The document describes identifying the critical path for a project involving replacing a sidewalk. It involves performing forward and backward passes on the network diagram to determine early/late start and finish dates for each activity. The critical path is determined to be activities 2.3.3.1 through 2.3.3.4 plus the 16-hour lag for concrete curing before 2.3.3.7 can finish, totaling 81 hours. Activities 2.3.3.5 and 2.3.3.6 have 10 hours of total float but share it, so increasing one activity's duration would reduce the other's float.