3. Estimation Levels - Introduction
Source: Barrie & Paulson, 1992
Different types of estimates are required as a project evolves
Conceptual & Preliminary Estimates
Prepared early in the project prior to engineering design completion (e.g., to
tell Owner whether the contemplated project scope is feasible)
Incorporate new information from design to obtain an updated estimate of
the project
Detailed Estimates
Prepared from completed plans and specifications
Definitive Estimates
Forecast the project cost within allowable limits from a combination of
conceptual and detailed information often including partial contract and
other procurement awards
6. Conceptual and Preliminary Estimates
Decide Feasibility
Great Variability According to Type
Categories:
Time-referenced Cost Indices
Cost-capacity Factors
Parameter Costs
Accuracy
Complexity
8. Cost Indices
Source: http://www.enr.com/features/conEco/
Show changes of costs over time by upgrading the cost of similar
facilities from the past to the present
Cost indices show the changes of a certain facility’s costs over time
Year 1913 = 100, …Year 2007 = 4432
If Facility A is similar to my ‘wish’ facility and I know the value of Facility A at 1913,
I can assume my ‘wish’ facility’s value at 2007.
9. Cost Indices
Source: http://www.enr.com/features/conEco/
Show changes of costs over time by upgrading the cost of similar
facilities from the past to the present
Used to determine the general construction costs of structures
Published periodically by Engineering News Record (ENR) and other
publications
ENR’s Building Cost Index (BCI): Changes of facility’s costs over time
Facility’s components are:
1,088 Board Feet of Lumber (2x4, 20-city Average)
1 Board Feet = 1’ x 1’ x 1” = 144 in3
(e.g., 2×4 - 10 ft long contains [(2×4)×10] × 12] = 960 in3 → 6.67 board feet)
2500 Pounds of Structural-Steel Shapes (20-city Average, Base Mill Price before 1996,
Fabricated after 1996)
1.128 Tons of Portland Cement (Bulk, 20-city Average)
66.38 Hours of Skilled Labor (20-City Average of Bricklayers, Carpenters, and Structural
Ironworkers)
11. Building Cost Index Data (Prior to 1990)
Source: http://www.enr.com/features/conEco/
12. Cost Indices Time Conversion
Example:
Warehouse Estimate: Assume you have an estimate to a similar warehouse
located nearby and completed in 1993 for a cost of $4,200,000. We are
planning to build a new warehouse in Feb. of 2007. The Building Cost
Index from ENR for 1993, relative to the base date of 1913, was 2996%
and Building Cost Index from ENR for Feb. 2007 is 4432%. What is the
estimated project cost if you establish the estimate using Building Cost
Index from ENR?
Adapted from: Barrie & Paulson, 1992
13. Cost Indices Time Conversion
What Information Do We Need?
Current Building Cost Index (Feb. 2007) = 4432
Building Cost Index for Year 1993 = 2996
Similar Facility’s Cost at Year 1993 = $4,200,000
We Convert From One Base Period to Another
2996 : $4,200,000 = 4432 : $X
$X = (4432/2996) * $4,200,000 = $6,213,084
Adapted from: Barrie & Paulson, 1992
14. Cost Indices Component Calculations
ENR’s Construction Cost Index:
Used when labor costs are a high proportion of total cost
Components:
1,088 Board Feet of Lumber (2x4, 20-city Average)
1 Board Feet = 1’ x 1’ x 1” = 144 in3
2,500 Pounds of Structural-Steel Shapes (20-city Average, Base Mill Price Before
1996, Fabricated after 1996)
1.128 Tons of Portland Cement (Bulk, 20-city Average)
200 Hours of Common Labor (20-city Average)
Source: http://www.enr.com/features/conEco/
costIndexes/constIndexHist.asp
15. Cost Indices Use and Accuracy
Accuracies Within 20% to 30% of Actual Costs
Negligible Time and Effort
Valuable for Preliminary Planning
16. Cost Indices - Limitations
Adapted from: Barrie & Paulson, 1992
Problems could arise if the proportions of the input components (e.g.,
lumber) in a building type cost index do not reflect the resources used on the
project in question
E.g., about 40 % of the costs in a petrochemical project is in piping (pipe and pipe
fitters)
Problems could arise if the project on which the Index is based has very little
in common with the project under consideration
Some types of indices do not consider factors such as: productivity, changes
in technology, and competitiveness of contractors
18. Cost-Capacity Factor
Apply to changes in size, scope, or capacity of projects of
similar types
Reflect the nonlinear increase in cost with size (economies
of scale, learning curves)
C2 = C1 (Q2/Q1) x
Where
C2 = estimated cost of the new facility w/capacity Q2
C1 = known cost of facility of capacity Q1
x = the cost-capacity factor for this type of work
19. Cost-Capacity Factor
Source: Barrie & Paulson, 1992
Q is a parameter that reasonably reflects the size of the facility
(e.g., barrels per day produced by a refinery, tons of steel per day
produced by a steel mill, gross floor area for a warehouse)
X is an empirically derived factor based on well-documented
historical records for a variety of different types of projects
20. Cost-Capacity Factor Example
Example Revisit:
Warehouse Estimate: Assume you have an estimate to a similar warehouse
located nearby and completed in 1993 for a cost of $4,200,000. We are
planning to build a new warehouse in Feb. of 2007. The ENR index for
1993, relative to the base date of 1913, was 2996% and the ENR index for
2007 is 4432%.
Consider the cost-capacity factor x = 0.8 for a warehouse.
The above warehouse has a usable area of 120,000 square feet
The prospective owner for the new warehouse wants a structure with a
usable area of 150,000 square feet
21. Cost-Capacity Factor Example
What Information Do We Need?
Q2/Q1 = 150,000/120,000 = 1.25
Cost-capacity factor x = 0.8
Known cost = $4,200,000
C2 = $4,200,000 * (1.25)0.8 = $5,020,851
A 25% more capacity implies only 20% more costs
22. Combining Cost Indices & Cost-
Capacity Factor
Combine Cost Indices & Cost Capacity Factors to take into
account changes in both time & capacity
C2 = C1 (Ib / Ia) (Q2 / Q1)x
Where
Ib = Index number “Now” or present time.
Ia = Index number at that time
Source: Barrie & Paulson, 1992
23. Cost Indices & Cost-Capacity Factor
Example
Example Revisit:
Warehouse Estimate: Assume you have an estimate to a similar warehouse
located nearby and completed in 1993 for a cost of $4,200,000. We are
planning to build a new warehouse in Feb. of 2007. The ENR index for
1993, relative to the base date of 1913, was 2996% and the ENR index for
2007 is 4432%.
Consider the cost-capacity factor x = 0.8 for a warehouse.
The above warehouse has a usable area of 120,000 square feet
The prospective owner for the new warehouse wants a structure with a
usable area of 150,000 square feet
24. C2 = 4,200,000 * (4432/2996) * (150,000/120,000)0.8 = $7,188,731
Cost Indices & Cost-Capacity Factor
Example
26. Parameter Costs Source Data
Commonly used in building construction
ENR “Quarterly Cost Roundup”
R.S. Means “Means Square Foot Costs”
Source: RS Means, Square Foot Costs Data, 2006
27. Parameter Costs Characteristics
Source: Barrie & Paulson, 1992
Relates all costs of a project to just a few physical measures,
or “Parameters”, that reflect the size or scope of the project
E.g., warehouse - the “Parameter” would be “Gross Enclosed Floor
Area”
all costs represented by X ($/S.F) → total cost = X ($/S.F.) × the
project’s gross enclosed floor area (S.F.)
With good historical records on comparable structures,
parameter costing can give reasonable levels of accuracy for
preliminary estimates
28. Means Square Foot Cost
Costs per Square Foot
Type of Facility (total 23,000 S.F apartment with 3 stories)
Source: RS Means, Square Foot Costs Data, 2006
Story Height = 10’ and No Basement
29. Costs per S.F. of Floor Area
Means Square Foot Cost
Source: RS Means, Square Foot Costs Data, 2006
23,000 S.F
30. Costs per S.F. of Floor Area
Means Square Foot Cost
Source: RS Means, Square Foot Costs Data, 2006
23,000 S.F
31. Costs per S.F. of Floor Area
Means Square Foot Cost
Source: RS Means, Square Foot Costs Data, 2006
Exterior
wall
variation
32. Costs per S.F. of Floor Area
Means Square Foot Cost
Source: RS Means, Square Foot Costs Data, 2006
Exterior
wall
variation
Base Cost =
129.65 $/S.F
33. Costs per S.F. of Floor Area
Means Square Foot Cost
Source: RS Means, Square Foot Costs Data, 2006
Perimeter
&
Height
Adjustment
34. Costs per S.F. of Floor Area
Means Square Foot Cost
Source: RS Means, Square Foot Costs Data, 2006
Perimeter
&
Height
Adjustment
35. Costs per S.F. of Floor Area
Means Square Foot Cost
Source: RS Means, Square Foot Costs Data, 2006
Basement
36. Costs per S.F. of Floor Area
Means Square Foot Cost
Source: RS Means, Square Foot Costs Data, 2006
Additives
37. Costs per S.F. of Floor Area
Means Square Foot Cost
Source: RS Means, Square Foot Costs Data, 2006
38. Means Square Foot Cost
Information: Detail Specs for the Cost
Source: RS Means, Square Foot Costs Data, 2006
39. Means Square Foot Cost
Information: Sub-total, Fees, and Total
Source: RS Means, Square Foot Costs Data, 2006
40. Parameter Cost Example
Source: RS Means, Square Foot Costs Data, 2006
What is the Cost for an apartment building (7 Story) if the
perimeter of the building is 502 L.F. and the story height is
11’-4”? Assume that the apartment building has decorative
concrete block on the east, west & south walls. The north
walls external finish is brick with concrete block backup.
The area of each floor of the apartment building 11,460 S.F.
The basement floor area s 4,200 S.F. Please use the Means
Square Foot Cost to obtain an estimate. The building frame
is steel. The apartment building is located in Atlantic City,
New Jersey, Zip Code 07410.
42. Characteristics of the Apartment Building
60’ x 191’ = 11,460 S.F./Floor
2 * [191’ + 60’] = 502 L.F. Perimeter
7 Floors
Exterior Walls:
North wall: Face brick w/ concrete block backup
East, West & South walls: Decorative Concrete Block
Story Height: 11’-4”
Basement Area: 4,200 S.F
Steel Frame
Located in Atlantic City, New Jersey, Zip Code 07410
Coefficients are determined from Model Number M.020 for Apartment,
4-7 Story type (Refer to RS Means (2006) - Square Foot Costs, page 80)
Source: RS Means, Square Foot Costs Data, 2006
Parameter Cost Example
43. Source: RS Means, Square Foot Costs Data, 2006
RS Means (2006) – Square
Foot Costs, Page 80
Choose
type
Parameter Cost Example
44. Source: RS Means, Square Foot Costs Data, 2006
RS Means (2006) – Square
Foot Costs, Page 80
S.F. Area = 11,460 * 7 = 80220
L.F. Perimeter = 502
Parameter Cost Example
45. Source: RS Means, Square Foot Costs Data, 2006
What should be adjusted when the cost is to be established
by using the Means Square Foot Cost Method?
Exterior Wall Variation
Perimeter Adjustment
Story Height Adjustment
Basement Addition
Location Modifier
Parameter Cost Example
46. Source: RS Means, Square Foot Costs Data, 2006
Basic SF Costs for 80,000 S.F
apartment building with Face Brick
w/ Concrete Block Backup
Basic SF Costs for 80,000 S.F
apartment building with Decorative
Concrete Block
Parameter Cost Example
47. Basic SF Cost in R.S. Means for S.F Area=80000, L.F Perimeter = 530, Story
Height = 10’ & No Basement
$128.35/SF when exterior walls are Brick w/ Concrete Block Backup (North)
$122.25/SF when exterior walls are Decorative Concrete Block (East, West, south)
Source: RS Means, Square Foot Costs Data, 2006
Parameter Cost Example
N
48. Basic SF Cost in R.S. Means for S.F Area=80000, L.F Perimeter = 530, Story
Height = 10’ & No Basement
$128.35/SF when exterior walls are Brick w/ Concrete Block Backup (North)
$122.25/SF when exterior walls are Decorative Concrete Block (East, West, south)
North wall makes up:
[191’/502’] x 100 = 38.04 % of total building perimeter
East, West & South walls make up:
[(191’+2x60’)/502’] x 100 = 61.96 % of total building perimeter
Exterior Wall Variation
[$128.35 * 38.04%] + [$122.25 * 61.96%] = $124.6/S.F.
Source: RS Means, Square Foot Costs Data, 2006
Parameter Cost Example
49. Source: RS Means, Square Foot Costs Data, 2006
What should be adjusted when the cost is to be established
by using the Means Square Foot Cost Method?
Exterior Wall Variation
Perimeter Adjustment
Story Height Adjustment
Basement Addition
Location Modifier
Parameter Cost Example
51. Exterior Wall Variation :
[$128.35 * 38.04%] + [$122.25 * 61.96%] = $124.6/S.F.
Perimeter Adjustment:
Apartment building perimeter is 28 L.F (530 -502) less than the M.020 model building in RS Means
Perimeter adjustment factor: $2.65 per 100 L.F
$124.6 – ( $2.65/100 L.F * 28 L.F ) = $123.9/S.F
Height Adjustment:
Apartment building story height is 1’ 4” (11’ 4’’-10’) more than the M.020 model building in RS Means
Height adjustment factor: $1.20 per ft
$123.9 + $1.20 * 1.3 = $125.5/S.F.
Apartment Building initial total cost: $125.5 * 80,220 S.F = $10,067,610
Source: RS Means, Square Foot Costs Data, 2006
Parameter Cost Example
52. Source: RS Means, Square Foot Costs Data, 2006
What should be adjusted when the cost is to be established
by using the Means Square Foot Cost Method?
Exterior Wall Variation
Perimeter Adjustment
Story Height Adjustment
Basement Addition
Location Modifier
Parameter Cost Example
54. Apartment Building initial total cost: $125.5 * 80,220 S.F = $10,067,610
Basement Addition:
Apartment building has 4,200 S.F basement
Basement Addition Factor: $27.30 per S.F of basement area
Basement added cost : $10,067,610 + $27.30 * 4,200 S.F = $10,182,270
Source: RS Means, Square Foot Costs Data, 2006
Parameter Cost Example
55. Source: RS Means, Square Foot Costs Data, 2006
What should be adjusted when the cost is to be established
by using the Means Square Foot Cost Method?
Exterior Wall Variation
Perimeter Adjustment
Story Height Adjustment
Basement Addition
Location Modifier
Parameter Cost Example
57. Basement Addition:
$10,182,270
Location Modifier for Residential Bldg: 1.13 (Refer to RS Means (2006) -
Square Foot Costs, page 455)
Apartment building modified total cost: $10,182,270 * 1.13 = $ 11,505,965
Source: RS Means, Square Foot Costs Data, 2006
Parameter Cost Example
58. Parameter Cost Example
Source: RS Means, Square Foot Costs Data, 2006
What is the Cost for an apartment building (7 Story) if the
perimeter of the building is 502 L.F. and the story height is
11’-4”? Assume that the apartment building has decorative
concrete block on the east, west & south walls. The north
walls external finish is brick with concrete block backup.
The area of each floor of the apartment building 11,460 S.F.
The basement floor area s 4,200 S.F. Please use the Means
Square Foot Cost to obtain an estimate. The building frame
is steel with an observed age of 20 years. The apartment
building is located in Atlantic City, New Jersey, Zip Code
07410.
59. Source: RS Means, Square Foot Costs Data, 2006
What should be adjusted when the cost is to be established by using the
Means Square Foot Cost Method?
Exterior Wall Variation
Perimeter Adjustment
Story Height Adjustment
Basement Addition
Location Modifier
Depreciation Adjustment
Parameter Cost Example
63. Estimation Levels - Revisit
Source: Barrie & Paulson, 1992
Different types of estimates are required as a project evolves
Conceptual & Preliminary Estimates
Prepared early in the project prior to engineering design completion (to tell
Owner whether the contemplated project scope is feasible)
Incorporate new information from design to obtain an updated estimate of
the project
Detailed Estimates
Prepared from completed plans and specifications
Definitive Estimates
Forecast the project cost within allowable limits from a combination of
conceptual and detailed information often including partial contract and
other procurement awards
65. Important General Lesson
Precision in detailed estimates does not mean accuracy!
More an art than a science
Detailed quantitative estimates possible – but ignore important qualitative factors
Have differing ranges of uncertainties
Actual costs depend on systemic complexity
Two types of complexity at issue
Detail complexity (myriad components required)
System complexity (dynamic interactions, etc.)
Always consider:
What are assumptions behind the estimate?
What factors are being ignored?
How might these factors change the estimate?
66. Detailed Estimates
After most or all of the detail design work is complete,
approximate estimates are refined using detailed estimates
Engineer’s Detailed Estimates
Bid Detailed Estimates
68. Engineer’s Detailed Estimates
Part of actual bid documents
Who? - owner, consultant, CM, or design-build team
Use unit prices databases
Estimate = Σ [Quantity] × [Unit Prices]
RS Means or other sources
Unit prices as result of average industry standards
69. Engineer’s Detailed Estimates
Source: RS Means, Building Construction Cost Data, 2006
RS Means (2006) – Building Construction Cost Data, Page 84
Unit price (RS Means) = Mat. + Lab. + Equip. + Overhead + Profit
70. Engineer’s Detailed Estimates
Part of actual bid documents
Who? – owner, consultant, or CM
Use unit prices databases
Estimate = Σ[Quantity] × [Unit Prices]
RS Means or other sources
Unit prices as result of average industry standards
No lump-sum subcontract quotations
May be simplified number of line items (e.g., mark-up: not detailed)
73. Bid Detailed Estimates
Contractor’s estimate low enough to obtain the work, yet high enough to make
profit
Who? – contractor
More detail depending upon the contractor’s own procedures
Overall unit prices (past) → detailed categories (present)
Often relies on
Historical productivity data for company
Intuition on speed of movement
Quantity takeoff for most important items
Subcontractor bids
Sometimes less detailed than engineer’s estimates - subcontractors from 30% to 80% of
the project
75. Bid Detailed Estimates
Is estimating a streamlined process?
A look at bids received for a typical project in a competitive area will
sometimes show more than 50% difference between the low and the high
bidders
76. Estimation Levels - Revisit
Source: Barrie & Paulson, 1992
Different types of estimates are required as a project evolves
Conceptual & Preliminary Estimates
Prepared early in the project prior to engineering design completion (to tell
Owner whether the contemplated project scope is feasible)
Incorporate new information from design to obtain an updated estimate of
the project
Detailed Estimates
Prepared from completed plans and specifications
Definitive Estimates
Forecast the project cost within allowable limits from a combination
of conceptual and detailed information often including partial
contract and other procurement awards
78. Definitive Estimates
There comes a time when a definitive estimate can be prepared that will forecast
the final project cost with little margin for error…
This error can be minimized through the proper addition of an evaluated
contingency
Engineer’s estimates can complete this process
The proper time to classify an estimate as ‘definitive’ will vary according to the
characteristics of the project. For example:
Traditional
Unit-price
Professional CM
Design-Build
79. Definitive Estimates:
Traditional & Unit Price
Start Contract
Detailed design
Preliminary design
Start Contract
Detailed design
Preliminary design
DBB definitive estimate
Unit Price definitive estimate
82. Cost Classification
Direct Cost
Labor Cost
Direct Labor
Indirect Labor
Material Cost
Equipment Cost
Subcontractor Price
Indirect Cost (i.e., Job Overhead)
Project Overhead
Markup
General Overhead
Profit
Contingency
Source: Shtub et al., 1994
83. Cost Classification - Direct Cost
Labor Cost
Direct Labor Cost
Difficult to evaluate precisely but all effort is done to get an accurate estimate as possible
Greatest amount of uncertainty in project estimation
Indirect Labor Cost
Costs that are additional to the basic hourly rates (e.g., tax, insurance, fringe benefits)
Substantial in amount: add 25 to 50 percent to direct labor costs
Commonly used approach adds indirect labor costs as a percentage to the total direct labor costs or for
each major work category
Material Cost
All materials that are utilized in the finished structure.
Equipment Cost
Costs Includes: ownership, lease or rental expenses, and operating costs
Subcontractor Price
Includes quotations from all subcontractors working on the project
Quotations submitted by the subcontractor usually require extensive review by the general
contractor’s estimator to determine what they include & do not include
Source: Clough et al., 2005; Barrie & Paulson, 1992
84. Source: Clough et al., 2005
Cost Classification – Indirect Cost
Project Overhead (i.e., Job Overhead)
Costs that do not pertain directly to any given construction work
Generally constitutes 5-15 percent of the total project cost
Costs computed by listing & evaluating each item of overhead individually
Examples of typical items included:
Job Mobilization, Project Manager, General Superintendent, Nonworking Foremen, Heat,
Utilities, Storage Buildings, Field Office Supplies, Job Telephone, Computer Equipment &
Software, Computer Networking & Internet Connectivity, Small Tools, Permits & Fees,
Special Insurance, Builder’s Risk Insurance, Security Clearances, Material & Load Tests,
Storage Area Rental, Protection of Adjoining Property, Field Offices, Parking Areas, Legal
Expenses, Surveys, Engineering Services.
85. Source: Clough et al., 2005
Cost Classification – Markup
Markup
Added at the close of the estimating process
Varies between 5 to 20 percent of the job cost
Reflects the contractor’s appraisal of the probability of being the lowest
bidder for the project & the chances of making a reasonable profit
Factors considered when deciding on a job markup include: project size &
complexity, provisions of the contract documents, difficulties inherent in
the work, identities of the owner & architect/engineer
Include allowance for:
General Overhead or Office Overhead
Includes costs that are incurred to support the overall company construction program
Normally included in the bid as a percentage of the total estimated job cost
Examples of general business expenses include: office rent, office insurance, heat, electricity,
office supplies, furniture, telephone & internet, legal expenses, donations, advertising, travel,
association dues, and the salaries of executives & office employees
Profit
Contingency
89. Detailed Estimates - Methodology
Stage 1: Quantity takeoff
Decomposition into items, measurement of quantities
Challenges: tremendous detail complexity
Stage 2: Direct Cost contribution
Σ[Quantity] × [Unit Price]
Challenge: determination unit price (based on historical data)
Example:
Item unit quantity Unit price price
Reinforced steel lb 6,300 0.60 $ 3,780
90. Labor Costs
Categorized Bid Estimate (not overall unit prices)
Basic Unit Labor Cost = P / LP ($/unit)
P = Price of all money elements ($/hours)
LP = Labor Productivity (units/hour)
Total Labor Cost = Q * P/LP
Q = Total quantity of work
Estimation of labor costs particularly tricky
Prices: In United States, highly detail intensive
Productivity: Many qualitative components
91. Labor Cost - Prices Related
Components
Wages (varies by area, seniority, …)
Insurance (varies w/contractor record, work type)
Social security benefits
Fringe benefits (health…)
Wage premiums (e.g., overtime, shift-work differentials, hazardous work)
92. Labor Cost - Productivity
Difficult but critical
High importance of qualitative factors (environment, morale, fatigue,
learning, etc)
The primary means by which to control labor costs
Historical data available
Firm updated database
Department of Labor, professional organizations, state governments
= P / LP ($/unit)
96. Concluding Remarks
Functions of Estimating
Could Assess cost of construction from the conceptual design phase
(Owner, Designer & Sometimes Contractor ). Feedback to
Conceptual Design for Alternative Architecture
Feasibility of the Project
Project / Company Alignment of Objectives, Constraints, Strategic
Goals and Policies
Provide the basis for bidding & contracting (Contractor)
Provide a baseline for cost control and post project evaluation
(Owner & Contractor)
97. Concluding Remarks
In Converting an Estimate to a Control Budget, Consider:
The organization and categorization of costs suitable for preparing an
estimate are often not compatible with realistic field cost control (e.g.,
might be convenient for the owner)
Estimates necessarily deal in averages, whereas tighter standards are
sometimes desirable for control purposes