SlideShare a Scribd company logo
CASE STUDIES 
UNBONDED POST-TENSIONING IN INFRASTRUCTURE— 
BUFORD AVENUE PAVEMENT RECONSTRUCTION 
PTI JOURNAL | August 2014 1 
BY NEEL KHOSA 
The Buford Avenue Pavement Reconstruction project 
involved replacing a conventional reinforced concrete 
pavement with a post-tensioned concrete pavement for 
the University of Minnesota. The reconstruction of Buford 
Avenue occurred in a 220-foot stretch between Eckles 
Avenue and Buford Circle Road. The post-tensioned 
section was 102 feet long by roughly 32 feet wide 
(approximately 3250 square feet in area)(Fig. 1). 
One distinctive aspect of the project was that the road 
was built on top of an underground building that needed 
to operate during the construction phase. Due to the dete-rioration 
of the concrete pavement, buses and other large 
vehicles would produce noise and vibrations from impact 
at deteriorated joints which transferred through the pave-ment 
to the underground Saint Paul Student Center and 
the bookstore. The deteriorated pavement allowed storm 
Fig. 1—Plan view of the pavement and tendon layout. 
Fig. 2—Finished joint free pavement.
CASE STUDIES 
water runoff to leak through the cracks to the Student Center 
roof below, which had previously experienced minor water 
problems in the bookstore. Post-tensioning was chosen as 
the preferred structural system due to its ability to elimi-nate 
joints in the large pavement area over the underground 
building while maintaining a 7-in. concrete thickness. 
“The bus tires impacting the deteriorated pavement joints 
rattled merchandise on the shelves and caused ceiling tile 
to fall in the bookstore, creating anxiety for employees and 
customers. Now with the new pavement, all is quiet and 
calm in the student center and bookstore” said Jeff Johnson, 
PE, SEH Project Structural Engineer. 
Justin Gese, PE, SEH Project Manager, explained that 
“we determined the new post-tensioning design was the 
best solution to meet the goals of the project,” which were: 
1. To minimize future maintenance on this segment 
of roadway and increase durability; 
2. To minimize vibrations and noise caused by traffic 
due to presence of joints, and create a raised profile 
with additional insulation (Fig. 2). The addi-tional 
insulation also provided less heat loss from 
the Student Center below, which minimizes the 
impacts of future freezing-and-thawing cycles on 
the pavement above; 
3. To minimize formation of cracks in the segment 
to prevent storm water runoff migration from the 
roadway to the roof below. 
Unlike most infrastructure projects, Buford Avenue was 
designed with unbonded 0.6-in. post-tensioning tendons 
rather than precast or bonded post-tensioning tendons. 
0.6-in. unbonded tendons have a final average force of 
2 August 2014 | PTI JOURNAL 
approximately 38 kip (as compared to approximately 27 kip 
for 0.5-in. tendons). Encapsulated unbonded tendons were 
specified to meet the project’s requirement of reducing long-term 
corrosion or other distress for 40 years. The transverse 
and longitudinal post-tensioning tendons were supported 
by intersectional chairs on top of precast concrete blocks 
(Fig. 3). The support system rested above compacted sand 
and insulation on top of the Student Center’s under-ground 
bookstore. 
Graham Construction successfully completed the 
$234,000 roadway repair project within 2 month window 
given by the University of Minnesota—in time for the 
Minnesota State Fair on August 13, 2010. Graham Construc-tion 
hired AMSYSCO, Inc. to supply the unbonded 
0.6-in. post-tensioning tendons for this expedited project. 
According to Neel Khosa, Vice President at AMSYSCO, 
“The Buford Pavement project illustrates the potential for 
utilizing unbonded post-tensioning in infrastructure projects 
such as concrete roadways or pedestrian bridges.” 
Neel Khosa is the Vice President of AMSYSCO, Inc. He 
is the Chair of CRT-30 and a voting member on M-10 
and Certification Advisory Board. Mr. Khosa has a MBA 
from the University of Chicago and a Bachelor’s of Science 
in Civil Engineering from the University of Illinois. 
Lastly, he manages the corporate blog at www.amsyscoinc. 
com/our-blog which primarily deals with unbonded post-tensioned 
concrete. 
Fig. 3—Transverse section through the pavement.

More Related Content

What's hot

Metropol Parasol Surface Structure Design Report
Metropol Parasol Surface Structure Design ReportMetropol Parasol Surface Structure Design Report
Metropol Parasol Surface Structure Design Report
Kelvin Ng
 
AR Gunnar Birkerts
AR Gunnar BirkertsAR Gunnar Birkerts
AR Gunnar Birkerts
Vishakha Thole
 
Ceb 706 design of reinforeced and presressed concrete updated!
Ceb 706 design of reinforeced and presressed concrete updated!Ceb 706 design of reinforeced and presressed concrete updated!
Ceb 706 design of reinforeced and presressed concrete updated!
vishwaleenram
 
Chudyk, Austin_CIE 579_FINAL Presentation
Chudyk, Austin_CIE 579_FINAL PresentationChudyk, Austin_CIE 579_FINAL Presentation
Chudyk, Austin_CIE 579_FINAL Presentation
Austin Chudyk
 
Building construction
Building constructionBuilding construction
Building construction
prashant sharma
 
powerpoint presentation
powerpoint presentationpowerpoint presentation
powerpoint presentation
Anjan Majumder
 
Bridge rehabilitation
Bridge rehabilitationBridge rehabilitation
Bridge rehabilitation
Hendro Widagdo
 
Marina bay sands
Marina bay sandsMarina bay sands
Marina bay sands
Suranjith Hemarathne
 
Fallingwater Residence
Fallingwater ResidenceFallingwater Residence
Fallingwater Residence
PostTensioningInstitute
 
Presentation1
Presentation1Presentation1
Presentation1
9587091257
 
building construction project 1 report
building construction project 1 reportbuilding construction project 1 report
building construction project 1 report
Yq Chong
 
stress ribbon bridge by kaiser malik
stress ribbon bridge by kaiser  malikstress ribbon bridge by kaiser  malik
stress ribbon bridge by kaiser malik
junaid bashir
 
Studies in Construction Engineering of New and Existing Complex Steel Bridge...
 Studies in Construction Engineering of New and Existing Complex Steel Bridge... Studies in Construction Engineering of New and Existing Complex Steel Bridge...
Studies in Construction Engineering of New and Existing Complex Steel Bridge...
James Gregg
 
PORTFOLIO_FINISHED
PORTFOLIO_FINISHEDPORTFOLIO_FINISHED
PORTFOLIO_FINISHED
Caylee Griner
 
Building construction 2 project 1 report
Building construction 2 project 1 reportBuilding construction 2 project 1 report
Building construction 2 project 1 report
Ong Seng Peng Jeff
 
Edward Rice House
Edward Rice HouseEdward Rice House
Edward Rice House
PostTensioningInstitute
 
Foundation Engineering
Foundation Engineering Foundation Engineering
Foundation Engineering
VISHNU VIJAYAN
 
Aldar Headqaurter
Aldar Headqaurter  Aldar Headqaurter
Aldar Headqaurter
Othman Othman
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters Dubai
Neha Rampuria
 
Al dar hq
Al dar hqAl dar hq
Al dar hq
Nikhil Jaiswal
 

What's hot (20)

Metropol Parasol Surface Structure Design Report
Metropol Parasol Surface Structure Design ReportMetropol Parasol Surface Structure Design Report
Metropol Parasol Surface Structure Design Report
 
AR Gunnar Birkerts
AR Gunnar BirkertsAR Gunnar Birkerts
AR Gunnar Birkerts
 
Ceb 706 design of reinforeced and presressed concrete updated!
Ceb 706 design of reinforeced and presressed concrete updated!Ceb 706 design of reinforeced and presressed concrete updated!
Ceb 706 design of reinforeced and presressed concrete updated!
 
Chudyk, Austin_CIE 579_FINAL Presentation
Chudyk, Austin_CIE 579_FINAL PresentationChudyk, Austin_CIE 579_FINAL Presentation
Chudyk, Austin_CIE 579_FINAL Presentation
 
Building construction
Building constructionBuilding construction
Building construction
 
powerpoint presentation
powerpoint presentationpowerpoint presentation
powerpoint presentation
 
Bridge rehabilitation
Bridge rehabilitationBridge rehabilitation
Bridge rehabilitation
 
Marina bay sands
Marina bay sandsMarina bay sands
Marina bay sands
 
Fallingwater Residence
Fallingwater ResidenceFallingwater Residence
Fallingwater Residence
 
Presentation1
Presentation1Presentation1
Presentation1
 
building construction project 1 report
building construction project 1 reportbuilding construction project 1 report
building construction project 1 report
 
stress ribbon bridge by kaiser malik
stress ribbon bridge by kaiser  malikstress ribbon bridge by kaiser  malik
stress ribbon bridge by kaiser malik
 
Studies in Construction Engineering of New and Existing Complex Steel Bridge...
 Studies in Construction Engineering of New and Existing Complex Steel Bridge... Studies in Construction Engineering of New and Existing Complex Steel Bridge...
Studies in Construction Engineering of New and Existing Complex Steel Bridge...
 
PORTFOLIO_FINISHED
PORTFOLIO_FINISHEDPORTFOLIO_FINISHED
PORTFOLIO_FINISHED
 
Building construction 2 project 1 report
Building construction 2 project 1 reportBuilding construction 2 project 1 report
Building construction 2 project 1 report
 
Edward Rice House
Edward Rice HouseEdward Rice House
Edward Rice House
 
Foundation Engineering
Foundation Engineering Foundation Engineering
Foundation Engineering
 
Aldar Headqaurter
Aldar Headqaurter  Aldar Headqaurter
Aldar Headqaurter
 
Aldar Headquarters Dubai
Aldar Headquarters DubaiAldar Headquarters Dubai
Aldar Headquarters Dubai
 
Al dar hq
Al dar hqAl dar hq
Al dar hq
 

Similar to PTI Journal : Buford Ave post-tensioned pavement

Deep basement excavation
Deep basement excavation Deep basement excavation
Deep basement excavation
Davis Ciprikis
 
Case study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsCase study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutions
IRJET Journal
 
Project
ProjectProject
Project
Sallim Abdi
 
Water_Intrusion
Water_IntrusionWater_Intrusion
Water_Intrusion
Jonathan Marshall
 
Rehab of an existing mse(1)
Rehab of an existing mse(1)Rehab of an existing mse(1)
Rehab of an existing mse(1)
Dr. Ganesh Kame
 
Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptx
RajeshKumar25548
 
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESEXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
A Makwana
 
EQUIP-WORLD-RS-MAY-2015-FINAL
EQUIP-WORLD-RS-MAY-2015-FINALEQUIP-WORLD-RS-MAY-2015-FINAL
EQUIP-WORLD-RS-MAY-2015-FINAL
Mostafa Fakharifar
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Parag Pal
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Rajesh Burde
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
ghildiyal8811
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
ghildiyal8811
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...
Ramin Vaghei
 
Deep_Excavations.pdf
Deep_Excavations.pdfDeep_Excavations.pdf
Deep_Excavations.pdf
MPSingh80
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
IRJET Journal
 
Ijciet 10 02_065
Ijciet 10 02_065Ijciet 10 02_065
Ijciet 10 02_065
IAEME Publication
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
Matthias Schueller
 
Final thesis presentation.
Final thesis presentation.Final thesis presentation.
Final thesis presentation.
Md.Rashidul Islam Tuhin
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
Vishvendu pandey
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALS
SOUMYA KHANDELWAL
 

Similar to PTI Journal : Buford Ave post-tensioned pavement (20)

Deep basement excavation
Deep basement excavation Deep basement excavation
Deep basement excavation
 
Case study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutionsCase study: Widening an existing bridge structure Challenges and solutions
Case study: Widening an existing bridge structure Challenges and solutions
 
Project
ProjectProject
Project
 
Water_Intrusion
Water_IntrusionWater_Intrusion
Water_Intrusion
 
Rehab of an existing mse(1)
Rehab of an existing mse(1)Rehab of an existing mse(1)
Rehab of an existing mse(1)
 
Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptx
 
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESEXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
 
EQUIP-WORLD-RS-MAY-2015-FINAL
EQUIP-WORLD-RS-MAY-2015-FINALEQUIP-WORLD-RS-MAY-2015-FINAL
EQUIP-WORLD-RS-MAY-2015-FINAL
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 
Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...Performance of ibs precast concrete beam column connections under earthquake ...
Performance of ibs precast concrete beam column connections under earthquake ...
 
Deep_Excavations.pdf
Deep_Excavations.pdfDeep_Excavations.pdf
Deep_Excavations.pdf
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
Ijciet 10 02_065
Ijciet 10 02_065Ijciet 10 02_065
Ijciet 10 02_065
 
Deh Cho Bridge
Deh Cho BridgeDeh Cho Bridge
Deh Cho Bridge
 
Final thesis presentation.
Final thesis presentation.Final thesis presentation.
Final thesis presentation.
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALS
 

More from AMSYSCO Inc.

CTBUH Innovation Award Nominee - Vertical Unbonded Post-Tensioning
CTBUH Innovation Award Nominee - Vertical Unbonded Post-TensioningCTBUH Innovation Award Nominee - Vertical Unbonded Post-Tensioning
CTBUH Innovation Award Nominee - Vertical Unbonded Post-Tensioning
AMSYSCO Inc.
 
Case Study - University of Colorado Parking Garage and Field
Case Study - University of Colorado Parking Garage and FieldCase Study - University of Colorado Parking Garage and Field
Case Study - University of Colorado Parking Garage and Field
AMSYSCO Inc.
 
Case Study - One Eleven Tower
Case Study - One Eleven TowerCase Study - One Eleven Tower
Case Study - One Eleven Tower
AMSYSCO Inc.
 
OneEleven Tower - post tensioned transfer deck
OneEleven Tower - post tensioned transfer deckOneEleven Tower - post tensioned transfer deck
OneEleven Tower - post tensioned transfer deck
AMSYSCO Inc.
 
Concrete International - Wayzata Bay Infrastructure
Concrete International - Wayzata Bay InfrastructureConcrete International - Wayzata Bay Infrastructure
Concrete International - Wayzata Bay Infrastructure
AMSYSCO Inc.
 
What Could You Buy For $263 Trillion
What Could You Buy For $263 TrillionWhat Could You Buy For $263 Trillion
What Could You Buy For $263 Trillion
AMSYSCO Inc.
 
AMSYSCO's resume of Tall Buildings
AMSYSCO's resume of Tall BuildingsAMSYSCO's resume of Tall Buildings
AMSYSCO's resume of Tall Buildings
AMSYSCO Inc.
 
One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)
AMSYSCO Inc.
 
Post Tensioning Review Session for Installers
Post Tensioning Review Session for InstallersPost Tensioning Review Session for Installers
Post Tensioning Review Session for Installers
AMSYSCO Inc.
 
Infrastructure and Unbonded Post Tensioning
Infrastructure and Unbonded Post TensioningInfrastructure and Unbonded Post Tensioning
Infrastructure and Unbonded Post Tensioning
AMSYSCO Inc.
 
The Importance of Unbonded Field Certification
The Importance of Unbonded Field CertificationThe Importance of Unbonded Field Certification
The Importance of Unbonded Field Certification
AMSYSCO Inc.
 
Minnesota Twins Target Field & Post Tensioning
Minnesota Twins Target Field & Post TensioningMinnesota Twins Target Field & Post Tensioning
Minnesota Twins Target Field & Post Tensioning
AMSYSCO Inc.
 
Case Study – Social Media Small Business
Case Study – Social Media Small BusinessCase Study – Social Media Small Business
Case Study – Social Media Small Business
AMSYSCO Inc.
 
2009 PTI Legends & Fellow Awards
2009 PTI Legends & Fellow Awards2009 PTI Legends & Fellow Awards
2009 PTI Legends & Fellow Awards
AMSYSCO Inc.
 
2008 PTI Awards Booklet
2008 PTI Awards Booklet2008 PTI Awards Booklet
2008 PTI Awards Booklet
AMSYSCO Inc.
 
Build for You
Build for YouBuild for You
Build for You
AMSYSCO Inc.
 
Post-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsPost-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for Contractors
AMSYSCO Inc.
 
White paper - Encapsulated Post Tensioned Concrete
White paper -  Encapsulated Post Tensioned ConcreteWhite paper -  Encapsulated Post Tensioned Concrete
White paper - Encapsulated Post Tensioned Concrete
AMSYSCO Inc.
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post Tensioning
AMSYSCO Inc.
 
Parking Today article: Louisville Arena
Parking Today article: Louisville ArenaParking Today article: Louisville Arena
Parking Today article: Louisville Arena
AMSYSCO Inc.
 

More from AMSYSCO Inc. (20)

CTBUH Innovation Award Nominee - Vertical Unbonded Post-Tensioning
CTBUH Innovation Award Nominee - Vertical Unbonded Post-TensioningCTBUH Innovation Award Nominee - Vertical Unbonded Post-Tensioning
CTBUH Innovation Award Nominee - Vertical Unbonded Post-Tensioning
 
Case Study - University of Colorado Parking Garage and Field
Case Study - University of Colorado Parking Garage and FieldCase Study - University of Colorado Parking Garage and Field
Case Study - University of Colorado Parking Garage and Field
 
Case Study - One Eleven Tower
Case Study - One Eleven TowerCase Study - One Eleven Tower
Case Study - One Eleven Tower
 
OneEleven Tower - post tensioned transfer deck
OneEleven Tower - post tensioned transfer deckOneEleven Tower - post tensioned transfer deck
OneEleven Tower - post tensioned transfer deck
 
Concrete International - Wayzata Bay Infrastructure
Concrete International - Wayzata Bay InfrastructureConcrete International - Wayzata Bay Infrastructure
Concrete International - Wayzata Bay Infrastructure
 
What Could You Buy For $263 Trillion
What Could You Buy For $263 TrillionWhat Could You Buy For $263 Trillion
What Could You Buy For $263 Trillion
 
AMSYSCO's resume of Tall Buildings
AMSYSCO's resume of Tall BuildingsAMSYSCO's resume of Tall Buildings
AMSYSCO's resume of Tall Buildings
 
One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)One Museum Park West (Post-Tensioning case study)
One Museum Park West (Post-Tensioning case study)
 
Post Tensioning Review Session for Installers
Post Tensioning Review Session for InstallersPost Tensioning Review Session for Installers
Post Tensioning Review Session for Installers
 
Infrastructure and Unbonded Post Tensioning
Infrastructure and Unbonded Post TensioningInfrastructure and Unbonded Post Tensioning
Infrastructure and Unbonded Post Tensioning
 
The Importance of Unbonded Field Certification
The Importance of Unbonded Field CertificationThe Importance of Unbonded Field Certification
The Importance of Unbonded Field Certification
 
Minnesota Twins Target Field & Post Tensioning
Minnesota Twins Target Field & Post TensioningMinnesota Twins Target Field & Post Tensioning
Minnesota Twins Target Field & Post Tensioning
 
Case Study – Social Media Small Business
Case Study – Social Media Small BusinessCase Study – Social Media Small Business
Case Study – Social Media Small Business
 
2009 PTI Legends & Fellow Awards
2009 PTI Legends & Fellow Awards2009 PTI Legends & Fellow Awards
2009 PTI Legends & Fellow Awards
 
2008 PTI Awards Booklet
2008 PTI Awards Booklet2008 PTI Awards Booklet
2008 PTI Awards Booklet
 
Build for You
Build for YouBuild for You
Build for You
 
Post-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsPost-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for Contractors
 
White paper - Encapsulated Post Tensioned Concrete
White paper -  Encapsulated Post Tensioned ConcreteWhite paper -  Encapsulated Post Tensioned Concrete
White paper - Encapsulated Post Tensioned Concrete
 
What Is Post Tensioning
What Is Post TensioningWhat Is Post Tensioning
What Is Post Tensioning
 
Parking Today article: Louisville Arena
Parking Today article: Louisville ArenaParking Today article: Louisville Arena
Parking Today article: Louisville Arena
 

Recently uploaded

Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
zubairahmad848137
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
gerogepatton
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
HODECEDSIET
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
insn4465
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
NidhalKahouli2
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
IJNSA Journal
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
mahammadsalmanmech
 

Recently uploaded (20)

Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Casting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdfCasting-Defect-inSlab continuous casting.pdf
Casting-Defect-inSlab continuous casting.pdf
 
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELDEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODEL
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
哪里办理(csu毕业证书)查尔斯特大学毕业证硕士学历原版一模一样
 
basic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdfbasic-wireline-operations-course-mahmoud-f-radwan.pdf
basic-wireline-operations-course-mahmoud-f-radwan.pdf
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSA SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMS
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
Question paper of renewable energy sources
Question paper of renewable energy sourcesQuestion paper of renewable energy sources
Question paper of renewable energy sources
 

PTI Journal : Buford Ave post-tensioned pavement

  • 1. CASE STUDIES UNBONDED POST-TENSIONING IN INFRASTRUCTURE— BUFORD AVENUE PAVEMENT RECONSTRUCTION PTI JOURNAL | August 2014 1 BY NEEL KHOSA The Buford Avenue Pavement Reconstruction project involved replacing a conventional reinforced concrete pavement with a post-tensioned concrete pavement for the University of Minnesota. The reconstruction of Buford Avenue occurred in a 220-foot stretch between Eckles Avenue and Buford Circle Road. The post-tensioned section was 102 feet long by roughly 32 feet wide (approximately 3250 square feet in area)(Fig. 1). One distinctive aspect of the project was that the road was built on top of an underground building that needed to operate during the construction phase. Due to the dete-rioration of the concrete pavement, buses and other large vehicles would produce noise and vibrations from impact at deteriorated joints which transferred through the pave-ment to the underground Saint Paul Student Center and the bookstore. The deteriorated pavement allowed storm Fig. 1—Plan view of the pavement and tendon layout. Fig. 2—Finished joint free pavement.
  • 2. CASE STUDIES water runoff to leak through the cracks to the Student Center roof below, which had previously experienced minor water problems in the bookstore. Post-tensioning was chosen as the preferred structural system due to its ability to elimi-nate joints in the large pavement area over the underground building while maintaining a 7-in. concrete thickness. “The bus tires impacting the deteriorated pavement joints rattled merchandise on the shelves and caused ceiling tile to fall in the bookstore, creating anxiety for employees and customers. Now with the new pavement, all is quiet and calm in the student center and bookstore” said Jeff Johnson, PE, SEH Project Structural Engineer. Justin Gese, PE, SEH Project Manager, explained that “we determined the new post-tensioning design was the best solution to meet the goals of the project,” which were: 1. To minimize future maintenance on this segment of roadway and increase durability; 2. To minimize vibrations and noise caused by traffic due to presence of joints, and create a raised profile with additional insulation (Fig. 2). The addi-tional insulation also provided less heat loss from the Student Center below, which minimizes the impacts of future freezing-and-thawing cycles on the pavement above; 3. To minimize formation of cracks in the segment to prevent storm water runoff migration from the roadway to the roof below. Unlike most infrastructure projects, Buford Avenue was designed with unbonded 0.6-in. post-tensioning tendons rather than precast or bonded post-tensioning tendons. 0.6-in. unbonded tendons have a final average force of 2 August 2014 | PTI JOURNAL approximately 38 kip (as compared to approximately 27 kip for 0.5-in. tendons). Encapsulated unbonded tendons were specified to meet the project’s requirement of reducing long-term corrosion or other distress for 40 years. The transverse and longitudinal post-tensioning tendons were supported by intersectional chairs on top of precast concrete blocks (Fig. 3). The support system rested above compacted sand and insulation on top of the Student Center’s under-ground bookstore. Graham Construction successfully completed the $234,000 roadway repair project within 2 month window given by the University of Minnesota—in time for the Minnesota State Fair on August 13, 2010. Graham Construc-tion hired AMSYSCO, Inc. to supply the unbonded 0.6-in. post-tensioning tendons for this expedited project. According to Neel Khosa, Vice President at AMSYSCO, “The Buford Pavement project illustrates the potential for utilizing unbonded post-tensioning in infrastructure projects such as concrete roadways or pedestrian bridges.” Neel Khosa is the Vice President of AMSYSCO, Inc. He is the Chair of CRT-30 and a voting member on M-10 and Certification Advisory Board. Mr. Khosa has a MBA from the University of Chicago and a Bachelor’s of Science in Civil Engineering from the University of Illinois. Lastly, he manages the corporate blog at www.amsyscoinc. com/our-blog which primarily deals with unbonded post-tensioned concrete. Fig. 3—Transverse section through the pavement.