Critical Path Method (CPM)
CPM is a network diagramming technique used
to predict total project duration.
CPM is an analysis technique with three main
purposes:
To calculate the project’s finish date
To indentify to what extent each activity in the
schedule can slip(float) without delaying the
project
To identify the activities with highest risk that
cannot slip without changing the project finish
date2
CPM
How does the Critical Path Method calculate the
project’s finish date?
o Forward pass calculation
 calculates Early Start and Early Finish dates
o Backward pass calculation
 calculates Late Start and Late Finish dates
3
Early Start (ES) is the earliest date a task can
start
Early Finish (EF) is the earliest date a task can
be completed
Late Start (LS) is the latest date a task can start
without delaying the project and date
Late Finish (LF) is the latest date a task can
finish without delaying the project end date
4
5
Start
D
5
F
2
C
6
Finish
E
4
B
1
A
2
Forward Pass
0 0
0 1511652
550
1515
1111 13
• Early Start (ES) = Latest related early date of all
immediate predecessors
ES= immediate Predecessors’ ES max
Early finish (EF) = Early Start + Duration
EF= ES + D
6
Activity A
ES EF
ES=3
ES=9
ES=10
D
7
Start
D
5
F
2
C
6
Finish
E
4
A
2
0
0
0
0
0
108
50
15
15
11
1165
1110
2
550
115
1515
1515
1111 13
B
1
1513
Backward Pass
Late Finish (LF) = Earliest related late date of all
immediate successors
LF= immediate Successors’ LF min
Late Start (LS) = Late Finish – Duration
LS= LF-D
8
Activity A
LS LF
LF=3
LF=9
LF=10D
The purpose of backward pass is to find the float.
Float is the amount of time an activity can be
delayed or lengthened. Also called slack.
Total float: the amount of time an activity can be
delayed or extended without extending the overall
project’s completion time
9
What is the total Float for activity A?
10
Start
D
5
F
2
C
6
Finish
E
4
A
2
0
0
0
0
0
108
50
15
15
11
1165
1110
2
550
115
1515
1515
1111 13
B
1
1513
11
Total float = LF-ES-D
A
2
0
108
65
1110
2
B
1
LFLSEFES
10820
A
A
Float
Float
Total Float:
TF= LF - ES – D
TF= LF – (ES+D) = LF-EF
TF= LF-D-ES= LS-ES
12
Activity A
LS LF
ES EF
Free Float: the amount of time an activity can be
delayed without delaying the early start date of its
subsequent tasks
13
Activity A
LS LF
ES EF
What is the FF for activity A?
What would happen if A uses its max float?
(A)EF=LF=10 (B) ES=LS=10
IF the early finish date of activity A =5
the early start date of activity B=5
FF=5-2=3
14
A
2
0
108
65
1110
2
B
1
Free Float: the amount of time an activity can be
delayed without delaying the early start date of its
subsequent tasks
EF= ES(B) – EF(A)
EF= ES(earliest successor)- EF
15
Activity A
LS LF
ES EF
Why floats are important in the critical path
method?
If an activity has a TF=0, what does this mean?
Floats determine thee criticality of an activity
Critical activities have the least amount of Float
Floats determine the critical path
16
The critical path is made of activities that cannot
be delayed without delaying the final date of the
project
If an item is on critical path, it has a zero float
The critical path is the path with longest duration
It is possible to have more than one critical path
17
What is the critical path?
What is the length of the critical path?
18
Start
D
5
F
2
C
6
Finish
E
4
A
2
0
0
0
0
0
108
50
15
15
11
1165
1110
2
550
115
1515
1515
1111 13
B
1
1513
Critical Path Method (CPM)
CPM is a network diagramming technique used
to predict total project duration
A critical path for a project is the series of
activities that determines the earliest time by
which the project can be completed
The critical path is the longest path through the
network diagram and has the least amount of
slack or float
Slack or float is the amount of time an activity
may be delayed without delaying a succeeding
activity or the project finish date
19
Calculating the Critical Path
First develop a good network diagram
Add the duration estimates for all activities on
each path through the network diagram
The longest path is the critical path
If one or more of the activities on the critical path
takes longer than planned, the whole project
schedule will slip unless the project manager
takes corrective action
20

More Related Content

What's hot

What's hot (20)

Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
Critical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network AnalysisCritical Path Method (CPM) & Network Analysis
Critical Path Method (CPM) & Network Analysis
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Pert
PertPert
Pert
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Pert analysis
Pert analysisPert analysis
Pert analysis
 
Critical path method
Critical path methodCritical path method
Critical path method
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
Project Planning
Project PlanningProject Planning
Project Planning
 
Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Project management techniques
Project management techniquesProject management techniques
Project management techniques
 
Critical Path Method(CPM)
Critical Path Method(CPM)Critical Path Method(CPM)
Critical Path Method(CPM)
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Pert and cpm
Pert and cpmPert and cpm
Pert and cpm
 
CPM - Critical Path Method
CPM - Critical Path Method CPM - Critical Path Method
CPM - Critical Path Method
 
Project management and project life cycle
Project management and project life cycleProject management and project life cycle
Project management and project life cycle
 
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
#Project Scheduling - Network Diagrams : PERT & CPM# By SN Panigrahi
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 

Similar to Critical path method (cpm)

Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptxHimanshuKaklotar1
 
Critical path presentation for timely project completion
Critical path presentation for timely project completionCritical path presentation for timely project completion
Critical path presentation for timely project completionAniruddha Kulkarni
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysistutor2u
 
SPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxSPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxMuhammadAbubakar114879
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfSalahudin Babar
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesSAJID ALI RUK
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementAmit Kumbar
 
Lec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project schedulingLec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project schedulingSyed Hamza
 
NETWORK SCHEDULING TECHNIQUES Of software
NETWORK SCHEDULING TECHNIQUES Of softwareNETWORK SCHEDULING TECHNIQUES Of software
NETWORK SCHEDULING TECHNIQUES Of softwarexainkhan8
 
project-network-diagram.ppt
project-network-diagram.pptproject-network-diagram.ppt
project-network-diagram.pptalbert937613
 
Project Management Fundamental
Project Management FundamentalProject Management Fundamental
Project Management FundamentalAndy Pham, PMP
 
OM_SECTION 4 PART C_STUDENT.ppt
OM_SECTION 4 PART C_STUDENT.pptOM_SECTION 4 PART C_STUDENT.ppt
OM_SECTION 4 PART C_STUDENT.pptPhmLanAnh23
 

Similar to Critical path method (cpm) (20)

CPM NETWORK
CPM NETWORKCPM NETWORK
CPM NETWORK
 
Lecture 5.pdf
Lecture 5.pdfLecture 5.pdf
Lecture 5.pdf
 
Critical path method (CPM).pptx
Critical path method (CPM).pptxCritical path method (CPM).pptx
Critical path method (CPM).pptx
 
Critical path presentation for timely project completion
Critical path presentation for timely project completionCritical path presentation for timely project completion
Critical path presentation for timely project completion
 
Critical Path Analysis
Critical Path AnalysisCritical Path Analysis
Critical Path Analysis
 
SPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptxSPM presentation extra material-Lect 9and 10.pptx
SPM presentation extra material-Lect 9and 10.pptx
 
Gantt PERT and CPM
Gantt PERT and CPMGantt PERT and CPM
Gantt PERT and CPM
 
criticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdfcriticalpathmethod-151022164503-lva1-app6892.pdf
criticalpathmethod-151022164503-lva1-app6892.pdf
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Lec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project schedulingLec 9 & 10 chapter 5 project scheduling
Lec 9 & 10 chapter 5 project scheduling
 
NETWORK SCHEDULING TECHNIQUES Of software
NETWORK SCHEDULING TECHNIQUES Of softwareNETWORK SCHEDULING TECHNIQUES Of software
NETWORK SCHEDULING TECHNIQUES Of software
 
Project management
Project managementProject management
Project management
 
project-network-diagram.ppt
project-network-diagram.pptproject-network-diagram.ppt
project-network-diagram.ppt
 
Project Management Fundamental
Project Management FundamentalProject Management Fundamental
Project Management Fundamental
 
OM_SECTION 4 PART C_STUDENT.ppt
OM_SECTION 4 PART C_STUDENT.pptOM_SECTION 4 PART C_STUDENT.ppt
OM_SECTION 4 PART C_STUDENT.ppt
 
Cpmprt
CpmprtCpmprt
Cpmprt
 

Recently uploaded

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 

Critical path method (cpm)

  • 2. CPM is a network diagramming technique used to predict total project duration. CPM is an analysis technique with three main purposes: To calculate the project’s finish date To indentify to what extent each activity in the schedule can slip(float) without delaying the project To identify the activities with highest risk that cannot slip without changing the project finish date2
  • 3. CPM How does the Critical Path Method calculate the project’s finish date? o Forward pass calculation  calculates Early Start and Early Finish dates o Backward pass calculation  calculates Late Start and Late Finish dates 3
  • 4. Early Start (ES) is the earliest date a task can start Early Finish (EF) is the earliest date a task can be completed Late Start (LS) is the latest date a task can start without delaying the project and date Late Finish (LF) is the latest date a task can finish without delaying the project end date 4
  • 6. • Early Start (ES) = Latest related early date of all immediate predecessors ES= immediate Predecessors’ ES max Early finish (EF) = Early Start + Duration EF= ES + D 6 Activity A ES EF ES=3 ES=9 ES=10 D
  • 8. Late Finish (LF) = Earliest related late date of all immediate successors LF= immediate Successors’ LF min Late Start (LS) = Late Finish – Duration LS= LF-D 8 Activity A LS LF LF=3 LF=9 LF=10D
  • 9. The purpose of backward pass is to find the float. Float is the amount of time an activity can be delayed or lengthened. Also called slack. Total float: the amount of time an activity can be delayed or extended without extending the overall project’s completion time 9
  • 10. What is the total Float for activity A? 10 Start D 5 F 2 C 6 Finish E 4 A 2 0 0 0 0 0 108 50 15 15 11 1165 1110 2 550 115 1515 1515 1111 13 B 1 1513
  • 11. 11 Total float = LF-ES-D A 2 0 108 65 1110 2 B 1 LFLSEFES 10820 A A Float Float
  • 12. Total Float: TF= LF - ES – D TF= LF – (ES+D) = LF-EF TF= LF-D-ES= LS-ES 12 Activity A LS LF ES EF
  • 13. Free Float: the amount of time an activity can be delayed without delaying the early start date of its subsequent tasks 13 Activity A LS LF ES EF
  • 14. What is the FF for activity A? What would happen if A uses its max float? (A)EF=LF=10 (B) ES=LS=10 IF the early finish date of activity A =5 the early start date of activity B=5 FF=5-2=3 14 A 2 0 108 65 1110 2 B 1
  • 15. Free Float: the amount of time an activity can be delayed without delaying the early start date of its subsequent tasks EF= ES(B) – EF(A) EF= ES(earliest successor)- EF 15 Activity A LS LF ES EF
  • 16. Why floats are important in the critical path method? If an activity has a TF=0, what does this mean? Floats determine thee criticality of an activity Critical activities have the least amount of Float Floats determine the critical path 16
  • 17. The critical path is made of activities that cannot be delayed without delaying the final date of the project If an item is on critical path, it has a zero float The critical path is the path with longest duration It is possible to have more than one critical path 17
  • 18. What is the critical path? What is the length of the critical path? 18 Start D 5 F 2 C 6 Finish E 4 A 2 0 0 0 0 0 108 50 15 15 11 1165 1110 2 550 115 1515 1515 1111 13 B 1 1513
  • 19. Critical Path Method (CPM) CPM is a network diagramming technique used to predict total project duration A critical path for a project is the series of activities that determines the earliest time by which the project can be completed The critical path is the longest path through the network diagram and has the least amount of slack or float Slack or float is the amount of time an activity may be delayed without delaying a succeeding activity or the project finish date 19
  • 20. Calculating the Critical Path First develop a good network diagram Add the duration estimates for all activities on each path through the network diagram The longest path is the critical path If one or more of the activities on the critical path takes longer than planned, the whole project schedule will slip unless the project manager takes corrective action 20