The document describes identifying the critical path for a project involving replacing a sidewalk. It involves calculating early start, early finish, late start and late finish dates for each activity by performing forward and backward passes on the network diagram. The critical path is determined to be activities 2.3.3.1 through 2.3.3.4 plus 2.3.3.7, totaling 81 hours. Activities 2.3.3.5 and 2.3.3.6 have 10 hours of total float but share it, so increasing one activity's duration would decrease the other's float.