Cisco_Icons.ppt
 
Exception Handling notes in java exception
Exception Handling notes in java exceptionException Handling notes in java exception
Exception Handling notes in java exception
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdfIron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
Iron and Steel Technology Roadmap - Towards more sustainable steelmaking.pdf
 
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
5214-1693458878915-Unit 6 2023 to 2024 academic year assignment (AutoRecovere...
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 
Manufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptxManufacturing Process of molasses based distillery ppt.pptx
Manufacturing Process of molasses based distillery ppt.pptx
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 

Design of Flexible Pavements for an Existing Road

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 09 | Sep 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 295 Design of Flexible Pavements for an Existing Road Dr. S. S. Saraf1, Mr. Aniket D. Dhoke2, Mr. M. R. Vyawhare3, Mr. A. R. Bijwe4. ¹ First Author, Assistance Professor, Department of Civil Engineering, P. R. Pote ( Patil ) College of Engineering and Management, Amravati ² - Second Author, PG Student, M.E Transportation Engineering and Management, Dr. Rajendra Gode Institute of Technology and Research, (SGBAU) Amravati ³ - Third Author, Professor and Head, Civil Engineering Department, Dr. Rajendra Gode Institute of Technology and Research, (SGBAU) Amravati 4 – Fourth Author, Assistant Professor, Civil Engineering Department, Dr. Rajendra Gode Institute of Technology and Research, (SGBAU) Amravati ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract - Pavements are expected for the smooth, protected and orderly entry of traffic, Pavements are by and large named adaptable and unbending Pavements. Adaptable Pavements are those which have are for the most part named adaptable and unbending Pavements. Adaptable Pavements are those which have low flexural strength and are adaptable in their primary activity under loads. Unbending Pavements are low flexural strength and are adaptable in their primary activity those which have essential flexural strength and flexural inflexibility. The significant advancement in the auto versatile innovation has come about weighty moving burdens on the current expressways for streamlining of the vehicle cost. The current streets which are planned in view of the thumb rules can't take special care of the weighty wheel loads bringing about the crumbling of the current streets. In the venture report, an endeavor is made to plan a street at Paratwada, in light of the standards of Pavement plan. On the current arrangement of the street, soil tests are gathered for the assurance of soil attributes like consistency limit, strainer examination, CBR values and so on, Based on this the thickness of Pavement (flexible)is planned. The arrangement of the streets is likewise planned and fixed by studying and evening out. The absolute street length being 497 meters of which, on segment is 247m, other is 200m and the third area is 50m. 1. INTRODUCTION For financial and effective development of interstates, right plan of the thickness of Pavements for various states of traffic and sub-grades is fundamental. The study of Pavement configuration is moderately new. In India, already street outside was planned on a few level headed information however more on the experience of the street engineer. A few erratic thicknesses of the Pavements were utilized which lead to exorbitant disappointments and wastage as at times, the thickness of Pavements was lacking and in different cases costly. As there could be no legitimate plan measures, the development of streets was pretty much uneconomical in practically all cases. Consequently sensible strategy for planning and ascertaining the outside layer thickness based on assessment of traffic loads and bearing limit of sub-grade and so on. 2. PAVEMENT Pavement is a planned design laid on an area, expected to support vehicular traffic. The capability of Pavement is to communicate burdens to the sub-base and under lying soil. Presently a day's Flexible Pavements contain sand and rock or squashed stone compacted with a cover of bituminous material, like Pavementic tar or Pavementic oil. Such Pavement has sufficient versatility to retain shocks. Types of Pavements: Based on the structural behavior, pavements are generally classified into the following three categories: 1. Flexible pavement 2. Rigid pavement 3. Semi-rigid pavement. 2.1 Flexible Pavement: Figure 1: Flexible Pavement Adaptable Pavements are those which are adaptable in their primary activity under the heaps. A few significant elements of these Pavements are: 1.It has no flexural strength,
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 09 | Sep 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 296 2.It reflects the deformation of lower layers, 3.It will transmit the vertical compressive stress to bottom layers by grain to grain transfer, Design procedure of Flexible pavement using IRC method. Flexible pavements consist of the following components: 1.Soil sub grade 2.Sub base course 3.Base course 4.Surface course 2.2 Rigid Pavement: Figure 2: Rigid Pavement Rigid pavements are those which possess noteworthy flexural rigidity. 1.It possesses flexural strength 2. Load transfer is by the way of slab action and it distributes the wheel load to a wider area below 3. Flexural stresses will be developed due to wheel load temperature changes Survey. Rigid pavement consists of the following components: 1. Cement Concrete slab 2. Base course 3. Soil sub grade 2.3 Semi-Rigid Pavement: 1. At the point when fortified materials like pozzolanic concrete, lean cement or soil concrete are utilized, then the Pavement layer has impressively high flexural strength than the normal adaptable Pavement is known as a semi- inflexible Pavement. 2. These materials have low protection from effect and scraped spot and are in this manner utilized with adaptable Pavement surface course. Figure 3: Functions of Pavement 2.4 Functions Of Pavement Components 2.4.1 Soil Subgrade: 1. The Pavement load is at last taken by soil sub grade and thus for no situation it ought to be over focused and top 50cm layer of soil sub grade ought to be all around compacted at O.M.C. 2. Common strength tests used for evaluation of soil sub grade are: a. California Bearing Ratio test b. California resistance value test c. Tri-axial compression test d. Plate bearing test 2.4.2 Sub base and Base Courses: These are broken stone totals. It is alluring to utilize more modest size evaluated totals at sub base course rather than rock stones. Base and sub base courses are utilized under adaptable Pavements principally to further develop load supporting limit by dissemination of burden through a limited thickness. Base courses are used under rigid pavements for : a.Preventing pumping b. Protecting the sub grade 2.4.3 Wearing Course: Purpose behind this course is to give smooth riding surface. It opposes pressure applied by tires and takes up mileage because of traffic. It additionally offers water snugness. The dependability of wearing course is assessed by Marshaling solidness test where in ideal percent of bituminous material is worked out in light of steadiness thickness, voids in mineral total (V M A) and voids loaded up with bitumen (V F B). Plate Bearing test are likewise in some cases made use for hoisting the wearing course and the Pavement in general.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 09 | Sep 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 297 2.5 Factors to be considered in the design of pavements Pavement configuration comprises of two sections: 1. Mix plan of material to be utilized in every Pavement part layer 2. Thickness plan of the Pavement and the part layer The different variables to be considered for the plan of Pavement are: 1. Design wheel load 2. Sub grade soil 3. Climatic factors 4. Pavement component material 5. Environmental factors 2.5.1 Traffic & Loads acting on pavement Traffic and Loads following up on Pavement are thought about while planning an Pavement. Loads cause stresses, distortions, and removals in structures Analysis of their belongings is done by the strategies for primary examination. Over-burdening might cause primary disappointment, and consequently underlying disappointment ought to be either viewed as in the plan or stringently controlled. The various sorts of burdens following up on streets are as per the following: 1. Contact pressure. 2. Repetition of loads. 3. Wheel load. 4. Axle configuration. 2.5.2 Contact Pressure: The tire pressure is a significant element, as it decides the contact region of the wheel to the Pavement surface. Despite the fact that the state of the contact region is curved, a round region is frequently considered for purpose of effortlessness in examination. 2.5.3 Repetition of Loads: The impact of traffic on Pavement, not just rely upon the size of the wheel load, yet additionally on the recurrence of the heap application. Each heap application cause a few distortion and the complete twisting is the summation of every one of these. Consequently, present day plan depends on all out number of standard axles. 2.5.4 Wheel load: The following significant variable is the wheel load it decides the profundity of the Pavement expected to guarantee that the sub grade soil isn't fizzled. The pressure dissemination and diversion inside an Pavement are affected by wheel design. 2.5.5 Axle configuration: The Standard Axle thought about is Single Axle with Dual wheel 80 KN, where Single wheel load is 20 KN. 3. LITERATURE REVIEW Adaptable Pavements are liked over concrete substantial streets as they enjoy an extraordinary benefit that these can be reinforced and worked on in stages with the development of traffic and furthermore their surfaces can be processed and reused for restoration. The adaptable Pavements are more affordable additionally concerning introductory venture and upkeep. Albeit Rigid Pavement is costly yet have less upkeep and having great plan period. The monetary part is completed for the plan Pavement of a segment by utilizing the outcomes got by plan strategy and their relating part layer thickness. Saurabh Jain, Dr. Y. P. Joshi, S. S. Goliya: This paper talks about the plan techniques that are generally being followed and inspects the "Plan of inflexible and adaptable Pavements by different strategies and their expense investigation by every strategy" D. S. V. Prasad and G. V. R. Prasada Raju : This paper examines the exhibition of adaptable Pavement on far reaching soil sub grade utilizing rock/fly debris as sub base course with squander tire elastic as a building up material. It was seen that from the research center test aftereffects of direct shear and CBR, the rock sub base shows better execution when contrasted with fly debris sub base with various rates of waste tire elastic as supporting material. Cyclic burden tests are likewise completed in the research center by putting a roundabout metal plate on the model adaptable Pavements. It was seen that the greatest burden conveying limit related with less worth of bounce back avoidance got for rock supported sub base contrasted with fly debris built up sub base. 4. METHODOLOGY The three soil tests are utilized in the review. For these Soil samples1,2,3 are the Index and Engineering properties are resolved are organized in the Table.1.The soil protuberances were broken into pieces and sieved through 4.75mm sifter and afterward dried in broiler at 1050c for 24 hours. The dirt are named I.S Classification system(IS 1498-1970).
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 09 | Sep 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 298 Description Sample 1 Sample2 Sample3 D10 0.18 0.075 0.09 D30 0.4 0.22 0.26 D60 0.65 0.89 0.9 Uniform Coefficient(CU) 3.61 11.86 10 Coefficient of Curvature(CC) 1.367 0.725 0.834 Liquid limit 38.5 26.5 25.5 Plastic limit 22.2 21.05 19.32 Plasticity index 16.3 5.45 6.18 Free swell index 80 80 72 Specific gravity 2.2 2.2 2 Maximum Dry Density (g/cc) 1.678 1.91 2.05 Optimum Moisture Content (%) 10.63 8.1 11.5 Table 1: Properties of Soil 4.1 Experimental Programme & Discussion 4.1.1 Collection of Samples: Three samples of soils had been collected in the location ofthe Paratwada site (work). 4.1.2 Types of Soil Test: The different types of tests conducted on the samples are; 1. Index properties 2. Specific gravity 3. Compaction characteristics 4. California bearing ratio Type of material Suggested CBR value(%) Gravel 25 Road metal 55 Table 2: CBR values of Sample A, Sample B, Sample C (Soaking) Graph 1: CBR values of Sample A, Sample B,Sample C (Soaking) 4.2 Design of Pavement Thickness by CBR Method: 1. The soil tests are taken and their ideal dampness still up in the air by Proctor's thickness test for light compaction. 2. The soil test is then compacted in CBR shape for ideal thickness and the form is drenched for 3 days. 3. The CBR test is then performed to get the CBR values for the dirt sub grade Figure 4: CBR Design chart Sample 1: CBR corresponding to 2.5mm penetration =(74.4/1370) × 100 = 5.4% Assume, Average Daily Traffic (ADT) = 300Annual rate of growth of traffic (r) = 8% Time taken for pavement construction (n) = 1 yearNo. of vehicles for design (A) = P (1 + r )(n +10) 325 300 275 250 225 200 175 150 125 Sample 1 Sample 2 Sample 3 0 1 2 3 4 5 6 7 8 9 10 11 Penetration in (mm)
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 09 | Sep 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 299 = 300(1 +8/ 100 )(1 + 10) = 699.49 vehicles/day = 700 vehicles/day  Thus 40cm of pavement materials is required to cover thenatural soil subgrade having 5.4% CBR value. Therefore, the thickness of base and sub base courses are12.5cm and 22cm having CBR value 55% and 25% usingthe design chart.  The CBR values for the gravel and road metal are assumedas follows Description Sample1 Sample2 Sample3 CBR value of 2.5mm 14.36% 13.59% 14.756% CBR value of 5.0mm 11.13% 12.426% 11.12% Table 3: The Suggested CBR Values of Sample 1 for Type of material Sample 2: CBR corresponding to 5 mm penetration = 4.91% Assume, Average Daily Traffic (ADT) = 300 Annual rate of growth of traffic (r) = 8% Time taken for pavement construction (n) = 1 year No. ofvehicles for design (A) = P (1 + r )(n + 10) = 300(1 +8/100) (1 + 10) = 699.49 vehicles/day = 700 vehicles/day  Thus 45cm of pavement materials is required to cover thenatural soil sub grade having 4.9% CBR value.  Therefore, the thickness of base and sub base courses are 13cm and 25cm having CBR value 50% and 25% using the design chart. The CBR values for the gravel and road metal are assumedas follows: Type of material Suggested CBR value(%) Gravel 25 Road metal 50 Sample 3: CBR corresponding to 2.5mm penetration =(77.8/1370) ×100 = 5.8% Assume, Average Daily Traffic (ADT) = 300 Annual rate of growth of traffic (r) = 8% Time taken for pavement construction (n) = 1 yearNo. of vehicles for design (A) = P (1 + r )(n + 10) = 300(1 +8/100 )(1 + 10) = 699.49 vehicles/day = 700 vehicles/day  Thus 38cm of pavement materials is required to cover thenatural soil subgrade having 5.8% CBR value.  Therefore, the thickness of base and sub base courses are 11cm and 22cm having CBR value 47% and 25% using thedesign chart. The CBR values for the gravel and road metal are assumedas follows: Type of material Suggested CBR value (%) Gravel 25 Road metal 47 Table 5: The Suggested CBR Values of Sample 3for Type of material 5. CONCLUSION In this task work, an endeavor is made to consolidate most recent methods of mathematical plan, Pavement plan for a street for a current state which 2 km away from Paratwada. • The IRC details depend on levelheaded reasoning, the proposed street is protected in both geometrics as well as Pavement plan. It is likewise proposed to plan an adaptable Pavement by Group Index technique and CBR strategy. • A few additional techniques are accessible in the plan of adaptable Pavement, which are greatly exceptional like California opposing worth strategy, Mc leod technique, Tri-pivotal strategy and Burnister strategy. In light of the limits of time and degree, just GI technique and CBR strategy are embraced. Table 4: The Suggested CBR Values of Sample 2 for Type of material
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 09 | Sep 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 300 6. REFERENCES [1] “Highway Engineering” by S.K.Khanna and C.E.G.Justo [2] “ Highway Engineering” by T.D.Ahuja [3] “Estimation and costing in civil engineering” by B.N.Dutta [4] “Soil mechanics and foundation engineering” by K.R.Arora [5] “Surveying” by K.R.Arora [6] “Surveying” by B.C.Punmia [7] “IRC 37-2001”: Guidelines for the design of flexible pavements.