SlideShare a Scribd company logo
1 of 20
Planning, Analysis & design
Of
Prestressed Concrete Bridge
Prestressed Concrete
ABSTRACT.
This project deals with the proposal of a PRESTRESSED CONCRETE BRIDGE. This structure consist of
Beam, peirs, girders and footing . And the PSC bridge decks constructed in two methods (i).Pretensioned prestressed
concrete bridge decks, (ii). Post-tensioned prestressed concrete bridge decks. Pretensioned prestressed concrete bridge
decks generally comprise precast pretensioned units used in conjunction with cast in situ concrete, resulting in composite
bridge decks which are ideally suited for small and medium span in the range of 20 to 30 m. Post-tensioned prestressed
concrete bridge decks are generally adopted for longer spans exceeding 20 m. This project relates the model of
‘KINATHTHUKKADAVU PRESTRESSED CONCRETE BRIDGE’ and mainly this bridge constructed the by the
advantages of, it provided for long span, it reduced the deflection and it can carry maximum of loads compared to
reinforced concrete bridges. Prestressed concrete(PC) technology is being used all over the world in the construction of a
wide range of bridge structures. However, many PC bridges have been deteriorating even before the end of their design
service-life due to corrosion and other environmental effects. In view of this, a number of innovative technologies have
been developed in JAPAN to increase not only the structural performance of PC bridge, but also their long-term
durability.
INTRODUCTION
PLANNING
The proposal of prestressed concrete bridge consists of deck slab, piers, bearings, footing
and other amenities of single span of PSC Bridge having the length of the span is 30 m.
SPECIFICATIONS
1.CLEANING THE SITE
The proposal area is to be cleaned of all the loose stones, plants, trees, materials, rubbish of
all kinds as well as of root of trees etc., entirely rubbed out.
2.EARTHWORK EXCAVATION
After cleaning the site, centre line of foundation lines for excavation is started. The
submerged unit weight of concrete is 9.5 N/𝑚𝑚2
.
FOUNDATION CONCRETE
The earth work excavation for the foundation is proposed to a depth of 2.0 m
below the ground level. For design, the submerged unit weight of the soil is
9.5 N/𝑚𝑚2.
P.C.C (1:5:10) mix using 40mm stone aggregate is provided as levelling
course for pier footings. The footings are provided in 𝑀20 grade concrete.
FOOTINGS
Footing are provided pile footing for the bridge consists of 16 group of 16
piles. And the length of the pile is 12 m spaced at 1.5 m c/c.
GRADE OF CONCRETE AND STEEL
For the PSC Bridge construction, 𝑀40 - 𝑀45 grade concrete is provided and
900 N/𝑚𝑚2 – 1500 N/𝑚𝑚2 grade steels are to be provided.
SUPERS STRUCTURE
The super structure includes the beam, deck slab, piers and bearings. The piers are
constructed using 𝑀20 grade of concrete and deck slabs are constructed using 𝑀40 - 𝑀45
concrete respectively.
DECK SLAB
The primary function of a bridge deck is to support the vehicular vertical loads and distribute
these loads to the steel superstructure. The deck is typically continuous along the span of the
bridge and continuous across the width of the span.
BEAM
A properly prestressed concrete beam can span longer distance than a reinforced concrete
beam and it is thinner, lighter in weight, and uses less concrete without cracking or breaking
PIER
A pier is a raised structure, including bridge and building supported by Widely spread piles or
pillars. The lighter structure of a pier allows tides and currents to flow almost unhindered,
whereas the more solid foundations of a quay or the closely spaced piles of a wharf can act as
a breakwater, and are consequently more liable to silting.
BEARING
Bearing are mechanical arrangements provided in the superstructure to transmit the
load to the substructure. They can be thought of as the interface or via media between the
superstructure and the substructure.
GIRDER
A girder bridge is perhaps the most common and most basic bridge. A log across a
creek is an example of a girder bridge in its simplest form. In modern steel girder bridges, the
two most common girders are I-beam girders and box-girders.
AGGREGATES
Is a granular material, such as sand, gravel, crushed stone and iron blast furnace slab,
and when used with a cementing medium forms a hydraulic cement concrete or mortar.
CEMENT
Cement is any material that hardens and becomes strongly adhesive after application in
plastic form. The term cement is often used interchangeably with glue and adhesive.In
engineering and building construction, the term usually refers to a finely powdered,
manufactured substance consisting of gypsum plaster or Portland cement that hardens and
adheres after being mixed with water.
PRESTRESSING TENDONS
Because of the high creep and shrinkage losses in concrete, effective
prestressing can be achieved by using very high strength steels in the range of 270,000 psi
or more.
DATA COLLECTION FOR PLANNING
PLANNING OF THE STRUCTURE
ANALYSIS OF THE STRUCTURE
METHODOLOGY
PLAN
Types of designs.
1.Design of slab
2.Design of beam
3.Design of bearing
4.Design of pier
5.Design of well foundation
6.Design of pile foundation
Design of slab
The slab of the bridge is designed for 30 m span and 7.5 m carriage width.
The slab elements are to be designed under the following steps are to be considered
1. Design of interior panel.
2. Shear force.
3. Dead load bending moment and shear force.
4. Design moment and shear.
5. Design of slab and reinforcement.
6. Check for shear stress.
7. Design of longitudinal girder.
8. Check for ultimate flexural strength.
9. Design of end block.
Design of beam
B =800 mm
D =1600 mm
L =30 m
Fct= 16 N/mm2
Loss ratio = 𝜂 = 0.85
Fu = ftw = 1.4 N/mm2
The above data’s are to be used to design the bridge beam. And the following steps are to be
provided.
1.Check for adequacy
2. Prestressing force
3. Eccentricity
4. Design of web shear
5. Design of flexural
6. Area of steel required
Design of bearing
The bearing is designed for the purpose of allowed to control the movement and it can be
reduce the stresses involved. And it is provides a resting surface between the bridge piers and
bridge deck.
span = 30 m
Reaction = 2500 kN
In this bridge provides the rock and roller bearing is to designed.
The following steps are to be used to designed
1. Design the Rocker pin
2. Check for bearing stress
Design of piers
A structure built on posts extending from land out over the water.
Mean velocity of flow = 0.64 m/sec
Safe bearing capacity of soil = 350 kN/𝑚2
Span = 30 m
Thickness of wearing coat = 100 mm
Thickness of footing = 600 mm
The following design steps are to be followed.
1. Loading on super structure
2. Design the loading
3. Water current on pier
4. Wind force
5. Area of steel required.
Design of well foundation
A well foundation is designed for an abutment of 10 m × 5 m base dimensions. The
well foundation on a sandy soil.
Height of abutment = 6.0 m
Total vertical load = 12,000 kN
Total lateral load at the scour level = 400 kN
Submerged unit weight of soil = 9.5 kN/𝑚2
The above data’s is to be adopt the design the well foundation
Design steps
1. Calculation of length
2. Thickness of steining
3. Reinforcement
4. Bottom plug
5. Check for the section
Design of Pile foundation
Pile foundation is type of deep foundation which are generally used in high raise
building construction and bridge construction.
Bridge consists of piles = 16
Total load = 12,000 kN
Space = 1.5 m c/c
Depth = 12 m
The above data’s are to be used for pile foundation design.
Steps adopted for pile design are,
1. Dimension
2. Lateral reinforcement
3. Lateral reinforcement near the pile head
4. Lateral reinforcement near the pile end.
CONCLUSION
• 30 m Length Bridge is considered for analysis of precast pre-stressed concrete
bridges, and for all the cases, deflection and stresses are within the permissible limits.
• We can clearly see the effectiveness of using precast pre-stressed concrete girder
configuration as it gives us most of the design parameters within permissible limits
of serviceability, deflection and shear compared to ordinary deck slab configuration.
• To obtain even better working results the precast pre-stressed concrete girder
configuration deck slab can be subjected to pre/post tensioning. The pre-stressing
force can be applied more easily.
• Ordinary configuration of deck slab creates long term maintenance and serviceability
problems as it has more number of exposed components in the structure. This
problem can be overcome conveniently in case of precast pre-stressed concrete girder
deck slab configuration.
REFERENCES
• [1] IRC 6:2010, Standard Specifications and code of practice for Road Bridges Section II:
Loads and Stresses.
• [2] IRC 18:2000, Design Criteria for Prestressed Concrete Road Bridges.
• [3] IRC 21:2000, Standard Specifications and code of practice for Road Bridges Section
III: Cement Concrete.
• [4] IS 1343: 2012, Code of practice for Prestressed Concrete.
• [5] N. Krishna Raju, 1981, Prestressed Concrete, Tata McGraw-Hill Publishing Company
Limited.
• [6] S. Ramamrutham, Theory of Structures, Dhanpat Rai Publishing Company.
THANKING YOU

More Related Content

Similar to Prestressed Concrete Bridge.pptx

Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteParag Pal
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concreteRajesh Burde
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptxSauravShahane
 
Cast in situ bridge superstracture
Cast in situ bridge superstractureCast in situ bridge superstracture
Cast in situ bridge superstracturekhushal tadas
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETEghildiyal8811
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETEghildiyal8811
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea linkKAVYA H
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxsfQyoom
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdfRijuDasgupta
 
Precast Concrete is the most prominent structure
Precast Concrete is the most prominent structurePrecast Concrete is the most prominent structure
Precast Concrete is the most prominent structureNisshantSinghSaud
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelIRJET Journal
 
Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)Shekh Muhsen Uddin Ahmed
 
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
 DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPANfaishalniet
 
3 RCD_Chapter 1 Introduction.pdf
3 RCD_Chapter 1 Introduction.pdf3 RCD_Chapter 1 Introduction.pdf
3 RCD_Chapter 1 Introduction.pdfKristineMayMaturan
 
The effect of varying span on Design of Medium span Reinforced Concrete T-bea...
The effect of varying span on Design of Medium span Reinforced Concrete T-bea...The effect of varying span on Design of Medium span Reinforced Concrete T-bea...
The effect of varying span on Design of Medium span Reinforced Concrete T-bea...theijes
 

Similar to Prestressed Concrete Bridge.pptx (20)

Prestressing ppt
Prestressing pptPrestressing ppt
Prestressing ppt
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
Cast in situ bridge superstracture
Cast in situ bridge superstractureCast in situ bridge superstracture
Cast in situ bridge superstracture
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 
PRESTRESSED CONCRETE
PRESTRESSED CONCRETEPRESTRESSED CONCRETE
PRESTRESSED CONCRETE
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
 
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptxAsif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
Asif2 CONSTRUCTION_OF_RIGID_PAVEMENT.pptx
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)702A.pdf
 
Precast Concrete is the most prominent structure
Precast Concrete is the most prominent structurePrecast Concrete is the most prominent structure
Precast Concrete is the most prominent structure
 
Bridges Functionality and Aesthetics
Bridges Functionality and AestheticsBridges Functionality and Aesthetics
Bridges Functionality and Aesthetics
 
Presentation1
Presentation1Presentation1
Presentation1
 
Retrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck LevelRetrofitting of Bridge with Voided Slab to raise the Deck Level
Retrofitting of Bridge with Voided Slab to raise the Deck Level
 
Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)
 
Railway over bridge
Railway over bridgeRailway over bridge
Railway over bridge
 
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
 DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
DEVELOPMENT OF MODERN PRESTRESSED CONCRETE BRIDGES IN JAPAN
 
3 RCD_Chapter 1 Introduction.pdf
3 RCD_Chapter 1 Introduction.pdf3 RCD_Chapter 1 Introduction.pdf
3 RCD_Chapter 1 Introduction.pdf
 
Concrete ppt
Concrete pptConcrete ppt
Concrete ppt
 
The effect of varying span on Design of Medium span Reinforced Concrete T-bea...
The effect of varying span on Design of Medium span Reinforced Concrete T-bea...The effect of varying span on Design of Medium span Reinforced Concrete T-bea...
The effect of varying span on Design of Medium span Reinforced Concrete T-bea...
 

More from RajeshKumar25548

More from RajeshKumar25548 (20)

PPT Notes.pdf
PPT Notes.pdfPPT Notes.pdf
PPT Notes.pdf
 
pradeep.pptx
pradeep.pptxpradeep.pptx
pradeep.pptx
 
vishnu coir ppt.pptx
vishnu coir ppt.pptxvishnu coir ppt.pptx
vishnu coir ppt.pptx
 
UNIT 4 SUSTAINABILITY.pptx
UNIT 4 SUSTAINABILITY.pptxUNIT 4 SUSTAINABILITY.pptx
UNIT 4 SUSTAINABILITY.pptx
 
UNIT 4 Intro_to_Sustainability.ppt
UNIT 4  Intro_to_Sustainability.pptUNIT 4  Intro_to_Sustainability.ppt
UNIT 4 Intro_to_Sustainability.ppt
 
SELF COMPACTING CONCRETE. ppt.pptx
SELF COMPACTING CONCRETE. ppt.pptxSELF COMPACTING CONCRETE. ppt.pptx
SELF COMPACTING CONCRETE. ppt.pptx
 
Prestressed concrete structures –general.pptx
Prestressed  concrete structures –general.pptxPrestressed  concrete structures –general.pptx
Prestressed concrete structures –general.pptx
 
BACTERIAL CONCRETE ppt.pptx
BACTERIAL CONCRETE  ppt.pptxBACTERIAL CONCRETE  ppt.pptx
BACTERIAL CONCRETE ppt.pptx
 
Application of coir fiber in civil Engg.pptx
Application of coir fiber in civil Engg.pptxApplication of coir fiber in civil Engg.pptx
Application of coir fiber in civil Engg.pptx
 
PPT DGFH.pptx
PPT DGFH.pptxPPT DGFH.pptx
PPT DGFH.pptx
 
Residential cum commercial.pptx
Residential cum commercial.pptxResidential cum commercial.pptx
Residential cum commercial.pptx
 
1600752000647_GREEN CONCRETE PPT.pptx
1600752000647_GREEN CONCRETE PPT.pptx1600752000647_GREEN CONCRETE PPT.pptx
1600752000647_GREEN CONCRETE PPT.pptx
 
Hospital Building(PPT).pptx
Hospital Building(PPT).pptxHospital Building(PPT).pptx
Hospital Building(PPT).pptx
 
bagasse_ash[1].pptx
bagasse_ash[1].pptxbagasse_ash[1].pptx
bagasse_ash[1].pptx
 
project ppt.pptx
project ppt.pptxproject ppt.pptx
project ppt.pptx
 
Madhu PPT.pptx
Madhu PPT.pptxMadhu PPT.pptx
Madhu PPT.pptx
 
VICKY GRP.pptx
VICKY GRP.pptxVICKY GRP.pptx
VICKY GRP.pptx
 
SPM.pptx
SPM.pptxSPM.pptx
SPM.pptx
 
sandy batch.pptx
sandy batch.pptxsandy batch.pptx
sandy batch.pptx
 
PROJECT PPTt.pptx
PROJECT PPTt.pptxPROJECT PPTt.pptx
PROJECT PPTt.pptx
 

Recently uploaded

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 

Recently uploaded (20)

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 

Prestressed Concrete Bridge.pptx

  • 1. Planning, Analysis & design Of Prestressed Concrete Bridge
  • 3. ABSTRACT. This project deals with the proposal of a PRESTRESSED CONCRETE BRIDGE. This structure consist of Beam, peirs, girders and footing . And the PSC bridge decks constructed in two methods (i).Pretensioned prestressed concrete bridge decks, (ii). Post-tensioned prestressed concrete bridge decks. Pretensioned prestressed concrete bridge decks generally comprise precast pretensioned units used in conjunction with cast in situ concrete, resulting in composite bridge decks which are ideally suited for small and medium span in the range of 20 to 30 m. Post-tensioned prestressed concrete bridge decks are generally adopted for longer spans exceeding 20 m. This project relates the model of ‘KINATHTHUKKADAVU PRESTRESSED CONCRETE BRIDGE’ and mainly this bridge constructed the by the advantages of, it provided for long span, it reduced the deflection and it can carry maximum of loads compared to reinforced concrete bridges. Prestressed concrete(PC) technology is being used all over the world in the construction of a wide range of bridge structures. However, many PC bridges have been deteriorating even before the end of their design service-life due to corrosion and other environmental effects. In view of this, a number of innovative technologies have been developed in JAPAN to increase not only the structural performance of PC bridge, but also their long-term durability.
  • 4. INTRODUCTION PLANNING The proposal of prestressed concrete bridge consists of deck slab, piers, bearings, footing and other amenities of single span of PSC Bridge having the length of the span is 30 m. SPECIFICATIONS 1.CLEANING THE SITE The proposal area is to be cleaned of all the loose stones, plants, trees, materials, rubbish of all kinds as well as of root of trees etc., entirely rubbed out. 2.EARTHWORK EXCAVATION After cleaning the site, centre line of foundation lines for excavation is started. The submerged unit weight of concrete is 9.5 N/𝑚𝑚2 .
  • 5. FOUNDATION CONCRETE The earth work excavation for the foundation is proposed to a depth of 2.0 m below the ground level. For design, the submerged unit weight of the soil is 9.5 N/𝑚𝑚2. P.C.C (1:5:10) mix using 40mm stone aggregate is provided as levelling course for pier footings. The footings are provided in 𝑀20 grade concrete. FOOTINGS Footing are provided pile footing for the bridge consists of 16 group of 16 piles. And the length of the pile is 12 m spaced at 1.5 m c/c. GRADE OF CONCRETE AND STEEL For the PSC Bridge construction, 𝑀40 - 𝑀45 grade concrete is provided and 900 N/𝑚𝑚2 – 1500 N/𝑚𝑚2 grade steels are to be provided.
  • 6. SUPERS STRUCTURE The super structure includes the beam, deck slab, piers and bearings. The piers are constructed using 𝑀20 grade of concrete and deck slabs are constructed using 𝑀40 - 𝑀45 concrete respectively. DECK SLAB The primary function of a bridge deck is to support the vehicular vertical loads and distribute these loads to the steel superstructure. The deck is typically continuous along the span of the bridge and continuous across the width of the span. BEAM A properly prestressed concrete beam can span longer distance than a reinforced concrete beam and it is thinner, lighter in weight, and uses less concrete without cracking or breaking PIER A pier is a raised structure, including bridge and building supported by Widely spread piles or pillars. The lighter structure of a pier allows tides and currents to flow almost unhindered, whereas the more solid foundations of a quay or the closely spaced piles of a wharf can act as a breakwater, and are consequently more liable to silting.
  • 7. BEARING Bearing are mechanical arrangements provided in the superstructure to transmit the load to the substructure. They can be thought of as the interface or via media between the superstructure and the substructure. GIRDER A girder bridge is perhaps the most common and most basic bridge. A log across a creek is an example of a girder bridge in its simplest form. In modern steel girder bridges, the two most common girders are I-beam girders and box-girders. AGGREGATES Is a granular material, such as sand, gravel, crushed stone and iron blast furnace slab, and when used with a cementing medium forms a hydraulic cement concrete or mortar. CEMENT Cement is any material that hardens and becomes strongly adhesive after application in plastic form. The term cement is often used interchangeably with glue and adhesive.In engineering and building construction, the term usually refers to a finely powdered, manufactured substance consisting of gypsum plaster or Portland cement that hardens and adheres after being mixed with water.
  • 8. PRESTRESSING TENDONS Because of the high creep and shrinkage losses in concrete, effective prestressing can be achieved by using very high strength steels in the range of 270,000 psi or more.
  • 9. DATA COLLECTION FOR PLANNING PLANNING OF THE STRUCTURE ANALYSIS OF THE STRUCTURE METHODOLOGY
  • 10. PLAN
  • 11. Types of designs. 1.Design of slab 2.Design of beam 3.Design of bearing 4.Design of pier 5.Design of well foundation 6.Design of pile foundation
  • 12. Design of slab The slab of the bridge is designed for 30 m span and 7.5 m carriage width. The slab elements are to be designed under the following steps are to be considered 1. Design of interior panel. 2. Shear force. 3. Dead load bending moment and shear force. 4. Design moment and shear. 5. Design of slab and reinforcement. 6. Check for shear stress. 7. Design of longitudinal girder. 8. Check for ultimate flexural strength. 9. Design of end block.
  • 13. Design of beam B =800 mm D =1600 mm L =30 m Fct= 16 N/mm2 Loss ratio = 𝜂 = 0.85 Fu = ftw = 1.4 N/mm2 The above data’s are to be used to design the bridge beam. And the following steps are to be provided. 1.Check for adequacy 2. Prestressing force 3. Eccentricity 4. Design of web shear 5. Design of flexural 6. Area of steel required
  • 14. Design of bearing The bearing is designed for the purpose of allowed to control the movement and it can be reduce the stresses involved. And it is provides a resting surface between the bridge piers and bridge deck. span = 30 m Reaction = 2500 kN In this bridge provides the rock and roller bearing is to designed. The following steps are to be used to designed 1. Design the Rocker pin 2. Check for bearing stress
  • 15. Design of piers A structure built on posts extending from land out over the water. Mean velocity of flow = 0.64 m/sec Safe bearing capacity of soil = 350 kN/𝑚2 Span = 30 m Thickness of wearing coat = 100 mm Thickness of footing = 600 mm The following design steps are to be followed. 1. Loading on super structure 2. Design the loading 3. Water current on pier 4. Wind force 5. Area of steel required.
  • 16. Design of well foundation A well foundation is designed for an abutment of 10 m × 5 m base dimensions. The well foundation on a sandy soil. Height of abutment = 6.0 m Total vertical load = 12,000 kN Total lateral load at the scour level = 400 kN Submerged unit weight of soil = 9.5 kN/𝑚2 The above data’s is to be adopt the design the well foundation Design steps 1. Calculation of length 2. Thickness of steining 3. Reinforcement 4. Bottom plug 5. Check for the section
  • 17. Design of Pile foundation Pile foundation is type of deep foundation which are generally used in high raise building construction and bridge construction. Bridge consists of piles = 16 Total load = 12,000 kN Space = 1.5 m c/c Depth = 12 m The above data’s are to be used for pile foundation design. Steps adopted for pile design are, 1. Dimension 2. Lateral reinforcement 3. Lateral reinforcement near the pile head 4. Lateral reinforcement near the pile end.
  • 18. CONCLUSION • 30 m Length Bridge is considered for analysis of precast pre-stressed concrete bridges, and for all the cases, deflection and stresses are within the permissible limits. • We can clearly see the effectiveness of using precast pre-stressed concrete girder configuration as it gives us most of the design parameters within permissible limits of serviceability, deflection and shear compared to ordinary deck slab configuration. • To obtain even better working results the precast pre-stressed concrete girder configuration deck slab can be subjected to pre/post tensioning. The pre-stressing force can be applied more easily. • Ordinary configuration of deck slab creates long term maintenance and serviceability problems as it has more number of exposed components in the structure. This problem can be overcome conveniently in case of precast pre-stressed concrete girder deck slab configuration.
  • 19. REFERENCES • [1] IRC 6:2010, Standard Specifications and code of practice for Road Bridges Section II: Loads and Stresses. • [2] IRC 18:2000, Design Criteria for Prestressed Concrete Road Bridges. • [3] IRC 21:2000, Standard Specifications and code of practice for Road Bridges Section III: Cement Concrete. • [4] IS 1343: 2012, Code of practice for Prestressed Concrete. • [5] N. Krishna Raju, 1981, Prestressed Concrete, Tata McGraw-Hill Publishing Company Limited. • [6] S. Ramamrutham, Theory of Structures, Dhanpat Rai Publishing Company.