SlideShare a Scribd company logo
1 of 16
Download to read offline
January 11, 2021
Eglinton Crosstown LRT
Leaside-Laird CLC
ACTION ITEM #1
January 19, 2021
CYCLE LANE
BIKE PARKING
ACTION ITEM 2
3
CTS to share a picture of the rendering of the area of Eglinton Avenue at the Brentcliffe portal, including the road that
will open onto Eglinton Eastbound at the portal.
Leaside Station
LEASIDE STATION UPDATE
5
Activity Location Approx. Date & Duration
Station Box Construction
• Waterproofing
• Rebar, steel, and conduit installations
• Formwork
• Concrete pours
• Masonry block installations
Underneath Eglinton Avenue within the Station Box Underway through mid 2021
Main Entrance Construction
• Rebar, steel and M&E installations
• Formwork installations
• Concrete pours
• Masonry block installations
South east corner of Bayview Ave and Eglinton Ave Underway through early 2021
Secondary Entrance Construction
• Waterproofing
• Rebar, steel, and conduit installations
• Formwork
• Concrete pours
North west corner of Bayview Ave and Eglinton Ave Underway through early 2021
LEASIDE STATION LOOK-AHEAD
6
Year What to Expect
2021
• Extended construction hours will continue through 2021.
• Periodic lane closures may be required to facilitate deliveries, dewatering and concrete
works.
• Permanent works are ongoing within the station box and entrances, and will continue into
early 2021, including waterproofing, formwork, rebar installation and concrete works.
• Above ground construction of the Main Entrance is underway, with crews completing the
concrete pour for the floor slab and south wall.
• Architectural works, including masonry block installations, have begun at the Main
Entrance. Structural steel and pre-cast panel installations are expected to start in Spring
2021.
• Construction of the Secondary Entrance is progressing upwards and is expected to reach
street level in Spring 2021.
CURRENT TRAFFIC CONFIGURATION
7
Through Summer 2021.
CONSTRUCTION PROGRESS PHOTOS
8
M&E WORKS
- MAIN ENTRANCE
FORMWORK INSTALLATIONS
- STATION BOX
CONSTRUCTION PROGRESS PHOTOS
MAIN ENTRANCE OVERVIEW
9
2020 2021
Laird Station
LAIRD STATION UPDATE
11
Activity Location Approx. Date & Duration
Main Entrance Construction
Forming, concrete works, deliveries, rebar
and structural steel
Main Entrance
Monday – Sunday, 6:00 a.m. – 1:00 a.m.
through March 2021
Secondary Entrance Construction
Forming, concrete works and back-fill
Secondary Entrance
Monday – Sunday, 24 hours through March
2021
Station Box and Tunnel Works
Track installation, rebar installation
Beneath Eglinton Ave Underway through January 2021
Crane Demobilization
Short-term traffic change
Main Entrance
As early as mid-February 2021 for one (1)
week
Escalator Delivery
Short-term traffic change (same as crane
demobilization configuration)
Main Entrance
As early as mid-February 2021 for two (2)
weeks
CURRENT TRAFFIC CONFIGURATION
12
Through mid-February 2021
UPCOMING TRAFFIC CONFIGURATION
13
Mid-February 2021 – March 2021
CONSTRUCTION PROGRESS PHOTOS
14
SECONDARY ENTRANCE MAIN ENTRANCE
RETAINING WALL CONSTRUCTION
NORTH SIDE OF EGLINTON
EAST OF BRENTCLIFFE ROAD
15
• This retaining wall is required to hold the
embankment created from the widened Eglinton
Ave.
• Retaining wall construction is on hold while
slope remediation work takes place
• Remedial work will continue into February 2021,
and includes installation of steel anchors,
application of shotcrete and back-filling
• Retaining wall construction will resume in 2021
• Slope restoration design is with the City of
Toronto for review
Leaside and Laird CLC - January 11, 2021

More Related Content

What's hot

CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
Crosstown TO
 

What's hot (20)

CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)Cedarvale & Forest Hill Construction Update (March 31, 2021)
Cedarvale & Forest Hill Construction Update (March 31, 2021)
 
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
 
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)
 
Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
 
Eastern Virtual Open House Deck
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House Deck
 
Pharmacy to Kennedy CLC meeting
Pharmacy to Kennedy  CLC meetingPharmacy to Kennedy  CLC meeting
Pharmacy to Kennedy CLC meeting
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Final central east open house oct282020
Final central east open house oct282020Final central east open house oct282020
Final central east open house oct282020
 
Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021Leaside and Laird CLC 8Mar2021
Leaside and Laird CLC 8Mar2021
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
 
Eastern Segment 5 works monthly meeting January 2021
Eastern Segment 5 works monthly meeting January 2021Eastern Segment 5 works monthly meeting January 2021
Eastern Segment 5 works monthly meeting January 2021
 
Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021Eglinton and Mt Pleasant CLC - 12, May 2021
Eglinton and Mt Pleasant CLC - 12, May 2021
 
Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021
 
CLC Eglinton and Mount Pleasant
CLC Eglinton and Mount PleasantCLC Eglinton and Mount Pleasant
CLC Eglinton and Mount Pleasant
 
Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021Brentcliffe to Victoria Park - March 4, 2021
Brentcliffe to Victoria Park - March 4, 2021
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 

Similar to Leaside and Laird CLC - January 11, 2021

Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Crosstown TO
 

Similar to Leaside and Laird CLC - January 11, 2021 (20)

Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021
 
Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)Cedarvale & Forest Hill Construction Update (January 27, 2021)
Cedarvale & Forest Hill Construction Update (January 27, 2021)
 
Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021Fairbank-Oakwood Construction Update - May 2021
Fairbank-Oakwood Construction Update - May 2021
 
Eglinton & Mt Pleasant CLC - January 2022
Eglinton & Mt Pleasant CLC - January 2022Eglinton & Mt Pleasant CLC - January 2022
Eglinton & Mt Pleasant CLC - January 2022
 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021
 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
 
Leaside& Laird CLC - 12July2021
Leaside& Laird CLC - 12July2021Leaside& Laird CLC - 12July2021
Leaside& Laird CLC - 12July2021
 
Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November Eglinton & Mt pleasant CLC - November
Eglinton & Mt pleasant CLC - November
 
Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)
 
Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021Fairbank-Oakwood Construction Update - March 2021
Fairbank-Oakwood Construction Update - March 2021
 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019
 
CLC Pharmacy to Kennedy January
CLC Pharmacy to Kennedy JanuaryCLC Pharmacy to Kennedy January
CLC Pharmacy to Kennedy January
 
Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022Avenue & Chaplin CLC - Construction Update: January 5, 2022
Avenue & Chaplin CLC - Construction Update: January 5, 2022
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
Eglinton & Mt Pleasant CLC - march 9 2022
Eglinton & Mt Pleasant CLC - march 9 2022Eglinton & Mt Pleasant CLC - march 9 2022
Eglinton & Mt Pleasant CLC - march 9 2022
 
Eglinton - Mt Pleasant CLC - May 11, 2022 compressed.pptx
Eglinton - Mt Pleasant CLC - May 11, 2022 compressed.pptxEglinton - Mt Pleasant CLC - May 11, 2022 compressed.pptx
Eglinton - Mt Pleasant CLC - May 11, 2022 compressed.pptx
 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
 
Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021Avenue & Chaplin CLC - Construction Update: November 3, 2021
Avenue & Chaplin CLC - Construction Update: November 3, 2021
 
Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021Fairbank-Oakwood Construction Update - July 2021
Fairbank-Oakwood Construction Update - July 2021
 

More from Crosstown TO

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Recently uploaded

Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Recently uploaded (20)

Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORSPPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
PPT BIJNOR COUNTING Counting of Votes on ETPBs (FOR SERVICE ELECTORS
 
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...Junnar ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For S...
Junnar ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For S...
 
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
 
An Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCCAn Atoll Futures Research Institute? Presentation for CANCC
An Atoll Futures Research Institute? Presentation for CANCC
 
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition PlansSustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
 
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
VIP Model Call Girls Lohegaon ( Pune ) Call ON 8005736733 Starting From 5K to...
 
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...The Economic and Organised Crime Office (EOCO) has been advised by the Office...
The Economic and Organised Crime Office (EOCO) has been advised by the Office...
 
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 
Government e Marketplace GeM Presentation
Government e Marketplace GeM PresentationGovernment e Marketplace GeM Presentation
Government e Marketplace GeM Presentation
 
2024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 292024: The FAR, Federal Acquisition Regulations - Part 29
2024: The FAR, Federal Acquisition Regulations - Part 29
 
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...Call On 6297143586  Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
Call On 6297143586 Viman Nagar Call Girls In All Pune 24/7 Provide Call With...
 
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakurbest call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
best call girls in Pune - 450+ Call Girl Cash Payment 8005736733 Neha Thakur
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
 
1935 CONSTITUTION REPORT IN RIPH FINALLS
1935 CONSTITUTION REPORT IN RIPH FINALLS1935 CONSTITUTION REPORT IN RIPH FINALLS
1935 CONSTITUTION REPORT IN RIPH FINALLS
 
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...Pimpri Chinchwad ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi R...
Pimpri Chinchwad ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi R...
 
Finance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCCFinance strategies for adaptation. Presentation for CANCC
Finance strategies for adaptation. Presentation for CANCC
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptx
 

Leaside and Laird CLC - January 11, 2021

  • 1. January 11, 2021 Eglinton Crosstown LRT Leaside-Laird CLC
  • 2. ACTION ITEM #1 January 19, 2021 CYCLE LANE BIKE PARKING
  • 3. ACTION ITEM 2 3 CTS to share a picture of the rendering of the area of Eglinton Avenue at the Brentcliffe portal, including the road that will open onto Eglinton Eastbound at the portal.
  • 5. LEASIDE STATION UPDATE 5 Activity Location Approx. Date & Duration Station Box Construction • Waterproofing • Rebar, steel, and conduit installations • Formwork • Concrete pours • Masonry block installations Underneath Eglinton Avenue within the Station Box Underway through mid 2021 Main Entrance Construction • Rebar, steel and M&E installations • Formwork installations • Concrete pours • Masonry block installations South east corner of Bayview Ave and Eglinton Ave Underway through early 2021 Secondary Entrance Construction • Waterproofing • Rebar, steel, and conduit installations • Formwork • Concrete pours North west corner of Bayview Ave and Eglinton Ave Underway through early 2021
  • 6. LEASIDE STATION LOOK-AHEAD 6 Year What to Expect 2021 • Extended construction hours will continue through 2021. • Periodic lane closures may be required to facilitate deliveries, dewatering and concrete works. • Permanent works are ongoing within the station box and entrances, and will continue into early 2021, including waterproofing, formwork, rebar installation and concrete works. • Above ground construction of the Main Entrance is underway, with crews completing the concrete pour for the floor slab and south wall. • Architectural works, including masonry block installations, have begun at the Main Entrance. Structural steel and pre-cast panel installations are expected to start in Spring 2021. • Construction of the Secondary Entrance is progressing upwards and is expected to reach street level in Spring 2021.
  • 8. CONSTRUCTION PROGRESS PHOTOS 8 M&E WORKS - MAIN ENTRANCE FORMWORK INSTALLATIONS - STATION BOX
  • 9. CONSTRUCTION PROGRESS PHOTOS MAIN ENTRANCE OVERVIEW 9 2020 2021
  • 11. LAIRD STATION UPDATE 11 Activity Location Approx. Date & Duration Main Entrance Construction Forming, concrete works, deliveries, rebar and structural steel Main Entrance Monday – Sunday, 6:00 a.m. – 1:00 a.m. through March 2021 Secondary Entrance Construction Forming, concrete works and back-fill Secondary Entrance Monday – Sunday, 24 hours through March 2021 Station Box and Tunnel Works Track installation, rebar installation Beneath Eglinton Ave Underway through January 2021 Crane Demobilization Short-term traffic change Main Entrance As early as mid-February 2021 for one (1) week Escalator Delivery Short-term traffic change (same as crane demobilization configuration) Main Entrance As early as mid-February 2021 for two (2) weeks
  • 15. RETAINING WALL CONSTRUCTION NORTH SIDE OF EGLINTON EAST OF BRENTCLIFFE ROAD 15 • This retaining wall is required to hold the embankment created from the widened Eglinton Ave. • Retaining wall construction is on hold while slope remediation work takes place • Remedial work will continue into February 2021, and includes installation of steel anchors, application of shotcrete and back-filling • Retaining wall construction will resume in 2021 • Slope restoration design is with the City of Toronto for review