SlideShare a Scribd company logo
CONSTRUCTION EQUIPMENT
CE-216
Engr M Zeeshan Ahad
INU, CED
EQUIPMENT
INTRODUCTION
One problem an estimator faces is the
selection of equipment suitable to use for a
given project. The equipment must pay for
itself. Unless a piece of equipment will earn
money for the contractor, it should not be
used.
INTRODUCTION
It is impossible for contractors to own all types and sizes of
equipment, the selection of equipment will be primarily
from that which they own. However, new equipment can be
purchased if the cost can be justified
For example, if a piece of equipment costing $15,000 will
save $20,000 on a project, it should be purchased regardless
of whether it will be used on future projects or whether it
can be sold at the end of the current project.
INTRODUCTION
If the equipment is to be used for a time and then will not be needed again for a few weeks,
the estimator should ask the following:
What will be done with it?
Will it be returned to the
main yard?
Is there room to store it on
the project?
If rented, will it be returned
so that the rental charge
will be saved?
Figuring the cost of equipment required for a project presents the same problems to
estimators as figuring labour. It is necessary for the estimator to decide what equipment is
required for each phase of the work and for what length of time it will have to be used.
OPERATING COSTS
The costs of operating the construction equipment should be calculated on the basis
of the working hour since the ownership or rental cost is also a cost per hour.
Included are items such as fuel, grease, oil, electricity, miscellaneous supplies, and
repairs.
Operators’ wages and mobilization costs are not included in equipment operation
costs.
OPERATING COSTS
• Costs for power equipment are usually based on the horsepower of the
equipment. Generally, a gasoline engine will use between 0.06 and 0.07
gallons of gasoline per horsepower per hour when operating at full
capacity
• Fuel costs are calculated using Formula
OPERATING COSTS
When operating, the engine will probably operate at 55 to 80 percent of full capacity, or 55 to 80
percent of its available power will be utilized.
This is known as power utilization and reduces fuel consumption. In addition, it will not be operated for
the full hour.
Typically, equipment is operated between 30 and 50 minutes per hour. This is known as the system
efficiency or use factor and is expressed as a percentage of the hour that the equipment is operating.
For example, 45 minutes per hour would be 75 percent (0.75) and 50 minutes per hour would be 83
percent (0.83).
FUEL COST
What is the estimated fuel cost of a 120-
horsepower pay loader? A job condition
analysis indicates that the unit will operate
about 45 minutes per hour (75 percent) at
about 70 percent of its rated horsepower.
SOLUTION
LUBRICATION
The amount of oil and grease required by any given piece of
equipment varies with the type of equipment and job conditions.
A piece of equipment usually has its oil changed and is greased
every 100 to 150 hours.
Under severe conditions, the equipment may need much more
frequent servicing.
Any oil and grease consumed between oil changes must also be
included in the cost.
TIRES
The cost of tires can be quite high on an hourly basis.
Because the cost of tires is part of the original cost, it is left in when figuring the
cost of interest, but taken out for the cost of repairs and salvage values.
The cost of tires, replacement, repair, and depreciation should be figured
separately.
The cost of the tires is depreciated over the useful life of the tires, and the cost of
repairs is taken as a percentage of the depreciation, based on past experience.
DEPRECIATION
As soon as a piece of equipment is purchased, it begins to decrease
(depreciate) in value.
As the equipment is used on the projects, it begins to wear out, and in a given
amount of time it will have become completely worn out or obsolete.
If an allowance for depreciation is not included in the estimate, there will be no
money set aside to purchase new equipment when the equipment is worn out.
This is not profit, and the money for equipment should not be taken from
profit.
DEPRECIATION
On a yearly basis, for tax purposes, depreciation can be figured in a
number of ways.
But for practical purposes, the total depreciation for any piece of
equipment will be 100 percent of the capital investment minus the
scrap or salvage value, divided by the number of years it will be used.
For estimating depreciation costs, assign the equipment a useful life
expressed in years, hours, or units of production, whichever is the
most appropriate for a given piece of equipment.
INTEREST
Interest rates must be checked by the estimator.
The interest should be charged against the entire cost of the equipment, even
though the contractor paid part of the cost in cash.
Contractors should figure that the least they should get for the use of their money
is the current rate of interest.
Interest is paid on the unpaid balance. On this basis, the balance due begins at the
cost price and decreases to virtually nothing when the last payment is made.
Since the balance on which interest is being charged ranges from 100 to 0 percent,
the average amount on which the interest is paid is 50 percent of the cost.
OWNERSHIP COSTS
To estimate the cost of using a piece of equipment owned by the
contractor, the estimator must consider depreciation, major repairs,
and overhaul as well as interest, insurance, taxes, and storage.
These items are most often taken as a percentage of the initial cost to
the owner.
Also to be added later is the cost for fuel, oil, and tires. The cost to the
owner should include all freight costs, sales taxes, and preparation
charges
DEPRECIATION METHOD
• In this method of finding the value of the building, the method of depreciation is
used to find the value of the building.
• This value is the value of the building at a particular life of a building based on the
percentage of depreciation at that age.
• The total cost of the property is found when the cost of the land is included in the
value.
• The formula for acquiring the value of the building through the method of
depreciation is as follow:
D = p (100 – rd/100)^n
27Engr. Muhammad Zeeshan Ahad
DEPRECIATION METHOD
where
D = The Depreciated value of the building structure after n years
P = cost of new building
rd= fixed percentage of the depreciation
n = Present age of the building
28Engr. Muhammad Zeeshan Ahad
DEPRECIATION METHOD
• The value of the fixed percentage of depreciation (rd) for different duration of life
of a building is as under
Life of Building Value of rd
100 1.00
75 1.25
50 2.00
25 4.00
20 5.00
29Engr. Muhammad Zeeshan Ahad
DEPRECIATION METHOD
• Example : Determine the present value of a property having a land area of 250
sq.m. life of the building is 20 years. Plinth area 175 sq.m @ Rs.2000/sq.m
• Solution
Plinth area = 175 sq.m
Rate of construction= Rs. 2000/sq.m
cost of new Building= P = 175 * 2000 Rs.3,50,000
life of building = n = 20 years
Percentage of Depreciation = rd = 5.00
30Engr. Muhammad Zeeshan Ahad
DEPRECIATION METHOD
depreciated value of building = D = p (100 – rd/100)^n
=D = 350000 (100 – 5.00/100)^20
=Rs. 1,25,470/-
31Engr. Muhammad Zeeshan Ahad
End of Lecture

More Related Content

What's hot

Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
ALI HYDER GADHI
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
Aravind Samala
 
L1 Planning for Earthwork Construction
L1 Planning for Earthwork ConstructionL1 Planning for Earthwork Construction
L1 Planning for Earthwork Construction
Don W. Lewis
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
Kabilan Kabi
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity
SSudhaVelan
 

What's hot (20)

Equipments used for aggregate production_Advanced Construction Technology (Se...
Equipments used for aggregate production_Advanced Construction Technology (Se...Equipments used for aggregate production_Advanced Construction Technology (Se...
Equipments used for aggregate production_Advanced Construction Technology (Se...
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
Chapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipmentsChapter 8 introduction to construction equipments
Chapter 8 introduction to construction equipments
 
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Rate analysis
Rate analysisRate analysis
Rate analysis
 
Construction equipments - Introduction and Classification
Construction equipments - Introduction and ClassificationConstruction equipments - Introduction and Classification
Construction equipments - Introduction and Classification
 
Introduction to construction project management
Introduction to construction project managementIntroduction to construction project management
Introduction to construction project management
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
L1 Planning for Earthwork Construction
L1 Planning for Earthwork ConstructionL1 Planning for Earthwork Construction
L1 Planning for Earthwork Construction
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Resources of Construction Industry
Resources of Construction IndustryResources of Construction Industry
Resources of Construction Industry
 
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDFCTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
CTEP - UNIT-V - CONSTRUCTION EQUIPMENTS PDF
 
labour vs machionary (cep lecture)
labour vs machionary (cep lecture)labour vs machionary (cep lecture)
labour vs machionary (cep lecture)
 
Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity Heavy Construction Equipment Productivity
Heavy Construction Equipment Productivity
 
What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 

Similar to Construction equipment

Similar to Construction equipment (20)

Construction equipment need and factors-nrc
Construction equipment need and factors-nrcConstruction equipment need and factors-nrc
Construction equipment need and factors-nrc
 
CH 1.pptx
CH 1.pptxCH 1.pptx
CH 1.pptx
 
Rate analysis brief
Rate analysis briefRate analysis brief
Rate analysis brief
 
Accounting Lec#9.pptx
Accounting Lec#9.pptxAccounting Lec#9.pptx
Accounting Lec#9.pptx
 
Depreciation
DepreciationDepreciation
Depreciation
 
Replacement models and maintenance analysis
Replacement models and maintenance analysisReplacement models and maintenance analysis
Replacement models and maintenance analysis
 
Chap5 engeco
Chap5 engecoChap5 engeco
Chap5 engeco
 
Operations REsearch
Operations REsearchOperations REsearch
Operations REsearch
 
Seminar _5.pptx
Seminar _5.pptxSeminar _5.pptx
Seminar _5.pptx
 
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENTOWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
 
Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...
Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...
Investment Appraisal – Asset Replacement Decisions, EAC, Lease vs. Buy, Capit...
 
Replacement Strategies
Replacement StrategiesReplacement Strategies
Replacement Strategies
 
Depreciation with different methods
Depreciation with different methodsDepreciation with different methods
Depreciation with different methods
 
Replacement model
Replacement modelReplacement model
Replacement model
 
POWER PLANT ECONOMICS AND ENVIRONMENTAL CONSIDERATIONS - SNIST
POWER  PLANT  ECONOMICS AND ENVIRONMENTAL  CONSIDERATIONS - SNISTPOWER  PLANT  ECONOMICS AND ENVIRONMENTAL  CONSIDERATIONS - SNIST
POWER PLANT ECONOMICS AND ENVIRONMENTAL CONSIDERATIONS - SNIST
 
life cycle costing.pptx
life cycle costing.pptxlife cycle costing.pptx
life cycle costing.pptx
 
Charging of Engineering Services.pptx
Charging of Engineering Services.pptxCharging of Engineering Services.pptx
Charging of Engineering Services.pptx
 
Finance presentation Depreciation
Finance presentation DepreciationFinance presentation Depreciation
Finance presentation Depreciation
 
Non-Current Assets & Depreciation
Non-Current Assets & DepreciationNon-Current Assets & Depreciation
Non-Current Assets & Depreciation
 
Economic consideration
Economic considerationEconomic consideration
Economic consideration
 

More from Muhammad Zeeshan Ahad (6)

Disaster management cycle
Disaster management cycle Disaster management cycle
Disaster management cycle
 
National Disaster management Policy
National Disaster management PolicyNational Disaster management Policy
National Disaster management Policy
 
Significance of Disaster
Significance of DisasterSignificance of Disaster
Significance of Disaster
 
Concept of Disaster
Concept of DisasterConcept of Disaster
Concept of Disaster
 
Concrete mix design
Concrete mix designConcrete mix design
Concrete mix design
 
Concrete mix design
Concrete mix designConcrete mix design
Concrete mix design
 

Recently uploaded

Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
Kamal Acharya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
Kamal Acharya
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
AbrahamGadissa
 
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdfONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 

Recently uploaded (20)

Pharmacy management system project report..pdf
Pharmacy management system project report..pdfPharmacy management system project report..pdf
Pharmacy management system project report..pdf
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answer
 
Hall booking system project report .pdf
Hall booking system project report  .pdfHall booking system project report  .pdf
Hall booking system project report .pdf
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
 
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data StreamKIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
 
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdfONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
 
Explosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdfExplosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdf
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
IT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data AnalysisIT-601 Lecture Notes-UNIT-2.pdf Data Analysis
IT-601 Lecture Notes-UNIT-2.pdf Data Analysis
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptx
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
 

Construction equipment

  • 1. CONSTRUCTION EQUIPMENT CE-216 Engr M Zeeshan Ahad INU, CED
  • 3. INTRODUCTION One problem an estimator faces is the selection of equipment suitable to use for a given project. The equipment must pay for itself. Unless a piece of equipment will earn money for the contractor, it should not be used.
  • 4. INTRODUCTION It is impossible for contractors to own all types and sizes of equipment, the selection of equipment will be primarily from that which they own. However, new equipment can be purchased if the cost can be justified For example, if a piece of equipment costing $15,000 will save $20,000 on a project, it should be purchased regardless of whether it will be used on future projects or whether it can be sold at the end of the current project.
  • 5. INTRODUCTION If the equipment is to be used for a time and then will not be needed again for a few weeks, the estimator should ask the following: What will be done with it? Will it be returned to the main yard? Is there room to store it on the project? If rented, will it be returned so that the rental charge will be saved? Figuring the cost of equipment required for a project presents the same problems to estimators as figuring labour. It is necessary for the estimator to decide what equipment is required for each phase of the work and for what length of time it will have to be used.
  • 6. OPERATING COSTS The costs of operating the construction equipment should be calculated on the basis of the working hour since the ownership or rental cost is also a cost per hour. Included are items such as fuel, grease, oil, electricity, miscellaneous supplies, and repairs. Operators’ wages and mobilization costs are not included in equipment operation costs.
  • 7. OPERATING COSTS • Costs for power equipment are usually based on the horsepower of the equipment. Generally, a gasoline engine will use between 0.06 and 0.07 gallons of gasoline per horsepower per hour when operating at full capacity • Fuel costs are calculated using Formula
  • 8. OPERATING COSTS When operating, the engine will probably operate at 55 to 80 percent of full capacity, or 55 to 80 percent of its available power will be utilized. This is known as power utilization and reduces fuel consumption. In addition, it will not be operated for the full hour. Typically, equipment is operated between 30 and 50 minutes per hour. This is known as the system efficiency or use factor and is expressed as a percentage of the hour that the equipment is operating. For example, 45 minutes per hour would be 75 percent (0.75) and 50 minutes per hour would be 83 percent (0.83).
  • 9. FUEL COST What is the estimated fuel cost of a 120- horsepower pay loader? A job condition analysis indicates that the unit will operate about 45 minutes per hour (75 percent) at about 70 percent of its rated horsepower.
  • 11. LUBRICATION The amount of oil and grease required by any given piece of equipment varies with the type of equipment and job conditions. A piece of equipment usually has its oil changed and is greased every 100 to 150 hours. Under severe conditions, the equipment may need much more frequent servicing. Any oil and grease consumed between oil changes must also be included in the cost.
  • 12.
  • 13. TIRES The cost of tires can be quite high on an hourly basis. Because the cost of tires is part of the original cost, it is left in when figuring the cost of interest, but taken out for the cost of repairs and salvage values. The cost of tires, replacement, repair, and depreciation should be figured separately. The cost of the tires is depreciated over the useful life of the tires, and the cost of repairs is taken as a percentage of the depreciation, based on past experience.
  • 14.
  • 15. DEPRECIATION As soon as a piece of equipment is purchased, it begins to decrease (depreciate) in value. As the equipment is used on the projects, it begins to wear out, and in a given amount of time it will have become completely worn out or obsolete. If an allowance for depreciation is not included in the estimate, there will be no money set aside to purchase new equipment when the equipment is worn out. This is not profit, and the money for equipment should not be taken from profit.
  • 16. DEPRECIATION On a yearly basis, for tax purposes, depreciation can be figured in a number of ways. But for practical purposes, the total depreciation for any piece of equipment will be 100 percent of the capital investment minus the scrap or salvage value, divided by the number of years it will be used. For estimating depreciation costs, assign the equipment a useful life expressed in years, hours, or units of production, whichever is the most appropriate for a given piece of equipment.
  • 17.
  • 18. INTEREST Interest rates must be checked by the estimator. The interest should be charged against the entire cost of the equipment, even though the contractor paid part of the cost in cash. Contractors should figure that the least they should get for the use of their money is the current rate of interest. Interest is paid on the unpaid balance. On this basis, the balance due begins at the cost price and decreases to virtually nothing when the last payment is made. Since the balance on which interest is being charged ranges from 100 to 0 percent, the average amount on which the interest is paid is 50 percent of the cost.
  • 19.
  • 20. OWNERSHIP COSTS To estimate the cost of using a piece of equipment owned by the contractor, the estimator must consider depreciation, major repairs, and overhaul as well as interest, insurance, taxes, and storage. These items are most often taken as a percentage of the initial cost to the owner. Also to be added later is the cost for fuel, oil, and tires. The cost to the owner should include all freight costs, sales taxes, and preparation charges
  • 21.
  • 22.
  • 23.
  • 24.
  • 25.
  • 26.
  • 27. DEPRECIATION METHOD • In this method of finding the value of the building, the method of depreciation is used to find the value of the building. • This value is the value of the building at a particular life of a building based on the percentage of depreciation at that age. • The total cost of the property is found when the cost of the land is included in the value. • The formula for acquiring the value of the building through the method of depreciation is as follow: D = p (100 – rd/100)^n 27Engr. Muhammad Zeeshan Ahad
  • 28. DEPRECIATION METHOD where D = The Depreciated value of the building structure after n years P = cost of new building rd= fixed percentage of the depreciation n = Present age of the building 28Engr. Muhammad Zeeshan Ahad
  • 29. DEPRECIATION METHOD • The value of the fixed percentage of depreciation (rd) for different duration of life of a building is as under Life of Building Value of rd 100 1.00 75 1.25 50 2.00 25 4.00 20 5.00 29Engr. Muhammad Zeeshan Ahad
  • 30. DEPRECIATION METHOD • Example : Determine the present value of a property having a land area of 250 sq.m. life of the building is 20 years. Plinth area 175 sq.m @ Rs.2000/sq.m • Solution Plinth area = 175 sq.m Rate of construction= Rs. 2000/sq.m cost of new Building= P = 175 * 2000 Rs.3,50,000 life of building = n = 20 years Percentage of Depreciation = rd = 5.00 30Engr. Muhammad Zeeshan Ahad
  • 31. DEPRECIATION METHOD depreciated value of building = D = p (100 – rd/100)^n =D = 350000 (100 – 5.00/100)^20 =Rs. 1,25,470/- 31Engr. Muhammad Zeeshan Ahad