Estimate Considerations
2
Estimate Considerations.
Project Size.
Project Quality.
Project Location.
Time.
Market Conditions.
Steps for Preparing a Detailed Estimate.
Today’s Lecture
Building Economy ARE 431
Dr. Mohammad A. Hassanain 2
3
Estimate Considerations
Every estimate, whether it is generated in the conceptual
phase of a project or at bidding time, must consider a
number of issues.
The price of the project is affected by a number of factors:
The size of the project.
The quality of the project.
The location of the project.
The construction start and duration.
Market conditions.
The accuracy of an estimate is directly affected by the
ability of the estimator to properly analyze these basic
issues.
4
Project Size
As a general rule in construction, as a project gets bigger,
the cost of the project increases.
The size of the project is a factor of the owner’s
requirements.
Size is handled differently depending on the stage in the
project’s life at which the estimate is being conducted.
At the conceptual phase, size will be an issue of basic
capacity, such as:
Apartment units for a real estate developer.
Miles of roadway for a highway engineer.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 3
5
Project Size
As the project becomes a little better understood, the
project’s size will begin to be quantified more accurately.
The basic capacities will begin to be thought of in terms of
more specific parameters such as:
Square footage of floor or roof.
Quantity of excavation.
Further design leads to more specific quantities, eventually
ending with exact numbers for every project item.
6
Project Size
The principle of economy of scale must be considered when
addressing project size
Essentially, as projects gets bigger they get more
expensive.
The larger the project, the more efficiently people
and equipment can be utilized.
As people repeat a task, particularly many times
over and over, they get better and faster at it, thus
reducing the cost of labor.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 4
7
Project Size
On large commercial buildings and heavy engineering
projects, worker productivities are plotted into what are
called Learning curves.
Number of Units
Time
Required
Per Unit
Learning Curve
Learning curves show
that as the number of
repetitions or units a
worker needs to
accomplish increases, the
time required to perform
that repetition decreases.
8
Project Quality
As the quality and complexity of a project increases, so does
the project’s cost.
A high level of quality may be required for:
Aesthetic reasons as specified by the project
architect.
The safety of the project users or the public.
As the expected quality of a project increases, the cost of
providing this quality increases as well.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 5
9
Project Location
The location of the project is a major consideration in the
preparation of an estimate.
Depending on the location, a great variation exists in:
The purchasing of materials and their delivery:
material costs are a factor of availability,
competition between suppliers, and access to
efficient methods of transportation.
Rental or purchase of equipment.
The cost of labor: the cost of labor is a factor of the
level of training found at the project location. On
some projects, the number and the skill levels of
workers are not available locally, so labor forces
have to be imported.
10
Project Location
The cost of constructing projects in different locations can
be predicted by establishing what are called location
indices for different cities and parts of the country.
An index is created for a particular city by comparing the
cost of labor, equipment, and material for that city to the
national average.
This allows an estimator using national average costs to
adjust the estimate to a particular location.
Most major design and construction companies have
developed an accurate set of location indices which they
use for their pricing, or they buy this cost data from national
pricing suppliers.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 6
11
Time
The time at which a project is built can have a major impact
on the cost of the project.
Since estimates, by definition, are prepared in advance of
the actual construction, the estimator must “project” or
“forecast” to the future what the cost of the work will be.
The estimate must predict what the cost of material and
labor will be when these costs will be paid – not when the
estimate is prepared.
Initial project estimates are often two or more years in
advance of the start of construction, and if the project takes
three years to construct, the estimator therefore must
identify costs as far as five years into the future.
12
Time
Historical indices can be used to adjust the cost of a past
project to one today.
This concept is similar to the location indices.
This adjustment combined with the location adjustments
allow an estimator to estimate the cost of a new project
today in one location by looking at a similar project built
several years ago and hundreds of miles away.
Sometimes, it is difficult to project with accuracy what the
index will be for a future year, so the best an estimator can
do is to look at the current trends and anticipate future labor
and material prices.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 7
13
Other Market Conditions
An estimator who accurately incorporates the four major
considerations that we just identified:
Project size.
Project quality.
Project location.
Time.
Will have an estimate that reflects the fair value of the
project. Assuming a normal market without any unusual
circumstances, this estimate should reflect the price to be
paid.
14
Other Market Conditions
In a market without much work, contractors may bid for a
project with little profit to keep their staff employed.
On complex projects, contractors may bid the work low in
the hopes of making additional profit on future change
orders.
Sometimes, contractors provide very competitive prices
when they enter a new market or work with a new owner.
These issues are difficult to quantify, but should be
considered in the preparation of the estimate.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 8
15
Steps for Preparing a Detailed Estimate
1. Review the scope of the project.
Consider the effect of location (availability of
electric power and water supply), traffic, availability
of skilled and common labor, available storage
space on costs.
2. Determine quantities.
Perform a material quantity takeoff for all work
items in the project, and record the quantity and
the unit of measure for each item.
3. Price material. Material cost = Quantity x Unit price
16
Steps for Preparing a Detailed Estimate
4. Price labor.
Based on probable labor production rates and crew
sizes, determine labor costs:
Labor cost = (Quantity x Labor rate)/Labor production rate
5. Price equipment.
Based on probable equipment production rates,
determine equipment costs:
Equipment cost = (Quantity x Equipment rate)/Equipment
production rate
Building Economy ARE 431
Dr. Mohammad A. Hassanain 9
17
Steps for Preparing a Detailed Estimate
6. Obtain specialty contractors’ bid.
Receive and tabulate the costs for each specialty
contractor on the project.
7. Calculate taxes, insurance and overhead.
Tabulate the costs of material and labor taxes,
insurance and job overhead.
8. Add an amount for contingency.
Add costs for potential unforeseen work based on
the amount of risk.
18
Steps for Preparing a Detailed Estimate
9. Add an amount for profit.
Add costs for compensation for performing the
work in accordance with the bid documents.

More Related Content

What's hot

Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...
Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...
Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...Galala University
 
ARCHITECTS (PROFESSIONAL CONDUCT) REGULATIONS, 1989.pptx
ARCHITECTS (PROFESSIONAL CONDUCT) REGULATIONS, 1989.pptxARCHITECTS (PROFESSIONAL CONDUCT) REGULATIONS, 1989.pptx
ARCHITECTS (PROFESSIONAL CONDUCT) REGULATIONS, 1989.pptxChinmoyGhosh40
 
Architecture Professional practice
Architecture Professional  practice Architecture Professional  practice
Architecture Professional practice Ar. Mukunda K.S
 
Architecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliationArchitecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliationAditi Garg
 
Users’ analysis
Users’ analysisUsers’ analysis
Users’ analysisFatema Qaed
 
Understanding Complex Buildings.
Understanding Complex Buildings.Understanding Complex Buildings.
Understanding Complex Buildings.UCL
 
22006361-The-Council-of-Architecture.ppt
22006361-The-Council-of-Architecture.ppt22006361-The-Council-of-Architecture.ppt
22006361-The-Council-of-Architecture.pptvritisachdeva1
 
Architectural thesis-manual
Architectural thesis-manualArchitectural thesis-manual
Architectural thesis-manualLawrence Ting
 
Architecture design housing ppt
Architecture design housing pptArchitecture design housing ppt
Architecture design housing pptSalwaShah3
 
bus terminal design
bus terminal designbus terminal design
bus terminal designaklilu11
 
Modular High Rise Construction.pptx
Modular High Rise Construction.pptxModular High Rise Construction.pptx
Modular High Rise Construction.pptxGeethikaSV
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
Valuation - professional prractice and valuation
Valuation - professional prractice and valuationValuation - professional prractice and valuation
Valuation - professional prractice and valuationKavin Raval
 
internship report on architecture
internship report on architectureinternship report on architecture
internship report on architecturebiruktigistu1
 
Site analysis for a neighborhood
Site analysis for a neighborhoodSite analysis for a neighborhood
Site analysis for a neighborhoodAjit Katari
 

What's hot (20)

Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...
Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...
Architectural Design Concepts Approaches - كونسيبت التصميم المعمارى و الفكرة ...
 
ARCHITECTS (PROFESSIONAL CONDUCT) REGULATIONS, 1989.pptx
ARCHITECTS (PROFESSIONAL CONDUCT) REGULATIONS, 1989.pptxARCHITECTS (PROFESSIONAL CONDUCT) REGULATIONS, 1989.pptx
ARCHITECTS (PROFESSIONAL CONDUCT) REGULATIONS, 1989.pptx
 
Architecture Professional practice
Architecture Professional  practice Architecture Professional  practice
Architecture Professional practice
 
Architecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliationArchitecture practice- arbitration and conciliation
Architecture practice- arbitration and conciliation
 
Building Economics
Building Economics Building Economics
Building Economics
 
Users’ analysis
Users’ analysisUsers’ analysis
Users’ analysis
 
Redevelopment of Buildings
Redevelopment of Buildings Redevelopment of Buildings
Redevelopment of Buildings
 
uap doc 207-208
uap doc 207-208uap doc 207-208
uap doc 207-208
 
Understanding Complex Buildings.
Understanding Complex Buildings.Understanding Complex Buildings.
Understanding Complex Buildings.
 
22006361-The-Council-of-Architecture.ppt
22006361-The-Council-of-Architecture.ppt22006361-The-Council-of-Architecture.ppt
22006361-The-Council-of-Architecture.ppt
 
Architectural thesis-manual
Architectural thesis-manualArchitectural thesis-manual
Architectural thesis-manual
 
Architecture design housing ppt
Architecture design housing pptArchitecture design housing ppt
Architecture design housing ppt
 
bus terminal design
bus terminal designbus terminal design
bus terminal design
 
Modular High Rise Construction.pptx
Modular High Rise Construction.pptxModular High Rise Construction.pptx
Modular High Rise Construction.pptx
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Valuation - professional prractice and valuation
Valuation - professional prractice and valuationValuation - professional prractice and valuation
Valuation - professional prractice and valuation
 
Presentation on Redevelopment
Presentation on RedevelopmentPresentation on Redevelopment
Presentation on Redevelopment
 
internship report on architecture
internship report on architectureinternship report on architecture
internship report on architecture
 
Professional practice
Professional practiceProfessional practice
Professional practice
 
Site analysis for a neighborhood
Site analysis for a neighborhoodSite analysis for a neighborhood
Site analysis for a neighborhood
 

Viewers also liked

Construction Estimate worksheet
Construction Estimate worksheetConstruction Estimate worksheet
Construction Estimate worksheetJoseph V. Scorese
 
Composite Crews in Construction Cost Estimating
Composite Crews in Construction Cost Estimating Composite Crews in Construction Cost Estimating
Composite Crews in Construction Cost Estimating Doina Dobre, P.Eng, GSC
 
22274325 engineer-s-estimate-construction-of-technical-building-for-national-...
22274325 engineer-s-estimate-construction-of-technical-building-for-national-...22274325 engineer-s-estimate-construction-of-technical-building-for-national-...
22274325 engineer-s-estimate-construction-of-technical-building-for-national-...imaduddin91
 
Construction Cost Estimating - Quality Cost Estimating
Construction Cost Estimating - Quality Cost EstimatingConstruction Cost Estimating - Quality Cost Estimating
Construction Cost Estimating - Quality Cost EstimatingDoina Dobre, P.Eng, GSC
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementYudha Pratama, PMP
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1Anand Bobade
 

Viewers also liked (8)

Construction Estimate worksheet
Construction Estimate worksheetConstruction Estimate worksheet
Construction Estimate worksheet
 
Construction Cost Estimating
Construction Cost Estimating Construction Cost Estimating
Construction Cost Estimating
 
Composite Crews in Construction Cost Estimating
Composite Crews in Construction Cost Estimating Composite Crews in Construction Cost Estimating
Composite Crews in Construction Cost Estimating
 
ACH 216 Lecture 04c (Project Award)
ACH 216 Lecture 04c (Project Award)ACH 216 Lecture 04c (Project Award)
ACH 216 Lecture 04c (Project Award)
 
22274325 engineer-s-estimate-construction-of-technical-building-for-national-...
22274325 engineer-s-estimate-construction-of-technical-building-for-national-...22274325 engineer-s-estimate-construction-of-technical-building-for-national-...
22274325 engineer-s-estimate-construction-of-technical-building-for-national-...
 
Construction Cost Estimating - Quality Cost Estimating
Construction Cost Estimating - Quality Cost EstimatingConstruction Cost Estimating - Quality Cost Estimating
Construction Cost Estimating - Quality Cost Estimating
 
Pmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost managementPmp – pmbok 5th edition chapter7 project cost management
Pmp – pmbok 5th edition chapter7 project cost management
 
PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1PMP Chap 7 - Project Cost Management - Part 1
PMP Chap 7 - Project Cost Management - Part 1
 

Similar to 3 estimate considerations

Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to EstimationMuthanna Abbu
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdfJunaidMughal34
 
4. offer tendering - site
4. offer   tendering - site4. offer   tendering - site
4. offer tendering - siteAbdulaziz Kaya
 
Suvarna consultancy services
Suvarna consultancy services Suvarna consultancy services
Suvarna consultancy services Ashok Tundare
 
1 introduction to cost estimating
1 introduction to cost estimating1 introduction to cost estimating
1 introduction to cost estimatingAli Juma Albahrani
 
Building Construction 4. offer tendering - site
Building Construction 4. offer   tendering - siteBuilding Construction 4. offer   tendering - site
Building Construction 4. offer tendering - siteHamdija Velagic
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONAr Naveen Naveen
 
Reduction of cost in construction
Reduction of cost in constructionReduction of cost in construction
Reduction of cost in constructionSaravana murthy
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET Journal
 
46R-11 Skills & Knowledge of Cost Estimators.pdf
46R-11 Skills & Knowledge of Cost Estimators.pdf46R-11 Skills & Knowledge of Cost Estimators.pdf
46R-11 Skills & Knowledge of Cost Estimators.pdfssuserad21d8
 
8. implementation (2) cost management
8. implementation (2)   cost management8. implementation (2)   cost management
8. implementation (2) cost managementDania Abdel-aziz
 
Module Three Exercises 2BA 1200 Foundations of Business.docx
Module Three Exercises  2BA 1200 Foundations of Business.docxModule Three Exercises  2BA 1200 Foundations of Business.docx
Module Three Exercises 2BA 1200 Foundations of Business.docxroushhsiu
 

Similar to 3 estimate considerations (20)

Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf
 
2 types of estimates
2 types of estimates2 types of estimates
2 types of estimates
 
Estimation
EstimationEstimation
Estimation
 
4. offer tendering - site
4. offer   tendering - site4. offer   tendering - site
4. offer tendering - site
 
Suvarna consultancy services
Suvarna consultancy services Suvarna consultancy services
Suvarna consultancy services
 
1 introduction to cost estimating
1 introduction to cost estimating1 introduction to cost estimating
1 introduction to cost estimating
 
ESTIMATING.pdf
ESTIMATING.pdfESTIMATING.pdf
ESTIMATING.pdf
 
Building Construction 4. offer tendering - site
Building Construction 4. offer   tendering - siteBuilding Construction 4. offer   tendering - site
Building Construction 4. offer tendering - site
 
5.2 unit pricing
5.2 unit pricing5.2 unit pricing
5.2 unit pricing
 
5.1 quantity take-off
5.1 quantity take-off5.1 quantity take-off
5.1 quantity take-off
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
SPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATIONSPECIFICATION AND ESTIMATION
SPECIFICATION AND ESTIMATION
 
4.1 conceptual estimates
4.1 conceptual estimates4.1 conceptual estimates
4.1 conceptual estimates
 
Reduction of cost in construction
Reduction of cost in constructionReduction of cost in construction
Reduction of cost in construction
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
46R-11 Skills & Knowledge of Cost Estimators.pdf
46R-11 Skills & Knowledge of Cost Estimators.pdf46R-11 Skills & Knowledge of Cost Estimators.pdf
46R-11 Skills & Knowledge of Cost Estimators.pdf
 
8. implementation (2) cost management
8. implementation (2)   cost management8. implementation (2)   cost management
8. implementation (2) cost management
 
Module Three Exercises 2BA 1200 Foundations of Business.docx
Module Three Exercises  2BA 1200 Foundations of Business.docxModule Three Exercises  2BA 1200 Foundations of Business.docx
Module Three Exercises 2BA 1200 Foundations of Business.docx
 
4.3 assemblies estimating
4.3 assemblies estimating4.3 assemblies estimating
4.3 assemblies estimating
 

More from Ali Juma Albahrani

More from Ali Juma Albahrani (14)

10 depreciation and depletion
10 depreciation and depletion10 depreciation and depletion
10 depreciation and depletion
 
9 benefit to cost ratio method
9 benefit to cost ratio method9 benefit to cost ratio method
9 benefit to cost ratio method
 
8.the rate of return method
8.the rate of return method8.the rate of return method
8.the rate of return method
 
7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method
 
7.1 present worth method
7.1 present worth method7.1 present worth method
7.1 present worth method
 
7.0 life cycle costing
7.0 life cycle costing7.0 life cycle costing
7.0 life cycle costing
 
6.4 multiple factors
6.4 multiple factors6.4 multiple factors
6.4 multiple factors
 
6.3 use of interest tables
6.3 use of interest tables6.3 use of interest tables
6.3 use of interest tables
 
6.2 cash flow - time diagrams
6.2 cash flow - time diagrams6.2 cash flow - time diagrams
6.2 cash flow - time diagrams
 
6.1 simple versus compound interest
6.1 simple versus compound interest6.1 simple versus compound interest
6.1 simple versus compound interest
 
5.3 estimate setup
5.3 estimate setup5.3 estimate setup
5.3 estimate setup
 
5.0 detailed estimating
5.0 detailed estimating5.0 detailed estimating
5.0 detailed estimating
 
4.2 square foot estimating
4.2 square foot estimating4.2 square foot estimating
4.2 square foot estimating
 
4.0 pre-construction estimates
4.0 pre-construction estimates4.0 pre-construction estimates
4.0 pre-construction estimates
 

Recently uploaded

(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 

3 estimate considerations

  • 1. Building Economy ARE 431 Dr. Mohammad A. Hassanain 1 Estimate Considerations 2 Estimate Considerations. Project Size. Project Quality. Project Location. Time. Market Conditions. Steps for Preparing a Detailed Estimate. Today’s Lecture
  • 2. Building Economy ARE 431 Dr. Mohammad A. Hassanain 2 3 Estimate Considerations Every estimate, whether it is generated in the conceptual phase of a project or at bidding time, must consider a number of issues. The price of the project is affected by a number of factors: The size of the project. The quality of the project. The location of the project. The construction start and duration. Market conditions. The accuracy of an estimate is directly affected by the ability of the estimator to properly analyze these basic issues. 4 Project Size As a general rule in construction, as a project gets bigger, the cost of the project increases. The size of the project is a factor of the owner’s requirements. Size is handled differently depending on the stage in the project’s life at which the estimate is being conducted. At the conceptual phase, size will be an issue of basic capacity, such as: Apartment units for a real estate developer. Miles of roadway for a highway engineer.
  • 3. Building Economy ARE 431 Dr. Mohammad A. Hassanain 3 5 Project Size As the project becomes a little better understood, the project’s size will begin to be quantified more accurately. The basic capacities will begin to be thought of in terms of more specific parameters such as: Square footage of floor or roof. Quantity of excavation. Further design leads to more specific quantities, eventually ending with exact numbers for every project item. 6 Project Size The principle of economy of scale must be considered when addressing project size Essentially, as projects gets bigger they get more expensive. The larger the project, the more efficiently people and equipment can be utilized. As people repeat a task, particularly many times over and over, they get better and faster at it, thus reducing the cost of labor.
  • 4. Building Economy ARE 431 Dr. Mohammad A. Hassanain 4 7 Project Size On large commercial buildings and heavy engineering projects, worker productivities are plotted into what are called Learning curves. Number of Units Time Required Per Unit Learning Curve Learning curves show that as the number of repetitions or units a worker needs to accomplish increases, the time required to perform that repetition decreases. 8 Project Quality As the quality and complexity of a project increases, so does the project’s cost. A high level of quality may be required for: Aesthetic reasons as specified by the project architect. The safety of the project users or the public. As the expected quality of a project increases, the cost of providing this quality increases as well.
  • 5. Building Economy ARE 431 Dr. Mohammad A. Hassanain 5 9 Project Location The location of the project is a major consideration in the preparation of an estimate. Depending on the location, a great variation exists in: The purchasing of materials and their delivery: material costs are a factor of availability, competition between suppliers, and access to efficient methods of transportation. Rental or purchase of equipment. The cost of labor: the cost of labor is a factor of the level of training found at the project location. On some projects, the number and the skill levels of workers are not available locally, so labor forces have to be imported. 10 Project Location The cost of constructing projects in different locations can be predicted by establishing what are called location indices for different cities and parts of the country. An index is created for a particular city by comparing the cost of labor, equipment, and material for that city to the national average. This allows an estimator using national average costs to adjust the estimate to a particular location. Most major design and construction companies have developed an accurate set of location indices which they use for their pricing, or they buy this cost data from national pricing suppliers.
  • 6. Building Economy ARE 431 Dr. Mohammad A. Hassanain 6 11 Time The time at which a project is built can have a major impact on the cost of the project. Since estimates, by definition, are prepared in advance of the actual construction, the estimator must “project” or “forecast” to the future what the cost of the work will be. The estimate must predict what the cost of material and labor will be when these costs will be paid – not when the estimate is prepared. Initial project estimates are often two or more years in advance of the start of construction, and if the project takes three years to construct, the estimator therefore must identify costs as far as five years into the future. 12 Time Historical indices can be used to adjust the cost of a past project to one today. This concept is similar to the location indices. This adjustment combined with the location adjustments allow an estimator to estimate the cost of a new project today in one location by looking at a similar project built several years ago and hundreds of miles away. Sometimes, it is difficult to project with accuracy what the index will be for a future year, so the best an estimator can do is to look at the current trends and anticipate future labor and material prices.
  • 7. Building Economy ARE 431 Dr. Mohammad A. Hassanain 7 13 Other Market Conditions An estimator who accurately incorporates the four major considerations that we just identified: Project size. Project quality. Project location. Time. Will have an estimate that reflects the fair value of the project. Assuming a normal market without any unusual circumstances, this estimate should reflect the price to be paid. 14 Other Market Conditions In a market without much work, contractors may bid for a project with little profit to keep their staff employed. On complex projects, contractors may bid the work low in the hopes of making additional profit on future change orders. Sometimes, contractors provide very competitive prices when they enter a new market or work with a new owner. These issues are difficult to quantify, but should be considered in the preparation of the estimate.
  • 8. Building Economy ARE 431 Dr. Mohammad A. Hassanain 8 15 Steps for Preparing a Detailed Estimate 1. Review the scope of the project. Consider the effect of location (availability of electric power and water supply), traffic, availability of skilled and common labor, available storage space on costs. 2. Determine quantities. Perform a material quantity takeoff for all work items in the project, and record the quantity and the unit of measure for each item. 3. Price material. Material cost = Quantity x Unit price 16 Steps for Preparing a Detailed Estimate 4. Price labor. Based on probable labor production rates and crew sizes, determine labor costs: Labor cost = (Quantity x Labor rate)/Labor production rate 5. Price equipment. Based on probable equipment production rates, determine equipment costs: Equipment cost = (Quantity x Equipment rate)/Equipment production rate
  • 9. Building Economy ARE 431 Dr. Mohammad A. Hassanain 9 17 Steps for Preparing a Detailed Estimate 6. Obtain specialty contractors’ bid. Receive and tabulate the costs for each specialty contractor on the project. 7. Calculate taxes, insurance and overhead. Tabulate the costs of material and labor taxes, insurance and job overhead. 8. Add an amount for contingency. Add costs for potential unforeseen work based on the amount of risk. 18 Steps for Preparing a Detailed Estimate 9. Add an amount for profit. Add costs for compensation for performing the work in accordance with the bid documents.