This document summarizes recent construction technologies presented by Chandana Yadav. It discusses technologies like robot swarm construction using drones, carbon nanotubes to strengthen materials, self-healing concrete using capsules of healing agents, permeable plastic roads that allow water drainage, aerogel as an ultra-light insulating material, drones for advanced mapping, 3D printing for construction elements and structures, using recycled plastic to build durable roads, and holographic computers to view 3D designs overlaid on the physical world. The technologies aim to make construction faster, more sustainable and durable using innovative materials, automation, and information technologies.
The document describes two structural failures: the 1995 collapse of the Sampoong Department Store in South Korea and the 2004 Nicoll Highway incident in Singapore. The Sampoong collapse was caused by overloaded floors and weakened support columns, trapping over 1,500 people and killing 500. The Nicoll Highway incident involved the collapse of an excavation site for an MRT tunnel, caving in a highway and killing 4 workers. Recovery efforts like stabilizing the soil and monitoring nearby structures were undertaken. Learning points on construction methods and their risks were discussed.
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSASHOK KUMAR TIWARY
The document summarizes a technical seminar on advanced construction techniques for high-rise buildings. It defines high-rise buildings according to different standards, and discusses the need for high-rises due to increasing population density. Various construction methods are described, including slip forming, jump forming, and tunnel forming. Main equipment used includes tower cranes and concrete pumps. Advantages of high-rises include accommodating more people and businesses while using less land area. Disadvantages include higher construction costs and accessibility issues if elevators fail.
The document describes the foundation design for the Burj Khalifa in Dubai, the world's tallest building. The foundation system is a piled raft founded on deep deposits of carbonate soils and rocks. Extensive geotechnical investigations and testing were conducted. The tower is supported by 1.5m diameter bored piles 47.5m long, with a 3.7m thick raft at -7.55m. Load testing and analyses showed the piled raft foundation would experience settlements of 45-62mm, meeting tolerances. The foundation design and performance has exceeded expectations.
ICWES15 - Challenging Design: Foundations for Tall Buildings. Presented by M...Engineers Australia
This document discusses the challenges in designing foundations for tall buildings and provides examples of two tall building projects. It outlines the major design issues, process, and criteria for tall building foundations. It then describes the foundation systems and performance assessments for the Incheon 151 Tower in Korea and Nakheel Tall Tower in Dubai as case studies. Both cases involved complex subsurface conditions that required advanced numerical modeling to analyze foundation behavior and ensure stability and acceptable settlement.
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEMVineeshkumar K V
The document describes a robot aided tunnel inspection and maintenance system. It discusses common tunnel defects, current tunnel inspection methods, and the need for automated inspection using robotics. The system uses a robot arm mounted on a mobile platform with a specially designed tool for tasks like surface preparation, crack injection, and installing fiber reinforced polymer composites. The tool integrates cameras, lasers, and other sensors to allow automated inspection and maintenance while improving safety, efficiency, and results compared to manual methods.
This document summarizes recent construction technologies presented by Chandana Yadav. It discusses technologies like robot swarm construction using drones, carbon nanotubes to strengthen materials, self-healing concrete using capsules of healing agents, permeable plastic roads that allow water drainage, aerogel as an ultra-light insulating material, drones for advanced mapping, 3D printing for construction elements and structures, using recycled plastic to build durable roads, and holographic computers to view 3D designs overlaid on the physical world. The technologies aim to make construction faster, more sustainable and durable using innovative materials, automation, and information technologies.
The document describes two structural failures: the 1995 collapse of the Sampoong Department Store in South Korea and the 2004 Nicoll Highway incident in Singapore. The Sampoong collapse was caused by overloaded floors and weakened support columns, trapping over 1,500 people and killing 500. The Nicoll Highway incident involved the collapse of an excavation site for an MRT tunnel, caving in a highway and killing 4 workers. Recovery efforts like stabilizing the soil and monitoring nearby structures were undertaken. Learning points on construction methods and their risks were discussed.
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSASHOK KUMAR TIWARY
The document summarizes a technical seminar on advanced construction techniques for high-rise buildings. It defines high-rise buildings according to different standards, and discusses the need for high-rises due to increasing population density. Various construction methods are described, including slip forming, jump forming, and tunnel forming. Main equipment used includes tower cranes and concrete pumps. Advantages of high-rises include accommodating more people and businesses while using less land area. Disadvantages include higher construction costs and accessibility issues if elevators fail.
The document describes the foundation design for the Burj Khalifa in Dubai, the world's tallest building. The foundation system is a piled raft founded on deep deposits of carbonate soils and rocks. Extensive geotechnical investigations and testing were conducted. The tower is supported by 1.5m diameter bored piles 47.5m long, with a 3.7m thick raft at -7.55m. Load testing and analyses showed the piled raft foundation would experience settlements of 45-62mm, meeting tolerances. The foundation design and performance has exceeded expectations.
ICWES15 - Challenging Design: Foundations for Tall Buildings. Presented by M...Engineers Australia
This document discusses the challenges in designing foundations for tall buildings and provides examples of two tall building projects. It outlines the major design issues, process, and criteria for tall building foundations. It then describes the foundation systems and performance assessments for the Incheon 151 Tower in Korea and Nakheel Tall Tower in Dubai as case studies. Both cases involved complex subsurface conditions that required advanced numerical modeling to analyze foundation behavior and ensure stability and acceptable settlement.
ROBOT AIDED TUNNEL INSPECTION AND MAINTENANCE SYSTEMVineeshkumar K V
The document describes a robot aided tunnel inspection and maintenance system. It discusses common tunnel defects, current tunnel inspection methods, and the need for automated inspection using robotics. The system uses a robot arm mounted on a mobile platform with a specially designed tool for tasks like surface preparation, crack injection, and installing fiber reinforced polymer composites. The tool integrates cameras, lasers, and other sensors to allow automated inspection and maintenance while improving safety, efficiency, and results compared to manual methods.
Metropol Parasol Surface Structure Design ReportKelvin Ng
The Metropol Parasol project in Seville, Spain consists of a large wooden structure covering a public plaza. It was designed by architect Jürgen Mayer H. and took over 6 years to construct from 2005-2011. The complex wooden structure supports platforms and terraces and provides shade over the plaza below. It was constructed using innovative timber construction techniques and transfers the weight of the large wooden canopy down to concrete cores at its center.
The Marquette Plaza in Minneapolis, Minnesota was designed by architect Gunnar Birkerts and originally constructed in 1972 as the headquarters for the Federal Reserve Bank of Minneapolis. It features a unique catenary arch design supported by 16 cables strung between two towers, which gave the building its signature U-shape. The building underwent renovations from 1997-2002 that transformed it into a premier Class A office property. The suspension structure was chosen for its design to bridge over an open public plaza while maximizing sunlight and views. Loads are transferred between floors, towers, cables, and foundations through an innovative system of trusses, struts, and piles.
Ceb 706 design of reinforeced and presressed concrete updated!vishwaleenram
This document discusses prestressed concrete design. It begins with an introduction to prestressed concrete as a widely used structural material. It then covers:
1. The history of prestressed concrete in Fiji, including notable structures built with it such as the Reserve Bank of Fiji and bridges.
2. The advantages of prestressed concrete over reinforced concrete, such as increased strength, reduced cracking, and longer spans. It also discusses disadvantages like higher production costs.
3. A site visit and interview conducted at Humes Concrete to learn about their products, casting procedures, past projects, challenges, and future plans.
Over 25% of US bridges are structurally deficient or functionally obsolete, and funding for infrastructure maintenance is decreasing while needs are increasing. Structurally deficient bridges have safety issues while functionally obsolete bridges no longer meet current design standards. Deciding whether to rehabilitate or replace a bridge involves considering its structural condition, costs, impacts, regulations, and remaining lifespan, though no single algorithm can account for all factors. Bridge owners must prioritize options based on their goals, and rehabilitation is often more challenging but cheaper than replacement.
The document discusses various elements of building construction including foundations, structural systems, and types of foundations. It provides details on individual footings, pile foundations, load-bearing walls, and lateral force bracing. The key points are that foundations transfer the weight of a building to the ground, common types include individual footings and pile foundations, and structural systems include load-bearing walls, skeleton framing, and combinations of the two.
The document is a PowerPoint presentation about bridges. It discusses what bridges are, their importance, components, types of foundations, materials used, fabrication methods, classifications of bridges according to various factors like span length and structural form, loads acting on bridges, and some landmark bridges in India like the Saraighat Bridge and Howrah Bridge.
Bridge rehabilitation covers many complex engineering problems and economic issues. It involves repairing, strengthening, or replacing existing bridges to improve their structural condition and functional capabilities. The main factors that can lead to bridge deterioration include inner bridge factors like design flaws; traffic load factors from increasing vehicle loads and speeds; weather and environmental factors such as pollution and temperature fluctuations; and inadequate maintenance. Bridge rehabilitation aims to address deterioration from these sources and extend the usable life of bridges.
The document summarizes key details about the Marina Bay Sands project in Singapore. It describes the 340m long sky park with a 66.5m cantilever deck and pool. It faced challenges with the soft marine clay and sandy soil and high winds. Cofferdams were used to excavate the foundations, with piles 1.8-2.4m in diameter driven 50-60m deep. Shear walls and concrete core walls provided stability for the 57 story, 3 tower structure with 2560 rooms that was completed in 2010 for $5.7 billion.
Built in 1937, the Fallingwater Residence stands to this day as one of the greatest architectural achievements of Frank Lloyd Wright. Over time, the structure has endured a number of structural issues, which included cracking and deflection at the cantilever terraces. To ensure its historic value, contractors used post-tensioning systems to rehab a portion of the deteriorating elements. Post-tensioning allowed for hidden repairs in the floor cavity between the girders, making rehabilitation virtually invisible from many viewpoints. With repairs completed in 2002, the post-tensioned systems used proved to be a durable solution for the Fallingwater residence.
This document discusses prestressed concrete, which uses steel that is tensioned to put concrete in compression and increase its strength. There are two main types: pre-tensioned concrete, where steel is tensioned before the concrete is poured; and post-tensioned concrete, where steel is tensioned after the concrete has hardened. Post-tensioned concrete can be bonded or unbonded. Prestressed concrete allows for longer spans, thinner sections, and increased strength over traditional reinforced concrete. It has applications in buildings, bridges, parking structures, and other structures.
This document describes a project to construct a temporary bus shelter made of bamboo and other recycled materials. It discusses the design process including initial designs, final drawings and photos. The construction process is explained through sequences and progress photos. Key materials used are bamboo for the structure, plywood for subflooring and nipa palm thatching for the roof. Different types of joints and connections used in the structure are illustrated such as notching, nailing and lashing techniques. Load distribution diagrams show how stress is transferred through the curved structure. The conclusion reflects on lessons learned regarding bamboo properties, construction skills and considering strength, stiffness and stability in skeletal structures.
This document discusses stress ribbon bridges. It provides an introduction to stress ribbon bridges, describing them as slender concrete deck segments placed on bearing cables shaped like a catenary curve. It explains their construction, comparing them to simple suspension bridges. Advantages include being economical, aesthetic, environmentally friendly structures that require little material and can be erected without falsework. Stress ribbon bridges transfer loads via tension in the thin, precast concrete deck between cable-anchored abutments.
Studies in Construction Engineering of New and Existing Complex Steel Bridge...James Gregg
The US 84 Mississippi River Bridge is a 5 span cantilever truss bridge crossing the Mississippi River in Natchez,Mississippi. Two lower truss pins on the bridge shifted transversely and were flush with the outside gusset. The existing truss pins and links were removed and replaced. Temporary restraints were used to bypass the load in the truss pins and link and instrumentation used to evaluate stresses in the truss during removal.
The portfolio contains information about Caylee Griner's architectural projects and experiences. It includes summaries of a children's hospital in Boston, a courthouse in Bessemer, Alabama, an impact crater science center, a concrete bench in Auburn, and watercolor paintings from a study abroad program in Turkey. The portfolio demonstrates experience in architectural design, construction, and representation techniques across different project types and locations.
The document describes the design process of a group of students in creating a temporary bus shelter. It details their initial design which utilized wood but failed. They redesigned the shelter with a skeletal structure using steel brackets, bolts, and a concrete foundation. Key elements of the successful design include a pitched roof for rainwater, columns arranged at a 25 degree angle for stability, and horizontal V-bracing between the columns. Load testing showed the arch-shaped bracing successfully distributed compression and tension forces to withstand weather conditions.
After more than 40 years, the California home of post-tensioning pioneer Edward K. Rice, PE, FACI, stands as a testament to the durability of post-tensioning used with shrinkage-compensating Type K cement.
A structure consists of two parts, one which is supported on the other. The lower part in contact with the soil is called foundation and the upper part, the superstructure.
Thus the foundation of a structure may be defined as part of structure which is in contact with ground (usually placed below the ground), which transmit the load of structure together with imposed load and wind load to the ground.
The Aldar Headquarters in Abu Dhabi is the first spherical building in the Middle East. Designed by architect Marwan Zgheib, it has a distinctive semi-spherical shape composed of two curved glass facades linked by a narrow glazed band. With a total area of 123,000 square meters, it was constructed from 2005-2010 using an innovative diagrid structural system of triangular steel members that provided stability and allowed the curved facade. The building received silver LEED certification for its sustainable design including natural lighting, efficient systems, and waste recycling.
The Aldar Headquarters building in Abu Dhabi is the first spherical building in the Middle East. It has a diameter of 120.9 meters and stands 121 meters tall. The building's unique design includes a diagrid structural system that eliminates the need for internal columns. It also has a glass facade composed of triangular glass pieces that fit together to curve with the building's spherical shape. The building was constructed using sustainable materials and methods, such as a vacuum waste collection system and prefabricated elements, and achieved LEED Silver certification.
The document discusses the critical components and modern construction materials used to build Al Dar Headquarters, located on reclaimed land in the Persian Gulf. Some key points:
- A raft foundation was constructed using 20 million cubic meters of marine sand and 400 concrete piles to support the building's 59,000 ton weight. 12,000 cubic meters of concrete were used.
- Two separate concrete cores act as the backbone, connected by a heavy steel mesh reinforcement. Slip forms were used to pour the cores continuously without joints.
- A diagrid system of interconnected steel frames forms the signature curved external shell and channels wind loads to the cores. Triangular glass modules create the façade.
The construction site for the project will be a multi-story commercial dwelling with deep basement car park located in city centre at Smithfield where there is a high level of water content as it is in close proximity to the river Liffey, lack of space due to other buildings, traffic level are high and one way system is the only option. The design team have proposed ‘type C drained cavity’ basement that will consist of ‘secant piling system that has to be delivered in accordance with the project schedule.
Case study: Widening an existing bridge structure Challenges and solutionsIRJET Journal
This document summarizes the process of widening an existing bridge in the UAE. It faced several challenges, including replacing deteriorated bearings, repairing cracks and defects found after removing pavement, constructing approach slabs where there were none previously, addressing differences in cross-slope between the existing and new structures, protecting the deck from chemicals, and strengthening an existing pier with carbon fiber reinforced polymer sheets. These challenges were addressed through methods like jacking the bridge to replace bearings, repairing cracks, constructing new approach slabs, using leveling concrete to create uniform cross-slope, applying waterproofing, and installing CFRP sheets to strengthen the pier according to product specifications. The widening resulted in two bridges with four
Metropol Parasol Surface Structure Design ReportKelvin Ng
The Metropol Parasol project in Seville, Spain consists of a large wooden structure covering a public plaza. It was designed by architect Jürgen Mayer H. and took over 6 years to construct from 2005-2011. The complex wooden structure supports platforms and terraces and provides shade over the plaza below. It was constructed using innovative timber construction techniques and transfers the weight of the large wooden canopy down to concrete cores at its center.
The Marquette Plaza in Minneapolis, Minnesota was designed by architect Gunnar Birkerts and originally constructed in 1972 as the headquarters for the Federal Reserve Bank of Minneapolis. It features a unique catenary arch design supported by 16 cables strung between two towers, which gave the building its signature U-shape. The building underwent renovations from 1997-2002 that transformed it into a premier Class A office property. The suspension structure was chosen for its design to bridge over an open public plaza while maximizing sunlight and views. Loads are transferred between floors, towers, cables, and foundations through an innovative system of trusses, struts, and piles.
Ceb 706 design of reinforeced and presressed concrete updated!vishwaleenram
This document discusses prestressed concrete design. It begins with an introduction to prestressed concrete as a widely used structural material. It then covers:
1. The history of prestressed concrete in Fiji, including notable structures built with it such as the Reserve Bank of Fiji and bridges.
2. The advantages of prestressed concrete over reinforced concrete, such as increased strength, reduced cracking, and longer spans. It also discusses disadvantages like higher production costs.
3. A site visit and interview conducted at Humes Concrete to learn about their products, casting procedures, past projects, challenges, and future plans.
Over 25% of US bridges are structurally deficient or functionally obsolete, and funding for infrastructure maintenance is decreasing while needs are increasing. Structurally deficient bridges have safety issues while functionally obsolete bridges no longer meet current design standards. Deciding whether to rehabilitate or replace a bridge involves considering its structural condition, costs, impacts, regulations, and remaining lifespan, though no single algorithm can account for all factors. Bridge owners must prioritize options based on their goals, and rehabilitation is often more challenging but cheaper than replacement.
The document discusses various elements of building construction including foundations, structural systems, and types of foundations. It provides details on individual footings, pile foundations, load-bearing walls, and lateral force bracing. The key points are that foundations transfer the weight of a building to the ground, common types include individual footings and pile foundations, and structural systems include load-bearing walls, skeleton framing, and combinations of the two.
The document is a PowerPoint presentation about bridges. It discusses what bridges are, their importance, components, types of foundations, materials used, fabrication methods, classifications of bridges according to various factors like span length and structural form, loads acting on bridges, and some landmark bridges in India like the Saraighat Bridge and Howrah Bridge.
Bridge rehabilitation covers many complex engineering problems and economic issues. It involves repairing, strengthening, or replacing existing bridges to improve their structural condition and functional capabilities. The main factors that can lead to bridge deterioration include inner bridge factors like design flaws; traffic load factors from increasing vehicle loads and speeds; weather and environmental factors such as pollution and temperature fluctuations; and inadequate maintenance. Bridge rehabilitation aims to address deterioration from these sources and extend the usable life of bridges.
The document summarizes key details about the Marina Bay Sands project in Singapore. It describes the 340m long sky park with a 66.5m cantilever deck and pool. It faced challenges with the soft marine clay and sandy soil and high winds. Cofferdams were used to excavate the foundations, with piles 1.8-2.4m in diameter driven 50-60m deep. Shear walls and concrete core walls provided stability for the 57 story, 3 tower structure with 2560 rooms that was completed in 2010 for $5.7 billion.
Built in 1937, the Fallingwater Residence stands to this day as one of the greatest architectural achievements of Frank Lloyd Wright. Over time, the structure has endured a number of structural issues, which included cracking and deflection at the cantilever terraces. To ensure its historic value, contractors used post-tensioning systems to rehab a portion of the deteriorating elements. Post-tensioning allowed for hidden repairs in the floor cavity between the girders, making rehabilitation virtually invisible from many viewpoints. With repairs completed in 2002, the post-tensioned systems used proved to be a durable solution for the Fallingwater residence.
This document discusses prestressed concrete, which uses steel that is tensioned to put concrete in compression and increase its strength. There are two main types: pre-tensioned concrete, where steel is tensioned before the concrete is poured; and post-tensioned concrete, where steel is tensioned after the concrete has hardened. Post-tensioned concrete can be bonded or unbonded. Prestressed concrete allows for longer spans, thinner sections, and increased strength over traditional reinforced concrete. It has applications in buildings, bridges, parking structures, and other structures.
This document describes a project to construct a temporary bus shelter made of bamboo and other recycled materials. It discusses the design process including initial designs, final drawings and photos. The construction process is explained through sequences and progress photos. Key materials used are bamboo for the structure, plywood for subflooring and nipa palm thatching for the roof. Different types of joints and connections used in the structure are illustrated such as notching, nailing and lashing techniques. Load distribution diagrams show how stress is transferred through the curved structure. The conclusion reflects on lessons learned regarding bamboo properties, construction skills and considering strength, stiffness and stability in skeletal structures.
This document discusses stress ribbon bridges. It provides an introduction to stress ribbon bridges, describing them as slender concrete deck segments placed on bearing cables shaped like a catenary curve. It explains their construction, comparing them to simple suspension bridges. Advantages include being economical, aesthetic, environmentally friendly structures that require little material and can be erected without falsework. Stress ribbon bridges transfer loads via tension in the thin, precast concrete deck between cable-anchored abutments.
Studies in Construction Engineering of New and Existing Complex Steel Bridge...James Gregg
The US 84 Mississippi River Bridge is a 5 span cantilever truss bridge crossing the Mississippi River in Natchez,Mississippi. Two lower truss pins on the bridge shifted transversely and were flush with the outside gusset. The existing truss pins and links were removed and replaced. Temporary restraints were used to bypass the load in the truss pins and link and instrumentation used to evaluate stresses in the truss during removal.
The portfolio contains information about Caylee Griner's architectural projects and experiences. It includes summaries of a children's hospital in Boston, a courthouse in Bessemer, Alabama, an impact crater science center, a concrete bench in Auburn, and watercolor paintings from a study abroad program in Turkey. The portfolio demonstrates experience in architectural design, construction, and representation techniques across different project types and locations.
The document describes the design process of a group of students in creating a temporary bus shelter. It details their initial design which utilized wood but failed. They redesigned the shelter with a skeletal structure using steel brackets, bolts, and a concrete foundation. Key elements of the successful design include a pitched roof for rainwater, columns arranged at a 25 degree angle for stability, and horizontal V-bracing between the columns. Load testing showed the arch-shaped bracing successfully distributed compression and tension forces to withstand weather conditions.
After more than 40 years, the California home of post-tensioning pioneer Edward K. Rice, PE, FACI, stands as a testament to the durability of post-tensioning used with shrinkage-compensating Type K cement.
A structure consists of two parts, one which is supported on the other. The lower part in contact with the soil is called foundation and the upper part, the superstructure.
Thus the foundation of a structure may be defined as part of structure which is in contact with ground (usually placed below the ground), which transmit the load of structure together with imposed load and wind load to the ground.
The Aldar Headquarters in Abu Dhabi is the first spherical building in the Middle East. Designed by architect Marwan Zgheib, it has a distinctive semi-spherical shape composed of two curved glass facades linked by a narrow glazed band. With a total area of 123,000 square meters, it was constructed from 2005-2010 using an innovative diagrid structural system of triangular steel members that provided stability and allowed the curved facade. The building received silver LEED certification for its sustainable design including natural lighting, efficient systems, and waste recycling.
The Aldar Headquarters building in Abu Dhabi is the first spherical building in the Middle East. It has a diameter of 120.9 meters and stands 121 meters tall. The building's unique design includes a diagrid structural system that eliminates the need for internal columns. It also has a glass facade composed of triangular glass pieces that fit together to curve with the building's spherical shape. The building was constructed using sustainable materials and methods, such as a vacuum waste collection system and prefabricated elements, and achieved LEED Silver certification.
The document discusses the critical components and modern construction materials used to build Al Dar Headquarters, located on reclaimed land in the Persian Gulf. Some key points:
- A raft foundation was constructed using 20 million cubic meters of marine sand and 400 concrete piles to support the building's 59,000 ton weight. 12,000 cubic meters of concrete were used.
- Two separate concrete cores act as the backbone, connected by a heavy steel mesh reinforcement. Slip forms were used to pour the cores continuously without joints.
- A diagrid system of interconnected steel frames forms the signature curved external shell and channels wind loads to the cores. Triangular glass modules create the façade.
The construction site for the project will be a multi-story commercial dwelling with deep basement car park located in city centre at Smithfield where there is a high level of water content as it is in close proximity to the river Liffey, lack of space due to other buildings, traffic level are high and one way system is the only option. The design team have proposed ‘type C drained cavity’ basement that will consist of ‘secant piling system that has to be delivered in accordance with the project schedule.
Case study: Widening an existing bridge structure Challenges and solutionsIRJET Journal
This document summarizes the process of widening an existing bridge in the UAE. It faced several challenges, including replacing deteriorated bearings, repairing cracks and defects found after removing pavement, constructing approach slabs where there were none previously, addressing differences in cross-slope between the existing and new structures, protecting the deck from chemicals, and strengthening an existing pier with carbon fiber reinforced polymer sheets. These challenges were addressed through methods like jacking the bridge to replace bearings, repairing cracks, constructing new approach slabs, using leveling concrete to create uniform cross-slope, applying waterproofing, and installing CFRP sheets to strengthen the pier according to product specifications. The widening resulted in two bridges with four
This document discusses water intrusion in the I-93 tunnels in Boston and efforts to seal leaks. It notes that some water intrusion is normal during tunnel construction and leaks are typically sealed through pressure grouting of cracks in the concrete. While the tunnels experience more leaks currently than completed tunnels, the amount of leakage is within industry norms. Efforts to seal leaks through grouting are standard practice and will continue through project completion to further reduce water intrusion.
This document summarizes the rehabilitation of a failing mechanically stabilized earth retaining wall using permanent soil nails. An investigation found the wall was failing due to improper drainage, unsuitable backfill compaction, and other factors. Ninety-three permanent soil nails were installed through the existing precast concrete panels to depths of up to 40 feet using a hydraulic rotary percussion drill. Verification testing of test nails found lower pullout capacities than initially estimated, requiring nail lengths to increase by 33% on redesign. Construction challenges including high entry points and utilities were addressed through specialized drilling methods and equipment.
The document summarizes the planning, analysis, and design of a prestressed concrete bridge. It includes the design of various components like the deck slab, beams, piers, footings, and pile foundations. The bridge is a single span of 30 meters made of M40-M45 grade concrete and high strength steel tendons. The design considers aspects like dead and live loads, shear forces, bending moments, reinforcement requirements, and stress limits to construct the different elements of the prestressed concrete bridge according to code specifications.
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESA Makwana
The document discusses expansion joints in civil engineering structures. It defines expansion joints as gaps provided in structures to allow for movement due to temperature changes and prevent cracking. It describes the different types of joints used in concrete and factors that affect the need for expansion joints like material properties and building size. The document outlines best practices for expansion joint design, including proper spacing and installation. It discusses common expansion joint materials like joint fillers, sealing compounds, and water bars used to make the joints watertight. The document also presents a case study on issues with untreated or poorly installed expansion joints like leakage and cracking.
This document summarizes research presented at the 2015 Transportation Research Board meeting regarding new approaches to bridge construction.
Researchers at LSU developed a new approach slab system using precast deck slabs paired with geotextile-reinforced embankments to eliminate differential settlement issues that cause "end bumps" at bridge approaches in Louisiana. Field testing over two years showed the new system had better performance than traditional methods.
Additional research showed that connections and grouts used in precast deck panels are critical to their long-term performance. Tests identified best practices for surface preparation, grout selection, and design considerations to ensure durability of the connections under loading.
Other research presented testing of a hybrid jacketing
This document discusses methods of prestressing concrete, including pretensioning and post-tensioning. Pretensioning involves stressing steel tendons before concrete is poured around them. Post-tensioning involves stressing steel tendons inserted into voids in cured concrete using jacks. Both methods put the concrete in compression and improve its tensile strength. Common applications include building floors/roofs, bridges, and parking structures.
This document discusses different methods of prestressing concrete, including pretensioning and post-tensioning. Pretensioning involves stressing steel tendons before placing concrete around them, while post-tensioning involves stressing tendons after the concrete has cured using hydraulic jacks. Post-tensioning allows for longer spans, thinner slabs, and more architectural freedom compared to conventional reinforced concrete or pretensioned concrete. Common applications of post-tensioning include parking structures, bridges, and building floors and roofs.
The document provides information on methods of prestressing in concrete, including pretensioning and post-tensioning. It discusses:
- Pretensioning involves stressing steel tendons before the concrete is cast around them.
- Post-tensioning involves stressing steel tendons after the concrete has cured using jacks, then grouting the voids.
- Both methods put the concrete in compression and increase its strength and durability compared to conventional reinforced concrete.
The document provides information on methods of prestressing concrete, including pretensioning and post-tensioning. It discusses:
- Pretensioning involves stressing steel tendons before the concrete is cast around them.
- Post-tensioning involves stressing steel tendons after the concrete has cured using jacks, then grouting the voids.
- Both methods put the concrete in compression and increase its strength and durability compared to conventional reinforced concrete.
Performance of ibs precast concrete beam column connections under earthquake ...Ramin Vaghei
This literature review examines the performance of precast concrete beam-column connections under earthquake effects. It finds that the seismic performance of precast structures depends greatly on the ductility of connectors joining components like beams and columns. Two commonly used connectors identified are the hybrid post-tensioned beam-column connection and the Dywidag Ductile Connector. The review concludes that future research could optimize these connections for use in low seismicity regions, with a focus on practical designs that do not further impede precast construction acceptance.
This document summarizes various topics related to the design of deep excavations, including different types of earth retaining walls, water pressures and related problems, earth pressures, types of wall support, stability analyses, displacements, and instrumentation. The types of retaining walls discussed include braced walls, sheet pile walls, pile walls, diaphragm walls, reinforced concrete walls, soil nail walls, cofferdams, and caissons. The document provides details on the characteristics and suitable applications of each wall type. It also discusses water pressures, dewatering needs, and soil investigations related to groundwater conditions.
Review on studies and research on widening of existing concrete bridgesIRJET Journal
This document summarizes several studies that have been conducted on widening existing concrete bridges. It describes a study from China that examined load distribution factors for a bridge widened with composite steel-concrete girders. It also outlines challenges and solutions for widening a bridge in the UAE, including replacing bearings and stitching the new and existing structures. Additionally, it discusses two bridge widening projects in New Zealand that involved adding precast beams and stitching to connect structures. Finally, safety measures and challenges for strengthening a historic bridge in Switzerland under live traffic are presented.
The precast channel system (U-Ditch) is one of the innovations of precast concrete
designated as a channel for drainage and irrigation systems. The U-Ditch must have
sufficient bending capacity to carry a major load due to ground pressure. However,
the addition of wall thickness will lead to the heavy construction product. Therefore, a
new product innovation was developed in this study, where the wall thickness was
reduced and strengthened using fiber reinforced polymer (FRP). In these regards, this
study aims to investigate the effect of FRP strengthening on the behavior of precast
channel systems. Three types of specimens were tested in this study. Type N was
normal U-ditch which without a reduction of wall thickness. Type C was U-ditch with
a reduction of wall thickness (corrugate). Type CF was U-ditch with a reduction of
wall thickness (corrugate) and strengthened using fiber reinforced polymer (FRP).
The dimension of all specimens was 500x500x1000 mm3. The specimens were tested
based on Japan Industrial Standard (JIS). The results indicated that the weight
reduction can be achieved by reducing the wall thickness in the area between the main
reinforcement. However, it reduced the bending capacity of the wall. The
strengthening using FRP sheet in the thickness reduction section was effectively to
increase the bending capacity of wall, which had relatively the same with Type N
(normal). Finally, all the specimens failed due to the flexural cracks around hook area
of the precast channel
The document discusses the design and construction challenges of the Deh Cho Bridge in the Northwest Territories of Canada. Some key points:
- The bridge crosses the Mackenzie River and connects Yellowknife to Highway 1, replacing a ferry. Its remote northern location and extreme winter conditions of -40°C posed challenges.
- An innovative extradosed bridge design was used with a 1045m continuous superstructure and expansion joints only at the abutments.
- Construction methods like incremental launching and extensive prefabrication were employed to minimize field work during the short construction season.
- Rigorous shop trial assembly and quality control processes were required given the remote site and need to minimize repairs.
This document summarizes research on post-tensioning in buildings. It details the history of post-tensioning from its origins in the 1940s-1950s to its use in the first high-rise building with post-tensioned slabs in 1956. The document then discusses the benefits of post-tensioned slabs and methodology used in the research, including monitoring a construction site. Test results are presented analyzing properties of post-tensioned concrete mixes. The research concludes that post-tensioned slabs provide construction speed and cost benefits compared to reinforced concrete.
This document discusses prestressed concrete, which uses tensioned steel cables or bars to put concrete members into compression and increase their strength. It describes three main methods: pre-tensioned concrete where the steel is tensioned before the concrete is cast; bonded post-tensioned concrete where steel is tensioned after casting to compress the concrete; and unbonded post-tensioned concrete where greased steel is used to allow individual adjustment. Applications include buildings, bridges, nuclear reactors and earthquake resistant structures. Advantages are lower costs, thinner members, and increased spans.
CTBUH Innovation Award Nominee - Vertical Unbonded Post-TensioningAMSYSCO Inc.
AMSYSCO's submission for the CTBUH's (Council on Tall Buildings and Urban Habitat) 2015 Innovation Award. Along with post-tensioned slabs and transfer deck, unbonded post-tensioned was used in vertical shear walls.
Case Study - University of Colorado Parking Garage and FieldAMSYSCO Inc.
The University of Colorado Colorado Springs (UCCS)
needed more campus parking for the Alpine Village student
housing complex. In addition, the UCCS planning board
approved financing to expand their sporting complex.
This project served two purposes: a parking structure
that acted as a recreational field. The 1200-car, four-story
post-tensioned (PT) parking structure supported the
240 x 360 ft (73 x 110 m) artificial turf field on the roof
level.
The high-rise building located at 111 W. Wacker Drive
in downtown Chicago, IL, was formerly known as the “Waterview.” The structure was originally designed as an 89-story luxury hotel located along the Chicago River. The construction of the conventionally-reinforced building progressed until the 27th floor, when it was shelved due to financing issues. In 2012, the hotel was redesigned as a 60-story residential apartment building and renamed “OneEleven.”
OneEleven Tower - post tensioned transfer deckAMSYSCO Inc.
The high-rise building located at 111 W. Wacker Drive in downtown Chicago was formerly known as the ‘Waterview.’ The structure was originally designed as an 89-story luxury hotel located along the Chicago River. The construction of the conventionally-reinforced building progressed until the 27th floor when the 2007 economic recession hit the U.S. Ultimately, the original project was shelved due to financing issues. The unfinished building became a visible eye-sore in the heart of Chicago for several years. Fortunately, a consortium of creditors and lienholders (Clark Wacker LLC) took ownership of the project and formed a Joint Venture with Related Midwest in 2010.
In 2012, the hotel was redesigned as a 60-story residential apartment building and renamed ‘OneEleven.’ There were several major design issues with converting a hotel into a 500-unit apartment with a smaller floor-plate and different column layout. Since the column were poured until the 28th floor, this floor was built as originally designed. The 29th floor was constructed with a 12-inch post-tensioned slab and functioned as an amenity level.
What separates this high-rise tower from others is the 60-inch transfer deck (located on the 30th floor). The transfer deck was designed to be a 72-inch conventionally-reinforced slab with the post-tensioned floors above. The PT Supplier and Concrete Contractor redesigned it into a 60-inch thick slab using post-tensioned to replace roughly 372 tons of rebar. The redesign saved around $380,000 from the cost of the transfer deck (excluding costs of other vertical elements). The reduced dead load of the slab also helped eliminate the reshoring requirements. The 12-inch building height reduction funneled into lower costs for all vertical elements and lower operational energy costs. A flat-plate was used in lieu of large beams and transfer girders in order to reduce forming costs.
The installation of the transfer slab and coordination of trades was extremely complex. Additionally, the coordination was fast-paced since the transfer slab was the second floor of the new construction. Construction trades and engineer spent almost one month on coordinating PT tendons, rebar and MEP piping/penetrations.
The transfer mat was poured in two lifts (20-inch and 40-inch lifts) for a total of roughly 2,250 cubic yards of 6000 psi concrete. One of the pours lasted 17 hours – and had an increased degree of complexity due to being poured mid-air. In total, there was 60 tons of unbonded-post-tensioning (gross weight) used in the transfer deck.
The use of unbonded post-tensioning in the original design was also used to reduce the high-rise building height by at least 1” per floor as compared to mildly-reinforced concrete. PT helped make a stalled project more economical due to the reduction in material costs (concrete columns/walls, MEP piping, elevators/stairs and curtain-wall).
Each tower has 750,000 square feet of space with 50 floors and 10 units per floor of 15,000 square feet. There are 7.1 billion people in the world that would require 2.85 million towers of 500 units each to house the world's population at 5 people per unit. At a cost of $92 million per tower, it would cost over $262 trillion to house the entire world's population.
This document provides a list of 64 buildings in the United States with details including their height in meters and feet, number of floors, year completed, and primary construction material and use. The tallest is Aqua in Chicago at 261.8 meters (859 feet) with 86 floors completed in 2009 using concrete for residential and hotel use. The shortest is Clark and Grand Hotels in Chicago with unspecified height and floors completed in 2013 using concrete for hotel use.
One Museum Park West (Post-Tensioning case study)AMSYSCO Inc.
The One Museum Park West high-rise condominium tower in Chicago was originally designed with conventionally reinforced concrete slabs and transfer girders, but went over budget. A value engineering analysis proposed converting the structural design to unbonded post-tensioning, which would reduce costs by deleting some interior columns, transfer girders, and reducing girder depths. This option was chosen and resulted in $4 million in savings through reductions to concrete, rebar, forming costs, and other structure elements like caissons and walls. The post-tensioning supplier worked with the engineer of record to implement the new design, which increased PT usage from an initial 35,000 feet to 1.6 million feet and helped complete
Infrastructure and Unbonded Post TensioningAMSYSCO Inc.
The document discusses the use of unbonded post-tensioning for infrastructure projects. It begins with an overview of concrete versus asphalt pavements. Unbonded post-tensioning can be used for applications like airport runways, parking lots, and pedestrian bridges. The document then presents three case studies where unbonded post-tensioning was used: a road project in Wayzata Bay with poor soil conditions, an emergency vehicle operator course, and a reconstruction project on Buford Avenue. It concludes that unbonded encapsulated post-tensioning is an effective alternative to reinforced concrete or asphalt for infrastructure projects.
The Importance of Unbonded Field CertificationAMSYSCO Inc.
This document summarizes the Post-Tensioning Institute's (PTI) Unbonded Post-Tensioning Field Personnel Certification program. It outlines the various certification levels including Level 1 Field Installation, Level 1 and 2 Inspector, and Level 1 and 2 Ironworker. It provides information on registration prerequisites, training workshops, certification requirements, benefits of certification for projects, contractors, installers and individuals, as well as testimonials and the certification schedule. The goal of the program is to satisfy building code requirements and improve quality, safety, productivity and profitability through certified personnel.
Minnesota Twins Target Field & Post TensioningAMSYSCO Inc.
Presentation by Neel Khosa given during the Post-Tensioning Institute's 2011 Technical Conference. Topic is about the use of unbonded post-tensioned concrete in Target Field stadium, home of the Minnesota Twins MLB team.
Abridged version of the Post-Tensioning Institute's 2009 Legends and Fellows Award ceremony. Rattan Khosa, President of AMSYSCO, Inc., received a PTI Fellows Award.
Abridged version of the Post-Tensioning Institute booklet for the 2008 Project Awards. The New Guthrie Theater Center in Minneapolis, MN won the Project-of-the-Year. Post-tensioning was supplied by AMSYSCO, Inc. The Architect was Jean Nouvel, the Engineer was Erickson Roed & Associates, and the Contractor was McGough Construction.
This document provides information about a company called Amsysco Inc. that has been manufacturing post-tensioned concrete buildings since 1981. They help customers entertain friends, reinforce foundations for the future, store vehicles while away, and reach career goals through their post-tensioned concrete products and services. Amsysco has been in business since 1981 and is PTI-certified for manufacturing.
Post-Tension Concrete - Info session for ContractorsAMSYSCO Inc.
This presentation is to help General and Concrete Contractors manage construction projects that use Post-Tensioned Concrete.
1. Intro to Post-Tension
2. Components of Post-Tension
3. Construction Team
4. Submittals
5. Pre-Installation
6. Installation Management
7. Post-Concrete Placement
8. Troubleshooting
Post-tensioning is a method of reinforcing (strengthening) concrete or other materials with high-strength steel strands or bars, typically referred to as tendons. Post-tensioning applications include office and apartment buildings, parking structures, slabs-on-ground, bridges, sports stadiums, rock and soil anchors, and water-tanks.
>>>Published by Post-Tensioning Institute
Parking Today article: Louisville ArenaAMSYSCO Inc.
The Louisville Arena and Parking Structure project was covered in the September 2009 issue of Parking Today Magazine, a leading publication serving the parking industry.
In the article, Neel Khosa of AMSYSCO discusses why post tensioned concrete was used for the marquee project in Louisville, Kentucky. Additionally, representatives from Walter P. Moore (Structural Engineer – Arena), Populous (Architect) and QK4 (Structural Engineer – Garage) describe how the project benefited from the use of unbonded post-tensioning in the Arena and Garage.
Embedded machine learning-based road conditions and driving behavior monitoringIJECEIAES
Car accident rates have increased in recent years, resulting in losses in human lives, properties, and other financial costs. An embedded machine learning-based system is developed to address this critical issue. The system can monitor road conditions, detect driving patterns, and identify aggressive driving behaviors. The system is based on neural networks trained on a comprehensive dataset of driving events, driving styles, and road conditions. The system effectively detects potential risks and helps mitigate the frequency and impact of accidents. The primary goal is to ensure the safety of drivers and vehicles. Collecting data involved gathering information on three key road events: normal street and normal drive, speed bumps, circular yellow speed bumps, and three aggressive driving actions: sudden start, sudden stop, and sudden entry. The gathered data is processed and analyzed using a machine learning system designed for limited power and memory devices. The developed system resulted in 91.9% accuracy, 93.6% precision, and 92% recall. The achieved inference time on an Arduino Nano 33 BLE Sense with a 32-bit CPU running at 64 MHz is 34 ms and requires 2.6 kB peak RAM and 139.9 kB program flash memory, making it suitable for resource-constrained embedded systems.
DEEP LEARNING FOR SMART GRID INTRUSION DETECTION: A HYBRID CNN-LSTM-BASED MODELgerogepatton
As digital technology becomes more deeply embedded in power systems, protecting the communication
networks of Smart Grids (SG) has emerged as a critical concern. Distributed Network Protocol 3 (DNP3)
represents a multi-tiered application layer protocol extensively utilized in Supervisory Control and Data
Acquisition (SCADA)-based smart grids to facilitate real-time data gathering and control functionalities.
Robust Intrusion Detection Systems (IDS) are necessary for early threat detection and mitigation because
of the interconnection of these networks, which makes them vulnerable to a variety of cyberattacks. To
solve this issue, this paper develops a hybrid Deep Learning (DL) model specifically designed for intrusion
detection in smart grids. The proposed approach is a combination of the Convolutional Neural Network
(CNN) and the Long-Short-Term Memory algorithms (LSTM). We employed a recent intrusion detection
dataset (DNP3), which focuses on unauthorized commands and Denial of Service (DoS) cyberattacks, to
train and test our model. The results of our experiments show that our CNN-LSTM method is much better
at finding smart grid intrusions than other deep learning algorithms used for classification. In addition,
our proposed approach improves accuracy, precision, recall, and F1 score, achieving a high detection
accuracy rate of 99.50%.
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMHODECEDSIET
Time Division Multiplexing (TDM) is a method of transmitting multiple signals over a single communication channel by dividing the signal into many segments, each having a very short duration of time. These time slots are then allocated to different data streams, allowing multiple signals to share the same transmission medium efficiently. TDM is widely used in telecommunications and data communication systems.
### How TDM Works
1. **Time Slots Allocation**: The core principle of TDM is to assign distinct time slots to each signal. During each time slot, the respective signal is transmitted, and then the process repeats cyclically. For example, if there are four signals to be transmitted, the TDM cycle will divide time into four slots, each assigned to one signal.
2. **Synchronization**: Synchronization is crucial in TDM systems to ensure that the signals are correctly aligned with their respective time slots. Both the transmitter and receiver must be synchronized to avoid any overlap or loss of data. This synchronization is typically maintained by a clock signal that ensures time slots are accurately aligned.
3. **Frame Structure**: TDM data is organized into frames, where each frame consists of a set of time slots. Each frame is repeated at regular intervals, ensuring continuous transmission of data streams. The frame structure helps in managing the data streams and maintaining the synchronization between the transmitter and receiver.
4. **Multiplexer and Demultiplexer**: At the transmitting end, a multiplexer combines multiple input signals into a single composite signal by assigning each signal to a specific time slot. At the receiving end, a demultiplexer separates the composite signal back into individual signals based on their respective time slots.
### Types of TDM
1. **Synchronous TDM**: In synchronous TDM, time slots are pre-assigned to each signal, regardless of whether the signal has data to transmit or not. This can lead to inefficiencies if some time slots remain empty due to the absence of data.
2. **Asynchronous TDM (or Statistical TDM)**: Asynchronous TDM addresses the inefficiencies of synchronous TDM by allocating time slots dynamically based on the presence of data. Time slots are assigned only when there is data to transmit, which optimizes the use of the communication channel.
### Applications of TDM
- **Telecommunications**: TDM is extensively used in telecommunication systems, such as in T1 and E1 lines, where multiple telephone calls are transmitted over a single line by assigning each call to a specific time slot.
- **Digital Audio and Video Broadcasting**: TDM is used in broadcasting systems to transmit multiple audio or video streams over a single channel, ensuring efficient use of bandwidth.
- **Computer Networks**: TDM is used in network protocols and systems to manage the transmission of data from multiple sources over a single network medium.
### Advantages of TDM
- **Efficient Use of Bandwidth**: TDM all
A review on techniques and modelling methodologies used for checking electrom...nooriasukmaningtyas
The proper function of the integrated circuit (IC) in an inhibiting electromagnetic environment has always been a serious concern throughout the decades of revolution in the world of electronics, from disjunct devices to today’s integrated circuit technology, where billions of transistors are combined on a single chip. The automotive industry and smart vehicles in particular, are confronting design issues such as being prone to electromagnetic interference (EMI). Electronic control devices calculate incorrect outputs because of EMI and sensors give misleading values which can prove fatal in case of automotives. In this paper, the authors have non exhaustively tried to review research work concerned with the investigation of EMI in ICs and prediction of this EMI using various modelling methodologies and measurement setups.
A SYSTEMATIC RISK ASSESSMENT APPROACH FOR SECURING THE SMART IRRIGATION SYSTEMSIJNSA Journal
The smart irrigation system represents an innovative approach to optimize water usage in agricultural and landscaping practices. The integration of cutting-edge technologies, including sensors, actuators, and data analysis, empowers this system to provide accurate monitoring and control of irrigation processes by leveraging real-time environmental conditions. The main objective of a smart irrigation system is to optimize water efficiency, minimize expenses, and foster the adoption of sustainable water management methods. This paper conducts a systematic risk assessment by exploring the key components/assets and their functionalities in the smart irrigation system. The crucial role of sensors in gathering data on soil moisture, weather patterns, and plant well-being is emphasized in this system. These sensors enable intelligent decision-making in irrigation scheduling and water distribution, leading to enhanced water efficiency and sustainable water management practices. Actuators enable automated control of irrigation devices, ensuring precise and targeted water delivery to plants. Additionally, the paper addresses the potential threat and vulnerabilities associated with smart irrigation systems. It discusses limitations of the system, such as power constraints and computational capabilities, and calculates the potential security risks. The paper suggests possible risk treatment methods for effective secure system operation. In conclusion, the paper emphasizes the significant benefits of implementing smart irrigation systems, including improved water conservation, increased crop yield, and reduced environmental impact. Additionally, based on the security analysis conducted, the paper recommends the implementation of countermeasures and security approaches to address vulnerabilities and ensure the integrity and reliability of the system. By incorporating these measures, smart irrigation technology can revolutionize water management practices in agriculture, promoting sustainability, resource efficiency, and safeguarding against potential security threats.
Using recycled concrete aggregates (RCA) for pavements is crucial to achieving sustainability. Implementing RCA for new pavement can minimize carbon footprint, conserve natural resources, reduce harmful emissions, and lower life cycle costs. Compared to natural aggregate (NA), RCA pavement has fewer comprehensive studies and sustainability assessments.
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Sinan KOZAK
Sinan from the Delivery Hero mobile infrastructure engineering team shares a deep dive into performance acceleration with Gradle build cache optimizations. Sinan shares their journey into solving complex build-cache problems that affect Gradle builds. By understanding the challenges and solutions found in our journey, we aim to demonstrate the possibilities for faster builds. The case study reveals how overlapping outputs and cache misconfigurations led to significant increases in build times, especially as the project scaled up with numerous modules using Paparazzi tests. The journey from diagnosing to defeating cache issues offers invaluable lessons on maintaining cache integrity without sacrificing functionality.
Introduction- e - waste – definition - sources of e-waste– hazardous substances in e-waste - effects of e-waste on environment and human health- need for e-waste management– e-waste handling rules - waste minimization techniques for managing e-waste – recycling of e-waste - disposal treatment methods of e- waste – mechanism of extraction of precious metal from leaching solution-global Scenario of E-waste – E-waste in India- case studies.
ACEP Magazine edition 4th launched on 05.06.2024Rahul
This document provides information about the third edition of the magazine "Sthapatya" published by the Association of Civil Engineers (Practicing) Aurangabad. It includes messages from current and past presidents of ACEP, memories and photos from past ACEP events, information on life time achievement awards given by ACEP, and a technical article on concrete maintenance, repairs and strengthening. The document highlights activities of ACEP and provides a technical educational article for members.
1. CASE STUDIES
UNBONDED POST-TENSIONING IN INFRASTRUCTURE—
BUFORD AVENUE PAVEMENT RECONSTRUCTION
PTI JOURNAL | August 2014 1
BY NEEL KHOSA
The Buford Avenue Pavement Reconstruction project
involved replacing a conventional reinforced concrete
pavement with a post-tensioned concrete pavement for
the University of Minnesota. The reconstruction of Buford
Avenue occurred in a 220-foot stretch between Eckles
Avenue and Buford Circle Road. The post-tensioned
section was 102 feet long by roughly 32 feet wide
(approximately 3250 square feet in area)(Fig. 1).
One distinctive aspect of the project was that the road
was built on top of an underground building that needed
to operate during the construction phase. Due to the dete-rioration
of the concrete pavement, buses and other large
vehicles would produce noise and vibrations from impact
at deteriorated joints which transferred through the pave-ment
to the underground Saint Paul Student Center and
the bookstore. The deteriorated pavement allowed storm
Fig. 1—Plan view of the pavement and tendon layout.
Fig. 2—Finished joint free pavement.
2. CASE STUDIES
water runoff to leak through the cracks to the Student Center
roof below, which had previously experienced minor water
problems in the bookstore. Post-tensioning was chosen as
the preferred structural system due to its ability to elimi-nate
joints in the large pavement area over the underground
building while maintaining a 7-in. concrete thickness.
“The bus tires impacting the deteriorated pavement joints
rattled merchandise on the shelves and caused ceiling tile
to fall in the bookstore, creating anxiety for employees and
customers. Now with the new pavement, all is quiet and
calm in the student center and bookstore” said Jeff Johnson,
PE, SEH Project Structural Engineer.
Justin Gese, PE, SEH Project Manager, explained that
“we determined the new post-tensioning design was the
best solution to meet the goals of the project,” which were:
1. To minimize future maintenance on this segment
of roadway and increase durability;
2. To minimize vibrations and noise caused by traffic
due to presence of joints, and create a raised profile
with additional insulation (Fig. 2). The addi-tional
insulation also provided less heat loss from
the Student Center below, which minimizes the
impacts of future freezing-and-thawing cycles on
the pavement above;
3. To minimize formation of cracks in the segment
to prevent storm water runoff migration from the
roadway to the roof below.
Unlike most infrastructure projects, Buford Avenue was
designed with unbonded 0.6-in. post-tensioning tendons
rather than precast or bonded post-tensioning tendons.
0.6-in. unbonded tendons have a final average force of
2 August 2014 | PTI JOURNAL
approximately 38 kip (as compared to approximately 27 kip
for 0.5-in. tendons). Encapsulated unbonded tendons were
specified to meet the project’s requirement of reducing long-term
corrosion or other distress for 40 years. The transverse
and longitudinal post-tensioning tendons were supported
by intersectional chairs on top of precast concrete blocks
(Fig. 3). The support system rested above compacted sand
and insulation on top of the Student Center’s under-ground
bookstore.
Graham Construction successfully completed the
$234,000 roadway repair project within 2 month window
given by the University of Minnesota—in time for the
Minnesota State Fair on August 13, 2010. Graham Construc-tion
hired AMSYSCO, Inc. to supply the unbonded
0.6-in. post-tensioning tendons for this expedited project.
According to Neel Khosa, Vice President at AMSYSCO,
“The Buford Pavement project illustrates the potential for
utilizing unbonded post-tensioning in infrastructure projects
such as concrete roadways or pedestrian bridges.”
Neel Khosa is the Vice President of AMSYSCO, Inc. He
is the Chair of CRT-30 and a voting member on M-10
and Certification Advisory Board. Mr. Khosa has a MBA
from the University of Chicago and a Bachelor’s of Science
in Civil Engineering from the University of Illinois.
Lastly, he manages the corporate blog at www.amsyscoinc.
com/our-blog which primarily deals with unbonded post-tensioned
concrete.
Fig. 3—Transverse section through the pavement.