This document provides an overview of demolition processes and methods. It discusses the history of demolition using explosives, the objectives of demolition projects, and the typical steps and safety measures involved in planning a demolition. It then describes various demolition methods including ball and crane, dismantling, pneumatic breakers, pressure bursting, and explosives. Explosive demolition, also called implosion, involves strategically placing explosives to bring down a structure in a controlled collapse. Proper planning including pre-weakening, test blasts, and explosive placement is needed to conduct an implosion safely and minimize environmental impacts.
We know every structure is designed for a life period.
The existence of the structure after the service life period is very dangerous to its occupants and surrounding buildings .
The building act usually contains provisions that enable local authorities to control demolition works for the protection of public safety and to ensure adjoining premises and the site are made good on completion of the demolition.
Demolition Methods and Process for Building Structures Surveying of Buildings for Demolition. Removal of Hazardous Materials. Preparation of Demolition Plan for Structures. Safety Measures during Demolition of Building Structures. 1. Non-Explosive Demolition Method. Explosive Demolition Method ...
demolition of buildings videos
small building demolition and removal
building demolition explosives
building demolition equipment
demolition of building with asbestos
methods of demolition of building
depreciation demolition of building
contract for demolition of building
interesting civil engineering topics
seminar topics pdf
civil engineering topics for presentation
civil seminar topics ppt
best seminar topics for civil engineering
seminar topics for mechanical engineers
civil engineering ppt
latest civil engineering seminar topics
steps to demolish a building
building demolition techniques
types of demolition method
how to demolish a building
method statement for demolition works
structure demolition
videos of buildings being demolished
demolition techniques
We know every structure is designed for a life period.
The existence of the structure after the service life period is very dangerous to its occupants and surrounding buildings .
The building act usually contains provisions that enable local authorities to control demolition works for the protection of public safety and to ensure adjoining premises and the site are made good on completion of the demolition.
Demolition Methods and Process for Building Structures Surveying of Buildings for Demolition. Removal of Hazardous Materials. Preparation of Demolition Plan for Structures. Safety Measures during Demolition of Building Structures. 1. Non-Explosive Demolition Method. Explosive Demolition Method ...
demolition of buildings videos
small building demolition and removal
building demolition explosives
building demolition equipment
demolition of building with asbestos
methods of demolition of building
depreciation demolition of building
contract for demolition of building
interesting civil engineering topics
seminar topics pdf
civil engineering topics for presentation
civil seminar topics ppt
best seminar topics for civil engineering
seminar topics for mechanical engineers
civil engineering ppt
latest civil engineering seminar topics
steps to demolish a building
building demolition techniques
types of demolition method
how to demolish a building
method statement for demolition works
structure demolition
videos of buildings being demolished
demolition techniques
DEMOLITION:-Demolition is the process of tearing down or falling down of a building after its life period with the help of some equipments or any other method. When explosives are used for this then the demolition process are called as an implosion. Every civil engineering structure is designed for a life period. After that the existence of a structure is very dangerous. So removal of such structures with proper safety measures has got great importance. There are different steps involved before and during the time of a demolition activity.
brief explanation about methods and safety measures in demolition of buildings
i hope this will help you know the demolition safety factors.
thank you
suggestions to:-
vamsiila@gmail.com +91 9581202355
It contains lots of images and videos which can easily explain the processes.
It contains 48 slides and crucial information for demolition of structures.
This presentation contains basic demolishing techniques of concrete structure both manual and mechanical methods supported with photographic illustration.
Description about demolition of building, what is demoltion and how it is different from deconstruction. What are the method of Demolition and how demolition is crried out in a site. Phase of Demoliton. Safety precaution during Demolition etc.
The presentation includes difference between repair, retrofitting and rehabilitation. methods of repairs, repair materials, various methods for retrofitting etc.
for the subject offered in GTU, BCT, ace, cm
module 4 demolition of the structure
for the 3rd sem & also for the 6th sem subject and for the master of construction management
DEMOLITION:-Demolition is the process of tearing down or falling down of a building after its life period with the help of some equipments or any other method. When explosives are used for this then the demolition process are called as an implosion. Every civil engineering structure is designed for a life period. After that the existence of a structure is very dangerous. So removal of such structures with proper safety measures has got great importance. There are different steps involved before and during the time of a demolition activity.
brief explanation about methods and safety measures in demolition of buildings
i hope this will help you know the demolition safety factors.
thank you
suggestions to:-
vamsiila@gmail.com +91 9581202355
It contains lots of images and videos which can easily explain the processes.
It contains 48 slides and crucial information for demolition of structures.
This presentation contains basic demolishing techniques of concrete structure both manual and mechanical methods supported with photographic illustration.
Description about demolition of building, what is demoltion and how it is different from deconstruction. What are the method of Demolition and how demolition is crried out in a site. Phase of Demoliton. Safety precaution during Demolition etc.
The presentation includes difference between repair, retrofitting and rehabilitation. methods of repairs, repair materials, various methods for retrofitting etc.
for the subject offered in GTU, BCT, ace, cm
module 4 demolition of the structure
for the 3rd sem & also for the 6th sem subject and for the master of construction management
for the subject offered in GTU, BCT, ace, cm
module 4 demolition of the structure
for the 3rd sem & also for the 6th sem subject and for the master of construction management
The structures which have already passed their design life need to be reconstructed, for safety and operational requirements.This presentation contains the basic demolishing techniques of concrete structures manual, mechanical and use of explosives along with illustrative photos.
Demolition (also known as razing, cartage, and wrecking) is the science and engineering in safely and efficiently tearing down of buildings and other artificial structures. Demolition contrasts with deconstruction, which involves taking a building apart while carefully preserving valuable elements for reuse purposes.
For small buildings, such as houses, that are only two or three stories high, demolition is a rather simple process. The building is pulled down either manually or mechanically using large hydraulic equipment: elevated work platforms, cranes, excavators or bulldozers. Larger buildings may require the use of a wrecking ball, a heavy weight on a cable that is swung by a crane into the side of the buildings. Wrecking balls are especially effective against masonry, but are less easily controlled and often less efficient than other methods. Newer methods may use rotational hydraulic shears and silenced rock-breakers attached to excavators to cut or break through wood, steel, and concrete. The use of shears is especially common when flame cutting would be dangerous.
Building services engineering, technical building services, architectural engineering, building engineering, or facilities and services planning engineering refers to the implementation of the engineering for the internal environment and environmental impact of a building.
Tall Structures
Usually structure or building having height more than 80m is considered as a tall structure.
Generally tall structure may be defined as one that because of its height it is affected by lateral.
Classification: 1. Multi storeyedresidential building.
2. Multi storeyedcommercial building.
3. Tall chimneys.
4. Transmission Towers
5. Cooling towers
Prestressed Concrete
•Prestressis defined as a method of applying pre-compression to control the stresses resulting due to external loads below the neutral axis of the beam tension developed due to external load which is more than the permissible limits of the plain concrete.
Demolition
•The action or process of destroying(demolishing)the building or other structures.
•In congested area, in particular, the quality of demolition technique becomes an essential element which determines the success of revitalization of city.
•In addition to efficiency in demolition, strategies must be adopted to avoid noise, vibration and dust which affect the surrounding environment and there must be efficient disposal of waste products
6th International Conference on Machine Learning & Applications (CMLA 2024)ClaraZara1
6th International Conference on Machine Learning & Applications (CMLA 2024) will provide an excellent international forum for sharing knowledge and results in theory, methodology and applications of on Machine Learning & Applications.
Immunizing Image Classifiers Against Localized Adversary Attacksgerogepatton
This paper addresses the vulnerability of deep learning models, particularly convolutional neural networks
(CNN)s, to adversarial attacks and presents a proactive training technique designed to counter them. We
introduce a novel volumization algorithm, which transforms 2D images into 3D volumetric representations.
When combined with 3D convolution and deep curriculum learning optimization (CLO), itsignificantly improves
the immunity of models against localized universal attacks by up to 40%. We evaluate our proposed approach
using contemporary CNN architectures and the modified Canadian Institute for Advanced Research (CIFAR-10
and CIFAR-100) and ImageNet Large Scale Visual Recognition Challenge (ILSVRC12) datasets, showcasing
accuracy improvements over previous techniques. The results indicate that the combination of the volumetric
input and curriculum learning holds significant promise for mitigating adversarial attacks without necessitating
adversary training.
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
Forklift Classes Overview by Intella PartsIntella Parts
Discover the different forklift classes and their specific applications. Learn how to choose the right forklift for your needs to ensure safety, efficiency, and compliance in your operations.
For more technical information, visit our website https://intellaparts.com
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
Terzaghi's soil bearing capacity theory, developed by Karl Terzaghi, is a fundamental principle in geotechnical engineering used to determine the bearing capacity of shallow foundations. This theory provides a method to calculate the ultimate bearing capacity of soil, which is the maximum load per unit area that the soil can support without undergoing shear failure. The Calculation HTML Code included.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
3. I. INTRODUCTION
Demolition is bringing down the building and other
structures safely.
The demolition of structure with the help of
explosives is called as implosion.
The main objective for demolition may be the age of
the structure.
Methods of demolition depends upon the type of
structure, height and surrounding structures.
5. II. HISTORY
Historians generally agree that the first true "explosive" was
black powder, which was developed around the 13th century.
The first recorded use of black powder for demolition purposes
appears to have occurred in the early 1600s, when quarries in
Hungary began using it for rock blasting.
Black powder was put to use in the tin mines of England, and
Switzerland adopted blasting technology for road construction.
Throughout the 1930s, structural explosive demolition was
overseen by engineers working directly for large dynamite
manufacturers.
6. III. OBJECTIVES
Prevention damaging the neighbourhood environment.
Repair of damaged structures.
Construction of other structure at that previously constructed
site.
Provides safety for the occupants in the building.
7. IV. STEPS BEFORE DEMOLITION
1. Surveying
2. Removal of hazardous
materials
3. Preparation of plan
4. Safety measures
8. 1. Surveying:
The building survey should cover following:
The construction materials.
The existing use and, if possible, the past uses of the building prior
to demolition.
Adjoining pedestrian and vehicular traffic conditions.
The sensitivity of neighbourhood with respect to noise, dust, vibration
and traffic impact.
Available site area to allow on-site sorting of building debris.
9. 2. Removal of hazardous
materials:
Asbestos Containing Material
In the case when asbestos
containing material are
discovered, specialist contractor
shall be employed to remove such
asbestos containing material. The
asbestos waste should be
handled, stored and disposed of
as chemical waste in accordance
with the Waste Disposal
Regulation.
Soil Contamination Material
In the case when possible soil
contamination material is present,
specialist shall be employed to
prepare soil contamination test
proposal and submit such
proposal to the Environmental
Protection Department for
comment.
Asbestos Material
Soil Contamination
10. 3. Preparation of plan:
A plan showing location of the building to be demolished, sections
of the slopes with ground level contours and detailed topography,
ground removal and backfilling, distances of adjacent structures
from the building to be demolished.
A layout plan of all floors of the building to be demolished, with
adequate sections.
A plan showing the procedure for the demolition of the building.
A plan showing the proposed shoring and temporary support to be
provided to the building to be demolished.
In the case when powered mechanical plants and equipment are
used, a plan showing the route of movement of powered
mechanical plants and equipment.
11.
12.
13. 4. Safety measures:
Training and Communication:
Demolition workers, including
plant or equipment operators,
shall go through proper job safety
training and be informed of the
potential hazards by attending
training sessions as well as on-
the-job training.
Equipment Maintenance:
All equipment shall be tested and
examined before use. They shall
be properly stored and
maintained. The equipment shall
be inspected daily and results of
the inspection shall be recorded
accordingly.
14. Electrical Safety
A properly connected power source from a local electric utility
supplier or a mobile electricity generator shall be utilized in
demolition sites.
Fire
All flammable goods shall be removed from site unless they are
necessary for the works involved. Any remaining flammable goods
shall be stored in proper storage facilities. All furniture, timber,
doors, etc. shall be removed before any welding work is performed.
Fire fighting appliances shall be provided and maintained in working
conditions.
16. V. DEMOLITION SEQUENCE
All cantilevered structures, verandas and features attached to
the external walls shall first be demolished prior to demolition
of main building.
When demolishing the roof structure, all lift machine rooms
and water tanks at high level shall be demolished in “top
down” sequence to the main roof level.
Floor beams shall be demolished in the order of cantilevered
beams, secondary beams and then main beams.
Columns and load bearing walls shall be demolished after
removal of beams on top.
If site conditions permit, the first floor slab directly above the
ground floor may be demolished by machine standing on
ground.
17. Demolition of the floor slabs shall begin at mid span and
work towards the supporting beams.
18. Floor beams shall be demolished in the order of cantilevered
beams, secondary beams and then main beams.
Wire and winch shall be used to secure the cross beam to other
structural members.
The concrete is first broken away at both ends near its column
supports to expose the reinforcement.
Reinforcement shall be then cut to partially drop the beam and
the brought down with wire.
19. Secure the column by wire and
winch to existing structure.
Pre-weakening at the bottom of
column:
1) Break away the concrete to
expose the reinforcing bars.
2) Cut the reinforcing bars at the
exterior half of the column.
Cutting shall be performed
immediately prior to pulling.
Pulling down the column in a
controlled motion.
20. VI. METHODS OF DEMOLITION:
A. Ball and crane
B. Dismantling
C. Pneumatic and hydraulic breaker
D. Pressure bursting
E. Explosives
21. A. Ball and crane
This is one of the oldest and
most commonly used methods
for building demolition. A crane
uses a wrecking ball, weighing
up to 6120 kg, which is either
dropped onto or swung into the
element to be demolished.
The ball is made
from forged steel, which means
the steel is not cast into a
mould in a molten state. It is
formed under very high
pressure while the steel is red
hot (soft but not molten) to
compress and to strengthen it.
Concrete members can be
broken into small pieces, but
secondary cutting of reinforcing
may be necessary.
Wrecking ball at rest
Swinging the wrecking ball
22.
23.
24. Advantages:
1) To demolish roofs and other horizontal spans.
2) The wrecking balls are still used when demolition may not
be possible due to local environmental issues or
asbestos/lead building content.
1) It demands a great deal of skill from the crane operator.
2) The height of a building that can be demolished is limited
by crane size and working room; however, buildings as high
as 20 stories have been demolished.
3) The breakup process can cause considerable dust,
vibration and noise which may be objectionable.
Advantages and Disadvantages of Ball and
Crane method:
Advantages
Disadvantages
25. B. Dismantling
Selective or complete demolition of
concrete structures is possible by
cutting elements and then
removing them with a crane.
The cutting process may be by
sawing, water jetting or thermal
lance.
Because the surface of the cut
concrete is smooth and relatively
regular, these methods have
particular application when the
objective is partial demolition, for
instance in the creation of
openings in walls and slabs.
Dismantling a beam
26. Cutting with a water jet
minimizes dust and eliminates
vibration and fire hazards. An
abrasive and water-catching
system is required to clean up
during the jetting process.
Hydro demolition uses a high
pressure supersonic water jet,
that penetrates the pores and
cracks of the concrete
and builds up an internal
pressure. When this pressure
exceeds the tensile strength of
the concrete, the concrete
breaks.
The water jet can be used not
only for cutting straight lines
but also contours, a useful
feature for cutting access
manholes.
Water Jet cutting
27. A thermal lance is created by packing a seamless mild steel
tube with low carbon rods and passing oxygen through the tube.
While this method eliminates vibration and dust problems, it
creates other hazards associated with smoke and fire danger.
Whether sawing, jetting or lancing is used to dismantle the
structure or its components, each element must be safely
lowered to the ground.
Thermal Lance Sawing method
28. 1) Dismantlement of building components, specifically for re-
use, recycling, and waste management.
2) Reducing disposal costs where waste collection, hauling or
disposal is supported by the tax base.
3) Building components that are dismantled will need to be stored
in a secure, dry location. This will protect them from water
damage and theft.
1) The amount of time and cost of labor are the main drawbacks.
2) Harvesting materials from a structure can take weeks, whereas
demolition may be completed in roughly a day.
3) Toxic waste such as asbestos sheets and lead paint have no
resale value so they are discarded.
Advantages and Disadvantages of Dismantling
method:
Advantages
Disadvantages
29. C. Pneumatic and hydraulic breaker
A common piece of equipment used for demolishing bridge
decks, foundations and pavements is a hydraulically or
pneumatically operated, boom-mounted breaker.
The advantages of a machine mounted breaker may include a
telescoping boom for easy reach and, remote control
operation and underwater demolition capabilities
Some of the smaller remote- controlled machines can be lifted
through window openings and used inside a building to
demolish floors and walls.
Productivity can vary greatly depending on hammer size, type
of concrete, amount of reinforcing and working conditions.
30. Pneumatic hammer
A jackhammer is
a pneumatic or electro-
mechanical tool that combines
a hammer directly with
a chisel.
Hand-held jackhammers are
typically powered
by compressed air, but some
use electric motors.
Electric powered tools come
in a variety of sizes from about
12 lbs - 65 lbs.
They require an external
power source, but do not
require a compressor.
31. Hydraulic breaker
A hydraulic jackhammer, typically much larger than portable ones, may be
fitted to mechanical excavators or backhoes and is widely used for
roadwork, quarrying and general demolition or construction groundwork.
They are used
in mines where there is an
explosion risk since they lack
any high-power electrical
circuitry that might cause a
triggering spark.
The jackhammer is
connected with hydraulic
hoses to a portable hydraulic
power pack: either a petrol or
diesel engine driving a
hydraulic pump
32. 1) The hydraulic breakers have tremendous power output
also means they are the most power efficient, getting the
most work out of the available energy.
2) A properly used and maintained hydraulic machine can last
for a long time.
3) Pneumatic breakers are simpler tools with fewer moving
parts, requiring less maintenance.
1) They require power, fuel or battery for their work.
2) They tend to be the most expensive types.
3) They require an external power source.
Advantages and Disadvantages of Pressure
Bursting method:
Advantages
Disadvantages
33. D. Pressure bursting
Pressure bursting can be used in
cases where relatively quiet, dust-
free, controlled demolition is
preferred.
Both mechanical and chemical
pressure bursting split the concrete,
either with a splitting machine
operating on hydraulic pressure
provided by a motor in the case of
mechanical bursting, or through the
insertion of an expansive slurry into
a pre-determined pattern of
boreholes in the case of chemical
bursting.
The split concrete is then easily
removed, either by hand or by crane.
Both methods work by applying
lateral forces against the inside of
holes drilled into the concrete.
Pressure bursting
34. E. Explosives
Introduction
In the controlled
demolition industry, building
implosion is the strategic placing
of explosive material and timing of its
detonation so that a structure collapses
on itself in a matter of seconds,
minimizing the physical damage to its
immediate surroundings.
Despite its terminology, building
implosion also includes the controlled
demolition of other structures, such
as bridges, smokestacks, towers,
and tunnels.
Numerous small explosives,
strategically placed within the structure,
are used to catalyze the collapse. Nitro-
glycerine, dynamite, or other explosives
are used to shatter reinforced concrete
supports.
RDX-based explosive
compounds expand at a very
high rate of
speed, up to 27,000 feet per
second (8,230 meters per
second)
36. Blasting methods employ rapidly
expanding gases confined within
a series of boreholes to produce
controlled fractures which provide
for easy concrete removal.
For the demolition of concrete
structures it is usual to drill holes
at a predetermined angle into the
concrete to be removed.
Implosion is the strategic placing
of explosive material and timing
of its detonation so that a
structure collapses on itself in a
matter of seconds, minimizing the
physical damage to its immediate
surroundings.
The technique weakens or
removes critical supports so that
the building can no longer
withstand the force of gravity and
falls under its own weight.
Strategic implosion
37. Pre-blast Considerations
The design may include pre-weakening of the structure, the
strategy in placement of the explosives and time delay so that
the building will collapse in a safe manner.
Pre-weakening of the structure may include cutting out a
portion of the shear walls and other structural elements.
A test blast may be conducted to verify the strength of the
structural member and to fine tune the explosive design.
Protection of the adjacent properties and habitats is also an
important consideration.
38. Pre-weakening of the structure may include cutting out a
portion of the shear walls and other structural elements.
A test blast may be conducted to verify the strength of the
structural member and to fine tune the explosive design.
Protection of the adjacent properties and habitats is also an
important consideration.
41. Test Blast:
Before carrying out the actual blasting, a test blast, in ordered
to ascertain the efficiency of explosive & detonators.
42. Wrapping of holes:
The wrapping of holes is done to ensure that due to explosion
of charges the debris does not fly in air. For this purpose, the
holes were covered with gunny bags and iron net after
placement of explosive and detonators.
43. Ballasting:
Ballasting of Charges / Explosives work are carried out in a
controlled manner such that there will be a time gap of 1/100
second between two successive blasts. The trigger of charges
is done in such a control manner so that the noise pollution
and air pollution should be minimum.
Falling of structure:
Once central support/column will be destroyed and adjoining
columns will be weakened, due to its gravity the entire mass
will come down on its footprints
44. CONCLUSION
It can be concluded that demolishing/imploding the
building structure will prove very useful, economical
and quickest for reconstruction.
Leads to a safe and controlled demolition for the
occupants and neighbourhood.
Development in techniques allows rapid demolition
with no harm to the environment.