SlideShare a Scribd company logo
1 of 50
Download to read offline
LONG RANGE
ULTRASONIC TESTING
( LRUT )
May 1
2020
As a product of transportation facility, pipeline sould be having a
good integrity. Pipeline failure means that pipeline can not
operate both at some segment/section or all of pipeline segment
can not deliver product/service as per their function. Or failure
of pipeline also means loss of pipeline integrity for some
segment pipeline section or all of segment pipeline.
PAULUS KONDA
PIPELINE INTEGRITY ASSESSMENT
1
CHAPTER I INTRODUCTION
1.1 PIPELINE INTEGRITY INTRODUCTION
As a product of transportation facility, pipeline sould be having a good integrity. Pipeline
failure means that pipeline can not operate both at some segment/section or all of pipeline
segment can not deliver product/service as per their function. Or failure of pipeline also
means loss of pipeline integrity for some segment pipeline section or all of segment
pipeline.
Pipeline incident refer to gas release from pipeline can be gave consequence like
dead/fatality, injury, pollution, or property damage included loss that cause by gas release
with huge nominal value (typically value more than $ 50.000).
Pipeline leak refer to release of product/service from pipeline that not by design.
Consequence of pipeline leak can not cause dead/fatality and or serius injury, but in some
cases was happen. Most of pipeline leak consequences are loss of product/service,
environtment pollution, property loss and company image (typically value more than $
50.000).
Both pipeline incident and pipeline leak are happing consequence with high level of fatality.
Area with these categories usually knows as High Consequence Area – HCA.
By definition, pipeline that lacated at location class 3 and 4 are catagorized at High
Consequence Area – HCA. These areas were devided on two zones, i.e High Impact Zone
(zone with high impact) and Moderate Impact Zone (zone with moderate impact). If these
area were located at Potential Impact Zone – PIC than these area catagorized as high impact
zone, but if these area were located out of Potential impact Zone – PIC than catagorized as
moderate impact zone. But for pipeline that located at location class 1 and 2, high
consequence area defined with different manner.
In general, Potential Impact Zone having Threshold Radius – TR that calculated base on
Potential Impact Radius – PIR. Potential Impact Radius can be entented for the special
condition.
1.2 PIPELINE INCIDENT AND LEAK
There are some cause as trigger of incident and leak of pipeline, i.e:
 Third party damage
 Corrosion:
o Internal corrosion
o External corrosion
o Stress corrosion cracking
 Construction
2
 Manufacturing
 Incorrect operation
 Equipment
 Weather
Figure 1 below showing typicall data for pipeline incident at High Consequence Area – HCA.
From these data, we can see that most contribution incident for pipeline incident cause by
third party damage (around 47% from total cause of incident). It’s mean that to minimize
pipeline incident, pipeline owner/operator should be focus to manage and maintaince
potential of third party damage, equipment/pipeline it self, construction, incorrect
operation, etc.
Figure 1 Pipeline Incident at High Consequence Area – HCA catagorized by its cause
1
Figure 2 below showing typicall data for pipeline leak at High Consequence Area – HCA.
From these data, we can see that equipment/pipeline it self giving most contribution of
pipeline leak, around 57% from total others cause of pipeline leak. It’s mean that to
minimize pipeline leak, pipeline owner/operator should be focus to manage and maintain of
their equipment/pipeline it self, external corrosion, thrid party damage, construction, etc.
Threat of pipeline integrity can be devided as below:
 Threat of pipeline integrity that base on time (time dependent), i.e:
o External Corrosion
o Internal Corrosion
o Stress corrosion cracking
o
1
Incident Data 2004 – 2007at Amerika, coming from https://primis.phmsa.dot.gov/gasimp/PerformanceMeasures.htm
3
Figure 2 Pipeline Leak at High Consequence Area – HCA catagorized by its cause
2
 Threat of pipeline integrity that not base on time (time independent), i.e:
o Incorrect operation
o Weather related and outside force), i.e:
 Thunderclap
 Flood and rain
 Land movement
 Threat of pipeline integrity that related with manufacturing process,
fabrication/welding process, and equipment, i.e:
o Defect that related with manufacturing process, i.e:
 Defect at pipe seam
 Defect at the pipe
o Fabrication and welding process, i.e:
 Weld defect at pipe girth
 Weld defect at fabrication
 Wrinkle bend or buckle
 Damage at coupling and pipe
o Equipment:
 Damage Gasket O-Ring
 Malfunction at control/relief valve
 Damage at pump seal / packing
1.3 PROJECT BACKGROUND
Pipeline is a pipe system which is designed to bring something like oil, natural gas, or other
products that are oil-based long-distance, usually placed above ground or often
underground offshore and onshore. As a system, the pipeline must have high integrity and
reliability for the system operated. Pipeline who lost their integrity and reliability means if
2
Leak Data 2004 – 2007 at Amerika, coming from dari https://primis.phmsa.dot.gov/gasimp/PerformanceMeasures.htm
4
not ability to operate and is below the minimum requirement allowed by the code /
standard or owner specification used.
If still ignored by the conditions below minimum requirements, the pipe will someday be a
failure at the time later or at the time that was not suspected. As a result of this failure
would have broad impact on economic value, safety and human health, and cause
disruption to the environment. The cause of failure in the pipeline caused by several
factors index, as follows:
 Third party damaged index
 Design index
 Incorrect operation index
 Corrosion index
The combination of the impact of failure or the consequences of failure (CoF) to the cause
of the failure or the probability of failure (PoF) is a risk. The higher of the consequences of
failure and the probability of failure in a pipeline means higher risks for the operation.
Risk = CoF x PoF
Various methods used to mitigate these variables to minimize the risks. To mitigate the
consequences of failure should the policies of the management authority of the owner of
the pipeline that will impact on all sectors in the company in a long time, these
considerations need to be a long time, and complicated.
Mitigate the probability of failure is not as complicated as compared to mitigate the
consequences of failure, but it also takes preparation. Mitigate the probabilities of failure,
as follows:
 Supervision and oversight in the initial design fabrication process.
 Documenting the design data after completed the fabrication process.
 Monitoring and maintaining operational conditions, perform maintenance
and repair of facilities in the Right Of Way (ROW) and the pipe itself.
5
 Monitoring the condition pipe with a potentially damaged by the activities
of third parties as well as create educational programs in the community
about hazard potential
 Create a plan for inspection at the appropriate time and appropriate
method of inspection in accordance with the mode of failure in the pipeline.
Related one of the efforts to mitigate probabilities of failure mentioned above is to make
an inspection plan with appropriate method, Chevron Pacific Indonesia (CPI) has made an
inspection plan in the period 2011/2012 using the method of Long Range Ultrasonic (LRUT)
to detect any defects in pipe material caused by corrosion or erosion.
For executive jobs LRUT, the CPI has conducted a tender to the contractors. PT. Putra Riau
Kemari (PRK), PT. Trihasco Utama (THU), and Techcorr, USA, joined in the consortium
appointed as the winner of the tender. With no C 788 493 contract, the consortium
running the project will serve the work area CPI. Results from LRUT will be verified with a
manual ultrasonic, the data obtained will be reported in this report in engineering
calculations to obtain the value of maximum allowable working pressure (MAWP),
corrosion rate, as well as the recommendations included suggestions to repair the pipe if it
is found that critical area.
1.4 PORPOSE
Purpose of the job "Long Range Ultrasonic Testing (LRUT) Project" is to determine the
external and internal condition of pipes in the CPI and provide recommendations to the
CPI for repair and replacement of pipes when the pipe is not acceptable to operate
according to the code / standard that is used.
Scope of executive summary report is only for segment PF-12 & 14 Inch Benar 45 to
Bekasap GS, with total length is 863.84 meters
6
1.5 WORK ORDER NUMBER
This report to be submitted for Work Order/JDE Number: 2218826 with scope of area
inspection only for PF-12 and 14 inch –Benar 5 to Benar GS.
1.6 TECHNICAL DATA
Area : Benar, SLN
Segment/ Length of Pipe : 12 and 14 Inch – Benar 5 to Benar GS / 863.84 meters
Fluid Content : Crude Oil
Outside Diameter : 12.750 inch and 14 Inch
Material Specification : API 5L Grade B
Nominal Thickness : 9.525 mm
Construction : Aboveground and Road Crossing
Design Press/Temp : 257 psi/ 200 o
F
Operating Press/Temp : 257 psi/ 150 o
F
The data obtained from the CPI and the CPI has been approved above data if that is the
data assumption.
7
CHAPTER II SCOPE OF WORK & EQUIPMENT
2.1. SCOPE OF WORK
The scope of work for WO No. 2221124 in the area Sumatra Light North (SLN) Benar, is as
follows:
 Survey and field data collection
 Preparing Standard Operating Procedure (SOP) above ground
 Preparing LRUT equipment
 Preparing General Work Permit
 LRUT analyze data, and classify categories of analysis.
 Follow-up and verification, if found anomalies in the results LRUT analysis,
using a manual ultrasonic scanning (internal corrosion indication) or visual
(external corrosion indication).
 Record minimum remaining thickness and reporting result verification
data.
 Calculating data to determine corrosion rate, MAWP and remaining life.
 Recommendation.
2.2. EQUIPMENT & TOOLS
Equipment:
 1 set LRUT with collar size 8 inch
 Thermometer gun infrared
 UT Wall thickness : Cygnus
 UT Scanning : DMS-2
 Global Positioning System (GPS): Garmin
Tools:
 Gas Detector
 Hoe
 Shovel
 Sandpaper
8
CHAPTER III INSPECTION METHODOLOGY
3.1 PREPARATION OF JOB
For this project, there are some of task that included as preparation of job, i.e:
 Daily coordination with all of team member before executes the job.
 Preparation of working permit every day at site.
 Preparation of inspection equipment and tools for this job.
 Safety briefing if we execute new work order.
3.2 INITIAL FIELD SURVEY
Propose of initial survey is:
a. Performing initial general screening propose to know where is pipeline location and
road acess as reference of team and equipment mobilization.
b. Performing initial visual inspection along the pipeline to know external surface
condition of pipeline.
c. To know condition of pipeline system protection for underground pipeline,
withness land slide potential, free span potential, pipe support condition, etc.
3.3 COLLECTING DOCUMENT
Collecting data related with pipeline were perfomed together with CPI counterpart. These
data very important to know the history of pipeline design, operation, inspection and
maintenance.
Related data that we hope can be collected from pipeline owner and using as our
reference during analysis and calculation data are:
 Alignment Sheet
 Data design of pipeline
 Historical of inspection report and ROW Survey
 Report of last UT Wall Thickness
 Maintenance/Repair Record
 Operation Report
9
 Historical data of repair and pipe replacement
 Soil Movement data (if any)
3.4 FIELD DATA COLLECTION
3.4.1 Visual Inspection and UT Wall Thickness
Visual inspection performed as method to screening surface condition of pipeline
segment. These conventional inspection methods are effective enough to screening
of potential damage that probably happen at existing pipeline. The Potential
damage included external general corrosion, extrem metal loss, erosion, blisters,
dents-gouges- combination dents gauges or pitting / flaw corrosion.
UT Wall Thickness performed at every Test point (TP) or Test Location (TL) at 4
location (at 12 o’clock, at 3 o’clock, at 6 o’clock, and at 9 o’clock). But to make sure
that LRUT dead zone are also screening, we were performed UT wall thickness
inspection forward and backward every 1 ft, but data not recorded due to porpose
of inspection only to make sure pipeline condition at LRUT dead zone. If we found
any anomalies or indication during that inspection, we will performing direct
assessment/investigation on it.
Figure 3. LRUT Inspection
Detail result of UT Wall Thickness Measurement at every TP or TL for this pipeline
can be found at attachment report.
3.4.2 Long Range Ultrasonic Testing (LRUT) Inspection
Indications identified on the A-scan plots are evaluated on the basis of a
combination of:
10
1. The signal amplitude
2. The directionality of the focused response.
This takes into account that large amplitude responses will be from a large cross-
sectional area defect. Small defects cannot produce large amplitude reflections.
However, the converse is not always true; a small amplitude response does not
necessarily mean that the defect is small, as the response may be affected by a
number of factors.
In order to provide a means of identifying defects which are potentially significant
in terms of the integrity of the pipe it is also necessary to examine how localized the
response is in terms of the pipe circumference. This may be obtained from the
focused tests and is plotted on a polar response chart.
To incorporate these changes, some aspects of the interpretation procedure have
been altered compared with earlier versions of the Teletest®
test procedures:
Whereas the indications were previously assessed primarily in terms of amplitude,
with the categories being ‘Minor’, ‘Moderate’ and ‘Severe’, the signals are now
described as being of Amplitude Category 1, 2 or 3, with Category 3 being the
highest.
An additional DAC curve has been added to the analysis screen. This is a red line at -
20dB compared with a 100% reflector (equivalent to a pipe end), so that it plots in
between the blue weld line (-14dB) and the green 9% reflector line (-26dB). This
defines the boundary between Categories 2 and 3 - see below.
The additional DAC curve and the areas corresponding to the categories above are
shown in Figure 4, below.
11
Figure 4. Schematic of the Teletest A-scan, showing the amplitude categories.
Category 1 responses are those which are lower than the green -26dB line (formerly
minor). Category 2 responses are those above the -26dB line, but are lower than
the new red line at -20dB (formerly Moderate). Category 3 responses exceed the
new red -20dB line (these are broadly the same as the previous severe
classification, but the limiting amplitude is now better defined.
Below the Greenline is category 1, between the green and red line is category 2 and
above the red is category 3. The collection of focused data from suspected defects
is an integral part of the test regime. The results from focused tests on each defect
are analyzed in terms of the directionality of the response.
If the polar plot shows a high level of directionality, indicated by a single peak in the
plot at one focus angle, it is classed as category 3 (figure 5). This indicates that the
defect is highly localized on a narrow part of the circumference, so that it is likely to
be deep for given amplitude of response.
12
Figure 5. Category 3 responses from focused tests
If the polar plot has two adjacent high amplitude responses it is classed as category
2. This is shown in figure 6. This suggests that the defect is localised, but has some
circumferential length.
Figure 6. Category 2 responses from focused tests
If the polar plot has 3 or more adjacent high amplitude peaks (figure 7) it is classed
as category 1. This suggests that it is spread over a wide area of circumference, so
that it is likely to be less deep for a given response amplitude.
Figure 7. Category 1 response from a focused test
13
Figure 8. Category 0 response from a weld from a focused test
The overall classification is obtained by multiplying the two values, amplitude x
directionality, obtained from a defect. A score of 3 or greater gives a
recommendation for a High priority follow up, a score of 2 gives a Medium priority
and a score of 1 gives a low priority. This is summarized in Table 1 below.
Table 1. Evaluation Matrix
Amplitude Directionality Score
Follow
up
priority
3 3 9 High
3 2 6 High
3 1 3 High
3 0 0 Weld
2 3 6 High
2 2 4 High
2 1 2 Medium
1 3 3 High
1 2 2 Medium
1 1 1 Low
3.4.3 Direct Assessment/Investigation
If we found some indication or anomalies base on LRUT Inspection result, that we
will perform direct assessment inspection/investigation on it. Investigation will
perform by both visual inspection and also UT Scanning at point that indicated any
anomalies. Detail direct assessment inspection/investigation inspection can be
found on next chapter and also on attachment of this report.
14
3.5 ANALYSIS DATA & CALCULATION
After all of inspection data and investigation data completed and available, we will perform
analyisis of data and also making calculation base on that data. We are performing analysis
for below data:
a. Result of initial survey and visual inspection.
b. Result of UT Wall Thickness at every TP or TL.
c. Result of LRUT Inspection.
d. Result of UT Scanning during direct assessment/investigation at indicated
anomalies point.
And we are also performing calculation base on above data inspection, i.e:
a. Calculation of new MAWP.
b. Calculation of estimated Corrosion Rate.
c. Calculation of Remaining Life.
Detail of analysis data and calculation can be found at next chapter and also on attachment
of this report.
3.5.1 MAWP Calculation for Internal Corrosion
Refer to ANSI B 31.4 Paragraph 403.2.1, Calculation Maximum Allowable Work
Pressure (MAWP) based on actual thickness using formula:
Where,
P = MAWP (psi)
S = Maximum Allowable Strength (psi)
D = Pipe outside diameter (inch)
t = Nominal thickness (inch)
E = Longitudinal Joint Factor
Corrosion rate calculation API 570 paragraph 7.1.1, using below formula:
15
Where,
ipy = corrosion rate (inch per year)
t = thickness nominal (inch)
ta = minimum actual thickness (inch)
Remaining Life, using formula:
Where,
Rem. Life = Remaining life (years)
td = thickness requirement design (inch)
tact = minimum actual thickness (inch)
3.5.2 MAWP Calculation for External Corrosion
Refer to ANSI B 31.G part 4, Calculation of Maximum Allowable Work Pressure
(MAWP) using formula:
- Determine strength of corroded area (A or G)
Where,
L = Length of corroded Area (inch)
D = Outside Diameter of Pipe (inch)
t = thickness nominal (inch)
If A or G less than 4, using below formula:
16
Where,
P’ = MAWP Corroded Area (psi)
P = Design Pressure based nominal thickness (psi)
D = depth of pitting (inch)
t = thickness nominal (inch)
If A or G greater than 4, using below formula:
Where,
P’ = MAWP Corroded Area (psi)
P = Design Pressure based nominal thickness (psi)
3.6 CONCLUTION & RECOMMENDATION PREPARATION
3.6.1 Conclution
The conclusions given in this report is the actual condition of the pipeline after
application of above inspection methodology, i.e: initial field survey, visual
inspection, UT Wall Thickness, LRUT, and direct assessment (UT Scanning and Depth
Gauge if there is pitting corrosion found).
3.6.2 Recommendation
Some of the recommendations that will be recommended on this report consider
the following:
 If Metal loss of pipe less than or maximum 20% of thickness required
design.
17
In these conditions, the recommendation given is an inspection plan that
considers the results of the calculation of remaining life. Basically, the
calculation of remaining life is only for the age-related corrosion condition,
while condition base is the result of remaining life multiple confidence rating
and is focus on individual pipeline. Thickness measurements should be
scheduled based on the calculation of not more than half the remaining life
determination.
 An area of corrosion with maximum depth greater than 20% but less than or
equal to 80% of the wall thickness.
In these condition, conducted the evaluation using the ASME B. 31.G, and the
corrected thickness plus Corrosion Allowance. If that fails will be recommended
to the mounting sleeve type A or composite sleeve temporary.
 An area of corrosion with more than 80% of the wall thickness.
In these conditions, the pipe shall be removed or repaired.
All of these conditions are illustrated in the diagram below:
18
Figure 9. Repair for internal corrosion
Figure 10. Repair for external corrosion
Detail recommendation will be explained at Chapter V at this report.
19
CHAPTER IV RESULT, ANALYSIS AND CALCULATION
4.1 INITIAL SURVEY & VISUAL INSPECTION RESULT
Surveys have been conducted in the area Bekasap, SLN Ø12 and 14 Inch- Benar 5 to Benar
GS, with total length 863.84 meters, and getting conditions of the pipeline.
The survey results above are used by CPI as reference to issued WO No. 2218826
Survey result base on visual inspection/naked eye inspection during initial survey are:
1. In general, pipeline was constructed above ground
2. Pipeline in coated condition
3. There are not found leak or sleeve or patching.
4. This pipeline segment has 2 road crossing and the protected by casing.
4.2 LONG RANGE ULTRASONIC TESTING (LRUT) RESULT
Our main method of inspection for this job is Long Range Ultrasonic Test (LRUT) inspection.
Porpose of LRUT inspection are to screening pipeline condition both external and internal
condition at the same time. LRUT inspection performed and applied for all of pipeline SLN
12 and 14 Inch Benar 5 to Benar GS, with total length 863.84 meters. Before shooting of
LRUT performed, we are devide some Test Point (TP) or Test Location (TL) where LRUT
shooting will be done. Because porpose of this job are to screening 100% pipeline
condition, than TP/TL second and onward depend on result length of LRUT shooting for
first TP/TL.
Below, step by step explanation LRUT inspection:
1. Indicated first Test Point (TP) or Test Location (TL).
2. Cleaning location TP/TL, open coating (wrapping tape)/insulation around 30 - 40 cm
(if any.
3. Visual inspection at pipeline around TP/TL.
4. Collecting data UT wall thickness at 4 locations (at 12 o’clock, 3 0’clock, 6 o’clock,
and 9 0’clock).
5. Install Collar Size Transducer at location that has been cleaning above (Test Point) ;
be carefull flow of oil (follow LRUT Expert instruction/sugestion).
6. Install cable to Collar Size Transducer, Compressor Data Logger dan Laptop.
20
7. LRUT expert collecting data at that TP for forward and backward direction.
If LRUT expert found high priority (see table 1. Evaluation Matrix above), than we must
performing direct assessment/investigation at location were found anomalies/indication.
Mostly, indication that should be follow up by direct assessment/investigation are if
shooting result indicated found category 2 with ECSL : Estimated Cross Sectional Loss
around 9 – 16% from nominal thickness and also indication 3 with ECSL : Estimated Cross
Sectional Loss more than 16% from nominal thickness. Some equipment that we are use
during perform direct assessment/investigation are Manual UT Thickness, UT Scanning,
and Pitch Gauge (for check depth of corrosion and length of corroded area).
Below, we can found set up of LRUT Equipment that we were used for this job:
Figure 9. Set Up of LRUT Equipment
Below (table 3), we can found conclution of LRUT inspection result per TP for segment
pipeline SLN Ø 12 and 14 Inch Benar 5 to Benar GS, with total length 863.84 meters,
included their each anomalies indication.
Table 3. Resume of LRUT Result
21
A G UG R C F wd (m) B wd (m) F wd ( m) B wd ( m )
D
(mm)
T
(mm)
L M H
External Pitting
Corossion
-2.46 1.8 - 100 50 Medium Pict 1
External Pitting
Corossion
-8.14 1.1 - 500 200 Low Pict 2
External Pitting
Corossion
-9.02 1.6 - 500 200 Low Pict 3
- -
External Pitting
Corossion
-11.86 1.1 - 100 100 Low Pict 4
External Pitting
Corossion
-22.50 2-2.5 - 200 150 Medium Pict 5
External Pitting
Corossion
-23.26 1.2 - 100 50 Low Pict 6
External Pitting
Corossion
+6.75 1.2 - 100 100 Low Pict 7
External Pitting
Corossion
+10-
13.40
1.6-3.4 - 3400 250 Medium Pict 8
-6.21 - - - - Low
-32.94 - - - - Low
3 Good -1.02 - - - - Low
External Pitting
Corossion
-14.18 1.2 - 50 50 Low Pict 9
External
Corossion
+3.77 2.5 - 2000 200 Medium Picy 10
Good +9.20 - - - - Low
Good +12.43 - - - - Low
Good +17.24 - - - - Low
- - Good +18.79 - - - - Low
680 24 12 Good +24.84 - - - - Low
Good +25.49 - - - - Low
External Pitting
Corossion
+27.52 1.7 - 700 200 Low Pict 11
External Pitting
Corossion
+31.11-
32
1.8-2.7 - 1000 200 Medium Pict 12
External Pitting
Corossion
35.69 1 - 50 50 Low Pict 13
External Pitting
Corossion
+37.18 1 - 50 50 Low Pict 14
External Pitting
Corossion
-33.19 2.4-3.3 - 1000 200 Medium Pict 15
External Pitting
Corossion
-40.40 1.4 - 50 50 Low Pict 16
External Pitting
Corossion
+11.17 1.4 - 50 50 Low Pict 17
External Pitting
Corossion
+15.17 2 - 50 59 Low Pict 18
External Pitting
Corossion
+21.77 1.5 - 50 50 Low Pict 19
External Pitting
Corossion
+26.36 1.5 - 200 200 Low Pict 20
Good -14.27 - - - - Low
Good -18.14 - - - - Low
- - 907 55.8 20
External Pitting
Corossion
-26.42 1 - 500 100 Low Pict 21
External Pitting
Corossion
-36.42 1.2 - 500 200 Low Pict 22
Tack Weld -18.14 - - - - Low Pict 23
6 TL 06 √ - -
N 01 41'31.6"
E100 59'03.9"
Paint 38.90 14.62 - - Category 2 7.50 8.00 709.00 26.80 13.00
External Pitting
Corossion
-5.75/
-11.49
2-2.5 - 6000 200 Medium Pict 24
7 TL 07 √
N 01 41'33.0"
E100 59'02.8"
Paint - 6.46 23.49 Category 1 8.70 9.50 1091.00 122.20 20.00
External Pitting
Corossion
-1.63 1 - 250 70 Low Pict 25
R/C lengh
23.49 M
External Pitting
Corossion
-5.57 1.4-2.2 - 750 1000 Medium Pict 26
External Pitting
Corossion
+1.40 -
'+1.68
1.8 -2.5 - 360 1000 Medium Pict 27
- - 774 34.1 17
External Pitting
Corossion
+2.30 1.6 -2 - 350 600 Medium Pict 28
External Pitting
Corossion
+2.80 1.3 -2 - 350 600 Medium Pict 29
External Pitting
Corossion
+3.40 1 - 750 600 Low Pict 30
9 TL 09 √ - -
N 01 41'34.4"
E100 59'02.0"
Paint 10.16 4.05
No Relevan
Indication
7.30 8.00 984.00 55.50 20.00 Good - - - - - Low
262.3 250.28 23.49 - 1
23.49 M
1 TL 01 √ - -
N 01 41.332'
E 101 59.194'
Paint 21.46 - - 15.68
No Relevan
Indication
6.32 6.98 984.00 55.50 20.00 Good - - - - - Low
2 TL 02 √ - -
N 01 41.322'
E 101 59.202'
Paint - 52.74 8.54 -
No Relevan
Indication
6.40 6.70 996.00 57.80 20.00 Good - - - - - Low
3 TL 03 √ - -
N 01 41.260'
E 101 59.244'
Paint 88.46 59.34 - -
No Relevan
Indication
6.47 6.57 996.00 57.80 20.00 Good - - - - - Low
TL 04 √ - -
N 01 41.211'
E 101 59.278'
Paint 50.91 30.63 - -
No Relevan
Indication
6.55 6.70 1016.00 61.80 20.00 Good - - - - - Low
160.83 142.71 1
24.23 M
N o .
T est
Lo catio n
C o nstructio n
C o o rdinats
P ipeline
P ipe
C o nditio n
T est Length
A bo ve gro und
T est Length
R o ad C ro ssing
TL 02 √ - -
N 01 41'22.6"
E100 59'09.4" Paint
14'' Production Line Benar 5 to Benar GS
1 TL 01 √ - -
N 01 41'20.5"
E100 59'10.9" Paint 44.7 14.02 10
1076 113.8 20
4 TL 04 √ - -
N 01 41'28.5"
E100 59'05.8" Paint
8 Good
TL 03 √ - -
N 01 41'25.4"
E100 59'08.0" Paint 46.85 52.34
39.18 47.53 - -
No Relevan
Indication
7.62
30.33 56.44 Category 1 & 2 7.5 7.7- -
Category 1 & 2 7.5 7.9
Paint 45.95 40.77 Category 1 7.6 85 TL 05 √ - -
N 01 41'30.5"
E100 59'04.6"
Paint 6.23 14.05 Category 1 & 2 7.95 8.18 TL 08 √ - -
N 01 41'33.1"
E100 59'03.0"
Total Length Pipe Line 303.54 24.23 Total Test Length Road Crossing
Total Road Crossing
Total Length Pipe Line 513.1 23.49 Total test Length Road Crossing
12'' Production Line Benar 5 to Benar GS
R/C
length
24.23M
Total Road Crossing
Category 1 & 2 8 8.3
A no maly
F o to N o .
R emark
Dist ance
f rom TL
M etal Lo ss
L
(mm)
W
(mm)
LR UT
C atego ry
Indicatio n
T hickness
M in.(mm)
T hickness
M ax.(mm)
Visual
F inding
A no maly F inding
598 17.2 8
M A WP
co rro ded
(psi)
R emaining
life
(year)
N ext
inspectio n
(year)
655 21.8
22
Detail of LRUT result per TL including each their graph and interpretation for segment
pipeline Bekasap, SLN; Ø 12 and 14 Inch- Benar 5 to Benar GS, with total length 863.84
meters were described at attachment of this report.
Some of anomalies indication that we found for segment pipeline Bekasap, SLN; Ø 12 and
14 Inch Benar 5 to Benar GS, with total length 863.84 meters can be found at Direct
Assessment Report LRUT as below:
- Category 1 and 2 indication at TL 6
TL 06 - 14" Production Line
All of above anomalies indication should be investigated/performing direct assessment to
prove what actually happen at that location.
4.3 DIRECT ASSESSMENT/VERIFICATION RESULT
Base on data LRUT Result and also data indication of anomalies above, we are performing
direct assessment/investigation to make sure that what really happen at that point. Result
of investigation describe below:
23
Table 3. Verification Result
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
TL 08 Forward 2.80 meter
EXTERNAL COROSSION AT LOCATION FROM TL 08
FORWARD 2.80 M Depth = 1.3 - 2 mm, length 350 mm x 600 mm, position of
defect = 3 - 7 o’clock
TL 08 Forward 3.40 meter
EXTERNAL COROSSION AT LOCATION FROM TL 08
FORWARD 3.40 M Depth = 1mm, length 750 mm x 600 mm, position of
defect = 3 - 9 o’clock
TL 08 Forward 1.40 - 1.68 meter
EXTERNAL COROSSION AT LOCATION FROM TL 08
FORWARD 1.40 - 1.68 M Depth = 1.8 - 2.5 mm, length 360 mm x 1000 mm,
position of defect = 3 - 7 o’clock
TL 08 Forward 2.30 meter
EXTERNAL COROSSION AT LOCATION FROM TL 08
FORWARD 2.30 M Depth = 1.6 - 2 mm, length 350 mm x 600 mm, position of
defect = 3 - 7 o’clock
Ø 12'' & 14'' PRODUCTION LINE BENAR 5
TO BENAR GS
TL 07 TL 07 Backward 1.63 meter
EXTERNAL COROSSION AT LOCATION FROM TL 07
BACKWARD 1.63 M Depth = 1mm, length 250 mm x 70 mm, position of defect
= 6 o’clock
TL 08 Backward 5.57 meter
EXTERNAL COROSSION AT LOCATION FROM TL 08
BACKWARD 5.57 M Depth = 1.4 - 2.2 mm, length 750 mm x 1000 mm, position
of defect = 3 - 9 o’clock
Ø 12'' & 14'' PRODUCTION LINE BENAR 5
TO BENAR GS
TL 08
TL 05 Backward 18.14 meter
TAG WELD AT LOCATION FROM TL 05
BACKWARD 18.14
Ø 12'' & 14'' PRODUCTION LINE BENAR 5
TO BENAR GS
TL 06 TL 06 Backward 18.14 meter
EXTERNAL COROSSION AT LOCATION FROM TL 06
BACKWARD 5.75 - 11.49 M Depth = 2 - 2.5 mm, length 6000 mm x 200 mm,
position of defect = 4 - 6 o’clock
Ø 12'' & 14'' PRODUCTION LINE BENAR 5
TO BENAR GS
TL 05
TL 05 Backward 26.42 meter
EXTERNAL COROSSION AT LOCATION FROM TL 05
BACKWARD 26.42 M Depth = 1mm, length 500 mm x 100 mm, position of
defect = 6 o’clock
TL 05 Backward 36.42 meter
EXTERNAL COROSSION AT LOCATION FROM TL 05
BACKWARD 36.42 M Depth = 1.2 mm, length 500 mm x 200 mm, position of
defect = 5 - 8 o’clock
TL 04 Forward 21.77 meter
EXTERNAL COROSSION AT LOCATION FROM TL 04
FORWARD 21.77 M Depth = 1.5 mm, length 50 mm x 50 mm, position of defect
= 6 o’clock
TL 04 Forward 26.36 meter
EXTERNAL COROSSION AT LOCATION FROM TL 04
FORWARD 26.36 M Depth = 1.5 mm, length 200 mm x 200 mm, position of
defect = 4 - 6 o’clock
Ø 12'' & 14'' PRODUCTION LINE BENAR 5
TO BENAR GS
TL 04
TL 04 Forward 11.17 meter
EXTERNAL COROSSION AT LOCATION FROM TL 04
FORWARD 11.17 M Depth = 1.4 mm, length 50 mm x 50 mm, position of defect
= 6 o’clock
TL 04 Forward 15.17 meter
EXTERNAL COROSSION AT LOCATION FROM TL 04
FORWARD 15.17 M Depth = 2 mm, length 50 mm x 50 mm, position of defect =
7 o’clock
TL 04 Backward 33.19 meter
EXTERNAL COROSSION AT LOCATION FROM TL 04
BACKWARD 33.19 M Depth = 2.4 - 3.3 mm, length 1000 mm x 200 mm,
position of defect = 6 o’clock
TL 04 Backward 40.40 meter
EXTERNAL COROSSION AT LOCATION FROM TL 04
BACKWARD 40.40 M Depth = 1.4 mm, length 50 mm x 50 mm, position of
defect = 6 o’clock
TL 03 Forward 35.69 meter
EXTERNAL COROSSION AT LOCATION FROM TL 03
FORWARD 35.69 M Depth = 1mm, length 50 mm x 50mm, position of defect
= 6 o’clock
TL 03 Forward 37.18 meter
EXTERNAL COROSSION AT LOCATION FROM TL 03
FORWARD 37.18 M Depth = 1mm, length 50 mm x 50 mm, position of defect =
9 o’clock
Ø 12'' & 14'' PRODUCTION LINE BENAR
5 TO BENAR GS
TL 03
EXTERNAL COROSSION AT LOCATION FROM TL 03
FORWARD 27.52 M Depth = 1.7 mm, length 700mm x 200mm, position of
defect = 3 - 9 o’clock
TL 03 Forward 31.11 meter
EXTERNAL COROSSION AT LOCATION FROM TL 03
FORWARD 31.11M Depth = 1.8 - 2.7 mm, length 1000mm x 200mm, position
of defect = 6 o’clock
TL.01
Ø 12'' & 14'' PRODUCTION LINE BENAR
5 TO BENAR GS
TL 03 Forward 3.77 meter
INTERNAL COROSSION AT LOCATION FROM TL 03
FORWARD 3.77 M Depth = 2.5 mm, length 2000mm x 200mm, position of
defect = 5 - 7 o’clock
TL 01 Forward 10 - 13.40 meter
EXTERNAL CORROSION AT LOCATION FROM TL 01
BACKWARD 9.02 M
Depth = 1.6 mm, length 500 mm x 200mm , position of defect = 6 o’clock
EXTERNAL CORROSION AT LOCATION FROM TL 01
BACKWARD 11.86 M
Depth = 1.1mm, length 100 mm x 100mm , position of defect = 6 o’clock
EXTERNAL CORROSION AT LOCATION FROM TL 01
BACKWARD 22.50 M Depth = 2 - 2.5 mm, length 200 mm x 150mm , position of
defect = 7 o’clock
EXTERNAL CORROSION AT LOCATION FROM TL 01
BACKWARD 23.26 M
Depth = 1.2 mm, length 100 mm x 50mm , position of defect = 6 o’clock
EXTERNAL CORROSION AT LOCATION FROM TL 01
FOWARD 6.75 M
Depth = 1.2 mm, length 100 mm x 100mm , position of defect = 6 o’clock
EXTERNAL CORROSION AT LOCATION FROM TL 01
BACKWARD 8.14 M
Depth = 1.1mm, length 500 mm x 200mm , position of defect = 6 o’clock
EXTERNAL COROSSION AT LOCATION FROM TL 03
FORWARD 14.18 M
Depth = 1.2 mm, length 50mm x 50mm, position of defect = 7 o’clock
TL 01 Backward 9.02 meter
TL 01 Backward 11.86 meter
TL 01 Backward 22.50 meter
TL 01 Backward 23.26 meter
TL 01 Forward 6.75 meter
LINE NUMBER
EXTERNAL CORROSION AT LOCATION FROM TL 01
BACKWARD 2.46 M
Depth = 1.8 mm, length 100 mm x 150mm , position of defect = 6 o’clock
TL 01 Backward 8.14 meter
TL 01 Backward 2.46 meter
TL 03 Forward 27.52 meter
Ø 12'' & 14'' PRODUCTION LINE BENAR 5
TO BENAR GS
TL 08
TL NUMBER DISTANCES FROM TEST LOCATION REMARK
EXTERNAL CORROSION AT LOCATION FROM TL 01
FOWARD 10 - 13.40 M Depth = 1.6 -3.4 mm, length 3400 mm x 250mm ,
position of defect = 6 o’clock
TL 03 Backward 14.18 meter
24
Detail investigation report can be founded at attachment of this executive summary
report.
4.4 ANALYSIS DATA AND CALCULATION
In Minas Area at the Segment Pipe Ø 12 and 14 Inch – Benar 5 to Benar GS, with total
length 864.36 meters has been carried out total 13 shooting LRUT at Test Point (TP) or Test
Location (TL). In this segment has founded indications of anomalies at 7 test locations.
Base on design basis data that have been collected together with CPI counterpart, data
result of UT Wall Thickness and LRUT, and also result of investigation at corroded area of
pipeline, we are continuing to making calculation of new MAWP, estimated Corrosion Rate
and Remaining Life of segment pipeline Ø 12 and 14 Inch – Benar 5 to Benar GS.
Base on result, minimum remaining thickness was found at corroded location at TL 4
backward 33.19 meters is 4.4 mm or depth of external corrosion is 3.3 mm.
Refer to above data, design data and operational data as data input and refer to
ANSI/ASME B 31.4 and ANSI/ASME B 31G, than we are making MAWP calculation based on
actual minimum thickness. Using below template, we are found new MAWP are 598 psi.
MAWP calculation results seen in the table below:
Table 5. Verification Result
No
Test Location
No.
Thickness
Min. Req.
(mm)
Design
Press (psi)
MAWP
Nom.
Thickness
(psi)
MAWP
Corroded
Condt (psi)
Corrosion
Rate
(mm/Year)
Rem. Life
(years)
Next
Inspection
1 14" - TL01 1.8 257 1350 655 0.129 21.8 10
2 TL02 1.8 257 1350 1076 0.051 113.8 20
3 TL03 1.8 257 1350 680 0.124 24 12
4 TL04 1.8 257 1350 598 0.139 17.2 8
5 TL05 1.8 257 1350 907 0.081 55.8 20
6 TL06 1.8 257 1350 709 0.119 26.8 13
7 TL07 1.8 257 1350 1091 0.048 122.2 20
8 TL08 1.8 257 1350 774 0.106 34.1 17
9 12" - TL 01 1.8 257 1350 984 0.083 55.5 20
10 TL02 1.8 257 1350 996 0.081 57.8 20
11 TL03 1.8 257 1350 996 0.081 57.8 20
12 TL04 1.8 257 1350 1016 0.078 61.8 20
25
Detail MAWP calculation can be found on below template figure:
I. Line Number Data :
Line Number : PF- 14'' - Benar 5 to Benar GS Material Specification : GRB ERW
Content : Oil Long'nal Joint Fact. (E) : 1.00
Type of Services : PIPELINE Nominal Thickness (t) : 0.375 Inch
Operating Pressure : 257 Psi Actual Thickness (ta) : 0.295 Inch
Operating Temperature : 150 o
F / 66 O
C Depth of Localized Pitting (d) : 0.209 Inch (at pit)
Pipe Nominal Diameter : 14 inch Remaining thickness : 0.166 Inch
Pipe Out Side Diameter : 14.000 inch Thickness Lost (FromNom.) : 55.73 %
Test Location : TL4-33.19
II. Calculation : (Refer to ANSI/ASME B31.4) ANSI B 31.4 Paragraph 403.2.1
MaximumAllowable Strength (S) = 35000 psi (See Table 402.3.1(a) for material being used)
Maximum Allowable Working Pressure (MAWP) basedon Nominal Thickness is :
2 x S x t x E x 0.72 2 x 35000 x 0.375 x 1.00 x 0.72
P = --------------------------------------------- = --------------------------------------------------------------------------- = Psi
D 14.00
MAWP for pipe basedon minimum actual thickness is :
2 x S x ta x E x 0.72 2 x 35000 x 0.166 x 1.00 x 0.72
P = -------------------------------------------- = --------------------------------------------------------------------------- = Psi
D 14.00
Corrosion rate API 570 paragraph 7.1.1
t - ta 0.375 - 0.166
ipy = ---------------- = --------------------------------- = inch/year
life time 38
Remaining life :
tact - td 0.166 - 0.071
Rem. life = -------------------------- = ------------------------------ = year = months
Corrosion rate
CONCLUSION :
Based on above Calculation, the MAWP for the pipe is 598 which is Higher than
operating Pressure of psi. and Higher than design pressure of psi
17.2 206.4
257
0.0055
0.0055
PIPE CALCULATION SHEET
FACILITYENGINEERING & INSPECTION
1350
598
psi
257
To make calculation of remaining life, corrosion rate dan tmin we are making asumption
that derating pressure are = 257 psi. From calculation that refer to ANSI/ASME B 31G, we
are found below result:
a. Remaining Life : 17.2 years
b. Corrosion Rate : 0,0055 inch/years = 0.139mm/years
26
CHAPTER V CONCLUTION AND RECOMMENDATION
5.1 CONCLUTION
There are some conclution that can be found during our inspection, analysis and
calculation data for segment Ø 12 and 14 Inch – Benar 5 to Benar GS, with total length
864.36 meters, i.e:
a. It has been found category 1 and 2 with medium anomalies finding relevan indication at
5 Test location on pipe Ø 14 Inch Benar 5 to Benar GS, with the types of damage are:
 External corrosion at TL 1 with maximum depth 3.4 mm, location 10 – 13.4
meter forward from TL 1
 External corrosion at TL 03 with maximum depth 2.5 mm, location 3.77 – 5.77
mater forward from TL 03
 External corrosion at TL 04 with maximum depth 3.3 mm, location 33.19 – 34.19
meter backward from TL 04
 External corrosion at TL 06 with maximum depth 2.5 mm, location 5.75 – 11.49
meter backward from TL 06
 External corrosion at TL 08 with maximum depth 2.5 mm, location 1.4 – 1.68
meter forward from TL 08
b. Base on calculation the data from the verification findings, and in the external corroded
conditions, pipeline segments Ø 12 and 14 Inch – Benar 5 to Benar GS is still allowed to
operate with pressure up to 598 psi.
c. Corrosion Rate at the pipeline segments Ø 12 and 14 Inch – Benar 5 to Benar GS is
0.00547 mm/year = 0.139 mm/years and remaing life time is 17.2 years.
d. Pipe condition is Medium anomali finding, with total lenght of corroded pipe 26.889
meters or approximately 3.1 % of the overall segment length of 864.36 meters, with
minimum thickness is 4.4 mm
27
5.2 RECOMMENDATION
Some recommendation that can be proposed to CPI as reference to mitigate the problem
that were be found during inspection, analysis, and calculation data for segment Ø 12 and
14 Inch – Benar 5 to Benar GS with total length 863.84meters, i.e:
5.2.1. Repaint
In the flow chart in figure 10. above, the first analysis is to calculate the ratio
between the depth of pitting and nominal thikness (d/t), the results in this
segment is still below 80%, with a minimum of metal loss 10.5 % and maximum
metal loss 53 %
External corrosion occured in this segment approximately 10 % of the lenght , to
avoid futher damaged, then we recommend to do clean up and repaint on the
location of the pipe as follows:
1. At a distance of 13 meters forward to 23 26 backward from datum TL 01
2. At a distance of 27 meters to 37 meters forward from datum TL 03
3. At a distance of 33 meters to 34 meters Backward from datum TL 4
4. At a distance of 5.7 meters to 11.49 meters backward from datum TL 06
5. At a distance of 2.8 meters forward to 5.57 meters backward from datum
TL 08
5.2.2. Plan and Method Inspection
Based on a calculation of the remaining thickness of the pipe, the remaining period
of this pipe, was 17.2 years. Refer to API 570, an inspection plan at least half of
remaining life. Planning the next inspection is recommended 8 years or due date
inspection conducted in June 2019.
28
While the method of inspection, as follows:
a. Visual Inspection.
Perform visual inspection on bottom of pipe section that was found defective in
LRUT, to ensure the occurrence of external corrosion.
b. Ultrasonic Wall Thickness
Perform wall thickness measurement at critical location:
1 Bend Pipe
29
Area 1 at least Sq Ft
Flow fluid Direction and
flow inspection
Flow fluid Direction and
flow inspection
Area 1 at least Sq Ft
Weld joint
2 Straight pipe After Bend at least 1 sq ft area
3 Every straight stright pipe after joint weld at least 1 sq ft area
Long Range Ultrasonic Testing
Chevron Pasific Indonesia
Under ground Road crossing Above ground
Long range ultrasonic testing
A scan graph road crossing
Long range ultrasonic testing
at Road crossing/under
ground
Result of LRUT at area road
crossing founded 3 anomaly
Category 1 and 1 anomaly
category 2
Direct verification by UT flaw
detector is found external
corrosion at location 3 – 9
o’clock
Dimension of corrosion.
Depth = 4 mm
Length = 4.8 meter
Width = 250 mm
Long range ultrasonic testing
A scan graph Above ground
Jangkauan LRUT ± 200 Meter
Long range ultrasonic testing
A scan graph Above ground
Jangkauan LRUT 12 Meter
Long range ultrasonic testing
at Above ground
Ø 8 Inch Gas Line Petani GS
Result of LRUT at area above
gound founded 10 anomaly
Category 3
Direct verification by UT flaw
detector is found Internal
corrosion at location on
circular pipe.
With depth maximum
corrosion is 4 mm.
Remaining thickness of
material Is 2.5 mm.
Inspection finding summary report
Long Range Ultrasonic Testing
sample report anomaly category medium ( yellow )
and High ( Red )
Recommendation for sleeve
Long Range Ultrasonic Testing
Full Encirclement sleeve due to internal corrosion
Long range ultrasonic testing
Method Repair with
Half sleeve
Half sleeve on segment 24
Inch production line at area
12 due to internal corrosion.
Owner / User: Chevron Pasific Indonesia Pipe Identification : 12'' & 14'' Production Line Benar 5 to Benar GS
Service : Crude Oil Nominal Diameter : 14.00 & 12.00
Drawing No. : - Thickness Nominal : 9.35
Periode Inspection: 23 May - 27 May 2011 Material : API 5L Gr.B
Location Area: BENAR Field, SLN LRUT Level 2 : Dhirendra/Ashish Matre
Assisten Operator : Romi Hendra/Isa
AG UG RC Fwd (m) Bwd (m) Fwd ( m) Bwd ( m ) D (mm)
T
(mm)
L M H
External Pitting
Corossion
-2.46 1,8 - 100 50 Medium Pict 1
External Pitting
Corossion
-8.14 1,1 - 500 200 Low Pict 2
External Pitting
Corossion
-9.02 1,6 - 500 200 Low Pict 3
- -
External Pitting
Corossion
-11.86 1,1 - 100 100 Low Pict 4
External Pitting
Corossion
-22.50 2-2.5 - 200 150 Low Pict 5
External Pitting
Corossion
-23.26 1,2 - 100 50 Low Pict 6
External Pitting
Corossion
+6.75 1,2 - 100 100 Low Pict 7
External Pitting
Corossion
+10-13.40 1.6-3.4 - 3400 250 Medium Pict 8
-6.21 - - - - Low
-32.94 - - - - Low
3 Good -1.02 - - - - Low
External Pitting
Corossion
-14.18 1,2 - 50 50 Low Pict 9
Internal Corossion +3.77 2,5 - 2000 200 Low Picy 10
Good +9.20 - - - - Low
Good +12.43 - - - - Low
Good +17.24 - - - - Low
- - Good +18.79 - - - - Low
Good +24.84 - - - - Low
Good +25.49 - - - - Low
External Pitting
Corossion
+27.52 1,7 - 700 200 Low Pict 11
External Pitting
Corossion
+31.11-32 1.8-2.7 - 1000 200 Medium Pict 12
External Pitting
Corossion
35,69 1 - 50 50 Low Pict 13
External Pitting
Corossion
+37.18 1 - 50 50 Low Pict 14
External Pitting
Corossion
-33.19 2.4-3.3 - 1000 200 Medium Pict 15
External Pitting
Corossion
-40.40 1,4 - 50 50 Low Pict 16
External Pitting
Corossion
+11.17 1,4 - 50 50 Low Pict 17
External Pitting
Corossion
+15.17 2 - 50 59 Low Pict 18
INSPECTION FINDING SUMMARY
LONG RANGE ULTRASONIC TEST
Work Order No. : 2221124
No.
Test
Location
Coordinats Pipeline Pipe Condition
Paint 44,7 14,02 Category 1 & 2 8 8,3
Anomaly Foto No. Remark
1 TL 01 √ - -
N 01 41'20.5"
E 100 59'10.9"
LRUT Category
Indication
Thickness
Min.(mm)
Thickness Max.(mm) Visual
Finding
Good
TL 03 √ - -
N 01 41'25.4"
E 100 59'08.0" Paint 46,85 52,34
Paint 39,18 47,53
No Relevan
Indication
7,6 8TL 02 √ -
Construction
Test Length
Above ground
Distance
from TL
-
N 01 41'22.6"
E 100 59'09.4"
Category 1 & 2 7,5 7,9
4 TL 04 √ - -
N 01 41'28.5"
E 100 59'05.8" Paint 30,33 56,44 Category 1 & 2 7,5 7,7
- -
- -
2
Test Length
Road Crossing
14'' Production Line Benar 5 to Benar GS
Metal Loss
L (mm) W (mm)
Anomaly Finding
Owner / User: Chevron Pasific Indonesia Pipe Identification : 12'' & 14'' Production Line Benar 5 to Benar GS
Service : Crude Oil Nominal Diameter : 14.00 & 12.00
Drawing No. : - Thickness Nominal : 9.35
Periode Inspection: 23 May - 27 May 2011 Material : API 5L Gr.B
Location Area: BENAR Field, SLN LRUT Level 2 : Dhirendra/Ashish Matre
Assisten Operator : Romi Hendra/Isa
AG UG RC Fwd (m) Bwd (m) Fwd ( m) Bwd ( m ) D (mm)
T
(mm)
L M H
INSPECTION FINDING SUMMARY
LONG RANGE ULTRASONIC TEST
Work Order No. : 2221124
No.
Test
Location
Coordinats Pipeline Pipe Condition Anomaly Foto No. Remark
LRUT Category
Indication
Thickness
Min.(mm)
Thickness Max.(mm) Visual
Finding
Construction
Test Length
Above ground
Distance
from TL
Test Length
Road Crossing
Metal Loss
L (mm) W (mm)
Anomaly Finding
External Pitting
Corossion
+21.77 1,5 - 50 50 Low Pict 19
External Pitting
Corossion
+26.36 1,5 - 200 200 Low Pict 20
Good -14.27 - - - - Low
Good -18.14 - - - - Low
- -
External Pitting
Corossion
-26.42 1 - 500 100 Low Pict 21
External Pitting
Corossion
-36.42 1,2 - 500 200 Low Pict 22
Tack Weld -18.14 - - - - Low Pict 23
6 TL 06 √ - -
N 01 41'31.6"
E 100 59'03.9" Paint 38,90 14,62 - - Category 2 7,50 8,00
External Pitting
Corossion
-5.75/
-11.49
2-2.5 - 6000 200 Medium Pict 24
7 TL 07 √
N 01 41'33.0"
E 100 59'02.8" Paint - 6,46 23,49 Category 1 8,70 9,50
External Pitting
Corossion
-1.63 1 - 250 70 Low Pict 25
R/C lengh
23.49 M
External Pitting
Corossion
-5.57 1.4-2.2 - 750 1000 Medium Pict 26
External Pitting
Corossion
+1.40 -
'+1.68
1.8 - 2.5 - 360 1000 Medium Pict 27
- -
External Pitting
Corossion
+2.30 1.6 - 2 - 350 600 Medium Pict 28
External Pitting
Corossion
+2.80 1.3 - 2 - 350 600 Medium Pict 29
External Pitting
Corossion
+3.40 1 - 750 600 Low Pict 30
9 TL 09 √ - -
N 01 41'34.4"
E 100 59'02.0" Paint 10,16 4,05
No Relevan
Indication
7,30 8,00 Good - - - - - Low
262,3 250,28 23,49 - 1
23.49 M
1 TL 01 √ - -
N 01 41.332'
E 101 59.194' Paint 21,46 - - 15,68
No Relevan
Indication
6,32 6,98 Good - - - - - Low
2 TL 02 √ - -
N 01 41.322'
E 101 59.202' Paint - 52,74 8,54 -
No Relevan
Indication
6,40 6,70 Good - - - - - Low
3 TL 03 √ - -
N 01 41.260'
E 101 59.244' Paint 88,46 59,34 - -
No Relevan
Indication
6,47 6,57 Good - - - - - Low
TL 04 √ - -
N 01 41.211'
E 101 59.278' Paint 50,91 30,63 - -
No Relevan
Indication
6,55 6,70 Good - - - - - Low
160,83 142,71 1
24.23 M
LOW : metal lost less than 20 % nominal thickness D : Depth
MEDIUM : metal lost more than 20 % and below 80% nominal thickness T : Thickness
HIGH : metal lost more than 80% nominal thickness L : Length
Note : W: Width
Duri, June 2011
Prepared by
Paulus Konda
R/C
length
24.23M
4 TL 04 √ - -
N 01 41'28.5"
E 100 59'05.8" Paint 30,33 56,44 Category 1 & 2 7,5 7,7
√ - -
Total Test Length Road Crossing
8
√ - -
Total Length Pipe Line 512,58 23,49
Total Road Crossing
Total test Length Road Crossing
Category 1 & 2 7,95 8,1
Total Road Crossing
24,23
PT.Chevron Pasific Indonesia
Kuswantoro Basuki
5 TL 05
8 TL 08
N 01 41'33.1"
E 100 59'03.0" Paint 6,23 14,05
N 01 41'30.5"
E 100 59'04.6" Paint 45,95 40,77 Category 1 7,6
12'' Production Line Benar 5 to Benar GS
303,54
Acknowledge by Approved by
Total Length Pipe Line
Anomaly Pictures per Test Location
Ø 12'' & 14'' Production Line Benar 5 to Benar GS
No. Test Location Finding Picture
1
TL 01
EXTERNAL PITTING CORROSION AT LOCATION FROM TL 01
BACKWARD 2,46 M
Depth = 1.8 mm, length 100 mm x 150 mm, position of defect = 6
o’clock
2
EXTERNAL PITTING CORROSION AT LOCATION FROM TL 01
BACKWARD 8.14 M
Depth = 1.1 mm, length 500 mm x 200 mm, position of defect = 6
o’clock
3
EXTERNAL PITTING CORROSION AT LOCATION FROM TL 01
BACKWARD 9.02 M
Depth = 1.6 mm, length 500 mm x 200 mm, position of defect = 6
o’clock
4
EXTERNAL PITTING CORROSION AT LOCATION FROM TL 01
BACKWARD 11.86 M
Depth = 1.1 mm, length 100 mm x 100 mm, position of defect = 6
o’clock
5
EXTERNAL PITTING CORROSION AT LOCATION FROM TL 01
BACKWARD 22.50 M
Depth = 2-2.5 mm, length 200 mm x 150 mm, position of defect = 7
o’clock
Prepared by
Paulus Konda
Anomaly Pictures per Test Location
Ø 12'' & 14'' Production Line Benar 5 to Benar GS
No. Test Location Finding Picture
6
TL 01
EXTERNAL PITTING CORROSION AT LOCATION FROM TL 01
BACKWARD 23.26 M
Depth = 1.2 mm, length 100 mm x 50 mm, position of defect = 6 o’clock
7
EXTERNAL PITTING CORROSION AT LOCATION FROM TL 01
FORWARD 6.75M
Depth = 1.2 mm, length 100 mm x 100 mm, position of defect = 6 o’clock
8
EXTERNAL PITTING CORROSION AT LOCATION FROM TL 01
FORWARD 10 – 13.40 M
Depth = 1.6 – 3.4 mm, length 3400 mm x 250 mm, position of defect = 6
o’clock
9
TL 03
EXTERNAL PITTING CORROSION AT LOCATION FROM TL 03
BACKWARD 14.18 M
Depth = 1.2 mm, length 50 mm x 50 mm, position of defect = 7 o’clock
10
EXTERNAL CORROSION AT LOCATION FROM TL 03
FORWARD 3.77 M
Depth = 2.5 mm, length 2000 mm x 200 mm, position of defect = 5 - 7
o’clock
Prepared by
Paulus Konda
Owner / User : Chevron Pasific Indonesia Pipe Identification : 12'' & 14'' Production Line Benar 5 to Benar GS
Service : Crude Oil Nominal Diameter : 12.00 & 14.00 Inch
Drawing No. : - Thickness Nominal : 9.525 mm
Periode Inspection: 23 May - 27 May 2011 Material : API 5L Gr.B
Location Area : Benar Field, SLN LRUT Level 2 : dhirendra/Ashish Matre
Assisten Operator : Romi Hendra/Isa
No.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
TABLE OF ANOMALIES
LONG RANGE ULTRASONIC TEST
Work Order No. : 2221121
TL NUMBER DISTANCES FROM TEST LOCATION REMARK
EXTERNAL CORROSION AT LOCATION FROM TL 01
FOWARD 10 - 13.40 M Depth = 1.6 -3.4 mm, length 3400 mm x 250mm , position of defect = 6
o’clock
TL 03 Backward 14.18 meter
LINE NUMBER
EXTERNAL CORROSION AT LOCATION FROM TL 01
BACKWARD 2.46 M
Depth = 1.8 mm, length 100 mm x 150mm , position of defect = 6 o’clock
TL 01 Backward 8.14 meter
TL 01 Backward 2.46 meter
TL 03 Forward 27.52 meter
EXTERNAL CORROSION AT LOCATION FROM TL 01
BACKWARD 8.14 M
Depth = 1.1 mm, length 500 mm x 200mm , position of defect = 6 o’clock
EXTERNAL COROSSION AT LOCATION FROM TL 03
FORWARD 14.18 M
Depth = 1.2 mm, length 50mm x 50mm, position of defect = 7 o’clock
TL 01 Backward 9.02 meter
TL 01 Backward 11.86 meter
TL 01 Backward 22.50 meter
TL 01 Backward 23.26 meter
TL 01 Forward 6.75 meter
TL.01
Ø 12'' & 14'' PRODUCTION LINE BENAR 5
TO BENAR GS
TL 03 Forward 3.77 meter
INTERNAL COROSSION AT LOCATION FROM TL 03
FORWARD 3.77 M Depth = 2.5 mm, length 2000mm x 200mm, position of defect = 5 - 7
o’clock
TL 01 Forward 10 - 13.40 meter
EXTERNAL CORROSION AT LOCATION FROM TL 01
BACKWARD 9.02 M
Depth = 1.6 mm, length 500 mm x 200mm , position of defect = 6 o’clock
EXTERNAL CORROSION AT LOCATION FROM TL 01
BACKWARD 11.86 M
Depth = 1.1 mm, length 100 mm x 100mm , position of defect = 6 o’clock
EXTERNAL CORROSION AT LOCATION FROM TL 01
BACKWARD 22.50 M Depth = 2 - 2.5 mm, length 200 mm x 150mm , position of defect = 7
o’clock
EXTERNAL CORROSION AT LOCATION FROM TL 01
BACKWARD 23.26 M
Depth = 1.2 mm, length 100 mm x 50mm , position of defect = 6 o’clock
EXTERNAL CORROSION AT LOCATION FROM TL 01
FOWARD 6.75 M
Depth = 1.2 mm, length 100 mm x 100mm , position of defect = 6 o’clock
TL 03 Forward 35.69 meter
EXTERNAL COROSSION AT LOCATION FROM TL 03
FORWARD 35.69 M Depth = 1 mm, length 50 mm x 50mm, position of defect = 6 o’clock
TL 03 Forward 37.18 meter
EXTERNAL COROSSION AT LOCATION FROM TL 03
FORWARD 37.18 M Depth = 1 mm, length 50 mm x 50 mm, position of defect = 9 o’clock
Ø 12'' & 14'' PRODUCTION LINE BENAR 5
TO BENAR GS
TL 03
EXTERNAL COROSSION AT LOCATION FROM TL 03
FORWARD 27.52 M Depth = 1.7 mm, length 700mm x 200mm, position of defect = 3 - 9
o’clock
TL 03 Forward 31.11 meter
EXTERNAL COROSSION AT LOCATION FROM TL 03
FORWARD 31.11 M Depth = 1.8 - 2.7 mm, length 1000mm x 200mm, position of defect = 6
o’clock
23 May - 27 May 2011
Pipe Elbow Tee Redc
DIA
(inch)
Above
Ground
Lay
Down
Under
Groun
d
Good Corr Sleeve Clamp
Isolatio
n
Condom
Ø 12'' - Benar 5 -To Benar GS 1 v v - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 2 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 3 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 4 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 5 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 6 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 7 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 8 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 9 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 10 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 11 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 12 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 13 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 14 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 15 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 16 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 17 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 18 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 19 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 20 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 21 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 22 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 23 v - - - 12 v - - v - - - - - -
Ø 12'' - Benar 5 -To Benar GS 24 v v - - 12 - - v v - - - - -
Ø 12'' - Benar 5 -To Benar GS 25 v v - - 12 - - v v - - - - -
Road crossing 1
CONDITION PIPE
Visual Inspection at Ø 12 " and 14 " Benar 58 to Benar GS
REMARKSSERVICE LINE WD
MATERIAL POSITION PIPE
I. Line Number Data :
Line Number : PF - 14'' - Benar 5 to Benar GS Material Specification : GRB ERW
Content : Oil Long'nal Joint Fact. (E) : 1,00
Type of Services : PIPELINE Nominal Thickness (t) : 0,375 Inch
Operating Pressure : 257 Psi Actual Thickness (ta) : 0,315 Inch
Operating Temperature : 150
o
F / 66
O
C Depth of Localized Pitting (d) : 0,193 Inch (at pit)
Pipe Nominal Diameter : 14 inch Remaining thickness : 0,182 Inch
Pipe Out Side Diameter : 14,000 inch Thickness Lost (From Nom.) : 51,47 %
Test Location : TL 1
II. Calculation : (Refer to ANSI/ASME B31.4) ANSI B 31.4 Paragraph 403.2.1
Maximum Allowable Strength (S) = 35000 psi (See Table 402.3.1(a) for material being used)
Maximum Allowable Working Pressure (MAWP) based on Nominal Thickness is :
2 x S x t x E x 0.72 2 x 35000 x 0,375 x 1,00 x 0,72
P = --------------------------------------------- = --------------------------------------------------------------------------- = Psi
D 14,00
MAWP for pipe based on minimum actual thickness is :
2 x S x ta x E x 0.72 2 x 35000 x 0,182 x 1,00 x 0,72
P = -------------------------------------------- = --------------------------------------------------------------------------- = Psi
D 14,00
Corrosion rate API 570 paragraph 7.1.1
t - ta 0,375 - 0,182
ipy = ---------------- = --------------------------------- = inch/year
life time 38
Remaining life :
tact - td 0,182 - 0,071
Rem. life = -------------------------- = ------------------------------ = year = months
Corrosion rate
CONCLUSION :
Based on above Calculation, the MAWP for the pipe is 655 which is Higher than
operating Pressure of psi. and Higher than design pressure of psi
Duri
Prepared by: Approved by
Kuswantoro Basuki
Pipeline Inspector Project Manager
PIPE CALCULATION SHEET
FACILITY ENGINEERING & INSPECTION
1350
655
Paulus Konda
May 1, 2020
psi
257
21,8 261,3
257
0,0051
0,0051
D:Manual Book Training NDT - LRUTLRUT - FINAL REPORT 14'' & 12'' BENAR GSAppendix 4 -MAWP CalkulationMAWP Kalkulasi Dia. 14 Inch
benar TL 1+10M
EXECUTIVE SUMMARY REPORT
1. EXAMINATION TYPE
PT. Putra Riau Kemari (PRK), PT. Trihasco Utama (THU), and Techcorr, USA, joined in
the consortium performed Long Range Ultrasonic Test (LRUT) pipeline inspection at
12 & 14 Inch Production Line Benar 5 to Benar GS to determine the external and
internal condition. LRUT inspection is also followed by thickness measurement,
Ultrasonic Flow Detector, visual inspection, and GPS coordinates in accordance with
the method used by existing contract no.C788493.
2. DATA INSPECTION RESULT
a.Long Range Ultrasonic Test (LRUT)
Examination with LRUT have been done at 13 Test Location of pipeline with length
863.84 M . This pipeline is located at N 01o
41’20.5” E 100o
59’10.9” ( Ø 14” - TL 01 ) finished at N 01o
41’211” E 101o
59’278” ( Ø12 “ – TL4 )
with total length 863.84 meters. 41 anomalies condition were found as follows:
 Found 30 anomalies category Low (Below 20 % Metal Loss) at TL 01, 03, 04,
05, 07 and TL 08 due to external corrosion
 Found 11 anomaly category Medium ( 20 – 80 % Metal loss ) at TL 01, 03 ,04,
06 and 08 due to external corrosion
b.Direct Examination
Visual inspection discovered the existence of external corrosion in 7 Test Locations
with maximum depth at area of external corrosion is 3.4 mm. No emergency clamp
or pipe sleeve has been found that indicated no pipeline leak history.
3. CONCLUSION
Refer to ANSI B31.4 , ANSI B31.G and API 570 as standard code for on plot pipeline.
Summary of data analysis and calculation as follow:
a. The Pipe is medium condition, the metal loss below 80 %, with a minimum
10.5 % metal loss and maximum 53 % metal loss.
b. The minimum remaining thickness is 4.4 mm in Location TL 4 forward 33.19
meters.
c. Data Calculation:
 Design Pressure/Operation : 257 psig
 Material : API 5L Grade B
 Corrosion Rate : 0.00547 ipy (0.139 mm/years).
 MAOP at min actual thickness : 598 psi
 Remaining life : 17.2 years
 Next Inspection interval : 8 years ( June 2019 )
4. RECOMMENDATIONS
a. Inspection with visual and Wall thickness method on June 2019
b. Clean up and repaint the pipe line at TL 01, TL 03, TL 04, TL 6 , and TL 8
Detail data analysis and recommendation could be find in chapter IV and V of 12 & 14
Inch Production Line Benar 5 to Benard GS final report.
30
REFERENCES :
1. Anon. ASME B. 31.4 - 2009, ” Pipeline Transportation Systems for Liquid Hydrocarbons and
Other Liquids, Date of Issuance: March 24, 2010”. The American Society of Mechanical
Engineers, Three Park Avenue, New York, NY 10016-5990
2. Muhlbauer, K. Pipeline Risk Management Manual, Gulf Publishing, 3rd Edition 2004
3. Anon. ASME B.31.G- 2009, “Manual Determining The Remaining Strength of Corroded
Pipelines”, Date of Issuance: October 30, 2009. The American Society of Mechanical
Engineers, Three Park Avenue, New York, NY 10016-5990
4. Anon. API 570, Piping Inspection Code, ”Inspection, repair,Alteration, and Rerating of In-
Service Piping Systems, Second edition, Oct, 1998, addemdum 4, June 2006
5. John, F Kiefner, Pipeline Research Council International, ”Pipeline Repair Manual”, Publication
Date : December,31, 1994. Revision 2006
6. Anon. API RP 580, ”Risk Based Inspection”, First edition 2002
LIST ASUMSI
Data Pipeline
Line Ø12 & 14” Benar 5 to Benar GS
Dimension ( Length x Dia. ) 12 & 14 Inch – 864.36 M
Content Crude Oil
Outside Diameter 12.750 Inch & 14.0 Inch
Material Specification API 5L Grade B
SMYS 35.000 Psi
Pipe Schedule Schedule 40S/std
Thickness Material 9.525 mm
Type of Joint Seam Less
Design Pressure 257 Psi
Design Temperatur 200° F
Operating Pressure 257 Psi
Operating Temperatur 150° F
Year Built 1973
Class Location -
PT. Trihasco Utama
Nama : Paulus Konda
Position : Pipeline Inspector

More Related Content

What's hot

Piping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfPiping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfMDAbdullah621330
 
Basic whp presentation(1)
Basic whp presentation(1)Basic whp presentation(1)
Basic whp presentation(1)nguyen_uptorcem
 
Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...
Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...
Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...Sangilimuthu Samiayyah
 
Peaking & Banding
Peaking & BandingPeaking & Banding
Peaking & BandingWeld Maniac
 
Pr 1159 - commissioning and start-up procedure
Pr 1159 - commissioning and start-up procedurePr 1159 - commissioning and start-up procedure
Pr 1159 - commissioning and start-up procedureRagul Selvam
 
PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync
 
fundamentals of Piping engineering
fundamentals of Piping engineeringfundamentals of Piping engineering
fundamentals of Piping engineeringMobinVarghese8
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docxSharad Naik
 
Piping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingPiping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingAbhijeet Nagle
 
Piping inspector questions 1
Piping inspector questions  1 Piping inspector questions  1
Piping inspector questions 1 MOHAMMAD ATIF ALI
 
API 510 Practise Question Nov 07 rev1.ppt
API 510 Practise Question Nov 07 rev1.pptAPI 510 Practise Question Nov 07 rev1.ppt
API 510 Practise Question Nov 07 rev1.pptSeptianHariPradana1
 

What's hot (20)

Api 570 01_api_570
Api 570 01_api_570Api 570 01_api_570
Api 570 01_api_570
 
Piping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdfPiping Installation and Erection Procedure.pdf
Piping Installation and Erection Procedure.pdf
 
Presentation on SECVIII
Presentation on SECVIIIPresentation on SECVIII
Presentation on SECVIII
 
TPI - Example Report.
TPI - Example Report.TPI - Example Report.
TPI - Example Report.
 
343312365 mt-ppt
343312365 mt-ppt343312365 mt-ppt
343312365 mt-ppt
 
Saudi Aramco Inspection Procedure (SAIP)
Saudi Aramco Inspection Procedure (SAIP)Saudi Aramco Inspection Procedure (SAIP)
Saudi Aramco Inspection Procedure (SAIP)
 
Hydrotest
HydrotestHydrotest
Hydrotest
 
Basic whp presentation(1)
Basic whp presentation(1)Basic whp presentation(1)
Basic whp presentation(1)
 
Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...
Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...
Cv of qaqc, inspection engineer, welding, painting & coating inspector. s.san...
 
Peaking & Banding
Peaking & BandingPeaking & Banding
Peaking & Banding
 
Pr 1159 - commissioning and start-up procedure
Pr 1159 - commissioning and start-up procedurePr 1159 - commissioning and start-up procedure
Pr 1159 - commissioning and start-up procedure
 
API_510_for_Exam.pdf
API_510_for_Exam.pdfAPI_510_for_Exam.pdf
API_510_for_Exam.pdf
 
External Corrosion Direct Assessment (ECDA)
External Corrosion Direct Assessment (ECDA) External Corrosion Direct Assessment (ECDA)
External Corrosion Direct Assessment (ECDA)
 
PetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-UpPetroSync - Pre-Commissioning, Commissioning and Start-Up
PetroSync - Pre-Commissioning, Commissioning and Start-Up
 
fundamentals of Piping engineering
fundamentals of Piping engineeringfundamentals of Piping engineering
fundamentals of Piping engineering
 
API 650 vs 620
API 650 vs 620API 650 vs 620
API 650 vs 620
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
 
Piping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / HydrotestingPiping Hydrostatic Test / Hydrotesting
Piping Hydrostatic Test / Hydrotesting
 
Piping inspector questions 1
Piping inspector questions  1 Piping inspector questions  1
Piping inspector questions 1
 
API 510 Practise Question Nov 07 rev1.ppt
API 510 Practise Question Nov 07 rev1.pptAPI 510 Practise Question Nov 07 rev1.ppt
API 510 Practise Question Nov 07 rev1.ppt
 

Similar to Pipeline integrity assessment with LRUT method

Emergency Pipeline Repair Systems, A Global Overview of Best Practice
Emergency Pipeline Repair Systems, A Global Overview of Best PracticeEmergency Pipeline Repair Systems, A Global Overview of Best Practice
Emergency Pipeline Repair Systems, A Global Overview of Best PracticeJames Rowley
 
Impact of Crack Length into Pipe Conveying Fluid Utilizing Fast Fourier trans...
Impact of Crack Length into Pipe Conveying Fluid Utilizing Fast Fourier trans...Impact of Crack Length into Pipe Conveying Fluid Utilizing Fast Fourier trans...
Impact of Crack Length into Pipe Conveying Fluid Utilizing Fast Fourier trans...IJECEIAES
 
OSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact finalOSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact finalJohn Grover
 
Fitness for Service Assessment of Ageing Pressure Vessel Experiencing Externa...
Fitness for Service Assessment of Ageing Pressure Vessel Experiencing Externa...Fitness for Service Assessment of Ageing Pressure Vessel Experiencing Externa...
Fitness for Service Assessment of Ageing Pressure Vessel Experiencing Externa...theijes
 
CUI PAPER Bahrain v2 - 7April2015 (2)- edited 02 November 2015 Short
CUI PAPER Bahrain v2 - 7April2015 (2)- edited 02 November 2015 ShortCUI PAPER Bahrain v2 - 7April2015 (2)- edited 02 November 2015 Short
CUI PAPER Bahrain v2 - 7April2015 (2)- edited 02 November 2015 ShortGary Penney
 
CV - Khoi TU
CV - Khoi TUCV - Khoi TU
CV - Khoi TUKhoi Tu
 
SPE 171517_Estimating Probability of Failure _2014_Final
SPE 171517_Estimating Probability of Failure _2014_FinalSPE 171517_Estimating Probability of Failure _2014_Final
SPE 171517_Estimating Probability of Failure _2014_FinalKatrina Carter-Journet
 
Aged aircraft maintenance.
Aged aircraft maintenance.Aged aircraft maintenance.
Aged aircraft maintenance.S P Singh
 
NG3S903 - Electronic Systems - Louise Pennell - Assignment 2 - ESD
NG3S903 - Electronic Systems - Louise Pennell - Assignment 2 - ESDNG3S903 - Electronic Systems - Louise Pennell - Assignment 2 - ESD
NG3S903 - Electronic Systems - Louise Pennell - Assignment 2 - ESDChris Francis
 
A Study of the Root Causes of High Failure Rate of Distribution Transformer -...
A Study of the Root Causes of High Failure Rate of Distribution Transformer -...A Study of the Root Causes of High Failure Rate of Distribution Transformer -...
A Study of the Root Causes of High Failure Rate of Distribution Transformer -...theijes
 
Presentation for MEED - Copy
Presentation for MEED - CopyPresentation for MEED - Copy
Presentation for MEED - CopySenthil Kumar, S
 
Field Failure Analysis of DTH Hammer Bit
Field Failure Analysis of DTH Hammer BitField Failure Analysis of DTH Hammer Bit
Field Failure Analysis of DTH Hammer BitIRJET Journal
 
Root causes of fluid spills from earthmoving plant and equipment: Implication...
Root causes of fluid spills from earthmoving plant and equipment: Implication...Root causes of fluid spills from earthmoving plant and equipment: Implication...
Root causes of fluid spills from earthmoving plant and equipment: Implication...Turlough Guerin GAICD FGIA
 

Similar to Pipeline integrity assessment with LRUT method (20)

Emergency Pipeline Repair Systems, A Global Overview of Best Practice
Emergency Pipeline Repair Systems, A Global Overview of Best PracticeEmergency Pipeline Repair Systems, A Global Overview of Best Practice
Emergency Pipeline Repair Systems, A Global Overview of Best Practice
 
Impact of Crack Length into Pipe Conveying Fluid Utilizing Fast Fourier trans...
Impact of Crack Length into Pipe Conveying Fluid Utilizing Fast Fourier trans...Impact of Crack Length into Pipe Conveying Fluid Utilizing Fast Fourier trans...
Impact of Crack Length into Pipe Conveying Fluid Utilizing Fast Fourier trans...
 
HIPPS
HIPPSHIPPS
HIPPS
 
software Paper published.pdf
software Paper published.pdfsoftware Paper published.pdf
software Paper published.pdf
 
OSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact finalOSEA 2006 - Precom Impact final
OSEA 2006 - Precom Impact final
 
Fitness for Service Assessment of Ageing Pressure Vessel Experiencing Externa...
Fitness for Service Assessment of Ageing Pressure Vessel Experiencing Externa...Fitness for Service Assessment of Ageing Pressure Vessel Experiencing Externa...
Fitness for Service Assessment of Ageing Pressure Vessel Experiencing Externa...
 
CUI PAPER Bahrain v2 - 7April2015 (2)- edited 02 November 2015 Short
CUI PAPER Bahrain v2 - 7April2015 (2)- edited 02 November 2015 ShortCUI PAPER Bahrain v2 - 7April2015 (2)- edited 02 November 2015 Short
CUI PAPER Bahrain v2 - 7April2015 (2)- edited 02 November 2015 Short
 
CV - Khoi TU
CV - Khoi TUCV - Khoi TU
CV - Khoi TU
 
SPE 171517_Estimating Probability of Failure _2014_Final
SPE 171517_Estimating Probability of Failure _2014_FinalSPE 171517_Estimating Probability of Failure _2014_Final
SPE 171517_Estimating Probability of Failure _2014_Final
 
Hydraulic catalogue
Hydraulic catalogueHydraulic catalogue
Hydraulic catalogue
 
Aged aircraft maintenance.
Aged aircraft maintenance.Aged aircraft maintenance.
Aged aircraft maintenance.
 
Pipeline repair techniques
Pipeline repair techniquesPipeline repair techniques
Pipeline repair techniques
 
Report
ReportReport
Report
 
NG3S903 - Electronic Systems - Louise Pennell - Assignment 2 - ESD
NG3S903 - Electronic Systems - Louise Pennell - Assignment 2 - ESDNG3S903 - Electronic Systems - Louise Pennell - Assignment 2 - ESD
NG3S903 - Electronic Systems - Louise Pennell - Assignment 2 - ESD
 
PPT-on-false-air.ppt
PPT-on-false-air.pptPPT-on-false-air.ppt
PPT-on-false-air.ppt
 
A Study of the Root Causes of High Failure Rate of Distribution Transformer -...
A Study of the Root Causes of High Failure Rate of Distribution Transformer -...A Study of the Root Causes of High Failure Rate of Distribution Transformer -...
A Study of the Root Causes of High Failure Rate of Distribution Transformer -...
 
Oil & Gas Maintenance Guide
Oil & Gas Maintenance GuideOil & Gas Maintenance Guide
Oil & Gas Maintenance Guide
 
Presentation for MEED - Copy
Presentation for MEED - CopyPresentation for MEED - Copy
Presentation for MEED - Copy
 
Field Failure Analysis of DTH Hammer Bit
Field Failure Analysis of DTH Hammer BitField Failure Analysis of DTH Hammer Bit
Field Failure Analysis of DTH Hammer Bit
 
Root causes of fluid spills from earthmoving plant and equipment: Implication...
Root causes of fluid spills from earthmoving plant and equipment: Implication...Root causes of fluid spills from earthmoving plant and equipment: Implication...
Root causes of fluid spills from earthmoving plant and equipment: Implication...
 

Recently uploaded

(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 

Recently uploaded (20)

(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 

Pipeline integrity assessment with LRUT method

  • 1. LONG RANGE ULTRASONIC TESTING ( LRUT ) May 1 2020 As a product of transportation facility, pipeline sould be having a good integrity. Pipeline failure means that pipeline can not operate both at some segment/section or all of pipeline segment can not deliver product/service as per their function. Or failure of pipeline also means loss of pipeline integrity for some segment pipeline section or all of segment pipeline. PAULUS KONDA PIPELINE INTEGRITY ASSESSMENT
  • 2. 1 CHAPTER I INTRODUCTION 1.1 PIPELINE INTEGRITY INTRODUCTION As a product of transportation facility, pipeline sould be having a good integrity. Pipeline failure means that pipeline can not operate both at some segment/section or all of pipeline segment can not deliver product/service as per their function. Or failure of pipeline also means loss of pipeline integrity for some segment pipeline section or all of segment pipeline. Pipeline incident refer to gas release from pipeline can be gave consequence like dead/fatality, injury, pollution, or property damage included loss that cause by gas release with huge nominal value (typically value more than $ 50.000). Pipeline leak refer to release of product/service from pipeline that not by design. Consequence of pipeline leak can not cause dead/fatality and or serius injury, but in some cases was happen. Most of pipeline leak consequences are loss of product/service, environtment pollution, property loss and company image (typically value more than $ 50.000). Both pipeline incident and pipeline leak are happing consequence with high level of fatality. Area with these categories usually knows as High Consequence Area – HCA. By definition, pipeline that lacated at location class 3 and 4 are catagorized at High Consequence Area – HCA. These areas were devided on two zones, i.e High Impact Zone (zone with high impact) and Moderate Impact Zone (zone with moderate impact). If these area were located at Potential Impact Zone – PIC than these area catagorized as high impact zone, but if these area were located out of Potential impact Zone – PIC than catagorized as moderate impact zone. But for pipeline that located at location class 1 and 2, high consequence area defined with different manner. In general, Potential Impact Zone having Threshold Radius – TR that calculated base on Potential Impact Radius – PIR. Potential Impact Radius can be entented for the special condition. 1.2 PIPELINE INCIDENT AND LEAK There are some cause as trigger of incident and leak of pipeline, i.e:  Third party damage  Corrosion: o Internal corrosion o External corrosion o Stress corrosion cracking  Construction
  • 3. 2  Manufacturing  Incorrect operation  Equipment  Weather Figure 1 below showing typicall data for pipeline incident at High Consequence Area – HCA. From these data, we can see that most contribution incident for pipeline incident cause by third party damage (around 47% from total cause of incident). It’s mean that to minimize pipeline incident, pipeline owner/operator should be focus to manage and maintaince potential of third party damage, equipment/pipeline it self, construction, incorrect operation, etc. Figure 1 Pipeline Incident at High Consequence Area – HCA catagorized by its cause 1 Figure 2 below showing typicall data for pipeline leak at High Consequence Area – HCA. From these data, we can see that equipment/pipeline it self giving most contribution of pipeline leak, around 57% from total others cause of pipeline leak. It’s mean that to minimize pipeline leak, pipeline owner/operator should be focus to manage and maintain of their equipment/pipeline it self, external corrosion, thrid party damage, construction, etc. Threat of pipeline integrity can be devided as below:  Threat of pipeline integrity that base on time (time dependent), i.e: o External Corrosion o Internal Corrosion o Stress corrosion cracking o 1 Incident Data 2004 – 2007at Amerika, coming from https://primis.phmsa.dot.gov/gasimp/PerformanceMeasures.htm
  • 4. 3 Figure 2 Pipeline Leak at High Consequence Area – HCA catagorized by its cause 2  Threat of pipeline integrity that not base on time (time independent), i.e: o Incorrect operation o Weather related and outside force), i.e:  Thunderclap  Flood and rain  Land movement  Threat of pipeline integrity that related with manufacturing process, fabrication/welding process, and equipment, i.e: o Defect that related with manufacturing process, i.e:  Defect at pipe seam  Defect at the pipe o Fabrication and welding process, i.e:  Weld defect at pipe girth  Weld defect at fabrication  Wrinkle bend or buckle  Damage at coupling and pipe o Equipment:  Damage Gasket O-Ring  Malfunction at control/relief valve  Damage at pump seal / packing 1.3 PROJECT BACKGROUND Pipeline is a pipe system which is designed to bring something like oil, natural gas, or other products that are oil-based long-distance, usually placed above ground or often underground offshore and onshore. As a system, the pipeline must have high integrity and reliability for the system operated. Pipeline who lost their integrity and reliability means if 2 Leak Data 2004 – 2007 at Amerika, coming from dari https://primis.phmsa.dot.gov/gasimp/PerformanceMeasures.htm
  • 5. 4 not ability to operate and is below the minimum requirement allowed by the code / standard or owner specification used. If still ignored by the conditions below minimum requirements, the pipe will someday be a failure at the time later or at the time that was not suspected. As a result of this failure would have broad impact on economic value, safety and human health, and cause disruption to the environment. The cause of failure in the pipeline caused by several factors index, as follows:  Third party damaged index  Design index  Incorrect operation index  Corrosion index The combination of the impact of failure or the consequences of failure (CoF) to the cause of the failure or the probability of failure (PoF) is a risk. The higher of the consequences of failure and the probability of failure in a pipeline means higher risks for the operation. Risk = CoF x PoF Various methods used to mitigate these variables to minimize the risks. To mitigate the consequences of failure should the policies of the management authority of the owner of the pipeline that will impact on all sectors in the company in a long time, these considerations need to be a long time, and complicated. Mitigate the probability of failure is not as complicated as compared to mitigate the consequences of failure, but it also takes preparation. Mitigate the probabilities of failure, as follows:  Supervision and oversight in the initial design fabrication process.  Documenting the design data after completed the fabrication process.  Monitoring and maintaining operational conditions, perform maintenance and repair of facilities in the Right Of Way (ROW) and the pipe itself.
  • 6. 5  Monitoring the condition pipe with a potentially damaged by the activities of third parties as well as create educational programs in the community about hazard potential  Create a plan for inspection at the appropriate time and appropriate method of inspection in accordance with the mode of failure in the pipeline. Related one of the efforts to mitigate probabilities of failure mentioned above is to make an inspection plan with appropriate method, Chevron Pacific Indonesia (CPI) has made an inspection plan in the period 2011/2012 using the method of Long Range Ultrasonic (LRUT) to detect any defects in pipe material caused by corrosion or erosion. For executive jobs LRUT, the CPI has conducted a tender to the contractors. PT. Putra Riau Kemari (PRK), PT. Trihasco Utama (THU), and Techcorr, USA, joined in the consortium appointed as the winner of the tender. With no C 788 493 contract, the consortium running the project will serve the work area CPI. Results from LRUT will be verified with a manual ultrasonic, the data obtained will be reported in this report in engineering calculations to obtain the value of maximum allowable working pressure (MAWP), corrosion rate, as well as the recommendations included suggestions to repair the pipe if it is found that critical area. 1.4 PORPOSE Purpose of the job "Long Range Ultrasonic Testing (LRUT) Project" is to determine the external and internal condition of pipes in the CPI and provide recommendations to the CPI for repair and replacement of pipes when the pipe is not acceptable to operate according to the code / standard that is used. Scope of executive summary report is only for segment PF-12 & 14 Inch Benar 45 to Bekasap GS, with total length is 863.84 meters
  • 7. 6 1.5 WORK ORDER NUMBER This report to be submitted for Work Order/JDE Number: 2218826 with scope of area inspection only for PF-12 and 14 inch –Benar 5 to Benar GS. 1.6 TECHNICAL DATA Area : Benar, SLN Segment/ Length of Pipe : 12 and 14 Inch – Benar 5 to Benar GS / 863.84 meters Fluid Content : Crude Oil Outside Diameter : 12.750 inch and 14 Inch Material Specification : API 5L Grade B Nominal Thickness : 9.525 mm Construction : Aboveground and Road Crossing Design Press/Temp : 257 psi/ 200 o F Operating Press/Temp : 257 psi/ 150 o F The data obtained from the CPI and the CPI has been approved above data if that is the data assumption.
  • 8. 7 CHAPTER II SCOPE OF WORK & EQUIPMENT 2.1. SCOPE OF WORK The scope of work for WO No. 2221124 in the area Sumatra Light North (SLN) Benar, is as follows:  Survey and field data collection  Preparing Standard Operating Procedure (SOP) above ground  Preparing LRUT equipment  Preparing General Work Permit  LRUT analyze data, and classify categories of analysis.  Follow-up and verification, if found anomalies in the results LRUT analysis, using a manual ultrasonic scanning (internal corrosion indication) or visual (external corrosion indication).  Record minimum remaining thickness and reporting result verification data.  Calculating data to determine corrosion rate, MAWP and remaining life.  Recommendation. 2.2. EQUIPMENT & TOOLS Equipment:  1 set LRUT with collar size 8 inch  Thermometer gun infrared  UT Wall thickness : Cygnus  UT Scanning : DMS-2  Global Positioning System (GPS): Garmin Tools:  Gas Detector  Hoe  Shovel  Sandpaper
  • 9. 8 CHAPTER III INSPECTION METHODOLOGY 3.1 PREPARATION OF JOB For this project, there are some of task that included as preparation of job, i.e:  Daily coordination with all of team member before executes the job.  Preparation of working permit every day at site.  Preparation of inspection equipment and tools for this job.  Safety briefing if we execute new work order. 3.2 INITIAL FIELD SURVEY Propose of initial survey is: a. Performing initial general screening propose to know where is pipeline location and road acess as reference of team and equipment mobilization. b. Performing initial visual inspection along the pipeline to know external surface condition of pipeline. c. To know condition of pipeline system protection for underground pipeline, withness land slide potential, free span potential, pipe support condition, etc. 3.3 COLLECTING DOCUMENT Collecting data related with pipeline were perfomed together with CPI counterpart. These data very important to know the history of pipeline design, operation, inspection and maintenance. Related data that we hope can be collected from pipeline owner and using as our reference during analysis and calculation data are:  Alignment Sheet  Data design of pipeline  Historical of inspection report and ROW Survey  Report of last UT Wall Thickness  Maintenance/Repair Record  Operation Report
  • 10. 9  Historical data of repair and pipe replacement  Soil Movement data (if any) 3.4 FIELD DATA COLLECTION 3.4.1 Visual Inspection and UT Wall Thickness Visual inspection performed as method to screening surface condition of pipeline segment. These conventional inspection methods are effective enough to screening of potential damage that probably happen at existing pipeline. The Potential damage included external general corrosion, extrem metal loss, erosion, blisters, dents-gouges- combination dents gauges or pitting / flaw corrosion. UT Wall Thickness performed at every Test point (TP) or Test Location (TL) at 4 location (at 12 o’clock, at 3 o’clock, at 6 o’clock, and at 9 o’clock). But to make sure that LRUT dead zone are also screening, we were performed UT wall thickness inspection forward and backward every 1 ft, but data not recorded due to porpose of inspection only to make sure pipeline condition at LRUT dead zone. If we found any anomalies or indication during that inspection, we will performing direct assessment/investigation on it. Figure 3. LRUT Inspection Detail result of UT Wall Thickness Measurement at every TP or TL for this pipeline can be found at attachment report. 3.4.2 Long Range Ultrasonic Testing (LRUT) Inspection Indications identified on the A-scan plots are evaluated on the basis of a combination of:
  • 11. 10 1. The signal amplitude 2. The directionality of the focused response. This takes into account that large amplitude responses will be from a large cross- sectional area defect. Small defects cannot produce large amplitude reflections. However, the converse is not always true; a small amplitude response does not necessarily mean that the defect is small, as the response may be affected by a number of factors. In order to provide a means of identifying defects which are potentially significant in terms of the integrity of the pipe it is also necessary to examine how localized the response is in terms of the pipe circumference. This may be obtained from the focused tests and is plotted on a polar response chart. To incorporate these changes, some aspects of the interpretation procedure have been altered compared with earlier versions of the Teletest® test procedures: Whereas the indications were previously assessed primarily in terms of amplitude, with the categories being ‘Minor’, ‘Moderate’ and ‘Severe’, the signals are now described as being of Amplitude Category 1, 2 or 3, with Category 3 being the highest. An additional DAC curve has been added to the analysis screen. This is a red line at - 20dB compared with a 100% reflector (equivalent to a pipe end), so that it plots in between the blue weld line (-14dB) and the green 9% reflector line (-26dB). This defines the boundary between Categories 2 and 3 - see below. The additional DAC curve and the areas corresponding to the categories above are shown in Figure 4, below.
  • 12. 11 Figure 4. Schematic of the Teletest A-scan, showing the amplitude categories. Category 1 responses are those which are lower than the green -26dB line (formerly minor). Category 2 responses are those above the -26dB line, but are lower than the new red line at -20dB (formerly Moderate). Category 3 responses exceed the new red -20dB line (these are broadly the same as the previous severe classification, but the limiting amplitude is now better defined. Below the Greenline is category 1, between the green and red line is category 2 and above the red is category 3. The collection of focused data from suspected defects is an integral part of the test regime. The results from focused tests on each defect are analyzed in terms of the directionality of the response. If the polar plot shows a high level of directionality, indicated by a single peak in the plot at one focus angle, it is classed as category 3 (figure 5). This indicates that the defect is highly localized on a narrow part of the circumference, so that it is likely to be deep for given amplitude of response.
  • 13. 12 Figure 5. Category 3 responses from focused tests If the polar plot has two adjacent high amplitude responses it is classed as category 2. This is shown in figure 6. This suggests that the defect is localised, but has some circumferential length. Figure 6. Category 2 responses from focused tests If the polar plot has 3 or more adjacent high amplitude peaks (figure 7) it is classed as category 1. This suggests that it is spread over a wide area of circumference, so that it is likely to be less deep for a given response amplitude. Figure 7. Category 1 response from a focused test
  • 14. 13 Figure 8. Category 0 response from a weld from a focused test The overall classification is obtained by multiplying the two values, amplitude x directionality, obtained from a defect. A score of 3 or greater gives a recommendation for a High priority follow up, a score of 2 gives a Medium priority and a score of 1 gives a low priority. This is summarized in Table 1 below. Table 1. Evaluation Matrix Amplitude Directionality Score Follow up priority 3 3 9 High 3 2 6 High 3 1 3 High 3 0 0 Weld 2 3 6 High 2 2 4 High 2 1 2 Medium 1 3 3 High 1 2 2 Medium 1 1 1 Low 3.4.3 Direct Assessment/Investigation If we found some indication or anomalies base on LRUT Inspection result, that we will perform direct assessment inspection/investigation on it. Investigation will perform by both visual inspection and also UT Scanning at point that indicated any anomalies. Detail direct assessment inspection/investigation inspection can be found on next chapter and also on attachment of this report.
  • 15. 14 3.5 ANALYSIS DATA & CALCULATION After all of inspection data and investigation data completed and available, we will perform analyisis of data and also making calculation base on that data. We are performing analysis for below data: a. Result of initial survey and visual inspection. b. Result of UT Wall Thickness at every TP or TL. c. Result of LRUT Inspection. d. Result of UT Scanning during direct assessment/investigation at indicated anomalies point. And we are also performing calculation base on above data inspection, i.e: a. Calculation of new MAWP. b. Calculation of estimated Corrosion Rate. c. Calculation of Remaining Life. Detail of analysis data and calculation can be found at next chapter and also on attachment of this report. 3.5.1 MAWP Calculation for Internal Corrosion Refer to ANSI B 31.4 Paragraph 403.2.1, Calculation Maximum Allowable Work Pressure (MAWP) based on actual thickness using formula: Where, P = MAWP (psi) S = Maximum Allowable Strength (psi) D = Pipe outside diameter (inch) t = Nominal thickness (inch) E = Longitudinal Joint Factor Corrosion rate calculation API 570 paragraph 7.1.1, using below formula:
  • 16. 15 Where, ipy = corrosion rate (inch per year) t = thickness nominal (inch) ta = minimum actual thickness (inch) Remaining Life, using formula: Where, Rem. Life = Remaining life (years) td = thickness requirement design (inch) tact = minimum actual thickness (inch) 3.5.2 MAWP Calculation for External Corrosion Refer to ANSI B 31.G part 4, Calculation of Maximum Allowable Work Pressure (MAWP) using formula: - Determine strength of corroded area (A or G) Where, L = Length of corroded Area (inch) D = Outside Diameter of Pipe (inch) t = thickness nominal (inch) If A or G less than 4, using below formula:
  • 17. 16 Where, P’ = MAWP Corroded Area (psi) P = Design Pressure based nominal thickness (psi) D = depth of pitting (inch) t = thickness nominal (inch) If A or G greater than 4, using below formula: Where, P’ = MAWP Corroded Area (psi) P = Design Pressure based nominal thickness (psi) 3.6 CONCLUTION & RECOMMENDATION PREPARATION 3.6.1 Conclution The conclusions given in this report is the actual condition of the pipeline after application of above inspection methodology, i.e: initial field survey, visual inspection, UT Wall Thickness, LRUT, and direct assessment (UT Scanning and Depth Gauge if there is pitting corrosion found). 3.6.2 Recommendation Some of the recommendations that will be recommended on this report consider the following:  If Metal loss of pipe less than or maximum 20% of thickness required design.
  • 18. 17 In these conditions, the recommendation given is an inspection plan that considers the results of the calculation of remaining life. Basically, the calculation of remaining life is only for the age-related corrosion condition, while condition base is the result of remaining life multiple confidence rating and is focus on individual pipeline. Thickness measurements should be scheduled based on the calculation of not more than half the remaining life determination.  An area of corrosion with maximum depth greater than 20% but less than or equal to 80% of the wall thickness. In these condition, conducted the evaluation using the ASME B. 31.G, and the corrected thickness plus Corrosion Allowance. If that fails will be recommended to the mounting sleeve type A or composite sleeve temporary.  An area of corrosion with more than 80% of the wall thickness. In these conditions, the pipe shall be removed or repaired. All of these conditions are illustrated in the diagram below:
  • 19. 18 Figure 9. Repair for internal corrosion Figure 10. Repair for external corrosion Detail recommendation will be explained at Chapter V at this report.
  • 20. 19 CHAPTER IV RESULT, ANALYSIS AND CALCULATION 4.1 INITIAL SURVEY & VISUAL INSPECTION RESULT Surveys have been conducted in the area Bekasap, SLN Ø12 and 14 Inch- Benar 5 to Benar GS, with total length 863.84 meters, and getting conditions of the pipeline. The survey results above are used by CPI as reference to issued WO No. 2218826 Survey result base on visual inspection/naked eye inspection during initial survey are: 1. In general, pipeline was constructed above ground 2. Pipeline in coated condition 3. There are not found leak or sleeve or patching. 4. This pipeline segment has 2 road crossing and the protected by casing. 4.2 LONG RANGE ULTRASONIC TESTING (LRUT) RESULT Our main method of inspection for this job is Long Range Ultrasonic Test (LRUT) inspection. Porpose of LRUT inspection are to screening pipeline condition both external and internal condition at the same time. LRUT inspection performed and applied for all of pipeline SLN 12 and 14 Inch Benar 5 to Benar GS, with total length 863.84 meters. Before shooting of LRUT performed, we are devide some Test Point (TP) or Test Location (TL) where LRUT shooting will be done. Because porpose of this job are to screening 100% pipeline condition, than TP/TL second and onward depend on result length of LRUT shooting for first TP/TL. Below, step by step explanation LRUT inspection: 1. Indicated first Test Point (TP) or Test Location (TL). 2. Cleaning location TP/TL, open coating (wrapping tape)/insulation around 30 - 40 cm (if any. 3. Visual inspection at pipeline around TP/TL. 4. Collecting data UT wall thickness at 4 locations (at 12 o’clock, 3 0’clock, 6 o’clock, and 9 0’clock). 5. Install Collar Size Transducer at location that has been cleaning above (Test Point) ; be carefull flow of oil (follow LRUT Expert instruction/sugestion). 6. Install cable to Collar Size Transducer, Compressor Data Logger dan Laptop.
  • 21. 20 7. LRUT expert collecting data at that TP for forward and backward direction. If LRUT expert found high priority (see table 1. Evaluation Matrix above), than we must performing direct assessment/investigation at location were found anomalies/indication. Mostly, indication that should be follow up by direct assessment/investigation are if shooting result indicated found category 2 with ECSL : Estimated Cross Sectional Loss around 9 – 16% from nominal thickness and also indication 3 with ECSL : Estimated Cross Sectional Loss more than 16% from nominal thickness. Some equipment that we are use during perform direct assessment/investigation are Manual UT Thickness, UT Scanning, and Pitch Gauge (for check depth of corrosion and length of corroded area). Below, we can found set up of LRUT Equipment that we were used for this job: Figure 9. Set Up of LRUT Equipment Below (table 3), we can found conclution of LRUT inspection result per TP for segment pipeline SLN Ø 12 and 14 Inch Benar 5 to Benar GS, with total length 863.84 meters, included their each anomalies indication. Table 3. Resume of LRUT Result
  • 22. 21 A G UG R C F wd (m) B wd (m) F wd ( m) B wd ( m ) D (mm) T (mm) L M H External Pitting Corossion -2.46 1.8 - 100 50 Medium Pict 1 External Pitting Corossion -8.14 1.1 - 500 200 Low Pict 2 External Pitting Corossion -9.02 1.6 - 500 200 Low Pict 3 - - External Pitting Corossion -11.86 1.1 - 100 100 Low Pict 4 External Pitting Corossion -22.50 2-2.5 - 200 150 Medium Pict 5 External Pitting Corossion -23.26 1.2 - 100 50 Low Pict 6 External Pitting Corossion +6.75 1.2 - 100 100 Low Pict 7 External Pitting Corossion +10- 13.40 1.6-3.4 - 3400 250 Medium Pict 8 -6.21 - - - - Low -32.94 - - - - Low 3 Good -1.02 - - - - Low External Pitting Corossion -14.18 1.2 - 50 50 Low Pict 9 External Corossion +3.77 2.5 - 2000 200 Medium Picy 10 Good +9.20 - - - - Low Good +12.43 - - - - Low Good +17.24 - - - - Low - - Good +18.79 - - - - Low 680 24 12 Good +24.84 - - - - Low Good +25.49 - - - - Low External Pitting Corossion +27.52 1.7 - 700 200 Low Pict 11 External Pitting Corossion +31.11- 32 1.8-2.7 - 1000 200 Medium Pict 12 External Pitting Corossion 35.69 1 - 50 50 Low Pict 13 External Pitting Corossion +37.18 1 - 50 50 Low Pict 14 External Pitting Corossion -33.19 2.4-3.3 - 1000 200 Medium Pict 15 External Pitting Corossion -40.40 1.4 - 50 50 Low Pict 16 External Pitting Corossion +11.17 1.4 - 50 50 Low Pict 17 External Pitting Corossion +15.17 2 - 50 59 Low Pict 18 External Pitting Corossion +21.77 1.5 - 50 50 Low Pict 19 External Pitting Corossion +26.36 1.5 - 200 200 Low Pict 20 Good -14.27 - - - - Low Good -18.14 - - - - Low - - 907 55.8 20 External Pitting Corossion -26.42 1 - 500 100 Low Pict 21 External Pitting Corossion -36.42 1.2 - 500 200 Low Pict 22 Tack Weld -18.14 - - - - Low Pict 23 6 TL 06 √ - - N 01 41'31.6" E100 59'03.9" Paint 38.90 14.62 - - Category 2 7.50 8.00 709.00 26.80 13.00 External Pitting Corossion -5.75/ -11.49 2-2.5 - 6000 200 Medium Pict 24 7 TL 07 √ N 01 41'33.0" E100 59'02.8" Paint - 6.46 23.49 Category 1 8.70 9.50 1091.00 122.20 20.00 External Pitting Corossion -1.63 1 - 250 70 Low Pict 25 R/C lengh 23.49 M External Pitting Corossion -5.57 1.4-2.2 - 750 1000 Medium Pict 26 External Pitting Corossion +1.40 - '+1.68 1.8 -2.5 - 360 1000 Medium Pict 27 - - 774 34.1 17 External Pitting Corossion +2.30 1.6 -2 - 350 600 Medium Pict 28 External Pitting Corossion +2.80 1.3 -2 - 350 600 Medium Pict 29 External Pitting Corossion +3.40 1 - 750 600 Low Pict 30 9 TL 09 √ - - N 01 41'34.4" E100 59'02.0" Paint 10.16 4.05 No Relevan Indication 7.30 8.00 984.00 55.50 20.00 Good - - - - - Low 262.3 250.28 23.49 - 1 23.49 M 1 TL 01 √ - - N 01 41.332' E 101 59.194' Paint 21.46 - - 15.68 No Relevan Indication 6.32 6.98 984.00 55.50 20.00 Good - - - - - Low 2 TL 02 √ - - N 01 41.322' E 101 59.202' Paint - 52.74 8.54 - No Relevan Indication 6.40 6.70 996.00 57.80 20.00 Good - - - - - Low 3 TL 03 √ - - N 01 41.260' E 101 59.244' Paint 88.46 59.34 - - No Relevan Indication 6.47 6.57 996.00 57.80 20.00 Good - - - - - Low TL 04 √ - - N 01 41.211' E 101 59.278' Paint 50.91 30.63 - - No Relevan Indication 6.55 6.70 1016.00 61.80 20.00 Good - - - - - Low 160.83 142.71 1 24.23 M N o . T est Lo catio n C o nstructio n C o o rdinats P ipeline P ipe C o nditio n T est Length A bo ve gro und T est Length R o ad C ro ssing TL 02 √ - - N 01 41'22.6" E100 59'09.4" Paint 14'' Production Line Benar 5 to Benar GS 1 TL 01 √ - - N 01 41'20.5" E100 59'10.9" Paint 44.7 14.02 10 1076 113.8 20 4 TL 04 √ - - N 01 41'28.5" E100 59'05.8" Paint 8 Good TL 03 √ - - N 01 41'25.4" E100 59'08.0" Paint 46.85 52.34 39.18 47.53 - - No Relevan Indication 7.62 30.33 56.44 Category 1 & 2 7.5 7.7- - Category 1 & 2 7.5 7.9 Paint 45.95 40.77 Category 1 7.6 85 TL 05 √ - - N 01 41'30.5" E100 59'04.6" Paint 6.23 14.05 Category 1 & 2 7.95 8.18 TL 08 √ - - N 01 41'33.1" E100 59'03.0" Total Length Pipe Line 303.54 24.23 Total Test Length Road Crossing Total Road Crossing Total Length Pipe Line 513.1 23.49 Total test Length Road Crossing 12'' Production Line Benar 5 to Benar GS R/C length 24.23M Total Road Crossing Category 1 & 2 8 8.3 A no maly F o to N o . R emark Dist ance f rom TL M etal Lo ss L (mm) W (mm) LR UT C atego ry Indicatio n T hickness M in.(mm) T hickness M ax.(mm) Visual F inding A no maly F inding 598 17.2 8 M A WP co rro ded (psi) R emaining life (year) N ext inspectio n (year) 655 21.8
  • 23. 22 Detail of LRUT result per TL including each their graph and interpretation for segment pipeline Bekasap, SLN; Ø 12 and 14 Inch- Benar 5 to Benar GS, with total length 863.84 meters were described at attachment of this report. Some of anomalies indication that we found for segment pipeline Bekasap, SLN; Ø 12 and 14 Inch Benar 5 to Benar GS, with total length 863.84 meters can be found at Direct Assessment Report LRUT as below: - Category 1 and 2 indication at TL 6 TL 06 - 14" Production Line All of above anomalies indication should be investigated/performing direct assessment to prove what actually happen at that location. 4.3 DIRECT ASSESSMENT/VERIFICATION RESULT Base on data LRUT Result and also data indication of anomalies above, we are performing direct assessment/investigation to make sure that what really happen at that point. Result of investigation describe below:
  • 24. 23 Table 3. Verification Result No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 TL 08 Forward 2.80 meter EXTERNAL COROSSION AT LOCATION FROM TL 08 FORWARD 2.80 M Depth = 1.3 - 2 mm, length 350 mm x 600 mm, position of defect = 3 - 7 o’clock TL 08 Forward 3.40 meter EXTERNAL COROSSION AT LOCATION FROM TL 08 FORWARD 3.40 M Depth = 1mm, length 750 mm x 600 mm, position of defect = 3 - 9 o’clock TL 08 Forward 1.40 - 1.68 meter EXTERNAL COROSSION AT LOCATION FROM TL 08 FORWARD 1.40 - 1.68 M Depth = 1.8 - 2.5 mm, length 360 mm x 1000 mm, position of defect = 3 - 7 o’clock TL 08 Forward 2.30 meter EXTERNAL COROSSION AT LOCATION FROM TL 08 FORWARD 2.30 M Depth = 1.6 - 2 mm, length 350 mm x 600 mm, position of defect = 3 - 7 o’clock Ø 12'' & 14'' PRODUCTION LINE BENAR 5 TO BENAR GS TL 07 TL 07 Backward 1.63 meter EXTERNAL COROSSION AT LOCATION FROM TL 07 BACKWARD 1.63 M Depth = 1mm, length 250 mm x 70 mm, position of defect = 6 o’clock TL 08 Backward 5.57 meter EXTERNAL COROSSION AT LOCATION FROM TL 08 BACKWARD 5.57 M Depth = 1.4 - 2.2 mm, length 750 mm x 1000 mm, position of defect = 3 - 9 o’clock Ø 12'' & 14'' PRODUCTION LINE BENAR 5 TO BENAR GS TL 08 TL 05 Backward 18.14 meter TAG WELD AT LOCATION FROM TL 05 BACKWARD 18.14 Ø 12'' & 14'' PRODUCTION LINE BENAR 5 TO BENAR GS TL 06 TL 06 Backward 18.14 meter EXTERNAL COROSSION AT LOCATION FROM TL 06 BACKWARD 5.75 - 11.49 M Depth = 2 - 2.5 mm, length 6000 mm x 200 mm, position of defect = 4 - 6 o’clock Ø 12'' & 14'' PRODUCTION LINE BENAR 5 TO BENAR GS TL 05 TL 05 Backward 26.42 meter EXTERNAL COROSSION AT LOCATION FROM TL 05 BACKWARD 26.42 M Depth = 1mm, length 500 mm x 100 mm, position of defect = 6 o’clock TL 05 Backward 36.42 meter EXTERNAL COROSSION AT LOCATION FROM TL 05 BACKWARD 36.42 M Depth = 1.2 mm, length 500 mm x 200 mm, position of defect = 5 - 8 o’clock TL 04 Forward 21.77 meter EXTERNAL COROSSION AT LOCATION FROM TL 04 FORWARD 21.77 M Depth = 1.5 mm, length 50 mm x 50 mm, position of defect = 6 o’clock TL 04 Forward 26.36 meter EXTERNAL COROSSION AT LOCATION FROM TL 04 FORWARD 26.36 M Depth = 1.5 mm, length 200 mm x 200 mm, position of defect = 4 - 6 o’clock Ø 12'' & 14'' PRODUCTION LINE BENAR 5 TO BENAR GS TL 04 TL 04 Forward 11.17 meter EXTERNAL COROSSION AT LOCATION FROM TL 04 FORWARD 11.17 M Depth = 1.4 mm, length 50 mm x 50 mm, position of defect = 6 o’clock TL 04 Forward 15.17 meter EXTERNAL COROSSION AT LOCATION FROM TL 04 FORWARD 15.17 M Depth = 2 mm, length 50 mm x 50 mm, position of defect = 7 o’clock TL 04 Backward 33.19 meter EXTERNAL COROSSION AT LOCATION FROM TL 04 BACKWARD 33.19 M Depth = 2.4 - 3.3 mm, length 1000 mm x 200 mm, position of defect = 6 o’clock TL 04 Backward 40.40 meter EXTERNAL COROSSION AT LOCATION FROM TL 04 BACKWARD 40.40 M Depth = 1.4 mm, length 50 mm x 50 mm, position of defect = 6 o’clock TL 03 Forward 35.69 meter EXTERNAL COROSSION AT LOCATION FROM TL 03 FORWARD 35.69 M Depth = 1mm, length 50 mm x 50mm, position of defect = 6 o’clock TL 03 Forward 37.18 meter EXTERNAL COROSSION AT LOCATION FROM TL 03 FORWARD 37.18 M Depth = 1mm, length 50 mm x 50 mm, position of defect = 9 o’clock Ø 12'' & 14'' PRODUCTION LINE BENAR 5 TO BENAR GS TL 03 EXTERNAL COROSSION AT LOCATION FROM TL 03 FORWARD 27.52 M Depth = 1.7 mm, length 700mm x 200mm, position of defect = 3 - 9 o’clock TL 03 Forward 31.11 meter EXTERNAL COROSSION AT LOCATION FROM TL 03 FORWARD 31.11M Depth = 1.8 - 2.7 mm, length 1000mm x 200mm, position of defect = 6 o’clock TL.01 Ø 12'' & 14'' PRODUCTION LINE BENAR 5 TO BENAR GS TL 03 Forward 3.77 meter INTERNAL COROSSION AT LOCATION FROM TL 03 FORWARD 3.77 M Depth = 2.5 mm, length 2000mm x 200mm, position of defect = 5 - 7 o’clock TL 01 Forward 10 - 13.40 meter EXTERNAL CORROSION AT LOCATION FROM TL 01 BACKWARD 9.02 M Depth = 1.6 mm, length 500 mm x 200mm , position of defect = 6 o’clock EXTERNAL CORROSION AT LOCATION FROM TL 01 BACKWARD 11.86 M Depth = 1.1mm, length 100 mm x 100mm , position of defect = 6 o’clock EXTERNAL CORROSION AT LOCATION FROM TL 01 BACKWARD 22.50 M Depth = 2 - 2.5 mm, length 200 mm x 150mm , position of defect = 7 o’clock EXTERNAL CORROSION AT LOCATION FROM TL 01 BACKWARD 23.26 M Depth = 1.2 mm, length 100 mm x 50mm , position of defect = 6 o’clock EXTERNAL CORROSION AT LOCATION FROM TL 01 FOWARD 6.75 M Depth = 1.2 mm, length 100 mm x 100mm , position of defect = 6 o’clock EXTERNAL CORROSION AT LOCATION FROM TL 01 BACKWARD 8.14 M Depth = 1.1mm, length 500 mm x 200mm , position of defect = 6 o’clock EXTERNAL COROSSION AT LOCATION FROM TL 03 FORWARD 14.18 M Depth = 1.2 mm, length 50mm x 50mm, position of defect = 7 o’clock TL 01 Backward 9.02 meter TL 01 Backward 11.86 meter TL 01 Backward 22.50 meter TL 01 Backward 23.26 meter TL 01 Forward 6.75 meter LINE NUMBER EXTERNAL CORROSION AT LOCATION FROM TL 01 BACKWARD 2.46 M Depth = 1.8 mm, length 100 mm x 150mm , position of defect = 6 o’clock TL 01 Backward 8.14 meter TL 01 Backward 2.46 meter TL 03 Forward 27.52 meter Ø 12'' & 14'' PRODUCTION LINE BENAR 5 TO BENAR GS TL 08 TL NUMBER DISTANCES FROM TEST LOCATION REMARK EXTERNAL CORROSION AT LOCATION FROM TL 01 FOWARD 10 - 13.40 M Depth = 1.6 -3.4 mm, length 3400 mm x 250mm , position of defect = 6 o’clock TL 03 Backward 14.18 meter
  • 25. 24 Detail investigation report can be founded at attachment of this executive summary report. 4.4 ANALYSIS DATA AND CALCULATION In Minas Area at the Segment Pipe Ø 12 and 14 Inch – Benar 5 to Benar GS, with total length 864.36 meters has been carried out total 13 shooting LRUT at Test Point (TP) or Test Location (TL). In this segment has founded indications of anomalies at 7 test locations. Base on design basis data that have been collected together with CPI counterpart, data result of UT Wall Thickness and LRUT, and also result of investigation at corroded area of pipeline, we are continuing to making calculation of new MAWP, estimated Corrosion Rate and Remaining Life of segment pipeline Ø 12 and 14 Inch – Benar 5 to Benar GS. Base on result, minimum remaining thickness was found at corroded location at TL 4 backward 33.19 meters is 4.4 mm or depth of external corrosion is 3.3 mm. Refer to above data, design data and operational data as data input and refer to ANSI/ASME B 31.4 and ANSI/ASME B 31G, than we are making MAWP calculation based on actual minimum thickness. Using below template, we are found new MAWP are 598 psi. MAWP calculation results seen in the table below: Table 5. Verification Result No Test Location No. Thickness Min. Req. (mm) Design Press (psi) MAWP Nom. Thickness (psi) MAWP Corroded Condt (psi) Corrosion Rate (mm/Year) Rem. Life (years) Next Inspection 1 14" - TL01 1.8 257 1350 655 0.129 21.8 10 2 TL02 1.8 257 1350 1076 0.051 113.8 20 3 TL03 1.8 257 1350 680 0.124 24 12 4 TL04 1.8 257 1350 598 0.139 17.2 8 5 TL05 1.8 257 1350 907 0.081 55.8 20 6 TL06 1.8 257 1350 709 0.119 26.8 13 7 TL07 1.8 257 1350 1091 0.048 122.2 20 8 TL08 1.8 257 1350 774 0.106 34.1 17 9 12" - TL 01 1.8 257 1350 984 0.083 55.5 20 10 TL02 1.8 257 1350 996 0.081 57.8 20 11 TL03 1.8 257 1350 996 0.081 57.8 20 12 TL04 1.8 257 1350 1016 0.078 61.8 20
  • 26. 25 Detail MAWP calculation can be found on below template figure: I. Line Number Data : Line Number : PF- 14'' - Benar 5 to Benar GS Material Specification : GRB ERW Content : Oil Long'nal Joint Fact. (E) : 1.00 Type of Services : PIPELINE Nominal Thickness (t) : 0.375 Inch Operating Pressure : 257 Psi Actual Thickness (ta) : 0.295 Inch Operating Temperature : 150 o F / 66 O C Depth of Localized Pitting (d) : 0.209 Inch (at pit) Pipe Nominal Diameter : 14 inch Remaining thickness : 0.166 Inch Pipe Out Side Diameter : 14.000 inch Thickness Lost (FromNom.) : 55.73 % Test Location : TL4-33.19 II. Calculation : (Refer to ANSI/ASME B31.4) ANSI B 31.4 Paragraph 403.2.1 MaximumAllowable Strength (S) = 35000 psi (See Table 402.3.1(a) for material being used) Maximum Allowable Working Pressure (MAWP) basedon Nominal Thickness is : 2 x S x t x E x 0.72 2 x 35000 x 0.375 x 1.00 x 0.72 P = --------------------------------------------- = --------------------------------------------------------------------------- = Psi D 14.00 MAWP for pipe basedon minimum actual thickness is : 2 x S x ta x E x 0.72 2 x 35000 x 0.166 x 1.00 x 0.72 P = -------------------------------------------- = --------------------------------------------------------------------------- = Psi D 14.00 Corrosion rate API 570 paragraph 7.1.1 t - ta 0.375 - 0.166 ipy = ---------------- = --------------------------------- = inch/year life time 38 Remaining life : tact - td 0.166 - 0.071 Rem. life = -------------------------- = ------------------------------ = year = months Corrosion rate CONCLUSION : Based on above Calculation, the MAWP for the pipe is 598 which is Higher than operating Pressure of psi. and Higher than design pressure of psi 17.2 206.4 257 0.0055 0.0055 PIPE CALCULATION SHEET FACILITYENGINEERING & INSPECTION 1350 598 psi 257 To make calculation of remaining life, corrosion rate dan tmin we are making asumption that derating pressure are = 257 psi. From calculation that refer to ANSI/ASME B 31G, we are found below result: a. Remaining Life : 17.2 years b. Corrosion Rate : 0,0055 inch/years = 0.139mm/years
  • 27. 26 CHAPTER V CONCLUTION AND RECOMMENDATION 5.1 CONCLUTION There are some conclution that can be found during our inspection, analysis and calculation data for segment Ø 12 and 14 Inch – Benar 5 to Benar GS, with total length 864.36 meters, i.e: a. It has been found category 1 and 2 with medium anomalies finding relevan indication at 5 Test location on pipe Ø 14 Inch Benar 5 to Benar GS, with the types of damage are:  External corrosion at TL 1 with maximum depth 3.4 mm, location 10 – 13.4 meter forward from TL 1  External corrosion at TL 03 with maximum depth 2.5 mm, location 3.77 – 5.77 mater forward from TL 03  External corrosion at TL 04 with maximum depth 3.3 mm, location 33.19 – 34.19 meter backward from TL 04  External corrosion at TL 06 with maximum depth 2.5 mm, location 5.75 – 11.49 meter backward from TL 06  External corrosion at TL 08 with maximum depth 2.5 mm, location 1.4 – 1.68 meter forward from TL 08 b. Base on calculation the data from the verification findings, and in the external corroded conditions, pipeline segments Ø 12 and 14 Inch – Benar 5 to Benar GS is still allowed to operate with pressure up to 598 psi. c. Corrosion Rate at the pipeline segments Ø 12 and 14 Inch – Benar 5 to Benar GS is 0.00547 mm/year = 0.139 mm/years and remaing life time is 17.2 years. d. Pipe condition is Medium anomali finding, with total lenght of corroded pipe 26.889 meters or approximately 3.1 % of the overall segment length of 864.36 meters, with minimum thickness is 4.4 mm
  • 28. 27 5.2 RECOMMENDATION Some recommendation that can be proposed to CPI as reference to mitigate the problem that were be found during inspection, analysis, and calculation data for segment Ø 12 and 14 Inch – Benar 5 to Benar GS with total length 863.84meters, i.e: 5.2.1. Repaint In the flow chart in figure 10. above, the first analysis is to calculate the ratio between the depth of pitting and nominal thikness (d/t), the results in this segment is still below 80%, with a minimum of metal loss 10.5 % and maximum metal loss 53 % External corrosion occured in this segment approximately 10 % of the lenght , to avoid futher damaged, then we recommend to do clean up and repaint on the location of the pipe as follows: 1. At a distance of 13 meters forward to 23 26 backward from datum TL 01 2. At a distance of 27 meters to 37 meters forward from datum TL 03 3. At a distance of 33 meters to 34 meters Backward from datum TL 4 4. At a distance of 5.7 meters to 11.49 meters backward from datum TL 06 5. At a distance of 2.8 meters forward to 5.57 meters backward from datum TL 08 5.2.2. Plan and Method Inspection Based on a calculation of the remaining thickness of the pipe, the remaining period of this pipe, was 17.2 years. Refer to API 570, an inspection plan at least half of remaining life. Planning the next inspection is recommended 8 years or due date inspection conducted in June 2019.
  • 29. 28 While the method of inspection, as follows: a. Visual Inspection. Perform visual inspection on bottom of pipe section that was found defective in LRUT, to ensure the occurrence of external corrosion. b. Ultrasonic Wall Thickness Perform wall thickness measurement at critical location: 1 Bend Pipe
  • 30. 29 Area 1 at least Sq Ft Flow fluid Direction and flow inspection Flow fluid Direction and flow inspection Area 1 at least Sq Ft Weld joint 2 Straight pipe After Bend at least 1 sq ft area 3 Every straight stright pipe after joint weld at least 1 sq ft area
  • 31. Long Range Ultrasonic Testing Chevron Pasific Indonesia Under ground Road crossing Above ground
  • 32. Long range ultrasonic testing A scan graph road crossing
  • 33. Long range ultrasonic testing at Road crossing/under ground Result of LRUT at area road crossing founded 3 anomaly Category 1 and 1 anomaly category 2 Direct verification by UT flaw detector is found external corrosion at location 3 – 9 o’clock Dimension of corrosion. Depth = 4 mm Length = 4.8 meter Width = 250 mm
  • 34. Long range ultrasonic testing A scan graph Above ground Jangkauan LRUT ± 200 Meter
  • 35. Long range ultrasonic testing A scan graph Above ground Jangkauan LRUT 12 Meter
  • 36. Long range ultrasonic testing at Above ground Ø 8 Inch Gas Line Petani GS Result of LRUT at area above gound founded 10 anomaly Category 3 Direct verification by UT flaw detector is found Internal corrosion at location on circular pipe. With depth maximum corrosion is 4 mm. Remaining thickness of material Is 2.5 mm.
  • 37. Inspection finding summary report Long Range Ultrasonic Testing sample report anomaly category medium ( yellow ) and High ( Red )
  • 38. Recommendation for sleeve Long Range Ultrasonic Testing Full Encirclement sleeve due to internal corrosion
  • 39. Long range ultrasonic testing Method Repair with Half sleeve Half sleeve on segment 24 Inch production line at area 12 due to internal corrosion.
  • 40. Owner / User: Chevron Pasific Indonesia Pipe Identification : 12'' & 14'' Production Line Benar 5 to Benar GS Service : Crude Oil Nominal Diameter : 14.00 & 12.00 Drawing No. : - Thickness Nominal : 9.35 Periode Inspection: 23 May - 27 May 2011 Material : API 5L Gr.B Location Area: BENAR Field, SLN LRUT Level 2 : Dhirendra/Ashish Matre Assisten Operator : Romi Hendra/Isa AG UG RC Fwd (m) Bwd (m) Fwd ( m) Bwd ( m ) D (mm) T (mm) L M H External Pitting Corossion -2.46 1,8 - 100 50 Medium Pict 1 External Pitting Corossion -8.14 1,1 - 500 200 Low Pict 2 External Pitting Corossion -9.02 1,6 - 500 200 Low Pict 3 - - External Pitting Corossion -11.86 1,1 - 100 100 Low Pict 4 External Pitting Corossion -22.50 2-2.5 - 200 150 Low Pict 5 External Pitting Corossion -23.26 1,2 - 100 50 Low Pict 6 External Pitting Corossion +6.75 1,2 - 100 100 Low Pict 7 External Pitting Corossion +10-13.40 1.6-3.4 - 3400 250 Medium Pict 8 -6.21 - - - - Low -32.94 - - - - Low 3 Good -1.02 - - - - Low External Pitting Corossion -14.18 1,2 - 50 50 Low Pict 9 Internal Corossion +3.77 2,5 - 2000 200 Low Picy 10 Good +9.20 - - - - Low Good +12.43 - - - - Low Good +17.24 - - - - Low - - Good +18.79 - - - - Low Good +24.84 - - - - Low Good +25.49 - - - - Low External Pitting Corossion +27.52 1,7 - 700 200 Low Pict 11 External Pitting Corossion +31.11-32 1.8-2.7 - 1000 200 Medium Pict 12 External Pitting Corossion 35,69 1 - 50 50 Low Pict 13 External Pitting Corossion +37.18 1 - 50 50 Low Pict 14 External Pitting Corossion -33.19 2.4-3.3 - 1000 200 Medium Pict 15 External Pitting Corossion -40.40 1,4 - 50 50 Low Pict 16 External Pitting Corossion +11.17 1,4 - 50 50 Low Pict 17 External Pitting Corossion +15.17 2 - 50 59 Low Pict 18 INSPECTION FINDING SUMMARY LONG RANGE ULTRASONIC TEST Work Order No. : 2221124 No. Test Location Coordinats Pipeline Pipe Condition Paint 44,7 14,02 Category 1 & 2 8 8,3 Anomaly Foto No. Remark 1 TL 01 √ - - N 01 41'20.5" E 100 59'10.9" LRUT Category Indication Thickness Min.(mm) Thickness Max.(mm) Visual Finding Good TL 03 √ - - N 01 41'25.4" E 100 59'08.0" Paint 46,85 52,34 Paint 39,18 47,53 No Relevan Indication 7,6 8TL 02 √ - Construction Test Length Above ground Distance from TL - N 01 41'22.6" E 100 59'09.4" Category 1 & 2 7,5 7,9 4 TL 04 √ - - N 01 41'28.5" E 100 59'05.8" Paint 30,33 56,44 Category 1 & 2 7,5 7,7 - - - - 2 Test Length Road Crossing 14'' Production Line Benar 5 to Benar GS Metal Loss L (mm) W (mm) Anomaly Finding
  • 41. Owner / User: Chevron Pasific Indonesia Pipe Identification : 12'' & 14'' Production Line Benar 5 to Benar GS Service : Crude Oil Nominal Diameter : 14.00 & 12.00 Drawing No. : - Thickness Nominal : 9.35 Periode Inspection: 23 May - 27 May 2011 Material : API 5L Gr.B Location Area: BENAR Field, SLN LRUT Level 2 : Dhirendra/Ashish Matre Assisten Operator : Romi Hendra/Isa AG UG RC Fwd (m) Bwd (m) Fwd ( m) Bwd ( m ) D (mm) T (mm) L M H INSPECTION FINDING SUMMARY LONG RANGE ULTRASONIC TEST Work Order No. : 2221124 No. Test Location Coordinats Pipeline Pipe Condition Anomaly Foto No. Remark LRUT Category Indication Thickness Min.(mm) Thickness Max.(mm) Visual Finding Construction Test Length Above ground Distance from TL Test Length Road Crossing Metal Loss L (mm) W (mm) Anomaly Finding External Pitting Corossion +21.77 1,5 - 50 50 Low Pict 19 External Pitting Corossion +26.36 1,5 - 200 200 Low Pict 20 Good -14.27 - - - - Low Good -18.14 - - - - Low - - External Pitting Corossion -26.42 1 - 500 100 Low Pict 21 External Pitting Corossion -36.42 1,2 - 500 200 Low Pict 22 Tack Weld -18.14 - - - - Low Pict 23 6 TL 06 √ - - N 01 41'31.6" E 100 59'03.9" Paint 38,90 14,62 - - Category 2 7,50 8,00 External Pitting Corossion -5.75/ -11.49 2-2.5 - 6000 200 Medium Pict 24 7 TL 07 √ N 01 41'33.0" E 100 59'02.8" Paint - 6,46 23,49 Category 1 8,70 9,50 External Pitting Corossion -1.63 1 - 250 70 Low Pict 25 R/C lengh 23.49 M External Pitting Corossion -5.57 1.4-2.2 - 750 1000 Medium Pict 26 External Pitting Corossion +1.40 - '+1.68 1.8 - 2.5 - 360 1000 Medium Pict 27 - - External Pitting Corossion +2.30 1.6 - 2 - 350 600 Medium Pict 28 External Pitting Corossion +2.80 1.3 - 2 - 350 600 Medium Pict 29 External Pitting Corossion +3.40 1 - 750 600 Low Pict 30 9 TL 09 √ - - N 01 41'34.4" E 100 59'02.0" Paint 10,16 4,05 No Relevan Indication 7,30 8,00 Good - - - - - Low 262,3 250,28 23,49 - 1 23.49 M 1 TL 01 √ - - N 01 41.332' E 101 59.194' Paint 21,46 - - 15,68 No Relevan Indication 6,32 6,98 Good - - - - - Low 2 TL 02 √ - - N 01 41.322' E 101 59.202' Paint - 52,74 8,54 - No Relevan Indication 6,40 6,70 Good - - - - - Low 3 TL 03 √ - - N 01 41.260' E 101 59.244' Paint 88,46 59,34 - - No Relevan Indication 6,47 6,57 Good - - - - - Low TL 04 √ - - N 01 41.211' E 101 59.278' Paint 50,91 30,63 - - No Relevan Indication 6,55 6,70 Good - - - - - Low 160,83 142,71 1 24.23 M LOW : metal lost less than 20 % nominal thickness D : Depth MEDIUM : metal lost more than 20 % and below 80% nominal thickness T : Thickness HIGH : metal lost more than 80% nominal thickness L : Length Note : W: Width Duri, June 2011 Prepared by Paulus Konda R/C length 24.23M 4 TL 04 √ - - N 01 41'28.5" E 100 59'05.8" Paint 30,33 56,44 Category 1 & 2 7,5 7,7 √ - - Total Test Length Road Crossing 8 √ - - Total Length Pipe Line 512,58 23,49 Total Road Crossing Total test Length Road Crossing Category 1 & 2 7,95 8,1 Total Road Crossing 24,23 PT.Chevron Pasific Indonesia Kuswantoro Basuki 5 TL 05 8 TL 08 N 01 41'33.1" E 100 59'03.0" Paint 6,23 14,05 N 01 41'30.5" E 100 59'04.6" Paint 45,95 40,77 Category 1 7,6 12'' Production Line Benar 5 to Benar GS 303,54 Acknowledge by Approved by Total Length Pipe Line
  • 42. Anomaly Pictures per Test Location Ø 12'' & 14'' Production Line Benar 5 to Benar GS No. Test Location Finding Picture 1 TL 01 EXTERNAL PITTING CORROSION AT LOCATION FROM TL 01 BACKWARD 2,46 M Depth = 1.8 mm, length 100 mm x 150 mm, position of defect = 6 o’clock 2 EXTERNAL PITTING CORROSION AT LOCATION FROM TL 01 BACKWARD 8.14 M Depth = 1.1 mm, length 500 mm x 200 mm, position of defect = 6 o’clock 3 EXTERNAL PITTING CORROSION AT LOCATION FROM TL 01 BACKWARD 9.02 M Depth = 1.6 mm, length 500 mm x 200 mm, position of defect = 6 o’clock 4 EXTERNAL PITTING CORROSION AT LOCATION FROM TL 01 BACKWARD 11.86 M Depth = 1.1 mm, length 100 mm x 100 mm, position of defect = 6 o’clock 5 EXTERNAL PITTING CORROSION AT LOCATION FROM TL 01 BACKWARD 22.50 M Depth = 2-2.5 mm, length 200 mm x 150 mm, position of defect = 7 o’clock Prepared by Paulus Konda
  • 43. Anomaly Pictures per Test Location Ø 12'' & 14'' Production Line Benar 5 to Benar GS No. Test Location Finding Picture 6 TL 01 EXTERNAL PITTING CORROSION AT LOCATION FROM TL 01 BACKWARD 23.26 M Depth = 1.2 mm, length 100 mm x 50 mm, position of defect = 6 o’clock 7 EXTERNAL PITTING CORROSION AT LOCATION FROM TL 01 FORWARD 6.75M Depth = 1.2 mm, length 100 mm x 100 mm, position of defect = 6 o’clock 8 EXTERNAL PITTING CORROSION AT LOCATION FROM TL 01 FORWARD 10 – 13.40 M Depth = 1.6 – 3.4 mm, length 3400 mm x 250 mm, position of defect = 6 o’clock 9 TL 03 EXTERNAL PITTING CORROSION AT LOCATION FROM TL 03 BACKWARD 14.18 M Depth = 1.2 mm, length 50 mm x 50 mm, position of defect = 7 o’clock 10 EXTERNAL CORROSION AT LOCATION FROM TL 03 FORWARD 3.77 M Depth = 2.5 mm, length 2000 mm x 200 mm, position of defect = 5 - 7 o’clock Prepared by Paulus Konda
  • 44. Owner / User : Chevron Pasific Indonesia Pipe Identification : 12'' & 14'' Production Line Benar 5 to Benar GS Service : Crude Oil Nominal Diameter : 12.00 & 14.00 Inch Drawing No. : - Thickness Nominal : 9.525 mm Periode Inspection: 23 May - 27 May 2011 Material : API 5L Gr.B Location Area : Benar Field, SLN LRUT Level 2 : dhirendra/Ashish Matre Assisten Operator : Romi Hendra/Isa No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 TABLE OF ANOMALIES LONG RANGE ULTRASONIC TEST Work Order No. : 2221121 TL NUMBER DISTANCES FROM TEST LOCATION REMARK EXTERNAL CORROSION AT LOCATION FROM TL 01 FOWARD 10 - 13.40 M Depth = 1.6 -3.4 mm, length 3400 mm x 250mm , position of defect = 6 o’clock TL 03 Backward 14.18 meter LINE NUMBER EXTERNAL CORROSION AT LOCATION FROM TL 01 BACKWARD 2.46 M Depth = 1.8 mm, length 100 mm x 150mm , position of defect = 6 o’clock TL 01 Backward 8.14 meter TL 01 Backward 2.46 meter TL 03 Forward 27.52 meter EXTERNAL CORROSION AT LOCATION FROM TL 01 BACKWARD 8.14 M Depth = 1.1 mm, length 500 mm x 200mm , position of defect = 6 o’clock EXTERNAL COROSSION AT LOCATION FROM TL 03 FORWARD 14.18 M Depth = 1.2 mm, length 50mm x 50mm, position of defect = 7 o’clock TL 01 Backward 9.02 meter TL 01 Backward 11.86 meter TL 01 Backward 22.50 meter TL 01 Backward 23.26 meter TL 01 Forward 6.75 meter TL.01 Ø 12'' & 14'' PRODUCTION LINE BENAR 5 TO BENAR GS TL 03 Forward 3.77 meter INTERNAL COROSSION AT LOCATION FROM TL 03 FORWARD 3.77 M Depth = 2.5 mm, length 2000mm x 200mm, position of defect = 5 - 7 o’clock TL 01 Forward 10 - 13.40 meter EXTERNAL CORROSION AT LOCATION FROM TL 01 BACKWARD 9.02 M Depth = 1.6 mm, length 500 mm x 200mm , position of defect = 6 o’clock EXTERNAL CORROSION AT LOCATION FROM TL 01 BACKWARD 11.86 M Depth = 1.1 mm, length 100 mm x 100mm , position of defect = 6 o’clock EXTERNAL CORROSION AT LOCATION FROM TL 01 BACKWARD 22.50 M Depth = 2 - 2.5 mm, length 200 mm x 150mm , position of defect = 7 o’clock EXTERNAL CORROSION AT LOCATION FROM TL 01 BACKWARD 23.26 M Depth = 1.2 mm, length 100 mm x 50mm , position of defect = 6 o’clock EXTERNAL CORROSION AT LOCATION FROM TL 01 FOWARD 6.75 M Depth = 1.2 mm, length 100 mm x 100mm , position of defect = 6 o’clock TL 03 Forward 35.69 meter EXTERNAL COROSSION AT LOCATION FROM TL 03 FORWARD 35.69 M Depth = 1 mm, length 50 mm x 50mm, position of defect = 6 o’clock TL 03 Forward 37.18 meter EXTERNAL COROSSION AT LOCATION FROM TL 03 FORWARD 37.18 M Depth = 1 mm, length 50 mm x 50 mm, position of defect = 9 o’clock Ø 12'' & 14'' PRODUCTION LINE BENAR 5 TO BENAR GS TL 03 EXTERNAL COROSSION AT LOCATION FROM TL 03 FORWARD 27.52 M Depth = 1.7 mm, length 700mm x 200mm, position of defect = 3 - 9 o’clock TL 03 Forward 31.11 meter EXTERNAL COROSSION AT LOCATION FROM TL 03 FORWARD 31.11 M Depth = 1.8 - 2.7 mm, length 1000mm x 200mm, position of defect = 6 o’clock
  • 45. 23 May - 27 May 2011 Pipe Elbow Tee Redc DIA (inch) Above Ground Lay Down Under Groun d Good Corr Sleeve Clamp Isolatio n Condom Ø 12'' - Benar 5 -To Benar GS 1 v v - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 2 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 3 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 4 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 5 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 6 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 7 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 8 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 9 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 10 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 11 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 12 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 13 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 14 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 15 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 16 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 17 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 18 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 19 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 20 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 21 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 22 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 23 v - - - 12 v - - v - - - - - - Ø 12'' - Benar 5 -To Benar GS 24 v v - - 12 - - v v - - - - - Ø 12'' - Benar 5 -To Benar GS 25 v v - - 12 - - v v - - - - - Road crossing 1 CONDITION PIPE Visual Inspection at Ø 12 " and 14 " Benar 58 to Benar GS REMARKSSERVICE LINE WD MATERIAL POSITION PIPE
  • 46. I. Line Number Data : Line Number : PF - 14'' - Benar 5 to Benar GS Material Specification : GRB ERW Content : Oil Long'nal Joint Fact. (E) : 1,00 Type of Services : PIPELINE Nominal Thickness (t) : 0,375 Inch Operating Pressure : 257 Psi Actual Thickness (ta) : 0,315 Inch Operating Temperature : 150 o F / 66 O C Depth of Localized Pitting (d) : 0,193 Inch (at pit) Pipe Nominal Diameter : 14 inch Remaining thickness : 0,182 Inch Pipe Out Side Diameter : 14,000 inch Thickness Lost (From Nom.) : 51,47 % Test Location : TL 1 II. Calculation : (Refer to ANSI/ASME B31.4) ANSI B 31.4 Paragraph 403.2.1 Maximum Allowable Strength (S) = 35000 psi (See Table 402.3.1(a) for material being used) Maximum Allowable Working Pressure (MAWP) based on Nominal Thickness is : 2 x S x t x E x 0.72 2 x 35000 x 0,375 x 1,00 x 0,72 P = --------------------------------------------- = --------------------------------------------------------------------------- = Psi D 14,00 MAWP for pipe based on minimum actual thickness is : 2 x S x ta x E x 0.72 2 x 35000 x 0,182 x 1,00 x 0,72 P = -------------------------------------------- = --------------------------------------------------------------------------- = Psi D 14,00 Corrosion rate API 570 paragraph 7.1.1 t - ta 0,375 - 0,182 ipy = ---------------- = --------------------------------- = inch/year life time 38 Remaining life : tact - td 0,182 - 0,071 Rem. life = -------------------------- = ------------------------------ = year = months Corrosion rate CONCLUSION : Based on above Calculation, the MAWP for the pipe is 655 which is Higher than operating Pressure of psi. and Higher than design pressure of psi Duri Prepared by: Approved by Kuswantoro Basuki Pipeline Inspector Project Manager PIPE CALCULATION SHEET FACILITY ENGINEERING & INSPECTION 1350 655 Paulus Konda May 1, 2020 psi 257 21,8 261,3 257 0,0051 0,0051 D:Manual Book Training NDT - LRUTLRUT - FINAL REPORT 14'' & 12'' BENAR GSAppendix 4 -MAWP CalkulationMAWP Kalkulasi Dia. 14 Inch benar TL 1+10M
  • 47.
  • 48. EXECUTIVE SUMMARY REPORT 1. EXAMINATION TYPE PT. Putra Riau Kemari (PRK), PT. Trihasco Utama (THU), and Techcorr, USA, joined in the consortium performed Long Range Ultrasonic Test (LRUT) pipeline inspection at 12 & 14 Inch Production Line Benar 5 to Benar GS to determine the external and internal condition. LRUT inspection is also followed by thickness measurement, Ultrasonic Flow Detector, visual inspection, and GPS coordinates in accordance with the method used by existing contract no.C788493. 2. DATA INSPECTION RESULT a.Long Range Ultrasonic Test (LRUT) Examination with LRUT have been done at 13 Test Location of pipeline with length 863.84 M . This pipeline is located at N 01o 41’20.5” E 100o 59’10.9” ( Ø 14” - TL 01 ) finished at N 01o 41’211” E 101o 59’278” ( Ø12 “ – TL4 ) with total length 863.84 meters. 41 anomalies condition were found as follows:  Found 30 anomalies category Low (Below 20 % Metal Loss) at TL 01, 03, 04, 05, 07 and TL 08 due to external corrosion  Found 11 anomaly category Medium ( 20 – 80 % Metal loss ) at TL 01, 03 ,04, 06 and 08 due to external corrosion b.Direct Examination Visual inspection discovered the existence of external corrosion in 7 Test Locations with maximum depth at area of external corrosion is 3.4 mm. No emergency clamp or pipe sleeve has been found that indicated no pipeline leak history. 3. CONCLUSION Refer to ANSI B31.4 , ANSI B31.G and API 570 as standard code for on plot pipeline. Summary of data analysis and calculation as follow: a. The Pipe is medium condition, the metal loss below 80 %, with a minimum 10.5 % metal loss and maximum 53 % metal loss. b. The minimum remaining thickness is 4.4 mm in Location TL 4 forward 33.19 meters. c. Data Calculation:  Design Pressure/Operation : 257 psig  Material : API 5L Grade B  Corrosion Rate : 0.00547 ipy (0.139 mm/years).  MAOP at min actual thickness : 598 psi  Remaining life : 17.2 years  Next Inspection interval : 8 years ( June 2019 ) 4. RECOMMENDATIONS a. Inspection with visual and Wall thickness method on June 2019 b. Clean up and repaint the pipe line at TL 01, TL 03, TL 04, TL 6 , and TL 8 Detail data analysis and recommendation could be find in chapter IV and V of 12 & 14 Inch Production Line Benar 5 to Benard GS final report.
  • 49. 30 REFERENCES : 1. Anon. ASME B. 31.4 - 2009, ” Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liquids, Date of Issuance: March 24, 2010”. The American Society of Mechanical Engineers, Three Park Avenue, New York, NY 10016-5990 2. Muhlbauer, K. Pipeline Risk Management Manual, Gulf Publishing, 3rd Edition 2004 3. Anon. ASME B.31.G- 2009, “Manual Determining The Remaining Strength of Corroded Pipelines”, Date of Issuance: October 30, 2009. The American Society of Mechanical Engineers, Three Park Avenue, New York, NY 10016-5990 4. Anon. API 570, Piping Inspection Code, ”Inspection, repair,Alteration, and Rerating of In- Service Piping Systems, Second edition, Oct, 1998, addemdum 4, June 2006 5. John, F Kiefner, Pipeline Research Council International, ”Pipeline Repair Manual”, Publication Date : December,31, 1994. Revision 2006 6. Anon. API RP 580, ”Risk Based Inspection”, First edition 2002
  • 50. LIST ASUMSI Data Pipeline Line Ø12 & 14” Benar 5 to Benar GS Dimension ( Length x Dia. ) 12 & 14 Inch – 864.36 M Content Crude Oil Outside Diameter 12.750 Inch & 14.0 Inch Material Specification API 5L Grade B SMYS 35.000 Psi Pipe Schedule Schedule 40S/std Thickness Material 9.525 mm Type of Joint Seam Less Design Pressure 257 Psi Design Temperatur 200° F Operating Pressure 257 Psi Operating Temperatur 150° F Year Built 1973 Class Location - PT. Trihasco Utama Nama : Paulus Konda Position : Pipeline Inspector