CAVITY WALLINGCAVITY WALLING
OBJECTIVESOBJECTIVES
 EXPLAIN HOW TO MAINTAIN A CLEAN CAVITY
 DESCRIBE WITH THE AID OF A SKETCH GOOD BEDDING
PRACTICE FOR WALL TIES
 COMPARE THE TYPES OF MATERIALS USED
UNDERGROUND
 DESCRIBE HOW TO TREAT AT CILLS AND OPENINGS
 SKETCH FOUR TYPES OF WALL TIE
CAVITY WALLSCAVITY WALLS
 MORE RAIN RESISTANT
 BETTER INSULATED
 DEPENDENT ON GOOD
DESIGN AND
WORKMANSHIP
CAVITY WALLINGCAVITY WALLING
 STANDARD FORM OF EXTERNAL WALLING USED IN
CONSTRUCTION
 TWO SKINS OF WALLING USUALLY 102mm BRICK
EXTERIOR AND 100/125/150 LIGHTWEIGHT BLOCK
INTERNAL
 MINIMUM OF 50mm CAVITY TO BE MAINTAINED
THROUGHOUT CONSTRUCTION
 SKINS JOINED TOGETHER USING NON-CORROSIVE
TIE WIRES FOR STABILITY
CAVITY WALLINGCAVITY WALLING
Internal Blockwork
Damp Proof Membrane
Oversite Concrete
Rain penetrates the
outer leaf but is
unable to bridge the
cavity
TIE WIRES IN CAVITY WALLSTIE WIRES IN CAVITY WALLS
WIND
LOAD
SINGLE
LEAVES
EFFECTIVELY
TIED
LEAVES
DEFLECT
UNDER
LOAD
COMMON TIES USED IN CAVITYCOMMON TIES USED IN CAVITY
WALLINGWALLING
CAVITY WALL TIESCAVITY WALL TIES
CAVITY WALL PROBLEMSCAVITY WALL PROBLEMS
excessive mortar
droppings in cavity
and building up on
wall ties
Deteriorated fish tail wall ties.
GOOD PRACTICE FOR PLACING TIESGOOD PRACTICE FOR PLACING TIES
ENSURE THAT TIES
ARE FIRMLY BEDDED
INTO THE BED JOINTS
AT LEAST 50 mm
NEVER SLOPE TIES TO INNER
LEAF
KEEP TIES HORIZONTAL OR IF UNAVOIDABLE
SLOPE TO OUTER LEAF
MAIN POINTS TO CONSIDERMAIN POINTS TO CONSIDER
 ONLY USE SPECIFIED TIES
 PRESS FIRMLY INTO MORTAR BED
 BED TIES AT LEAST 50mm INTO EACH LEAF
 ENSURE DRIP IS IN CENTRE OF CAVITY
 NEVER INCLINE TIES TOWARDS INNER LEAF
 EXTRA TIES ARE REQUIRED AT JAMBS OF OPENINGS AND UP RAKES
AT GABLES
 NEVER BEND TIES TO SUIT VARIATION IN GAUGE
 KEEP TIES CLEAR OF MORTAR DROPPINGS
 TIES SPACED 900mm HORIZONTALLY AND 450mm VERTICALLY
MAINTAINING A CLEAN CAVITYMAINTAINING A CLEAN CAVITY
CLEAN EXCESS
MORTAR OFF
WHEN
BUILDING
AVOID ROUGH
EDGES INTO
CAVITY
ABOVE D.P.C.
TRAYS
WEEPHOLES AT
900mm CENTRES
CAVITY
BATTEN
KEEP CAVITY
TRAYS AND
TIES CLEAR
OF MORTAR
CAVITY WALLS BELOW GROUNDCAVITY WALLS BELOW GROUND
CONCRETE STRIP
FOUNDATION
HORIZONTAL D.P.C. MIN.
150mm ABOVE G.L.
LEAN MIX CONCRETE TO
RESIST LATERAL
PRESSURE
OPENINGS FOR
SERVICE
DUCTS
SPANNED BY
LINTEL
FACEWORK SET OUT
BELOW GROUND
LEVEL
CAVITY WALLING FORMED BY USE OFCAVITY WALLING FORMED BY USE OF
FOUNDATION BLOCKFOUNDATION BLOCK
1 METRE
G.L.
SECTION THROUGH CAVITY WALL
CAVITY WALL FORMED BY USING SOLIDCAVITY WALL FORMED BY USING SOLID
FOUNDATION BLOCKFOUNDATION BLOCK
G.L.
SOLID FOUNDATION
BLOCKS ARE AVAILABLE
AS LIGHTWEIGHT
BLOCKS. THEY CAN BE
HANDLED BY ONE PERSON
THEY ARE ALSO
AVAILABLE IN HEAVY
CONCRETE. THESE
SHOULD BE LIFTED BY
TWO PERSONS TO AVOID
INJURY
CAVITY DETAIL AT CILL AND OPENINGCAVITY DETAIL AT CILL AND OPENING
ALTERNATE METHOD OF CLOSING CAVITYALTERNATE METHOD OF CLOSING CAVITY
AT REVEALSAT REVEALS
BLOCKWORK
RETURNED TO
OUTER BRICK
LEAF
D.P.C. PLACED
AS A BARRIER
TO RAIN
PENETRATION
CAVITY CLOSERCAVITY CLOSER
CAVITY CLOSER
ALLOWS OPENINGS TO
BE QUICKLY AND
EFFECTIVELY CLOSED
CAVITIES BELOW GROUND (3)CAVITIES BELOW GROUND (3)
D.P.C. MIN
150mm
ABOVE G.L.
Brick

Cavity walling ppoint

  • 1.
    CAVITY WALLINGCAVITY WALLING OBJECTIVESOBJECTIVES EXPLAIN HOW TO MAINTAIN A CLEAN CAVITY  DESCRIBE WITH THE AID OF A SKETCH GOOD BEDDING PRACTICE FOR WALL TIES  COMPARE THE TYPES OF MATERIALS USED UNDERGROUND  DESCRIBE HOW TO TREAT AT CILLS AND OPENINGS  SKETCH FOUR TYPES OF WALL TIE
  • 2.
    CAVITY WALLSCAVITY WALLS MORE RAIN RESISTANT  BETTER INSULATED  DEPENDENT ON GOOD DESIGN AND WORKMANSHIP
  • 3.
    CAVITY WALLINGCAVITY WALLING STANDARD FORM OF EXTERNAL WALLING USED IN CONSTRUCTION  TWO SKINS OF WALLING USUALLY 102mm BRICK EXTERIOR AND 100/125/150 LIGHTWEIGHT BLOCK INTERNAL  MINIMUM OF 50mm CAVITY TO BE MAINTAINED THROUGHOUT CONSTRUCTION  SKINS JOINED TOGETHER USING NON-CORROSIVE TIE WIRES FOR STABILITY
  • 4.
    CAVITY WALLINGCAVITY WALLING InternalBlockwork Damp Proof Membrane Oversite Concrete Rain penetrates the outer leaf but is unable to bridge the cavity
  • 5.
    TIE WIRES INCAVITY WALLSTIE WIRES IN CAVITY WALLS WIND LOAD SINGLE LEAVES EFFECTIVELY TIED LEAVES DEFLECT UNDER LOAD
  • 6.
    COMMON TIES USEDIN CAVITYCOMMON TIES USED IN CAVITY WALLINGWALLING
  • 7.
  • 8.
    CAVITY WALL PROBLEMSCAVITYWALL PROBLEMS excessive mortar droppings in cavity and building up on wall ties Deteriorated fish tail wall ties.
  • 9.
    GOOD PRACTICE FORPLACING TIESGOOD PRACTICE FOR PLACING TIES ENSURE THAT TIES ARE FIRMLY BEDDED INTO THE BED JOINTS AT LEAST 50 mm
  • 10.
    NEVER SLOPE TIESTO INNER LEAF KEEP TIES HORIZONTAL OR IF UNAVOIDABLE SLOPE TO OUTER LEAF
  • 12.
    MAIN POINTS TOCONSIDERMAIN POINTS TO CONSIDER  ONLY USE SPECIFIED TIES  PRESS FIRMLY INTO MORTAR BED  BED TIES AT LEAST 50mm INTO EACH LEAF  ENSURE DRIP IS IN CENTRE OF CAVITY  NEVER INCLINE TIES TOWARDS INNER LEAF  EXTRA TIES ARE REQUIRED AT JAMBS OF OPENINGS AND UP RAKES AT GABLES  NEVER BEND TIES TO SUIT VARIATION IN GAUGE  KEEP TIES CLEAR OF MORTAR DROPPINGS  TIES SPACED 900mm HORIZONTALLY AND 450mm VERTICALLY
  • 13.
    MAINTAINING A CLEANCAVITYMAINTAINING A CLEAN CAVITY CLEAN EXCESS MORTAR OFF WHEN BUILDING AVOID ROUGH EDGES INTO CAVITY ABOVE D.P.C. TRAYS WEEPHOLES AT 900mm CENTRES CAVITY BATTEN KEEP CAVITY TRAYS AND TIES CLEAR OF MORTAR
  • 14.
    CAVITY WALLS BELOWGROUNDCAVITY WALLS BELOW GROUND CONCRETE STRIP FOUNDATION HORIZONTAL D.P.C. MIN. 150mm ABOVE G.L. LEAN MIX CONCRETE TO RESIST LATERAL PRESSURE OPENINGS FOR SERVICE DUCTS SPANNED BY LINTEL FACEWORK SET OUT BELOW GROUND LEVEL
  • 15.
    CAVITY WALLING FORMEDBY USE OFCAVITY WALLING FORMED BY USE OF FOUNDATION BLOCKFOUNDATION BLOCK 1 METRE G.L. SECTION THROUGH CAVITY WALL
  • 16.
    CAVITY WALL FORMEDBY USING SOLIDCAVITY WALL FORMED BY USING SOLID FOUNDATION BLOCKFOUNDATION BLOCK G.L. SOLID FOUNDATION BLOCKS ARE AVAILABLE AS LIGHTWEIGHT BLOCKS. THEY CAN BE HANDLED BY ONE PERSON THEY ARE ALSO AVAILABLE IN HEAVY CONCRETE. THESE SHOULD BE LIFTED BY TWO PERSONS TO AVOID INJURY
  • 17.
    CAVITY DETAIL ATCILL AND OPENINGCAVITY DETAIL AT CILL AND OPENING
  • 18.
    ALTERNATE METHOD OFCLOSING CAVITYALTERNATE METHOD OF CLOSING CAVITY AT REVEALSAT REVEALS BLOCKWORK RETURNED TO OUTER BRICK LEAF D.P.C. PLACED AS A BARRIER TO RAIN PENETRATION
  • 19.
    CAVITY CLOSERCAVITY CLOSER CAVITYCLOSER ALLOWS OPENINGS TO BE QUICKLY AND EFFECTIVELY CLOSED
  • 20.
    CAVITIES BELOW GROUND(3)CAVITIES BELOW GROUND (3) D.P.C. MIN 150mm ABOVE G.L. Brick