PMBOK 4th Edition              PMI-CCVC Time managment PMP Prep                                      6/18/2011




                                      Progressive elaboration where near term work is planned in detail and
  1       Define Activities       a
                                      future work is planned at a higher level of the WBS.

                                      The process of estimating the type and quantities of material, people,
  2     Sequence Activities       b
                                      equipment, or supplies required to perform each activity.

         Estimate Activity            The process of monitoring the status of the project to update project
  3                               c
             Resources                progress and managing changes to the schedule baseline.

         Estimate Activity            Specify when and how long identified project resources are available.
  4                               d
             Durations                This includes resource skill level and geographical locations of orgin.
                                      The process of identifying and documenting relationships among the
  5      Develop Schedule         e
                                      project activities.
                                      Preferred logic, preferential logic, or soft logic. When fast tracking
  6      Control Schedule         f   techniques are used, these should be reviewed and considered for
                                      modification or removal.
                                      A project schedule developed from the schedule network analysis. It is
      Finalized and Approved          accepted and approved by the project management team as the
  7                               g
              Schedule                schedule with start and finish dates. It is a component of the project
                                      management plan.
                                      Uses Most likely, Optimistic and Pessimistic values for Three-Point
  8       Decomposition           h
                                      Estimates.
                                      Resource need is estimated and the quantities are totaled for each
  9    Rolling Wave Planning      i
                                      activitiy's resources.
                                      Uses parameters such as duration, budget, size, weight and complexity
 10      Activity Attributes      j   from a previous project as the basis for estimating the same parameter
                                      for a future project.
            Precedence
                                      Used for schedule development and for selecting, ordering, and sorting
 11    Diagramming Method         k
                                      the planned activities in reports.
              (PDM)
           Discretionary
 12                               l   The baseline that is used in the Control Schedule process.
           dependencies
                                      Subdividing the project work packages into smaller, more manageable
 13     Resource Calendars        m
                                      compoents called activities.
                                      Uses boxes, referred to as nodes, to represent activities, and connects
 14    Bottom-Up Estimating       n   them with arrows that show the logical relationships that exist
                                      between them. This technique is also called Activity-On-Node (AON).

       Resource Breakdown             A structure of identified resources by resource category and resource
 15                               o
            Structure                 type.

                                      A schedule network analysis technique applied to a schedule that has
 16    Analogous Estimating       p been analysised by critical path method. Can be used when shared
                                      resources are only available at certain times or limited quantities.

      Program Evaluation and
                                      Schedule performance measurements (SV, SPI) are used to assess the
 17      Review Technique         q
                                      changes from the original schedule baseline.
              (PERT)

                                           Page 1 of 2
PMBOK 4th Edition            PMI-CCVC Time managment PMP Prep                                      6/18/2011


         Schedule Network           Uses analytical techniques such as critical path method, critical chain
 18                             r
             Analysis               method and resource leveling for generating a project schedule.

                                    The process of approximating the number of work periods needed to
 19      Resource Leveling      s
                                    complete individual activities with estimated resources.

                                    The process of analyzing activity sequences, durations, resource
 20      Schedule Baseline      t
                                    requirements, and schedule constraints to create the project schedule.
                                    The process of identifying the specific actions to be performed to
 21      Variance Analysis      v
                                    produce the project deliverables.




                                         Page 2 of 2

Capm time mgmt matching exercise

  • 1.
    PMBOK 4th Edition PMI-CCVC Time managment PMP Prep 6/18/2011 Progressive elaboration where near term work is planned in detail and 1 Define Activities a future work is planned at a higher level of the WBS. The process of estimating the type and quantities of material, people, 2 Sequence Activities b equipment, or supplies required to perform each activity. Estimate Activity The process of monitoring the status of the project to update project 3 c Resources progress and managing changes to the schedule baseline. Estimate Activity Specify when and how long identified project resources are available. 4 d Durations This includes resource skill level and geographical locations of orgin. The process of identifying and documenting relationships among the 5 Develop Schedule e project activities. Preferred logic, preferential logic, or soft logic. When fast tracking 6 Control Schedule f techniques are used, these should be reviewed and considered for modification or removal. A project schedule developed from the schedule network analysis. It is Finalized and Approved accepted and approved by the project management team as the 7 g Schedule schedule with start and finish dates. It is a component of the project management plan. Uses Most likely, Optimistic and Pessimistic values for Three-Point 8 Decomposition h Estimates. Resource need is estimated and the quantities are totaled for each 9 Rolling Wave Planning i activitiy's resources. Uses parameters such as duration, budget, size, weight and complexity 10 Activity Attributes j from a previous project as the basis for estimating the same parameter for a future project. Precedence Used for schedule development and for selecting, ordering, and sorting 11 Diagramming Method k the planned activities in reports. (PDM) Discretionary 12 l The baseline that is used in the Control Schedule process. dependencies Subdividing the project work packages into smaller, more manageable 13 Resource Calendars m compoents called activities. Uses boxes, referred to as nodes, to represent activities, and connects 14 Bottom-Up Estimating n them with arrows that show the logical relationships that exist between them. This technique is also called Activity-On-Node (AON). Resource Breakdown A structure of identified resources by resource category and resource 15 o Structure type. A schedule network analysis technique applied to a schedule that has 16 Analogous Estimating p been analysised by critical path method. Can be used when shared resources are only available at certain times or limited quantities. Program Evaluation and Schedule performance measurements (SV, SPI) are used to assess the 17 Review Technique q changes from the original schedule baseline. (PERT) Page 1 of 2
  • 2.
    PMBOK 4th Edition PMI-CCVC Time managment PMP Prep 6/18/2011 Schedule Network Uses analytical techniques such as critical path method, critical chain 18 r Analysis method and resource leveling for generating a project schedule. The process of approximating the number of work periods needed to 19 Resource Leveling s complete individual activities with estimated resources. The process of analyzing activity sequences, durations, resource 20 Schedule Baseline t requirements, and schedule constraints to create the project schedule. The process of identifying the specific actions to be performed to 21 Variance Analysis v produce the project deliverables. Page 2 of 2