SlideShare a Scribd company logo
PROJECT MANAGEMENT
CPM AND PERT OF NETWORK ANALYSIS
BY
INDRAKUMAR R PADWANI
BE MECHANICAL MBA MARKETING .PGDCA
LECTURER IN MECHANICAL ENGG DEPT
GOVERNMENT POLYTECHNIC GODHRA
GUJARAT
 A PROJECT IS AN ACTIVITIES PERFORM IN A
SEQUENCE HAVING RESOURCES FOR
GENERATING SOME OUTPUT.THEY INCORPORATE
THE STAGES FROM DESIGNING TO COMPLETION
OF PROJECT
PROJECT MANGEMENT INVOLVES
ISSUES LIKE SCHEDULING,ACTIVITIES
ALLOCATING RESOURCES ETC.
 THERE ARE TWO METHODS FREQUENTLY USED
FOR NETWORK PLANNING
 CPM----- CRITICAL PATH METHOD
 PERT-----PROGRAMME EVALUATION AND REVIEW
TECHNIQUES
 CPM AND PERT ARE THE CRUCIAL TECHNIQUES
WHICH ARE WIDELY USED IN MANAGING COMPLEX
PROJECTS HAVING SEVERAL SEQUENTIAL AND
CONCURRENT ACTIVITIES
 CPM AND PERT ARE APPLICABLE TO ALL ACTIVITIES
LIKE SETTING UP A BUSINESS,LAUNCHING A NEW
PRODUCT.
 ACTIVITY --- IT IS A DISTINET PART OF A PROJECT
CONSUMING SOME RESOURCES AND TIME FOR ITS
COMPLETION.FOR EXAMPLE IN MECHANICAL UNIT
SUCH AS DRILLING A HOLE.ETC
 EVENT---- IT IS THE STARTING OR END POINT OF
AN ACTIVITY.IT CAN BE SAID AS BEGINNING AND
COMPLETION POINTS OF AN PROJECTS.
 PREDECESSOR ACTIVITY----- IT IS AN ACTIVITY THAT
MUST OCCURS BEFORE ANOTHER ACTIVITY IN THE
PROJECT.
 SUCCESSOR ACTIVITY---- IT IS THE ACTIVITY THAT
MUST OCCUR AFTER ANOTHER ACTIVITY IN THE
PROJECT.
 CONCURRENT OR PARALLEL ACTIVITYS ----- TWO
OR MORE ACTIVITIES CAN BE STARTED AT THE
SAME TIME AND THESE ARE CALLED PARALLEL
ACTIVITIES.
 CRITICAL ACTIVITIES -----THESE ARE THE
ACTIVITIES ON WHICH OVERALL PROJECTS
COMPLETION TIME DEPENDS.
 EPO---- EPO MEANS EARLIEST POSSIBLE
OCCURRENCE.IT IS ALSO KNOWN AS EFT(EARLIST
FINISH TIME ).IT IS OBTAINED AS EARLIST START
TIME(EST)+ DURATION OF THAT ACTIVITY.
 LPO ------ LPO MEANS LATEST POSSIBLE
OCCURRENCE.IT IS ALSO KNOWN AS LFT (LATEST
FINISH TIME ) LFT+ DURATION OF THAT ACTIVITY.
 FLOAT AND SLACK ----- FLOAT REPRESENT THE
MARGIN OF EXTRA TIME WHICH DO NOT RESULT
INTO DELAY OF THE PROJECT COMPLETION.IT IS
CALCULATED AS LS-ES OR LPO-EPO
 DUMMY ACTIVITY----- DUMMY ACTIVITY DO NOT
CONSUME ANY RESOURCE AND TIME.IT IS USED TO
COMPLETE OR FULFIL THE COMPLETE
PRESENTATION OF INTERRELATIONSHIP OF ALL
ACTIVITIES.
 ACTIVITY IS REPRESENTED BY ARROW
 EVENT IS REPRESENTED BY ⃝ (NODE )
 DUMMY −IS REPRESENTED BY ---------- DOTTED
LINE
FIG SHOWS ACTIVITIES AND EVENTS
Tailevent Headevent
Activity
Start Completion
1 1 2
4
3
5 6
A
B
D
C
E
ACTIVITY DESCRIPTION
A Cutting Plates
B Purchasing Nuts
C Purchasing Bolts
D Drilling Hole
E Assembly Plates with Nuts
and Bolts
Here B,C,D are the parallel activities and
successor activity of A.
Activity joining Nodes 4-5 and 3-5 are dummy
activities drawn just to complete network
diagram.
Activity D is predecessor of E. Since drilling
must be done first to insert bolt into Plate for
assemblies.
 PREPARE A LIST OF ACTIVITIES REQUIRED TO
COMPLETE THE PROJECT.
 INDICATE INITIAL EVENT AT LEFT HAND SIDE BY
NODE.
 INDICATE ACTIVITY BY ARROW,JOINING TWO
EVENTS.
 DETERMINE
PRECEDDING,SUCCEEDING,CONCURRENT
ACTIVITIES
 PERT IS A SPECIALISED TECHNIQUE OF MANAGING THE
HIGHLY SPECIALIZED PROJECT.
 THE TIME DURATION OF EACH ACTIVITY IS DETERMINED
WITH THREE PROBABILISTIC MEASURES
 OPTIMISTIC TIME (to)
 MOST LIKELY TIME (tm)
 PESSIMISTIC TIME (tp)
 EXPECTED TIME IS CALCULATED BY
te = t0 + 4tm + tp
6
CPM PEERT
IT IS ACTIVITY ORIENTED IT IS EVENT ORIENTED
HERE TIME ESTIMATES ARE
DETERMISTIC
HERE TIME ESTIMATES ARE
PROBALISTIC
ACTIVITIES ARE DIVIDED INTO
CRITICAL AND NON CRITICAL
CATEGORY
HERE SUCH DIVISION IS NOT
POSSIBLE
CPM USED FOR CONSTRUCTION
PROJECT
PERT USED FOR R&D PROJECTS
ACTIVITY DURATION (DAYS ) PREDECESSORS
A 8 ----
B 4 ----
C 6 ----
D 10 A
E 6 B
F 8 C
G 4 D,E,F
1 3
2
4
5 6
B
C
E
A
G
6
4
8
6
F
8
D
10
4
Critical Path A-D-G
= 8 +10 +4
= 22 Days
ACTIVIT
Y
DURATIO
N
EST LST EFT LFT FLOAT
LST-EST
OR
LFT-EFT
A 8 0 0 8 8 0
B 4 0 8 4 12 8
C 6 0 4 6 10 4
D 10 8 8 18 18 0
E 6 4 12 10 18 8
F 8 6 10 14 18 4
G 4 18 18 22 22 0
 EST ---- IT IS THE EARLIEST TIME BY WHICH AN
ACTIVITY CAN BE STARTED.
 LST---- IT IS THE LATEST POSSIBLE TIME BY WHICH
ANY ACTIVITY CAN START WITHOUT DELAYING THE
PROJECT COMPLETION DATE.
 IT IS CALCULATED BY MOVING BACKWARD
DIRECTION IN NETWORK DIAGRAM
PROJECT COMPLETION T IME IS 22 DAYS
BY FOLLOWING NETWORK DIAGRAM WE CAN SOLVE THE FOLLOWING
DIAGRAMS
1.LST
FOR G= 22-4
=18 DAYS FOR C =22-(6+8+4)
FOR F =22-(4+8) =22-18
= 22-12 =04
= 10DAYS FOR B = 22-(4+6+4)
FOR E =22-(6+4) =22-14
=22-10 =08
=12 FOR A= 22-(8+10+4)
FOR D =22-(10+4) =22-22
=22-14 =0
=08
 TO FIND OUT LFT WE CAN SOLVE BY
 LFT= LST + DURATION OF THAT ACTIVITY.
 FOR A = 0+8=08
 FOR B=08+04=12
 FORC =04+06=10
 FOR D= 08+10 =18
 FOR E= 12+6=18
 FOR F=10+8=18
 FOR G=18+04=22
 TO CALCULATE EFT =EST+ DURATION OF THAT ACTIVITY
 FOR A 08+00= 08
 FOR B 00+04=04
 FOR C 00+06=06
 FOR D 08+10=18
 FOR E 06+04=10
 FOR F 08+06=14
 FOR G 18+04=22
 D AND G ARE HAVING 0 SLACKS BECAUSE THEY ARE ON
CRITICAL PATH.THAT MEANS THESE ACTIVITIES SHOULD NOT
BE DELAYED TO COMPLETE THE PROJECT IN TIME.
 CRITICAL PATH HAVE ZERO FLOAT SO THAT PROJECT CAN
NOT BE DELAYED IN TIME.
CPM AND PERT NETWORK DIAGRAM

More Related Content

What's hot

Introduction to UML
Introduction to UMLIntroduction to UML
Software Metrics
Software MetricsSoftware Metrics
Software Metrics
swatisinghal
 
4 p’s of management spectrum and the w5hh principle
4 p’s of management spectrum and the w5hh principle4 p’s of management spectrum and the w5hh principle
4 p’s of management spectrum and the w5hh principle
Mohammad Hafiz-Al-Masud
 
Statement of stochastic programming problems
Statement of stochastic programming problemsStatement of stochastic programming problems
Statement of stochastic programming problems
SSA KPI
 
Dijkstra's Algorithm
Dijkstra's Algorithm Dijkstra's Algorithm
Dijkstra's Algorithm
Rashik Ishrak Nahian
 
Koningsberg bridge problem
Koningsberg  bridge  problemKoningsberg  bridge  problem
Koningsberg bridge problem
Sudiksha Joshi
 
N queen problem
N queen problemN queen problem
N queen problem
Ridhima Chowdhury
 
Software engineering srs, dfd
Software engineering srs, dfdSoftware engineering srs, dfd
Software engineering srs, dfd
Dr. Anthony Vincent. B
 
Loc and function point
Loc and function pointLoc and function point
Loc and function point
Mitali Chugh
 
Merge sort
Merge sortMerge sort
Merge sort
Rojin Khadka
 
Shortest Path in Graph
Shortest Path in GraphShortest Path in Graph
Shortest Path in Graph
Dr Sandeep Kumar Poonia
 
Software project planning
Software project planningSoftware project planning
Software project planning
rajvir_kaur
 
Branch and bound
Branch and boundBranch and bound
Branch and bound
Nv Thejaswini
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project Management
Reetesh Gupta
 
15 puzzle problem using branch and bound
15 puzzle problem using branch and bound15 puzzle problem using branch and bound
15 puzzle problem using branch and bound
Abhishek Singh
 
Prim's algorithm
Prim's algorithmPrim's algorithm
Prim's algorithm
Pankaj Thakur
 
Knapsack problem using greedy approach
Knapsack problem using greedy approachKnapsack problem using greedy approach
Knapsack problem using greedy approach
padmeshagrekar
 
Lecture4 requirement engineering
Lecture4 requirement engineeringLecture4 requirement engineering
Lecture4 requirement engineering
Shahid Riaz
 
Spm unit 1
Spm unit 1Spm unit 1
Spm unit 1
sweetyammu
 
PRESCRIPTIVE PROCESS MODEL(SOFTWARE ENGINEERING)
PRESCRIPTIVE PROCESS MODEL(SOFTWARE ENGINEERING)PRESCRIPTIVE PROCESS MODEL(SOFTWARE ENGINEERING)
PRESCRIPTIVE PROCESS MODEL(SOFTWARE ENGINEERING)
IrtazaAfzal3
 

What's hot (20)

Introduction to UML
Introduction to UMLIntroduction to UML
Introduction to UML
 
Software Metrics
Software MetricsSoftware Metrics
Software Metrics
 
4 p’s of management spectrum and the w5hh principle
4 p’s of management spectrum and the w5hh principle4 p’s of management spectrum and the w5hh principle
4 p’s of management spectrum and the w5hh principle
 
Statement of stochastic programming problems
Statement of stochastic programming problemsStatement of stochastic programming problems
Statement of stochastic programming problems
 
Dijkstra's Algorithm
Dijkstra's Algorithm Dijkstra's Algorithm
Dijkstra's Algorithm
 
Koningsberg bridge problem
Koningsberg  bridge  problemKoningsberg  bridge  problem
Koningsberg bridge problem
 
N queen problem
N queen problemN queen problem
N queen problem
 
Software engineering srs, dfd
Software engineering srs, dfdSoftware engineering srs, dfd
Software engineering srs, dfd
 
Loc and function point
Loc and function pointLoc and function point
Loc and function point
 
Merge sort
Merge sortMerge sort
Merge sort
 
Shortest Path in Graph
Shortest Path in GraphShortest Path in Graph
Shortest Path in Graph
 
Software project planning
Software project planningSoftware project planning
Software project planning
 
Branch and bound
Branch and boundBranch and bound
Branch and bound
 
Introduction to Software Project Management
Introduction to Software Project ManagementIntroduction to Software Project Management
Introduction to Software Project Management
 
15 puzzle problem using branch and bound
15 puzzle problem using branch and bound15 puzzle problem using branch and bound
15 puzzle problem using branch and bound
 
Prim's algorithm
Prim's algorithmPrim's algorithm
Prim's algorithm
 
Knapsack problem using greedy approach
Knapsack problem using greedy approachKnapsack problem using greedy approach
Knapsack problem using greedy approach
 
Lecture4 requirement engineering
Lecture4 requirement engineeringLecture4 requirement engineering
Lecture4 requirement engineering
 
Spm unit 1
Spm unit 1Spm unit 1
Spm unit 1
 
PRESCRIPTIVE PROCESS MODEL(SOFTWARE ENGINEERING)
PRESCRIPTIVE PROCESS MODEL(SOFTWARE ENGINEERING)PRESCRIPTIVE PROCESS MODEL(SOFTWARE ENGINEERING)
PRESCRIPTIVE PROCESS MODEL(SOFTWARE ENGINEERING)
 

Similar to CPM AND PERT NETWORK DIAGRAM

PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
TecnicoItca
 
Spm
SpmSpm
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Siddanna Balapgol
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
kongara
 
Project-Management.ppt
Project-Management.pptProject-Management.ppt
Project-Management.ppt
TecnicoItca
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
IrtizaMalik
 
Operation research's CPM techniques
Operation research's CPM techniques Operation research's CPM techniques
Operation research's CPM techniques
Mohammad Younus
 
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
Siddharth Modi
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
Hafiz JUNAID
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
AynetuTerefe2
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
SAJID ALI RUK
 
Cpmprt
CpmprtCpmprt
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysis
Dr.R. SELVAM
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
Dr. Divya Khandelwal
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
BetshaTizazu2
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
Naganna Chetty
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
Sougata Das
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
Sheetu Goel
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
Deepak Paithankar
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
ahsanrabbani
 

Similar to CPM AND PERT NETWORK DIAGRAM (20)

PROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptxPROJECT-SCHEDULING-pptx.pptx
PROJECT-SCHEDULING-pptx.pptx
 
Spm
SpmSpm
Spm
 
Pertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOLPertcpm projectmanagement SIDDANNA M BALAPGOL
Pertcpm projectmanagement SIDDANNA M BALAPGOL
 
Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02Pertcpm projectmanagement-120628224438-phpapp02
Pertcpm projectmanagement-120628224438-phpapp02
 
Project-Management.ppt
Project-Management.pptProject-Management.ppt
Project-Management.ppt
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
 
Operation research's CPM techniques
Operation research's CPM techniques Operation research's CPM techniques
Operation research's CPM techniques
 
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
2018,sem7,ala,pm,160993119017,160993119018,160993119019,160993119020,16099311...
 
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERSPLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
 
Ch 5.pptx
Ch 5.pptxCh 5.pptx
Ch 5.pptx
 
Lec 09 network scheduling_techniques
Lec 09 network scheduling_techniquesLec 09 network scheduling_techniques
Lec 09 network scheduling_techniques
 
Cpmprt
CpmprtCpmprt
Cpmprt
 
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysis
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Chapter 3.pptx
Chapter 3.pptxChapter 3.pptx
Chapter 3.pptx
 
project management-cpm and pert methods for managers
project management-cpm and pert methods for managersproject management-cpm and pert methods for managers
project management-cpm and pert methods for managers
 
pert-cpm.pptx
pert-cpm.pptxpert-cpm.pptx
pert-cpm.pptx
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
Project Management & Engineering Economics
Project Management & Engineering EconomicsProject Management & Engineering Economics
Project Management & Engineering Economics
 
Network analysis cpm module3 ppt
Network analysis cpm module3 pptNetwork analysis cpm module3 ppt
Network analysis cpm module3 ppt
 

More from INDRAKUMAR PADWANI

A PROJECT REPORT ONBREAK EVEN CHART. by INDRAKUMAR R PADWANI ...
A PROJECT REPORT ONBREAK EVEN CHART. by INDRAKUMAR R PADWANI                 ...A PROJECT REPORT ONBREAK EVEN CHART. by INDRAKUMAR R PADWANI                 ...
A PROJECT REPORT ONBREAK EVEN CHART. by INDRAKUMAR R PADWANI ...
INDRAKUMAR PADWANI
 
A PROJECT REPORT ON BREAK EVEN CHART BY Indrakumar Padwani.pptx
A PROJECT REPORT ON BREAK EVEN CHART BY Indrakumar Padwani.pptxA PROJECT REPORT ON BREAK EVEN CHART BY Indrakumar Padwani.pptx
A PROJECT REPORT ON BREAK EVEN CHART BY Indrakumar Padwani.pptx
INDRAKUMAR PADWANI
 
vegetable cleaning and cutting machine.pdf
vegetable cleaning and cutting machine.pdfvegetable cleaning and cutting machine.pdf
vegetable cleaning and cutting machine.pdf
INDRAKUMAR PADWANI
 
electromagnetic braking system by Indrakumar R Padwani.pdf
electromagnetic braking system by Indrakumar R Padwani.pdfelectromagnetic braking system by Indrakumar R Padwani.pdf
electromagnetic braking system by Indrakumar R Padwani.pdf
INDRAKUMAR PADWANI
 
A project report on Foot Step Power Generation By Indrakumar R Padwani
A project report on Foot Step Power Generation By Indrakumar R PadwaniA project report on Foot Step Power Generation By Indrakumar R Padwani
A project report on Foot Step Power Generation By Indrakumar R Padwani
INDRAKUMAR PADWANI
 
Project report on Geneva operated belt conveyor By Indrakumar R Padwani
Project report on Geneva operated belt conveyor By Indrakumar R PadwaniProject report on Geneva operated belt conveyor By Indrakumar R Padwani
Project report on Geneva operated belt conveyor By Indrakumar R Padwani
INDRAKUMAR PADWANI
 
Project report on Screw jack - By Indrakumar R Padwani
Project report on Screw jack - By Indrakumar R PadwaniProject report on Screw jack - By Indrakumar R Padwani
Project report on Screw jack - By Indrakumar R Padwani
INDRAKUMAR PADWANI
 
Screw jack 17
Screw jack 17Screw jack 17
Screw jack 17
INDRAKUMAR PADWANI
 
Performance testing of IC engine
Performance testing of IC enginePerformance testing of IC engine
Performance testing of IC engine
INDRAKUMAR PADWANI
 
Thermodynamics process sand mollier chart
Thermodynamics process sand mollier chartThermodynamics process sand mollier chart
Thermodynamics process sand mollier chart
INDRAKUMAR PADWANI
 
Human resources management
Human resources managementHuman resources management
Human resources management
INDRAKUMAR PADWANI
 
A project report on network diagram
A project report on network diagramA project report on network diagram
A project report on network diagram
INDRAKUMAR PADWANI
 

More from INDRAKUMAR PADWANI (12)

A PROJECT REPORT ONBREAK EVEN CHART. by INDRAKUMAR R PADWANI ...
A PROJECT REPORT ONBREAK EVEN CHART. by INDRAKUMAR R PADWANI                 ...A PROJECT REPORT ONBREAK EVEN CHART. by INDRAKUMAR R PADWANI                 ...
A PROJECT REPORT ONBREAK EVEN CHART. by INDRAKUMAR R PADWANI ...
 
A PROJECT REPORT ON BREAK EVEN CHART BY Indrakumar Padwani.pptx
A PROJECT REPORT ON BREAK EVEN CHART BY Indrakumar Padwani.pptxA PROJECT REPORT ON BREAK EVEN CHART BY Indrakumar Padwani.pptx
A PROJECT REPORT ON BREAK EVEN CHART BY Indrakumar Padwani.pptx
 
vegetable cleaning and cutting machine.pdf
vegetable cleaning and cutting machine.pdfvegetable cleaning and cutting machine.pdf
vegetable cleaning and cutting machine.pdf
 
electromagnetic braking system by Indrakumar R Padwani.pdf
electromagnetic braking system by Indrakumar R Padwani.pdfelectromagnetic braking system by Indrakumar R Padwani.pdf
electromagnetic braking system by Indrakumar R Padwani.pdf
 
A project report on Foot Step Power Generation By Indrakumar R Padwani
A project report on Foot Step Power Generation By Indrakumar R PadwaniA project report on Foot Step Power Generation By Indrakumar R Padwani
A project report on Foot Step Power Generation By Indrakumar R Padwani
 
Project report on Geneva operated belt conveyor By Indrakumar R Padwani
Project report on Geneva operated belt conveyor By Indrakumar R PadwaniProject report on Geneva operated belt conveyor By Indrakumar R Padwani
Project report on Geneva operated belt conveyor By Indrakumar R Padwani
 
Project report on Screw jack - By Indrakumar R Padwani
Project report on Screw jack - By Indrakumar R PadwaniProject report on Screw jack - By Indrakumar R Padwani
Project report on Screw jack - By Indrakumar R Padwani
 
Screw jack 17
Screw jack 17Screw jack 17
Screw jack 17
 
Performance testing of IC engine
Performance testing of IC enginePerformance testing of IC engine
Performance testing of IC engine
 
Thermodynamics process sand mollier chart
Thermodynamics process sand mollier chartThermodynamics process sand mollier chart
Thermodynamics process sand mollier chart
 
Human resources management
Human resources managementHuman resources management
Human resources management
 
A project report on network diagram
A project report on network diagramA project report on network diagram
A project report on network diagram
 

Recently uploaded

Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
IJECEIAES
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
HODECEDSIET
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
KrishnaveniKrishnara1
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
sachin chaurasia
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
Hitesh Mohapatra
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
enizeyimana36
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
JamalHussainArman
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
mamunhossenbd75
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
mamamaam477
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 

Recently uploaded (20)

Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...Advanced control scheme of doubly fed induction generator for wind turbine us...
Advanced control scheme of doubly fed induction generator for wind turbine us...
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.pptUnit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
Unit-III-ELECTROCHEMICAL STORAGE DEVICES.ppt
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
 
Generative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of contentGenerative AI leverages algorithms to create various forms of content
Generative AI leverages algorithms to create various forms of content
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
 
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptxML Based Model for NIDS MSc Updated Presentation.v2.pptx
ML Based Model for NIDS MSc Updated Presentation.v2.pptx
 
Heat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation pptHeat Resistant Concrete Presentation ppt
Heat Resistant Concrete Presentation ppt
 
Engine Lubrication performance System.pdf
Engine Lubrication performance System.pdfEngine Lubrication performance System.pdf
Engine Lubrication performance System.pdf
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 

CPM AND PERT NETWORK DIAGRAM

  • 1. PROJECT MANAGEMENT CPM AND PERT OF NETWORK ANALYSIS BY INDRAKUMAR R PADWANI BE MECHANICAL MBA MARKETING .PGDCA LECTURER IN MECHANICAL ENGG DEPT GOVERNMENT POLYTECHNIC GODHRA GUJARAT
  • 2.  A PROJECT IS AN ACTIVITIES PERFORM IN A SEQUENCE HAVING RESOURCES FOR GENERATING SOME OUTPUT.THEY INCORPORATE THE STAGES FROM DESIGNING TO COMPLETION OF PROJECT
  • 3. PROJECT MANGEMENT INVOLVES ISSUES LIKE SCHEDULING,ACTIVITIES ALLOCATING RESOURCES ETC.
  • 4.  THERE ARE TWO METHODS FREQUENTLY USED FOR NETWORK PLANNING  CPM----- CRITICAL PATH METHOD  PERT-----PROGRAMME EVALUATION AND REVIEW TECHNIQUES
  • 5.  CPM AND PERT ARE THE CRUCIAL TECHNIQUES WHICH ARE WIDELY USED IN MANAGING COMPLEX PROJECTS HAVING SEVERAL SEQUENTIAL AND CONCURRENT ACTIVITIES  CPM AND PERT ARE APPLICABLE TO ALL ACTIVITIES LIKE SETTING UP A BUSINESS,LAUNCHING A NEW PRODUCT.
  • 6.  ACTIVITY --- IT IS A DISTINET PART OF A PROJECT CONSUMING SOME RESOURCES AND TIME FOR ITS COMPLETION.FOR EXAMPLE IN MECHANICAL UNIT SUCH AS DRILLING A HOLE.ETC  EVENT---- IT IS THE STARTING OR END POINT OF AN ACTIVITY.IT CAN BE SAID AS BEGINNING AND COMPLETION POINTS OF AN PROJECTS.  PREDECESSOR ACTIVITY----- IT IS AN ACTIVITY THAT MUST OCCURS BEFORE ANOTHER ACTIVITY IN THE PROJECT.  SUCCESSOR ACTIVITY---- IT IS THE ACTIVITY THAT MUST OCCUR AFTER ANOTHER ACTIVITY IN THE PROJECT.
  • 7.  CONCURRENT OR PARALLEL ACTIVITYS ----- TWO OR MORE ACTIVITIES CAN BE STARTED AT THE SAME TIME AND THESE ARE CALLED PARALLEL ACTIVITIES.  CRITICAL ACTIVITIES -----THESE ARE THE ACTIVITIES ON WHICH OVERALL PROJECTS COMPLETION TIME DEPENDS.  EPO---- EPO MEANS EARLIEST POSSIBLE OCCURRENCE.IT IS ALSO KNOWN AS EFT(EARLIST FINISH TIME ).IT IS OBTAINED AS EARLIST START TIME(EST)+ DURATION OF THAT ACTIVITY.  LPO ------ LPO MEANS LATEST POSSIBLE OCCURRENCE.IT IS ALSO KNOWN AS LFT (LATEST FINISH TIME ) LFT+ DURATION OF THAT ACTIVITY.
  • 8.  FLOAT AND SLACK ----- FLOAT REPRESENT THE MARGIN OF EXTRA TIME WHICH DO NOT RESULT INTO DELAY OF THE PROJECT COMPLETION.IT IS CALCULATED AS LS-ES OR LPO-EPO  DUMMY ACTIVITY----- DUMMY ACTIVITY DO NOT CONSUME ANY RESOURCE AND TIME.IT IS USED TO COMPLETE OR FULFIL THE COMPLETE PRESENTATION OF INTERRELATIONSHIP OF ALL ACTIVITIES.
  • 9.  ACTIVITY IS REPRESENTED BY ARROW  EVENT IS REPRESENTED BY ⃝ (NODE )  DUMMY −IS REPRESENTED BY ---------- DOTTED LINE FIG SHOWS ACTIVITIES AND EVENTS Tailevent Headevent Activity Start Completion
  • 10. 1 1 2 4 3 5 6 A B D C E ACTIVITY DESCRIPTION A Cutting Plates B Purchasing Nuts C Purchasing Bolts D Drilling Hole E Assembly Plates with Nuts and Bolts
  • 11. Here B,C,D are the parallel activities and successor activity of A. Activity joining Nodes 4-5 and 3-5 are dummy activities drawn just to complete network diagram. Activity D is predecessor of E. Since drilling must be done first to insert bolt into Plate for assemblies.
  • 12.  PREPARE A LIST OF ACTIVITIES REQUIRED TO COMPLETE THE PROJECT.  INDICATE INITIAL EVENT AT LEFT HAND SIDE BY NODE.  INDICATE ACTIVITY BY ARROW,JOINING TWO EVENTS.  DETERMINE PRECEDDING,SUCCEEDING,CONCURRENT ACTIVITIES
  • 13.  PERT IS A SPECIALISED TECHNIQUE OF MANAGING THE HIGHLY SPECIALIZED PROJECT.  THE TIME DURATION OF EACH ACTIVITY IS DETERMINED WITH THREE PROBABILISTIC MEASURES  OPTIMISTIC TIME (to)  MOST LIKELY TIME (tm)  PESSIMISTIC TIME (tp)  EXPECTED TIME IS CALCULATED BY te = t0 + 4tm + tp 6
  • 14. CPM PEERT IT IS ACTIVITY ORIENTED IT IS EVENT ORIENTED HERE TIME ESTIMATES ARE DETERMISTIC HERE TIME ESTIMATES ARE PROBALISTIC ACTIVITIES ARE DIVIDED INTO CRITICAL AND NON CRITICAL CATEGORY HERE SUCH DIVISION IS NOT POSSIBLE CPM USED FOR CONSTRUCTION PROJECT PERT USED FOR R&D PROJECTS
  • 15. ACTIVITY DURATION (DAYS ) PREDECESSORS A 8 ---- B 4 ---- C 6 ---- D 10 A E 6 B F 8 C G 4 D,E,F
  • 16. 1 3 2 4 5 6 B C E A G 6 4 8 6 F 8 D 10 4 Critical Path A-D-G = 8 +10 +4 = 22 Days
  • 17. ACTIVIT Y DURATIO N EST LST EFT LFT FLOAT LST-EST OR LFT-EFT A 8 0 0 8 8 0 B 4 0 8 4 12 8 C 6 0 4 6 10 4 D 10 8 8 18 18 0 E 6 4 12 10 18 8 F 8 6 10 14 18 4 G 4 18 18 22 22 0
  • 18.  EST ---- IT IS THE EARLIEST TIME BY WHICH AN ACTIVITY CAN BE STARTED.  LST---- IT IS THE LATEST POSSIBLE TIME BY WHICH ANY ACTIVITY CAN START WITHOUT DELAYING THE PROJECT COMPLETION DATE.  IT IS CALCULATED BY MOVING BACKWARD DIRECTION IN NETWORK DIAGRAM
  • 19. PROJECT COMPLETION T IME IS 22 DAYS BY FOLLOWING NETWORK DIAGRAM WE CAN SOLVE THE FOLLOWING DIAGRAMS 1.LST FOR G= 22-4 =18 DAYS FOR C =22-(6+8+4) FOR F =22-(4+8) =22-18 = 22-12 =04 = 10DAYS FOR B = 22-(4+6+4) FOR E =22-(6+4) =22-14 =22-10 =08 =12 FOR A= 22-(8+10+4) FOR D =22-(10+4) =22-22 =22-14 =0 =08
  • 20.  TO FIND OUT LFT WE CAN SOLVE BY  LFT= LST + DURATION OF THAT ACTIVITY.  FOR A = 0+8=08  FOR B=08+04=12  FORC =04+06=10  FOR D= 08+10 =18  FOR E= 12+6=18  FOR F=10+8=18  FOR G=18+04=22
  • 21.  TO CALCULATE EFT =EST+ DURATION OF THAT ACTIVITY  FOR A 08+00= 08  FOR B 00+04=04  FOR C 00+06=06  FOR D 08+10=18  FOR E 06+04=10  FOR F 08+06=14  FOR G 18+04=22
  • 22.  D AND G ARE HAVING 0 SLACKS BECAUSE THEY ARE ON CRITICAL PATH.THAT MEANS THESE ACTIVITIES SHOULD NOT BE DELAYED TO COMPLETE THE PROJECT IN TIME.  CRITICAL PATH HAVE ZERO FLOAT SO THAT PROJECT CAN NOT BE DELAYED IN TIME.