Innovative Business Development in a Shared Services
Model through Project Portfolio Management
Gartner PPM & IT Governance Summit | 9-10 June, 2014
23%
24%
44%
6%
2%
Norway
Europe excl
Norway
Asia
Broadcast
Other
More than 172 million consolidated mobile
subscriptions, Q1 2014
• Mobile operations in 13 markets in Europe
and Asia
• An economic stake of 33 per cent in
VimpelCom Ltd. with 215 mill. mobile
subscriptions in 17 markets
• Among the top performers on Dow Jones
Sustainability Indexes
• Revenues 2013: NOK 104 bn
Telenor Group
Revenue distribution
3.2
2.4
1.8
3.9
3.2
3.5
58.7
30.5
35.2
28.2
10.8
Norway
Sweden
Denmark
Bulgaria
Hungary
Montenegro & Serbia
Bangladesh
India
Pakistan
Thailand
Malaysia
Norway
Serbi
a
Montenegro
Bangladesh
India
Pakistan
Thailand
Malaysia
Sweden
Denmark
Hungary
Bulgaria Myanmar
Learning the basics in Norway
Beliefs in the early 1990’s:
• Growth outside Norway
• Growth in mobile
1966
Manual
Mobile
Norway
1993
GSM
Norway
1981
Automated
Mobile
Norway
- 1970 1980 1990 2000 2010
Early international expansion
Taking positions in Europe
and Asia
1994
Russia
2000
Thailand
Denmark
1998
Ukraine
1996
Montenegro
Austria
Bangladesh
1995
Ireland
1993
Hungary
1997
Greece
Germany
- 1970 1980 1990 2000 2010
1999
Malaysia
2009
India
From minority to
majority positions
2007
EXIT
Austria
2006
Serbia
2005
Pakistan
2005
Sweden
2004
EXIT
Greece
- 1970 1980 1990 2000
2000
EXIT
Ireland
Germany
2010
2010
VimpelCom Ltd.
established
2013
Bulgaria
Myanmar
Quality and efficiency through
new operating models
Deliver on customer needs
Leverage scale and volume
Group Industrialization
Shared Services: an important part of the
Industrialization agenda
Future Customer Service
Shared Services established with multifunctional and cross-
geographical mandate
Page 3
Five key principles
Cornerstones of new Telenor SSC strategy
Set bold 5 year ambition based on end-to-end process approach
and mandatory functional scope
1
Roll-out in phased approach – phase 1 focus on resolving TSS
challenges & ensuring coordinated delivery of ongoing initiatives
2
SSC activities to be managed in multifunctional organization
under GID – governance to support strong role of policy owners
(Group Finance, People & Organisation, GID). Regional or
global delivery through SSC and/or external partners
3
Clear cost & quality targets - with transparency on performance
to BUs based on continuous monitoring & feedback
4
Systematic learning from best practice approaches – within Telco
industry and other industries
5
1
A bold 5 year ambition is set based on end-to-end process approach and
mandatory functional scope for Business Units
Page 3
Five key principles
Cornerstones of new Telenor SSC strategy
Set bold 5 year ambition based on end-to-end process approach
and mandatory functional scope
1
Roll-out in phased approach – phase 1 focus on resolving TSS
challenges & ensuring coordinated delivery of ongoing initiatives
2
SSC activities to be managed in multifunctional organization
under GID – governance to support strong role of policy owners
(Group Finance, People & Organisation, GID). Regional or
global delivery through SSC and/or external partners
3
Clear cost & quality targets - with transparency on performance
to BUs based on continuous monitoring & feedback
4
Systematic learning from best practice approaches – within Telco
industry and other industries
5
2
Roll-out is planned in a phased approach – phase 1 focus on ensuring coordinated
and successful delivery of ongoing initiatives and projects
Page 3
Five key principles
Cornerstones of new Telenor SSC strategy
Set bold 5 year ambition based on end-to-end process approach
and mandatory functional scope
1
Roll-out in phased approach – phase 1 focus on resolving TSS
challenges & ensuring coordinated delivery of ongoing initiatives
2
SSC activities to be managed in multifunctional organization
under GID – governance to support strong role of policy owners
(Group Finance, People & Organisation, GID). Regional or
global delivery through SSC and/or external partners
3
Clear cost & quality targets - with transparency on performance
to BUs based on continuous monitoring & feedback
4
Systematic learning from best practice approaches – within Telco
industry and other industries
5
4
Clear cost and quality targets – with transparency on performance to BUs based
on continuous monitoring and feedback
Page 3
Five key principles
Cornerstones of new Telenor SSC strategy
Set bold 5 year ambition based on end-to-end process approach
and mandatory functional scope
1
Roll-out in phased approach – phase 1 focus on resolving TSS
challenges & ensuring coordinated delivery of ongoing initiatives
2
SSC activities to be managed in multifunctional organization
under GID – governance to support strong role of policy owners
(Group Finance, People & Organisation, GID). Regional or
global delivery through SSC and/or external partners
3
Clear cost & quality targets - with transparency on performance
to BUs based on continuous monitoring & feedback
4
Systematic learning from best practice approaches – within Telco
industry and other industries
5
5
Systematic learning from best practice approaches – within Telco industry and
other industries
Page 3
Five key principles
Cornerstones of new Telenor SSC strategy
Set bold 5 year ambition based on end-to-end process approach
and mandatory functional scope
1
Roll-out in phased approach – phase 1 focus on resolving TSS
challenges & ensuring coordinated delivery of ongoing initiatives
2
SSC activities to be managed in multifunctional organization
under GID – governance to support strong role of policy owners
(Group Finance, People & Organisation, GID). Regional or
global delivery through SSC and/or external partners
3
Clear cost & quality targets - with transparency on performance
to BUs based on continuous monitoring & feedback
4
Systematic learning from best practice approaches – within Telco
industry and other industries
5
3
Shared Services is managed in a multifunctional organization under Group
governance to support strong role of policy owners. Regional or global delivery
internally or through external partners
Build capabilities and manage change – build world-class Shared Services
competencies to execute centrally and lead organizational change on all levels
6
Challenges that we
experience with projects
• Lack of standardized and
integrated tools for Project and
Portfolio Management, both in the
Shared Services organization and
within Business Units
• Existing solutions, where present,
do not sufficiently support resource
management, idea management,
and agile methods
• Room for quality improvements in
both portfolio management and
project management through more
use of PPM solutions
9
How do we meet these challenges ?
• Implement Project and Portfolio Management tool globally as a shared service
for Business Units in the Telenor Group
 Current road map includes close to 5000 users
 In 7 different Business Units
 Integrated with critical business systems
• Implement the same tool for internal projects in the Shared Services
organization
 Raising the bar on project execution in a global environment
 Taking the same medicine as our customers
10
What are we implementing ?
Idea Management
Portfolio Management
Project Management
Resource Management
Time Tracking
PPM provides substantial business benefits to
Business Units and Shared Services
Business Units:
• Increased effectiveness of PPM
processes
• Integrated with local applications
giving up to date and consistent
information
• Optimized resource allocation and
prioritization
• Increased visibility and portfolio
prioritization
• Improved execution of Group projects
across Business Units
Shared Services:
• Remove legacy system and clean up
architecture
• One global PPM solution to Telenor
users; stable, cost efficient, with right
quality
• Integrated with other Shared Services
applications (Oracle E-Business
Suite, Workday HRMS, others);
utilizing common master data to
improve process efficiency and data
quality
• Improved execution of Shared
Services projects across Business
Units
12
How we are executing the implementation project
• Organization • Timeline
13
• Governance
Project
Manager
Test
Manager
BU …
Test Manager
BU N
Test Manager
BU 2
Test Manager
Migration
Reports
BU 1
Test Manager
Platform/
Infrastructure
Data
Migration
Functional
Architect
Release
Manager
Interfaces
Middleware
Training
PMO
14
Project Organization
Steering
Committee
Change
Advisory
Board
Project
Owner
High level project plan, final stages
Q2-14 Q3-14 Q4-14
Apr May Jun Jul Aug Sep Oct Nov Dec
Go-live wave 1
Go-live wave 2
Go-live wave 3
Early life support
• UAT
• Migration
• Performance
Prod environment
steady state
23-24.08
04.07
09.08
13-14.09
18-26.10
KT to support
organization
09.08
19.12Project closure
05.12
Project improvement in Global Shared Services (GSS)
- not only about tools
• Strengthen GSS Capabilities to execute projects successfully
• Increase Capacity to execute transformation projects across Business Units
• Improve Competence on all levels in GSS related to project execution
• Four main focus areas in 2014
−Handover process from Project to Line organization
−Managing change process within projects
−Project costing and planning
−Improved process for effect realization
• Improved KPI set for monthly follow up and reporting
16

Innovative Business Development in a Shared Services Model through Project Portfolio Management

  • 1.
    Innovative Business Developmentin a Shared Services Model through Project Portfolio Management Gartner PPM & IT Governance Summit | 9-10 June, 2014
  • 2.
    23% 24% 44% 6% 2% Norway Europe excl Norway Asia Broadcast Other More than172 million consolidated mobile subscriptions, Q1 2014 • Mobile operations in 13 markets in Europe and Asia • An economic stake of 33 per cent in VimpelCom Ltd. with 215 mill. mobile subscriptions in 17 markets • Among the top performers on Dow Jones Sustainability Indexes • Revenues 2013: NOK 104 bn Telenor Group Revenue distribution 3.2 2.4 1.8 3.9 3.2 3.5 58.7 30.5 35.2 28.2 10.8 Norway Sweden Denmark Bulgaria Hungary Montenegro & Serbia Bangladesh India Pakistan Thailand Malaysia Norway Serbi a Montenegro Bangladesh India Pakistan Thailand Malaysia Sweden Denmark Hungary Bulgaria Myanmar
  • 3.
    Learning the basicsin Norway Beliefs in the early 1990’s: • Growth outside Norway • Growth in mobile 1966 Manual Mobile Norway 1993 GSM Norway 1981 Automated Mobile Norway - 1970 1980 1990 2000 2010
  • 4.
    Early international expansion Takingpositions in Europe and Asia 1994 Russia 2000 Thailand Denmark 1998 Ukraine 1996 Montenegro Austria Bangladesh 1995 Ireland 1993 Hungary 1997 Greece Germany - 1970 1980 1990 2000 2010 1999 Malaysia
  • 5.
    2009 India From minority to majoritypositions 2007 EXIT Austria 2006 Serbia 2005 Pakistan 2005 Sweden 2004 EXIT Greece - 1970 1980 1990 2000 2000 EXIT Ireland Germany 2010 2010 VimpelCom Ltd. established 2013 Bulgaria Myanmar
  • 6.
    Quality and efficiencythrough new operating models Deliver on customer needs Leverage scale and volume Group Industrialization
  • 7.
    Shared Services: animportant part of the Industrialization agenda Future Customer Service
  • 8.
    Shared Services establishedwith multifunctional and cross- geographical mandate Page 3 Five key principles Cornerstones of new Telenor SSC strategy Set bold 5 year ambition based on end-to-end process approach and mandatory functional scope 1 Roll-out in phased approach – phase 1 focus on resolving TSS challenges & ensuring coordinated delivery of ongoing initiatives 2 SSC activities to be managed in multifunctional organization under GID – governance to support strong role of policy owners (Group Finance, People & Organisation, GID). Regional or global delivery through SSC and/or external partners 3 Clear cost & quality targets - with transparency on performance to BUs based on continuous monitoring & feedback 4 Systematic learning from best practice approaches – within Telco industry and other industries 5 1 A bold 5 year ambition is set based on end-to-end process approach and mandatory functional scope for Business Units Page 3 Five key principles Cornerstones of new Telenor SSC strategy Set bold 5 year ambition based on end-to-end process approach and mandatory functional scope 1 Roll-out in phased approach – phase 1 focus on resolving TSS challenges & ensuring coordinated delivery of ongoing initiatives 2 SSC activities to be managed in multifunctional organization under GID – governance to support strong role of policy owners (Group Finance, People & Organisation, GID). Regional or global delivery through SSC and/or external partners 3 Clear cost & quality targets - with transparency on performance to BUs based on continuous monitoring & feedback 4 Systematic learning from best practice approaches – within Telco industry and other industries 5 2 Roll-out is planned in a phased approach – phase 1 focus on ensuring coordinated and successful delivery of ongoing initiatives and projects Page 3 Five key principles Cornerstones of new Telenor SSC strategy Set bold 5 year ambition based on end-to-end process approach and mandatory functional scope 1 Roll-out in phased approach – phase 1 focus on resolving TSS challenges & ensuring coordinated delivery of ongoing initiatives 2 SSC activities to be managed in multifunctional organization under GID – governance to support strong role of policy owners (Group Finance, People & Organisation, GID). Regional or global delivery through SSC and/or external partners 3 Clear cost & quality targets - with transparency on performance to BUs based on continuous monitoring & feedback 4 Systematic learning from best practice approaches – within Telco industry and other industries 5 4 Clear cost and quality targets – with transparency on performance to BUs based on continuous monitoring and feedback Page 3 Five key principles Cornerstones of new Telenor SSC strategy Set bold 5 year ambition based on end-to-end process approach and mandatory functional scope 1 Roll-out in phased approach – phase 1 focus on resolving TSS challenges & ensuring coordinated delivery of ongoing initiatives 2 SSC activities to be managed in multifunctional organization under GID – governance to support strong role of policy owners (Group Finance, People & Organisation, GID). Regional or global delivery through SSC and/or external partners 3 Clear cost & quality targets - with transparency on performance to BUs based on continuous monitoring & feedback 4 Systematic learning from best practice approaches – within Telco industry and other industries 5 5 Systematic learning from best practice approaches – within Telco industry and other industries Page 3 Five key principles Cornerstones of new Telenor SSC strategy Set bold 5 year ambition based on end-to-end process approach and mandatory functional scope 1 Roll-out in phased approach – phase 1 focus on resolving TSS challenges & ensuring coordinated delivery of ongoing initiatives 2 SSC activities to be managed in multifunctional organization under GID – governance to support strong role of policy owners (Group Finance, People & Organisation, GID). Regional or global delivery through SSC and/or external partners 3 Clear cost & quality targets - with transparency on performance to BUs based on continuous monitoring & feedback 4 Systematic learning from best practice approaches – within Telco industry and other industries 5 3 Shared Services is managed in a multifunctional organization under Group governance to support strong role of policy owners. Regional or global delivery internally or through external partners Build capabilities and manage change – build world-class Shared Services competencies to execute centrally and lead organizational change on all levels 6
  • 9.
    Challenges that we experiencewith projects • Lack of standardized and integrated tools for Project and Portfolio Management, both in the Shared Services organization and within Business Units • Existing solutions, where present, do not sufficiently support resource management, idea management, and agile methods • Room for quality improvements in both portfolio management and project management through more use of PPM solutions 9
  • 10.
    How do wemeet these challenges ? • Implement Project and Portfolio Management tool globally as a shared service for Business Units in the Telenor Group  Current road map includes close to 5000 users  In 7 different Business Units  Integrated with critical business systems • Implement the same tool for internal projects in the Shared Services organization  Raising the bar on project execution in a global environment  Taking the same medicine as our customers 10
  • 11.
    What are weimplementing ? Idea Management Portfolio Management Project Management Resource Management Time Tracking
  • 12.
    PPM provides substantialbusiness benefits to Business Units and Shared Services Business Units: • Increased effectiveness of PPM processes • Integrated with local applications giving up to date and consistent information • Optimized resource allocation and prioritization • Increased visibility and portfolio prioritization • Improved execution of Group projects across Business Units Shared Services: • Remove legacy system and clean up architecture • One global PPM solution to Telenor users; stable, cost efficient, with right quality • Integrated with other Shared Services applications (Oracle E-Business Suite, Workday HRMS, others); utilizing common master data to improve process efficiency and data quality • Improved execution of Shared Services projects across Business Units 12
  • 13.
    How we areexecuting the implementation project • Organization • Timeline 13 • Governance
  • 14.
    Project Manager Test Manager BU … Test Manager BUN Test Manager BU 2 Test Manager Migration Reports BU 1 Test Manager Platform/ Infrastructure Data Migration Functional Architect Release Manager Interfaces Middleware Training PMO 14 Project Organization Steering Committee Change Advisory Board Project Owner
  • 15.
    High level projectplan, final stages Q2-14 Q3-14 Q4-14 Apr May Jun Jul Aug Sep Oct Nov Dec Go-live wave 1 Go-live wave 2 Go-live wave 3 Early life support • UAT • Migration • Performance Prod environment steady state 23-24.08 04.07 09.08 13-14.09 18-26.10 KT to support organization 09.08 19.12Project closure 05.12
  • 16.
    Project improvement inGlobal Shared Services (GSS) - not only about tools • Strengthen GSS Capabilities to execute projects successfully • Increase Capacity to execute transformation projects across Business Units • Improve Competence on all levels in GSS related to project execution • Four main focus areas in 2014 −Handover process from Project to Line organization −Managing change process within projects −Project costing and planning −Improved process for effect realization • Improved KPI set for monthly follow up and reporting 16