BUILDING CONSTRUCTION PROCESS FROM START TO FINISH
Building construction is an ancient human activity that began purely from a functional need to provide shelter from
the elements. Over time, human beings have adapted to a variety of climates. The first human shelters were basic
structures that did not last long.
Now, more durable structures are available thanks to the development of durable construction materials, elaborate
building techniques and processes, and improvements in construction labor.
Building construction is a complex undertaking, irrespective of the type of building. Succeeding requires a lot of
time, effort, and financial investment. The first step to a successful construction project is to develop an extensive
plan.
The building construction process must be done step by step to ensure an efficient construction process. Consider
important aspects such as the purpose of the building, finances, utility, and demand for work before starting the
planning phase.
This article will discuss the building construction process from start to finish.
WHAT IS BUILDING CONSTRUCTION?
Building construction describes the physical activity on a construction site that contributes to building or structure
construction. This process involves unloading plant, machinery, materials, cladding, fixtures, fitting of installations,
formwork, and external finish.
The building construction process is a series of routine tasks completed by skilled persons. It involves a lot of time
and tedious work and must be managed carefully. This process can be split into three phases:pre-construction,
construction, and post-construction.
STEP 1: PRE-CONSTRUCTION PROCESS
Before a project begins, the client must work closely with the design team and contractor to develop the project
plan. The pre-construction process is where the contractor and the design team develop detailed drawings, budgets,
schedules, and labor projections.
The core team defines the project and prepares cost estimates depending on the client’s budget. The team must also
identify potential risks and develop solutions to ensure optimal use of resources.
The pre-construction phase is characterized by deliberate thoroughness to ensure that all potential needs are
identified and addressed early. Regular communication between the core project team and the consultants is vital
during pre-construction.
ACQUIRING LAND
The most crucial step in building construction is acquiring land for the project. The location should be well-suited
for the project requirements. Before the land acquisition, it is best to conduct feasibility studies to ensure the land is
strategically located and is free from land-related issues. It is also necessary to evaluate the project's cost-
effectiveness before kickoff.
INITIAL MEETING
The pre-construction phase starts with an initial meeting between the client and the general contractor. The parties
can familiarize themselves with each other. It also allows contractors to understand the client’s needs.
The two parties must define the goals and objectives of the project at this stage. The client has an opportunity to ask
questions that the contractor must resolve. The contractor must use this meeting to understand the client’s vision
and decide whether or not they can execute it.
The initial meeting allows the contractor to determine the scope of work, the feasibility of the project, and the
amount of work required. The contractor can then define the project deliverables and outline a schedule.
ESTIMATING AND BUDGETS
Once the initial meeting is completed, the contractor can visit the site and develop a design and layout. Building
construction involves a considerable quantity of material and budget, and it is easy for costs to overrun. Once the
planning and structural detailing is done, the construction estimator shares the details.
The construction estimator estimates the quantity and quality of materials needed. The contractor will then develop
a budget that includes estimated costs of labor, materials, machinery, and other requirements. The budget will
depend on the quality and quantity of materials needed.
If financial resources are limited, the contractor and the property owner must seek pre-approval loans before
construction.
SCHEDULE
Once the project scope is laid out and the contractor has done a site visit, it is time to develop a project schedule.
The schedule defines when certain aspects of the work will start and end.
The schedule is typically updated during the project lifecycle to paint a clearer picture of construction timelines.
Project scheduling is crucial as it affects overall project costs and profit margins.
STEP 2: BUILDING CONSTRUCTION PHASE
With the project plan and team in place, it is time to clear the site and start building. The building construction
phase is where the project comes to life. It is a critical step because it involves multiple working parts and
deadlines.
Each contractor and subcontractor must now execute the plan, from site preparation to construction.
SITE PREPARATION
Site preparation is the clearing of the site in readiness for construction. Site preparation clears the way for other
remedial or demolition work required before workers start constructing the building.
Site clearing involves removing rubbish, machinery, equipment, and unwanted materials. Some site preparation
activities may require approvals. The workers must take care not to destroy any trees that are meant to be protected.
A site waste management plan (SWMP) is essential to ensure materials are managed and disposed of efficiently and
legally. The SWMP also outlines the reuse and recycling of materials where possible. Only professional disposal
experts should handle hazardous substances like asbestos and contaminated waste.
Site preparation is typically carried out under the main construction contract but can be carried out in advance. Site
preparation can also be part of a wider enabling works contract, including soil stabilization, demolition,
construction of access roads, and services diversion.
CONSTRUCTION
The construction process begins at excavation and ends once the interior and exterior finishes are complete.
EXCAVATION
Once the site is cleared, it is time for excavation. Excavation refers to the removal of earth to form a cavity in the
ground. Small sites may do excavation manually using shovels, picks, and wheelbarrows. However, heavy plant
machinery is used in large-scale excavations.
Excavation can be classified according to the material being removed, for instance, topsoil, muck, earth, and rock
excavation. It can also be classified according to the purpose: trench, road, basement, and bridge excavation.
FOUNDATION
The cleared and excavated site is now ready for construction, and the foundation can be poured. The foundation is
the lower part of the substructure. It transfers the building’s loads to the ground.
The foundation is built according to the architect’s drawings. The drawings determine the foundation's length,
width, depth, size, and type.
Concrete foundations are widely used for building structures. However, the choice of foundation can vary
depending on the water table level and soil composition of the location. Soil testing is crucial to determine the
bearing capacity of the soil.
Shallow foundations may be adequate for low-rise buildings. However, pile foundations are best for high-rise
buildings. Builders will place formworks and reinforcements in the excavated trenches to construct the foundation.
The Engineer must monitor the reinforcement works.
FRAMING
Framing is the installation of wood frames and steel beams to support the building. It is a time-consuming but
crucial part of building construction as it sets the groundwork for the rest of the building.
MASONRY
Now that the framing is complete, it is time to begin the masonry work. The architect’s drawings will determine the
material used: ash brick, concrete blocks, or bricks.
The masons bind the building materials using a cement mortar mix, leaving gas for the doors, windows, and
doorways.
ELECTRICAL AND PLUMBING WORK
The specialty contractors are brought in to complete the rough plumbing and electrical work. This process involves
installing pipes and wires under the floors, ceilings, and walls.
The electrical and plumbing work is not completed at this stage; only the rough work is done to enable drywall,
insulation, and ceiling installation. The point and pipe ends must be left out and finished later with plumbing
fixtures and electrical fittings.
This step is important to ensure that electrical and plumbing work is not visible after finishing.
ROOFING
Once the basic structure is done, roofing is installed. Roofing protects the interior from the weather elements,
preventing damage and disruptions. The contractors should be brought in to start working on the exterior of the
building at this stage.
EXTERIOR FINISHING
Exterior finishing involves plastering the external parts of the building. It also involves external cladding to elevate
the house.
HEATING AND COOLING WORK
With a roof and exterior walls in place, it is time to address the heating and cooling needs of the building. This
process involves the installation of vents, ducts, heating units, and cooling systems.
INTERIOR FINISHING
The next step is to plaster the internal walls for a smooth finish and install tiles on the floor. Interior finishing also
includes installing drywall, ceiling, and insulation. The electrician can also come in and finish the outlets and install
the light fixtures.
WOODWORK AND FIXTURE FITTINGS
The construction is almost complete now, and it is time to complete the plumbing fittings in the kitchen and
bathrooms. Toilets, cabinets, windows, and doors are fitted too.
WATERPROOFING
Waterproofing is the process of preventing water from penetrating the building. Waterproofing is done to reduce
humidity and keep the house dry.
PAINTING
Painting gives the house a beautiful finish and protects it from exposure to rain, dirt, sunlight, and stains. A good
paint job can give a building 5 to 10 extra years of life.
STEP 3: POST-CONSTRUCTION PHASE
The post-construction phase is the final process before the building is handed over to the client or owner. The
post-construction phase includes completing the punch list items and the final walk-through. A punch list is a
document that lists all the contract items a contractor must fulfill to be paid.
THE WALK-THROUGH
Once the construction is complete, the team must walk through the building to confirm that all the project
specifications have been met. The contractor and the architect must certify that the building is fully functional.
If the architect is satisfied, they will issue a certificate of satisfactory completion. The relevant supervisors must
confirm that the building meets the local authorities' requirements, and the local government will issue a certificate
of occupancy.
HANDOVER
The contractor can now hand over the building to the owner. The owner is given substantial time to confirm that
they are comfortable operating every aspect of the new building. The contractor can provide training and support as
necessary.
The contractor also must hand over all the blueprints and operation manuals to the owner.
SUMMARY
The building construction process is essential to the success of any construction project. It consumes a lot of time
and resources but ensures no stone is left unturned.
The building construction process can be split into three main phases, pre-construction, construction, and post-
construction. The three main phases of construction involve many systematic activities.
The pre-construction phase includes acquiring land, strategic design, preparing budgets and estimates, acquiring
licenses and permits, and hiring experts. The construction phase involves site preparation, excavation, foundation,
framing, masonry work, roofing, interior finishes, and exterior finishes.
Finally, post-construction involves the final walkthrough and the handover of the completed building.

More Related Content

What's hot

Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Anne Allan
 
Lecture 1 Building types and components of building.pptx
Lecture 1 Building types and components of building.pptxLecture 1 Building types and components of building.pptx
Lecture 1 Building types and components of building.pptx
meghajain275
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
Pang Khai Shuen
 
Backfilling 2014a-Lecture4
Backfilling 2014a-Lecture4Backfilling 2014a-Lecture4
Backfilling 2014a-Lecture4Anne Allan
 
Brick masonry ppt
Brick masonry pptBrick masonry ppt
Brick masonry ppt
monishkumark
 
An introduction to taking off building quantities
An introduction to taking off building quantities An introduction to taking off building quantities
An introduction to taking off building quantities
Arshad Mohanut
 
Load bearing elements part5
Load bearing elements part5Load bearing elements part5
Load bearing elements part5
College of North West London
 
Anchored Secant Pile Wall Presentation
Anchored Secant Pile Wall PresentationAnchored Secant Pile Wall Presentation
Anchored Secant Pile Wall PresentationKyle Beaudry, P.Eng
 
Concrete 2014a-Lecture7
Concrete 2014a-Lecture7Concrete 2014a-Lecture7
Concrete 2014a-Lecture7Anne Allan
 
Technical Journal: SB800 Guide To Requirements And Response Strategies
Technical Journal: SB800 Guide To Requirements And Response StrategiesTechnical Journal: SB800 Guide To Requirements And Response Strategies
Technical Journal: SB800 Guide To Requirements And Response Strategiesjpetrich2125
 
5#rate analysis problems
5#rate analysis   problems5#rate analysis   problems
5#rate analysis problems
LIJI A
 
Building materials - Soil
Building materials - SoilBuilding materials - Soil
Building materials - Soil
moonjazzy
 
Site Visit Report CT BM M1
Site Visit Report CT BM M1Site Visit Report CT BM M1
Site Visit Report CT BM M1
Zi Shan
 
wall masonary,door,paint and trusses
wall masonary,door,paint and trusseswall masonary,door,paint and trusses
wall masonary,door,paint and trusses
lithakoshi
 
Types of masonry walls
Types of masonry wallsTypes of masonry walls
Types of masonry walls
Mohit Dwivedi
 
Building estimation methods
Building estimation methodsBuilding estimation methods
Building estimation methods
Simarpreet Singh
 
Coloured Concrete - Metro Mix Concrete
Coloured Concrete - Metro Mix ConcreteColoured Concrete - Metro Mix Concrete
Coloured Concrete - Metro Mix Concrete
MetroMix Concrete
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
ZIyeeTan
 

What's hot (20)

lecture2 site investigation
lecture2   site investigationlecture2   site investigation
lecture2 site investigation
 
Excavation 2014a-Lecture3
Excavation 2014a-Lecture3Excavation 2014a-Lecture3
Excavation 2014a-Lecture3
 
Lecture 1 Building types and components of building.pptx
Lecture 1 Building types and components of building.pptxLecture 1 Building types and components of building.pptx
Lecture 1 Building types and components of building.pptx
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
 
Backfilling 2014a-Lecture4
Backfilling 2014a-Lecture4Backfilling 2014a-Lecture4
Backfilling 2014a-Lecture4
 
Brick masonry ppt
Brick masonry pptBrick masonry ppt
Brick masonry ppt
 
An introduction to taking off building quantities
An introduction to taking off building quantities An introduction to taking off building quantities
An introduction to taking off building quantities
 
Load bearing elements part5
Load bearing elements part5Load bearing elements part5
Load bearing elements part5
 
Anchored Secant Pile Wall Presentation
Anchored Secant Pile Wall PresentationAnchored Secant Pile Wall Presentation
Anchored Secant Pile Wall Presentation
 
Soil investigation
Soil investigationSoil investigation
Soil investigation
 
Concrete 2014a-Lecture7
Concrete 2014a-Lecture7Concrete 2014a-Lecture7
Concrete 2014a-Lecture7
 
Technical Journal: SB800 Guide To Requirements And Response Strategies
Technical Journal: SB800 Guide To Requirements And Response StrategiesTechnical Journal: SB800 Guide To Requirements And Response Strategies
Technical Journal: SB800 Guide To Requirements And Response Strategies
 
5#rate analysis problems
5#rate analysis   problems5#rate analysis   problems
5#rate analysis problems
 
Building materials - Soil
Building materials - SoilBuilding materials - Soil
Building materials - Soil
 
Site Visit Report CT BM M1
Site Visit Report CT BM M1Site Visit Report CT BM M1
Site Visit Report CT BM M1
 
wall masonary,door,paint and trusses
wall masonary,door,paint and trusseswall masonary,door,paint and trusses
wall masonary,door,paint and trusses
 
Types of masonry walls
Types of masonry wallsTypes of masonry walls
Types of masonry walls
 
Building estimation methods
Building estimation methodsBuilding estimation methods
Building estimation methods
 
Coloured Concrete - Metro Mix Concrete
Coloured Concrete - Metro Mix ConcreteColoured Concrete - Metro Mix Concrete
Coloured Concrete - Metro Mix Concrete
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 

Similar to BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx

building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENT
RiyaVerma238431
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
DougDos
 
Highway Construction
Highway ConstructionHighway Construction
Highway Construction
beverly0bennett8
 
Project background (1)(1)
Project background (1)(1)Project background (1)(1)
Project background (1)(1)JamesMoy7
 
Project management
Project managementProject management
Project management
Benjamin Tan
 
Residential building in Bangalore, Mysore, Mangalore, Karnataka, Hosur, Coimb...
Residential building in Bangalore, Mysore, Mangalore, Karnataka, Hosur, Coimb...Residential building in Bangalore, Mysore, Mangalore, Karnataka, Hosur, Coimb...
Residential building in Bangalore, Mysore, Mangalore, Karnataka, Hosur, Coimb...
SEO Tech Solution
 
Ici individual
Ici individualIci individual
Ici individual
Klaus Chiang
 
The Significance of a Site Survey in The Construction Industry
The Significance of a Site Survey in The Construction IndustryThe Significance of a Site Survey in The Construction Industry
The Significance of a Site Survey in The Construction Industry
Aussie Hydro-Vac Services
 
Construction economic
Construction economicConstruction economic
Construction economicfauziani
 
Unit 1 basics of construction
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of construction
SANJEEV Wazir
 
Final building-team
Final building-teamFinal building-team
Final building-team
Zheng Chee Cham
 
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
Firdaurs Abdullah
 
Latest project background 1
Latest project background 1Latest project background 1
Latest project background 1JamesMoy7
 
The Project Brief(group)
The Project Brief(group)The Project Brief(group)
The Project Brief(group)Pinky Chan
 
Industrial Training On Construction At Simplex Infrastructures Ltd
Industrial Training On Construction At Simplex Infrastructures LtdIndustrial Training On Construction At Simplex Infrastructures Ltd
Industrial Training On Construction At Simplex Infrastructures Ltd
Sk Md Nayar
 

Similar to BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx (20)

building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENT
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
 
Highway Construction
Highway ConstructionHighway Construction
Highway Construction
 
Project background (1)(1)
Project background (1)(1)Project background (1)(1)
Project background (1)(1)
 
Project management
Project managementProject management
Project management
 
Residential building in Bangalore, Mysore, Mangalore, Karnataka, Hosur, Coimb...
Residential building in Bangalore, Mysore, Mangalore, Karnataka, Hosur, Coimb...Residential building in Bangalore, Mysore, Mangalore, Karnataka, Hosur, Coimb...
Residential building in Bangalore, Mysore, Mangalore, Karnataka, Hosur, Coimb...
 
Ici individual
Ici individualIci individual
Ici individual
 
The Significance of a Site Survey in The Construction Industry
The Significance of a Site Survey in The Construction IndustryThe Significance of a Site Survey in The Construction Industry
The Significance of a Site Survey in The Construction Industry
 
Construction economic
Construction economicConstruction economic
Construction economic
 
Unit 1 basics of construction
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of construction
 
VACATION WORK REPORT 2
VACATION WORK REPORT 2VACATION WORK REPORT 2
VACATION WORK REPORT 2
 
Final building-team
Final building-teamFinal building-team
Final building-team
 
Final building-team
Final building-teamFinal building-team
Final building-team
 
Project background
Project backgroundProject background
Project background
 
CV sultan(Q)
CV sultan(Q)CV sultan(Q)
CV sultan(Q)
 
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
GROUP PROJECT: PROPOSAL FOR THE FINISHED/ EXISTING BUILDING CONSTRUCTION (CAS...
 
Latest project background 1
Latest project background 1Latest project background 1
Latest project background 1
 
The Project Brief(group)
The Project Brief(group)The Project Brief(group)
The Project Brief(group)
 
ICIP2G
ICIP2GICIP2G
ICIP2G
 
Industrial Training On Construction At Simplex Infrastructures Ltd
Industrial Training On Construction At Simplex Infrastructures LtdIndustrial Training On Construction At Simplex Infrastructures Ltd
Industrial Training On Construction At Simplex Infrastructures Ltd
 

More from Sudas Duddey

Assignment 2 case study D.Sudas R.No.11.docx
Assignment 2 case study  D.Sudas R.No.11.docxAssignment 2 case study  D.Sudas R.No.11.docx
Assignment 2 case study D.Sudas R.No.11.docx
Sudas Duddey
 
Assignment 2 case study D.Sudas R.No.11.pdf
Assignment 2 case study  D.Sudas R.No.11.pdfAssignment 2 case study  D.Sudas R.No.11.pdf
Assignment 2 case study D.Sudas R.No.11.pdf
Sudas Duddey
 
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.pdf
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.pdfBUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.pdf
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.pdf
Sudas Duddey
 
constructionsafetymanagement[1].pptx
constructionsafetymanagement[1].pptxconstructionsafetymanagement[1].pptx
constructionsafetymanagement[1].pptx
Sudas Duddey
 
Flyash bricks Orginasation chart & B2B.pdf
Flyash bricks Orginasation chart & B2B.pdfFlyash bricks Orginasation chart & B2B.pdf
Flyash bricks Orginasation chart & B2B.pdf
Sudas Duddey
 
Construction Safety Management.pdf
Construction Safety Management.pdfConstruction Safety Management.pdf
Construction Safety Management.pdf
Sudas Duddey
 
ISO_14000_Series[1].pdf
ISO_14000_Series[1].pdfISO_14000_Series[1].pdf
ISO_14000_Series[1].pdf
Sudas Duddey
 
Project_Planning_and_Control_by_B_C_Punm.pdf
Project_Planning_and_Control_by_B_C_Punm.pdfProject_Planning_and_Control_by_B_C_Punm.pdf
Project_Planning_and_Control_by_B_C_Punm.pdf
Sudas Duddey
 
Social aspect in Contract Conditions.pptx
Social aspect in Contract Conditions.pptxSocial aspect in Contract Conditions.pptx
Social aspect in Contract Conditions.pptx
Sudas Duddey
 
HRIDAY Scheme.pptx
HRIDAY Scheme.pptxHRIDAY Scheme.pptx
HRIDAY Scheme.pptx
Sudas Duddey
 

More from Sudas Duddey (10)

Assignment 2 case study D.Sudas R.No.11.docx
Assignment 2 case study  D.Sudas R.No.11.docxAssignment 2 case study  D.Sudas R.No.11.docx
Assignment 2 case study D.Sudas R.No.11.docx
 
Assignment 2 case study D.Sudas R.No.11.pdf
Assignment 2 case study  D.Sudas R.No.11.pdfAssignment 2 case study  D.Sudas R.No.11.pdf
Assignment 2 case study D.Sudas R.No.11.pdf
 
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.pdf
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.pdfBUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.pdf
BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.pdf
 
constructionsafetymanagement[1].pptx
constructionsafetymanagement[1].pptxconstructionsafetymanagement[1].pptx
constructionsafetymanagement[1].pptx
 
Flyash bricks Orginasation chart & B2B.pdf
Flyash bricks Orginasation chart & B2B.pdfFlyash bricks Orginasation chart & B2B.pdf
Flyash bricks Orginasation chart & B2B.pdf
 
Construction Safety Management.pdf
Construction Safety Management.pdfConstruction Safety Management.pdf
Construction Safety Management.pdf
 
ISO_14000_Series[1].pdf
ISO_14000_Series[1].pdfISO_14000_Series[1].pdf
ISO_14000_Series[1].pdf
 
Project_Planning_and_Control_by_B_C_Punm.pdf
Project_Planning_and_Control_by_B_C_Punm.pdfProject_Planning_and_Control_by_B_C_Punm.pdf
Project_Planning_and_Control_by_B_C_Punm.pdf
 
Social aspect in Contract Conditions.pptx
Social aspect in Contract Conditions.pptxSocial aspect in Contract Conditions.pptx
Social aspect in Contract Conditions.pptx
 
HRIDAY Scheme.pptx
HRIDAY Scheme.pptxHRIDAY Scheme.pptx
HRIDAY Scheme.pptx
 

Recently uploaded

Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
Jisc
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
EverAndrsGuerraGuerr
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
Celine George
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
Nguyen Thanh Tu Collection
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
GeoBlogs
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
rosedainty
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
Jheel Barad
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
Excellence Foundation for South Sudan
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 

Recently uploaded (20)

Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
Thesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.pptThesis Statement for students diagnonsed withADHD.ppt
Thesis Statement for students diagnonsed withADHD.ppt
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......Ethnobotany and Ethnopharmacology ......
Ethnobotany and Ethnopharmacology ......
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
How to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS ModuleHow to Split Bills in the Odoo 17 POS Module
How to Split Bills in the Odoo 17 POS Module
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
 
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
Fish and Chips - have they had their chips
Fish and Chips - have they had their chipsFish and Chips - have they had their chips
Fish and Chips - have they had their chips
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 

BUILDING CONSTRUCTION PROCESS FROM START TO FINISH 1.docx

  • 1. CASE STUDY SEQUENTIAL STEPS FOR A FIMILIARSATION WITH BUILDING PROJECTS Submitted By J. Nagabhushana Rao (22261NC010) D. Sudas (22261NC011) Kishore Kumar (22261NC012)
  • 2. BUILDING CONSTRUCTION PROCESS FROM START TO FINISH Building construction is an ancient human activity that began purely from a functional need to provide shelter from the elements. Over time, human beings have adapted to a variety of climates. The first human shelters were basic structures that did not last long. Now, more durable structures are available thanks to the development of durable construction materials, elaborate building techniques and processes, and improvements in construction labor. Building construction is a complex undertaking, irrespective of the type of building. Succeeding requires a lot of time, effort, and financial investment. The first step to a successful construction project is to develop an extensive plan. The building construction process must be done step by step to ensure an efficient construction process. Consider important aspects such as the purpose of the building, finances, utility, and demand for work before starting the planning phase. This article will discuss the building construction process from start to finish. WHAT IS BUILDING CONSTRUCTION? Building construction describes the physical activity on a construction site that contributes to building or structure construction. This process involves unloading plant, machinery, materials, cladding, fixtures, fitting of installations, formwork, and external finish. The building construction process is a series of routine tasks completed by skilled persons. It involves a lot of time and tedious work and must be managed carefully. This process can be split into three phases:pre-construction, construction, and post-construction. STEP 1: PRE-CONSTRUCTION PROCESS Before a project begins, the client must work closely with the design team and contractor to develop the project plan. The pre-construction process is where the contractor and the design team develop detailed drawings, budgets, schedules, and labor projections. The core team defines the project and prepares cost estimates depending on the client’s budget. The team must also identify potential risks and develop solutions to ensure optimal use of resources.
  • 3. The pre-construction phase is characterized by deliberate thoroughness to ensure that all potential needs are identified and addressed early. Regular communication between the core project team and the consultants is vital during pre-construction. ACQUIRING LAND The most crucial step in building construction is acquiring land for the project. The location should be well-suited for the project requirements. Before the land acquisition, it is best to conduct feasibility studies to ensure the land is strategically located and is free from land-related issues. It is also necessary to evaluate the project's cost- effectiveness before kickoff. INITIAL MEETING The pre-construction phase starts with an initial meeting between the client and the general contractor. The parties can familiarize themselves with each other. It also allows contractors to understand the client’s needs. The two parties must define the goals and objectives of the project at this stage. The client has an opportunity to ask questions that the contractor must resolve. The contractor must use this meeting to understand the client’s vision and decide whether or not they can execute it. The initial meeting allows the contractor to determine the scope of work, the feasibility of the project, and the amount of work required. The contractor can then define the project deliverables and outline a schedule. ESTIMATING AND BUDGETS Once the initial meeting is completed, the contractor can visit the site and develop a design and layout. Building construction involves a considerable quantity of material and budget, and it is easy for costs to overrun. Once the planning and structural detailing is done, the construction estimator shares the details. The construction estimator estimates the quantity and quality of materials needed. The contractor will then develop a budget that includes estimated costs of labor, materials, machinery, and other requirements. The budget will depend on the quality and quantity of materials needed. If financial resources are limited, the contractor and the property owner must seek pre-approval loans before construction. SCHEDULE Once the project scope is laid out and the contractor has done a site visit, it is time to develop a project schedule. The schedule defines when certain aspects of the work will start and end. The schedule is typically updated during the project lifecycle to paint a clearer picture of construction timelines. Project scheduling is crucial as it affects overall project costs and profit margins.
  • 4. STEP 2: BUILDING CONSTRUCTION PHASE With the project plan and team in place, it is time to clear the site and start building. The building construction phase is where the project comes to life. It is a critical step because it involves multiple working parts and deadlines. Each contractor and subcontractor must now execute the plan, from site preparation to construction. SITE PREPARATION Site preparation is the clearing of the site in readiness for construction. Site preparation clears the way for other remedial or demolition work required before workers start constructing the building. Site clearing involves removing rubbish, machinery, equipment, and unwanted materials. Some site preparation activities may require approvals. The workers must take care not to destroy any trees that are meant to be protected. A site waste management plan (SWMP) is essential to ensure materials are managed and disposed of efficiently and legally. The SWMP also outlines the reuse and recycling of materials where possible. Only professional disposal experts should handle hazardous substances like asbestos and contaminated waste. Site preparation is typically carried out under the main construction contract but can be carried out in advance. Site preparation can also be part of a wider enabling works contract, including soil stabilization, demolition, construction of access roads, and services diversion. CONSTRUCTION The construction process begins at excavation and ends once the interior and exterior finishes are complete. EXCAVATION Once the site is cleared, it is time for excavation. Excavation refers to the removal of earth to form a cavity in the ground. Small sites may do excavation manually using shovels, picks, and wheelbarrows. However, heavy plant machinery is used in large-scale excavations. Excavation can be classified according to the material being removed, for instance, topsoil, muck, earth, and rock excavation. It can also be classified according to the purpose: trench, road, basement, and bridge excavation.
  • 5. FOUNDATION The cleared and excavated site is now ready for construction, and the foundation can be poured. The foundation is the lower part of the substructure. It transfers the building’s loads to the ground. The foundation is built according to the architect’s drawings. The drawings determine the foundation's length, width, depth, size, and type. Concrete foundations are widely used for building structures. However, the choice of foundation can vary depending on the water table level and soil composition of the location. Soil testing is crucial to determine the bearing capacity of the soil. Shallow foundations may be adequate for low-rise buildings. However, pile foundations are best for high-rise buildings. Builders will place formworks and reinforcements in the excavated trenches to construct the foundation. The Engineer must monitor the reinforcement works. FRAMING Framing is the installation of wood frames and steel beams to support the building. It is a time-consuming but crucial part of building construction as it sets the groundwork for the rest of the building. MASONRY Now that the framing is complete, it is time to begin the masonry work. The architect’s drawings will determine the material used: ash brick, concrete blocks, or bricks. The masons bind the building materials using a cement mortar mix, leaving gas for the doors, windows, and doorways. ELECTRICAL AND PLUMBING WORK The specialty contractors are brought in to complete the rough plumbing and electrical work. This process involves installing pipes and wires under the floors, ceilings, and walls. The electrical and plumbing work is not completed at this stage; only the rough work is done to enable drywall, insulation, and ceiling installation. The point and pipe ends must be left out and finished later with plumbing fixtures and electrical fittings. This step is important to ensure that electrical and plumbing work is not visible after finishing. ROOFING Once the basic structure is done, roofing is installed. Roofing protects the interior from the weather elements, preventing damage and disruptions. The contractors should be brought in to start working on the exterior of the building at this stage. EXTERIOR FINISHING Exterior finishing involves plastering the external parts of the building. It also involves external cladding to elevate the house. HEATING AND COOLING WORK With a roof and exterior walls in place, it is time to address the heating and cooling needs of the building. This process involves the installation of vents, ducts, heating units, and cooling systems. INTERIOR FINISHING The next step is to plaster the internal walls for a smooth finish and install tiles on the floor. Interior finishing also includes installing drywall, ceiling, and insulation. The electrician can also come in and finish the outlets and install the light fixtures. WOODWORK AND FIXTURE FITTINGS The construction is almost complete now, and it is time to complete the plumbing fittings in the kitchen and bathrooms. Toilets, cabinets, windows, and doors are fitted too.
  • 6. WATERPROOFING Waterproofing is the process of preventing water from penetrating the building. Waterproofing is done to reduce humidity and keep the house dry. PAINTING Painting gives the house a beautiful finish and protects it from exposure to rain, dirt, sunlight, and stains. A good paint job can give a building 5 to 10 extra years of life. STEP 3: POST-CONSTRUCTION PHASE The post-construction phase is the final process before the building is handed over to the client or owner. The post-construction phase includes completing the punch list items and the final walk-through. A punch list is a document that lists all the contract items a contractor must fulfill to be paid. THE WALK-THROUGH Once the construction is complete, the team must walk through the building to confirm that all the project specifications have been met. The contractor and the architect must certify that the building is fully functional. If the architect is satisfied, they will issue a certificate of satisfactory completion. The relevant supervisors must confirm that the building meets the local authorities' requirements, and the local government will issue a certificate of occupancy. HANDOVER The contractor can now hand over the building to the owner. The owner is given substantial time to confirm that they are comfortable operating every aspect of the new building. The contractor can provide training and support as necessary. The contractor also must hand over all the blueprints and operation manuals to the owner. SUMMARY The building construction process is essential to the success of any construction project. It consumes a lot of time and resources but ensures no stone is left unturned. The building construction process can be split into three main phases, pre-construction, construction, and post- construction. The three main phases of construction involve many systematic activities.
  • 7. The pre-construction phase includes acquiring land, strategic design, preparing budgets and estimates, acquiring licenses and permits, and hiring experts. The construction phase involves site preparation, excavation, foundation, framing, masonry work, roofing, interior finishes, and exterior finishes. Finally, post-construction involves the final walkthrough and the handover of the completed building.