Technical Meeting
5/July/16
Project Slope
1
WP 3 – Integration of novel intelligent
harvesting systems operating in mountain
areas (hardware development)
Project Meeting-Trento 4-5 June 2016.
Technical Meeting
5 Jul 16
WP 3
wp 3 deliverable of the period
Technical Meeting
5 Jul 16
Task 3.6 DATA MANAGEMENT BACK UP is
still ongoing and deliverable (prototype) is
under development
Task 3.4 processor head
the team have been finalising the
integration of all
hardware/software components.
software tools have been implemented
(mostly previously developed) on the
central computer of the industrial PC
installed on the
processor/excavator.
Technical Meeting
5 Jul 16
The connection to the central database
(MHG) and uploading of required data
from the database is accomplished by
means of the web service.
The data are ready for integration with
other software tools, including production
plan, location map and user interface
(visualization of the logs, quality and
suggested cross-cuttings)
Technical Meeting
5 Jul 16
Team scheduled installation of the WIFI electronics in the central computer
The team (Compolab, Graphitech, CNR) worked on the connection of the
processor head and the cable crane (industrial PC and bananaPI)
The aim was to
verify possibility of the data transfer and further usage of the information to
be provided by the cable crane.
Technical Meeting
5 Jul 16
Task 3.3
Tecno carriage
Chockers
Rope launcher
Technical Meeting
5 Jul 16
Task 3.3TECNO
As seen in yesterday demo
the status of work is as
follows:
TECNO carriage: hardware
completed, software
completed
The only function that has
still to be checked is the rfid
tag reading in the forest,
since the connection was not
available.
Yet the Antenna worked
during our testing activities
Technical Meeting
5 Jul 16
Technical Meeting
5 Jul 16
Chockers work status
Chokers are ready. The
mechanical part is ready. We have
managed interaction between
them and the new software
Testing activities were carried
out also between Tecno carriage
and the Chockers
Technical Meeting
5 Jul 16
Synthetic rope launcher EASER status
https://www.dropbox.com/s/hd1z1uyfsbdiazj/
DSCN1065.MOV?dl=0
Technical Meeting
5 Jul 16
Contact info
Diego Graifenberg: graifenberg@gmail.com
Technical Meeting
5 Jul 16

4th Technical Meeting - WP3

  • 1.
    Technical Meeting 5/July/16 Project Slope 1 WP3 – Integration of novel intelligent harvesting systems operating in mountain areas (hardware development)
  • 2.
    Project Meeting-Trento 4-5June 2016. Technical Meeting 5 Jul 16
  • 3.
  • 4.
    wp 3 deliverableof the period Technical Meeting 5 Jul 16
  • 6.
    Task 3.6 DATAMANAGEMENT BACK UP is still ongoing and deliverable (prototype) is under development Task 3.4 processor head the team have been finalising the integration of all hardware/software components. software tools have been implemented (mostly previously developed) on the central computer of the industrial PC installed on the processor/excavator. Technical Meeting 5 Jul 16
  • 7.
    The connection tothe central database (MHG) and uploading of required data from the database is accomplished by means of the web service. The data are ready for integration with other software tools, including production plan, location map and user interface (visualization of the logs, quality and suggested cross-cuttings) Technical Meeting 5 Jul 16
  • 8.
    Team scheduled installationof the WIFI electronics in the central computer The team (Compolab, Graphitech, CNR) worked on the connection of the processor head and the cable crane (industrial PC and bananaPI) The aim was to verify possibility of the data transfer and further usage of the information to be provided by the cable crane. Technical Meeting 5 Jul 16
  • 9.
    Task 3.3 Tecno carriage Chockers Ropelauncher Technical Meeting 5 Jul 16
  • 10.
    Task 3.3TECNO As seenin yesterday demo the status of work is as follows: TECNO carriage: hardware completed, software completed The only function that has still to be checked is the rfid tag reading in the forest, since the connection was not available. Yet the Antenna worked during our testing activities Technical Meeting 5 Jul 16
  • 11.
  • 12.
    Chockers work status Chokersare ready. The mechanical part is ready. We have managed interaction between them and the new software Testing activities were carried out also between Tecno carriage and the Chockers Technical Meeting 5 Jul 16
  • 13.
    Synthetic rope launcherEASER status https://www.dropbox.com/s/hd1z1uyfsbdiazj/ DSCN1065.MOV?dl=0 Technical Meeting 5 Jul 16
  • 14.
    Contact info Diego Graifenberg:graifenberg@gmail.com Technical Meeting 5 Jul 16