This document outlines methods for developing factored cost estimates, including capacity factored estimates (CFE) and equipment factored estimates (EFE). CFEs derive a new plant's cost from a reference plant based on their capacity ratio and a scaling exponent between 0.5-0.85. EFEs factor in specific equipment costs and non-equipment multipliers. It discusses using capacity and equipment factors, cost indices, and accounting for differences in scope, size, location and time. Factored estimates are useful early in projects but become less reliable for larger extrapolations due to technology and regulatory changes.
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessAlberto Sanchez
The document provides guidance on developing and reviewing baseline construction schedules. It discusses common planning problems, the importance of the planning process before scheduling, and key elements to define the schedule basis including assumptions, exclusions, constraints, and more. It also covers estimating construction durations using productivity rates, developing resource loaded schedules, and factors that can impact the baseline schedule such as location, labor availability, and construction methods.
Pr 1159 - commissioning and start-up procedureRagul Selvam
This document provides guidance for the preparation and execution of commissioning, completion, startup, and project handover activities for projects. It aims to achieve consistency across projects. Successful execution depends on having a detailed commissioning scope, integrated planning, experienced resources, sufficient preparation time, and using effective processes. The document covers pre-commissioning, commissioning, startup testing, and handover of facilities to operations. It is intended for use by project, contractor, and operations personnel involved in commissioning and startup.
This document provides an overview of project management for engineering, procurement, and construction (EPC) projects. It discusses the typical project life cycle from inquiry to warranty, including the acquisition, bid, project, and warranty phases. It also describes common project management standards and frameworks such as ISO 21500, IPMA, PMI, and how they translate to EPC projects. The document is intended as a handbook for EPC project managers.
New Trends in Construction Management
Construction Management
Construction Technology
Construction Planning and Management Systems using Primavera
Fundamentals of Construction Costs and Estimating
Plumbing Systems I: Code and Engineering
Construction Changes and Claims Documentation
Legal Aspects of Construction Projects and Contracts
Principles of Structural Analysis
Advanced Estimating and Management of Project Costs in the Preconstruction and Construction Phases
Construction Surveying and Metrics
Construction Budget and Cost Control
Construction Job Site Management
Construction Project Management Using MS Project
Reading Construction Blueprints
Electrical Design and Construction
The Solar Energy Solution: Harnessing Solar Power in the Home and Office
Leadership in Energy and Environmental Design
Introduction to Building Information Modeling
Construction Estimating and Design Analysis Using BIM
Land Development Procedures
This document provides an overview of an oil and gas engineering training program. It covers topics like project engineering, design basis, engineering disciplines, process design, equipment, piping and instrumentation, civil works, and health and safety. The training aims to give participants a detailed understanding of the engineering activities in various disciplines and show sample deliverables. It also explains the challenges of oil and gas engineering projects. The document contains several figures to illustrate engineering workflows, project organization, and more.
Front End Engineering Design (FEED) Project Control TrainingDEVELOP
DEVELOP Training Center (TM) conducts Front End Engineering Design (FEED) Project Control Training, which is very useful to gain skills on how to plan & control projects, as well as navigate and optimize the Project execution.
This training will be useful to gain skills on how to plan & control projects, as well as navigate and optimize the FEED Project execution, such as : FEED Work Order-Scope,FEED Stakeholder identification,FEED Project Deliverables,FEED Multidiscipline Man-hour Calculation-productivity,Engineering-Procurement-Construction Project Contract technical issues-investment Cost Estimation ,FEED Review Cycle,EPC Long lead items,FEED Close out Report-Lessons Learnt
The document discusses construction productivity measurement and benchmarking. It defines productivity and explains why it is important, especially for the construction industry. Some key factors affecting construction labor productivity are identified. The document also discusses quality and its relationship to productivity. Various methods for improving productivity are outlined. Productivity calculation and benchmarking models and their application to the construction industry are explained. Labor productivity studies comparing different regions in India and internationally are summarized.
This document discusses engineering, procurement, and construction (EPC) projects and opportunities for improvement through automation. It provides an overview of EPC project challenges, contrasts EPC and architecture, engineering, and construction projects, reviews principal EPC functions and engineering disciplines. It also discusses the evolution of CAD use, levels of modeling including 2D, 3D, 4D, and 5D, and provides a case study of a $2.5 billion EPC copper concentrator plant project in Chile. The document proposes using a work execution package matrix to coordinate material management across spatial divisions and commodity types.
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessAlberto Sanchez
The document provides guidance on developing and reviewing baseline construction schedules. It discusses common planning problems, the importance of the planning process before scheduling, and key elements to define the schedule basis including assumptions, exclusions, constraints, and more. It also covers estimating construction durations using productivity rates, developing resource loaded schedules, and factors that can impact the baseline schedule such as location, labor availability, and construction methods.
Pr 1159 - commissioning and start-up procedureRagul Selvam
This document provides guidance for the preparation and execution of commissioning, completion, startup, and project handover activities for projects. It aims to achieve consistency across projects. Successful execution depends on having a detailed commissioning scope, integrated planning, experienced resources, sufficient preparation time, and using effective processes. The document covers pre-commissioning, commissioning, startup testing, and handover of facilities to operations. It is intended for use by project, contractor, and operations personnel involved in commissioning and startup.
This document provides an overview of project management for engineering, procurement, and construction (EPC) projects. It discusses the typical project life cycle from inquiry to warranty, including the acquisition, bid, project, and warranty phases. It also describes common project management standards and frameworks such as ISO 21500, IPMA, PMI, and how they translate to EPC projects. The document is intended as a handbook for EPC project managers.
New Trends in Construction Management
Construction Management
Construction Technology
Construction Planning and Management Systems using Primavera
Fundamentals of Construction Costs and Estimating
Plumbing Systems I: Code and Engineering
Construction Changes and Claims Documentation
Legal Aspects of Construction Projects and Contracts
Principles of Structural Analysis
Advanced Estimating and Management of Project Costs in the Preconstruction and Construction Phases
Construction Surveying and Metrics
Construction Budget and Cost Control
Construction Job Site Management
Construction Project Management Using MS Project
Reading Construction Blueprints
Electrical Design and Construction
The Solar Energy Solution: Harnessing Solar Power in the Home and Office
Leadership in Energy and Environmental Design
Introduction to Building Information Modeling
Construction Estimating and Design Analysis Using BIM
Land Development Procedures
This document provides an overview of an oil and gas engineering training program. It covers topics like project engineering, design basis, engineering disciplines, process design, equipment, piping and instrumentation, civil works, and health and safety. The training aims to give participants a detailed understanding of the engineering activities in various disciplines and show sample deliverables. It also explains the challenges of oil and gas engineering projects. The document contains several figures to illustrate engineering workflows, project organization, and more.
Front End Engineering Design (FEED) Project Control TrainingDEVELOP
DEVELOP Training Center (TM) conducts Front End Engineering Design (FEED) Project Control Training, which is very useful to gain skills on how to plan & control projects, as well as navigate and optimize the Project execution.
This training will be useful to gain skills on how to plan & control projects, as well as navigate and optimize the FEED Project execution, such as : FEED Work Order-Scope,FEED Stakeholder identification,FEED Project Deliverables,FEED Multidiscipline Man-hour Calculation-productivity,Engineering-Procurement-Construction Project Contract technical issues-investment Cost Estimation ,FEED Review Cycle,EPC Long lead items,FEED Close out Report-Lessons Learnt
The document discusses construction productivity measurement and benchmarking. It defines productivity and explains why it is important, especially for the construction industry. Some key factors affecting construction labor productivity are identified. The document also discusses quality and its relationship to productivity. Various methods for improving productivity are outlined. Productivity calculation and benchmarking models and their application to the construction industry are explained. Labor productivity studies comparing different regions in India and internationally are summarized.
This document discusses engineering, procurement, and construction (EPC) projects and opportunities for improvement through automation. It provides an overview of EPC project challenges, contrasts EPC and architecture, engineering, and construction projects, reviews principal EPC functions and engineering disciplines. It also discusses the evolution of CAD use, levels of modeling including 2D, 3D, 4D, and 5D, and provides a case study of a $2.5 billion EPC copper concentrator plant project in Chile. The document proposes using a work execution package matrix to coordinate material management across spatial divisions and commodity types.
The document discusses key issues faced in Engineering, Procurement, and Construction (EPC) projects and provides recommendations to address them. It summarizes EPC capabilities, project lifecycle, and common issues around quantity variation, drawings delays, constructability, procurement delays, and monitoring of critical items. Root cause analyses are presented for key issues. Recommendations are provided around talent retention, standardization, coordination, vendor management, approvals processes, and quality assurance to minimize variations and delays.
Process Related, Mechanical and Piping Workshop by Technipignitetribes
The document provides an overview of process related aspects in offshore oil and gas. It begins with an introduction to offshore oil and gas field layout, including satellite platforms that separate bulk fluids and a central processing platform for finer separation. It then outlines the key process areas in more detail, including gas/liquid separation, water/condensate separation, chemical injection, compression, dehydration, export pipelines, and pigging. The purpose and basic design of equipment for each process area is described.
The document provides an overview of EPC (engineering, procurement, and construction) contracts. Key points include:
1) EPC contracts involve a single contractor who is responsible for design, procurement, construction, and sometimes financing of a project for a fixed price.
2) EPC contracts simplify communication for owners but carry more risk for contractors.
3) Successful EPC projects require clear scopes, specifications, schedules, and payment terms from owners, as well as diligent coordination from contractors.
4) EPC contracts are commonly used for large oil/gas, power, and industrial projects worldwide.
This document is a proposal from Dirham Mujahid Al-Salah Est. for general contracting, building, road construction, mechanical, electrical maintenance and operation works. It was prepared for the Master Gas Pipeline Phase I Projects Division of the Ministry of Energy, Industry and Mineral Resources in Riyadh, Saudi Arabia, under contract number S6il0032833 with C.A.T. International Co. LTD. The proposal includes the contractor's contact information and credentials.
Mega Project Management In The Oil & Gas IndustryStephen_Forster
The document discusses challenges with managing mega-projects in the oil and gas industry. It describes a mega-project as having many participants that must coordinate complex activities. The top 5 challenges with mega-projects are identified as document control, performance reporting, change management, risk management, and system turnover. Best practices for resolving the challenges include using integrated software for scheduling, document management, risk analysis, and performance reporting to improve collaboration and project outcomes. The presentation concludes with a case study on a mega-project by Motiva and lessons learned on implementing best practices.
This document discusses construction productivity and benchmarking. It defines productivity as output per unit of input. Productivity is important for economic growth and competitiveness. Construction productivity depends on factors like project uniqueness, technology, management, labor organization, and training. Methods to improve productivity include training programs, incentives, site facilities, safety programs, and benchmarking. Benchmarking involves comparing performance to other organizations to identify best practices. Key performance indicators in construction include cost, schedule, quality, and labor productivity. The document presents data on labor productivity benchmarks for activities like concreting in different Indian regions and internationally.
Epc project interdepency and Work Flow- promoignitetribes
Engineering, Procurement and Construction are highly correlated and set precedence against each other. They are very interdependent and these dependencies become increasingly critical as the phases are overlapped. In this module we share the interdependence of Engineering - Procurement and the influence in Construction. Here we touch a bit on work front monitoring and work face planning.
Pipeline integrity assessment with LRUT methodpaulus konda
As a product of transportation facility, pipeline sould be having a good integrity. Pipeline failure means that pipeline can not operate both at some segment/section or all of pipeline segment can not deliver product/service as per their function. Or failure of pipeline also means loss of pipeline integrity for some segment pipeline section or all of segment pipeline.
The document discusses international EPC (engineering, procurement, and construction) projects. It defines EPC projects and international EPC projects. Typical international EPC project types include gas processing, power plants, steel mills, and infrastructure projects. The document also outlines the development process for EPC projects including bidding procedures. It discusses business models for international EPC contractors and a SWOT (strengths, weaknesses, opportunities, threats) analysis for contractors working on international projects.
This document appears to be a list of project documents and engineering procedures for Saudi Aramco. It includes titles such as "Project Execution Plan", "Equipment Inspection Schedule", "Capital Project Benchmarking Guidelines", "Pipelines/Piping Hydraulic Surge Analysis", and "Environmental Performance Assessment (EPA) Program". The document provides titles and identification codes for over 20 engineering documents and procedures related to projects, facilities, and systems for Saudi Aramco.
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
Details of how a Gas & Oil Plant is constructed, and how the progress, safety and quality is monitored and controlled. Also the measures to ensure that the site is environmentally friendly.
The document provides a method statement for piping installation works at the Dabbiya site for the Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins project. It outlines the scope of works, sequence of activities, resources, HSE requirements, and emergency contacts. Piping works will involve transporting prefabricated spools to site, lifting them into position, welding field joints, installing valves, and testing. Welding will follow approved procedures and NDT testing. HSE precautions like PPE and fire safety will be enforced during the medium risk work.
Construction Project Management is an important subject to learn in Civil Engineering.
Significance • As construction involves various activities starting from the design and planning to project completion and quality check, there is a exorbitant need for Management of construction. • Construction Industry plays a crucial role in the economy and development of a nation.
4. Objectives To complete the project in specified time and with allocated budget. To Plan and schedule the work and distribute between various departments. Deployment of personnel in Different tasks. To achieve High quality workmanship. Creating an organisation that works as a team. Using the limited available resources and producing maximum output. Providing safe and satisfactory working conditions for all personnel and workers.
5. Functions: Planning & Scheduling Organizing Staffing Directing Controlling & Co-ordinating
6. Stages of construction Briefing Designing Tendering Construction Commissioning
7. 1) Briefing Stage • This stage consists of framework required for the construction work to take a shape from the ideology of client and feasibility of Project which involves architects, engineers and project manager.
Objectives Developing Alternatives Feasible Solution ? Evaluation of Alternatives Report & Recommendation Technical and non technical Investigations
8. 2) Designing or planning Stage Prepare construction schedule Prepare final cost estimate Prepare Working Drawings and specificati ons Prepare scheme and detailed designs Soil investigations, Topographic investigation, material supply and market surveys etc Carry out Technical Investigations Final adoption of the most suitable summary Finalize Project Summary
This program addresses in an integrated manner the key activities involved in the safe, effective and timely commissioning and start-up of a new plant or facility. Start Up and Commissioning of new plant and equipment presents both a major technical and management challenge. An organisation’s personnel must familiarise themselves with new equipment, processes and technologies, develop the relevant operating and safety procedures.
At the same time there is the requirement to execute an exceptionally large scope of work – much of it complex when compared to routine operations - over a short period of time, with equipment and plant which is as yet unproven and that may pose significant risks to personnel, environment and profitability.
This 5 day training course addresses the technical issues of commissioning and starting up various equipment and asset types commonly found in processing plant environments, the development of specific commissioning procedures, process and facility wide commissioning strategies. The course will also address the broader managerial issues of commissioning and start up planning, resourcing, budgeting and cost control, risk management – safety, environmental, financial and operational, problem solving and trouble shooting.
Presentation by
Primary Information Services
www.primaryinfo.com
mailto:primaryinfo@gmail.com
Download PDF Version at
https://www.slideshare.net/thorapadi/presentations
See Youtube Channel
https://www.youtube.com/user/ch600091/videos?view_as=subscriber
The document discusses cost estimation for construction projects. It describes the major categories of costs for a construction project, which include initial capital costs like construction, land acquisition, and design fees, as well as ongoing operation and maintenance costs. It also discusses approaches to cost estimation, including estimating based on historical cost data, unit costs, and computer-aided methods. Cost contingencies are also addressed.
The document discusses strategies for improving asset integrity management in the oil and gas industry. It covers the importance of asset integrity, especially as Asia Pacific's role in oil and gas production increases. It outlines some danger signs that integrity is lacking, such as staff not feeling concerns are addressed and procedures being bent rather than followed. The document advocates making staff a central part of integrity processes so they can help identify and address small issues. It also lists 24 pillars that contribute to a successful asset integrity and HSE strategy, including performance management, knowledge management, and regulatory compliance.
Project Control Practical Way by Herve Baronignitetribes
Here are some key ways to measure procurement progress:
- % Progress based on weighted value of POs, broken down into steps like PO placement, material receipt, inspection, etc.
- Milestones like:
- % of PO value placed
- % of line items with approved submittals
- % of line items where material is received/inspected
- % of line items fully delivered
Tracking procurement progress through milestones helps ensure critical items are on track and identifies delays early. Milestones should reflect major stages from PO placement through delivery and inspection. This provides a more objective view than % progress alone.
Both % progress and milestone tracking are needed to effectively monitor procurement.
This document discusses various methods for estimating capital costs for chemical engineering projects. It describes different types of cost estimates ranging from order-of-magnitude to detailed estimates. It also covers adjusting costs based on changes in equipment capacity and time. Methods like Lang factors, module cost approach, and total plant cost estimates are outlined. Factors like materials, pressure, and temperature that influence capital costs are also addressed.
This document discusses different types of capital cost estimates for projects with increasing levels of accuracy:
1. Order of magnitude estimates (25-15% accuracy) use existing plant data for capacity and inflation adjustments.
2. Study estimates (30-20% accuracy) roughly size major equipment.
3. Preliminary design estimates (25-15% accuracy) include major equipment, piping, instrumentation, and electrical costs.
The total capital cost includes direct costs, indirect costs, contingency, fees, and auxiliary facilities. Direct costs cover equipment, materials, labor, freight, and taxes. Indirect costs include construction overhead and engineering expenses.
The document discusses key issues faced in Engineering, Procurement, and Construction (EPC) projects and provides recommendations to address them. It summarizes EPC capabilities, project lifecycle, and common issues around quantity variation, drawings delays, constructability, procurement delays, and monitoring of critical items. Root cause analyses are presented for key issues. Recommendations are provided around talent retention, standardization, coordination, vendor management, approvals processes, and quality assurance to minimize variations and delays.
Process Related, Mechanical and Piping Workshop by Technipignitetribes
The document provides an overview of process related aspects in offshore oil and gas. It begins with an introduction to offshore oil and gas field layout, including satellite platforms that separate bulk fluids and a central processing platform for finer separation. It then outlines the key process areas in more detail, including gas/liquid separation, water/condensate separation, chemical injection, compression, dehydration, export pipelines, and pigging. The purpose and basic design of equipment for each process area is described.
The document provides an overview of EPC (engineering, procurement, and construction) contracts. Key points include:
1) EPC contracts involve a single contractor who is responsible for design, procurement, construction, and sometimes financing of a project for a fixed price.
2) EPC contracts simplify communication for owners but carry more risk for contractors.
3) Successful EPC projects require clear scopes, specifications, schedules, and payment terms from owners, as well as diligent coordination from contractors.
4) EPC contracts are commonly used for large oil/gas, power, and industrial projects worldwide.
This document is a proposal from Dirham Mujahid Al-Salah Est. for general contracting, building, road construction, mechanical, electrical maintenance and operation works. It was prepared for the Master Gas Pipeline Phase I Projects Division of the Ministry of Energy, Industry and Mineral Resources in Riyadh, Saudi Arabia, under contract number S6il0032833 with C.A.T. International Co. LTD. The proposal includes the contractor's contact information and credentials.
Mega Project Management In The Oil & Gas IndustryStephen_Forster
The document discusses challenges with managing mega-projects in the oil and gas industry. It describes a mega-project as having many participants that must coordinate complex activities. The top 5 challenges with mega-projects are identified as document control, performance reporting, change management, risk management, and system turnover. Best practices for resolving the challenges include using integrated software for scheduling, document management, risk analysis, and performance reporting to improve collaboration and project outcomes. The presentation concludes with a case study on a mega-project by Motiva and lessons learned on implementing best practices.
This document discusses construction productivity and benchmarking. It defines productivity as output per unit of input. Productivity is important for economic growth and competitiveness. Construction productivity depends on factors like project uniqueness, technology, management, labor organization, and training. Methods to improve productivity include training programs, incentives, site facilities, safety programs, and benchmarking. Benchmarking involves comparing performance to other organizations to identify best practices. Key performance indicators in construction include cost, schedule, quality, and labor productivity. The document presents data on labor productivity benchmarks for activities like concreting in different Indian regions and internationally.
Epc project interdepency and Work Flow- promoignitetribes
Engineering, Procurement and Construction are highly correlated and set precedence against each other. They are very interdependent and these dependencies become increasingly critical as the phases are overlapped. In this module we share the interdependence of Engineering - Procurement and the influence in Construction. Here we touch a bit on work front monitoring and work face planning.
Pipeline integrity assessment with LRUT methodpaulus konda
As a product of transportation facility, pipeline sould be having a good integrity. Pipeline failure means that pipeline can not operate both at some segment/section or all of pipeline segment can not deliver product/service as per their function. Or failure of pipeline also means loss of pipeline integrity for some segment pipeline section or all of segment pipeline.
The document discusses international EPC (engineering, procurement, and construction) projects. It defines EPC projects and international EPC projects. Typical international EPC project types include gas processing, power plants, steel mills, and infrastructure projects. The document also outlines the development process for EPC projects including bidding procedures. It discusses business models for international EPC contractors and a SWOT (strengths, weaknesses, opportunities, threats) analysis for contractors working on international projects.
This document appears to be a list of project documents and engineering procedures for Saudi Aramco. It includes titles such as "Project Execution Plan", "Equipment Inspection Schedule", "Capital Project Benchmarking Guidelines", "Pipelines/Piping Hydraulic Surge Analysis", and "Environmental Performance Assessment (EPA) Program". The document provides titles and identification codes for over 20 engineering documents and procedures related to projects, facilities, and systems for Saudi Aramco.
Oil & Gas Plant Construction, Project Execution PlanDavid H Moloney
Details of how a Gas & Oil Plant is constructed, and how the progress, safety and quality is monitored and controlled. Also the measures to ensure that the site is environmentally friendly.
The document provides a method statement for piping installation works at the Dabbiya site for the Al Dabbiya Phase-1 Additional Injection Wells Tie-Ins project. It outlines the scope of works, sequence of activities, resources, HSE requirements, and emergency contacts. Piping works will involve transporting prefabricated spools to site, lifting them into position, welding field joints, installing valves, and testing. Welding will follow approved procedures and NDT testing. HSE precautions like PPE and fire safety will be enforced during the medium risk work.
Construction Project Management is an important subject to learn in Civil Engineering.
Significance • As construction involves various activities starting from the design and planning to project completion and quality check, there is a exorbitant need for Management of construction. • Construction Industry plays a crucial role in the economy and development of a nation.
4. Objectives To complete the project in specified time and with allocated budget. To Plan and schedule the work and distribute between various departments. Deployment of personnel in Different tasks. To achieve High quality workmanship. Creating an organisation that works as a team. Using the limited available resources and producing maximum output. Providing safe and satisfactory working conditions for all personnel and workers.
5. Functions: Planning & Scheduling Organizing Staffing Directing Controlling & Co-ordinating
6. Stages of construction Briefing Designing Tendering Construction Commissioning
7. 1) Briefing Stage • This stage consists of framework required for the construction work to take a shape from the ideology of client and feasibility of Project which involves architects, engineers and project manager.
Objectives Developing Alternatives Feasible Solution ? Evaluation of Alternatives Report & Recommendation Technical and non technical Investigations
8. 2) Designing or planning Stage Prepare construction schedule Prepare final cost estimate Prepare Working Drawings and specificati ons Prepare scheme and detailed designs Soil investigations, Topographic investigation, material supply and market surveys etc Carry out Technical Investigations Final adoption of the most suitable summary Finalize Project Summary
This program addresses in an integrated manner the key activities involved in the safe, effective and timely commissioning and start-up of a new plant or facility. Start Up and Commissioning of new plant and equipment presents both a major technical and management challenge. An organisation’s personnel must familiarise themselves with new equipment, processes and technologies, develop the relevant operating and safety procedures.
At the same time there is the requirement to execute an exceptionally large scope of work – much of it complex when compared to routine operations - over a short period of time, with equipment and plant which is as yet unproven and that may pose significant risks to personnel, environment and profitability.
This 5 day training course addresses the technical issues of commissioning and starting up various equipment and asset types commonly found in processing plant environments, the development of specific commissioning procedures, process and facility wide commissioning strategies. The course will also address the broader managerial issues of commissioning and start up planning, resourcing, budgeting and cost control, risk management – safety, environmental, financial and operational, problem solving and trouble shooting.
Presentation by
Primary Information Services
www.primaryinfo.com
mailto:primaryinfo@gmail.com
Download PDF Version at
https://www.slideshare.net/thorapadi/presentations
See Youtube Channel
https://www.youtube.com/user/ch600091/videos?view_as=subscriber
The document discusses cost estimation for construction projects. It describes the major categories of costs for a construction project, which include initial capital costs like construction, land acquisition, and design fees, as well as ongoing operation and maintenance costs. It also discusses approaches to cost estimation, including estimating based on historical cost data, unit costs, and computer-aided methods. Cost contingencies are also addressed.
The document discusses strategies for improving asset integrity management in the oil and gas industry. It covers the importance of asset integrity, especially as Asia Pacific's role in oil and gas production increases. It outlines some danger signs that integrity is lacking, such as staff not feeling concerns are addressed and procedures being bent rather than followed. The document advocates making staff a central part of integrity processes so they can help identify and address small issues. It also lists 24 pillars that contribute to a successful asset integrity and HSE strategy, including performance management, knowledge management, and regulatory compliance.
Project Control Practical Way by Herve Baronignitetribes
Here are some key ways to measure procurement progress:
- % Progress based on weighted value of POs, broken down into steps like PO placement, material receipt, inspection, etc.
- Milestones like:
- % of PO value placed
- % of line items with approved submittals
- % of line items where material is received/inspected
- % of line items fully delivered
Tracking procurement progress through milestones helps ensure critical items are on track and identifies delays early. Milestones should reflect major stages from PO placement through delivery and inspection. This provides a more objective view than % progress alone.
Both % progress and milestone tracking are needed to effectively monitor procurement.
This document discusses various methods for estimating capital costs for chemical engineering projects. It describes different types of cost estimates ranging from order-of-magnitude to detailed estimates. It also covers adjusting costs based on changes in equipment capacity and time. Methods like Lang factors, module cost approach, and total plant cost estimates are outlined. Factors like materials, pressure, and temperature that influence capital costs are also addressed.
This document discusses different types of capital cost estimates for projects with increasing levels of accuracy:
1. Order of magnitude estimates (25-15% accuracy) use existing plant data for capacity and inflation adjustments.
2. Study estimates (30-20% accuracy) roughly size major equipment.
3. Preliminary design estimates (25-15% accuracy) include major equipment, piping, instrumentation, and electrical costs.
The total capital cost includes direct costs, indirect costs, contingency, fees, and auxiliary facilities. Direct costs cover equipment, materials, labor, freight, and taxes. Indirect costs include construction overhead and engineering expenses.
This document is a lecture on cost estimation that covers several topics:
1) It discusses capital costs including fixed capital and working capital.
2) It explains the breakdown of total product costs including manufacturing costs, general expenses, and their typical percentages.
3) It provides examples of cost estimation problems from referenced textbooks, showing calculations for direct costs, indirect costs, depreciation, taxes, net profit, and cash flow.
03 Chemical Engineering Plant Design And Economicsguestac67362
The document is a past exam paper for a Chemical Engineering Plant Design and Economics course. It contains 8 multi-part questions testing various concepts related to plant design, economics, and capital investment analysis. Specifically, it examines topics such as batch vs continuous operation, methods for estimating capital investment, components of fixed charges, taxation, depreciation methods, rate of return analysis, and optimization of plant design. Students were required to answer any 5 of the 8 questions in the 3 hour exam.
This document discusses methods for estimating capital and product costs. It describes several methods for estimating capital costs, including: (1) a detailed-item estimate, (2) a unit cost estimate based on existing data, and (3) estimating other capital costs as percentages of the delivered equipment cost. It also covers the power factor method of scaling costs based on capacity, as well as estimating capital using the turnover ratio. The document provides an overview of cost components and recommends methods suited to different levels of estimate accuracy needed.
The document discusses factors that influence the design of vessels used in industrial processes. It focuses on selecting the appropriate vessel type based on the material properties, operating conditions, and intended function. The main types of vessels discussed are open vessels, closed cylindrical vessels with flat or conical bottoms, and spherical/modified spherical vessels. Criteria for selecting each type include operating pressure and temperature, material hazards, and storage volume.
Project Controls Expo – 13th Nov 2013- "The Key Role of the Cost Engineer Ach...Project Controls Expo
The document discusses the key role of the cost engineer in achieving an integrated work process through a holistic mindset. It describes how cost engineers can add value by moving beyond basic cost estimating and control to engage across the project lifecycle through what-if analysis, regression analysis, and key metrics analysis. The document advocates for continuous improvement by maintaining historical project data to inform future projects. It also discusses the challenges cost engineers face in modern complex projects and the need for an integrated approach rather than working in silos.
This document presents an estimate input checklist and maturity matrix to map the extent and maturity of estimate inputs against five different estimate classification levels from Class 5 to Class 1. The checklist includes general project data and engineering deliverables that are considered basic inputs for cost estimates. For each input, the matrix indicates the expected maturity level - none, started, preliminary or complete - depending on the classification level of the estimate. The maturity level refers to the degree of completion or development of the input deliverable.
This Slideshare presentation is a partial preview of the full business document. To view and download the full document, please go here:
http://flevy.com/browse/business-document/capital-investment-analysis-230
Capital Investment Analysis
Also called Capital Budgeting - a complex topic simplified in an easy to understand presentation which is completely self-explanatory. Explains the framework for financial analysis with examples and provides practical insights. Can be used for reference, training & self paced learning. The presentation includes examples worked in an Excel sheet.
Covers:
* The nature & characteristics of long term investments made by corporations
* The problem associated with measuring the rate of return with long term investments
* The approach to solving this problem
* The key methods used in calculating the rate of return and evaluating alternatives
* The practical aspects of the various inputs required to calculate the return on investment
* The basics of the risks associated with long term investments & how to factor ?in such risks
* The strategic considerations involved in long term investment decisions
* The processes involved in long term investment decisions & its implementation
Types and methods of financial analysis are summarized in 3 sentences:
Financial analysis involves establishing relationships between financial statements to evaluate a firm's financial strength. There are various types of financial analysis classified by user and method, including external analysis by outsiders using published statements and internal analysis by executives having full records access. Common analysis methods examined include comparative statements, trend analysis, common-size statements, and ratio analysis which are used to interpret changes in financial positions and performance over time.
This document provides an introduction to cost engineering in the process industry. It discusses cost engineering methods and techniques for estimating, planning, cost control, contracting, quantity surveying, and value engineering. It also discusses the work areas of cost engineering like feasibility studies, evaluations, optimizations, capitalizations, and fiscal aspects. Finally, it discusses total cost management over the entire project life cycle from identification to abandonment and provides an estimating classification system for process industries.
EVALUATION OF PRECAST TECHNOLOGY ON PROJECT PROFITABILITYIAEME Publication
Objectives: The objective of this paper is to compare the precast technology with conventional construction and evaluate the precast technology on project profitability.
Methods: The methodology is to collect the data from precast and conventional construction companies. And analyze the collected data to compare the cost details and duration of the project of precast technology with conventional construction and evaluate the precast technology on project profitability.
Findings: The cost of the project is more in precast technology than the conventional construction, the duration of the project is less in precast technology than conventional construction. The precast technology is faster than the conventional construction so it is very useful in our country to grow the construction projects.
A MODEL STUDY ON COMPARATIVE COST ANALYSIS OF EQUIPMENT MANAGEMENT IN CONSTRU...IAEME Publication
Construction Equipment is the important factor to run the project in a successful manner. it is
important for both private constructions and also for Trust based organizational Construction
projects’ success. A large number of quantities of equipment are required in construction even in
small construction companies also there is a need to invest high initial cost in equipment. Nearly
40% of construction cost is related to equipment. This paper elevates the elements to be considered
while purchasing, leasing or renting the equipment, and guide in optimizing the profitability.
Methods of life cycle cost estimating and decision methods were researched and compared. Data
was acquired from equipment rental companies, private construction companies, and Trust base
organizational projects
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Charlie Jackson
The document provides lessons learned for effectively updating and maintaining schedules in Primavera P6. It discusses the importance of understanding contract requirements, establishing baselines, assigning responsibilities, providing training, gathering data through site visits, and understanding P6 settings. The key lessons include planning the update process, entering progress data, reviewing reports and analyses, and communicating schedule status. Maintaining the schedule in P6 requires properly setting up the software and following a structured process of planning, data collection, review, and communication.
The document discusses various measures used to evaluate the profitability of projects, including return on investment (ROI), payback period (PBP), net present worth or value (NPV), and discounted cash flow rate of return (DCFRR). It provides definitions and examples of calculating each measure. ROI is defined as average annual profit divided by total capital investment. PBP is the time for cumulative cash flows to recover the fixed capital investment. NPV considers the time value of money by taking the present value of all after-tax cash flows. DCFRR is the interest rate that results in an NPV of 0.
The document summarizes benefits of proper cost estimating techniques and provides case studies. It discusses fundamentals of cost estimates, including purpose and potential legal liability. Case studies examine a cost to complete estimate for unfinished subdivision work, finding the plaintiff's claim overstated, and a design-build project where cost overruns occurred due to inadequate contingencies and misaligned expectations between the designer and contractor. The document emphasizes importance of clear communication and standard practices in cost estimating.
Cash flow estimation ppt @ bec doms on financeBabasab Patil
The document discusses estimating cash flows for capital budgeting projects. It explains that cash flow estimation involves forecasting sales, costs, expenses, assets needed, depreciation, and taxes over time. The general process is the same for new projects, expansions, and replacements, but replacements typically require less estimation. Key steps are outlined for estimating cash flows for new ventures and replacements, including identifying incremental impacts and dealing with subjective estimates.
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-PaperRussell Archibald
This document discusses linking a comprehensive six-phase project life cycle model and concepts of project team cognitive readiness to the Total Cost Management (TCM) Framework. It recommends adopting the six-phase model as a standard, which includes an Incubation/Feasibility Phase before the Starting Phase and a Post-Project Evaluation Phase after Close-out. It also recommends revising the TCM Framework to recognize this comprehensive model and linking TCM principles throughout the project life cycle. More research is needed on applying concepts of project team cognitive readiness to improve teamwork on projects.
This document discusses various methods for estimating capital costs for industrial projects. It provides equations and percentages for estimating costs of major cost components like equipment, piping, construction, etc. It also discusses factors that influence cost estimates like plant capacity, material of construction, location indices. Costs are classified as fixed, variable, direct, indirect. Methods covered include index-based cost adjustment, factor rating based on capacity, step-counting based on process units.
This document discusses various cost estimation methodologies used for capital projects in the chemical process industries. It describes the AACE International classification system, which categorizes estimates from Class 5 (conceptual) to Class 1 (definitive) based on factors like project definition, accuracy, and preparation effort. Capacity-factored estimates are discussed as a Class 5 methodology used early in feasibility studies to compare project alternatives. The document outlines the capacity-factored estimation process and factors to consider, such as adjusting for scope differences, location costs, and time escalation between new and existing plants.
Cost-Estimation-Techniques unit 2.pptxSudipBalLama
The document discusses various cost estimation techniques that can be used for engineering economic analyses and capital investments. It describes top-down and bottom-up approaches, with top-down using historical data and bottom-up breaking projects into smaller work elements. An integrated approach uses a work breakdown structure, cost/revenue structure, and estimating models. Specific techniques discussed include indexes, unit costs, factors, parametric models, and learning curves. Cost estimation is important for setting prices, determining profits, and justifying investments.
The document discusses estimating the total installed cost (TIC) for instrumentation in bioderived process plants. It notes that pilot and demonstration plants for novel technologies may require more customized and complex instrumentation that is difficult to estimate using traditional factor-based methods. The Aspen Capital Cost Estimator (ACCE) tool does not use factored costs for instrumentation and allows the user to select the level of instrumentation detail in the estimate. For highly accurate estimates, the instrumentation design should be shown on Piping and Instrumentation Drawings and the ACCE customized accordingly. Specialty analyzers and monitoring systems also require specific costing.
A CCP is an experienced practitioner with advanced knowledge and technical expertise to apply the broad principles and best practices of Total Cost Management (TCM) in the planning, execution and management of any organizational project or program. CCPs also demonstrate the ability to research and communicate aspects of TCM principles and practices to all levels of project or program stakeholders, both internally and externally.
Integration of cost-risk within an intelligent maintenance systemLaurent Carlander
This document discusses integrating cost-risk assessment into an intelligent maintenance system for the UK rail industry. As rail schedules become more complex, detailed cost estimation will be difficult. Therefore, a stochastic process using uncertainty modeling and Monte Carlo simulation is needed to predict costs of maintenance and resulting delays. The paper proposes a cost model that quantifies cost uncertainty based on historical data and statistical distributions. Estimates from this model would be integrated into an existing prototype intelligent maintenance system to help optimize maintenance budgets and reduce delays. Accurately assessing costs under uncertainty is important for achieving anticipated cost efficiencies.
Technical efficiency measurement by data envelopment analysis an applicatio...Geetika Sharma
- The document discusses technical efficiency measurement using Data Envelopment Analysis (DEA). DEA is an optimization technique that calculates efficiency scores for decision-making units on a scale of 0-100%, with 100% being fully efficient.
- The study uses DEA to measure the technical efficiency of 44 Indian state road transport undertakings based on multiple inputs and outputs. It finds that only 8 of the 44 undertakings were scale efficient, and undertakings operating as companies tended to be more technically efficient.
- DEA involves constructing a "piecewise linear" frontier based on sample data to approximate best practice efficiency and calculate efficiency scores relative to this frontier.
The document discusses various methods for estimating capital costs for chemical processes, including order-of-magnitude, study, preliminary, definitive, and detailed estimates. It also covers techniques for estimating costs of individual purchased equipment based on capacity and time, as well as total plant capital costs using the six-tenths rule, Lang factor method, and bare module costing method. The bare module costing method relates all costs back to the purchased equipment cost under base conditions and uses factors to account for non-base materials and operating pressures.
This document discusses approaches to construction cost estimation. It describes the major cost categories for a construction project, including capital costs like construction, land acquisition, and financing, as well as operation and maintenance costs over the facility's lifetime. It outlines several approaches to cost estimation, including using production functions relating inputs like labor and materials to outputs, statistical cost functions, estimating costs from a bill of quantities by assigning unit costs to project components, and allocating joint costs from existing accounts. An example is given comparing resource requirements and costs for different types of energy projects.
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9Moustafa Ismail Abu Dief
This document provides an overview of cost estimating methodologies. It discusses five classes of cost estimates based on the level of project definition. Conceptual estimates use stochastic or factored methods and are appropriate for early project stages with little definition. Deterministic estimates use more detailed data as projects are better defined. Common conceptual methods described include end product units, physical dimensions, capacity factor, ratio or factor, and parametric modeling. The document provides examples of applying each method.
The document discusses several techniques for cost estimation:
Parametric uses statistical models to relate costs to independent variables. Analogy estimates costs based on historical data from analogous systems, adjusting for differences. Engineering estimates break systems into components and aggregate labor, materials, and overhead costs. Actual costs project future costs based on experience from prototypes and early production. Cost estimation provides efficiency and control but requires accurate models and data. Demand estimation derives the relationship between demand and factors like price and income to inform pricing and other decisions. Surveys for demand estimation face tradeoffs between information and reliability versus cost and complexity.
International Journal of Business and Management Invention (IJBMI) is an international journal intended for professionals and researchers in all fields of Business and Management. IJBMI publishes research articles and reviews within the whole field Business and Management, new teaching methods, assessment, validation and the impact of new technologies and it will continue to provide information on the latest trends and developments in this ever-expanding subject. The publications of papers are selected through double peer reviewed to ensure originality, relevance, and readability. The articles published in our journal can be accessed online.
Enhancing the Software Effort Prediction Accuracy using Reduced Number of Cos...IRJET Journal
This document presents research on modifying the COCOMO II software cost estimation model to improve prediction accuracy. The researchers reduced the number of cost estimation factors (called cost drivers) from 17 to 13 by adjusting the definitions and impact levels to better reflect current industry situations. They estimated effort for software projects using the modified model and found lower percentage errors compared to the original COCOMO II model, demonstrating improved estimation efficiency. The goal of the research was to analyze cost drivers and their impact on effort estimation in COCOMO II and enhance the model for more accurate predictions.
This document discusses various cost estimating models including the per-unit model, segmenting model, cost indexes, power-sizing model, and triangulation. The per-unit model derives the cost per unit from variable and fixed costs divided by units produced. The segmenting model partitions the total estimate into segments that are estimated individually and then combined. Cost indexes account for historical cost changes using indices. The power-sizing model accounts for economies of scale. Triangulation compares results from different data collection methods.
Siad el quliti economic scheduling the construction of electric transmissionsarah7887
This document discusses using dynamic programming to schedule construction of electric transmission/distribution substations in Jeddah City over a 10-year period to minimize total costs. Electric load was forecasted using regression and neural networks. A dynamic model was formulated with the objective of minimizing investment and operating costs given budget constraints. Parametric analysis showed the optimal solution of 3 substations per year was robust except for extreme changes in costs. Future research areas include incorporating time value of money and simultaneous parameter changes.
The document summarizes a research paper that evaluates using parametric analysis to estimate production cost improvement rates in the aerospace industry. The research paper aims to investigate if cost improvement can be estimated without reference to specific product types, by using characteristics of the product and production environment applicable across different types. The document outlines the objectives, hypotheses, and insights from the research paper, including compiling cost improvement data from different aerospace products and using regression analysis to fit learning curves and investigate relationships between costs and predictive parameters.
This document provides guidance on calculating and interpreting the process capability index Cpk. It defines Cpk as a ratio that compares the specification tolerance to the process variation expressed in terms of standard deviations. It explains how to calculate Cpk and discusses factors that influence Cpk values such as sample size, process centering, and measurement uncertainty. The document also provides examples of the expected defective parts per million that correspond to different Cpk values and factors to consider when improving Cpk, such as machine, tooling, workholding, and workpiece variables.
IRJET- Forecast Modelling and Performance Load Volume Analytic Techniques of ...IRJET Journal
This document discusses techniques for forecasting workload volumes and building performance workload models (WLMs) for application testing. It describes several forecasting methods like moving average, incremental percentage and ARMA/ARIMAX that incorporate independent variables. The key steps to build a WLM are identified, including understanding the application, scenarios, test data and distributing loads. The importance of using forecasted volumes from multiple techniques to simulate realistic production loads is emphasized. Building accurate WLMs is important for performance testing to emulate real-world usage patterns and avoid failures.
Forecasting Crude Oil Prices by using Deep Learning Based ModelIRJET Journal
This document discusses using deep learning models to forecast crude oil prices. It proposes a new hybrid model that uses deep learning techniques like LSTM, CNN, and RNNs. The model is trained on West Texas Intermediate crude oil market data and shows improved accuracy in price predictions compared to other methods. The document also reviews several other studies applying machine learning and deep learning approaches to crude oil price and energy market forecasting.
Cost Forecasting of Construction Materials: A reviewIRJET Journal
This document reviews different methods for forecasting construction material costs, including artificial neural networks. It discusses vector error-correction models, various time series models like an automated time series cost forecasting system using ARIMA modeling, and 5D BIM. The main goal is to provide reliable tools for predicting future prices of construction materials to help stakeholders like contractors and project owners with cost estimation and management on construction projects. Artificial neural networks and other AI methods could provide more accurate forecasts than traditional methods used in India by incorporating economic factors that influence material prices.
Retrofitting a new process to an existing facilityGBX Summits
The document describes a case study where a company called Bioproduction Group used process modeling and economic analysis to evaluate new technologies for a biopharmaceutical manufacturer's future plant designs. They created a "Plant of the Future" toolset that integrated new technologies with existing process data to accurately estimate throughputs and costs. This allowed the biopharmaceutical manufacturer to identify which new technology developments offered the best returns and minimized risks.
Retrofitting a new process to an existing facility
Aace factored cost estimation
1. AACE International Recommended Practice No. 59R-10
DEVELOPMENT OF FACTORED COST ESTIMATES –
AS APPLIED IN ENGINEERING, PROCUREMENT, AND
CONSTRUCTION FOR THE PROCESS INDUSTRIES
TCM Framework: 7.3 – Cost Estimating and Budgeting
Acknowledgments:
Rashmi Prasad (Author) Peter R Bredehoeft Jr., CEP
Kul B. Uppal, PE CEP Larry R. Dysert, CCC CEP
A. Larry Aaron, CCE CEP PSP James D. Whiteside II, PE
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
2. AACE International Recommended Practice No. 59R-10
DEVELOPMENT OF FACTORED COST ESTIMATES –
AS APPLIED IN ENGINEERING, PROCUREMENT, AND
CONSTRUCTION FOR THE PROCESS INDUSTRIES
TCM Framework: 7.3 – Cost Estimating and Budgeting
June 18, 2011
INTRODUCTION
As identified in the AACE International Recommended Practice No. 18R-97 Cost Estimate Classification
System – As Applied in Engineering, Procurement, and Construction for the Process Industries, the
estimating methodology tends to progress from stochastic or factored to deterministic methods with
increase in the level of project definition.
Factored estimating techniques are proven to be reliable methods in the preparation of conceptual
estimates (Class 5 or 4 based on block flow diagrams (BFDs) or process flow diagrams (PFDs)) during
the feasibility stage in the process industries, and generally involves simple or complex modeling (or
factoring) based on inferred or statistical relationships between costs and other, usually design related,
parameters. The process industry being equipment-centric and process equipment being the cost driver
serves as the key independent variable in applicable cost estimating relationships.
This recommended practice outlines the common methodologies, techniques and data used to prepare
factored capital cost estimates in the process industries using estimating techniques such as: capacity
factored estimates (CFE), equipment factored estimates (EFE), and parametric cost estimates. However,
it does not cover the development of cost data and cost estimating relationships used in the estimating
process.
All data presented in this document is only for illustrative purposes to demonstrate principles. Although
the data has been derived from industry sources, it is not intended to be used for commercial purposes.
The user of this document should use current data derived from other commercial data subscription
services or their own project data.
CAPACITY FACTORED ESTIMATES (CFE)
Capacity factored estimates are used to provide a relatively quick and sufficiently accurate means of
determining whether a proposed project should be continued or to decide between alternative designs or
plant sizes. This early screening method is often used to estimate the cost of battery-limit process
facilities, but can also be applied to individual equipment items. The cost of a new plant is derived from
the cost of a similar plant of a known capacity with a similar production route (such as both are batch
processes), but not necessarily the same end products. It relies on the nonlinear relationship between
capacity and cost as per equation 1:
CostB/CostA = (CapB/CapA)r
where CostA and CostB are the costs of the two similar plants, CapA and CapB are the capacities of the
two plants and r is the exponent, or proration factor.
(equation 1)
The value of the exponent typically lies between 0.5 and 0.85, depending on the type of plant and must
be analyzed carefully for its applicability to each estimating situation. It is also the slope of the logarithmic
curve that reflects the change in the cost plotted against the change in capacity. It can be determined by
plotting cost estimates for several different operating capacities where the slope of the best line through
the points is r, which can also be calculated from two points as per equation 2:
r = ln(CapB/CapA)/ln(CostB/CostA)
(equation 2)
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
3. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 2 of 20
Construction for the Process Industries
June 18, 2011
The curves are typically drawn from the data points of the known costs of completed plants. With an
exponent less than 1, scales of economy are achieved wherein as plant capacity increases by a
percentage (say, by 20 percent), the costs to build the larger plant increases by less than 20 percent.
With more than two points, r is calculated by a least-squares regression analysis. A plot of the ratios on
log-log scale produces a straight line for values of r from 0.2 to 1.1.
This methodology of using capacity factors is also sometimes referred to as the “scale of operations”
method or the “six-tenths factor” method because of the reliance on an exponent of 0.6 if no other
information is available. With an exponent of 0.6, doubling the capacity of a plant increases costs by
approximately 50 percent, and tripling the capacity of a plant increases costs by approximately 100
percent. In reality, as plant capacity increases, the exponent tends to increase as per figure 1. The
capacity factor exponent between plants A and B may have a value of 0.6, between plants B and C a
value of 0.65, and between C and D, the exponent may have risen to 0.72. As plant capacity increases to
the limits of existing technology, the exponent approaches a value of one where it becomes as
economical to build two plants of a smaller size, rather than one large plant.
Figure 1 – The capacity factored relationships shown here are logarithmic. Exponents differ
across capacity ranges.
Usually companies should have indigenous capacity factors for several chemical process plants that must
be updated with regular studies. However, the above factors should be used with caution regarding their
applicability to any particular situation.
If the capacity factor used in the estimating algorithm is relatively close to the actual value, and if the plant
being estimated is relatively close in size to the similar plant of known cost, then the potential error from a
CFE is certainly well within the level of accuracy that would be expected from a stochastic method. Table
1 shows the typical capacity factors for some process plants. However, differences in scope, location, and
time should be accounted for where each of these adjustments also adds additional uncertainty and
potential error to the estimate. If the new plant is triple the size of an existing plant and the actual capacity
factor is 0.80 instead of the assumed 0.70, one will have underestimated the cost of the new plant by only
10 percent. Similarly, for the same three-fold scale-up in plant size, if the capacity factor should be 0.60
instead of the assumed 0.70, one will have overestimated the plant cost by only 12 percent. The capacity-
increase multiplier is CapB/CapA and in the base, r is 0.7. The error occurs as r varies from 0.7. Further,
table 2 shows percent error when 0.7 is the factor used for the estimate instead of the actual factor.
The CFE method should be used prudently. Making sure the new and existing known plants are near-
duplicates, include the risk in case of dissimilar process and size. Apply location and escalation
adjustments to normalize costs and use the capacity factor algorithm to adjust for plant size. In addition,
apply appropriate cost indices to accommodate the inflationary impact of time and adjustments for
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
4. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 3 of 20
Construction for the Process Industries
June 18, 2011
location. Finally, add any additional costs that are required for the new plant, but were not included in the
known plant.
COST INDICES
A cost index relates the costs of specific items at various dates to a specific time in the past and is useful
to adjust costs for inflation over time. Chemical Engineering (CE) publishes several useful cost indices
each month such as the CE Plant Cost Index and the Marshall & Swift Equipment Cost Index. The CE
Cost Index provides values for several plant-related costs including various types of equipment,
buildings, construction labor and engineering fees. These values relate costs of complete plants over
time, using the 1957–1959 timeframe as the base period (value = 100). The Marshall & Swift indices
provide equipment cost index values arranged in accordance to the process industry in which the unit is
used, using 1926 as the base period.
To use either of these indices to adjust for cost escalation, multiply the un-escalated cost by the ratio of
the index values for the years in question. For example, to determine the cost of a new chlorine plant in
February 2001 using capacity factored estimates where the cost of a similar chlorine plant built in 1994
was $25M, first the cost of the 1994 must be normalized for 2001. The CE index value for 1994 is 368.1.
The February 2001 value is 395.1. The escalated cost of the chlorine plant is therefore: $25M x
(395.1/368.1) = $25M x 1.073 = $26.8M.
Product Factor
Acrolynitrile 0.60
Butadiene 0.68
Chlorine 0.45
Ethanol 0.73
Ethylene Oxide 0.78
Hydrochloric Acid 0.68
Hydrogen Peroxide 0.75
Methanol 0.60
Nitric Acid 0.60
Phenol 0.75
Polymerization 0.58
Polypropylene 0.70
Polyvinyl Chloride 0.60
Sulfuric Acid 0.65
Styrene 0.60
Thermal Cracking 0.70
Urea 0.70
Vinyl Acetate 0.65
Vinyl Chloride 0.80
Table 1 – Capacity Factors for Process Plants[8]
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
5. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 4 of 20
Construction for the Process Industries
June 18, 2011
Actual Capacity-Increase Multiplier (CapB/CapA)
Exponent 1.5 2 2.5 3 3.5 4 4.5 5
0.20 23% 41% 58% 73% 88% 100% 113% 124%
0.25 20% 36% 51% 64% 75% 87% 97% 106%
0.30 18% 32% 44% 55% 64% 74% 83% 91%
0.35 16% 28% 38% 47% 55% 63% 70% 76%
0.40 13% 23% 32% 39% 46% 52% 57% 63%
0.45 11% 18% 26% 32% 36% 41% 46% 50%
0.50 9% 15% 20% 25% 28% 32% 35% 38%
0.55 6% 11% 15% 18% 21% 23% 25% 28%
0.60 4% 7% 10% 12% 13% 15% 16% 18%
0.65 2% 3% 5% 6% 6% 7% 8% 8%
0.70 0% 0% 0% 0% 0% 0% 0% 0%
0.75 -2% -4% -5% -5% -6% -7% -7% -8%
0.80 -4% -7% -9% -10% -12% -13% -14% -15%
0.85 -6% -10% -13% -15% -17% -19% -20% -21%
0.90 -8% -13% -17% -20% -22% -24% -26% -28%
0.95 -10% -16% -21% -24% -27% -29% -31% -33%
1.00 -11% -19% -24% -28% -31% -34% -36% -38%
1.05 -13% -22% -28% -32% -36% -39% -41% -43%
1.10 -15% -24% -31% -36% -40% -43% -45% -47%
1.15 -16% -27% -34% -39% -43% -46% -49% -52%
1.20 -18% -30% -37% -42% -47% -50% -53% -55%
Table 2 – % Error when factor r = 0.7 is used for estimate instead of actual exponent
Discrepancies are found in previously published factors due to variations in plant definition, scope, size
and other factors such as:
• Some of the data in the original sources covered a smaller range than what is now standard.
• Changes in processes and technology.
• Changes in regulations for environmental control and safety that was not required in earlier plants.
Exponents tend to be higher if the process involves equipment designed for high pressure or is
constructed of expensive alloys. As r approaches 1, cost becomes a linear function of capacity — that is,
doubling the capacity doubles the cost. The value of r may also approach 1 if product lines will be
duplicated rather than enlarged. Whereas a small plant may require only one reactor, a much larger plant
may need two or more operating in parallel.
Large capacity extrapolations must be done carefully because the maximum size of single-train process
plants may be restricted by the equipment's design and fabrication limitations. For example, single-train
methanol synthesis plants are now constrained mainly by the size of centrifugal compressors. Costs must
also be scaled down carefully from very large to very small plants because, in many cases the equipment
cost does not scale down but rather remains about the same regardless of plant capacity.
Despite these shortcomings, the r factor method represents a fast, easy and reliable way of arriving at
cost estimates at the predesigned stage. It is helpful for looking at the effect of plant size on profitability
when doing discounted cash-flow rate-of-return and payback-period calculations, and it is very useful for
making an economic sensitivity analysis involving a large number of variables.
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
6. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 5 of 20
Construction for the Process Industries
June 18, 2011
EQUIPMENT FACTORED ESTIMATES (EFE)
Equipment factored estimates are used when the engineering is approximately 1 to 15 percent complete
to determine whether there is sufficient reason to pursue the project. If so, this estimate is used to justify
the funding required to complete additional engineering and design for a Class 3 or budget estimate. It
can be quite precise if the equipment factors are appropriate, if the correct adjustments have been
applied, and if the list of process equipment is complete and accurate. This estimating procedure relies on
the existence of a ratio between the cost of an equipment item and costs for the associated non-
equipment items (such as foundations, piping, and electrical components) needed when building a plant.
Its advantage over CFEs is its basis upon specific process design.
The first step is to estimate the cost for each piece of process equipment. The equipment list should be
examined carefully for completeness and compared against the PFDs and piping & instrumentation
diagrams (P&IDs). When the equipment list is in a preliminary stage with only the major equipment
identified, assume a cost percentage for auxiliary equipment that has not yet been defined. The
equipment sizing should be verified since equipment is often sized at 100 percent of normal operating
duty, but by the time the purchase orders are issued, some percentage of over-sizing has been added to
the design specifications. The percentage of over-sizing varies with the type of equipment as well as with
the organization’s procedures and guidelines. It is prudent to check with the process engineers and
determine if an allowance for over-sizing the equipment, as listed on the preliminary equipment list,
should be added before pricing the equipment. The purchase cost of the equipment is often obtained from
purchase orders, published equipment-cost data, and vendor quotations, and should include the
associated nozzles and appurtences, manways, internals, baffles, packing, trays, and process
instrumentation. Since the material cost of equipment can represent 20 to 40 percent of the total project
costs for process plants, it is extremely important to estimate the equipment costs as accurately as
possible. If historical purchase information is used, the costs should be escalated appropriately and
adjustments made for location and market conditions.
Once the equipment cost is established, the appropriate equipment factors should be generated and
applied with necessary adjustments for equipment size, metallurgy and operating conditions specific to
project or process conditions. For example, if the plot layout of the project requires much closer
equipment placement than is typical, one may want to make adjustments for the shorter runs of piping
and electrical than would be accommodated by the equipment factors. If a project is situated in an active
seismic zone, one may need to adjust the factors for foundations and support steel.
After developing equipment factored costs, account should be made for project costs that are not covered
by the equipment factors such as by generating indirect field costs (IFCs) and home-office costs (HOCs),
engineering costs and fees.
[23]
J.J. Lang proposed a simple set of multiplicative factors to estimate the total installed cost of a plant
from the total cost of its major equipment items (TME) based on whether the given facility is a ”solids”
plant handling mainly solid process streams, or a “solids-fluids” plant, or a ”fluids” plant, where the factors
are 3.89, 5.04, and 6.21 respectively. Since, this approach has only one element, the error of the product
is greater than that of either the TME figure or that of the multiplicative factor and the latter itself is an
average based on a large number of industries and products. Accordingly, the accuracy of this method is
not attractive. It is least reliable for outside battery limits (OSBL) and offsite costs which are highly
variable.
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
7. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 6 of 20
Construction for the Process Industries
June 18, 2011
PROCESS Direct Costs ALL SOLID Process FLUID & SOLID Process (*) ALL FLUID Process
Mat’l Labor Total TC% Mat’l Labor Total TC% Mat’l Labor Total TC%
Purchased Equipment 1.000 N/A 1.00 26% 1.000 N/A 1.00 24% 1.000 N/A 1.00 20%
Equipment Setting 0.014 0.024 0.04 1% 0.014 0.024 0.04 1% 0.014 0.024 0.04 1%
Site Development 0.016 0.029 0.05 1% 0.016 0.029 0.05 1% 0.016 0.029 0.05 1%
Concrete 0.038 0.054 0.09 2% 0.031 0.059 0.09 2% 0.028 0.052 0.08 2%
Structural Steel 0.106 0.050 0.16 4% 0.103 0.040 0.14 3% 0.100 0.030 0.13 3%
Buildings 0.016 0.006 0.02 1% 0.016 0.006 0.02 1% 0.016 0.006 0.02 0%
Piping 0.200 0.160 0.36 9% 0.307 0.242 0.55 13% 0.520 0.450 0.97 19%
Instrumentation & Controls 0.100 0.200 0.30 8% 0.100 0.215 0.32 7% 0.140 0.280 0.42 8%
Electrical 0.109 0.086 0.20 5% 0.109 0.086 0.20 5% 0.088 0.072 0.16 3%
Insulation 0.020 0.004 0.02 1% 0.030 0.004 0.03 1% 0.060 0.012 0.07 1%
Painting 0.009 0.060 0.07 2% 0.009 0.060 0.07 2% 0.008 0.050 0.06 1%
Direct Costs = 1.63 0.67 2.30 59% 1.74 0.77 2.50 59% 1.99 1.01 3.00 59%
PROCESS Indirect Costs
Labor Indirects & Field Costs 0.160 0.392 0.55 14% 0.176 0.424 0.60 14% 0.220 0.500 0.72 14%
Contractor Engineering & Fee 0.015 0.703 0.72 18% 0.016 0.759 0.78 18% 0.020 0.890 0.91 18%
Owner Engineering & Oversight 0.080 0.242 0.32 8% 0.082 0.267 0.35 8% 0.085 0.330 0.42 8%
Total PROCESS Direct and Indirect = 1.88 2.01 3.89 100% 2.01 2.22 4.22 100% 2.32 2.73 5.04 100%
Excludes OSBL (non-process infrastructure), excludes land acquisition, excludes contingency, and assumes at-grade installations
(*) = Most reliable data
Assumed material equipment cost (MEC) factor for bulks and direct field labor (DFL) = 1.5
Labor is based on 1.0 labor productivity factor (LPF) @ $20.00 W2 rate + 91% for field indirects = $38.14 all in hourly composite labor rate
Table 3 – “Original” Lang factors (multipliers) of delivered equipment cost for capitalized costs
and % of total installed costs to construct large scale capacity US Gulf Coast process plants.
Happel[28] estimated purchase cost for all pieces of equipment (material), labor needed for installation
using factors for each class of equipment, extra material and labor for piping, insulation etc. from ratios
relative to sum of material and added installed cost of special equipment, overhead, engineering fees,
and contingency. A number of items given in table 4 below are prorated from the sum of key accounts G.
Material listing in the second column refers to delivered cost to the plant site ready for erection. The labor
items in the adjoining column are the direct labor involved in erecting each of the items noted. When
material items A through F are made of expensive material such as stainless steel, the labor percentage
will be much lower than shown in table 4 which is based on carbon steel items in material column.
Item Material Labor
Vessels A 10% of A
Towers, field fabricated B 30 to 35% of B
Towers, prefabricated C 10 to 15% of C
Exchangers D 10% of D
Pumps, compressors and other machinery E 10% of E
Instruments F 10 to 15% of F
Key accounts (Sum of A to F) G
Table 4 – Happel’s Method: Table 1
Item Material Labor
Key accounts (Sum of A to F) G
Insulation H = 5 to 10% of G 150% of H
Piping I = 40 to 50% of G 100% of I
Foundations J = 3 to 5% of G 150% of J
Buildings K = 4% of G 70% of K
Structures L = 4% of G 20% of L
Fireproofing M = 0.5 to 1% of G 500 to 800% of M
Electrical N = 3 to 6% of G 150% of N
Painting and cleanup O = 0.5 to 1% of G 500 to 800% of O
Sum of Material and Labor P
Table 5 – Happel’s Method: Table 2
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
8. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 7 of 20
Construction for the Process Industries
June 18, 2011
Sum of material and labor P
Installed cost of special equipment Q
Subtotal R = P+Q
Overheads S = 30% of R
Total erected cost T = R+S
Engineering fee U = 10% of T
Contingency fee V = 10% of T
Total investment W = T+U+V
Table 6 – Happel’s Method: Table 3
It presents difficulties in piping estimation as it is time-consuming to detail the piping sufficiently to
estimate it directly. If a percentage of 40 to 50% on key equipment for piping material is employed as
suggested above, errors may result in the estimates of plants having a large proportion of investment in
machinery, compressors or other relatively expensive equipment. The use of “exotic” pipe material such
as Teflon or stainless will also naturally completely upset calculations made on the basis of a simple
percentage. A good check can be made on piping material by noting that valves will constitute 40% of
total. Another item that must be considered carefully is the allowance for profit and fees to the
engineering contractor. Prices are fixed by supply and demand rather than arbitrary percentages like
those noted above, so that equipment companies with a considerable backlog of orders may be able to
enjoy greater profits. Another important factor to bear in mind when estimating construction costs from
published data or company records is that these costs are not constant like the physical properties of
chemical compounds. It is necessary to correct them by the use of some type of construction index,
especially when all information has not been obtained at the same time. In addition tables 4, 5, and 6
above do not cover OSBL items so these should be included separately in the estimate.
[24]
Hand advanced the above approaches by applying individual factors to major equipment categories. At
a 50% error range for the quantity and for the cost of each category, the error range for each element
would be 70.7%. But when the elements are added up, the error range of the sum (representing total
installed cost) is only 39.8%.
Hackney[25,26] developed an equipment ratio method with factors for labor and materials applied to not
only major equipment but also auxiliary equipment, to installation, and to various crafts, such as piping,
electrical and building. The auxiliary equipment cost is usually estimated as a percent of the major
equipment; the costs of installation and craft activities are taken as percentages of the major and auxiliary
equipment summed. A checklist was included for numerically estimating the certainty with which the
individual aspects of the project are known. Examples include the amounts, physical forms and allowable
impurities in the raw materials and products and the extent to which the process design has been
reviewed. The sum of the individual ratings is an indication of how accurate the estimate is. In spite of its
more detailed attention to uncertainty and accuracy, it does not lend itself to direct transfer to a more
detailed budget estimate. It is preferable to employ methods that can successively ”advance” to the more
detailed estimates.
[27]
Guthrie developed a module method that applied the Hackney approach to individual equipment
accounts. It used individual material factors for various crafts but one overall labor factor. The total plant
cost is the sum of the individual equipment modules, costs of linking the modules and indirect costs. The
latter, including design engineering, project management and contractor's profit, can account for about 10
to 30% of the total plant cost, depending on site topography, the economic climate of the area, the time of
year (i.e., the weather) and the nature of the bidding process itself. The modules can also serve to
monitor costs during construction and to control the scheduling of labor since the factors are replaced
with material and labor prices and the latter are translated into labor hours. Because of the extensive
summing involved, the accuracy of this method is high. Assume for instance, that the technique is being
used for a definitive estimate and that each quantity factor and cost factor for the pump module has an
accuracy of 5%. Summing the individual pump-installation elements brings the total accuracy for the
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
9. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 8 of 20
Construction for the Process Industries
June 18, 2011
module into the range of 3%, and when all the modules in the cost estimate for the plant are summed, the
accuracy of the plant estimate will improve to 2% or less.
The completion of any construction project yields cost data that can be valuable for future cost estimates
provided that these data are not time-indexed over an unreasonably large number of years. Cost data on
major pieces of equipment are readily available from computerized services whose databases are derived
from equipment vendor and vessel fabricator information. It is often possible to get better accuracy on the
factors for equipment installation by basing the installation outlays on the equipment size or design
available from the flow sheets for the plant. It often reveals circumstances affecting the installation cost
that are masked by the cost figures alone. The article “Sharpen Your Cost Estimating Skills” by Larry R.
[6]
Dysert , is a good source of process equipment factors. This document shows equipment factors for
process equipment range from 2.4 for columns to 3.4 for pumps and motors, based upon the raw
equipment costs.
Equipment costs must be estimated to gauge a project's economic viability, to evaluate alternative
investment opportunities, to choose from among several process designs the one likely to be the most
profitable, to plan capital appropriations, to budget and control expenditures or a competitive bid for
building a new plant or revamping an existing one. Shop fabricated costs including freight derived from
cost curves is suitable for making study estimates of total plant costs and is more than adequate for
making order-of magnitude ones. Since costs are changing and costs obtained from one source are likely
not to agree with those acquired from another, costs derived from the related graphs should not be
considered incontestable but rather should be adjusted in light of cost data from other sources according
to one's judgment and experience.
A good source of process equipment costs is DOE/NETL-2002/1169, “Process Equipment Cost
[10]
Estimation” report:
Cooling tower purchased equipment cost range from $4,000 for a 150 gal/min unit to $100,000 for a
6,000 gal/min. The cooling tower would consist of a factory assembled cooling tower including fans,
drivers and basins.
The design basis would be:
• Temperature Range: 15 °F
• Approach Gradient: 10 °F
• Wet Bulb Temperature: 75 °F
Air cooler purchased equipment cost range from $11,000 for a 100 sq/ft to $120,000 for a 10,000 sq/ft of
bare tube area. The air cooler would consist of variety of plenum chambers, louver arrangements, fin
types (or bare tubes), sizes, materials, free-standing or rack mounted, multiple bays and multiple services
within a single bay.
The design basis would be:
• Tube Material: A214
• Tube Length: 6 – 60 Feet
• Number of Bays: 1 – 3
• Power/ Fan: 2 – 25 HP
• Bay Width: 4 – 12 Feet
• Design Pressure: 150 psig
• Inlet Temperature: 300 °F
• Tube Diameter: 1 Inch
• Plenum Type: Transition shaped
• Louver Type: Face louvers only
• Fin Type: L-footed tension wound aluminum
Furnace/process heater purchased equipment cost range from $100,000 for 2 Million BTU/hour to
$5,000,000 for 500 Million BTU/hour of heat duty. The furnace heater would consist of gas or oil-fired
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
10. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 9 of 20
Construction for the Process Industries
June 18, 2011
vertical cylindrical type for low heat duty range moderate temperature with long contact time. Walls of the
furnace are refractory lined.
The design basis would be:
• Tube Material: A214
• Design Pressure: 500 psig
• Design Temperature: 750 °F
Rotary pump purchased equipment cost range from $2,000 for 10 gal/min to $10,000 for 800 gal/min of
capacity. The rotary pump would consist of rotary (sliding vanes) pump including motor driver.
The design basis would be:
• Material: Cast Iron
• Temperature: 68 °F
• Power: 25 – 20 HP
• Speed: 1800 RPM
• Liquid Specific Gravity: 1
• Efficiency: 82%
Single stage centrifugal pump purchased equipment cost range from $3,000 for 100 gal/min to $600,000
for 10,000 gal/min of capacity. The single stage centrifugal pumps would consist for process or general
service when flow/head conditions exceed general service, split casing not a cartridge or barrel and
includes standard motor driver.
The design basis would be:
• Material: Carbon Steel
• Design Temperature: 120 °F
• Design Pressure: 150 psig
• Liquid Specific Gravity: 1
• Efficiency: <50 GPM = 60%, 50 – 199 GPM = 65%, 100 – 500 GPM = 75%, > 500 GPM = 82%
• Driver Type: Standard motor
• Seal Type: Single mechanical seal
Reciprocating pump (duplex) purchased equipment cost range from $4,000 for 2 HP to $30,000 for 100
HP driver power. Reciprocating pump (triplex) purchased equipment cost range from $8,000 for 2 HP to
$80,000 for 100 HP driver power. The reciprocating pump would consist of duplex with steam driver
having Triplex (plunger) with pump motor driver.
The design basis would be:
• Material: Carbon Steel
• Design Temperature: 68 °F
• Liquid Specific Gravity: 1
• Efficiency: 82%
The direct field cost (DFC) factor is an uplift applied to the free on board (FOB) cost of the equipment and
ranges between 2.4 - 4.3 (with instrument) and 2 - 3.5(without instrument) for different equipment.
Guthrie introduced a module costing method as a type of EFE where the main relation is as per equation
3:
CBM = CPFBM
(equation 3)
For other items the related relations are shown below:
Labor CL = αL(CP + CM) = (1 + αM)αLCP
Direct
Freight CFIT = αFIT(CP+CM) = (1 + αM)αFITCP
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
11. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 10 of 20
Construction for the Process Industries
June 18, 2011
Overhead CO = αOCL = (1 + αM)αLαOCP
Indirect
Engineering CE = αE(CP + CM) = (1 + αM)αECP
Direct Field Labor Cost (DFL) = 0.25(DFC)
Indirect Field Cost (IFC) = 1.15(DFL)
Total Field Cost (TFC) = DFC + IFC
Home-Office Cost (HOC) = 0.3(DFC)
Other Project Cost (OTC) = 0.03(DFC) +0.15(TFC + HOC)
Total Project Cost (TPC) = OTC + TFC + HOC
where,
CBM = bare module cost of equipment (direct plus indirect costs)
CP = equipment cost in base case (carbon steel material at atmospheric pressure)
FBM = module factor (a factor that includes all direct and indirect costs)
CM = required material cost
CFIT = freight and insurance factor
αM = material factor
αL = labor factor
αO = overhead factor
αE = engineering factor
Each component of fixed capital investment can be considered as a factor of equipment cost. The
required material cost and the module factor are given in equations 4 and 5:
CM = αMCP
(equation 4)
FBM = (1+αM)(αL + αFIT + αLαO + αE)
(equation 5)
The bare module cost includes the direct and indirect cost only and doesn't include contingency and
auxiliary services costs. For example, if the cost of a heat exchanger in a base case (with carbon steel
material and operating at ambient pressure) equals to $10,000 then for (αM = 0.7, αL = 0.37, αFIT = 0.08,
α0 = 0.7, αE = 0.15) the bare module cost equals to $14,603. The equipment cost in a non-base case is
shown in equations 6 and 7:
FBM0 = B1 + B2FPFM
(equation 6)
CBM0 = CPFBM0
(equation 7)
where
FBM0 = module factor for non-base case;
FP = correction factor for pressure;
FM = correction factor for material.
B1 and B2 are calculated on the basis of fixed investment components, which obtained for different
equipments in specified ranges. The equipment cost (CP) is obtained by parametric models with a cost
relation shown in equation 8:
log10(CP) = K1 + K2log10(A) + K3log10(A)2
where A is a key parameter of equipment.
(equation 8)
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
12. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 11 of 20
Construction for the Process Industries
June 18, 2011
The pressure correction factor (FP) is described in equation 9:
log10(FP) = C1 + C2 log10(P) + C3log10(P)2
The coefficients K1, K2, K3, C1, C2, C3 are given for different equipment.
(equation 9)
By totaling the above module cost for equipments, the total module cost can be obtained. To calculate the
total plant cost one needs to add the auxiliary services and contingency costs, so 15 percent of the
module cost is considered for contingency, 3 percent for contractors, and 35 percent for auxiliary services.
Finally, the cost of a grass root plant can be calculated through equation 10:
0
CGR =1.18 CBM,i +0.35 CBM,i
where CGR = grass roots cost
(equation 10)
The auxiliary services and utilities do not depend on the pressure or material of the battery limit and
usually its cost is 35 percent of the module cost, at a base case of (CBM,i).
The capital cost, which includes all the capital, needed to ready a plant for startup is derived from:
• Direct project expenses include equipment FOB cost (CP), material (CM) required for installation,
and labor (CL) to install that equipment and material.
• Indirect project expenses include freight, insurance, and taxes (CFIT), construction overhead (CO)
and contractor engineering expenses (CE).
• Contingency and fees includes contractor fees (CFEE) and overall contingency (CCONT).
• Auxiliary facilities includes site development (CSITE), auxiliary buildings (CAUX) and off sites and
utilities (COFF).
TOTAL CAPITAL INVESTMENT COST BREAKDOWN
Total bare-module cost equipment CFE
Total bare-module cost machinery CPM
Total bare-module cost spares CSPARE
Total bare-module cost storage tanks CSTORAGE
Total bare-module cost initial catalyst CCATAL __________
Sums to total bare module investment CTBM
Cost of site preparation CSITE
Cost of service facilities (auxiliary buildings) CAUX
Cost of utility plant and related facilities COFF __________
Sums to cost of direct permanent investment CDPI
Cost of contingencies and contractors fees CCONT __________
Sums to total depreciable capital CTDC
Cost of land CLAND
Cost of royalties CROYALTY
Cost of plant startup CSTART__________
Sums to total permanent investment CTPI
Working capital CWC__________
Sums to total capital investment CTCI
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
13. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 12 of 20
Construction for the Process Industries
June 18, 2011
CSITE = (0.10 - 0.20) CTBM FOR GRASS ROOTS, (0.04 - 0.06) CTBM FOR INTEGRATED COMPLEX
CAUX = (0.1)CTBM FOR HOUSED OR INSIDE
Indirect on labor is based on U.S. Gulf Coast (USGC) as the suggested choice which is 115% to 180% of
direct labor cost. All other locations are compared with the USGC to establish their indirect percentages.
A typical make-up for all indirect on labor is shown below:
Proposed Ranges
Field Supervision & Field Office Expenses 25.0% to 41.0%
Temporary Facilities & Structures 9.0% to 18.0%
(Includes Temporary Support Systems & Utilities)
Construction Equipment & Tools 20.0% to 35.0%
Construction Consumables & Small Tools 9.0% to 15.0%
Statutory Burdens & Benefits 40.0% to 50.0%
Misc. Overhead & Indirects 2.5% to 6.0%
Profit/Fees for Construction Management 1.5% to 2.5%
Mobilization/Demobilization 4.0% to 6.5%
Scaffolding 4.0% to 6.0%
Total 115% to 180%
For international locations the field indirect and overheads (FIOH) percentage is identified through local
contacts or personal visits or through contacts with joint venture partners or from published information
from different sources. FIOH refers to a contractor’s construction costs necessary to support the direct
work and is a function of the project’s planned duration of need, as extended by a definable estimated
rate per hour, together with an estimated cost associated with site mobilization/transport and final
demobilization, relative size of project, type of project (grassroots or retrofit), local labor and construction
practices, site specific location and conditions (such as extremely remote site requiring daily transport of
workers to/from jobsite or special allowances for seasonal weather conditions). To compare the indirect
costs from different contractors, the multipliers should be on a similar basis and include field supervision
and indirect support staff, travel/relocation/subsistence, field per diems and relocation, temporary facilities
and structures, temporary support systems and utilities, construction equipment and tools, safety and first
aid, field office furnishings and supplies, communications, construction consumables, insurance/taxes,
statutory payroll burdens and benefits, miscellaneous overhead and indirects (home office overheads,
home office equipment, computers, purchasing services), and profit/fees. Statutory burdens should
include social security, medical insurance, unemployment benefits, worker’s compensation insurance,
general liability insurance, health and welfare, pension, education fund, industry fund, vacation, etc.
Temporary construction and consumables (TC&C) are the material, labor, and subcontract costs
associated with establishing and operating a temporary infrastructure to support construction work.
Examples of TC&Cs include: temporary facilities (such as trailers and temporary buildings, field offices,
furniture for temporary buildings, field shops including shop machinery, field warehouses, and worker
camps, temporary roads, and fencing), scaffolding materials and labor, site clean-up, temporary utility
costs, fuel, gas, welding rods, protective clothing and personal protective equipment, etc.
Field supervision/field office costs are the material, labor, and subcontract costs associated with
supervising the construction work. Examples of these costs include: wages, salaries, benefits, relocation
costs, travel expenses for assigned and local field staff (such as construction managers, superintendents,
area supervisors, craft supervisors, warehouse supervisors, field project controls, trainers, field
buyers/expediters, safety officers, etc.), and ongoing expenses for a field office such as personal
computers, telephone, fax machines, copiers, etc.
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
14. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 13 of 20
Construction for the Process Industries
June 18, 2011
Construction equipment/tools are material, labor, and subcontract costs necessary for providing tools and
machines to support the construction work. Examples include: cranes, trucks, welding machines, jacking
equipment, small tools, rigging devices, etc.
The contractor engineering is based on total equipment items:
• Small projects: 650 to 950 work-hours per equipment item
• Grassroots projects: 1,100 to 1,550 work-hours per equipment item
• Retrofits: 30% to 45% of all direct costs (included in direct cost is equipment, material, and labor)
The individual item count includes all numbered equipment, any numbered spares, and the individually
numbered pieces of equipment on a packaged unit.
A secondary check for grassroots projects for contractor engineering will be a cost range of 12% to 25%
of all direct costs or 8% to 14% of total project costs. The owner engineering cost is estimated as 10% to
12% of all direct costs or 25% to 45% of contractor engineering.
The contingency amount will vary based on the type of unit under consideration:
• Well established process design (previously built): 5% to 10%
• Well established process designs, debottleneck type: 20% to 35%
• Any OSBL unit: 25% to 40%
• Brand new process design (never built before): 15% to 30%
• DCS implementation, any unit: 10% to 15%.
The escalation for equipment, materials, and construction activities is based on the most current
construction cost index. The freight cost for a typical project is 2% to 6% of equipment cost. For overseas
locations, the freight cost varies from 8% to 18% of equipment cost, depending upon the country under
consideration. The spare parts (capital spares only) for US installations are 4% to 8% of equipment costs.
The percentages are higher for overseas locations (8% to 12% of equipment cost) but should be looked
at on an individual basis.
PARAMETRIC COST ESTIMATES
Parametric cost estimates are used to estimate equipment cost and finally the total plant cost at an
acceptable error percentage when there is little technical data about equipment and other capital cost
items or engineering deliverables for submission to equipment manufacturers. It involves development of
parametric model based on data on equipment costs from specified time duration. Then, using statistical
methods, the models coefficients are obtained and their accuracy and estimation capabilities are studied.
The best reference for reliable cost data is the completed projects of an organization. Applying this data,
using regression methods and statistical tests, a final model is proposed.
A parametric model is a mathematical representation of cost relationships that provide a logical and
predictable correlation between the physical or functional characteristics of a plant and its resultant cost.
Capacity and equipment-factored estimates are simple parametric models. Sophisticated parametric
models involve several independent variables or cost drivers.
The first step in developing a parametric model is to establish its scope. This includes defining the end
use, physical characteristics, critical components and cost drivers of the model taking into consideration
the type of process to be covered, the type of costs to be estimated (such as TIC and TFC) and the
accuracy range.
The model should be based on actual costs from completed projects and reflect the company’s
engineering practices and technology. It should use key design parameters that can be defined with
reasonable accuracy early in the project scope development and provide the capability for the estimator
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
15. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 14 of 20
Construction for the Process Industries
June 18, 2011
to easily adjust the derived costs for specific factors affecting a particular project. Finally, the model
should generate current year costs or have the ability to escalate to current year costs.
Data collection and development for a parametric estimating model requires significant effort. Both cost
and scope information must be identified and collected. It is best to collect cost data at a fairly low level of
detail. The cost data can always be summarized later if an aggregate level of cost information provides a
better model. It is important to include the year for the cost data in order to normalize costs later. The type
of data to be collected is usually decided upon in cooperation with the engineering and project personnel.
It is best to create a formal data collection form that can be consistently used and revised if necessary.
After the data have been collected, it must be normalized. By doing this, we make adjustments to account
for escalation, location, site conditions, system specifications and cost scope. Data analysis, the next step
in the development of a parametric model, is achieved by a wide variety of techniques such as performing
regression of cost versus selected design parameters to determine the key drivers for the model. The
regression involves iterative experiments to find the best-fit algorithms or mathematical relationships that
describe how data behave. The result is a parametric model. Most spreadsheet applications provide
regression analysis and simulation functions that are reasonably simple to use. As an algorithm is
discovered that appears to provide good results, it must be tested to ensure that it properly explains the
data. Using advanced statistical tools can quicken the process but can be more difficult to use.
Sometimes erratic or outlying data points will need to be removed from the input data in order to avoid
distortions in the results. The algorithms will usually take one of the equations 11&12:
A linear relationship, such as,
Cost = a + bV1 + cV2 + ...
(equation 11)
or a nonlinear relationship, such as,
Cost = a + bV1x + cV2y + …
(equation 12)
where V1 and V2 are input variables; a, b, and c are constants derived from regression; and x and y are
exponents derived from regression.
The equation that is the best fit for the data will typically have the highest R-squared (R2) value, which
provides a measure of how well the algorithm predicts the calculated costs. However, a high value by
itself does not imply that the relationships between the data input and the resulting cost are statistically
significant. One still needs to examine the algorithm to ensure that it makes sense.
A cursory examination of the model can help identify the obvious relationships that are expected. If the
relationships from the model appear to be reasonable, then additional tests (such as the t-test and f-test)
can be run to determine statistical significance and to verify that the model is providing results with an
acceptable range of error. A quick check can be performed by running the regression results directly
against the input data to see the percent error for each of the inputs. This allows the estimator to
determine problems and refine the algorithms. After the individual algorithms have been developed and
assembled into a complete parametric cost model, it is important to test the model as a whole against
new data (data not used in the development of the model) for verification.
During the data application stage, a user interface and a presentation form for the parametric cost model
is established. Computer spreadsheets provide an excellent means of accepting estimator input,
calculating costs based upon algorithms, and displaying output.
Perhaps the most important effort in developing a parametric (and any other) cost model is making sure
the application is thoroughly documented. Record the actual data used to create the model, the resulting
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
16. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 15 of 20
Construction for the Process Industries
June 18, 2011
regression equations, test results and a discussion on how the data was adjusted or normalized for use in
the data analysis stage. Any assumptions and allowances designed into the cost model should be
documented, as should any exclusion. The range of applicable input values and the limitations of the
model’s algorithms should also be noted. Write a user manual to show the steps involved in preparing an
estimate using the cost model and to describe the required inputs to the cost model.
Induced-draft cooling towers are typically used in process plants to provide a recycle cooling-water loop.
These units are generally prefabricated and installed on a subcontract or turnkey basis by the vendor.
Key design parameters that appear to affect the costs of cooling towers are the cooling range, the
temperature approach and the water flow rate. The cooling range is the temperature difference between
the water entering the cooling tower and the water leaving it. The approach is the difference in the cold
water leaving the tower and the wet-bulb temperature of the ambient air.
Cooling Temperature Flow Rate, gal/min Actual Cost, $ Predicted Cost, $ % Error
Range, °F Approach, °F
30 15 50,000 1,040,200 1,014,000 -2.5%
30 15 40,000 787,100 843,000 7.1%
40 15 50,000 1,129,550 1,173,000 3.8%
40 20 50,000 868,200 830,000 -4.4%
25 10 30,000 926,400 914,000 -1.3%
35 8 35,000 1,332,400 1,314,000 -1.4%
Table 7 – Actual Costs versus Predicted Costs with Parametric Equation
Table 7 provides the actual costs and design parameters of six recently completed units whose costs
have been normalized (adjusted for location and time) to a Northeast US, year-2000 timeframe[6]. These
data are the input to a series of regression analyses that are run to determine an accurate algorithm for
estimating costs. Using a computer spreadsheet, the cost estimation algorithm was developed as per
equation 13:
Predicted Cost = $86,600 + $84,500(Cooling Range, °F)0.65 – $68,600(Approach, °F) +
+ $76,700(Flow Rate, 1,000 gal/min)0.7
(equation 13)
The above equation demonstrates that the cooling range and flow rates affect cost in a nonlinear fashion,
while the approach affects cost in a linear manner. Increasing the approach will result in a less costly
cooling tower, since it increases the efficiency of the heat transfer-taking place. These are reasonable
assumptions. The regression analysis resulted in an R2 value of 0.96, which indicates that the equation is
a “good fit” for explaining the variability in the data. The percentage of error varies from –4.4 percent to
7.1 percent. The estimating algorithm developed from regression analysis, can be used to develop cost
versus design parameters that can be represented graphically.
This information can then be used to prepare estimates for future cooling towers. It is fairly easy to
develop a spreadsheet model that will accept the design parameters as input variables, and calculate the
costs based on the parametric estimating algorithm.
To derive the models, one needs to suppose that a linear relationship exists between the cost of the
equipment and its key parameters as per equation 14:
2
ln(CE) = A + Bln(KP) + Cln(KP)
Where CE is equipment cost and KP is a key parameter. The models for other equipment are given in
Table 8 calculated using the linear regression method along with the coefficients.
(equation 14)
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
17. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 16 of 20
Construction for the Process Industries
June 18, 2011
.
Figure 2 – Graph developed from regression data for tower cost that can be used for future
cooling towers.
Equipment Proposed Models Parameter Ranges %AAD Coefficients
Pressure Vessels (Carbon Steel) CE = exp[A1 + B1ln(W) + C1ln(W)^2] 180 < W < 621,000 21%
A1 = -1.731737
2 < P < 20 B1 = 0.5598
C1 = 0.024773
Pressure Vessels (Stainless Steel) CE = exp[A2 + B2ln(W)] 168 < W < 108,849 27.6% A2 = -2.788577
2<P<5 B2 = 0.94935
Atmospheric Storage Tanks CE = exp[A3 + B3ln(W)] 2,800 < W < 1,540,000 4.2% A3 = -4.619487
(Carbon Steel) B3 = 0.9892
Separation Tower (Carbon Steel) CE = exp[A4 + B4ln(W) + C4ln(W)^2] 5,360 < W < 178,000 12.8% A4 = 13.271536
3.5 < P < 30 B4 = -2.253712
C4 = 0.154118
Separation Tower (Stainless Steel) CE = exp[A5 + B5ln(W) + C5(L/D)] 6,400 < W < 39,000 37% A5 = -2.484312
1.4 < (L/D) < 21.3 B5 = 0.964302
3.5 < P < 37 C5 = 0.04109
Shell and Tube Heat Exchangers – CE = exp[A6 + B6ln(W)] 4,400 < W < 77,400 3.2% A6 = -2.910474
BEU Type (Carbon Steel) 7 < P < 85 B6 = 1.016550
Oil Injected Screw Compressor CE = exp[A7 + B7WP + C7WP^0.5] 7 < WP < 315 9.2% A7 = 2.193159320
7 < P < 85 B7 = -0.01059287
C7 = 0.450875824
Where: W(weight, kg), P(operating pressure, bar), L(length, m), D(diameter, m), CE(equipment cost, Millions Iranian Rials),
WP(power, kW). Note: The above costs are related to year 2004 in the Iranian market.
Table 8 – Obtained models for some equipment
The parametric models for the above equipment were prepared using a provided data bank including the
cost and some specifications of equipment. Because of limitations, both in the number of projects and in
the type of equipment, the defined models are in specified limited domains. To increase these domains,
additional cost data in broader ranges are needed.
To increase these domains, additional cost data in broader ranges are needed. The achieved results can
be used as initial data to develop more complete models.
In the above table, the obtained models are shown, as well as the applicable ranges and absolute
average deviation percentages, which are listed as %AAD. The %AAD can be defined as per equation
15:
1 ABS Y − Y
%AAD = 100x
n Y
where Y is the estimated value and Yi is the cost value from data bank and n is the number of data.
(equation 15)
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
18. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 17 of 20
Construction for the Process Industries
June 18, 2011
For example, the cost of a BEU type heat exchanger (carbon steel) with a weight of 10,000 kg can be
calculated as:
CE = exp(-2.910474 + 1.01655 ln(10000)) = 631.15 MRls = $71253.60
(For exchange rate in 2004 use: 8900 Rials = 1 $)
The confidence interval method also provides a means of quantifying uncertainty. For each coefficient (Bi)
is as per equation 16:
Bi = B ± tSE
where B is estimated coefficients, t is t-student from the distribution table and depends on degree of
freedom and statistical significance. SE is the standard error for coefficients.
(equation 16)
The confidence interval was determined at 95 percent statistical significance for coefficients of the six first
models and 90 percent statistical significance for the last model for a compressor.
Table 9 shows the related confidence intervals and standard errors for coefficients in the proposed
models. Since none of the intervals straddle zero, then none of the coefficients are zero, and therefore,
they are acceptable.
2 2
The goodness of fit is explained by R-square in regression. R = 1 is a perfect score. R = 0.99 is a very
good score that shows the goodness of fit.
2
Equipment Coefficients t Standard Confidence Interval R
Error
Pressure Vessels (Carbon Steel) B1 = 0.5598 1.98 0.135254 0.292005 < B1 < 0.827595 0.99
C1 = 0.024773 1.98 0.007028 0.0108576 < C1 < 0.0386884 0.99
Pressure Vessels (Stainless Steel) B2 = 0.94935 2.074 0.035066 0.876623 < B2 < 1.022077 0.98
Atmospheric Storage Tanks (Carbon Steel) B3 = 0.9892 2.074 0.007508 0.97362 < B3 < 1.00477 0.99
Separation Tower (Carbon Steel) B4 = -2.253712 2.179 0.696337 -3.77103 < B4 < -0.73639 0.99
C4 = 0.154118 2.179 0.032736 0.082786 < C4 < 0.22545 0.99
Separation Tower (Stainless Steel) B5 = 0.964302 2.776 0.011674 0.640231 < B5 < 1.288372 0.99
C5 = 0.04109 2.776 0.001323 0.0004363 < C5 < 0.0077816 0.99
Shell and Tube Heat Exchangers – BEU B6 = 1.016550 2.131 0.006779 1.002104 < B6 < 1.030996 0.99
Type (Carbon Steel)
Oil Injected Screw Compressor B7 = -0.01059287 1.697 0.000939 -0.00624 < B7 < -0.00899 0.99
C7 = 0.450875824 1.697 0.025139 0.0024 < C7 < 0.087 0.99
Table 9 – Confidence Intervals
Cost estimation accuracy by parametric models in the feasibility study stages ranges between 20 to 50
percent (upper limit) and -15 to -30 percent (lower limit). These models can be accepted with accuracy
ranges between ±3 percent to ±37 percent. The obtained models are related to a specific year. Because
of inflation, they must be re-evaluated for use in following years.
ACCURACY OF FACTORED ESTIMATE
There are different kinds of cost estimates prepared in the conceptual arena depending on their purpose
or the amount of time and information available with an accuracy of plus or minus X %, implying that the
true value lies between (100 + X)% and (100 - X)%. However, that range is biased, because the largest
possible positive deviation theoretically approaches infinity whereas the largest possible negative
deviation is only 100%. So, a value of (100 - X) is a more significant departure from X than is the value
(100 + X).
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
19. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 18 of 20
Construction for the Process Industries
June 18, 2011
[1]
In line with this logic, the listing of cost estimates classes sanctioned by AACE typically uses ranges
with the positive deviation being larger than the negative:
Primary
Secondary Characteristic
Characteristic
DEGREE OF
EXPECTED
ESTIMATE PROJECT END USAGE METHODOLOGY
Typical purpose of ACCURACY RANGE
CLASS DEFINITION Typical estimating method Typical variation in low and
Expressed as % of estimate [a]
high ranges
complete definition
Capacity factored,
Concept L: -20% to -50%
Class 5 0% to 2% parametric models,
screening H: +30% to +100%
judgment, or analogy
Study or Equipment factored or L: -15% to -30%
Class 4 1% to 15%
feasibility parametric models H: +20% to +50%
Budget Semi-detailed unit costs
L: -10% to -20%
Class 3 10% to 40% authorization or with assembly level line
H: +10% to +30%
control items
Control or Detailed unit cost with L: -5% to -15%
Class 2 30% to 70%
bid/tender forced detailed take-off H: +5% to +20%
Check estimate Detailed unit cost with L: -3% to -10%
Class 1 70% to 100%
or bid/tender detailed take-off H: +3% to +15%
Notes: [a] The state of process technology and availability of applicable reference cost data affect the range markedly.
The +/- value represents typical percentage variation of actual costs from the cost estimate after application of
contingency (typically at a 50% level of confidence) for given scope.
Table 1 – Cost Estimate Classification Matrix for Process Industries[1]
It is important to understand how uncertainties propagate in cost estimates involving the four arithmetic
manipulations (being the sum of multiplicative products or requiring subtraction and division during its
calculation) since the values of the quantities, unit costs and other numbers being thus manipulated
typically are uncertain.
Consider an estimate to be a summation of elements with each element being the product of two
variables or factors: a) Quantity Factor: the number of units - individual pieces as reactors, areas as
surfaces to be insulated, volumes as cubic meters of concrete to be poured or other units that enumerate
the entity being priced, and b) Cost Factor: the corresponding unit cost. When two or more independent
variables A and B are multiplied together, any inaccuracies in the individual variables are amplified in their
product:
2 2 2 2 1/2
(A ± a)(B ± b) = AB ± (A b + B a )
If a is a symmetric accuracy range for A, and b is a symmetric accuracy range for B
For instance, consider a cost estimate element consisting of a tank. Its required volume A is expected to
be 21,000 gal with an uncertainty of ± 20%, and its anticipated unit capital cost B is $2/gal with an
uncertainty of ± 30%. Thus, a equals (21,000)(0.20) or 4,200, and b is (2)(0.30) or $0.60. Then their
product P becomes: P = (21,000)(2.00) ± (21,0002 x 0.602 + 22 x 4,2002)1/2 = 42,000 ± 15,143, or ± 36.1%
between the percent ranges corresponding to the product of two independent variables, each having its
own accuracy range. The range of the product is at the intersection of the row and column appropriate for
the two variables. The ± 20% quantity factor would be accurate enough for budgeting purposes under the
aforementioned conventional listing, and the ± 30% cost factor would qualify for study or factored
estimates, but their product qualifies only for use as a conventional order-of-magnitude or conceptual
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
20. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 19 of 20
Construction for the Process Industries
June 18, 2011
estimate. If the quantity and cost factors each were instead ± 50% accurate, their product would be ±
70.7%, unacceptable even for order-of-magnitude purposes.
Division has the same effect as multiplication, increasing the range of inaccuracy whereby the product or
quotient is less accurate than the more uncertain of the two factors involved.
When two or more independent variables are added, any inaccuracies in the individual variables are
decreased in their sums. The expression for two numbers A and B having symmetric accuracy ranges a
and b is:
2 2 1/2
(A ± a) + (B ± b) = A + B ± (a + b )
Consider, for instance, summing the costs of 10-in. and 8-in. flanges, respectively costing $120 with an
accuracy of 10% and $80 with an accuracy of ± 10%. Then a = (120)(0.10) = $12, and b = (80)(0.20) =
$16, and their sum S becomes: S = (120 + 80) ± (122 + 162)1/2 = 200 ± 20 = 200 ± 10%
The expected error range of the total will be less than the error in either of the individual numbers or, at
most, equal to the lower of them.
This decrease in accuracies is not limited to the summation of two variables. The inaccuracies of the
seven cost-estimating elements such as list of process equipment that is needed for a distillation unit
become far less significant when the associated costs are summed. This demonstrates that the more
detail in which we define the scope of our project, the more accurate our estimate becomes.
In subtraction, the same formula is used as for addition. The expected absolute range is the same as
when adding, but the percentage range is much greater. Consider again the two flanges mentioned
1/2
above and take the difference D in their costs: D = (120 - 80) ± (122 + 162) = 40 ± 20, or ± 50%
These uncertainty-propagation rules have significant implications for the accuracies that we can expect
from any given estimating method.
CONCLUSION
Factored cost estimation is proposed as sample methods to organizations and engineering companies to
derive their own cost relations by referring to their past project cost archives. When deciding upon
potential investment opportunities, management must employ a cost screening process that requires
various estimates to support key decision points. At each of these points, the level of engineering and
technical information needed to prepare the estimate will change. Accordingly, the techniques used
prepare the estimates will vary depending upon the information available at the time of preparation, the
end use of the estimate, and its desired accuracy. The challenge for the engineer is to know what is
needed to prepare these estimates, and to ensure they are well documented, consistent, reliable,
accurate and supportive of the decision-making process.
REFERENCES
1. AACE International Recommended Practice No. 18R-97, Cost Estimate Classification System – As
Applied in Engineering, Procurement, and Construction for the Process Industries, AACE
International, Morgantown, WV, (latest revision)
2. Black, Dr. J. H., “Application of Parametric Estimating to Cost Engineering”, 1984 AACE
Transactions, AACE International, 1984
3. Mohammed Reza Shabani and Reza Behradi Yekta, “Chemical Processes Equipment Cost
Estimation Using Parametric Models”, AACE International, May 2006
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices
21. Development of Factored Cost Estimates – As Applied in Engineering, Procurement, and
December 28, 2011 20 of 20
Construction for the Process Industries
June 18, 2011
4. Chilton, C. H., “Six Tenths Factor Applies to Complete Plant Costs”, Chemical Engineering, April
1950
5. Dysert, L. R., “Developing a Parametric Model for Estimating Process Control Costs”, 1999 AACE
Transactions, AACE International, 1999
6. Dysert, L. R., “Sharpen Your Cost Estimating Skills”, Cost Engineering, Vol. 45, No.6, AACE
International , Morgantown, WV, 2003
7. Guthrie, K. M., “Data and Techniques for Preliminary Capital Cost Estimating”, Chemical Engineering,
March 1969
8. Guthrie, K.M., Capital and Operating Costs for 54 Chemical Processes, Chem. Eng., June 1970.
9. Mohammed Reza Shabani and Reza Behradi Yekta, “Suitable Method for Capital cost estimation in
Chemical Process Industries”, AACE International, May 2006
10. Loh, H.P., Jennifer Lyons, and Charles W. White III, Process Equipment Cost Estimation Final
Report, DOE/NETL-2002/1169, U.S. Department of Energy/National Energy Technology Laboratory,
January 2002
11. Hand, W. E., “Estimating Capital Costs from Process Flow Sheets”, Cost Engineer’s Notebook, AACE
International, January 1964
12. Lang, H. J., “Cost Relationships in Preliminary Cost Estimation,” Chemical Engineering, October 1947
13. Lang, H. J., “Simplified Approach to Preliminary Cost Estimates,” Chemical Engineering, June 1948
14. Miller, C. A., “New Cost Factors Give Quick Accurate Estimates,” Chemical Engineering, September
1965
15. Miller, C. A., “Capital Cost Estimating – A Science Rather than an Art,” Cost Engineer’s Notebook,
AACE International, 1978
16. NASA, Parametric Cost Estimating Handbook
17. Nishimura, M., “Composite-Factored Estimating”, 1995 AACE Transactions, AACE International,
1995
18. Remer, D. and L. Chai, “Estimate Costs of Scaled-Up Process Plants”, Chemical Engineering, April
1990
19. Gustav Enyedy, “How Accurate is Your Estimate”, Chemical Engineering
20. Rodl, Dr. R. H. and Dr. P. Prinzing and D. Aichert, “Cost Estimating for Chemical Plants”, 1985 AACE
Transactions, AACE International, 1985
21. Rose, A., “An Organized Approach to Parametric Estimating”, Transactions of the Seventh
International Cost Engineering Congress, 1982
22. Williams Jr., R., “Six-Tenths Factor Aids in Approximating Costs,” Chemical Engineering, December
1947
23. Lang, H. J., Engineering approach to preliminary cost estimates, Chemical Engineering, September
1947, pp. 130-133.
24. Hand, W. E., From Flow sheet to Cost Estimate, Petroleum Refiner, September 1958, pp. 331-334.
25. Hackney, J. W., ``Control and Management of Capital Projects,'' Wiley, New York, 1965.
26. Hackney, J.W., Estimating methods for process industry capital costs, Chemical Engineering, April 4,
1960, pp. 119-134.
27. Guthrie, K. M., ``Process Plant Estimating Evaluation and Control,'' Craftsman, Saline Beach, Calif,
1974.
nd
28. Happel, J. and D.G. Jordan, Chemical Process Economics, 2 Ed., Marcel Dekker, New York, NY,
1975
CONTRIBUTORS
Rashmi Prasad (Author)
Kul B. Uppal, PE CEP
A. Larry Aaron, CCE CEP PSP
Peter R Bredehoeft Jr., CEP
Larry R. Dysert, CCC CEP
James D. Whiteside II, PE
Copyright 2011 AACE® International, Inc. AACE® International Recommended Practices