This document discusses expansion tanks, which are used in closed hydronic systems to accommodate changes in water volume as the temperature changes. There are four main types of expansion tanks - vented steel tanks, closed steel tanks, diaphragm tanks, and bladder tanks. Bladder tanks, which use a balloon-like bladder to accept expanded water, are now most commonly used in large commercial systems. The document reviews the fundamentals of how expansion tanks work and addresses common misunderstandings about tank sizing and placement. It provides simplified equations for sizing different types of expansion tanks and clarifies the conditions under which each equation applies.
There are four main types of expansion tanks: open, plain steel, bladder, and diaphragm. Open tanks are not commonly used due to corrosion issues. Plain steel tanks have air in direct contact with water which can cause corrosion problems and require a larger tank size. Bladder and diaphragm tanks separate the air from the water using a rubber bladder or diaphragm, reducing corrosion and allowing for a smaller tank size compared to plain steel tanks. Bladder and diaphragm tanks are preferred due to their ability to eliminate air from the system and provide improved performance with lower operating and maintenance costs.
The primary objective of this report is to provide a convenient, consistent and accurate method of calculating heating and cooling loads and to enable the designer to select systems that meet the requirement for efficient utilization and are also responsive to environmental needs. The ability to estimate loads more accurately due to changes in the calculation procedure provides a lessened margin of error. Therefore, it becomes increasingly important to survey and check more carefully the load sources, each item in the load and the effect of the system type on the load. Junaid Hussain | Syed Abdul Gaffar "Heat Load Calculation" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-3 | Issue-5 , August 2019, URL: https://www.ijtsrd.com/papers/ijtsrd26571.pdfPaper URL: https://www.ijtsrd.com/engineering/mechanical-engineering/26571/heat-load-calculation/junaid-hussain
The document discusses shell and tube heat exchangers. It describes the different types of shell and tube designs according to the TEMA standard, including U-tube, straight tube, and kettle-type designs. It also discusses design considerations for different components like stationary heads, rear ends, baffles, tubesheets, and joints. The TEMA standard provides terminology for naming heat exchangers based on these design features and components.
OPERATING ENVELOPES FOR CENTRIFUGAL PUMPSVijay Sarathy
The following tutorial provides a step by step procedure to predict the allowable operating range or “Operating Envelope” for a centrifugal pump’s range of operation.
CENTRIFUGAL COMPRESSOR SETTLE OUT CONDITIONS TUTORIALVijay Sarathy
Centrifugal Compressors are a preferred choice in gas transportation industry, mainly due to their ability to cater to varying loads. In the event of a compressor shutdown as a planned event, i.e., normal shutdown (NSD), the anti-surge valve is opened to recycle gas from the discharge back to the suction (thereby moving the operating point away from the surge line) and the compressor is tripped via the driver (electric motor or Gas turbine / Steam Turbine). In the case of an unplanned event, i.e., emergency shutdown such as power failure, the compressor trips first followed by the anti-surge valve opening. In doing so, the gas content in the suction side & discharge side mix.
Therefore, settle out conditions is explained as the equilibrium pressure and temperature reached in the compressor piping and equipment volume following a compressor shutdown
Chemical Process Calculations – Short TutorialVijay Sarathy
Often engineers are tasked with communicating equipment specifications with suppliers, where process data needs to be exchanged for engineering quotations & orders. Any dearth of data would need to be computed for which process related queries are sometimes sent back to the process engineer’s desk for the requested data.
The following tutorial is a refresher for non-process engineers such as project engineers, Piping, Instrumentation, Static & Rotating Equipment engineers to conduct basic process calculations related to estimation of mass %, volume %, mass flow, actual & standard volumetric flow, gas density, parts per million (ppm) by weight & by volume.
This document summarizes a presentation made by Allied Group of Companies to Triveni Turbines on February 8, 2012 about sterling deaeration technology. It introduces several companies in the Allied Group and discusses Allied Energy Systems' manufacturing of deaerators in collaboration with Sterling Deaerator Co. of the US. It also provides details on deaeration processes, Sterling deaerator models, performance guarantees, project execution methodology, and case studies of installations with valued clients.
The document discusses the design of a Heat Recovery Steam Generator (HRSG) undertaken at Thermax Limited in Pune, India. It provides an overview of Thermax Limited, introduces boilers and HRSGs, and discusses the mechanical design of an HRSG according to Indian and American standards. The objectives are to recover heat from gas turbine exhaust to increase overall plant efficiency and design the HRSG to meet regulatory requirements. The document outlines the components, calculations, and inferences of the HRSG design project.
There are four main types of expansion tanks: open, plain steel, bladder, and diaphragm. Open tanks are not commonly used due to corrosion issues. Plain steel tanks have air in direct contact with water which can cause corrosion problems and require a larger tank size. Bladder and diaphragm tanks separate the air from the water using a rubber bladder or diaphragm, reducing corrosion and allowing for a smaller tank size compared to plain steel tanks. Bladder and diaphragm tanks are preferred due to their ability to eliminate air from the system and provide improved performance with lower operating and maintenance costs.
The primary objective of this report is to provide a convenient, consistent and accurate method of calculating heating and cooling loads and to enable the designer to select systems that meet the requirement for efficient utilization and are also responsive to environmental needs. The ability to estimate loads more accurately due to changes in the calculation procedure provides a lessened margin of error. Therefore, it becomes increasingly important to survey and check more carefully the load sources, each item in the load and the effect of the system type on the load. Junaid Hussain | Syed Abdul Gaffar "Heat Load Calculation" Published in International Journal of Trend in Scientific Research and Development (ijtsrd), ISSN: 2456-6470, Volume-3 | Issue-5 , August 2019, URL: https://www.ijtsrd.com/papers/ijtsrd26571.pdfPaper URL: https://www.ijtsrd.com/engineering/mechanical-engineering/26571/heat-load-calculation/junaid-hussain
The document discusses shell and tube heat exchangers. It describes the different types of shell and tube designs according to the TEMA standard, including U-tube, straight tube, and kettle-type designs. It also discusses design considerations for different components like stationary heads, rear ends, baffles, tubesheets, and joints. The TEMA standard provides terminology for naming heat exchangers based on these design features and components.
OPERATING ENVELOPES FOR CENTRIFUGAL PUMPSVijay Sarathy
The following tutorial provides a step by step procedure to predict the allowable operating range or “Operating Envelope” for a centrifugal pump’s range of operation.
CENTRIFUGAL COMPRESSOR SETTLE OUT CONDITIONS TUTORIALVijay Sarathy
Centrifugal Compressors are a preferred choice in gas transportation industry, mainly due to their ability to cater to varying loads. In the event of a compressor shutdown as a planned event, i.e., normal shutdown (NSD), the anti-surge valve is opened to recycle gas from the discharge back to the suction (thereby moving the operating point away from the surge line) and the compressor is tripped via the driver (electric motor or Gas turbine / Steam Turbine). In the case of an unplanned event, i.e., emergency shutdown such as power failure, the compressor trips first followed by the anti-surge valve opening. In doing so, the gas content in the suction side & discharge side mix.
Therefore, settle out conditions is explained as the equilibrium pressure and temperature reached in the compressor piping and equipment volume following a compressor shutdown
Chemical Process Calculations – Short TutorialVijay Sarathy
Often engineers are tasked with communicating equipment specifications with suppliers, where process data needs to be exchanged for engineering quotations & orders. Any dearth of data would need to be computed for which process related queries are sometimes sent back to the process engineer’s desk for the requested data.
The following tutorial is a refresher for non-process engineers such as project engineers, Piping, Instrumentation, Static & Rotating Equipment engineers to conduct basic process calculations related to estimation of mass %, volume %, mass flow, actual & standard volumetric flow, gas density, parts per million (ppm) by weight & by volume.
This document summarizes a presentation made by Allied Group of Companies to Triveni Turbines on February 8, 2012 about sterling deaeration technology. It introduces several companies in the Allied Group and discusses Allied Energy Systems' manufacturing of deaerators in collaboration with Sterling Deaerator Co. of the US. It also provides details on deaeration processes, Sterling deaerator models, performance guarantees, project execution methodology, and case studies of installations with valued clients.
The document discusses the design of a Heat Recovery Steam Generator (HRSG) undertaken at Thermax Limited in Pune, India. It provides an overview of Thermax Limited, introduces boilers and HRSGs, and discusses the mechanical design of an HRSG according to Indian and American standards. The objectives are to recover heat from gas turbine exhaust to increase overall plant efficiency and design the HRSG to meet regulatory requirements. The document outlines the components, calculations, and inferences of the HRSG design project.
Knock out drums are vessels designed to remove and accumulate condensed and entrained liquids from relief gases. They can be either horizontal or vertical design, with the appropriate design determined by operating parameters and plant conditions. Horizontal drums are more economical for high vapor flow and large liquid storage needs, and have the lowest pressure drop. Vertical drums are used for low liquid loads or when space is limited, and are well-suited for incorporation into flare stacks. Knock out drums are available in different configurations that mainly differ in how the path of the vapor is directed, such as horizontally with vapor entering one end and exiting the other, or vertically with radial vapor inlet and top outlet.
This document discusses different components of fossil-fuel steam generators. It describes boilers, explaining that they are classified in various ways such as by tube content and fuel type. It also defines boiler horsepower. The document then discusses the purpose and advantages of economizers and air preheaters. It provides examples of calculating boiler and economizer efficiency. Finally, it describes superheaters and condensers, explaining superheater types and the purpose of condensers.
This document summarizes the major components of reciprocating compressors including the frame, cylinders, piston rods, crossheads, crankshaft, piston, bearings, packings, valves, capacity control devices, cylinder sizing considerations, rod loads, cooling and lubrication systems, and pipe sizing considerations. Key components are the cylinders which compress the gas, valves which regulate gas flow into and out of the cylinders, and connecting components like the piston rods, crossheads and crankshaft which convert rotational motion to linear motion to drive the pistons. The document discusses design considerations and specifications for each major component.
A QUICK ESTIMATION METHOD TO DETERMINE HOT RECYCLE REQUIREMENTS FOR CENTRIFUG...Vijay Sarathy
Turbomachinery Engineers often conduct studies to determine if a hot gas bypass is required for a given centrifugal compressor system. This would mean building a process model and simulating it for Emergency Shutdown conditions (ESD) & Normal Shutdown conditions (NSD) to check if the compressor operating point crosses the surge limit line (SLL). A quick estimation method that uses dimensionless number called the inertia number can be used to check prior to the study, if a Hot gas bypass (a.k.a. Hot Recycle) is required in addition to an Anti-surge line (ASV or a.k.a Cold Recycle).
The document describes different types of tank heads available from Baker Tank Head including:
1) 2:1 Semi-Elliptical tank heads available in sizes from 6-5/8 to 192 inches in diameter and thicknesses from 3/16 to 2 inches.
2) ASME flanged and dished tank heads in standard and intermediate sizes from 14 to 250 inches with thicknesses from 3/16 to 1-3/8 inches.
3) The document provides specifications on several other types of ASME and non-ASME compliant tank heads varying in size, thickness, and construction.
STEAM JET COOLING SYSTEM
Steam jet cooling system is a cooling technique which involves usage of steam and water for cooling purposes. In steam jet refrigeration systems, water can be used as the refrigerant. Like air, it is perfectly safe. These systems were applied successfully to refrigeration.
•Temperatures attained using water as a refrigerant are in the range which may satisfy air conditioning, cooling, or chilling requirements.
•Mostly low-grade energy and relatively small amounts of shaft work.
•This system are the utilization of mostly low-grade energy and relatively small amounts of shaft work.
•Not used when temperatures below 5°C are required.
Heat exchangers transfer thermal energy between two or more fluids at different temperatures. They are classified based on their transfer process, geometry, heat transfer mechanism, and flow arrangement. Shell-and-tube heat exchangers consist of a set of tubes in a shell container and are the most important type, used across many industries. Their design involves calculating the heat transfer rate, selecting appropriate materials and geometry, and ensuring optimal fluid velocities and pressure drops within design limits.
Heat exchanger: Shell And Tube Heat ExchangerAkshay Sarita
The document discusses shell and tube heat exchangers. It describes the basic heat transfer equation and dimensionless numbers used. Shell and tube heat exchangers are relatively inexpensive, compact, and can be designed for high pressures. They have fixed tube sheets, U-tubes, or floating heads. Components include shells, tubes, baffles, and tube sheets. Design considerations include materials, fluids, temperatures, pressures, and flow rates. Standards like TEMA provide guidelines for mechanical design and fabrication.
This document provides piping, instrumentation, and equipment symbols and numbering codes for a coke dry quenching plant. It includes symbols for various pumps, valves, heat exchangers, filters, blowers, instruments, and other components. The document also outlines equipment, instrument, motor/actuator, and nozzle numbering codes that include plant section numbers, tags, and progressive numbers for identification.
Analysis of Stress in Nozzle/Shell of Cylindrical Pressure Vessel under Inter...IJERA Editor
This work a comparative study of the methods of analysis of stress in vessel/nozzle, due to external loads. The
methods of analysis compared are WRC 107, WRC 297 and Method of Finite Elements. To make the
comparison between the methods, one model of nozzle has been developed without reinforcement plate. In this
nozzle it was applied external loads and after the application of the loads, compared the results of stress for the
three methods of analyses considered in this study.
This document provides guidelines for selecting, sizing, and specifying relief devices such as pressure relief valves and rupture disks. It discusses general criteria for relief device selection, mechanical design considerations, and specific selection criteria for different services. It also covers relief device calculations, requisitioning, specifications, identification, protection, packaging, and documentation. The guidelines are based on standards from ASME, API, and ISO, and are intended to help achieve maximum technical and economic benefit from standardization when designing oil, gas, chemical, and other processing facilities.
The document summarizes the key changes and new features in Version 4.40 of the CAESAR II pipe stress analysis software. Some of the main updates include revised piping codes, addition of the B31.11 code, expanded static load case options, automatic generation of hydrotest load cases, updates to the 3D graphics, and addition of new configuration options. The installation process for Version 4.40 is described, which includes running an installation driver from the included CD-ROM.
The document discusses performance assessment of compressors through field testing. It describes methods to measure free air delivery, isothermal power, volumetric efficiency and specific power requirement. The nozzle method and pump up method are explained to measure free air delivery. Calculations are provided as examples to determine isothermal efficiency and specific power consumption. Periodic performance assessment is important to minimize compressed air costs and improve system efficiencies.
The document provides details of a skirt analysis calculation for a vessel, including:
- Skirt and basering geometry and material properties
- Loads and stresses calculated using the Brownell and Young method
- Required thicknesses calculated for the basering, top ring, gusset plates, and skirt
- Minimum weld sizes calculated for the skirt/base junction and gusset/skirt welds
The analysis determines that the provided dimensions meet or exceed the calculated required thicknesses to withstand the loads from wind, dead weight, and other modeled conditions.
Estimating Gas Turbine Performance provides a method for estimating the performance of gas turbines using performance curves and site data. The method involves:
1. Calculating full load performance factors using site elevation, ambient temperature, and pressure drops to determine output, heat rate, heat consumption, and exhaust temperature and flow.
2. Calculating part load performance by first determining base load performance at site conditions, then using performance curves to determine heat consumption and exhaust conditions based on required load percentage.
3. Accounting for the effects of water or steam injection on output and heat rate using injection effects curves for a given flow required to meet a NOx emission level.
Definition and selection of design temperature and pressure prg.gg.gen.0001Efemena Doroh
This document provides guidelines for determining the design temperature and pressure of equipment and piping for oil and chemical plants. It defines key terms like operating temperature, design temperature, minimum metal temperature, and design pressure. It outlines general criteria for setting design temperature, such as adding 30°C to the maximum operating temperature below 343°C. It also provides special considerations and guidelines for various equipment types. Minimum design metal temperature should be set to avoid material brittleness at low temperatures and pressures.
An air preheater is a heat exchanger that heats incoming combustion air by transferring heat from the flue gases before they are exhausted to the atmosphere. This improves boiler efficiency. There are two main types: recuperative, which uses stationary heat transfer surfaces, and regenerative, which uses rotating heat transfer surfaces. Proper operation and maintenance is important to minimize issues like air leakage, erosion, corrosion, plugging, and fouling that can reduce the air preheater's effectiveness over time. Regular inspection and cleaning helps maintain high performance.
Cooling Tower: Types and performance evaluation, Efficient system operation, Flow control strategies and energy saving opportunities, Assessment of cooling towers
This document provides information on fired heaters, including methods of heat transfer, combustion, types of fired heaters, furnace parts, problems that can occur, and introduces several heaters at a refinery. It discusses the three main methods of heat transfer as conduction, convection, and radiation. Fired heaters use combustion of fuel to generate heat that is transferred to process fluids through tubes. Box and cylindrical designs are described. Key furnace parts and issues like overfiring, vibration, and inefficiency are outlined. Example heaters at the refinery include crude, vacuum, visbreaker, and hydrotreating unit heaters.
Taco CA expansion tanks provide air and water separation using a durable bladder. They are available in various sizes and capacities. CA tanks reduce expansion tank sizes by up to 80% compared to traditional steel tanks by using a bladder to separate air and water. This allows them to be pre-charged to the system pressure without needing initial water to compress air. CA tanks improve system performance by better controlling pressure and eliminating air issues.
The document discusses the design of emergency relief systems for exothermic batch reactors. It covers key components of a relief system including pressure relief devices, piping and headers, containment systems, and treatment systems. It also discusses models for sizing relief devices, including vessel and vent flow models as well as heat models. The CHEMCAD software is identified as a useful tool for designing relief systems and sizing relief devices.
Knock out drums are vessels designed to remove and accumulate condensed and entrained liquids from relief gases. They can be either horizontal or vertical design, with the appropriate design determined by operating parameters and plant conditions. Horizontal drums are more economical for high vapor flow and large liquid storage needs, and have the lowest pressure drop. Vertical drums are used for low liquid loads or when space is limited, and are well-suited for incorporation into flare stacks. Knock out drums are available in different configurations that mainly differ in how the path of the vapor is directed, such as horizontally with vapor entering one end and exiting the other, or vertically with radial vapor inlet and top outlet.
This document discusses different components of fossil-fuel steam generators. It describes boilers, explaining that they are classified in various ways such as by tube content and fuel type. It also defines boiler horsepower. The document then discusses the purpose and advantages of economizers and air preheaters. It provides examples of calculating boiler and economizer efficiency. Finally, it describes superheaters and condensers, explaining superheater types and the purpose of condensers.
This document summarizes the major components of reciprocating compressors including the frame, cylinders, piston rods, crossheads, crankshaft, piston, bearings, packings, valves, capacity control devices, cylinder sizing considerations, rod loads, cooling and lubrication systems, and pipe sizing considerations. Key components are the cylinders which compress the gas, valves which regulate gas flow into and out of the cylinders, and connecting components like the piston rods, crossheads and crankshaft which convert rotational motion to linear motion to drive the pistons. The document discusses design considerations and specifications for each major component.
A QUICK ESTIMATION METHOD TO DETERMINE HOT RECYCLE REQUIREMENTS FOR CENTRIFUG...Vijay Sarathy
Turbomachinery Engineers often conduct studies to determine if a hot gas bypass is required for a given centrifugal compressor system. This would mean building a process model and simulating it for Emergency Shutdown conditions (ESD) & Normal Shutdown conditions (NSD) to check if the compressor operating point crosses the surge limit line (SLL). A quick estimation method that uses dimensionless number called the inertia number can be used to check prior to the study, if a Hot gas bypass (a.k.a. Hot Recycle) is required in addition to an Anti-surge line (ASV or a.k.a Cold Recycle).
The document describes different types of tank heads available from Baker Tank Head including:
1) 2:1 Semi-Elliptical tank heads available in sizes from 6-5/8 to 192 inches in diameter and thicknesses from 3/16 to 2 inches.
2) ASME flanged and dished tank heads in standard and intermediate sizes from 14 to 250 inches with thicknesses from 3/16 to 1-3/8 inches.
3) The document provides specifications on several other types of ASME and non-ASME compliant tank heads varying in size, thickness, and construction.
STEAM JET COOLING SYSTEM
Steam jet cooling system is a cooling technique which involves usage of steam and water for cooling purposes. In steam jet refrigeration systems, water can be used as the refrigerant. Like air, it is perfectly safe. These systems were applied successfully to refrigeration.
•Temperatures attained using water as a refrigerant are in the range which may satisfy air conditioning, cooling, or chilling requirements.
•Mostly low-grade energy and relatively small amounts of shaft work.
•This system are the utilization of mostly low-grade energy and relatively small amounts of shaft work.
•Not used when temperatures below 5°C are required.
Heat exchangers transfer thermal energy between two or more fluids at different temperatures. They are classified based on their transfer process, geometry, heat transfer mechanism, and flow arrangement. Shell-and-tube heat exchangers consist of a set of tubes in a shell container and are the most important type, used across many industries. Their design involves calculating the heat transfer rate, selecting appropriate materials and geometry, and ensuring optimal fluid velocities and pressure drops within design limits.
Heat exchanger: Shell And Tube Heat ExchangerAkshay Sarita
The document discusses shell and tube heat exchangers. It describes the basic heat transfer equation and dimensionless numbers used. Shell and tube heat exchangers are relatively inexpensive, compact, and can be designed for high pressures. They have fixed tube sheets, U-tubes, or floating heads. Components include shells, tubes, baffles, and tube sheets. Design considerations include materials, fluids, temperatures, pressures, and flow rates. Standards like TEMA provide guidelines for mechanical design and fabrication.
This document provides piping, instrumentation, and equipment symbols and numbering codes for a coke dry quenching plant. It includes symbols for various pumps, valves, heat exchangers, filters, blowers, instruments, and other components. The document also outlines equipment, instrument, motor/actuator, and nozzle numbering codes that include plant section numbers, tags, and progressive numbers for identification.
Analysis of Stress in Nozzle/Shell of Cylindrical Pressure Vessel under Inter...IJERA Editor
This work a comparative study of the methods of analysis of stress in vessel/nozzle, due to external loads. The
methods of analysis compared are WRC 107, WRC 297 and Method of Finite Elements. To make the
comparison between the methods, one model of nozzle has been developed without reinforcement plate. In this
nozzle it was applied external loads and after the application of the loads, compared the results of stress for the
three methods of analyses considered in this study.
This document provides guidelines for selecting, sizing, and specifying relief devices such as pressure relief valves and rupture disks. It discusses general criteria for relief device selection, mechanical design considerations, and specific selection criteria for different services. It also covers relief device calculations, requisitioning, specifications, identification, protection, packaging, and documentation. The guidelines are based on standards from ASME, API, and ISO, and are intended to help achieve maximum technical and economic benefit from standardization when designing oil, gas, chemical, and other processing facilities.
The document summarizes the key changes and new features in Version 4.40 of the CAESAR II pipe stress analysis software. Some of the main updates include revised piping codes, addition of the B31.11 code, expanded static load case options, automatic generation of hydrotest load cases, updates to the 3D graphics, and addition of new configuration options. The installation process for Version 4.40 is described, which includes running an installation driver from the included CD-ROM.
The document discusses performance assessment of compressors through field testing. It describes methods to measure free air delivery, isothermal power, volumetric efficiency and specific power requirement. The nozzle method and pump up method are explained to measure free air delivery. Calculations are provided as examples to determine isothermal efficiency and specific power consumption. Periodic performance assessment is important to minimize compressed air costs and improve system efficiencies.
The document provides details of a skirt analysis calculation for a vessel, including:
- Skirt and basering geometry and material properties
- Loads and stresses calculated using the Brownell and Young method
- Required thicknesses calculated for the basering, top ring, gusset plates, and skirt
- Minimum weld sizes calculated for the skirt/base junction and gusset/skirt welds
The analysis determines that the provided dimensions meet or exceed the calculated required thicknesses to withstand the loads from wind, dead weight, and other modeled conditions.
Estimating Gas Turbine Performance provides a method for estimating the performance of gas turbines using performance curves and site data. The method involves:
1. Calculating full load performance factors using site elevation, ambient temperature, and pressure drops to determine output, heat rate, heat consumption, and exhaust temperature and flow.
2. Calculating part load performance by first determining base load performance at site conditions, then using performance curves to determine heat consumption and exhaust conditions based on required load percentage.
3. Accounting for the effects of water or steam injection on output and heat rate using injection effects curves for a given flow required to meet a NOx emission level.
Definition and selection of design temperature and pressure prg.gg.gen.0001Efemena Doroh
This document provides guidelines for determining the design temperature and pressure of equipment and piping for oil and chemical plants. It defines key terms like operating temperature, design temperature, minimum metal temperature, and design pressure. It outlines general criteria for setting design temperature, such as adding 30°C to the maximum operating temperature below 343°C. It also provides special considerations and guidelines for various equipment types. Minimum design metal temperature should be set to avoid material brittleness at low temperatures and pressures.
An air preheater is a heat exchanger that heats incoming combustion air by transferring heat from the flue gases before they are exhausted to the atmosphere. This improves boiler efficiency. There are two main types: recuperative, which uses stationary heat transfer surfaces, and regenerative, which uses rotating heat transfer surfaces. Proper operation and maintenance is important to minimize issues like air leakage, erosion, corrosion, plugging, and fouling that can reduce the air preheater's effectiveness over time. Regular inspection and cleaning helps maintain high performance.
Cooling Tower: Types and performance evaluation, Efficient system operation, Flow control strategies and energy saving opportunities, Assessment of cooling towers
This document provides information on fired heaters, including methods of heat transfer, combustion, types of fired heaters, furnace parts, problems that can occur, and introduces several heaters at a refinery. It discusses the three main methods of heat transfer as conduction, convection, and radiation. Fired heaters use combustion of fuel to generate heat that is transferred to process fluids through tubes. Box and cylindrical designs are described. Key furnace parts and issues like overfiring, vibration, and inefficiency are outlined. Example heaters at the refinery include crude, vacuum, visbreaker, and hydrotreating unit heaters.
Taco CA expansion tanks provide air and water separation using a durable bladder. They are available in various sizes and capacities. CA tanks reduce expansion tank sizes by up to 80% compared to traditional steel tanks by using a bladder to separate air and water. This allows them to be pre-charged to the system pressure without needing initial water to compress air. CA tanks improve system performance by better controlling pressure and eliminating air issues.
The document discusses the design of emergency relief systems for exothermic batch reactors. It covers key components of a relief system including pressure relief devices, piping and headers, containment systems, and treatment systems. It also discusses models for sizing relief devices, including vessel and vent flow models as well as heat models. The CHEMCAD software is identified as a useful tool for designing relief systems and sizing relief devices.
Stall can most easily be defined as a condition in which heat transfer equipment is unable to drain condensate and becomes flooded due to insufficient system pressure.
What causes stall?
Stall occurs primarily in heat transfer equipment where the steam pressure is modulated to obtain a desired output (i.e. product temperature). The pressure range of any such equipment ( coils, shell & tube, etc....) can be segmented into two (2) distinct operational modes: Operating and Stall
Operating: In the upper section of the pressure range the operating pressure (OP) of the equipment is greater than the back pressure (BP) present at the discharge of the steam trap. Therefore a positive pressure differential across the trap exists allowing for condensate to flow from the equipment to the condensate return line.
Stall: In the lower section of the pressure range the operating pressure (OP) of the equipment is less than or equal to the back pressure (BP) present at the discharge of the steam trap. Therefore a negative or no pressure differential exists, this does not allow condensate to be discharged to the return line and the condensate begins to collect and flood the equipment.
This document provides an overview of a project to install an air cooler on an existing well head facility. It discusses the project scope, aims, and objectives which are to reduce costs by allowing gas transfer through carbon steel piping using an air cooler. It then describes research conducted on air coolers, the different types including shell and tube, plate, regenerative, and adiabatic wheel heat exchangers. Finally, it discusses wellheads, their main components such as the casing head, tubing head, and Christmas tree, and their functions in regulating extraction of hydrocarbons from underground formations.
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805Vladimir Popovic
1. Pipelines must be pressure tested with all venting facilities closed and intermediate valves open. Pipelines must be slowly depressurized with all venting facilities open when emptying.
2. Before pressure testing, pipes must be covered with backfill to prevent movement, though joints and connections may be left unbackfilled for inspection. Temporary supports at pipe ends must not be removed until depressurization.
3. The allowable water loss is calculated using a formula that considers the pipeline volume, measured pressure loss, material properties, and includes an allowance factor for air content. The test section passes if the measured water loss does not exceed the calculated allowable amount.
Sealed central heating systems require components to accommodate for water expansion as the water is heated. These components include an external expansion vessel, pressure relief valve, filling loop, and pressure gauge. The expansion vessel replaces the feed and expansion cistern of vented systems. It comprises a steel cylinder divided by a rubber diaphragm that allows water to compress the air in the vessel as it expands with heat. System boilers also accommodate expansion internally without additional components. Proper sizing of the expansion vessel is necessary using formulas considering system volume, fill pressure and temperature, operating pressure and temperature, and resulting expansion factor.
This memo summarizes the design of a steam condenser for a 10MW power plant. Key aspects of the design include:
1. The condenser is single pass and single tube to condense steam from a turbine using cooling water at 25C from a river.
2. Calculations to determine the required heat transfer, mass flow rates, pressure drops and overall design took around 10-12 hours based on assumptions to simplify the complex real-world system.
3. The final design features 1703 condensing tubes that are 18 feet long in a 42 inch diameter cylindrical shell with 10 baffles and a triangular tube layout.
1. Ducts are sized using pressure drop and velocity criteria. The duct diameter is selected based on the air volume and desired constant pressure drop. Duct velocities are limited based on building type to control noise.
2. Elbows, T-branches, Y-branches, and reducers (transitions) are examples of duct fittings.
3. Volume dampers and fire dampers are examples of duct accessories.
4. Allowable duct velocities vary from 2-12 m/s depending on the building type, with typical office spaces around 6 m/s.
5. Supply ducts deliver conditioned air to spaces, return ducts remove air from spaces, and exhaust ducts remove
Pressure relief devices are important safety components that protect process equipment from overpressure. Standards like the ASME Boiler and Pressure Vessel Code provide guidelines for the proper design, installation, and sizing of relief valves, rupture disks, and other pressure relief devices. These standards help ensure personnel safety and prevent equipment damage in the event excess pressure develops from sources like explosions, fires, or pump failures.
5.good practice & hr imp activitiesRavi Shankar
The document provides guidance on good practices for collecting and maintaining important technical information about a power plant's equipment and operations. It recommends assembling a thermal kit from the turbine supplier with performance curves, as well as collecting heat balance diagrams, pump/fan curves, piping diagrams, specifications for heat exchangers and flow elements, and historical operating data. Maintaining this information in a centralized location helps engineers properly evaluate equipment performance and potential improvement projects.
The document provides guidance on preliminary design decisions for shell and tube heat exchangers. Key decisions include allocating which stream goes in the tubes vs shell based on factors like pressure, fouling, corrosion. The type of shell is selected based on the thermal stress from temperature differences between streams. Multiple exchangers can be arranged in parallel or series. An example process is given to estimate the number of exchangers in series needed based on the inlet and outlet temperatures of each stream. Initial estimates are also provided for calculating the heat duty, mean temperature difference, and overall heat transfer coefficient.
This document describes a procedure for determining the liquid permeability of a core sample using a liquid permeability device. The test involves applying confining pressure and nitrogen gas pressure to the core sample to force water through it. The time required to fill graduated flasks of different volumes is measured and entered into a template spreadsheet to calculate permeability based on Darcy's law. Potential sources of error are leakage through pores allowing gas to escape and not accounting for temperature effects.
This document discusses pressure relief systems, which are critical in the chemical process industries to safely handle overpressurization. It describes causes of overpressurization, types of safety valves and rupture disks used for relief, and components of open and closed pressure relief systems. Open systems vent non-hazardous gases to the atmosphere, while closed systems route flammable gases through flare headers and knockout drums to be burned in a flare stack. The document provides example calculations for sizing relief valves, piping, and other components to ensure systems can safely relieve pressure without resealing valves.
This document provides information about pipe stress analysis and thermal expansion. It discusses the objectives of stress analysis to ensure piping structural integrity and allowable load limits. Thermal expansion due to temperature changes is a key consideration, as it can cause stresses and loads on piping components. The document outlines the various loads on piping from weight, temperature changes, and occasional events. It also describes the steps of stress analysis and provides examples of calculating thermal expansion using equations and charts.
This document proposes a low-cost system for measuring steam flow in industrial processes. The system works by measuring the pressure drop across a steam pipeline, which is proportional to the square of the steam flow rate. A tank with a partition is installed in the pipeline, and the pressure difference is indicated by the water level in a gauge glass. By taking initial measurements and developing a plant-specific correlation, the steam flow can be estimated based on the pressure drop and used to optimize steam consumption. The proposed system provides a low-cost alternative for steam flow monitoring where more expensive meters cannot be afforded.
The document describes the piping systems on a ship. It discusses the importance of an efficient piping system and provides examples of common piping systems like bilge, ballast, fuel, cooling water, lubrication oil, compressed air, steam, and cargo tank systems. It emphasizes preparing accurate piping plans and diagrams using standardized symbols and labeling key details like pipe sizes, flow directions, and component capacities. Common arrangements for pumping, drainage, overflows, and other aspects of key systems are illustrated with diagrams.
Juan Pablo Hernández presented information on control valve sizing for compressible fluids. Control valves are used to meet process conditions and product quality specifications. Three methods for sizing control valves were compared: hand made calculations, Fisher software, and Aspen Hysys simulation. All three methods produced similar results for the example case of sizing a control valve for superheated steam. However, the Fisher software was identified as the preferred method due to providing reliable sizing in less time compared to hand calculations.
Blowing steam lines is done to remove foreign matter from equipment and piping after erection. It involves heating and cooling cycles from steam flow to loosen debris. Target plates are used to monitor cleaning, with stainless steel plates for final blows until plates show no pitting from debris. Procedures involve gradually opening and closing valves while maintaining pressure or rapid opening and closing to induce thermal shock for cleaning. Safety precautions must be followed regarding piping supports and exhaust direction.
PSV Flare system PSV Flare system PSV Flare systemBabaDook15
This document discusses the design of a typical flare system. It provides details on calculating flare loads for various contingencies like cooling water or power failure. It describes the causes of overpressure and discusses contingencies like fire, tube rupture, closed outlets, inadvertent valve openings, and utility failures. Sample calculations are presented for determining the temperature profile and sizing of flare headers and other system components like the flare stack. Manual calculation procedures are described along with the use of software programs for optimized header sizing.
This document discusses lessons learned from resolving issues with pilot valve instability on LNG storage tanks. It identifies several reasons for instability, including inaccurate plant design, sudden construction changes, and neglecting inlet pressure loss and built-up pressure in discharge lines. The key lessons are that the 3% rule for safety valves is insufficient for ensuring pilot valve stability, which requires understanding dynamics of the inlet line, discharge line, pressure source, and valve. Testing procedures that operate valves in unstable zones can also cause issues, so dampening systems may be needed to prevent chattering during startup with low evaporation rates. Cryogenic testing helps validate valve performance and damping system effectiveness at preventing instability.
Similar to Ashrae journal -_the_fundamentals_of_expansion_tanks (20)
ACEP Magazine edition 4th launched on 05.06.2024Rahul
This document provides information about the third edition of the magazine "Sthapatya" published by the Association of Civil Engineers (Practicing) Aurangabad. It includes messages from current and past presidents of ACEP, memories and photos from past ACEP events, information on life time achievement awards given by ACEP, and a technical article on concrete maintenance, repairs and strengthening. The document highlights activities of ACEP and provides a technical educational article for members.
Low power architecture of logic gates using adiabatic techniquesnooriasukmaningtyas
The growing significance of portable systems to limit power consumption in ultra-large-scale-integration chips of very high density, has recently led to rapid and inventive progresses in low-power design. The most effective technique is adiabatic logic circuit design in energy-efficient hardware. This paper presents two adiabatic approaches for the design of low power circuits, modified positive feedback adiabatic logic (modified PFAL) and the other is direct current diode based positive feedback adiabatic logic (DC-DB PFAL). Logic gates are the preliminary components in any digital circuit design. By improving the performance of basic gates, one can improvise the whole system performance. In this paper proposed circuit design of the low power architecture of OR/NOR, AND/NAND, and XOR/XNOR gates are presented using the said approaches and their results are analyzed for powerdissipation, delay, power-delay-product and rise time and compared with the other adiabatic techniques along with the conventional complementary metal oxide semiconductor (CMOS) designs reported in the literature. It has been found that the designs with DC-DB PFAL technique outperform with the percentage improvement of 65% for NOR gate and 7% for NAND gate and 34% for XNOR gate over the modified PFAL techniques at 10 MHz respectively.
We have compiled the most important slides from each speaker's presentation. This year’s compilation, available for free, captures the key insights and contributions shared during the DfMAy 2024 conference.
6th International Conference on Machine Learning & Applications (CMLA 2024)ClaraZara1
6th International Conference on Machine Learning & Applications (CMLA 2024) will provide an excellent international forum for sharing knowledge and results in theory, methodology and applications of on Machine Learning & Applications.
Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapte...University of Maribor
Slides from talk presenting:
Aleš Zamuda: Presentation of IEEE Slovenia CIS (Computational Intelligence Society) Chapter and Networking.
Presentation at IcETRAN 2024 session:
"Inter-Society Networking Panel GRSS/MTT-S/CIS
Panel Session: Promoting Connection and Cooperation"
IEEE Slovenia GRSS
IEEE Serbia and Montenegro MTT-S
IEEE Slovenia CIS
11TH INTERNATIONAL CONFERENCE ON ELECTRICAL, ELECTRONIC AND COMPUTING ENGINEERING
3-6 June 2024, Niš, Serbia
Embedded machine learning-based road conditions and driving behavior monitoringIJECEIAES
Car accident rates have increased in recent years, resulting in losses in human lives, properties, and other financial costs. An embedded machine learning-based system is developed to address this critical issue. The system can monitor road conditions, detect driving patterns, and identify aggressive driving behaviors. The system is based on neural networks trained on a comprehensive dataset of driving events, driving styles, and road conditions. The system effectively detects potential risks and helps mitigate the frequency and impact of accidents. The primary goal is to ensure the safety of drivers and vehicles. Collecting data involved gathering information on three key road events: normal street and normal drive, speed bumps, circular yellow speed bumps, and three aggressive driving actions: sudden start, sudden stop, and sudden entry. The gathered data is processed and analyzed using a machine learning system designed for limited power and memory devices. The developed system resulted in 91.9% accuracy, 93.6% precision, and 92% recall. The achieved inference time on an Arduino Nano 33 BLE Sense with a 32-bit CPU running at 64 MHz is 34 ms and requires 2.6 kB peak RAM and 139.9 kB program flash memory, making it suitable for resource-constrained embedded systems.
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesChristina Lin
Traditionally, dealing with real-time data pipelines has involved significant overhead, even for straightforward tasks like data transformation or masking. However, in this talk, we’ll venture into the dynamic realm of WebAssembly (WASM) and discover how it can revolutionize the creation of stateless streaming pipelines within a Kafka (Redpanda) broker. These pipelines are adept at managing low-latency, high-data-volume scenarios.
1. A S H R A E J O U R N A L ashrae.org N OVEM BER 201660
COLUMN ENGINEER’S NOTEBOOK
Steven T. Taylor
Steven T. Taylor, P.E., is a principal of Taylor Engineering in Alameda, Calif. He is a
member of SSPC 90.1.
BY STEVEN T. TAYLOR, P.E., FELLOW ASHRAE
The Fundamentals of
Expansion Tanks
Who would have thought such a simple piece of equipment, the expansion tank,
could be so misunderstood, including significant errors and misunderstandings in
published standards, handbooks, and manufacturer’s installation manuals? In this
month’s column, I hope to clear up some of these issues and to provide simple advice
for expansion tank sizing and piping.
I first got into the details of how expansion tanks work
when working as a commissioning agent for a mid-rise
office project in the late 1990s. The building operator
claimed the mechanical engineer made design errors
because:
•• The pressure at the bottom of the heating system
would rise to about 100 psig (690 kPag) when it warmed
up each morning, higher than the operator was used to
seeing.
•• The expansion tank, which was a precharged
bladder type tank, was not located at the pump
suction, as per the manufacturer’s installation and
operating manual (IOM), which stated, “…the expan-
sion tank must be connected as close as possible to
the suction side of the system circulating pump for
proper system operation.” Instead, the tank was lo-
cated on the roof, while the pumps (and boilers) were
in the basement.
•• The tank size was too small according to the sizing
equation in the mechanical code.
In fact, after looking into the details and fundamen-
tals of expansion tanks, which ultimately resulted in
an ASHRAEJournal article, “Understanding Expansion
Tanks,” published in 2003,1 I concluded there was noth-
ing at all wrong with the installation:
•• The pressure was well below the boiler and pip-
ing system component limits—all were rated for over
150 psig at 200°F (1034 kPag at 93°C)—so while the pres-
sure was higher than the operator was used to, it was not
excessive.
•• The manufacturer’s IOM was simply wrong. The
tank can literally be located anywhere in the system,
provided its precharge pressure and size are properly se-
lected. In this case, locating the tank on the roof resulted
in the smallest and least expensive tank.
•• The sizing equation in the model mechanical codes,
both the Uniform Mechanical Code2 and International
Mechanical Code,3 do not apply to precharged expan-
This article was published in ASHRAE Journal, November 2016. Copyright 2016 ASHRAE. Posted at www.ashrae.org. This article may not
be copied and/or distributed electronically or in paper form without permission of ASHRAE. For more information about ASHRAE Journal,
visit www.ashrae.org.
2. N OVEM BER 2016 ashrae.org A S H R A E J O U R N A L 61
COLUMN ENGINEER’S NOTEBOOK
sion tanks; they were extracted
from the ASMEBoilerandPressure
VesselCode-2015, Section VI,4 and
developed many years ago for plain
steel expansion tanks. They result
in larger than necessary sizes for
precharged expansion tanks.*
To understand these issues,
we need to revisit the funda-
mentals. Some of this discus-
sion is extracted from the
“Understanding Expansion Tanks”
article referenced above, but I
have not repeated all the details of
how to determine expansion tank
design pressures. Instead, these
calculations have been incorpo-
rated into a relatively easy to use
spreadsheet, described below.
FIGURE 1 Bladder expansion tank.
To System
Initial Precharge
Pressure, Pi
Before Connection to
System and When System
is Cold, Tmin
As Temperature Rises
Bladder Inflates
After Water Fully Expands at
Maximum Temperature, Tmax
Maximum
Pressure, Pmax
To System To System
In addition, information has been added showing
how expansion tank sizing formulas were derived
(see sidebar, “Expansion Tank Sizing Formulas”),
and typical expansion tank piping requirements are
described in detail (see sidebar, “Typical Expansion
Tank Piping”).
Purpose
Expansion tanks are provided in closed hydronic sys-
tems to:
•• Accept changes in system water volume as water
density changes with temperature to keep system pres-
sures below equipment and piping system component
pressure rating limits.
•• Maintain a positive gauge pressure in all parts of
the system to prevent air from leaking into the system.
•• Maintain sufficient pressures in all parts of the sys-
tem to prevent boiling, including cavitation at control
valves and similar constrictions.
•• Maintain net positive suction head required
(NPSHR) at the suction of pumps.
The latter two points generally apply only to high tem-
perature (greater than approximately 210°F [99°C]) hot
water systems. For most HVAC applications, only the
first two points need to be considered.
Tank Styles
There are four basic styles of expansion tanks:
1. Vented or open steel tanks. Since they are vented,
open tanks must be located at the highest point of the
system. Water temperature cannot be above 212°F
(100°C), and the open air/water contact results in a
constant migration of air into the system, causing cor-
rosion. Accordingly, this design is almost never used
anymore.
2. Closed steel tanks, also called plain steel tanks
or compression tanks by some manufacturers. This is
the same tank style as the vented tank, but with the vent
capped. This allows the tank to be located anywhere in
the system and work with higher temperatures. But they
still have the air/water contact that allows for corrosion,
and sometimes a gradual loss of air from the tank as it is
absorbed into the water.
Unless precharged to the minimum operating pres-
sure prior to connection to the system, this style
of tank also must be larger than precharged tanks.
(See sidebar, “Expansion Tank Sizing Formulas.”)
Accordingly, this design is also almost never used
anymore.
3. Diaphragm tanks. This was the first design of a
compression tank that included an air/water barrier (a
* These codes include a table that includes a column for “pressurized diaphragm type” tanks, correctly sized but limited to systems
with 195°F (91°C) average operating temperature, 12 psig (83 kPag) precharge pressure and 30 psig (200 kPag) maximum pres-
sure. No tables or equations are provided for other applications.
3. A S H R A E J O U R N A L ashrae.org N OVEM BER 201662
One of the first, and still the foremost, major pub-
lications on expansion tank sizing was written by
Lockhart and Carlson6 in 1953. The authors derived
the general formula for tank sizing, Equation 1 (with
variable names adjusted to match those used in this
article), from basic principles assuming perfect gas
laws:
V
V E E
P T
PT
P T
P T
E
P T
P T
E
t
s w p
s c
i s
s h
max s
wt
s c
max s
t
=
−( )
− − −
+
−
1
0..02Vs (1)
Where
Vt = tank total volume
Vs = system volume
Ps = starting pressure when water first starts to
enter the tank, absolute
Pi = initial (precharge) pressure, absolute
Pmax = maximum pressure, absolute
Ew = unit expansion ratio of the water in the sys-
tem due to temperature rise
=
v
v
h
c
−
1
vh = the specific volume of water at the maximum
temperature, Th.
vc = the specific volume of water at the minimum
temperature, Tc.
Ep = unit expansion ratio of the piping and other
system components in the system due to tem-
perature rise
= 3α T Th c−( )
a = coefficient of expansion of piping and other
system components, per degree
Th = maximum average water temperature in the
system, degrees absolute
Tc = minimum average water temperature in the
system, degrees absolute
Ts = starting air temperature in the tank prior to
fill, degrees absolute
Ewt = unit expansion ratio of water in the tank due
to temperature rise
Et = unit expansion ratio of the expansion tank
due to temperature rise
The last term (0.02Vs ) accounts for additional air
from desorption from dissolved air in the water.
This equation can be simplified to Equation2 by ignor-
ing small terms and assuming tank temperature stays
close to the initial fill temperature (typically a good
assumption, assuming no insulation on the tank or
piping to it, which is a common, and recommended,
practice):
V
V
v
v
T T
P
P
P
P
t
s
h
c
h c
s
i
s
max
=
−
− −( )
−
1 3α
(2)
This equation includes the credit for the expansion
of the piping system. This term is also relatively small
and the expansion coefficients are hard to deter-
mine given the various materials in the system, but
it is included in Equation2 since it is included in the
ASHRAEHandbook7 sizing equations, which in turn
were extracted from an article by Coad.8 This term is
also included in some, but not most, expansion tank
manufacturers’ selection software. Most manufactur-
ers conservatively ignore this term since it is small and
no larger than the terms already ignored in Equation2.
Ignoring this term results in Equation3.
V
v
v
V
P
P
P
P
t
h
c
s
s
i
s
max
=
−
−
1
(3)
The numerator is the volume of the expanded water,
Ve, as it warms from minimum to maximum tempera-
tures, so the equation can be written:
V
V
P
P
P
P
t
e
s
i
s
max
=
−
(4)
Expansion Tank
Sizing Formulas
flexible membrane, to eliminate air migration) and that
was designed to be precharged (to reduce tank size). The
flexible diaphragm typically is attached to the side of the
tank near the middle and is not field replaceable; if the
diaphragm ruptures, the tank must be replaced.
4. Bladder tanks. Bladder tanks use a balloon-like
bladder to accept the expanded water. Bladders are
often sized for the entire tank volume, called a “full
acceptance” bladder, to avoid damage to the bladder
in case they become waterlogged. Bladders are gener-
COLUMN ENGINEER’S NOTEBOOK
4. N OVEM BER 2016 ashrae.org A S H R A E J O U R N A L 63
† In the 2016 ASHRAE Handbook—Systems and Equipment, Chapter 13, the analogous equation includes a factor of 2, doubling
tank size. This is a common, but unnecessarily conservative, safety factor to ensure the tank does not overflow.
‡ In the 2016 ASHRAE Handbook Systems and Equipment, Chapter 13, the analogous equation is said to apply to all closed plain
steel tanks. In fact, it only applies to any tank that is not precharged.
§ The 12 psig (83 kPag) standard precharge comes from old residential construction where the boiler and expansion tank are typically
in the basement. This results in a slight positive pressure at the top of the system in a typical two-story house.
Where
Ve = (vh / vc – 1)Vs
Equation4 can be further simplified based on the style
of tank used. For vented tanks, the pressures are all the
same and the dominator limits to 1, so the tank size is
simply the volume of expanded water:†
Vented Tank V Vt e= (5)
For unvented plain steel tanks, the starting pres-
sure is typically atmospheric pressure with the tank
empty (no precharge). The tank is then connected to
the makeup water, which pressurizes the tank to the
fill pressure by displacing air in the system, essentially
wasting part of the tank volume. So the sizing equa-
tion‡ is:
Closed Tank (no precharge)
V
V
P
P
P
P
t
e
a
i
a
max
=
− (6)
Where
Pa = atmospheric pressure
For any tank that is precharged to the required initial
pressure, including properly charged diaphragm and
bladder tanks, but also including closed plain steel
tanks if precharged, Ps is equal to Pi so the sizing equa-
tion reduces to:
Precharged Tank V
V
P
P
t
e
i
max
=
−1
(7)
Note that this equation only applies when the
tank is precharged to the required Pi . Tanks are fac-
tory charged to a standard precharge of 12 psig (83
kPag).§ For higher desired precharge pressures,
either a special order can be made from the fac-
tory or the contractor must increase the pressure
with compressed air or a hand pump. But it is not
uncommon for this to be overlooked. This oversight
can be compensated for by sizing the tank using
Equation 8 (assuming atmospheric pressure at sea
level):
Closed Tank
(12 psig/26.7 psia [83 kPag/184 kPaa] precharge)
V
V
P P
t
e
i max
=
−
26.7 26 7. (8)
This will increase the tank size vs. a properly pre-
charged tank.
ASMEBoilerandPressureVesselCode-2015, Section VI,
includes sizing equations (as do the UMC and IMC,
which extract the equations verbatim), as shown in
Equation10, with variables revised to match those used
in this article:
V
V T
P
P
P
P
t
s h
a
i
a
max
=
−( )
−
0 00041 0 0466. .
(9)
Comparing the denominator of Equation9 to
Equation6, this formula is clearly for sizing a non-
precharged tank; it will overestimate the size of a pre-
charged tank.
The numerator is a curve fit of Ve; it assumes a mini-
mum temperature of 65°F (18°C) and is only accurate
in the range of about 170°F to 230°F (77°C to 110°C)
average operating temperature. Therefore, this equa-
tion cannot be used for very high temperature hot
water (e.g. 350°F [177°C]), closed-circuit condenser
water, or chilled water systems.
ally field replaceable. This is now the most common
type of large commercial expansion tank. (See sidebar,
“Typical Expansion Tank Piping,” for a typical piping
diagram.)
The three closed type expansion tanks described
above work by allowing water to compress a cham-
ber of air as the water expands with increasing tem-
perature (Figure 1). When the system is cold and the
water in the tank is at minimum level (which may
be no water at all), the tank pressure is at its initial
COLUMN ENGINEER’S NOTEBOOK
5. A S H R A E J O U R N A L ashrae.org N OVEM BER 201664
or precharge pressure, Pi . As the water in the system
expands upon a rise in temperature, water flows into
the tank and the air pocket is compressed, increasing
both the air and water system pressure. When the sys-
tem is at its highest temperature and the tank water
volume is at its design capacity, the resulting air and
water system pressure will be equal to or less than
the design maximum pressure, Pmax . Both Pi and Pmax
are predetermined by the designer as part of the tank
selection process.
# On one of our early high-rise projects in the late ‘80s, an improperly supported pipe caused a pump casing to crack, causing a ma-
jor leak. Naturally, the break occurred over a weekend when no one was around. The pump was located on the 30th floor. A security
guard in the lobby noticed the leak when water poured onto his desk after leaking through all 29 stories of office space. The damage
would have been minimal if the makeup water valve had been closed.
Figure2 shows how bladder expansion tanks are typi-
cally piped. Notes corresponding to numbers in the
figure are as follows:
1. Vertical tanks are most common for commercial
projects and mounted on the floor for ease of construc-
tion and maintenance access. Horizontal tanks are
also available for suspension from the structure above
where floor space is inadequate.
2. If makeup water is located at the expansion tank as
shown, the pressure reducing valve (PRV) setpoint may
conveniently be the same as the precharge pressure of
the tank (Pi ) so the two are coordinated regardless of
pump operation. It is possible, and sometimes neces-
sary, to have the two separated. For instance, there may
not be a convenient makeup water source near the
preferred tank location (see Note 5, for example).
In this case, the PRV setpoint must be adjusted to
account for the elevation difference between the PRV
and tank. In this case, however, the pressure at the
PRV will vary depending on pump operation. To avoid
overfilling the system, the makeup water connection
must be valved off once the system is filled and air
removed (see Note 3). In addition, because some over-
filling will inevitably occur, the tank should be sized
conservatively.
3. Once the system is filled and air is removed, the
makeup water connection should be valved off. This
prevents “feeding a flood” should there be a major
leak in the system.# When the system has small normal
water losses, e.g., at automatic air vents and pump
seals, the valve will have to be reopened occasionally.
A low-pressure alarm (Note 7) can be used to indicate
when a refill is needed.
4. A bypass around the PRV is recommended to
reduce the time required to fill the system. Higher
fill velocities also tend to help the water entrain air
bubbles and carry them toward the manual air vents at
high points.
5. Makeup water must be protected with backflow
preventers, per code. The available pressure must be
above the PRV setpoint. For high-rise buildings with
multiple domestic (or reclaimed) water pressure zones
and where the tank is located low in the building, it is
usually necessary to connect to the high pressure zone
riser rather than the low pressure zone serving plumb-
ing fixtures at the tank location. This requirement is
commonly overlooked.
6. A pressure relief valve must be located between
the tank isolation valve (Note 11) and the system con-
nection, so it is available even when the tank is valved
off for maintenance. On hot water systems, this valve
will be located at the boiler (per code), so it cannot be
valved off from the heat source.
7. A gauge pressure sensor or switch connected to the
building automation system is recommended to gener-
ate an alarm when the pressure drops below the mini-
mum pressure (Pi ), indicating either the system needs
refilling (see Note 3) or a major leak has occurred.
8. Expansion tank installation and operating manuals
(IOMs) generally recommend connecting to the side of
the system main piping, rather than the bottom (where
debris might migrate to the tank) or top (where air may
result in an air lock). If a bottom connection cannot be
avoided, a dirt leg with drain should be installed.
9. Sizing of the piping from the tank to the system is
somewhat controversial. In normal operation, the flow
rate of water as it moves back and forth to and from
the tank is very low. Even after a cold start, the water
temperature and volume in the system generally rise
slowly so the flow rate, and resulting pressure drop,
are low. A 0.75 in. (19 mm) line should be more than
Typical Expansion
Tank Piping
COLUMN ENGINEER’S NOTEBOOK
6. N OVEM BER 2016 ashrae.org A S H R A E J O U R N A L 65
The referenced article “Understanding Expansion
Tanks” goes into great detail about how to determine
the precharge and maximum pressures as well as pres-
sure relief valve setpoints. To improve ease of use and
accuracy, this procedure has been automated in an
expansion tank selection calculator spreadsheet5 that
may be downloaded for free from the author’s website.
Automated features include:
•• Calculation of water volume in piping based on
pipe size and length;
adequate in this case, regardless
of system size. (A larger line may
be desired for makeup water on
very large systems just to reduce fill
time, but it is not needed for the
expansion tank.) However, at least
two large manufacturers of expan-
sion tanks include in their IOMs a
pipe sizing table that varies pipe
size as a function of boiler capacity,
length of piping, and design water
temperature, with pipe sizes as
large as 2.5 in. (64 mm). The table
has apparently been around for
years and the assumptions used
to determine the pipe sizes are
apparently no longer known to the
manufacturers, based on enqui-
ries to the factory. In the author’s
opinion, it would take an almost
explosive rate of temperature
change to make the flow rate and
pressure drop through a 0.75 in.
(19 mm) pipe cause the relief valve
to open; and if that happens, so be it—that is what the
relief valve is for.
10. An isolation valve is needed to isolate the tank for
service. To prevent accidental discharge of the relief
valve due to overpressure, a lock guard or shield should
be installed, or the valve handle can simply be removed,
to discourage inadvertent closing of the valve.
11. A drain valve is needed at the tank to empty it for
service and to check and recharge air pressure.
12. An air separator is not actually part of the expansion
system (and not required on all systems), but is shown
here so its relationship with the tank connection is clear.
Locating it downstream of the makeup water supply al-
lows some of the air dissolved in the makeup water to be
immediately removed. Some manufacturers’ IOMs show
the makeup water upstream of the air separator and the
tank connection downstream to keep the tank connec-
tion close to the pump suction. But this compromises
the advantage of keeping the makeup and tank together
(Note 2), and there is usually no benefit to having the
tank connection right at the pump inlet (Note 14). How-
ever, either design will work satisfactorily.
13. An automatic air vent should be installed even
if the air separator is not used. Some tank manufac-
turers’ IOMs show automatic air vents right at the
expansion tank, but this should not be needed when
the tank is located below the piping main; air will rise
up to the vent in the main.
14. The figure shows the expansion tank upstream
of the pump. As explained in “Understanding Expan-
sion Tanks,” this is often the best location from a cost
perspective, but not always. In fact, the tank can be
located anywhere in the system as long as Pi and Pmax
are properly determined.
Automatic
Air Vent
From Chiller/Boiler
Connect to
Side of Pipe
Air Separator
To
Pump
13
12
8
9
7
10
6
11 2 5
3
1
4
Ball Valve with Locked Guard
Pressure Relief
(On Boiler for
HW System)
Low Pressure
Sensor/Switch
3/4 in.
Ball Valve
With Hose Bib
Connection
Precharged Bladder Expansion Tank Quick Fill Bypass
BFPD
Makeup
Water
With
Backflow
Protection
Pressure Reducing Valve
FIGURE 2 Typical expansion tank piping.
14
COLUMN ENGINEER’S NOTEBOOK
7. A S H R A E J O U R N A L ashrae.org N OVEM BER 201666
•• Determination of the critical pressure point based
on equipment ratings and elevations;
•• Calculation of pressure relief valve setpoint;
•• Determination of vapor pressure values based on
fluid temperature;
•• Suggested high and low temperature values based
on application; and
•• Calculation of expanded water volume and total
tank size.
All that is required to make the final expansion tank
selection is the manufacturer’s catalog or submittal
data.
Conclusions
Expansion tanks are a necessary part of all closed
hydronic systems to control both minimum and maxi-
mum pressure throughout the system. They are simple
pieces of equipment, but many misunderstandings exist
in manufacturer’s manuals, codes, and engineering
guides about where expansion tanks can and should be
located, how they are sized, and how they are piped. This
column, along with my prior article, “Understanding
Expansion Tanks,” should provide all the information
needed to properly design hydronic thermal expansion
systems.
References
1. Taylor, S. 2003. “Understanding expansion tanks.” ASHRAE
Journal (March).
2. Uniform Mechanical Code-2015.
3. International Mechanical Code-2015.
4. ASME Boiler and Pressure Vessel Code-2015, Section VI, Recom-
mended Rules for the Care and Operation of Heating Boilers.
5. Taylor Engineering. 2016. “TE Expansion Tank Selection Cal-
culator, v1.6.” http://tinyurl.com/j9l8ydk.
6. Lockhart, H., G. Carlson. 1953. “Compression tank selection
for hot water heating systems.” ASHVE Transactions 59:55 – 76.
7. 2016 ASHRAE Handbook—Systems and Equipment, Chap. 13, Equa-
tions 13 to 15.
8. Coad, W. 1980. “Expansion tanks,” HPAC Engineering (May).
COLUMN ENGINEER’S NOTEBOOK
Advertisement formerly in this space.