SlideShare a Scribd company logo
1 of 35
PERT/CPM Models for Project Management
Agenda What is Project Management Discuss PERT/CPM Motivating Case Study: The Reliable Construction Company Ways of Finding the Critical Path Considering Time-Cost Trade-Offs
What is Project Management Project management can be defined as the coordination of activities with the potential use of many organizations, both internal and external to the business, in order to conduct a large scale project from beginning to end. There are two management science techniques that are used for project management: Program and Evaluation Review Technique (PERT) Critical Path Method (CPM)
PERT/CPM PERT PERT was designed to examine projects from the standpoint of uncertainty. CPM CPM was designed to examine projects from the standpoint of costs. PERT and CPM techniques have been combined over time. PERT and CPM both rely heavily on the use of networks to help plan and display the coordination of all the activities for a project.
The Reliable Construction Company Reliable has just secured a contract to construct a new plant for a major manufacturer. The contract is for $5.4 million to cover all costs and any profits. The plant must be finished in a year. A penalty of $300,000 will be assessed if Reliable does not complete the project within 47 weeks. A bonus of $150,000 will be paid to Reliable if the plant is completed within 40 weeks.
Needed Terminology Activity A distinct task that needs to be performed as part of the project. Start Node This is a node that represents the beginning of the project. Finish Node This node represents the end of the project.
Needed Terminology Cont. Immediate Predecessor These are activities that must be completed by no later than the start time of the given activity. Immediate Successor Given the immediate predecessor of an activity, this activity becomes the immediate successor of each of these immediate predecessors. If an immediate successor has multiple immediate predecessors, then all must be finished before an activity can begin.
Activity List for Reliable Construction
Questions Needed to be Answered How can the project be displayed graphically? How much time is required to finish the project if no delays occur? When is earliest start and finish times for each activity if no delays occur? What activities are critical bottleneck activities where delays must be avoided to finish the project on time?
Questions Needed to be Answered Cont. For non bottleneck activities, how much can an activity be delayed and yet still keep the project on time? What is the probability of completing the project by the deadline? What is the least amount of money needed to expedite the project to obtain the bonus? How should costs be monitored to keep the project within budget?
Project Network A project network is a network diagram that uses nodes and arcs to represent the progression of the activities is a project from start to finish. Three pieces of information needed: Activity information Precedence relationship Time information
Project Network Cont. Two types of project networks Activity-on-Arc (AOA) On this diagram, the activity is represented on an arc, while a node is used to separate an activity from its immediate predecessors.  Activity-on-Node (AON) On this diagram, the activity is represented by the node, while the arc is used to showed the precedence relationship between the activities.
Microsoft Project Visual Diagram: Gantt Chart
Scheduling Using PERT/CPM A path through a project network is a route that follows a set of arcs from the start node to the finish node. The length of a path is defined as the sum of the durations of the activities of the path. What are the paths and their corresponding lengths for Reliable?
Critical Path This is the path that has the longest length through the project. The shortest time that a project can conceivably be finished is the critical path. Why?
More Terminology Earliest start time of an activity (ES) The time at which an activity will begin if there are no delays in a project. Earliest finish time of an activity (EF) The time at which an activity will finish if there are no delays in a project. Latest start time of an activity (LS) The latest possible time that an activity can start without delaying the project.
More Terminology Cont. Latest finish time of an activity (LF) The latest possible time that an activity can be completed without delaying the project. Forward pass The process of moving through a project from start to finish to determine the earliest start and finish times for the activities in the project.
More Terminology Cont. Backward pass The process of moving through a project from finish to start to determine the latest start and finish times for the activities in the project. Slack for an activity The amount of time that a particular activity can be delayed without delaying the whole project. It is calculated by taking the difference between the latest finish time with the earliest finish time.
More Terminology Cont. Earliest start time rule The earliest start time for an activity is equal to the largest of the earliest finish times of its immediate predecessors. Latest finish time rule The latest finish time is equal to the smallest of the latest start times of its immediate successors.
Procedure for Obtaining Earliest Times Step 1: For the activity that starts the project, assign an earliest start time of zero, i.e., ES=0. Step 2: For each activity whose ES has just been obtained, calculate its earliest finish time as ES plus duration of the activity. Step 3: For each new activity whose immediate predecessors have EF values, obtain its ES by using the earliest start time rule.
Procedure for Obtaining Earliest Times Cont. Step 4: Apply step 2 to calculate EF. Step 5: Repeat step 3 until ES and EF have been obtained for all activities including the finish node.
Procedure for Obtaining Latest Times Step 1: For each of the activities that together complete the project, set its latest finish time equal to the earliest finish time of the finish node. Step 2: For each activity whose LF value has just been obtained, calculate its latest start time as LS equals LF minus the duration of the activity.
Procedure for Obtaining Latest Times Cont. Step 3: For each new activity whose immediate successors now have LS values, obtain its LF by applying the latest finish time rule. Step 4: Apply step 2 to calculate its LS. Step 5: Repeat step 3 until LF and LS have been obtained for all activities.
Ways of Finding the Critical Path Examine all the paths and find the path with the maximum length. Calculate the slack for an activity. If the slack is zero, it is on the critical path. If the slack is positive, it is not on the critical path.
Time-Cost Trade-Offs Reliable had an incentive bonus of $150,000 to finish the project in 40 weeks. Is it worth while for Reliable to speed-up the project?
Crashing Crashing an activity refers to taking on extra expenditures in order to reduce the duration of an activity below its expected value. Crashing a project refers to crashing a number of activities to reduce the duration of the project.
CPM Method of Time-Cost Trade-Offs This is a method concerned with whether it is worthwhile to crash activities to reduce the anticipated duration of the project to a desired value. This assumes that there is a trade-off between time and cost that has an inverse relationship.
More Terminology Normal Point is the time and cost of an activity when it is performed in a normal way. Crash point show the time and cost when the activity is fully crashed.
Graph of Normal and Crash Points
Marginal Cost Analysis It is a method of using the marginal cost of crashing individual activities on the current critical path to determine the least expensive way of reducing the project duration to an acceptable level. This method requires you to calculate the cost per desired time unit and compare each cost with the other costs.
Marginal Cost Analysis Cont. Once the marginal cost for crashing each activity has been conducted, you next want to choose the crashing that has the smallest marginal cost. Next, calculate the effect that the crash has on each path. Note: Crashing can potentially cause another path to become a critical path.
Solving Crashing Problems Using LP There are three decisions to be made: The start time of each activity The reduction in each activity due to crashing The finish time of the project LP model will be examined in class.

More Related Content

What's hot

Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)El Moro
 
Diagrama Redes PERT CPM
Diagrama Redes PERT CPMDiagrama Redes PERT CPM
Diagrama Redes PERT CPMNeris Alfonzo
 
Use of forward pass and backward pass in primavera
Use of forward pass and backward pass in primaveraUse of forward pass and backward pass in primavera
Use of forward pass and backward pass in primaveraAmit Kumar Senapati, PMP®
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPMstudent
 
Network diagrams
Network diagramsNetwork diagrams
Network diagramsNicola2903
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and schedulingAditi Garg
 
Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path methodPrathima Girish
 
Project management Pert & cpm
Project management Pert & cpm Project management Pert & cpm
Project management Pert & cpm RandhirKumar172
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksPrasad Thanthratey
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt chartsVARSHA RUSTAGI
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALVismay Shah
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart Nicola2903
 
BOT MODEL.pdf
BOT MODEL.pdfBOT MODEL.pdf
BOT MODEL.pdfvsballa1
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERTPulchowk Campus
 
5 principles of construction project management
5 principles of construction project management5 principles of construction project management
5 principles of construction project managementreachfirst01
 

What's hot (20)

Cpm (critical path method)
Cpm (critical path method)Cpm (critical path method)
Cpm (critical path method)
 
Project Management - Critical path method
Project Management - Critical path methodProject Management - Critical path method
Project Management - Critical path method
 
Diagrama Redes PERT CPM
Diagrama Redes PERT CPMDiagrama Redes PERT CPM
Diagrama Redes PERT CPM
 
Use of forward pass and backward pass in primavera
Use of forward pass and backward pass in primaveraUse of forward pass and backward pass in primavera
Use of forward pass and backward pass in primavera
 
PERT and CPM
PERT and CPMPERT and CPM
PERT and CPM
 
Network diagrams
Network diagramsNetwork diagrams
Network diagrams
 
Pert analysis
Pert analysisPert analysis
Pert analysis
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
 
Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path method
 
Project management Pert & cpm
Project management Pert & cpm Project management Pert & cpm
Project management Pert & cpm
 
Critical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/SlacksCritical Path Method: Activities And Events, Float/Slacks
Critical Path Method: Activities And Events, Float/Slacks
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
CPM/PERT and Gantt charts
CPM/PERT and Gantt chartsCPM/PERT and Gantt charts
CPM/PERT and Gantt charts
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIAL
 
The gantt Chart
The gantt Chart The gantt Chart
The gantt Chart
 
BOT MODEL.pdf
BOT MODEL.pdfBOT MODEL.pdf
BOT MODEL.pdf
 
Network Problem CPM & PERT
Network Problem CPM &  PERTNetwork Problem CPM &  PERT
Network Problem CPM & PERT
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
5 principles of construction project management
5 principles of construction project management5 principles of construction project management
5 principles of construction project management
 

Viewers also liked

E governance, gartner's model by bhim upadhyaya
E governance, gartner's model by bhim upadhyayaE governance, gartner's model by bhim upadhyaya
E governance, gartner's model by bhim upadhyayaBhim Upadhyaya
 
Apj abdul kalam's vision of developed nepal nov 2008
Apj abdul kalam's vision of developed nepal nov 2008Apj abdul kalam's vision of developed nepal nov 2008
Apj abdul kalam's vision of developed nepal nov 2008Bhim Upadhyaya
 
My nepal is great ! (mero nepal mahaan)
My nepal is great ! (mero nepal mahaan)My nepal is great ! (mero nepal mahaan)
My nepal is great ! (mero nepal mahaan)Bhim Upadhyaya
 
A vision of prosperous new nepal by bhim upadhyaya 064.11.5
A vision of prosperous new nepal  by bhim upadhyaya 064.11.5A vision of prosperous new nepal  by bhim upadhyaya 064.11.5
A vision of prosperous new nepal by bhim upadhyaya 064.11.5Bhim Upadhyaya
 
जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19
जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19
जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19Bhim Upadhyaya
 
Workshop on Understnding E governance
Workshop on Understnding E governance Workshop on Understnding E governance
Workshop on Understnding E governance Venkat Subbu
 
Final ppg 520 group ppt (group 5)
Final ppg 520 group ppt (group 5)Final ppg 520 group ppt (group 5)
Final ppg 520 group ppt (group 5)litonielts
 
Electronic Transaction Act 2063 (ETA 2063)
Electronic Transaction Act 2063 (ETA 2063)Electronic Transaction Act 2063 (ETA 2063)
Electronic Transaction Act 2063 (ETA 2063)Krishna Pandey
 
FACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTAN
FACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTANFACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTAN
FACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTANMuhammad Ahmad
 
Lesson02_new
Lesson02_newLesson02_new
Lesson02_newshengvn
 
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...CA Technologies
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpasyamputra
 
Education management information system nepal
Education management information system   nepalEducation management information system   nepal
Education management information system nepalMero Campus
 
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)
Boeing  C-17 Critical Path Tooling  ASQ(Oct_11 _R2)Boeing  C-17 Critical Path Tooling  ASQ(Oct_11 _R2)
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)Ron Gill
 
Integrated Marketing Communications
Integrated Marketing CommunicationsIntegrated Marketing Communications
Integrated Marketing CommunicationsJeff Hilton
 

Viewers also liked (20)

The ant story
The ant storyThe ant story
The ant story
 
E governance, gartner's model by bhim upadhyaya
E governance, gartner's model by bhim upadhyayaE governance, gartner's model by bhim upadhyaya
E governance, gartner's model by bhim upadhyaya
 
Rebirth of the_eagle
Rebirth of the_eagleRebirth of the_eagle
Rebirth of the_eagle
 
Apj abdul kalam's vision of developed nepal nov 2008
Apj abdul kalam's vision of developed nepal nov 2008Apj abdul kalam's vision of developed nepal nov 2008
Apj abdul kalam's vision of developed nepal nov 2008
 
My nepal is great ! (mero nepal mahaan)
My nepal is great ! (mero nepal mahaan)My nepal is great ! (mero nepal mahaan)
My nepal is great ! (mero nepal mahaan)
 
A vision of prosperous new nepal by bhim upadhyaya 064.11.5
A vision of prosperous new nepal  by bhim upadhyaya 064.11.5A vision of prosperous new nepal  by bhim upadhyaya 064.11.5
A vision of prosperous new nepal by bhim upadhyaya 064.11.5
 
जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19
जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19
जलस्रोत विकास परिषद्को कार्यविधि तथा गठनविधि 054.08.19
 
Workshop on Understnding E governance
Workshop on Understnding E governance Workshop on Understnding E governance
Workshop on Understnding E governance
 
E gov lecture1
E gov lecture1E gov lecture1
E gov lecture1
 
Final ppg 520 group ppt (group 5)
Final ppg 520 group ppt (group 5)Final ppg 520 group ppt (group 5)
Final ppg 520 group ppt (group 5)
 
Electronic Transaction Act 2063 (ETA 2063)
Electronic Transaction Act 2063 (ETA 2063)Electronic Transaction Act 2063 (ETA 2063)
Electronic Transaction Act 2063 (ETA 2063)
 
Cyber law in nepal and implementation
Cyber law in nepal and implementationCyber law in nepal and implementation
Cyber law in nepal and implementation
 
FACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTAN
FACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTANFACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTAN
FACTORS INFLUENCING THE ADOPTION OF E-GOVERNMENT SERVICES IN PAKISTAN
 
Lesson02_new
Lesson02_newLesson02_new
Lesson02_new
 
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
Pre-Con Ed: Critical Path Analysis with CA Workload Automation (AE) iDash - O...
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpa
 
Education management information system nepal
Education management information system   nepalEducation management information system   nepal
Education management information system nepal
 
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)
Boeing  C-17 Critical Path Tooling  ASQ(Oct_11 _R2)Boeing  C-17 Critical Path Tooling  ASQ(Oct_11 _R2)
Boeing C-17 Critical Path Tooling ASQ(Oct_11 _R2)
 
Critical Path Analysis for a New Product Release
Critical Path Analysis for a New Product ReleaseCritical Path Analysis for a New Product Release
Critical Path Analysis for a New Product Release
 
Integrated Marketing Communications
Integrated Marketing CommunicationsIntegrated Marketing Communications
Integrated Marketing Communications
 

Similar to PERT/CPM Project Management Models

Chap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxChap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxmohammad_bilal
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)Debanjan15
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateSHAZEBALIKHAN1
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementAmit Kumbar
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managersNaganna Chetty
 
time mamangement.ppt
time mamangement.ppttime mamangement.ppt
time mamangement.pptMadhusha15
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4POOJA UDAYAN
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)hannahpepino1
 
[Document] MultiProject analysis with Critical Path Method
[Document] MultiProject analysis with Critical Path Method[Document] MultiProject analysis with Critical Path Method
[Document] MultiProject analysis with Critical Path MethodMichele Palumbo
 

Similar to PERT/CPM Project Management Models (20)

Chap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptxChap 4- CPM & PERT.pptx
Chap 4- CPM & PERT.pptx
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
Chapter 12(cpm pert)
Chapter 12(cpm pert)Chapter 12(cpm pert)
Chapter 12(cpm pert)
 
pert/cpm
pert/cpmpert/cpm
pert/cpm
 
CPM AND PERT
CPM AND PERTCPM AND PERT
CPM AND PERT
 
Pert
PertPert
Pert
 
PERT CPM Intro
PERT CPM IntroPERT CPM Intro
PERT CPM Intro
 
Pert 182
Pert 182Pert 182
Pert 182
 
06 pert cpm
06 pert cpm06 pert cpm
06 pert cpm
 
Critical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel TemplateCritical Path Explained With 7 Q&As and a Free Excel Template
Critical Path Explained With 7 Q&As and a Free Excel Template
 
CPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource managementCPM, Network Analysis A-O-A, A-O-N, Resource management
CPM, Network Analysis A-O-A, A-O-N, Resource management
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
time mamangement.ppt
time mamangement.ppttime mamangement.ppt
time mamangement.ppt
 
Pert & Cpm
Pert & CpmPert & Cpm
Pert & Cpm
 
Pert cpm
Pert cpm Pert cpm
Pert cpm
 
Advanced project management mod 4
Advanced project management mod 4Advanced project management mod 4
Advanced project management mod 4
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
[Document] MultiProject analysis with Critical Path Method
[Document] MultiProject analysis with Critical Path Method[Document] MultiProject analysis with Critical Path Method
[Document] MultiProject analysis with Critical Path Method
 

More from Bhim Upadhyaya

Role of engineers in infrastructure development for the prosperity of nepal ...
Role of engineers  in infrastructure development for the prosperity of nepal ...Role of engineers  in infrastructure development for the prosperity of nepal ...
Role of engineers in infrastructure development for the prosperity of nepal ...Bhim Upadhyaya
 
India's vision and roadmap for development of sanskrit report
India's vision and roadmap for development of sanskrit reportIndia's vision and roadmap for development of sanskrit report
India's vision and roadmap for development of sanskrit reportBhim Upadhyaya
 
Nepal faecal sludge management and regulatory framework 2074
Nepal faecal sludge management and regulatory framework 2074Nepal faecal sludge management and regulatory framework 2074
Nepal faecal sludge management and regulatory framework 2074Bhim Upadhyaya
 
Nepal- Total sanitation guidelines 2073 ministry of water supply and sanitat...
Nepal- Total  sanitation guidelines 2073 ministry of water supply and sanitat...Nepal- Total  sanitation guidelines 2073 ministry of water supply and sanitat...
Nepal- Total sanitation guidelines 2073 ministry of water supply and sanitat...Bhim Upadhyaya
 
जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15
जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15
जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15Bhim Upadhyaya
 
Water resources of nepal- in the context of climate change 2011 by wecs
Water resources of nepal- in the context of climate change 2011 by wecsWater resources of nepal- in the context of climate change 2011 by wecs
Water resources of nepal- in the context of climate change 2011 by wecsBhim Upadhyaya
 
Energy demand projection 2030 a study done by nepal investment board
Energy demand projection 2030  a study done by nepal investment boardEnergy demand projection 2030  a study done by nepal investment board
Energy demand projection 2030 a study done by nepal investment boardBhim Upadhyaya
 
Nepal Energy strategy 2013 by wecs
Nepal Energy strategy 2013 by wecsNepal Energy strategy 2013 by wecs
Nepal Energy strategy 2013 by wecsBhim Upadhyaya
 
National Water Plan Nepal 2005 by WECS
National Water Plan Nepal 2005 by WECSNational Water Plan Nepal 2005 by WECS
National Water Plan Nepal 2005 by WECSBhim Upadhyaya
 
Water Resources Strategy Nepal 2002 by WECs
Water Resources Strategy Nepal 2002 by WECsWater Resources Strategy Nepal 2002 by WECs
Water Resources Strategy Nepal 2002 by WECsBhim Upadhyaya
 
Nepal - energy sector synopsis report 2010- wecs
Nepal - energy sector synopsis report 2010- wecsNepal - energy sector synopsis report 2010- wecs
Nepal - energy sector synopsis report 2010- wecsBhim Upadhyaya
 
Nepal final report on energy sectors vision 2050 ad
Nepal  final report on energy sectors vision 2050 adNepal  final report on energy sectors vision 2050 ad
Nepal final report on energy sectors vision 2050 adBhim Upadhyaya
 
Andhra pradesh(india) sunrise vision 2029 draft by chandrababu naidu
Andhra pradesh(india) sunrise vision 2029 draft by chandrababu naiduAndhra pradesh(india) sunrise vision 2029 draft by chandrababu naidu
Andhra pradesh(india) sunrise vision 2029 draft by chandrababu naiduBhim Upadhyaya
 
Facebook sambad with naya patrika daily push 9th 2071
Facebook sambad with naya patrika daily push 9th 2071Facebook sambad with naya patrika daily push 9th 2071
Facebook sambad with naya patrika daily push 9th 2071Bhim Upadhyaya
 
Ma pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भए
Ma pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भएMa pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भए
Ma pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भएBhim Upadhyaya
 
Gurustrotam in sanskrit and hindi
Gurustrotam in sanskrit and hindiGurustrotam in sanskrit and hindi
Gurustrotam in sanskrit and hindiBhim Upadhyaya
 
Engineering council uk guidance on security for engineers & technicians
Engineering council uk guidance on security for engineers & techniciansEngineering council uk guidance on security for engineers & technicians
Engineering council uk guidance on security for engineers & techniciansBhim Upadhyaya
 
Sankskrit and science by dr raja ramanna
Sankskrit and  science by dr raja ramannaSankskrit and  science by dr raja ramanna
Sankskrit and science by dr raja ramannaBhim Upadhyaya
 
Ayurveda swadeshi chikitsa- part 1 by rajiv dixit
Ayurveda swadeshi chikitsa- part 1 by rajiv dixitAyurveda swadeshi chikitsa- part 1 by rajiv dixit
Ayurveda swadeshi chikitsa- part 1 by rajiv dixitBhim Upadhyaya
 
Ayurveda aapka swasthya aap ke haath by rajiv dixit
Ayurveda aapka swasthya aap ke haath by rajiv dixitAyurveda aapka swasthya aap ke haath by rajiv dixit
Ayurveda aapka swasthya aap ke haath by rajiv dixitBhim Upadhyaya
 

More from Bhim Upadhyaya (20)

Role of engineers in infrastructure development for the prosperity of nepal ...
Role of engineers  in infrastructure development for the prosperity of nepal ...Role of engineers  in infrastructure development for the prosperity of nepal ...
Role of engineers in infrastructure development for the prosperity of nepal ...
 
India's vision and roadmap for development of sanskrit report
India's vision and roadmap for development of sanskrit reportIndia's vision and roadmap for development of sanskrit report
India's vision and roadmap for development of sanskrit report
 
Nepal faecal sludge management and regulatory framework 2074
Nepal faecal sludge management and regulatory framework 2074Nepal faecal sludge management and regulatory framework 2074
Nepal faecal sludge management and regulatory framework 2074
 
Nepal- Total sanitation guidelines 2073 ministry of water supply and sanitat...
Nepal- Total  sanitation guidelines 2073 ministry of water supply and sanitat...Nepal- Total  sanitation guidelines 2073 ministry of water supply and sanitat...
Nepal- Total sanitation guidelines 2073 ministry of water supply and sanitat...
 
जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15
जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15
जल तथा उर्जा आयोग गठनको गठन आदेश राजपत्र 049.3.15
 
Water resources of nepal- in the context of climate change 2011 by wecs
Water resources of nepal- in the context of climate change 2011 by wecsWater resources of nepal- in the context of climate change 2011 by wecs
Water resources of nepal- in the context of climate change 2011 by wecs
 
Energy demand projection 2030 a study done by nepal investment board
Energy demand projection 2030  a study done by nepal investment boardEnergy demand projection 2030  a study done by nepal investment board
Energy demand projection 2030 a study done by nepal investment board
 
Nepal Energy strategy 2013 by wecs
Nepal Energy strategy 2013 by wecsNepal Energy strategy 2013 by wecs
Nepal Energy strategy 2013 by wecs
 
National Water Plan Nepal 2005 by WECS
National Water Plan Nepal 2005 by WECSNational Water Plan Nepal 2005 by WECS
National Water Plan Nepal 2005 by WECS
 
Water Resources Strategy Nepal 2002 by WECs
Water Resources Strategy Nepal 2002 by WECsWater Resources Strategy Nepal 2002 by WECs
Water Resources Strategy Nepal 2002 by WECs
 
Nepal - energy sector synopsis report 2010- wecs
Nepal - energy sector synopsis report 2010- wecsNepal - energy sector synopsis report 2010- wecs
Nepal - energy sector synopsis report 2010- wecs
 
Nepal final report on energy sectors vision 2050 ad
Nepal  final report on energy sectors vision 2050 adNepal  final report on energy sectors vision 2050 ad
Nepal final report on energy sectors vision 2050 ad
 
Andhra pradesh(india) sunrise vision 2029 draft by chandrababu naidu
Andhra pradesh(india) sunrise vision 2029 draft by chandrababu naiduAndhra pradesh(india) sunrise vision 2029 draft by chandrababu naidu
Andhra pradesh(india) sunrise vision 2029 draft by chandrababu naidu
 
Facebook sambad with naya patrika daily push 9th 2071
Facebook sambad with naya patrika daily push 9th 2071Facebook sambad with naya patrika daily push 9th 2071
Facebook sambad with naya patrika daily push 9th 2071
 
Ma pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भए
Ma pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भएMa pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भए
Ma pradhanmantri bhayeko bhaye as pub nayapatrika म प्रम भएको भए
 
Gurustrotam in sanskrit and hindi
Gurustrotam in sanskrit and hindiGurustrotam in sanskrit and hindi
Gurustrotam in sanskrit and hindi
 
Engineering council uk guidance on security for engineers & technicians
Engineering council uk guidance on security for engineers & techniciansEngineering council uk guidance on security for engineers & technicians
Engineering council uk guidance on security for engineers & technicians
 
Sankskrit and science by dr raja ramanna
Sankskrit and  science by dr raja ramannaSankskrit and  science by dr raja ramanna
Sankskrit and science by dr raja ramanna
 
Ayurveda swadeshi chikitsa- part 1 by rajiv dixit
Ayurveda swadeshi chikitsa- part 1 by rajiv dixitAyurveda swadeshi chikitsa- part 1 by rajiv dixit
Ayurveda swadeshi chikitsa- part 1 by rajiv dixit
 
Ayurveda aapka swasthya aap ke haath by rajiv dixit
Ayurveda aapka swasthya aap ke haath by rajiv dixitAyurveda aapka swasthya aap ke haath by rajiv dixit
Ayurveda aapka swasthya aap ke haath by rajiv dixit
 

Recently uploaded

Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........LeaCamillePacle
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.arsicmarija21
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
ROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint PresentationROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint PresentationAadityaSharma884161
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxsqpmdrvczh
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 

Recently uploaded (20)

Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
ROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint PresentationROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint Presentation
 
Romantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptxRomantic Opera MUSIC FOR GRADE NINE pptx
Romantic Opera MUSIC FOR GRADE NINE pptx
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 

PERT/CPM Project Management Models

  • 1. PERT/CPM Models for Project Management
  • 2. Agenda What is Project Management Discuss PERT/CPM Motivating Case Study: The Reliable Construction Company Ways of Finding the Critical Path Considering Time-Cost Trade-Offs
  • 3. What is Project Management Project management can be defined as the coordination of activities with the potential use of many organizations, both internal and external to the business, in order to conduct a large scale project from beginning to end. There are two management science techniques that are used for project management: Program and Evaluation Review Technique (PERT) Critical Path Method (CPM)
  • 4. PERT/CPM PERT PERT was designed to examine projects from the standpoint of uncertainty. CPM CPM was designed to examine projects from the standpoint of costs. PERT and CPM techniques have been combined over time. PERT and CPM both rely heavily on the use of networks to help plan and display the coordination of all the activities for a project.
  • 5. The Reliable Construction Company Reliable has just secured a contract to construct a new plant for a major manufacturer. The contract is for $5.4 million to cover all costs and any profits. The plant must be finished in a year. A penalty of $300,000 will be assessed if Reliable does not complete the project within 47 weeks. A bonus of $150,000 will be paid to Reliable if the plant is completed within 40 weeks.
  • 6. Needed Terminology Activity A distinct task that needs to be performed as part of the project. Start Node This is a node that represents the beginning of the project. Finish Node This node represents the end of the project.
  • 7. Needed Terminology Cont. Immediate Predecessor These are activities that must be completed by no later than the start time of the given activity. Immediate Successor Given the immediate predecessor of an activity, this activity becomes the immediate successor of each of these immediate predecessors. If an immediate successor has multiple immediate predecessors, then all must be finished before an activity can begin.
  • 8. Activity List for Reliable Construction
  • 9. Questions Needed to be Answered How can the project be displayed graphically? How much time is required to finish the project if no delays occur? When is earliest start and finish times for each activity if no delays occur? What activities are critical bottleneck activities where delays must be avoided to finish the project on time?
  • 10. Questions Needed to be Answered Cont. For non bottleneck activities, how much can an activity be delayed and yet still keep the project on time? What is the probability of completing the project by the deadline? What is the least amount of money needed to expedite the project to obtain the bonus? How should costs be monitored to keep the project within budget?
  • 11. Project Network A project network is a network diagram that uses nodes and arcs to represent the progression of the activities is a project from start to finish. Three pieces of information needed: Activity information Precedence relationship Time information
  • 12. Project Network Cont. Two types of project networks Activity-on-Arc (AOA) On this diagram, the activity is represented on an arc, while a node is used to separate an activity from its immediate predecessors. Activity-on-Node (AON) On this diagram, the activity is represented by the node, while the arc is used to showed the precedence relationship between the activities.
  • 13.
  • 14. Microsoft Project Visual Diagram: Gantt Chart
  • 15. Scheduling Using PERT/CPM A path through a project network is a route that follows a set of arcs from the start node to the finish node. The length of a path is defined as the sum of the durations of the activities of the path. What are the paths and their corresponding lengths for Reliable?
  • 16. Critical Path This is the path that has the longest length through the project. The shortest time that a project can conceivably be finished is the critical path. Why?
  • 17. More Terminology Earliest start time of an activity (ES) The time at which an activity will begin if there are no delays in a project. Earliest finish time of an activity (EF) The time at which an activity will finish if there are no delays in a project. Latest start time of an activity (LS) The latest possible time that an activity can start without delaying the project.
  • 18. More Terminology Cont. Latest finish time of an activity (LF) The latest possible time that an activity can be completed without delaying the project. Forward pass The process of moving through a project from start to finish to determine the earliest start and finish times for the activities in the project.
  • 19. More Terminology Cont. Backward pass The process of moving through a project from finish to start to determine the latest start and finish times for the activities in the project. Slack for an activity The amount of time that a particular activity can be delayed without delaying the whole project. It is calculated by taking the difference between the latest finish time with the earliest finish time.
  • 20. More Terminology Cont. Earliest start time rule The earliest start time for an activity is equal to the largest of the earliest finish times of its immediate predecessors. Latest finish time rule The latest finish time is equal to the smallest of the latest start times of its immediate successors.
  • 21. Procedure for Obtaining Earliest Times Step 1: For the activity that starts the project, assign an earliest start time of zero, i.e., ES=0. Step 2: For each activity whose ES has just been obtained, calculate its earliest finish time as ES plus duration of the activity. Step 3: For each new activity whose immediate predecessors have EF values, obtain its ES by using the earliest start time rule.
  • 22. Procedure for Obtaining Earliest Times Cont. Step 4: Apply step 2 to calculate EF. Step 5: Repeat step 3 until ES and EF have been obtained for all activities including the finish node.
  • 23. Procedure for Obtaining Latest Times Step 1: For each of the activities that together complete the project, set its latest finish time equal to the earliest finish time of the finish node. Step 2: For each activity whose LF value has just been obtained, calculate its latest start time as LS equals LF minus the duration of the activity.
  • 24. Procedure for Obtaining Latest Times Cont. Step 3: For each new activity whose immediate successors now have LS values, obtain its LF by applying the latest finish time rule. Step 4: Apply step 2 to calculate its LS. Step 5: Repeat step 3 until LF and LS have been obtained for all activities.
  • 25.
  • 26. Ways of Finding the Critical Path Examine all the paths and find the path with the maximum length. Calculate the slack for an activity. If the slack is zero, it is on the critical path. If the slack is positive, it is not on the critical path.
  • 27. Time-Cost Trade-Offs Reliable had an incentive bonus of $150,000 to finish the project in 40 weeks. Is it worth while for Reliable to speed-up the project?
  • 28. Crashing Crashing an activity refers to taking on extra expenditures in order to reduce the duration of an activity below its expected value. Crashing a project refers to crashing a number of activities to reduce the duration of the project.
  • 29. CPM Method of Time-Cost Trade-Offs This is a method concerned with whether it is worthwhile to crash activities to reduce the anticipated duration of the project to a desired value. This assumes that there is a trade-off between time and cost that has an inverse relationship.
  • 30. More Terminology Normal Point is the time and cost of an activity when it is performed in a normal way. Crash point show the time and cost when the activity is fully crashed.
  • 31. Graph of Normal and Crash Points
  • 32. Marginal Cost Analysis It is a method of using the marginal cost of crashing individual activities on the current critical path to determine the least expensive way of reducing the project duration to an acceptable level. This method requires you to calculate the cost per desired time unit and compare each cost with the other costs.
  • 33.
  • 34. Marginal Cost Analysis Cont. Once the marginal cost for crashing each activity has been conducted, you next want to choose the crashing that has the smallest marginal cost. Next, calculate the effect that the crash has on each path. Note: Crashing can potentially cause another path to become a critical path.
  • 35. Solving Crashing Problems Using LP There are three decisions to be made: The start time of each activity The reduction in each activity due to crashing The finish time of the project LP model will be examined in class.