SlideShare a Scribd company logo
1 of 5
Download to read offline
1/5
Civilverse Admin 17 April 2021
Project Time Estimation-6 Powerful Tips&Tricks
civilverse.org/project-time-estimation
Table of Contents for Project Time Estimation-Tips & Tricks–
1. Introduction
2. How to Estimate Activity Duration?
3. Bottom to Top Estimation
4. Top to Bottom Estimation
5. Expert Judgement
6. Analogous Estimation
7. Parametric Estimation
8. Three-Point Estimation
9. Conclusion
Introduction
The duration estimation of an activity is an important step in making a project schedule.
The success of the project schedule lies in the completion of scope work within the time.
Thus, the correct time estimation of activity is a critical task to ensure the timely
completion of the job.
The correct estimation of duration is also critical in terms of resource planning. The
incorrect duration estimate may lead to either scarcity of resource or the wastage of the
same. In the said case, either the time is lost or money or both.
The project time estimation tips & tricks include the top six approaches commonly
applied in construction, IT, defence, healthcare etc.
2/5
How to Estimate Project Activity Duration?
The precision in duration estimation of an activity depends on the quantum of work
involved in it. The higher the duration of an activity, the lesser is the precision in duration
estimation. DCMA recommends the activity to have a lower duration than 44 days. If
unavoidable, such activities should not be more than 5% of the total activities.
To accurately determine the time duration for an activity, the following data is required-
1. Complete Scope and inter-dependencies of the activities.
2. Available resources.
3. Priority of the job and criticality of the activity.
4. Working space availability.
5. Risks involved in the activity.
6. Time estimates from previous projects of similar nature.
The choice of the technique varies with the project, industry and organisation. It is the key
responsibility of the project manager to determine the correct duration estimation
technique.
The top six project time estimate tips & tricks are listed below.
Project Time Estimation Techniques
1. Bottom to Top Estimation
The bottom to top estimation method comprises of duration estimate of smaller activities
and summarising them to get the complete project duration. The method is backed up by
the data available from previous projects of similar nature.
3/5
The method is highly accurate as each activity is drilled down to the lowest level and is
discrete in nature. Bottom to top approach works well with projects that have clearly
defined activities and clear scope such as construction projects. It is a quick method to
assess the resources required for the project.
2. Top to Bottom Estimation
The project is divided into work packages. The packages are assigned with the duration
estimate. These packages are further divided into smaller activities when sufficient
information gets available.
Top to bottom method is suitable for initial planning and schedule. The planner can
suitably divide the work package and determines the duration using historical data.
3. Expert Judgement
The expert judgement technique can be used in conjugation with the top to bottom and
bottom to top technique. An expert’s opinion on duration estimation is bound by his/her
experience in similar nature projects, understanding of the project’s complexity and
analytical ability.
A planner should also consult the team members while deciding the duration of an
activity. The team is often comprised of people having experience of similar projects.
Thus, their input in duration estimation is valuable.
The method is useful in complex projects and estimation is to be done beyond the
numerical data.
The drawback of this method lies in the fact that it is opinion-based. The opinion for
duration estimate may change from person to person and hence not too reliable.
4. Analogous Estimation
The analogous estimation technique uses the data from previous projects of similar
nature. This method helps in estimating when and when not. The positive and negative
feedback both help in determining the duration of an activity.
It is the fastest method to estimate the time required for a job to complete. However,
similar projects may have different constraints that affect the project completion. Thus,
the analogous estimation may yield wrong data if the constraints of new and old projects
are not well understood.
5. Parametric Estimation
Parametric estimation is done by dividing the project scope into work packages of similar
nature and identifying the time taken by a single work package.
4/5
The duration estimate of any work package is determined either by historical data or
expert’s opinion. Thus, the accuracy of this method depends on the quality of data and its’
interpretation.
The method is useful for projects that have repetitive activities such as pipeline
construction, power transmission line construction etc.
6. Three-Point Estimation
The three-point estimation is widely used in research projects and product development.
The technique is highly suitable for projects that have high uncertainty and the duration
estimate is difficult.
The three-point technique uses three-time estimates to determine the likely time required
to complete the activity. The three estimates are-
1. Optimistic Time (t )- The time duration in which the activity can be completed if
all the ideal conditions are met.
2. Most Probable Time (t )- The time required for an activity to be completed in
normal working conditions.
3. Pessimistic Time (t )- The pessimistic time is the minimum duration of activity if
all the adverse conditions prevail.
The likely time to complete the activity is calculated as follows-
Three Point Time Estimate
Conclusion
The technique selection depends on the scope, details available, historical data
availability, complexity of the project, bottlenecks and constraints.
For the detailed scope project, bottom to top technique is best suited. If the detailed scope
of work is not defined, top to bottom technique provides a reasonable time estimate.
The research projects and new projects that have no historical data available, expert
judgement is crucial. If the experts’ opinion widely differs, a common ground should be
established and a three-point estimate technique should be used.
For projects of the same nature and similar scope, the analogous technique works well. It
saves a lot of effort. The projects having repeated work packages should use the
parametric technique.
o
m
p
5/5
Learn to create a construction project schedule with an example here.
Read my experiences of waterfall project management here.
Read about the schedule and project management here.

More Related Content

What's hot

How to change working days and time in MS Project?
How to change working days and time in MS Project?How to change working days and time in MS Project?
How to change working days and time in MS Project?SHAZEBALIKHAN1
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingSHAZEBALIKHAN1
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateSHAZEBALIKHAN1
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...Gaurav Verma
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis IOSR Journals
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
Planning can we do with out it?
Planning can we do with out it?Planning can we do with out it?
Planning can we do with out it?Catherine Bendell
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedMichael Pink
 
Estimating Time & Costs
 Estimating Time & Costs Estimating Time & Costs
Estimating Time & Costsmairemic
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesThe Vertex Companies, LLC
 
Delay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping StationDelay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping Stationchetlapally balakrishna
 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gertPranav Krishna
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance AnalysisAcumen
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Shabaz Khan
 

What's hot (20)

How to change working days and time in MS Project?
How to change working days and time in MS Project?How to change working days and time in MS Project?
How to change working days and time in MS Project?
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
A case study of Delay Analysis of construction project: Al Kut Olympic Stadiu...
 
Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis Statistical Methods for Construction Delay Analysis
Statistical Methods for Construction Delay Analysis
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Planning can we do with out it?
Planning can we do with out it?Planning can we do with out it?
Planning can we do with out it?
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
Project Controls Expo 09 Nov 2011, London - DELAY AND FORENSIC ANALYSIS By Ro...
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Estimating Time & Costs
 Estimating Time & Costs Estimating Time & Costs
Estimating Time & Costs
 
Construction Management - New Trends
Construction Management - New TrendsConstruction Management - New Trends
Construction Management - New Trends
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Delay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping StationDelay analysis of raw water reservoir and pumping Station
Delay analysis of raw water reservoir and pumping Station
 
Pert, cpm & gert
Pert, cpm & gertPert, cpm & gert
Pert, cpm & gert
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance Analysis
 
Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...Construction Planning and Scheduling of Residential Building by MS Project by...
Construction Planning and Scheduling of Residential Building by MS Project by...
 

Similar to Project Time Estimation 6 Powerful Tips & Tricks

TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWAREKHUSHBU SHAH
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdfSurashmie Kaalmegh
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Acumen
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimatingharwoodr
 
Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)AnkitaKadam20
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesSHAZEBALIKHAN1
 
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)danieljohn810
 
Program_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxProgram_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxmamtabisht10
 
Project management Using Pert
Project management Using PertProject management Using Pert
Project management Using PertVishnu RC Vijayan
 
Best Project Scheduling Techniques.
Best Project Scheduling Techniques.Best Project Scheduling Techniques.
Best Project Scheduling Techniques.NIILM University
 
Project management : Pert and Cpm
Project management : Pert and CpmProject management : Pert and Cpm
Project management : Pert and CpmShashank Kapoor
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Managementrielaantonio
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration EstimationHarsh Behl
 
Project Preparation and Management
Project Preparation and ManagementProject Preparation and Management
Project Preparation and ManagementGBPUA&T, Pantnagar
 

Similar to Project Time Estimation 6 Powerful Tips & Tricks (20)

PERT
PERTPERT
PERT
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARETIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
TIME & RESOURCE PLANNING,MANAGEMENT SOFTWARE
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdf
 
Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?Does Better Scheduling Drive Execution Success?
Does Better Scheduling Drive Execution Success?
 
3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating3 pm3 t_2%20-%20activity%20duration%20estimating
3 pm3 t_2%20-%20activity%20duration%20estimating
 
Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)Programme evaluation & review technique (pert)
Programme evaluation & review technique (pert)
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
Project time
Project timeProject time
Project time
 
Project schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & TechniquesProject schedule- What, How, Tools & Techniques
Project schedule- What, How, Tools & Techniques
 
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
Cert IV Project Management - Activity Duration Estimating (Tools and Techniques)
 
Program_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxProgram_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptx
 
Project management Using Pert
Project management Using PertProject management Using Pert
Project management Using Pert
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Best Project Scheduling Techniques.
Best Project Scheduling Techniques.Best Project Scheduling Techniques.
Best Project Scheduling Techniques.
 
Project management : Pert and Cpm
Project management : Pert and CpmProject management : Pert and Cpm
Project management : Pert and Cpm
 
Time Management within IT Project Management
Time Management within IT Project ManagementTime Management within IT Project Management
Time Management within IT Project Management
 
Project Duration Estimation
Project Duration EstimationProject Duration Estimation
Project Duration Estimation
 
Project Preparation and Management
Project Preparation and ManagementProject Preparation and Management
Project Preparation and Management
 

More from SHAZEBALIKHAN1

5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them TooSHAZEBALIKHAN1
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowSHAZEBALIKHAN1
 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateSHAZEBALIKHAN1
 
3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction WorksSHAZEBALIKHAN1
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil EngineersSHAZEBALIKHAN1
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateSHAZEBALIKHAN1
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation StepsSHAZEBALIKHAN1
 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileSHAZEBALIKHAN1
 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteSHAZEBALIKHAN1
 
Types of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepTypes of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepSHAZEBALIKHAN1
 
Basics of Contract Management
Basics of Contract ManagementBasics of Contract Management
Basics of Contract ManagementSHAZEBALIKHAN1
 
Bamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & PerformanceBamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & PerformanceSHAZEBALIKHAN1
 
Bricks- Size, Classification, Composition & Quality Control
Bricks- Size, Classification, Composition & Quality ControlBricks- Size, Classification, Composition & Quality Control
Bricks- Size, Classification, Composition & Quality ControlSHAZEBALIKHAN1
 
Design of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced BeamDesign of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced BeamSHAZEBALIKHAN1
 
Pile foundation -Types, Advantages & Load Carrying Capacity
Pile foundation -Types, Advantages & Load Carrying CapacityPile foundation -Types, Advantages & Load Carrying Capacity
Pile foundation -Types, Advantages & Load Carrying CapacitySHAZEBALIKHAN1
 
Steel Reinforcement Facts Every Civil Engineer Must Know
Steel Reinforcement Facts Every Civil Engineer Must KnowSteel Reinforcement Facts Every Civil Engineer Must Know
Steel Reinforcement Facts Every Civil Engineer Must KnowSHAZEBALIKHAN1
 
Civil Design of Structures -WSM & LSM
Civil Design of Structures -WSM & LSMCivil Design of Structures -WSM & LSM
Civil Design of Structures -WSM & LSMSHAZEBALIKHAN1
 
Cement -Types, Composition & QC
Cement -Types, Composition & QCCement -Types, Composition & QC
Cement -Types, Composition & QCSHAZEBALIKHAN1
 

More from SHAZEBALIKHAN1 (18)

5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should Know
 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel Template
 
3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel Template
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel file
 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at Site
 
Types of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepTypes of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and Deep
 
Basics of Contract Management
Basics of Contract ManagementBasics of Contract Management
Basics of Contract Management
 
Bamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & PerformanceBamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & Performance
 
Bricks- Size, Classification, Composition & Quality Control
Bricks- Size, Classification, Composition & Quality ControlBricks- Size, Classification, Composition & Quality Control
Bricks- Size, Classification, Composition & Quality Control
 
Design of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced BeamDesign of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced Beam
 
Pile foundation -Types, Advantages & Load Carrying Capacity
Pile foundation -Types, Advantages & Load Carrying CapacityPile foundation -Types, Advantages & Load Carrying Capacity
Pile foundation -Types, Advantages & Load Carrying Capacity
 
Steel Reinforcement Facts Every Civil Engineer Must Know
Steel Reinforcement Facts Every Civil Engineer Must KnowSteel Reinforcement Facts Every Civil Engineer Must Know
Steel Reinforcement Facts Every Civil Engineer Must Know
 
Civil Design of Structures -WSM & LSM
Civil Design of Structures -WSM & LSMCivil Design of Structures -WSM & LSM
Civil Design of Structures -WSM & LSM
 
Cement -Types, Composition & QC
Cement -Types, Composition & QCCement -Types, Composition & QC
Cement -Types, Composition & QC
 

Recently uploaded

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 

Recently uploaded (20)

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 

Project Time Estimation 6 Powerful Tips & Tricks

  • 1. 1/5 Civilverse Admin 17 April 2021 Project Time Estimation-6 Powerful Tips&Tricks civilverse.org/project-time-estimation Table of Contents for Project Time Estimation-Tips & Tricks– 1. Introduction 2. How to Estimate Activity Duration? 3. Bottom to Top Estimation 4. Top to Bottom Estimation 5. Expert Judgement 6. Analogous Estimation 7. Parametric Estimation 8. Three-Point Estimation 9. Conclusion Introduction The duration estimation of an activity is an important step in making a project schedule. The success of the project schedule lies in the completion of scope work within the time. Thus, the correct time estimation of activity is a critical task to ensure the timely completion of the job. The correct estimation of duration is also critical in terms of resource planning. The incorrect duration estimate may lead to either scarcity of resource or the wastage of the same. In the said case, either the time is lost or money or both. The project time estimation tips & tricks include the top six approaches commonly applied in construction, IT, defence, healthcare etc.
  • 2. 2/5 How to Estimate Project Activity Duration? The precision in duration estimation of an activity depends on the quantum of work involved in it. The higher the duration of an activity, the lesser is the precision in duration estimation. DCMA recommends the activity to have a lower duration than 44 days. If unavoidable, such activities should not be more than 5% of the total activities. To accurately determine the time duration for an activity, the following data is required- 1. Complete Scope and inter-dependencies of the activities. 2. Available resources. 3. Priority of the job and criticality of the activity. 4. Working space availability. 5. Risks involved in the activity. 6. Time estimates from previous projects of similar nature. The choice of the technique varies with the project, industry and organisation. It is the key responsibility of the project manager to determine the correct duration estimation technique. The top six project time estimate tips & tricks are listed below. Project Time Estimation Techniques 1. Bottom to Top Estimation The bottom to top estimation method comprises of duration estimate of smaller activities and summarising them to get the complete project duration. The method is backed up by the data available from previous projects of similar nature.
  • 3. 3/5 The method is highly accurate as each activity is drilled down to the lowest level and is discrete in nature. Bottom to top approach works well with projects that have clearly defined activities and clear scope such as construction projects. It is a quick method to assess the resources required for the project. 2. Top to Bottom Estimation The project is divided into work packages. The packages are assigned with the duration estimate. These packages are further divided into smaller activities when sufficient information gets available. Top to bottom method is suitable for initial planning and schedule. The planner can suitably divide the work package and determines the duration using historical data. 3. Expert Judgement The expert judgement technique can be used in conjugation with the top to bottom and bottom to top technique. An expert’s opinion on duration estimation is bound by his/her experience in similar nature projects, understanding of the project’s complexity and analytical ability. A planner should also consult the team members while deciding the duration of an activity. The team is often comprised of people having experience of similar projects. Thus, their input in duration estimation is valuable. The method is useful in complex projects and estimation is to be done beyond the numerical data. The drawback of this method lies in the fact that it is opinion-based. The opinion for duration estimate may change from person to person and hence not too reliable. 4. Analogous Estimation The analogous estimation technique uses the data from previous projects of similar nature. This method helps in estimating when and when not. The positive and negative feedback both help in determining the duration of an activity. It is the fastest method to estimate the time required for a job to complete. However, similar projects may have different constraints that affect the project completion. Thus, the analogous estimation may yield wrong data if the constraints of new and old projects are not well understood. 5. Parametric Estimation Parametric estimation is done by dividing the project scope into work packages of similar nature and identifying the time taken by a single work package.
  • 4. 4/5 The duration estimate of any work package is determined either by historical data or expert’s opinion. Thus, the accuracy of this method depends on the quality of data and its’ interpretation. The method is useful for projects that have repetitive activities such as pipeline construction, power transmission line construction etc. 6. Three-Point Estimation The three-point estimation is widely used in research projects and product development. The technique is highly suitable for projects that have high uncertainty and the duration estimate is difficult. The three-point technique uses three-time estimates to determine the likely time required to complete the activity. The three estimates are- 1. Optimistic Time (t )- The time duration in which the activity can be completed if all the ideal conditions are met. 2. Most Probable Time (t )- The time required for an activity to be completed in normal working conditions. 3. Pessimistic Time (t )- The pessimistic time is the minimum duration of activity if all the adverse conditions prevail. The likely time to complete the activity is calculated as follows- Three Point Time Estimate Conclusion The technique selection depends on the scope, details available, historical data availability, complexity of the project, bottlenecks and constraints. For the detailed scope project, bottom to top technique is best suited. If the detailed scope of work is not defined, top to bottom technique provides a reasonable time estimate. The research projects and new projects that have no historical data available, expert judgement is crucial. If the experts’ opinion widely differs, a common ground should be established and a three-point estimate technique should be used. For projects of the same nature and similar scope, the analogous technique works well. It saves a lot of effort. The projects having repeated work packages should use the parametric technique. o m p
  • 5. 5/5 Learn to create a construction project schedule with an example here. Read my experiences of waterfall project management here. Read about the schedule and project management here.