BTS Site Installation
               (Training Material)

Prepare By:-Usman Riaz
Date:- 1-July-2011
Types Of Installation:

Contents:

     Types Of Installation

     Indoor Installation

     Outdoor Installation
Indoor Installation:



   Indoor Cable Tray

   Grounding Bar

   Battery Bank Installation

   SMPS Installation

   BTS Installation

   Connection of Power Cable
Installation Of Indoor Cable Tray:




Indoor Cable tray types-

   Wall mounted

   Roof Mounted
Some Basic Things for the cable tray installation:


   Grounding of cable tray with IGB (Internal Grounding Bus Bar).

   Distance between cable tray & roof of shelter is Depends on the dimension of Hatch
    plate.

   Cable tray should right below the hatch Plate.

   Drills are made on the shelter walls or roof to provide support for Horizontal Cable
    Tray.

   After marking the drilling holes, the ladder is fixed using supporting clamps.

   Cable Tray forms a major part of installation work since all the Grounding,Power,E1,IF
    & RF Cable routing is done over this Cable tray.
Cable Tray forms a major part of
installation work since all the
Grounding,Power,E1,IF & RF Cable
routing is done over this Cable
tray.
Grounding Bar Installation:




There are two types of grounding bars-

   External Grounding Bar (EGB)

   Internal Grounding Bar (IGB)
Some Basic Things for Grounding Bar installation:


   EGB and IGB both are installed right below the hatch plate, and both are connected
    to each other by double connection of 35 mm square grounding cable.

   EGB (External Grounding Bar) is directly connected by the Earth Pit by the GI strip.

   IGB (Internal Grounding Bar) which is installed inside the shelter room, this is made
    up of GI strip.

   EGB (External Grounding Bar) which is installed on the out side of shelter, This is
    totally made of Copper strip.

   Every indoor equipment should be grounded through IGB.

   Then crimp and fix the Lugs at both ends of above these three types of cables &
    wrap with insulating tape with same color of cable.

   Grounding resistance of working ground, Protection ground and lightening arrester
    should be not more than 5 Ω. (Recommended range 0.5 Ω to 5Ω for working ground
    &1-5 Ω for protection ground).
Battery Bank Installation:


   In Telecom BTS site 48 volt DC battery bank installed. there are 24 cells in each
    Battery Bank each is having the 2 volt DC. These battery bank are installed on stand
    and grouted in the shelter properly.

   These battery bank have certain distance from the SMPS and we should try to keep
    O/P of each terminal is in opposite direction of SMPS.

   Grounding of Battery bank is done with the IGB by the 35 mm square grounding
    cable & connected to EGB (Internal Grounding Bar).
SMPS INSTALLATION:


   SMPS is installed nearby the Shelter Door.

   Battery bank directly connected with the SMPS.

   SMPS is the DC supply source by which all the equipment inside the shelter is
    connected like BTS and MW Rack.

   It charges the battery bank by the AC supply, There are modules which converts AC
    supply to DC supply.

   In absence of AC supply it gives the supply by Battery Bank to equipments.

   It Should be grounded on two points One is on positive bus bar and one is with the
    body of SMPS with the 35 mm square grounding cable.
SMPS GROUNDING:


  Positive Bus bar grounding   Body grounding
BTS Installation:


   The BTS installation position should be consistent and must be as per shelter layout
    design.

   Now mark the position of BTS base bolts position at ground & do the grouting of
    Bolts.

   Then fix base of BTS into grouted bolts also check the leveling.

   BTS, Microwave rack, DDF box and all the equipment except power equipment are
    installed on the same side right in front the power equipments.

   BTS should be grouted properly.
SURGE ARRESTER INSTALLATION:


   Surge arrester are high frequency protector, these surge arrester protects the BTS
    from the lightning. These surge arrester fix on the surge arrester stand and this
    surge arrester stand grounded with EGB.




            Surge Arrester Stand           Surge Arrester
JUMPER CABLE CONNECTION ON BTS:


   Jumper cable connects on the BTS top.

   All feeder of three sector connects by the jumper cable.

   Feeder connects by the jumper via Surge Arrester.
Power cable connection On BTS:


   BTS power cable blue one connects with the negative bar which is right in front the
    SMPS via the particular rating of fuses. And positive bus bar connect with black wire
    of BTS terminal. This negative blue cable connects with the negative terminal of BTS
    and black one connects with the Gnd of BTS.
Out Door Installation:


   GSM Antenna Installation on the Tower.

   Feeder cable Installation and routing.

   Earthing of Feeder cable.

   Connection of Jumper cable to Feeder on GSM antenna end.

   Connection of Jumper cable to Feeder on BTS end.
GSM Antenna Installation on the Tower:


   GSM Antenna installed on the tower according to the RF plan.

   The orientation (Azimuth) of the GSM antenna should be according to network
    plan.

   GSM antenna also have the tilt by which the coverage area can be increased or
    decreased, it is also according to plan.

   Tilt may be zero, two, three or four degree.

   GSM antenna clamp should be tightened on the tower properly, it should be not
    loose.
Feeder cable Installation and routing:


   Feeder cable ( 7/8”) connects with the BTS and GSM antenna.
   It is connected with BTS and GSM antenna via the Jumper cable.
   Feeder cable should be routed on the tower by Dummy clamp.
   In feeder cable installation feeder cable should not be bend more then 90 degree at
    certain point.




                                  Feeder cable routing   Bending is not more then 90 degree
Feeder cable comes in the shelter and
before entering in the shelter it takes a
“U” drop. Due to this U drop the water
do not go inside the shelter. So we
must take care about this U drop just
before the entrance in shelter.




                  U drop of Feeder
GROUNDING OF FEEDER CABLE:



• Feeder cable should be grounded
  on three points. Two on the tower
  and one with the EGB.

• Grounding is very necessary and it
  must be on three points.

• Grounding is done by the
  Grounding kit and it should be
  properly shield with weather proof.
Connection of Jumper cable to Feeder on GSM antenna end:


•   Feeder cable connects with GSM antenna by the
    jumper cable .
.

•   Connection should be very tight and shield with
    weather proof.

•   Weather proof should be properly done, if it is
    not proper then this may be on of the reason of
    VSWR.




                                                      Weather proofing on GSM
                                                      and jumper cable on Tower
Connection of Jumper cable to Feeder on BTS end:



    Feeder cable connect with BTS by the
     jumper cable.

    Between jumper and feeder surge arrester
     should be connected




                         Feeder Cable

                    Surge Arrester Stand

                         Jumper cable
Precaution:


   Connection of each power cable should be proper.

   Before switching on the BTS we should check the Input voltage on the BTS
    terminal by the Multimeter, If it is ok then we should switch on the BTS.

   We should visually check the Grounding connection of each equipment.

   All equipments inside the shelter must be grouted.

   At the time of connection of power cable to Battery Bank we must take care about
    the safety.
Thank You

More Related Content

What's hot

83092299 rru3804-overview
83092299 rru3804-overview83092299 rru3804-overview
83092299 rru3804-overview
Serik123
 
ZTE BTS Manual
ZTE BTS ManualZTE BTS Manual
ZTE BTS Manual
ibrahimnabil17
 
Base Transceiver Station (BTS)
Base Transceiver Station (BTS)Base Transceiver Station (BTS)
Base Transceiver Station (BTS)
Waqas Ahmed Nawaz
 
240243228 huawei-bts-3900-training
240243228 huawei-bts-3900-training240243228 huawei-bts-3900-training
240243228 huawei-bts-3900-training
Shelton Siziba
 
Rectifiers and Back up Batteries at Telecom Sites
Rectifiers and Back up Batteries at Telecom SitesRectifiers and Back up Batteries at Telecom Sites
Rectifiers and Back up Batteries at Telecom Sites
ibrahimnabil17
 
01 Bts3900 System Structure
01 Bts3900 System Structure01 Bts3900 System Structure
01 Bts3900 System StructureAtif Mahmood
 
Microwave Links Correct Installation at Telecom Site
Microwave Links Correct Installation at Telecom SiteMicrowave Links Correct Installation at Telecom Site
Microwave Links Correct Installation at Telecom Site
ibrahimnabil17
 
BTS SITE VISIT
BTS SITE VISITBTS SITE VISIT
BTS SITE VISIT
bhargav_shankhalpara
 
telecommunication Towers
telecommunication Towerstelecommunication Towers
telecommunication Towers
Towerpeople
 
Huawei DBS 3900 Hardware Structure
Huawei DBS 3900 Hardware StructureHuawei DBS 3900 Hardware Structure
Huawei DBS 3900 Hardware Structure
ibrahimnabil17
 
Ericsson RBS 6000
Ericsson RBS 6000Ericsson RBS 6000
Ericsson RBS 6000
ibrahimnabil17
 
Microwave Huawei RTN Hardware Structure
Microwave Huawei RTN Hardware StructureMicrowave Huawei RTN Hardware Structure
Microwave Huawei RTN Hardware Structure
ibrahimnabil17
 
Zte macro bts introduction
Zte macro bts  introductionZte macro bts  introduction
Zte macro bts introduction
Ramanuj Kumar
 
TRM MINI-LINK TN Presentation By Khalil Al-Alami
TRM MINI-LINK TN Presentation By Khalil Al-AlamiTRM MINI-LINK TN Presentation By Khalil Al-Alami
TRM MINI-LINK TN Presentation By Khalil Al-Alami
Khalil Al-Alami
 
Ericsson RBS 6000 & 3000 & 2000
Ericsson RBS 6000 & 3000 & 2000Ericsson RBS 6000 & 3000 & 2000
Ericsson RBS 6000 & 3000 & 2000
ibrahimnabil17
 
GSM Base transceiver station
GSM Base transceiver stationGSM Base transceiver station
GSM Base transceiver station
Naveen Jakhar, I.T.S
 
Telecommunication Tower
Telecommunication TowerTelecommunication Tower
Telecommunication Tower
ayishairshad
 
OptiX_RTN_950A_Radio_Transmission_System.pdf
OptiX_RTN_950A_Radio_Transmission_System.pdfOptiX_RTN_950A_Radio_Transmission_System.pdf
OptiX_RTN_950A_Radio_Transmission_System.pdf
HabtamuAdera3
 
Ericsson Radio System reaches new heights
Ericsson Radio System reaches new heightsEricsson Radio System reaches new heights
Ericsson Radio System reaches new heights
Ericsson
 

What's hot (20)

83092299 rru3804-overview
83092299 rru3804-overview83092299 rru3804-overview
83092299 rru3804-overview
 
ZTE BTS Manual
ZTE BTS ManualZTE BTS Manual
ZTE BTS Manual
 
Base Transceiver Station (BTS)
Base Transceiver Station (BTS)Base Transceiver Station (BTS)
Base Transceiver Station (BTS)
 
240243228 huawei-bts-3900-training
240243228 huawei-bts-3900-training240243228 huawei-bts-3900-training
240243228 huawei-bts-3900-training
 
Rectifiers and Back up Batteries at Telecom Sites
Rectifiers and Back up Batteries at Telecom SitesRectifiers and Back up Batteries at Telecom Sites
Rectifiers and Back up Batteries at Telecom Sites
 
01 Bts3900 System Structure
01 Bts3900 System Structure01 Bts3900 System Structure
01 Bts3900 System Structure
 
Microwave Links Correct Installation at Telecom Site
Microwave Links Correct Installation at Telecom SiteMicrowave Links Correct Installation at Telecom Site
Microwave Links Correct Installation at Telecom Site
 
BTS SITE VISIT
BTS SITE VISITBTS SITE VISIT
BTS SITE VISIT
 
telecommunication Towers
telecommunication Towerstelecommunication Towers
telecommunication Towers
 
Huawei DBS 3900 Hardware Structure
Huawei DBS 3900 Hardware StructureHuawei DBS 3900 Hardware Structure
Huawei DBS 3900 Hardware Structure
 
Ericsson RBS 6000
Ericsson RBS 6000Ericsson RBS 6000
Ericsson RBS 6000
 
Microwave Huawei RTN Hardware Structure
Microwave Huawei RTN Hardware StructureMicrowave Huawei RTN Hardware Structure
Microwave Huawei RTN Hardware Structure
 
Zte macro bts introduction
Zte macro bts  introductionZte macro bts  introduction
Zte macro bts introduction
 
TRM MINI-LINK TN Presentation By Khalil Al-Alami
TRM MINI-LINK TN Presentation By Khalil Al-AlamiTRM MINI-LINK TN Presentation By Khalil Al-Alami
TRM MINI-LINK TN Presentation By Khalil Al-Alami
 
Ericsson RBS 6000 & 3000 & 2000
Ericsson RBS 6000 & 3000 & 2000Ericsson RBS 6000 & 3000 & 2000
Ericsson RBS 6000 & 3000 & 2000
 
GSM Base transceiver station
GSM Base transceiver stationGSM Base transceiver station
GSM Base transceiver station
 
Telecommunication Tower
Telecommunication TowerTelecommunication Tower
Telecommunication Tower
 
BTS
BTSBTS
BTS
 
OptiX_RTN_950A_Radio_Transmission_System.pdf
OptiX_RTN_950A_Radio_Transmission_System.pdfOptiX_RTN_950A_Radio_Transmission_System.pdf
OptiX_RTN_950A_Radio_Transmission_System.pdf
 
Ericsson Radio System reaches new heights
Ericsson Radio System reaches new heightsEricsson Radio System reaches new heights
Ericsson Radio System reaches new heights
 

Similar to Bts-site-installation

RF Reserves for Installation, Preventative Maintenance and Acceptance
RF Reserves for Installation, Preventative Maintenance and AcceptanceRF Reserves for Installation, Preventative Maintenance and Acceptance
RF Reserves for Installation, Preventative Maintenance and Acceptance
ibrahimnabil17
 
EtisalatTelecom Model 2016 modified.pptx
EtisalatTelecom Model 2016 modified.pptxEtisalatTelecom Model 2016 modified.pptx
EtisalatTelecom Model 2016 modified.pptx
ssuser8298f2
 
Industrial training in telecom
Industrial training in telecomIndustrial training in telecom
Industrial training in telecom
123sudha
 
Ipmu ic procedure
Ipmu ic procedureIpmu ic procedure
Ipmu ic procedure
Raafat younis
 
KL1034 Lect2 Electrical wiring.pdf
KL1034 Lect2 Electrical wiring.pdfKL1034 Lect2 Electrical wiring.pdf
KL1034 Lect2 Electrical wiring.pdf
SysteDesig
 
WIRE BREAK CIRCUIT ALARAM
WIRE BREAK CIRCUIT ALARAMWIRE BREAK CIRCUIT ALARAM
WIRE BREAK CIRCUIT ALARAM
rookiedope8326
 
IGBT circuit diagram.pptx
IGBT circuit diagram.pptxIGBT circuit diagram.pptx
IGBT circuit diagram.pptx
yogeshkute
 
System Works Knowledge Sharing
System Works Knowledge SharingSystem Works Knowledge Sharing
System Works Knowledge Sharing
Mohd Zamir Abdul Rahman
 
DC potentiometers
DC potentiometersDC potentiometers
DC potentiometers
tadi1padma
 
Substation structures
Substation structuresSubstation structures
Substation structures
Jebitta Paul
 
Slide Wire Dc potentiometer
Slide Wire Dc potentiometerSlide Wire Dc potentiometer
Slide Wire Dc potentiometer
Zulfiqar Mangrio
 
ppt_ae.pdf
ppt_ae.pdfppt_ae.pdf
ppt_ae.pdf
aishwaryaaSanthosh
 
igbt and its characteristics
igbt and its characteristicsigbt and its characteristics
igbt and its characteristics
dharmendrawaghjipur007
 
igbt and its characteristics
igbt and its characteristicsigbt and its characteristics
igbt and its characteristics
dharmendrawaghjipur007
 
Microwave Reserves for Installation, Preventative Maintenance and Acceptance
Microwave Reserves for Installation, Preventative Maintenance and AcceptanceMicrowave Reserves for Installation, Preventative Maintenance and Acceptance
Microwave Reserves for Installation, Preventative Maintenance and Acceptance
ibrahimnabil17
 
Installation and troubleshooting of solar pv power plants
Installation and troubleshooting of solar pv power plantsInstallation and troubleshooting of solar pv power plants
Installation and troubleshooting of solar pv power plants
Gomathy Sengottaiyan
 
System Works Knowledge Sharing
System Works Knowledge SharingSystem Works Knowledge Sharing
System Works Knowledge Sharing
Mohd Zamir Abdul Rahman
 
Inverters
InvertersInverters
Strain Gauges
Strain GaugesStrain Gauges
Strain Gauges
Prashant Borakhede
 

Similar to Bts-site-installation (20)

RF Reserves for Installation, Preventative Maintenance and Acceptance
RF Reserves for Installation, Preventative Maintenance and AcceptanceRF Reserves for Installation, Preventative Maintenance and Acceptance
RF Reserves for Installation, Preventative Maintenance and Acceptance
 
EtisalatTelecom Model 2016 modified.pptx
EtisalatTelecom Model 2016 modified.pptxEtisalatTelecom Model 2016 modified.pptx
EtisalatTelecom Model 2016 modified.pptx
 
Industrial training in telecom
Industrial training in telecomIndustrial training in telecom
Industrial training in telecom
 
Ipmu ic procedure
Ipmu ic procedureIpmu ic procedure
Ipmu ic procedure
 
KL1034 Lect2 Electrical wiring.pdf
KL1034 Lect2 Electrical wiring.pdfKL1034 Lect2 Electrical wiring.pdf
KL1034 Lect2 Electrical wiring.pdf
 
WIRE BREAK CIRCUIT ALARAM
WIRE BREAK CIRCUIT ALARAMWIRE BREAK CIRCUIT ALARAM
WIRE BREAK CIRCUIT ALARAM
 
IGBT circuit diagram.pptx
IGBT circuit diagram.pptxIGBT circuit diagram.pptx
IGBT circuit diagram.pptx
 
System Works Knowledge Sharing
System Works Knowledge SharingSystem Works Knowledge Sharing
System Works Knowledge Sharing
 
User manual-part-2-3501466
User manual-part-2-3501466User manual-part-2-3501466
User manual-part-2-3501466
 
DC potentiometers
DC potentiometersDC potentiometers
DC potentiometers
 
Substation structures
Substation structuresSubstation structures
Substation structures
 
Slide Wire Dc potentiometer
Slide Wire Dc potentiometerSlide Wire Dc potentiometer
Slide Wire Dc potentiometer
 
ppt_ae.pdf
ppt_ae.pdfppt_ae.pdf
ppt_ae.pdf
 
igbt and its characteristics
igbt and its characteristicsigbt and its characteristics
igbt and its characteristics
 
igbt and its characteristics
igbt and its characteristicsigbt and its characteristics
igbt and its characteristics
 
Microwave Reserves for Installation, Preventative Maintenance and Acceptance
Microwave Reserves for Installation, Preventative Maintenance and AcceptanceMicrowave Reserves for Installation, Preventative Maintenance and Acceptance
Microwave Reserves for Installation, Preventative Maintenance and Acceptance
 
Installation and troubleshooting of solar pv power plants
Installation and troubleshooting of solar pv power plantsInstallation and troubleshooting of solar pv power plants
Installation and troubleshooting of solar pv power plants
 
System Works Knowledge Sharing
System Works Knowledge SharingSystem Works Knowledge Sharing
System Works Knowledge Sharing
 
Inverters
InvertersInverters
Inverters
 
Strain Gauges
Strain GaugesStrain Gauges
Strain Gauges
 

More from Ali Usman

Cisco Packet Tracer Overview
Cisco Packet Tracer OverviewCisco Packet Tracer Overview
Cisco Packet Tracer Overview
Ali Usman
 
Islamic Arts and Architecture
Islamic Arts and  ArchitectureIslamic Arts and  Architecture
Islamic Arts and Architecture
Ali Usman
 
Database ,18 Current Issues
Database ,18 Current IssuesDatabase ,18 Current Issues
Database ,18 Current IssuesAli Usman
 
Database , 17 Web
Database , 17 WebDatabase , 17 Web
Database , 17 WebAli Usman
 
Database ,16 P2P
Database ,16 P2P Database ,16 P2P
Database ,16 P2P Ali Usman
 
Database , 15 Object DBMS
Database , 15 Object DBMSDatabase , 15 Object DBMS
Database , 15 Object DBMSAli Usman
 
Database ,14 Parallel DBMS
Database ,14 Parallel DBMSDatabase ,14 Parallel DBMS
Database ,14 Parallel DBMSAli Usman
 
Database , 13 Replication
Database , 13 ReplicationDatabase , 13 Replication
Database , 13 ReplicationAli Usman
 
Database , 12 Reliability
Database , 12 ReliabilityDatabase , 12 Reliability
Database , 12 ReliabilityAli Usman
 
Database ,11 Concurrency Control
Database ,11 Concurrency ControlDatabase ,11 Concurrency Control
Database ,11 Concurrency ControlAli Usman
 
Database ,10 Transactions
Database ,10 TransactionsDatabase ,10 Transactions
Database ,10 TransactionsAli Usman
 
Database , 8 Query Optimization
Database , 8 Query OptimizationDatabase , 8 Query Optimization
Database , 8 Query OptimizationAli Usman
 
Database ,7 query localization
Database ,7 query localizationDatabase ,7 query localization
Database ,7 query localizationAli Usman
 
Database , 6 Query Introduction
Database , 6 Query Introduction Database , 6 Query Introduction
Database , 6 Query Introduction Ali Usman
 
Database , 5 Semantic
Database , 5 SemanticDatabase , 5 Semantic
Database , 5 SemanticAli Usman
 
Database , 4 Data Integration
Database , 4 Data IntegrationDatabase , 4 Data Integration
Database , 4 Data IntegrationAli Usman
 
Database, 3 Distribution Design
Database, 3 Distribution DesignDatabase, 3 Distribution Design
Database, 3 Distribution DesignAli Usman
 
Database ,2 Background
 Database ,2 Background Database ,2 Background
Database ,2 BackgroundAli Usman
 
Database , 1 Introduction
 Database , 1 Introduction Database , 1 Introduction
Database , 1 IntroductionAli Usman
 
Processor Specifications
Processor SpecificationsProcessor Specifications
Processor SpecificationsAli Usman
 

More from Ali Usman (20)

Cisco Packet Tracer Overview
Cisco Packet Tracer OverviewCisco Packet Tracer Overview
Cisco Packet Tracer Overview
 
Islamic Arts and Architecture
Islamic Arts and  ArchitectureIslamic Arts and  Architecture
Islamic Arts and Architecture
 
Database ,18 Current Issues
Database ,18 Current IssuesDatabase ,18 Current Issues
Database ,18 Current Issues
 
Database , 17 Web
Database , 17 WebDatabase , 17 Web
Database , 17 Web
 
Database ,16 P2P
Database ,16 P2P Database ,16 P2P
Database ,16 P2P
 
Database , 15 Object DBMS
Database , 15 Object DBMSDatabase , 15 Object DBMS
Database , 15 Object DBMS
 
Database ,14 Parallel DBMS
Database ,14 Parallel DBMSDatabase ,14 Parallel DBMS
Database ,14 Parallel DBMS
 
Database , 13 Replication
Database , 13 ReplicationDatabase , 13 Replication
Database , 13 Replication
 
Database , 12 Reliability
Database , 12 ReliabilityDatabase , 12 Reliability
Database , 12 Reliability
 
Database ,11 Concurrency Control
Database ,11 Concurrency ControlDatabase ,11 Concurrency Control
Database ,11 Concurrency Control
 
Database ,10 Transactions
Database ,10 TransactionsDatabase ,10 Transactions
Database ,10 Transactions
 
Database , 8 Query Optimization
Database , 8 Query OptimizationDatabase , 8 Query Optimization
Database , 8 Query Optimization
 
Database ,7 query localization
Database ,7 query localizationDatabase ,7 query localization
Database ,7 query localization
 
Database , 6 Query Introduction
Database , 6 Query Introduction Database , 6 Query Introduction
Database , 6 Query Introduction
 
Database , 5 Semantic
Database , 5 SemanticDatabase , 5 Semantic
Database , 5 Semantic
 
Database , 4 Data Integration
Database , 4 Data IntegrationDatabase , 4 Data Integration
Database , 4 Data Integration
 
Database, 3 Distribution Design
Database, 3 Distribution DesignDatabase, 3 Distribution Design
Database, 3 Distribution Design
 
Database ,2 Background
 Database ,2 Background Database ,2 Background
Database ,2 Background
 
Database , 1 Introduction
 Database , 1 Introduction Database , 1 Introduction
Database , 1 Introduction
 
Processor Specifications
Processor SpecificationsProcessor Specifications
Processor Specifications
 

Recently uploaded

Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
SACHIN R KONDAGURI
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
heathfieldcps1
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
Levi Shapiro
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf
CarlosHernanMontoyab2
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
GeoBlogs
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
vaibhavrinwa19
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
Ashokrao Mane college of Pharmacy Peth-Vadgaon
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
Balvir Singh
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
Jisc
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
BhavyaRajput3
 

Recently uploaded (20)

Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
 
The basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptxThe basics of sentences session 5pptx.pptx
The basics of sentences session 5pptx.pptx
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
June 3, 2024 Anti-Semitism Letter Sent to MIT President Kornbluth and MIT Cor...
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
 
Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.Biological Screening of Herbal Drugs in detailed.
Biological Screening of Herbal Drugs in detailed.
 
Operation Blue Star - Saka Neela Tara
Operation Blue Star   -  Saka Neela TaraOperation Blue Star   -  Saka Neela Tara
Operation Blue Star - Saka Neela Tara
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
The approach at University of Liverpool.pptx
The approach at University of Liverpool.pptxThe approach at University of Liverpool.pptx
The approach at University of Liverpool.pptx
 
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCECLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
CLASS 11 CBSE B.St Project AIDS TO TRADE - INSURANCE
 

Bts-site-installation

  • 1. BTS Site Installation (Training Material) Prepare By:-Usman Riaz Date:- 1-July-2011
  • 2. Types Of Installation: Contents:  Types Of Installation  Indoor Installation  Outdoor Installation
  • 3. Indoor Installation:  Indoor Cable Tray  Grounding Bar  Battery Bank Installation  SMPS Installation  BTS Installation  Connection of Power Cable
  • 4. Installation Of Indoor Cable Tray: Indoor Cable tray types-  Wall mounted  Roof Mounted
  • 5. Some Basic Things for the cable tray installation:  Grounding of cable tray with IGB (Internal Grounding Bus Bar).  Distance between cable tray & roof of shelter is Depends on the dimension of Hatch plate.  Cable tray should right below the hatch Plate.  Drills are made on the shelter walls or roof to provide support for Horizontal Cable Tray.  After marking the drilling holes, the ladder is fixed using supporting clamps.  Cable Tray forms a major part of installation work since all the Grounding,Power,E1,IF & RF Cable routing is done over this Cable tray.
  • 6. Cable Tray forms a major part of installation work since all the Grounding,Power,E1,IF & RF Cable routing is done over this Cable tray.
  • 7. Grounding Bar Installation: There are two types of grounding bars-  External Grounding Bar (EGB)  Internal Grounding Bar (IGB)
  • 8. Some Basic Things for Grounding Bar installation:  EGB and IGB both are installed right below the hatch plate, and both are connected to each other by double connection of 35 mm square grounding cable.  EGB (External Grounding Bar) is directly connected by the Earth Pit by the GI strip.  IGB (Internal Grounding Bar) which is installed inside the shelter room, this is made up of GI strip.  EGB (External Grounding Bar) which is installed on the out side of shelter, This is totally made of Copper strip.  Every indoor equipment should be grounded through IGB.  Then crimp and fix the Lugs at both ends of above these three types of cables & wrap with insulating tape with same color of cable.  Grounding resistance of working ground, Protection ground and lightening arrester should be not more than 5 Ω. (Recommended range 0.5 Ω to 5Ω for working ground &1-5 Ω for protection ground).
  • 9. Battery Bank Installation:  In Telecom BTS site 48 volt DC battery bank installed. there are 24 cells in each Battery Bank each is having the 2 volt DC. These battery bank are installed on stand and grouted in the shelter properly.  These battery bank have certain distance from the SMPS and we should try to keep O/P of each terminal is in opposite direction of SMPS.  Grounding of Battery bank is done with the IGB by the 35 mm square grounding cable & connected to EGB (Internal Grounding Bar).
  • 10. SMPS INSTALLATION:  SMPS is installed nearby the Shelter Door.  Battery bank directly connected with the SMPS.  SMPS is the DC supply source by which all the equipment inside the shelter is connected like BTS and MW Rack.  It charges the battery bank by the AC supply, There are modules which converts AC supply to DC supply.  In absence of AC supply it gives the supply by Battery Bank to equipments.  It Should be grounded on two points One is on positive bus bar and one is with the body of SMPS with the 35 mm square grounding cable.
  • 11. SMPS GROUNDING: Positive Bus bar grounding Body grounding
  • 12. BTS Installation:  The BTS installation position should be consistent and must be as per shelter layout design.  Now mark the position of BTS base bolts position at ground & do the grouting of Bolts.  Then fix base of BTS into grouted bolts also check the leveling.  BTS, Microwave rack, DDF box and all the equipment except power equipment are installed on the same side right in front the power equipments.  BTS should be grouted properly.
  • 13. SURGE ARRESTER INSTALLATION:  Surge arrester are high frequency protector, these surge arrester protects the BTS from the lightning. These surge arrester fix on the surge arrester stand and this surge arrester stand grounded with EGB. Surge Arrester Stand Surge Arrester
  • 14. JUMPER CABLE CONNECTION ON BTS:  Jumper cable connects on the BTS top.  All feeder of three sector connects by the jumper cable.  Feeder connects by the jumper via Surge Arrester.
  • 15. Power cable connection On BTS:  BTS power cable blue one connects with the negative bar which is right in front the SMPS via the particular rating of fuses. And positive bus bar connect with black wire of BTS terminal. This negative blue cable connects with the negative terminal of BTS and black one connects with the Gnd of BTS.
  • 16. Out Door Installation:  GSM Antenna Installation on the Tower.  Feeder cable Installation and routing.  Earthing of Feeder cable.  Connection of Jumper cable to Feeder on GSM antenna end.  Connection of Jumper cable to Feeder on BTS end.
  • 17. GSM Antenna Installation on the Tower:  GSM Antenna installed on the tower according to the RF plan.  The orientation (Azimuth) of the GSM antenna should be according to network plan.  GSM antenna also have the tilt by which the coverage area can be increased or decreased, it is also according to plan.  Tilt may be zero, two, three or four degree.  GSM antenna clamp should be tightened on the tower properly, it should be not loose.
  • 18. Feeder cable Installation and routing:  Feeder cable ( 7/8”) connects with the BTS and GSM antenna.  It is connected with BTS and GSM antenna via the Jumper cable.  Feeder cable should be routed on the tower by Dummy clamp.  In feeder cable installation feeder cable should not be bend more then 90 degree at certain point. Feeder cable routing Bending is not more then 90 degree
  • 19. Feeder cable comes in the shelter and before entering in the shelter it takes a “U” drop. Due to this U drop the water do not go inside the shelter. So we must take care about this U drop just before the entrance in shelter. U drop of Feeder
  • 20. GROUNDING OF FEEDER CABLE: • Feeder cable should be grounded on three points. Two on the tower and one with the EGB. • Grounding is very necessary and it must be on three points. • Grounding is done by the Grounding kit and it should be properly shield with weather proof.
  • 21. Connection of Jumper cable to Feeder on GSM antenna end: • Feeder cable connects with GSM antenna by the jumper cable . . • Connection should be very tight and shield with weather proof. • Weather proof should be properly done, if it is not proper then this may be on of the reason of VSWR. Weather proofing on GSM and jumper cable on Tower
  • 22. Connection of Jumper cable to Feeder on BTS end:  Feeder cable connect with BTS by the jumper cable.  Between jumper and feeder surge arrester should be connected Feeder Cable Surge Arrester Stand Jumper cable
  • 23. Precaution:  Connection of each power cable should be proper.  Before switching on the BTS we should check the Input voltage on the BTS terminal by the Multimeter, If it is ok then we should switch on the BTS.  We should visually check the Grounding connection of each equipment.  All equipments inside the shelter must be grouted.  At the time of connection of power cable to Battery Bank we must take care about the safety.