SlideShare a Scribd company logo
1 of 8
Download to read offline
1/8
Civilverse Admin 25 October 2020
Change Working Days and Time In MS Project
civilverse.org/change-working-days-and-time-in-ms-project
Table of Content for Change Working Days and Time in MS Project-
1. Introduction
2. What is Calendar in MS Project?
3. Task Calendar & Resource Calendar.
4. Customizing the Calendar.
5. Setting Working Days
6. Working Hours per day
7. Marking Holidays/Leaves
8. Work Contour
1. Introduction-
The Microsoft Project is a project scheduling tool. It makes the project scheduling easier
to visualize especially when the project involves the hundreds of activities. The MS Project
has the ability to integrate the project timeline with cost and resource.
The MS Project calculates the cost based on the working time of resources. The concept is
as simple as it can be. The more time a resource works the more it costs. Thus, it can be
said that the defining time for a resource to work is important to compute its’ cost.
The time duration for an activity to be completed is defined in MS Project along with
working time of the resource. The time is defined in terms of working days per week and
working hours per day.
For moving ahead, I assume that you are familiar with the basic terminology of MS
Project. If you are starting fresh or want to revise the basic terminology of MS Project, I
suggest visiting the below two links before moving ahead so that we can directly come to
our topic.
2/8
MS Project Terminology- Top 20 Terms Everyone Must Know
MS Project Terminology- 20 Must Know Terms-Part 2
Further, I will be using MS Project Professional to explain the features. The features may
differ in different versions.
2. What is Calendar in MS Project?
The Calendar is a function in MS project that enables the user to define the working days
per week and working hours per day. This feature also provides flexibility to add different
working time on different working days.
The holidays and leaves can be also be defined in the calendar so that these
holidays/leaves can be omitted when calculating the project completion date.
To change working days and time in MS Project-
Project Tab > Change Working Time
Change Working Time Dialog Box
The MS Project comes with the four numbers of default calendars that can be chosen as
per the project requirement.
These calendars are-
3/8
Default Calendar In MS Project
1. Standard (Project Calendar)– It has 5 days working with 8 hours per day and
Saturday and Sunday as non-working days.
2. Night Shift Calendar- It has with 12 am to 8 am working with Sunday off.
3. 24 Hour Calendar with 7 days for 24 hours working every day.
3. Task Calendar & Resource Calendar-
The calendar assigned to a task controls it. The task completion date is calculated as per
the task calendar. On the timeline, the duration is shown as per the calendar and the non-
working days are left off in the calculation.
Task Calendar
Similarly, the calendar assigned to a resource controls it and called the Resource
Calendar. The working hours of a resource unit are primarily defined by the resource
calendar.
4/8
Resource Calendar
4. Customizing the Calendar-
Project > Change Working Time > Create New Calendar > Create Copy/Make a New
Calendar
Creating a Copy of Default Calendar
To change the working days and time in MS Project, the calendar can be customized as
per the project requirement or resource availability.
In create new calendar option, you can either choose to create a copy of any of the default
calendars and make adjustments to it or make a completely new calendar.
Once you choose to make a copy of any of the default calendars or make a new one. Click
on ‘Work Weeks’ option and then ‘Details’ options to change the working days per week
and working time per day.
5. Setting Working days-
Project > Change Working Time > Work Weeks > Details
5/8
The workweeks can be defined in Change Working Time Dialog Box. The workweeks are
mentioned with start and finish dates.
6. Setting Working Time-
Project > Change Working Time > Work Weeks > Details.
Changing Working Time per Day
The days are set to working time as per the resource availability each day. On clicking the
‘Details’ option in Change Working Time Dialog Box, a new dialog box opens up. It has
three options-
Use Project default times for these days. Click on this option if you want to enter
standard 8 am-5 pm working time for the selected day.
Set Days to Non-Working time. Select your non-working day(s) and click on this
option to make it a non-working day in the project calendar.
Set day(s) to these working times: If you want to enter customized timing for each
day, click on this option and enter the working hours in the below available table.
Tip: To enter the same working time for days, press Ctrl key and select days. Now enter
the working time in the table.
7. Marking Holidays/Leaves
Project > Change Working Time > (Select Your Calendar) > Exceptions
6/8
Marking Holiday/Leave in Calendar
The calendar is marked with the holiday(s)/leave(s) to make an exception for that
day/period. With the marking of exception for a day, the MS Project doesn’t count that
day when calculating the completion date.
The ‘Exception’ feature is also helpful when a resource is not available to work on the
project. The unavailability of the resource can be marked in the calendar thus, preventing
the allocation of the task to that calendar on that day.
8. Work Contour–
The work of a resource is distributed equally throughout the duration of the task. This
may not always be true. Some task may require higher working hours in the beginning
and lesser hours in the end. Or lesser hours in the beginning and more hours as the work
proceeds. Many such trends can be observed when working with a huge number of
activities.
The work contour feature helps in distributing the work over the duration of the task in
the desired manner.
Task Tab > Gantt Chart (Bottom Half Part) > Resource Usage > (Select Resource & Right-
Click) > Information > General > Work Contour
7/8
Selecting Resource Usage Sheet
The MS Project offers following pre-defined work contours-
Work Contour
1. Flat
2. Back Loaded
3. Front Loaded
4. Double Peak
5. Early Peak
6. Late Peak
7. Bell
8. Turtle
You can also change the working time per day for a resource directly in the resource usage
view by typing the working hours.
Liked the article ‘Change Working Days and Time In MS Project’? Let me know in the
comment below.
8/8
Want to read about Project Schedule? Click here.
Check your schedule quality check here.
For Work Breakdown Structure (WBS), Click here.
Happy Engineering!

More Related Content

What's hot

Project Management using MS Project 2010
Project Management using MS Project 2010Project Management using MS Project 2010
Project Management using MS Project 2010Abdul Ghaffar, PMP
 
Ms project training ppt
Ms project training pptMs project training ppt
Ms project training pptglobalp7
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual Abbas Tahir
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS projectSamir Paralikar
 
MICROSOFT PROJECT
MICROSOFT PROJECTMICROSOFT PROJECT
MICROSOFT PROJECTSmit Patel
 
Ms project literature to read
Ms project   literature to readMs project   literature to read
Ms project literature to readChetan vadodariya
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - TutorialRajeev Sharma
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Chetanraj M
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsSHAZEBALIKHAN1
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures Ian Cammack
 
Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorialKetut Swandana
 

What's hot (20)

Project Management using MS Project 2010
Project Management using MS Project 2010Project Management using MS Project 2010
Project Management using MS Project 2010
 
Ms project training ppt
Ms project training pptMs project training ppt
Ms project training ppt
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Primavera P6 manual
Primavera P6 manual Primavera P6 manual
Primavera P6 manual
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Ms Project 2010
Ms Project 2010Ms Project 2010
Ms Project 2010
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS project
 
MS Project 2010 Training
MS Project 2010 TrainingMS Project 2010 Training
MS Project 2010 Training
 
MICROSOFT PROJECT
MICROSOFT PROJECTMICROSOFT PROJECT
MICROSOFT PROJECT
 
MS Project
MS ProjectMS Project
MS Project
 
Ms project literature to read
Ms project   literature to readMs project   literature to read
Ms project literature to read
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling Factors
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures
 
Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorial
 
Microsoft Project
Microsoft ProjectMicrosoft Project
Microsoft Project
 

Similar to How to change working days and time in MS Project?

MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docxMS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docxrosemarybdodson23141
 
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcUnderstanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcKhalid Noor Mohammed
 
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docx
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docxSCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docx
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docxbagotjesusa
 
Project 2007 full handout
Project 2007 full handoutProject 2007 full handout
Project 2007 full handoutZenawi Mehari
 
Free Timesheet Templates in Excel, PDF, Word Formats (Weekly, Monthly, Bi-Wee...
Free Timesheet Templates in Excel, PDF, Word Formats (Weekly, Monthly, Bi-Wee...Free Timesheet Templates in Excel, PDF, Word Formats (Weekly, Monthly, Bi-Wee...
Free Timesheet Templates in Excel, PDF, Word Formats (Weekly, Monthly, Bi-Wee...Time Doctor
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguideJason Koo
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide성철 박
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingSHAZEBALIKHAN1
 
Project NameCommunication PlanOverviewEffective and .docx
Project NameCommunication PlanOverviewEffective and .docxProject NameCommunication PlanOverviewEffective and .docx
Project NameCommunication PlanOverviewEffective and .docxwkyra78
 
2007 MS Project Training Instructors Manual (sample)
2007 MS Project Training Instructors Manual (sample)2007 MS Project Training Instructors Manual (sample)
2007 MS Project Training Instructors Manual (sample)Bruce Gordon
 
Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-scheduleRaaz Karkee
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Schedulingsslovepk
 
Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010Bhishma Bhatti
 
Time tracking in orangescrum
Time tracking in orangescrumTime tracking in orangescrum
Time tracking in orangescrumOrangescrum
 
2Project_management. Ghjjkkutfghuuijkpdf
2Project_management. Ghjjkkutfghuuijkpdf2Project_management. Ghjjkkutfghuuijkpdf
2Project_management. GhjjkkutfghuuijkpdfRedietWegene
 
Plan your Construction Schedule with Calendar 365.pdf
Plan your Construction Schedule with Calendar 365.pdfPlan your Construction Schedule with Calendar 365.pdf
Plan your Construction Schedule with Calendar 365.pdfAppJetty
 
Calendars are tools that can be assigned to the project and to indiv.docx
Calendars are tools that can be assigned to the project and to indiv.docxCalendars are tools that can be assigned to the project and to indiv.docx
Calendars are tools that can be assigned to the project and to indiv.docxchestnutkaitlyn
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorialRonald Oroya
 

Similar to How to change working days and time in MS Project? (20)

MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docxMS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
 
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcUnderstanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
 
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docx
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docxSCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docx
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docx
 
BhadaniS Microsoft Project Manual Training
BhadaniS Microsoft Project Manual TrainingBhadaniS Microsoft Project Manual Training
BhadaniS Microsoft Project Manual Training
 
Project 2007 full handout
Project 2007 full handoutProject 2007 full handout
Project 2007 full handout
 
Schedule management
Schedule managementSchedule management
Schedule management
 
Free Timesheet Templates in Excel, PDF, Word Formats (Weekly, Monthly, Bi-Wee...
Free Timesheet Templates in Excel, PDF, Word Formats (Weekly, Monthly, Bi-Wee...Free Timesheet Templates in Excel, PDF, Word Formats (Weekly, Monthly, Bi-Wee...
Free Timesheet Templates in Excel, PDF, Word Formats (Weekly, Monthly, Bi-Wee...
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide
 
Ms project2007 quickguide
Ms project2007 quickguideMs project2007 quickguide
Ms project2007 quickguide
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
 
Project NameCommunication PlanOverviewEffective and .docx
Project NameCommunication PlanOverviewEffective and .docxProject NameCommunication PlanOverviewEffective and .docx
Project NameCommunication PlanOverviewEffective and .docx
 
2007 MS Project Training Instructors Manual (sample)
2007 MS Project Training Instructors Manual (sample)2007 MS Project Training Instructors Manual (sample)
2007 MS Project Training Instructors Manual (sample)
 
Building a-project-schedule
Building a-project-scheduleBuilding a-project-schedule
Building a-project-schedule
 
Wbs & Project Scheduling
Wbs & Project SchedulingWbs & Project Scheduling
Wbs & Project Scheduling
 
Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010
 
Time tracking in orangescrum
Time tracking in orangescrumTime tracking in orangescrum
Time tracking in orangescrum
 
2Project_management. Ghjjkkutfghuuijkpdf
2Project_management. Ghjjkkutfghuuijkpdf2Project_management. Ghjjkkutfghuuijkpdf
2Project_management. Ghjjkkutfghuuijkpdf
 
Plan your Construction Schedule with Calendar 365.pdf
Plan your Construction Schedule with Calendar 365.pdfPlan your Construction Schedule with Calendar 365.pdf
Plan your Construction Schedule with Calendar 365.pdf
 
Calendars are tools that can be assigned to the project and to indiv.docx
Calendars are tools that can be assigned to the project and to indiv.docxCalendars are tools that can be assigned to the project and to indiv.docx
Calendars are tools that can be assigned to the project and to indiv.docx
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
 

More from SHAZEBALIKHAN1

Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateSHAZEBALIKHAN1
 
5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them TooSHAZEBALIKHAN1
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowSHAZEBALIKHAN1
 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateSHAZEBALIKHAN1
 
3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction WorksSHAZEBALIKHAN1
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil EngineersSHAZEBALIKHAN1
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateSHAZEBALIKHAN1
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation StepsSHAZEBALIKHAN1
 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileSHAZEBALIKHAN1
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims EffectivelySHAZEBALIKHAN1
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsSHAZEBALIKHAN1
 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteSHAZEBALIKHAN1
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementSHAZEBALIKHAN1
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingSHAZEBALIKHAN1
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction ContractsSHAZEBALIKHAN1
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksSHAZEBALIKHAN1
 
Types of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepTypes of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepSHAZEBALIKHAN1
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckSHAZEBALIKHAN1
 
Basics of Contract Management
Basics of Contract ManagementBasics of Contract Management
Basics of Contract ManagementSHAZEBALIKHAN1
 
Bamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & PerformanceBamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & PerformanceSHAZEBALIKHAN1
 

More from SHAZEBALIKHAN1 (20)

Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too5 Project Risk Identification Tools I Use & How You Can Use Them Too
5 Project Risk Identification Tools I Use & How You Can Use Them Too
 
Top 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should KnowTop 20 Standard Contract Clauses Every Manager Should Know
Top 20 Standard Contract Clauses Every Manager Should Know
 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel Template
 
3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works3 Most Important In-situ Soil Tests for Construction Works
3 Most Important In-situ Soil Tests for Construction Works
 
5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers5 Must Know Types of Concrete Testing for Civil Engineers
5 Must Know Types of Concrete Testing for Civil Engineers
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel Template
 
10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps10 Powerful Construction Cost Estimation Steps
10 Powerful Construction Cost Estimation Steps
 
Construction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel fileConstruction Material Estimate with MS Excel file
Construction Material Estimate with MS Excel file
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims Effectively
 
Most Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management TermsMost Popular 20 Evergreen Project Management Terms
Most Popular 20 Evergreen Project Management Terms
 
Top 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at SiteTop 5 Concrete Quality Control Methods at Site
Top 5 Concrete Quality Control Methods at Site
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
 
Construction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential BuildingConstruction Project Schedule Example- Residential Building
Construction Project Schedule Example- Residential Building
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts
 
Project Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & TricksProject Time Estimation 6 Powerful Tips & Tricks
Project Time Estimation 6 Powerful Tips & Tricks
 
Types of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and DeepTypes of Building Foundations- Shallow and Deep
Types of Building Foundations- Shallow and Deep
 
DCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality CheckDCMA 14-Point Schedule Quality Check
DCMA 14-Point Schedule Quality Check
 
Basics of Contract Management
Basics of Contract ManagementBasics of Contract Management
Basics of Contract Management
 
Bamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & PerformanceBamboo Reinforced Concrete - Criteria & Performance
Bamboo Reinforced Concrete - Criteria & Performance
 

Recently uploaded

INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 

Recently uploaded (20)

INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 

How to change working days and time in MS Project?

  • 1. 1/8 Civilverse Admin 25 October 2020 Change Working Days and Time In MS Project civilverse.org/change-working-days-and-time-in-ms-project Table of Content for Change Working Days and Time in MS Project- 1. Introduction 2. What is Calendar in MS Project? 3. Task Calendar & Resource Calendar. 4. Customizing the Calendar. 5. Setting Working Days 6. Working Hours per day 7. Marking Holidays/Leaves 8. Work Contour 1. Introduction- The Microsoft Project is a project scheduling tool. It makes the project scheduling easier to visualize especially when the project involves the hundreds of activities. The MS Project has the ability to integrate the project timeline with cost and resource. The MS Project calculates the cost based on the working time of resources. The concept is as simple as it can be. The more time a resource works the more it costs. Thus, it can be said that the defining time for a resource to work is important to compute its’ cost. The time duration for an activity to be completed is defined in MS Project along with working time of the resource. The time is defined in terms of working days per week and working hours per day. For moving ahead, I assume that you are familiar with the basic terminology of MS Project. If you are starting fresh or want to revise the basic terminology of MS Project, I suggest visiting the below two links before moving ahead so that we can directly come to our topic.
  • 2. 2/8 MS Project Terminology- Top 20 Terms Everyone Must Know MS Project Terminology- 20 Must Know Terms-Part 2 Further, I will be using MS Project Professional to explain the features. The features may differ in different versions. 2. What is Calendar in MS Project? The Calendar is a function in MS project that enables the user to define the working days per week and working hours per day. This feature also provides flexibility to add different working time on different working days. The holidays and leaves can be also be defined in the calendar so that these holidays/leaves can be omitted when calculating the project completion date. To change working days and time in MS Project- Project Tab > Change Working Time Change Working Time Dialog Box The MS Project comes with the four numbers of default calendars that can be chosen as per the project requirement. These calendars are-
  • 3. 3/8 Default Calendar In MS Project 1. Standard (Project Calendar)– It has 5 days working with 8 hours per day and Saturday and Sunday as non-working days. 2. Night Shift Calendar- It has with 12 am to 8 am working with Sunday off. 3. 24 Hour Calendar with 7 days for 24 hours working every day. 3. Task Calendar & Resource Calendar- The calendar assigned to a task controls it. The task completion date is calculated as per the task calendar. On the timeline, the duration is shown as per the calendar and the non- working days are left off in the calculation. Task Calendar Similarly, the calendar assigned to a resource controls it and called the Resource Calendar. The working hours of a resource unit are primarily defined by the resource calendar.
  • 4. 4/8 Resource Calendar 4. Customizing the Calendar- Project > Change Working Time > Create New Calendar > Create Copy/Make a New Calendar Creating a Copy of Default Calendar To change the working days and time in MS Project, the calendar can be customized as per the project requirement or resource availability. In create new calendar option, you can either choose to create a copy of any of the default calendars and make adjustments to it or make a completely new calendar. Once you choose to make a copy of any of the default calendars or make a new one. Click on ‘Work Weeks’ option and then ‘Details’ options to change the working days per week and working time per day. 5. Setting Working days- Project > Change Working Time > Work Weeks > Details
  • 5. 5/8 The workweeks can be defined in Change Working Time Dialog Box. The workweeks are mentioned with start and finish dates. 6. Setting Working Time- Project > Change Working Time > Work Weeks > Details. Changing Working Time per Day The days are set to working time as per the resource availability each day. On clicking the ‘Details’ option in Change Working Time Dialog Box, a new dialog box opens up. It has three options- Use Project default times for these days. Click on this option if you want to enter standard 8 am-5 pm working time for the selected day. Set Days to Non-Working time. Select your non-working day(s) and click on this option to make it a non-working day in the project calendar. Set day(s) to these working times: If you want to enter customized timing for each day, click on this option and enter the working hours in the below available table. Tip: To enter the same working time for days, press Ctrl key and select days. Now enter the working time in the table. 7. Marking Holidays/Leaves Project > Change Working Time > (Select Your Calendar) > Exceptions
  • 6. 6/8 Marking Holiday/Leave in Calendar The calendar is marked with the holiday(s)/leave(s) to make an exception for that day/period. With the marking of exception for a day, the MS Project doesn’t count that day when calculating the completion date. The ‘Exception’ feature is also helpful when a resource is not available to work on the project. The unavailability of the resource can be marked in the calendar thus, preventing the allocation of the task to that calendar on that day. 8. Work Contour– The work of a resource is distributed equally throughout the duration of the task. This may not always be true. Some task may require higher working hours in the beginning and lesser hours in the end. Or lesser hours in the beginning and more hours as the work proceeds. Many such trends can be observed when working with a huge number of activities. The work contour feature helps in distributing the work over the duration of the task in the desired manner. Task Tab > Gantt Chart (Bottom Half Part) > Resource Usage > (Select Resource & Right- Click) > Information > General > Work Contour
  • 7. 7/8 Selecting Resource Usage Sheet The MS Project offers following pre-defined work contours- Work Contour 1. Flat 2. Back Loaded 3. Front Loaded 4. Double Peak 5. Early Peak 6. Late Peak 7. Bell 8. Turtle You can also change the working time per day for a resource directly in the resource usage view by typing the working hours. Liked the article ‘Change Working Days and Time In MS Project’? Let me know in the comment below.
  • 8. 8/8 Want to read about Project Schedule? Click here. Check your schedule quality check here. For Work Breakdown Structure (WBS), Click here. Happy Engineering!