SlideShare a Scribd company logo
1 of 42
Benefits of Proper Cost Estimating Techniques
With Case Studies
for
Association for Advancement of Cost
Engineers
(AACE)
May8,2015
Brandon G. Hummel, Esq. [Riordan McKee & Piper, LLC]
Ryan Phillips, P.E., CCM, LEED AP, CDT [The Vertex Companies, LLC]
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Brandon G. Hummel, Esq. - Riordan McKee & Piper, LLC
Partner
Mr. Hummel is a Partner with the Chicago law firm of Riordan, McKee & Piper, LLC where
he devotes a substantial portion of his practice to litigating complex construction, surety,
and insurance coverage matters. Over the course of his career, Mr. Hummel has resolved
numerous construction and surety disputes in state and federal courts and in
mediation/arbitration settings. These include multi-million dollar matters with contested
scope/change order claims, delay/acceleration claims, defective design/construction
claims, warranty claims, and mechanics lien/payment bond claims. In addition, Mr.
Hummel has advised clients on various transactional matters including, but not limited to,
negotiating and drafting construction contracts as well as takeover, tender, forbearance,
and other dispute resolution documents in the surety setting.
Ryan Phillips, P.E., CCM, LEED AP, CDT - The Vertex Companies, Inc.
Executive Vice President
Mr. Phillips has a decade of construction management and construction claim experience in
the Rocky Mountain Region. Specific expertise includes: surety consulting and project
completion, owner’s representation, construction oversight, construction claim analysis
and preparation, construction defect cost estimating, liability review for construction
defect matters, construction bid package preparation, and cost to complete preparation. As
the Executive Vice President of Vertex’s Litigation Support group, Mr. Phillips oversees
contract claims and other legal consulting requiring environmental, engineering and
construction expertise. Mr. Phillips has testified numerous times in deposition, trial, and/or
arbitration settings.
Speaker Biographies
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Fundamentals of
Cost Estimates Generally
• What is the purpose of the opinion/estimate? What is it
being used for?
• Preliminary Cost Estimate for Proposed Project?
• Value Engineering Following Preliminary Estimate?
• For Construction Bid Packages?
• For Remedial Work Arising Out of Defect Situation?
• For Takeover of Incomplete Project by Surety?
• For Third Parties Such as Lenders for Construction Loan?
• In every instance, client/intended beneficiary and estimator
expectations must be aligned.
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Liability Associated
with Cost Estimates
• Potential liability for cost estimators starts with the contract
but doesn’t necessarily end with it.
• Liability of an estimator can extend beyond the contract to
tort liability where there is a breach of the professional
standard of care.
• Doesn’t matter if the tort liability is specifically disclaimed in the
contract.
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Liability Associated with Faulty Cost
Estimates
• Liability depends upon whether the variation in actual cost
from the estimate is within a reasonable range (i.e., 10 to 15
percent).
• This is usually a determination for the fact finder (i.e., jury).
• The determination of liability also often depends upon:
• the sophistication of the intended recipient of the information
• what information the recipient has received and when (i.e.,
construction bids)
• how the recipient uses the information received (i.e., whether
the recipient proceeds with work)
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
LiabilityAssociatedwith Faulty Cost
Estimatesin DesignBuild Scenario
• In a design build situation, however, failure to revise cost
estimates and to advise client of same can be a breach of the
professional standard of care.
• In one case an architect was not entitled to recover his fee
where his designs resulted in construction costs more than
double that contained in his design built estimates, and the
true cost of the project was not conveyed until the project
was complete.
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Damages Associated
with Faulty Cost Estimates
• There are usually two consequences to a breach of
contract/tort liability for a faulty cost estimate:
• Bar to Recovery of Estimator’s Professional Fees
• Recovery of Damages Associated with Owner Cost Overruns
Caused by Estimator’s Breach of Professional Standard of Care
• The Latter is Much More Difficult to Prove.
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
• Remaining Construction Costs
• Accounts Payable
• Projected Backcharges
• Contracts Funds
• Budgeted Contingencies
Fundamentals of a Cost to Complete
Estimate
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
• Remaining Construction Costs
 Unearned Subcontractor / Vendor Balances
 Remaining Buyout / Remaining Self-Performance
Items
 General Conditions for Completion Contractor
 Closeout Administration for Completion Contractor
 Completion Contractor Fee
Fundamentals of a Cost to Complete
Estimate
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
• Remaining Construction Costs
 Unearned Subcontractor/Vendor Balance
• Current job cost reports, subcontract agreements,
purchase orders, executed change orders, pending
change orders and claim information.
 Remaining Buyout/Remaining Self-Performance
Work
• Buyout review
• Look for scope gap and exclusions
• Calculate the reasonable cost to perform all remaining
buyout work
Fundamentals of a Cost to Complete
Estimate
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
• Remaining Construction Costs
 Remaining Buyout/Remaining Self-Performance
Work
• Calculate the reasonable cost to perform all remaining
buyout work.
 Pricing from local subcontractors and vendors.
 Historical pricing databases.
 Unit pricing from estimating guidelines such as RS Means,
Xactimate, HCSS, and Equipment Watch (Equipment Blue
Book).
 Quantity takeoff software such as OnScreen.
Fundamentals of a Cost to Complete
Estimate
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
• Preferred Option
 Subcontractor bids:
• Proper bid coverage (3-5 bids) will reveal fair
market value for the work.
• Will assist with proving reasonableness of costs in
a recovery/indemnification action.
• Multiple bids are oftentimes difficult to get.
• Sole source bidding doesn’t necessarily mean fair
market value.
• Difficult with small scopes of work and work that
is not clearly defined.
• Bonding requirements may limit subcontractor
pool.
Fundamentals of a Cost to Complete
Estimate
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
• Step One: Quantification
• Step Two: Costing
• Step Three: Pricing
Fundamentals of a Cost to Complete
Estimate
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
• Independent Estimate Preparation:
 Define the scope of work per contract and
change order.
 Step One: Quantify the work
• Square feet of stucco.
• Cubic yards of concrete.
• Lineal feet of trim.
• Count of plumbing fixtures.
• Square footage of scaffolding.
• Count of site features/trees.
Fundamentals of a Cost to Complete
Estimate
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
DIGITAL TAKEOFF
•Easy to use
•Clear Presentation
Takeoff Tab
•Printable Takeoffs
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
• Independent Estimate Preparation:
 Step Two: Costing the Work – Assigning
realistic costs to the items.
• Subcontractor bids.
• RS Means
• Xactimate
• HSS
• Equipment Watch
• Historical Pricing from Similar Projects
Fundamentals of a Cost to Complete
Estimate
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Fundamentals of a Cost to Complete
Estimate
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Fundamentals of a Cost to Complete
Estimate
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
•Multiple Source Information
•Large Volume of
Searchable Equipment
•Location Specific
Fundamentals of a Cost to Complete
Estimate
• Estimate Verification
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
ESTIMATING PROGRAMS
•Most Used in North
America
•Pre-built Database
•Takeoff Compatibility
Timberline
ICE
•Widely Used
•Takeoff Compatibility
•Interface with
Manufacturer Price Data
•Built-in Digital Takeoff
•Heavy Civil and
Infrastructure
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
• Independent Estimate Preparation:
 Step 3: Pricing the Work
• Economic considerations
• Competitive bidding environment
• Overhead and Profit considerations
• Adapt to specific project circumstances
Fundamentals of a Cost to Complete
Estimate
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
• Subdivision Bond Claim(s)
• Five separate subdivision bonds for five separate
neighborhoods within a new development are
issued.
• Named Principal is the Builder/Developer.
• The City is the Obligee.
• Builder/Developer completes portions of site
development work before filing for bankruptcy.
• Value of bonds determined by the City -
Engineer’s Estimate of Probable Cost
Cost to Complete Case Study
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Cost to Complete Case Study
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Cost to Complete Case Study
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
• Obligee/Plaintiff makes claim on the bond for
incomplete work.
• Plaintiff makes claim for $200,376 based on
new Engineer’s Estimate.
 No basis for pricing.
 Included additional work not included in
subdivision bond.
• Vertex’s comparable estimate was for $92,087;
a variance of $108,289.
Cost to Complete Case Study
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
TheVERTEXCompanies
Cost to Complete Case Study
Cost to Complete Case Study
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Cost to Complete Case Study
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
• Summary:
• Using industry standard pricing databases and
quantity take-off software, as opposed to
utilizing arbitrary and unsupported figures,
Vertex was able to cut the Plaintiff’s direct costs
by more than 40%.
• Applying a strict interpretation of the
subdivision bonds regarding what scopes are
included, the Plaintiff’s claim was further
reduced by approximately 15%.
• In sum, the matter went to trial….
Cost to Complete Case Study
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Proposal Risk Considerations for
Design-Build Projects
• The completeness of the Owner
provided Design Criteria Package
• The time allowed to prepare the
estimate and/or perform additional
design and investigation.
• Scheduling the work based on limited
information.
• Contingency Considerations(discussed
later)
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Design Build Case Study
• Background of Proposed Project
• Proposed roadway improvements spanning approximately
1.5 miles in Colorado.
• Colorado Department of Transportation solicits bids from
several contractors and provides outline specifications as
the basis of design and bid.
• Work generally consists of widening a roadway,
intersection/signal replacement and extensive drainage
redesign and installation.
• A Design-Builder contacts a local civil engineering company
to provide professional services.
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Design Build Case Study
Execution of Contractor/DB Agreement
The Agreement’s Standard of Care Provision Provides:
Standard of Care: While performing services under this
Agreement, Designer shall exercise that degree of care
and skill ordinarily exercised under similar circumstances
by members of the engineering profession, as applicable,
performing the kinds of services to be performed
hereunder and practicing in the same or similar locality at
the same time. Designer agrees to perform and correct at
its expense any work or Services performed by Designer
that fails to conform to the standard of care Contractor
has accepted pursuant to this subparagraph.
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Design Build Case Study
• First Stage of Design Services Performed
• DB fulfilled its requirements under the Professional
Agreement and provided estimated quantities of work
(2000 lf of 18” RCP, 100 lf of 32” RCP, 32 inlet
structures, etc.) and a schematic design based on the
RFP information.
• Discussions were had, although not clearly
documented between the two parties, regarding the
inclusion of contingencies in the estimate.
• DB was awarded the Project from CDOT.
• Contract value was approximately $40M.
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Design Build Case Study
• Following completion of 1st Professional Services Contract,
DB contracted with Designer to provide complete design
services - $285,000 value.
• Design Agreement:
• General Terms: This Agreement is binding and all parties
agree that if DB is awarded the Project from CDOT, team
members will execute a mutually agreed upon contract for
design services for the said project.
• Scope of Work: Designer will provide design and services
necessary for Contractor to develop quantities and unit
prices for the bid proposal.
• Designer will be compensated at a rate of $55.00 per hour,
not to exceed $5,000.
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Design Build Case Study
• Significant Cost Overruns Occur
• DB performed the work; however, significant quantity overruns
occurred for several civil related line items.
• DB files a claim against Designer for $952k.
• Deposition testimony on behalf of DB indicates DB
assumed 7.5% profit for the project. Final job cost
reports indicate the following:
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Design Build Case Study
• Even With Cost Overruns, DB Still Earned Profit
• The Project was profitable for the DB and the DB very
nearly met their estimated profit margin – a variance
of only $291k.
• DB’s claim was in the format of a modified total cost
claim and failed to meet the requisite four part test
that is necessary to utilize this claim method.
(1) that it is impractical to prove actual losses
directly
(2) the Contractor’s bid was reasonable
(3) the Contractor’s actual costs were
reasonable.
(4) the Contractor was not responsible for
any of the cost overruns.
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Design Build Case Study
• DB Maintained Inadequate Contingency
• Deposition testimony revealed the DB carried a
2% contingency.
• Expert consultant for the DB stated:
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Design Build Case Study
• Best Practices for Use of Contingencies
• RS Means states that contingencies should
generally be carried as follows:
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Design Build Case Study
• AACE Recommendations for Use of
Contingencies
• AACE guidelines would recommend the following
parameters be discussed (AACE International
Recommended Practice No. 17R-97).
Primary
Characteristic
Estimate
Class
Degree of Project
Definition
(expressed as % of
complete definition)
End Usage
(Typical purpose of estimate)
Methodology
(Typical estimating method)
Expected Accuracy
Range (Typical +/-
range relative to index
of 1 (i.e. Class 1
Estimate))
Preparation Effort
(Typical degree of
effort relative to
least cost index of 1)
Class 5 0%-2% Screening or feasibility
Stochastic (factors and/or
models) or judgment
4to 20 1
Class 4 1%-15% Concept study or feasibility Primarily stochastic 3to 12 2to 4
Class 3 10% to 40% Budget authorization or control Mixed but primarily stochastic 2to 6 3to 10
Class 2 30% to 70% Control or bid/tender Primarily deterministic 1to 3 5to 20
Class 1 70% to 100% Check estimate or bid/tender Deterministic 1 10to 100
Secondary Characteristic
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Design Build Case Study
• Failure to Align DB and Designer Expectations
• The DB assumed that for $5,000 they were
essentially getting a design and estimated
quantities in line with “Final Working Drawing
Stage (3.0% contingency), or in line with AACE
guidelines a Class I estimate with an accuracy
range on the low end of -3% to -10% and on the
high end of +3% to +15%.
• The failure to properly communicate what was
being provided by the Designer and what was
expected by the DB set the scene for a dispute.
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Design Build Case Study
• How the DB/Designer Communications Could
Have Averted a Dispute
• Clear communication on the basis of the
Designer’s design and quantity takeoffs would
have eliminated the possibility for a claim.
• The AACE provides estimating guidelines that
when used could have protected the Designer.
• The DB was awarded a small portion of their
claim but failed in their claim submittal primarily
due to the failure to support their modified total
cost claim method.
TheVERTEXCompanies
RiordanMcKee&Piper,LLC
Conclusions
TheVERTEXCompanies
RiordanMcKee&Piper,LLC

More Related Content

What's hot

EPC Contracts – Negotiation, Administration and Risk Management
EPC Contracts – Negotiation, Administration and Risk ManagementEPC Contracts – Negotiation, Administration and Risk Management
EPC Contracts – Negotiation, Administration and Risk Managementrockporshe
 
Team Structures and Project Performance in the Design-Build Marketplace
Team Structures and Project Performance in the Design-Build MarketplaceTeam Structures and Project Performance in the Design-Build Marketplace
Team Structures and Project Performance in the Design-Build MarketplaceWater Design-Build Council
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Kipcon Inc.
 
Commercial Management Scenarios
Commercial Management ScenariosCommercial Management Scenarios
Commercial Management ScenariosCKMCforstudents
 
CORE AIA Presentation
CORE AIA PresentationCORE AIA Presentation
CORE AIA Presentationcfiorilli
 
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractProject Controls Expo
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsFrancis Ho
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
2010 uci douglas hospital team platinum award by bdc
2010 uci douglas hospital team platinum award by bdc2010 uci douglas hospital team platinum award by bdc
2010 uci douglas hospital team platinum award by bdcAvi Grigorescu
 
Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Browne Jacobson LLP
 

What's hot (16)

EPC Contracts – Negotiation, Administration and Risk Management
EPC Contracts – Negotiation, Administration and Risk ManagementEPC Contracts – Negotiation, Administration and Risk Management
EPC Contracts – Negotiation, Administration and Risk Management
 
Team Structures and Project Performance in the Design-Build Marketplace
Team Structures and Project Performance in the Design-Build MarketplaceTeam Structures and Project Performance in the Design-Build Marketplace
Team Structures and Project Performance in the Design-Build Marketplace
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Commercial Management Scenarios
Commercial Management ScenariosCommercial Management Scenarios
Commercial Management Scenarios
 
CORE AIA Presentation
CORE AIA PresentationCORE AIA Presentation
CORE AIA Presentation
 
Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?Muckle LLP - Which contract should I be using?
Muckle LLP - Which contract should I be using?
 
uap doc 207-208
uap doc 207-208uap doc 207-208
uap doc 207-208
 
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
Project Controls Expo - 31st Oct 2012 - Delay Analysis Letting the Evidence S...
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction Contracts
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Uap Document
Uap DocumentUap Document
Uap Document
 
2010 uci douglas hospital team platinum award by bdc
2010 uci douglas hospital team platinum award by bdc2010 uci douglas hospital team platinum award by bdc
2010 uci douglas hospital team platinum award by bdc
 
Giang CV
Giang CVGiang CV
Giang CV
 
Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...Winning tenders / securing tenderers in a competitive construction market - N...
Winning tenders / securing tenderers in a competitive construction market - N...
 

Viewers also liked

ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Paper
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-PaperICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Paper
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-PaperRussell Archibald
 
A visual guide to Critical Chain Project Management (CCPM) Part 2: CCPM Solut...
A visual guide to Critical Chain Project Management (CCPM) Part 2: CCPM Solut...A visual guide to Critical Chain Project Management (CCPM) Part 2: CCPM Solut...
A visual guide to Critical Chain Project Management (CCPM) Part 2: CCPM Solut...Jonathan Sapir
 
A visual guide to Critical Chain Project Management (CCPM) Part 1
A visual guide to Critical Chain Project Management (CCPM) Part 1A visual guide to Critical Chain Project Management (CCPM) Part 1
A visual guide to Critical Chain Project Management (CCPM) Part 1Jonathan Sapir
 
Aace factored cost estimation
Aace factored cost estimationAace factored cost estimation
Aace factored cost estimationBrij Patwari
 
APM Presents - Why Value Management might reveal just what managing projects...
APM Presents - Why Value Management might reveal just what managing  projects...APM Presents - Why Value Management might reveal just what managing  projects...
APM Presents - Why Value Management might reveal just what managing projects...Association for Project Management
 
Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation iBich Lien Pham
 
What is Procurement
What is ProcurementWhat is Procurement
What is ProcurementFahad Ali
 
BIM project execution
BIM project executionBIM project execution
BIM project executionStephen Au
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project managementKabilan Kabi
 

Viewers also liked (16)

ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Paper
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-PaperICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Paper
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Paper
 
APM London branch BIM Breakfast: Introduction to BIM
APM London branch BIM Breakfast: Introduction to BIM APM London branch BIM Breakfast: Introduction to BIM
APM London branch BIM Breakfast: Introduction to BIM
 
A visual guide to Critical Chain Project Management (CCPM) Part 2: CCPM Solut...
A visual guide to Critical Chain Project Management (CCPM) Part 2: CCPM Solut...A visual guide to Critical Chain Project Management (CCPM) Part 2: CCPM Solut...
A visual guide to Critical Chain Project Management (CCPM) Part 2: CCPM Solut...
 
A visual guide to Critical Chain Project Management (CCPM) Part 1
A visual guide to Critical Chain Project Management (CCPM) Part 1A visual guide to Critical Chain Project Management (CCPM) Part 1
A visual guide to Critical Chain Project Management (CCPM) Part 1
 
Aace factored cost estimation
Aace factored cost estimationAace factored cost estimation
Aace factored cost estimation
 
What is proactive project management?
What is proactive project management?What is proactive project management?
What is proactive project management?
 
APM Presents - Why Value Management might reveal just what managing projects...
APM Presents - Why Value Management might reveal just what managing  projects...APM Presents - Why Value Management might reveal just what managing  projects...
APM Presents - Why Value Management might reveal just what managing projects...
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Lecture # 5 cost estimation i
Lecture # 5 cost estimation iLecture # 5 cost estimation i
Lecture # 5 cost estimation i
 
What is Procurement
What is ProcurementWhat is Procurement
What is Procurement
 
BIM project execution
BIM project executionBIM project execution
BIM project execution
 
Critical chain project management - Gary Palmer
Critical chain project management - Gary PalmerCritical chain project management - Gary Palmer
Critical chain project management - Gary Palmer
 
Calculating contingency for management reserve
Calculating contingency for management reserveCalculating contingency for management reserve
Calculating contingency for management reserve
 
An introduction to Critical Chain Project Management (CCPM)
An introduction to Critical Chain Project Management (CCPM)An introduction to Critical Chain Project Management (CCPM)
An introduction to Critical Chain Project Management (CCPM)
 
Guide to Project Portfolio Management
Guide to Project Portfolio ManagementGuide to Project Portfolio Management
Guide to Project Portfolio Management
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 

Similar to May AACE Presentation, FINAL

SOLAR Project-Finance-Nigeria-Case-Studies.pptx
SOLAR Project-Finance-Nigeria-Case-Studies.pptxSOLAR Project-Finance-Nigeria-Case-Studies.pptx
SOLAR Project-Finance-Nigeria-Case-Studies.pptxDNTPOWER
 
Ohio Construction Reform Finalized- The New Reality
Ohio Construction Reform Finalized- The New RealityOhio Construction Reform Finalized- The New Reality
Ohio Construction Reform Finalized- The New RealityKegler Brown Hill + Ritter
 
Smart Agreements and Green Litigation Risks
Smart Agreements and Green Litigation RisksSmart Agreements and Green Litigation Risks
Smart Agreements and Green Litigation RisksScott Wolfe
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionWaleed Liaqat
 
Construction Client Contracts
Construction Client ContractsConstruction Client Contracts
Construction Client ContractsDennis Anderson
 
Explore-Investment-Terms-8839789.ppsx
Explore-Investment-Terms-8839789.ppsxExplore-Investment-Terms-8839789.ppsx
Explore-Investment-Terms-8839789.ppsxJawedIqubal6
 
Smart real estate marketing By Boris Gantsevich
Smart real estate marketing By Boris GantsevichSmart real estate marketing By Boris Gantsevich
Smart real estate marketing By Boris GantsevichReal Estate Agent
 
C8 financing affordable rental projects p pt - obie baker
C8 financing affordable rental projects   p pt - obie bakerC8 financing affordable rental projects   p pt - obie baker
C8 financing affordable rental projects p pt - obie bakerHousing Assistance Council
 
Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBrown Smith Wallace
 
Fas drs power_point_2003
Fas drs power_point_2003Fas drs power_point_2003
Fas drs power_point_2003shallongammon
 
Webinar Slides: Accounting for Indirect Costs in Construction Contracts
Webinar Slides: Accounting for Indirect Costs in Construction ContractsWebinar Slides: Accounting for Indirect Costs in Construction Contracts
Webinar Slides: Accounting for Indirect Costs in Construction ContractsMHM (Mayer Hoffman McCann P.C.)
 
11 formalities for setting up a small business enterprise
11 formalities for setting up a small business enterprise11 formalities for setting up a small business enterprise
11 formalities for setting up a small business enterpriseabcde123321
 
Permit Place Asset Advantage
Permit Place Asset AdvantagePermit Place Asset Advantage
Permit Place Asset AdvantagePermit Place
 

Similar to May AACE Presentation, FINAL (20)

SOLAR Project-Finance-Nigeria-Case-Studies.pptx
SOLAR Project-Finance-Nigeria-Case-Studies.pptxSOLAR Project-Finance-Nigeria-Case-Studies.pptx
SOLAR Project-Finance-Nigeria-Case-Studies.pptx
 
Ohio Construction Reform Finalized- The New Reality
Ohio Construction Reform Finalized- The New RealityOhio Construction Reform Finalized- The New Reality
Ohio Construction Reform Finalized- The New Reality
 
Smart Agreements and Green Litigation Risks
Smart Agreements and Green Litigation RisksSmart Agreements and Green Litigation Risks
Smart Agreements and Green Litigation Risks
 
How to Write Better Proposals
How to Write Better Proposals How to Write Better Proposals
How to Write Better Proposals
 
AGC Webinar
AGC WebinarAGC Webinar
AGC Webinar
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Follow the Money_Subcontractor Payment Practices
Follow the Money_Subcontractor Payment PracticesFollow the Money_Subcontractor Payment Practices
Follow the Money_Subcontractor Payment Practices
 
Credicon Introduction
Credicon  IntroductionCredicon  Introduction
Credicon Introduction
 
Construction Client Contracts
Construction Client ContractsConstruction Client Contracts
Construction Client Contracts
 
Explore-Investment-Terms-8839789.ppsx
Explore-Investment-Terms-8839789.ppsxExplore-Investment-Terms-8839789.ppsx
Explore-Investment-Terms-8839789.ppsx
 
Smart real estate marketing By Boris Gantsevich
Smart real estate marketing By Boris GantsevichSmart real estate marketing By Boris Gantsevich
Smart real estate marketing By Boris Gantsevich
 
C8 financing affordable rental projects p pt - obie baker
C8 financing affordable rental projects   p pt - obie bakerC8 financing affordable rental projects   p pt - obie baker
C8 financing affordable rental projects p pt - obie baker
 
Balancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction ProjectsBalancing Flexibility and Cost Control in Construction Projects
Balancing Flexibility and Cost Control in Construction Projects
 
Fas drs power_point_2003
Fas drs power_point_2003Fas drs power_point_2003
Fas drs power_point_2003
 
Webinar Slides: Accounting for Indirect Costs in Construction Contracts
Webinar Slides: Accounting for Indirect Costs in Construction ContractsWebinar Slides: Accounting for Indirect Costs in Construction Contracts
Webinar Slides: Accounting for Indirect Costs in Construction Contracts
 
Budget Planning
Budget Planning Budget Planning
Budget Planning
 
CCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference SeminarCCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference Seminar
 
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
 
11 formalities for setting up a small business enterprise
11 formalities for setting up a small business enterprise11 formalities for setting up a small business enterprise
11 formalities for setting up a small business enterprise
 
Permit Place Asset Advantage
Permit Place Asset AdvantagePermit Place Asset Advantage
Permit Place Asset Advantage
 

May AACE Presentation, FINAL

  • 1. Benefits of Proper Cost Estimating Techniques With Case Studies for Association for Advancement of Cost Engineers (AACE) May8,2015 Brandon G. Hummel, Esq. [Riordan McKee & Piper, LLC] Ryan Phillips, P.E., CCM, LEED AP, CDT [The Vertex Companies, LLC] TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 2. Brandon G. Hummel, Esq. - Riordan McKee & Piper, LLC Partner Mr. Hummel is a Partner with the Chicago law firm of Riordan, McKee & Piper, LLC where he devotes a substantial portion of his practice to litigating complex construction, surety, and insurance coverage matters. Over the course of his career, Mr. Hummel has resolved numerous construction and surety disputes in state and federal courts and in mediation/arbitration settings. These include multi-million dollar matters with contested scope/change order claims, delay/acceleration claims, defective design/construction claims, warranty claims, and mechanics lien/payment bond claims. In addition, Mr. Hummel has advised clients on various transactional matters including, but not limited to, negotiating and drafting construction contracts as well as takeover, tender, forbearance, and other dispute resolution documents in the surety setting. Ryan Phillips, P.E., CCM, LEED AP, CDT - The Vertex Companies, Inc. Executive Vice President Mr. Phillips has a decade of construction management and construction claim experience in the Rocky Mountain Region. Specific expertise includes: surety consulting and project completion, owner’s representation, construction oversight, construction claim analysis and preparation, construction defect cost estimating, liability review for construction defect matters, construction bid package preparation, and cost to complete preparation. As the Executive Vice President of Vertex’s Litigation Support group, Mr. Phillips oversees contract claims and other legal consulting requiring environmental, engineering and construction expertise. Mr. Phillips has testified numerous times in deposition, trial, and/or arbitration settings. Speaker Biographies TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 3. Fundamentals of Cost Estimates Generally • What is the purpose of the opinion/estimate? What is it being used for? • Preliminary Cost Estimate for Proposed Project? • Value Engineering Following Preliminary Estimate? • For Construction Bid Packages? • For Remedial Work Arising Out of Defect Situation? • For Takeover of Incomplete Project by Surety? • For Third Parties Such as Lenders for Construction Loan? • In every instance, client/intended beneficiary and estimator expectations must be aligned. TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 4. Liability Associated with Cost Estimates • Potential liability for cost estimators starts with the contract but doesn’t necessarily end with it. • Liability of an estimator can extend beyond the contract to tort liability where there is a breach of the professional standard of care. • Doesn’t matter if the tort liability is specifically disclaimed in the contract. TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 5. Liability Associated with Faulty Cost Estimates • Liability depends upon whether the variation in actual cost from the estimate is within a reasonable range (i.e., 10 to 15 percent). • This is usually a determination for the fact finder (i.e., jury). • The determination of liability also often depends upon: • the sophistication of the intended recipient of the information • what information the recipient has received and when (i.e., construction bids) • how the recipient uses the information received (i.e., whether the recipient proceeds with work) TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 6. LiabilityAssociatedwith Faulty Cost Estimatesin DesignBuild Scenario • In a design build situation, however, failure to revise cost estimates and to advise client of same can be a breach of the professional standard of care. • In one case an architect was not entitled to recover his fee where his designs resulted in construction costs more than double that contained in his design built estimates, and the true cost of the project was not conveyed until the project was complete. TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 7. Damages Associated with Faulty Cost Estimates • There are usually two consequences to a breach of contract/tort liability for a faulty cost estimate: • Bar to Recovery of Estimator’s Professional Fees • Recovery of Damages Associated with Owner Cost Overruns Caused by Estimator’s Breach of Professional Standard of Care • The Latter is Much More Difficult to Prove. TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 8. • Remaining Construction Costs • Accounts Payable • Projected Backcharges • Contracts Funds • Budgeted Contingencies Fundamentals of a Cost to Complete Estimate TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 9. • Remaining Construction Costs  Unearned Subcontractor / Vendor Balances  Remaining Buyout / Remaining Self-Performance Items  General Conditions for Completion Contractor  Closeout Administration for Completion Contractor  Completion Contractor Fee Fundamentals of a Cost to Complete Estimate TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 10. • Remaining Construction Costs  Unearned Subcontractor/Vendor Balance • Current job cost reports, subcontract agreements, purchase orders, executed change orders, pending change orders and claim information.  Remaining Buyout/Remaining Self-Performance Work • Buyout review • Look for scope gap and exclusions • Calculate the reasonable cost to perform all remaining buyout work Fundamentals of a Cost to Complete Estimate TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 11. • Remaining Construction Costs  Remaining Buyout/Remaining Self-Performance Work • Calculate the reasonable cost to perform all remaining buyout work.  Pricing from local subcontractors and vendors.  Historical pricing databases.  Unit pricing from estimating guidelines such as RS Means, Xactimate, HCSS, and Equipment Watch (Equipment Blue Book).  Quantity takeoff software such as OnScreen. Fundamentals of a Cost to Complete Estimate TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 12. • Preferred Option  Subcontractor bids: • Proper bid coverage (3-5 bids) will reveal fair market value for the work. • Will assist with proving reasonableness of costs in a recovery/indemnification action. • Multiple bids are oftentimes difficult to get. • Sole source bidding doesn’t necessarily mean fair market value. • Difficult with small scopes of work and work that is not clearly defined. • Bonding requirements may limit subcontractor pool. Fundamentals of a Cost to Complete Estimate TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 13. • Step One: Quantification • Step Two: Costing • Step Three: Pricing Fundamentals of a Cost to Complete Estimate TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 14. • Independent Estimate Preparation:  Define the scope of work per contract and change order.  Step One: Quantify the work • Square feet of stucco. • Cubic yards of concrete. • Lineal feet of trim. • Count of plumbing fixtures. • Square footage of scaffolding. • Count of site features/trees. Fundamentals of a Cost to Complete Estimate TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 15. DIGITAL TAKEOFF •Easy to use •Clear Presentation Takeoff Tab •Printable Takeoffs TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 16. • Independent Estimate Preparation:  Step Two: Costing the Work – Assigning realistic costs to the items. • Subcontractor bids. • RS Means • Xactimate • HSS • Equipment Watch • Historical Pricing from Similar Projects Fundamentals of a Cost to Complete Estimate TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 17. Fundamentals of a Cost to Complete Estimate TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 18. Fundamentals of a Cost to Complete Estimate TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 19. •Multiple Source Information •Large Volume of Searchable Equipment •Location Specific Fundamentals of a Cost to Complete Estimate • Estimate Verification TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 20. ESTIMATING PROGRAMS •Most Used in North America •Pre-built Database •Takeoff Compatibility Timberline ICE •Widely Used •Takeoff Compatibility •Interface with Manufacturer Price Data •Built-in Digital Takeoff •Heavy Civil and Infrastructure TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 21. • Independent Estimate Preparation:  Step 3: Pricing the Work • Economic considerations • Competitive bidding environment • Overhead and Profit considerations • Adapt to specific project circumstances Fundamentals of a Cost to Complete Estimate TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 22. • Subdivision Bond Claim(s) • Five separate subdivision bonds for five separate neighborhoods within a new development are issued. • Named Principal is the Builder/Developer. • The City is the Obligee. • Builder/Developer completes portions of site development work before filing for bankruptcy. • Value of bonds determined by the City - Engineer’s Estimate of Probable Cost Cost to Complete Case Study TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 23. Cost to Complete Case Study TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 24. Cost to Complete Case Study TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 25. • Obligee/Plaintiff makes claim on the bond for incomplete work. • Plaintiff makes claim for $200,376 based on new Engineer’s Estimate.  No basis for pricing.  Included additional work not included in subdivision bond. • Vertex’s comparable estimate was for $92,087; a variance of $108,289. Cost to Complete Case Study TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 27. Cost to Complete Case Study TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 28. Cost to Complete Case Study TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 29. • Summary: • Using industry standard pricing databases and quantity take-off software, as opposed to utilizing arbitrary and unsupported figures, Vertex was able to cut the Plaintiff’s direct costs by more than 40%. • Applying a strict interpretation of the subdivision bonds regarding what scopes are included, the Plaintiff’s claim was further reduced by approximately 15%. • In sum, the matter went to trial…. Cost to Complete Case Study TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 30. Proposal Risk Considerations for Design-Build Projects • The completeness of the Owner provided Design Criteria Package • The time allowed to prepare the estimate and/or perform additional design and investigation. • Scheduling the work based on limited information. • Contingency Considerations(discussed later) TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 31. Design Build Case Study • Background of Proposed Project • Proposed roadway improvements spanning approximately 1.5 miles in Colorado. • Colorado Department of Transportation solicits bids from several contractors and provides outline specifications as the basis of design and bid. • Work generally consists of widening a roadway, intersection/signal replacement and extensive drainage redesign and installation. • A Design-Builder contacts a local civil engineering company to provide professional services. TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 32. Design Build Case Study Execution of Contractor/DB Agreement The Agreement’s Standard of Care Provision Provides: Standard of Care: While performing services under this Agreement, Designer shall exercise that degree of care and skill ordinarily exercised under similar circumstances by members of the engineering profession, as applicable, performing the kinds of services to be performed hereunder and practicing in the same or similar locality at the same time. Designer agrees to perform and correct at its expense any work or Services performed by Designer that fails to conform to the standard of care Contractor has accepted pursuant to this subparagraph. TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 33. Design Build Case Study • First Stage of Design Services Performed • DB fulfilled its requirements under the Professional Agreement and provided estimated quantities of work (2000 lf of 18” RCP, 100 lf of 32” RCP, 32 inlet structures, etc.) and a schematic design based on the RFP information. • Discussions were had, although not clearly documented between the two parties, regarding the inclusion of contingencies in the estimate. • DB was awarded the Project from CDOT. • Contract value was approximately $40M. TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 34. Design Build Case Study • Following completion of 1st Professional Services Contract, DB contracted with Designer to provide complete design services - $285,000 value. • Design Agreement: • General Terms: This Agreement is binding and all parties agree that if DB is awarded the Project from CDOT, team members will execute a mutually agreed upon contract for design services for the said project. • Scope of Work: Designer will provide design and services necessary for Contractor to develop quantities and unit prices for the bid proposal. • Designer will be compensated at a rate of $55.00 per hour, not to exceed $5,000. TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 35. Design Build Case Study • Significant Cost Overruns Occur • DB performed the work; however, significant quantity overruns occurred for several civil related line items. • DB files a claim against Designer for $952k. • Deposition testimony on behalf of DB indicates DB assumed 7.5% profit for the project. Final job cost reports indicate the following: TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 36. Design Build Case Study • Even With Cost Overruns, DB Still Earned Profit • The Project was profitable for the DB and the DB very nearly met their estimated profit margin – a variance of only $291k. • DB’s claim was in the format of a modified total cost claim and failed to meet the requisite four part test that is necessary to utilize this claim method. (1) that it is impractical to prove actual losses directly (2) the Contractor’s bid was reasonable (3) the Contractor’s actual costs were reasonable. (4) the Contractor was not responsible for any of the cost overruns. TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 37. Design Build Case Study • DB Maintained Inadequate Contingency • Deposition testimony revealed the DB carried a 2% contingency. • Expert consultant for the DB stated: TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 38. Design Build Case Study • Best Practices for Use of Contingencies • RS Means states that contingencies should generally be carried as follows: TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 39. Design Build Case Study • AACE Recommendations for Use of Contingencies • AACE guidelines would recommend the following parameters be discussed (AACE International Recommended Practice No. 17R-97). Primary Characteristic Estimate Class Degree of Project Definition (expressed as % of complete definition) End Usage (Typical purpose of estimate) Methodology (Typical estimating method) Expected Accuracy Range (Typical +/- range relative to index of 1 (i.e. Class 1 Estimate)) Preparation Effort (Typical degree of effort relative to least cost index of 1) Class 5 0%-2% Screening or feasibility Stochastic (factors and/or models) or judgment 4to 20 1 Class 4 1%-15% Concept study or feasibility Primarily stochastic 3to 12 2to 4 Class 3 10% to 40% Budget authorization or control Mixed but primarily stochastic 2to 6 3to 10 Class 2 30% to 70% Control or bid/tender Primarily deterministic 1to 3 5to 20 Class 1 70% to 100% Check estimate or bid/tender Deterministic 1 10to 100 Secondary Characteristic TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 40. Design Build Case Study • Failure to Align DB and Designer Expectations • The DB assumed that for $5,000 they were essentially getting a design and estimated quantities in line with “Final Working Drawing Stage (3.0% contingency), or in line with AACE guidelines a Class I estimate with an accuracy range on the low end of -3% to -10% and on the high end of +3% to +15%. • The failure to properly communicate what was being provided by the Designer and what was expected by the DB set the scene for a dispute. TheVERTEXCompanies RiordanMcKee&Piper,LLC
  • 41. Design Build Case Study • How the DB/Designer Communications Could Have Averted a Dispute • Clear communication on the basis of the Designer’s design and quantity takeoffs would have eliminated the possibility for a claim. • The AACE provides estimating guidelines that when used could have protected the Designer. • The DB was awarded a small portion of their claim but failed in their claim submittal primarily due to the failure to support their modified total cost claim method. TheVERTEXCompanies RiordanMcKee&Piper,LLC