SlideShare a Scribd company logo
1 of 48
Demolition of
Structures.
1
By: Chintan Varia
Pratik Sureja
Akshay Kasundra
Why DEMOLITION is DANGEROUS?
 Demolition work is one if the most dangerous operations in
construction.
 REASONS/CAUSES:
1. Easy to cause injury to human workers due to the difficulty of
accessing into or working inside a building which is under
construction.
2. Falling of smaller objects or debris from the demolishing
building.
3. Falling of Partially demolished structure.
4. Collapse of unstable structure due to original structure being
disturbed.
2
Why DEMOLITION is DANGEROUS?
5. Collapse of heavy demolition equipment due to inadequate
support of the partially demolished structure.
6. Collapse of the partially demolished structure due to the
accommodation of large amount of un-cleared debris.
7. Congested site environment that easily cause damage to
human workers, or to the third parties and their properties
that are situated nearby the demolition site.
3
DEMOLITION PLAN
 Forming part of the submission information, the DEMOLITION Plan should
include:
a) A set of drawings showing:
the location of the building to be demolished other
existing structures and facilities in vicinity.
b) Proposed method of DEMOLITION.
c) Proposed shoring and precautionary measures for the adjacent
buildings.
d) Proposed shoring and protection for the building to be demolished
4
DEMOLITION PLAN
e) Proposed methods of handling and disposing of the demolished
materials.
f) Proposed sequence of carrying out work.
g) Detail of equipment used, with methods of raising, lowering or
supporting the equipment.
h) Structural calculation to justify the proposal.
i) Proposed arrangements for site supervision.
5
6
Catch Fan
Typical dust screen and fans
provision to protect building
and minimize disturbance to
public during demolition
7
Provision of Hoarding as a
protection to public
8
Shaft for falling
of debris
Common ways to get rid of the
demolished debris – to control
the falling of the debris into a
pre-determined vertical shaft
formed on the floor slabs
9
Debris shaft formed by opening
temporarily cut on floor slab
Debris collection area at ground
floor under the debris shaft
10
Temporary props erected to
support heavy equipment
11
Erection of shoring to support
affected structure
a) Basement demolition (left)
b) A nearby retaining wall (right)
12
Typical sectioning/
sequencing arrangement of
work during demolition –
demolish from exterior
inward
13
Typical sectioning/
sequencing arrangement of
work during demolition –
demolish from one side to
the other side of building
14
Typical layout
arrangement in small and
medium sized building
under demolition
15
Typical layout
arrangement in
small and medium
sized building
under demolition
METHODS OF DEMOLITION
 GENERAL CONCERNS:
The choice of choosing a demolition method depends on a
number of factors such as the project conditions, site constraints, sensitivity
of the neighborhood and availability of equipment etc.
In general, top down methods are applicable for most sites,
particularly for those situated in busy urban areas. Other mechanical
methods applied from the outside of a building lines, demotion by hand held
tools or the cut and lift process may be a safe solution.
For structural projections such as balconies, canopies and
verandahs extending beyond the building lines, demolition by hand held
tools or the cut and lift process may be a safe solution.
16
METHODS OF DEMOLITION
 There are various methods of DEMOLITION of structures.
1. Demolition by human operatives.
2. Deliberate Collapse method.
3. Using of applied pulling / pushing forces.
4. Using of wrecking ball.
5. Use of powered plant or demolition machine.
6. Using saw cut method.
7. By Implosion (explosive).
17
DEMOLITION BY HUMAN OPERATIVES
 This method particularly suitable for use in smaller site
with congested space where larger machine cannot be
employed.
 In this case, human operatives are used in the demolition
process using simple electrically or pneumatically
powered tools such as picks, hammers, wire cutters or
hand driven hydraulic jacks etc. to carry out the
demolition of individual elements.
18
19
Typical demolition
arrangement done by
human operatives
20
Typical demolition
arrangement done by
human operatives
Slab with the sides
disconnected ready
for dismantle
21
Typical demolition
arrangement done by
human operatives
Worker breaking
down larger piece of
structure which was
demolished by
pulling/pushing
method.
22
A number of
works where
human
operative is
unavoidable
23
Working condition
and behavior of
human operatives
Back to Methods
of
DEMOLITION
DELIBERATE COLLAPSE METHOD
 DEMOLITION by deliberate collapse consists of systematic removal, or
weakening of the key structural elements to induce the collapse of the
structure.
 However, when applying this method, several precautions should be
observed, such as:
1. Sufficient distance of collapse should be provided.
2. Collapse procedure should be carefully designed so that there is no
pre-mature collapse or collapse out of anticipated area.
3. Control height of building structure to be collapsed.
24
Back to Methods
of
DEMOLITION
USING OF APPLIED PULLING / PUSHING
FORCES
 Connecting structural members are disconnected first allowing part of the
remaining structure to be dragged down by the use of some
pulling/pushing equipment such as powered jack, winching machine,
pulley systems, pushing arms, powered blocks or from the pull/push of a
hydraulic excavator.
 However, a firm base in the demolishing building is required such as
basing on an undisturbed core wall or a strong column section for the
applying of pulling/pushing forces.
25
USING OF APPLIED PULLING / PUSHING
FORCES
26
27Disconnected
external wall ready
to be pulled down
by an applied force
Remain fragments from
pulled-down structure to
be removed afterward
Demolition done by
applying a pulling force to
a portion of structure
Back to Methods
of
DEMOLITION
USING OF WRECKING BALL
 The use of wrecking ball method requires a crane equipped with a steel
ball.
 The DESTRUCTION of the building is caused by the impact energy of the
steel ball suspended from a crawler crane.
 The wrecking ball can be operated outside or inside a building.
 In case the process is operated inside a building, sufficient clearance from
the building interior should be made first .
 This also demands experienced operators in order to handle the wrecking
ball and control the DEMOLITION.
28
29
Swing action of
wrecking ball
Vertical drop of
wrecking ball
Back to Methods
of
DEMOLITION
USE OF POWERED PLANT OR DEMOLITION
MACHINE
 The principle of demolition by machine is typically the same as the top-
down manual method, except that most of the demolition begins with the
lifting of the mechanical plant on to the building top floor.
 Powered plant such as crawler mounted breaking hammer are used in the
demolition process and excavating machines with bucket are used in the
removal or handling of the demolished materials.
 However, due to the weight of these machines, they should be properly
supported such as by the use of steel props no matter in still or in
operating condition.
30
31
Demolition by the help of
mechanical plant – pneumatic
breaker and bucketed
excavator
32
Close-up view of the
pneumatic breaking machine
33
Lifting the
mechanical
equipment to top
of building
Demolition using top-down method using machines
Building before demolition
34
Moving down of the breaking
machine to the lower floor
Demolition using top-down
method using machines –
typical floor cycle and
machine movement
35Some more examples of mechanical means to demolish
36
Back to Methods
of
DEMOLITION
USING SAW CUT METHOD
 This method is suitable for alternation and additional works where
accuracy is important and restriction on noise and vibration is required.
 It can be used to cut concrete slab and wall elements into segments or for
the forming of openings, breaking into existing structure like a basement,
servicing tunnel, flyover, or the other part of an inhabited building in the
process of alteration or renovation works.
 Saw Cutting can be done using the following methods:
1. Wire Saw Cutting
2. Diamond Core Stitch Drilling
3. Disc Saw
37
WIRE SAW CUTTING
38
WIRE SAW CUTTING
39
DIAMOND CORE STITCHING DRILLING
40
DIAMOND CORE STITCHING DRILLING
41
USING DISC SAW
42Set-upandmountingofthe
sawdisonwall
Demolition using disc saw cutting
43
Using core and drill method to
demolish a pedestrian subway
Back to Methods
of
DEMOLITION
USING IMPLOSION (EXPLOSION)
 If using this method to demolish a building, contractor should carry out a
comprehensive risk and environmental assessment on the effect of
implosion on the neighborhood.
 A detail demolition design is also important, which should cover:
1. Method to pre-weaken the structure (e.g. demolish some load
taking structures)
2. Placement of explosive
3. Time-delay design to allow the building to collapse under control
director and location
44
USING IMPLOSION (EXPLOSION)
 Charges of explosive are placed within the fabric of structure and
detonated to cause partial or complete collapse. Competent explosive
specialist is required when demolition is to be done by using explosive.
 There are numerous types of explosives for use for various types of
demolition (sometimes including non-explosive agent). Consideration
such as the spacing and depth of explosive to be located, the amount of
explosive to be used, or the degree of fragmentation required in order to
control the boundary of demolition etc., are required throughout the
planning and operation process.
45
USING IMPLOSION (EXPLOSION)
46
DEMOLITION BY ONE LEVEL AT A TIME
47
48

More Related Content

What's hot

DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKKHUSHBU SHAH
 
Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 
Demolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codeDemolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codejaimin1702
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction Mereia Kali
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of buildingAglaia Connect
 
Techniques for Demolition of Structure
Techniques for Demolition of StructureTechniques for Demolition of Structure
Techniques for Demolition of StructureDinaker Dixit
 
Demolition of a building
Demolition of a buildingDemolition of a building
Demolition of a buildingAbhishekKadve
 
Safety in construction
Safety in constructionSafety in construction
Safety in constructionJitesh Dhule
 
Formwork failures and remedial measures
Formwork failures and remedial measuresFormwork failures and remedial measures
Formwork failures and remedial measuressabnisajit
 
DEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUESDEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUESNirant Patel
 
Construction Machines and Plants
Construction Machines and PlantsConstruction Machines and Plants
Construction Machines and PlantsXubitech
 
Maintenance and repair of buildings.
Maintenance and repair of buildings.Maintenance and repair of buildings.
Maintenance and repair of buildings.Satyaki Sikdar
 
Slipform construction
Slipform constructionSlipform construction
Slipform constructiontivar rose
 
Safety precautions during demolition
Safety precautions during demolitionSafety precautions during demolition
Safety precautions during demolitionManthan Vaghasiya
 
Demolition work of existing building
Demolition work of existing buildingDemolition work of existing building
Demolition work of existing buildingKishor Ade
 

What's hot (20)

DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORK
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Ila's ppt on demolition
Ila's ppt on demolitionIla's ppt on demolition
Ila's ppt on demolition
 
Demolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS codeDemolition of building and its precautionary measures as per IS code
Demolition of building and its precautionary measures as per IS code
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of building
 
Demolition of building
Demolition of building Demolition of building
Demolition of building
 
Techniques for Demolition of Structure
Techniques for Demolition of StructureTechniques for Demolition of Structure
Techniques for Demolition of Structure
 
Demolition pptx
Demolition pptxDemolition pptx
Demolition pptx
 
Demolition of a building
Demolition of a buildingDemolition of a building
Demolition of a building
 
Safety in construction
Safety in constructionSafety in construction
Safety in construction
 
Formwork failures and remedial measures
Formwork failures and remedial measuresFormwork failures and remedial measures
Formwork failures and remedial measures
 
DEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUESDEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUES
 
Construction Machines and Plants
Construction Machines and PlantsConstruction Machines and Plants
Construction Machines and Plants
 
SCAFFOLDING
SCAFFOLDINGSCAFFOLDING
SCAFFOLDING
 
Maintenance and repair of buildings.
Maintenance and repair of buildings.Maintenance and repair of buildings.
Maintenance and repair of buildings.
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Safety precautions during demolition
Safety precautions during demolitionSafety precautions during demolition
Safety precautions during demolition
 
Demolition work of existing building
Demolition work of existing buildingDemolition work of existing building
Demolition work of existing building
 

Viewers also liked

DEMOLITION OF STRUCTURE BY ABHINAV RAWAT
DEMOLITION OF STRUCTURE BY ABHINAV RAWATDEMOLITION OF STRUCTURE BY ABHINAV RAWAT
DEMOLITION OF STRUCTURE BY ABHINAV RAWATAbhinav Rawat
 
Demolition Equipment/Technique Available
Demolition Equipment/Technique Available Demolition Equipment/Technique Available
Demolition Equipment/Technique Available Girish Singh
 
Repairs and rehabilitation 2012
Repairs and rehabilitation 2012Repairs and rehabilitation 2012
Repairs and rehabilitation 2012Dhaval Jadhav
 
Chapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingChapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingAnkit Patel
 
Application of construction demolition waste.
Application of construction demolition waste.Application of construction demolition waste.
Application of construction demolition waste.SJMIT,now NMAMIT NITTE
 
Construction and demolition waste
Construction and demolition wasteConstruction and demolition waste
Construction and demolition waste12cl0viren
 
C & d waste management in india
C & d waste management in indiaC & d waste management in india
C & d waste management in indiaRavi Kumar
 
C and d waste ppt
C and d waste pptC and d waste ppt
C and d waste pptkybabita
 
Ms. Rana Al Hishmi - Construction & Demolition Waste Recycling
Ms. Rana Al Hishmi - Construction & Demolition Waste RecyclingMs. Rana Al Hishmi - Construction & Demolition Waste Recycling
Ms. Rana Al Hishmi - Construction & Demolition Waste RecyclingHudhaib Al-Allatti
 
Construction and Demolition Waste Recycling
Construction and Demolition Waste RecyclingConstruction and Demolition Waste Recycling
Construction and Demolition Waste RecyclingTom Ahern
 
reuse and recycle of construction material
reuse and recycle of construction materialreuse and recycle of construction material
reuse and recycle of construction materialRakesh Rahar
 
OSHA demolition
OSHA demolitionOSHA demolition
OSHA demolitionHni Amiera
 

Viewers also liked (20)

DEMOLITION OF STRUCTURE BY ABHINAV RAWAT
DEMOLITION OF STRUCTURE BY ABHINAV RAWATDEMOLITION OF STRUCTURE BY ABHINAV RAWAT
DEMOLITION OF STRUCTURE BY ABHINAV RAWAT
 
Demolition
 Demolition Demolition
Demolition
 
Demolition Equipment/Technique Available
Demolition Equipment/Technique Available Demolition Equipment/Technique Available
Demolition Equipment/Technique Available
 
Fully Demolition
Fully Demolition Fully Demolition
Fully Demolition
 
Presentation-Demolition-Yıkım
Presentation-Demolition-YıkımPresentation-Demolition-Yıkım
Presentation-Demolition-Yıkım
 
Repairs and rehabilitation 2012
Repairs and rehabilitation 2012Repairs and rehabilitation 2012
Repairs and rehabilitation 2012
 
Chapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiitingChapter 4 repair, rehabilitation & retrofiiting
Chapter 4 repair, rehabilitation & retrofiiting
 
Application of construction demolition waste.
Application of construction demolition waste.Application of construction demolition waste.
Application of construction demolition waste.
 
Construction and demolition waste
Construction and demolition wasteConstruction and demolition waste
Construction and demolition waste
 
C & d waste management in india
C & d waste management in indiaC & d waste management in india
C & d waste management in india
 
C and d waste ppt
C and d waste pptC and d waste ppt
C and d waste ppt
 
Bs bab 4
Bs bab 4Bs bab 4
Bs bab 4
 
Ms. Rana Al Hishmi - Construction & Demolition Waste Recycling
Ms. Rana Al Hishmi - Construction & Demolition Waste RecyclingMs. Rana Al Hishmi - Construction & Demolition Waste Recycling
Ms. Rana Al Hishmi - Construction & Demolition Waste Recycling
 
Construction and Demolition Waste Recycling
Construction and Demolition Waste RecyclingConstruction and Demolition Waste Recycling
Construction and Demolition Waste Recycling
 
reuse of c&d waste
reuse  of c&d wastereuse  of c&d waste
reuse of c&d waste
 
reuse and recycle of construction material
reuse and recycle of construction materialreuse and recycle of construction material
reuse and recycle of construction material
 
Cracks in Buildings
Cracks in BuildingsCracks in Buildings
Cracks in Buildings
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
 
OSHA demolition
OSHA demolitionOSHA demolition
OSHA demolition
 
Demolition, Civil Engineering and Hard Landscape Construction Work
Demolition, Civil Engineering and Hard Landscape Construction WorkDemolition, Civil Engineering and Hard Landscape Construction Work
Demolition, Civil Engineering and Hard Landscape Construction Work
 

Similar to Demolition of Structures.

Study of Safety in Demolition of Buildings
Study of Safety in Demolition of BuildingsStudy of Safety in Demolition of Buildings
Study of Safety in Demolition of BuildingsIRJET Journal
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of buildingAnimesh1714013
 
Demolition Techniques.pptx
Demolition Techniques.pptxDemolition Techniques.pptx
Demolition Techniques.pptxAnanthakumar75
 
Building Service Chapter 4
Building Service Chapter 4Building Service Chapter 4
Building Service Chapter 4Izam Lukman
 
Demolishing of concrete structures
Demolishing of concrete structuresDemolishing of concrete structures
Demolishing of concrete structuresTsegaye Arega
 
Rehabilitation of structures,Method of Demolition of Structures
Rehabilitation of  structures,Method of Demolition of  StructuresRehabilitation of  structures,Method of Demolition of  Structures
Rehabilitation of structures,Method of Demolition of StructuresPRAJWAL SHRIRAO
 
Demolishing of concrete structures
Demolishing of concrete structuresDemolishing of concrete structures
Demolishing of concrete structuresTsegaye Arega
 
Demolition of building and blasting equipment
Demolition of building and blasting equipmentDemolition of building and blasting equipment
Demolition of building and blasting equipmentChetan Karwa
 
Building Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing ConstructionBuilding Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing Constructionjisunfoo
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction ReportSheau Hui Tan
 

Similar to Demolition of Structures. (20)

Study of Safety in Demolition of Buildings
Study of Safety in Demolition of BuildingsStudy of Safety in Demolition of Buildings
Study of Safety in Demolition of Buildings
 
Demolition.pptx
Demolition.pptxDemolition.pptx
Demolition.pptx
 
BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)
 
Techniques behind demolition of structures
Techniques behind demolition of structuresTechniques behind demolition of structures
Techniques behind demolition of structures
 
BCT Mod 4 demolition of structure
BCT Mod 4 demolition of structureBCT Mod 4 demolition of structure
BCT Mod 4 demolition of structure
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of building
 
Demolition Techniques.pptx
Demolition Techniques.pptxDemolition Techniques.pptx
Demolition Techniques.pptx
 
Demolition of Structure ppt.pptx
Demolition of Structure ppt.pptxDemolition of Structure ppt.pptx
Demolition of Structure ppt.pptx
 
Building Service Chapter 4
Building Service Chapter 4Building Service Chapter 4
Building Service Chapter 4
 
Demolishing of concrete structures
Demolishing of concrete structuresDemolishing of concrete structures
Demolishing of concrete structures
 
Rehabilitation of structures,Method of Demolition of Structures
Rehabilitation of  structures,Method of Demolition of  StructuresRehabilitation of  structures,Method of Demolition of  Structures
Rehabilitation of structures,Method of Demolition of Structures
 
Demolishing of concrete structures
Demolishing of concrete structuresDemolishing of concrete structures
Demolishing of concrete structures
 
Syed Naireen.
Syed Naireen.Syed Naireen.
Syed Naireen.
 
Demolition of BUILDING.pptx
Demolition of BUILDING.pptxDemolition of BUILDING.pptx
Demolition of BUILDING.pptx
 
DOC pramod .pptx
DOC pramod .pptxDOC pramod .pptx
DOC pramod .pptx
 
DEMOLITION OF BUILDING 2.pptx
DEMOLITION OF BUILDING 2.pptxDEMOLITION OF BUILDING 2.pptx
DEMOLITION OF BUILDING 2.pptx
 
Demolition of building and blasting equipment
Demolition of building and blasting equipmentDemolition of building and blasting equipment
Demolition of building and blasting equipment
 
Building Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing ConstructionBuilding Construction 1 - Experiencing Construction
Building Construction 1 - Experiencing Construction
 
Building Construction Report
Building Construction ReportBuilding Construction Report
Building Construction Report
 
PPT DEMOLISH.pptx
PPT DEMOLISH.pptxPPT DEMOLISH.pptx
PPT DEMOLISH.pptx
 

Recently uploaded

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 

Recently uploaded (20)

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 

Demolition of Structures.

  • 1. Demolition of Structures. 1 By: Chintan Varia Pratik Sureja Akshay Kasundra
  • 2. Why DEMOLITION is DANGEROUS?  Demolition work is one if the most dangerous operations in construction.  REASONS/CAUSES: 1. Easy to cause injury to human workers due to the difficulty of accessing into or working inside a building which is under construction. 2. Falling of smaller objects or debris from the demolishing building. 3. Falling of Partially demolished structure. 4. Collapse of unstable structure due to original structure being disturbed. 2
  • 3. Why DEMOLITION is DANGEROUS? 5. Collapse of heavy demolition equipment due to inadequate support of the partially demolished structure. 6. Collapse of the partially demolished structure due to the accommodation of large amount of un-cleared debris. 7. Congested site environment that easily cause damage to human workers, or to the third parties and their properties that are situated nearby the demolition site. 3
  • 4. DEMOLITION PLAN  Forming part of the submission information, the DEMOLITION Plan should include: a) A set of drawings showing: the location of the building to be demolished other existing structures and facilities in vicinity. b) Proposed method of DEMOLITION. c) Proposed shoring and precautionary measures for the adjacent buildings. d) Proposed shoring and protection for the building to be demolished 4
  • 5. DEMOLITION PLAN e) Proposed methods of handling and disposing of the demolished materials. f) Proposed sequence of carrying out work. g) Detail of equipment used, with methods of raising, lowering or supporting the equipment. h) Structural calculation to justify the proposal. i) Proposed arrangements for site supervision. 5
  • 6. 6 Catch Fan Typical dust screen and fans provision to protect building and minimize disturbance to public during demolition
  • 7. 7 Provision of Hoarding as a protection to public
  • 8. 8 Shaft for falling of debris Common ways to get rid of the demolished debris – to control the falling of the debris into a pre-determined vertical shaft formed on the floor slabs
  • 9. 9 Debris shaft formed by opening temporarily cut on floor slab Debris collection area at ground floor under the debris shaft
  • 10. 10 Temporary props erected to support heavy equipment
  • 11. 11 Erection of shoring to support affected structure a) Basement demolition (left) b) A nearby retaining wall (right)
  • 12. 12 Typical sectioning/ sequencing arrangement of work during demolition – demolish from exterior inward
  • 13. 13 Typical sectioning/ sequencing arrangement of work during demolition – demolish from one side to the other side of building
  • 14. 14 Typical layout arrangement in small and medium sized building under demolition
  • 15. 15 Typical layout arrangement in small and medium sized building under demolition
  • 16. METHODS OF DEMOLITION  GENERAL CONCERNS: The choice of choosing a demolition method depends on a number of factors such as the project conditions, site constraints, sensitivity of the neighborhood and availability of equipment etc. In general, top down methods are applicable for most sites, particularly for those situated in busy urban areas. Other mechanical methods applied from the outside of a building lines, demotion by hand held tools or the cut and lift process may be a safe solution. For structural projections such as balconies, canopies and verandahs extending beyond the building lines, demolition by hand held tools or the cut and lift process may be a safe solution. 16
  • 17. METHODS OF DEMOLITION  There are various methods of DEMOLITION of structures. 1. Demolition by human operatives. 2. Deliberate Collapse method. 3. Using of applied pulling / pushing forces. 4. Using of wrecking ball. 5. Use of powered plant or demolition machine. 6. Using saw cut method. 7. By Implosion (explosive). 17
  • 18. DEMOLITION BY HUMAN OPERATIVES  This method particularly suitable for use in smaller site with congested space where larger machine cannot be employed.  In this case, human operatives are used in the demolition process using simple electrically or pneumatically powered tools such as picks, hammers, wire cutters or hand driven hydraulic jacks etc. to carry out the demolition of individual elements. 18
  • 20. 20 Typical demolition arrangement done by human operatives Slab with the sides disconnected ready for dismantle
  • 21. 21 Typical demolition arrangement done by human operatives Worker breaking down larger piece of structure which was demolished by pulling/pushing method.
  • 22. 22 A number of works where human operative is unavoidable
  • 23. 23 Working condition and behavior of human operatives Back to Methods of DEMOLITION
  • 24. DELIBERATE COLLAPSE METHOD  DEMOLITION by deliberate collapse consists of systematic removal, or weakening of the key structural elements to induce the collapse of the structure.  However, when applying this method, several precautions should be observed, such as: 1. Sufficient distance of collapse should be provided. 2. Collapse procedure should be carefully designed so that there is no pre-mature collapse or collapse out of anticipated area. 3. Control height of building structure to be collapsed. 24 Back to Methods of DEMOLITION
  • 25. USING OF APPLIED PULLING / PUSHING FORCES  Connecting structural members are disconnected first allowing part of the remaining structure to be dragged down by the use of some pulling/pushing equipment such as powered jack, winching machine, pulley systems, pushing arms, powered blocks or from the pull/push of a hydraulic excavator.  However, a firm base in the demolishing building is required such as basing on an undisturbed core wall or a strong column section for the applying of pulling/pushing forces. 25
  • 26. USING OF APPLIED PULLING / PUSHING FORCES 26
  • 27. 27Disconnected external wall ready to be pulled down by an applied force Remain fragments from pulled-down structure to be removed afterward Demolition done by applying a pulling force to a portion of structure Back to Methods of DEMOLITION
  • 28. USING OF WRECKING BALL  The use of wrecking ball method requires a crane equipped with a steel ball.  The DESTRUCTION of the building is caused by the impact energy of the steel ball suspended from a crawler crane.  The wrecking ball can be operated outside or inside a building.  In case the process is operated inside a building, sufficient clearance from the building interior should be made first .  This also demands experienced operators in order to handle the wrecking ball and control the DEMOLITION. 28
  • 29. 29 Swing action of wrecking ball Vertical drop of wrecking ball Back to Methods of DEMOLITION
  • 30. USE OF POWERED PLANT OR DEMOLITION MACHINE  The principle of demolition by machine is typically the same as the top- down manual method, except that most of the demolition begins with the lifting of the mechanical plant on to the building top floor.  Powered plant such as crawler mounted breaking hammer are used in the demolition process and excavating machines with bucket are used in the removal or handling of the demolished materials.  However, due to the weight of these machines, they should be properly supported such as by the use of steel props no matter in still or in operating condition. 30
  • 31. 31 Demolition by the help of mechanical plant – pneumatic breaker and bucketed excavator
  • 32. 32 Close-up view of the pneumatic breaking machine
  • 33. 33 Lifting the mechanical equipment to top of building Demolition using top-down method using machines Building before demolition
  • 34. 34 Moving down of the breaking machine to the lower floor Demolition using top-down method using machines – typical floor cycle and machine movement
  • 35. 35Some more examples of mechanical means to demolish
  • 37. USING SAW CUT METHOD  This method is suitable for alternation and additional works where accuracy is important and restriction on noise and vibration is required.  It can be used to cut concrete slab and wall elements into segments or for the forming of openings, breaking into existing structure like a basement, servicing tunnel, flyover, or the other part of an inhabited building in the process of alteration or renovation works.  Saw Cutting can be done using the following methods: 1. Wire Saw Cutting 2. Diamond Core Stitch Drilling 3. Disc Saw 37
  • 40. DIAMOND CORE STITCHING DRILLING 40
  • 41. DIAMOND CORE STITCHING DRILLING 41
  • 43. 43 Using core and drill method to demolish a pedestrian subway Back to Methods of DEMOLITION
  • 44. USING IMPLOSION (EXPLOSION)  If using this method to demolish a building, contractor should carry out a comprehensive risk and environmental assessment on the effect of implosion on the neighborhood.  A detail demolition design is also important, which should cover: 1. Method to pre-weaken the structure (e.g. demolish some load taking structures) 2. Placement of explosive 3. Time-delay design to allow the building to collapse under control director and location 44
  • 45. USING IMPLOSION (EXPLOSION)  Charges of explosive are placed within the fabric of structure and detonated to cause partial or complete collapse. Competent explosive specialist is required when demolition is to be done by using explosive.  There are numerous types of explosives for use for various types of demolition (sometimes including non-explosive agent). Consideration such as the spacing and depth of explosive to be located, the amount of explosive to be used, or the degree of fragmentation required in order to control the boundary of demolition etc., are required throughout the planning and operation process. 45
  • 47. DEMOLITION BY ONE LEVEL AT A TIME 47
  • 48. 48