1. Draw a network for the Project. Determine the critical path.
Activity A B C D E F G
Precedence None A None C A B,D E,F
Durations
( Day)
10 15 10 23 3 12 15
2. Draw a network for the Project. Determine the critical path.
Activity A B C D E G H I J K L
Precedence None None None A A B B D,E C H,J G,I,K
Durations
( Day)
2 2 2 3 4 7 6 4 10 3 4
3. Draw a network for the Project. Determine the critical path.
Activity A B C D E F G H S J K T M
Precedence None None A A B B B C D,E F H H,S,J J
Durations
( Day)
2 3 3 2 4 3 9 3 4 2 1 6 1
4. Draw a network for the Project. Determine the critical path.
Activity A B C D E F G H I J K
Precedence NO NO NO NO A,B A,B D
C,D,
F
C,D,
F
E,H G,I
Durations
( Day)
7 13 5 2 9 5 9 3 10 4 8
5. Draw a network for the Project. Determine the critical path.
Activity A B C D E F G
Precedence None None A B C,D C,D F
Durations
( Day)
3 2 5 5 6 2 2
6. Draw a network for the Project. Determine the critical path.
Activity A B C D E F G H I J
Precedence NO A A A B D B C,D F H,F
Durations
( Day)
2 3 4 5 7 4 6 3 3 2
Activity ES EF LS LF TF CP

Critical path method for project management.pptx

  • 1.
    1. Draw anetwork for the Project. Determine the critical path. Activity A B C D E F G Precedence None A None C A B,D E,F Durations ( Day) 10 15 10 23 3 12 15
  • 2.
    2. Draw anetwork for the Project. Determine the critical path. Activity A B C D E G H I J K L Precedence None None None A A B B D,E C H,J G,I,K Durations ( Day) 2 2 2 3 4 7 6 4 10 3 4
  • 3.
    3. Draw anetwork for the Project. Determine the critical path. Activity A B C D E F G H S J K T M Precedence None None A A B B B C D,E F H H,S,J J Durations ( Day) 2 3 3 2 4 3 9 3 4 2 1 6 1
  • 4.
    4. Draw anetwork for the Project. Determine the critical path. Activity A B C D E F G H I J K Precedence NO NO NO NO A,B A,B D C,D, F C,D, F E,H G,I Durations ( Day) 7 13 5 2 9 5 9 3 10 4 8
  • 5.
    5. Draw anetwork for the Project. Determine the critical path. Activity A B C D E F G Precedence None None A B C,D C,D F Durations ( Day) 3 2 5 5 6 2 2
  • 6.
    6. Draw anetwork for the Project. Determine the critical path. Activity A B C D E F G H I J Precedence NO A A A B D B C,D F H,F Durations ( Day) 2 3 4 5 7 4 6 3 3 2
  • 7.
    Activity ES EFLS LF TF CP