June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 1
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
PERSONAL PROTECTIVE EQUIPMENT
CSA or ANSI equivalent personal protective equipment must be worn
APPLICABLE LAWS IN ONTARIO
This procedur e is based on the requirements of the Ontario Electrical Safety Code, and
Regulation 851 Industrial Establishments of the Occupational Health and Safety Act.
Standards used in this procedure are based on CSA-Z460 and CSA Z142-10
ACTIVITIES PERMITTED WITH THIS PROCEDURE :
1. Inspecting dies
2. Maintenance of dies
3. Stock guide adjustments
4. Starting coil stock
5. Removing Scrap
6. Clearing Jams
7. Adjusting lube line in the die
8. Adjusting sensors in the die
For all other activities must follow the LOTO MASTER PLACARD and safe work procedures for
isolating energy on equipment being maintained
Lock Our Tag Out Criteria used for this procedure:
If any part of the body will enter the space between the upper and lower die sections, die blocks must
be inserted per the standard LOTO procedure for this press. Tools should be used to reach into die
areas to assist in starting coils, removing scrap and clearing jams.
June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 2
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
The different sources of hazardous energy and methods used to isolate them are shown below
Use Safety Blocks , Ram Or Die Blocks To
Block The Weight
Kinetic energy FLYWHEEL Rams, blades
Stop and block machine parts (e.g., stop
flywheels , disengage clutch , and ensure that
they do not recycle); review entire cycle of
mechanical motion, ensure that all motions are
stopped.
RAM WEIGHT, BOLSTER
Potential Energy,
Gravity
Hydraulic pressure
hydraulic systems (e.g., hydraulic
presses, rams, cylinders, hammers)
Shut off, lock (with chains, built-in lockout
devices, or lockout attachments) and tag
valves; bleed off and blank lines as
necessary.
Air pressure
pneumatic systems (e.g., lines,
pressure, accumulators, air surge
tanks, rams, cylinders)
Shut off, lock (with chains, built-in lockout
devices, or lockout attachments) and tag
valves; bleed off excess air; if pressure cannot
be relieved, block any possible movement of
machinery.
1- Turn off power at machine first (i.e., at point
of operation switch), and then 2- at the main
disconnect switch for the machine; 3- lock
and tag main disconnect switch . Disconnect
safety block plug and lock out plug
ENERGY FORM ENERGY SOURCE LOCKOUT METHODS
Electricity
power transmission lines; machine
power, motors; solenoids; capacitors,
interlock ram blocks
June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 3
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
LOCKOUT / TAGOUT PROCEDURE DIE SETUP AND DIE CHANGES
DIE CHANGE-OVER / DIE SETUP STEPS
1. Run out material.
2. Park transfer, TURN OFF POWER TO DRIVES AND LOGOUT HMI (LINEAR Lockout)
3. *SHUT DOWN PRESS USING MASTER STOP -WAIT UNTIL FLYWHEEL HAS COME TO A
FULL STOP
4. *RAISE THE RAM AND LOCK OUT THE PRESS USING SAFETY BLOCKS, and lock out the
plug with your lock (see next page ) ----1min per ram block
5. Unclamp & open die, clean die , inspect it for wear
6. REMOVE SAFETY BLOCKS AND LOCK FROM BOLSTER
7. Move Bolster up and out.
8. Recipe & Ram adjust.
9. Clean tracks on bolster part.
10. Bolster in and clamp.
11. *RAISE THE RAM AND LOCK OUT THE PRESS USING RAM BLOCKS (same as # 4)
12. Close die & clamp, connect sensor and lube cable.
13. REMOVE SAFETY BLOCKS AND LOCK FROM BOLSTER (same as # 6)
14. Hook up transfer bar
15. Login into HMI Linear, turn on drives and UN-Park transfer
16. Line fill through manual hits - set to continuous
NOTE: ITEMS WITH * ARE LOTO POINTS SPECIFIED ON LOTO PLACARD DIE SETUP
June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 4
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
BOLSTER ENTRY AND E-STOP LOCK OUT
Before entering the bolster from either the rear or front the opeprator must push the the E-stop button
and must lock out using hius/her lockout device.
LIGHT CURTAIN AREA
When the person remains in the light curtain area, the person is protected from accidental restarting of
the press and all hazardous energy are contained. However the area outside light curtain, specifically
the bolster is not detected by the light curtain and not safe without locking out. Therefore before the
person steps foot onto the bolter that person MUST lock out the ESTOP by placing a cover over
it, twisting the cover onto it
PROTECTED AREA BY LIGHT CURTAIN
June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 5
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
STOPPING THE MOTOR AND FLYWHEEL
Before stopping the press notify everyone affected , i.e. supervisor, lead hand, operators and
maintenance if needed . The flywheel generates kinetic energy that drives the press ram in the
downward stroke, To stop the press drive motor and flywheel press the MASTER STOP BUTTON
which will stop the motor and flywheel.
It is critically important to ensure that the flywheel has stopped before continuing
Wait for the flywheel light to come on before inserting the ram blocks.
Master stop button
Flywheel Stopped Light
Flywheel Stopped Light
June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 6
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
As per section CSA z142- “the press is not considered locked out until the flywheel has
stopped” If the flywheel has not stopped within 2 minutes apply the brakes and continue
applying the brakes until the flywheel has come to a full stop.
June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 7
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
LOCKING OUT THE MASTER STOP
Alternative lockout method
LOCKED PLUG ON THE
SAFETY BLOCK
June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 8
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
Section 7.4 CSA Z460 permits other types of lock out /control of hazardous energy other than
traditional lock out tag out. The Master Stop is the only control that shuts off the motor and stops the
flywheel. In some cases where the die is setup, clamped in position, but there are material feed issues,
multiple minor quick adjustments required or when changing grippers on the transfer is required ,
locking out using safety blocks may not be effective and may create more hazardous conditions for the
operators.
Specifically in situations where operator exposure time in the die< 30 seconds and 2 T-stands
are being used to cycle the press, locking out with safety blocks will increase the exposure under the
die from 30 seconds to 2 min and may not permit the resolution of the material ejection / feed issues. In
those cases alternative safer way is to lock out the master stop after the flywheel has stopped
make the quick adjustment remove the lock and restart the press, The 2 hand trip controls by both
operators is required in all circumstances
LOCKOUT PROCEDURE FOR DIE REMOVAL “ZERO KINETIC ENERGY STATE”.
June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 9
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
1. Identify Lockout Situations and Energy Sources
Assess equipment energy sources (figure 1.0), either potential or kinetic and determine
the most effective method to achieve a “ZERO ENERGY STATE”. Contact Safety Engineer to
help identify system shutdown procedures.
2. Notify Persons Affected
Once energy sources have been isolated, notify affected personnel of the shutdown.
3. Shutdown Procedure
Stop the press motor by pressing the master stop button, and selecting the OFF condition. Place a lock
cover over the master stop and lock it out. Disconnect the interlocked RAM block by removing the RAM
block connector.
4. Verify Flywheel Complete Stop –CRITICAL STEP
Verify that the flywheel has come to a full stop before placing the ram block into the press. The light at
the press control will turn on when the flywheel stopped. Also check the rear of the press and see if it
has stopped, Use a flywheel brake to stop the flywheel
WARNING : DO NOT PERFORM DIE CHANGES WHILE THE FLYWHEEL IS RUNNING,
5. Install Ram blocks
Raise the ram and Lock Out the press using ram safety blocks. Wait for the flywheel to stop, and install Ram
Blocks in place on the bolster.
6. Verify Effectiveness of Lockout—ZERO ENERGY
Try starting the press by pushing the start button, and 2 hand trip controls
Try starting the hydraulic pump and see if the bolster will move.
Press coil feed and try to cycle the feeder. If the feeder does not move, flywheel stopped light is on and the press
lights remain off and press will not start then you have achieved ZERO ENERGY STATE and can perform die
change
RESCUE AND RECOVERY
June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 10
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
IF A PERSON BECOMES TRAPPED IN THE PTC 1000 TON PRESS # 23:
Do not start motor.
Assess the problem and do the following :
Call maintenance and senior press shop personnel to Press
Crank will not move with light curtain blocked. Switch key switch for Ram/Slide
adjustment to 'ON' and reactivate power
Move Ram/Slide to free person:
If a person is trapped BELOW the Ram/Slide, use Ram/Slide adjust UP to raise the
Ram/Slide
If a person is trapped ABOVE the Ram/Slide, Use Ram/Slide adjust DOWN to lower the
Ram/Slide
If Ram/Slide adjust is not enough to free the person, maintenance must make changes to
further move the Ram/Slide Remove the trapped person and provide first aid
Call 911 if required
Safety Standards:
ANSI B11.0-2010 – Safety of Machinery – General Requirements and Risk Assessment
June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 11
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
ANSI B11.TR3-2000 – Risk Assessment and Risk Reduction – A Guide to Estimate, Evaluate
and Reduce Risks Associated with Machine Tools
ANSI/RIA R15.06-1999 (R2009) – For Industrial Robots and Robot Systems – Safety
Requirements
ANSI/PMMI B155.1-2011 – Standard for Packaging Machinery and Packaging-Related Converting
Machinery – Safety Requirements for Construction, Care, and Use
SEMI S10-0307 – Safety Guideline for Risk Assessment and Risk Evaluation Process
CSA Z432-04 – Safeguarding of Machinery – Occupational Health and Safety
CSA Z434-03 – Industrial Robots and Robot Systems – General Safety Requirements
CSA Z460-05 – Control of Hazardous Energy – Lockout and Other Methods
ISO 12100:2010 – Safety of machinery – General principles for design – Risk assessment and
risk reduction
X
Safety Manager
X
DEPARTMENT MANAGER
X
GENERAL MANAGER
June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 12
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 13
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 14
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 15
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 16
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
June 27, 2018 PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 17
SAFE WORK PROCEDURE
PRESS 23 WITH LINEAR TRANSFER
DIE REMOVAL/SETUP/CHANGEOVER LOTO
Created by : Julian Kalac Approved by AGM Department Press Shop
Date Created June 25 2018 Revision Date: N/A Press No. 23
SAFETY BLOCKS REQUIREMENT
The CSA standard Z142-10 requires that Safety Blocks be used whenever dies are being repaired in
a press or when work of any kind is being performed between the slide and bolster. Safety
Blocks are placed between the die punch and holder and must be rated to support the combined
static load of the slide and associated components.
Correct Usage Safety Blocks must be used when anyone is working in and around the die area of a
press. An electrical interlock must be attached to the Safety Block so that the press cannot be
operated when the blocks are in place. When not being used the blocks must be stored in a location
where the electrical interlock can be interfaced with the press controls ensuring the press can only be
started when the block is in the stored position, i.e. not in the press.

1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER

  • 1.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 1 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23 PERSONAL PROTECTIVE EQUIPMENT CSA or ANSI equivalent personal protective equipment must be worn APPLICABLE LAWS IN ONTARIO This procedur e is based on the requirements of the Ontario Electrical Safety Code, and Regulation 851 Industrial Establishments of the Occupational Health and Safety Act. Standards used in this procedure are based on CSA-Z460 and CSA Z142-10 ACTIVITIES PERMITTED WITH THIS PROCEDURE : 1. Inspecting dies 2. Maintenance of dies 3. Stock guide adjustments 4. Starting coil stock 5. Removing Scrap 6. Clearing Jams 7. Adjusting lube line in the die 8. Adjusting sensors in the die For all other activities must follow the LOTO MASTER PLACARD and safe work procedures for isolating energy on equipment being maintained Lock Our Tag Out Criteria used for this procedure: If any part of the body will enter the space between the upper and lower die sections, die blocks must be inserted per the standard LOTO procedure for this press. Tools should be used to reach into die areas to assist in starting coils, removing scrap and clearing jams.
  • 2.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 2 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23 The different sources of hazardous energy and methods used to isolate them are shown below Use Safety Blocks , Ram Or Die Blocks To Block The Weight Kinetic energy FLYWHEEL Rams, blades Stop and block machine parts (e.g., stop flywheels , disengage clutch , and ensure that they do not recycle); review entire cycle of mechanical motion, ensure that all motions are stopped. RAM WEIGHT, BOLSTER Potential Energy, Gravity Hydraulic pressure hydraulic systems (e.g., hydraulic presses, rams, cylinders, hammers) Shut off, lock (with chains, built-in lockout devices, or lockout attachments) and tag valves; bleed off and blank lines as necessary. Air pressure pneumatic systems (e.g., lines, pressure, accumulators, air surge tanks, rams, cylinders) Shut off, lock (with chains, built-in lockout devices, or lockout attachments) and tag valves; bleed off excess air; if pressure cannot be relieved, block any possible movement of machinery. 1- Turn off power at machine first (i.e., at point of operation switch), and then 2- at the main disconnect switch for the machine; 3- lock and tag main disconnect switch . Disconnect safety block plug and lock out plug ENERGY FORM ENERGY SOURCE LOCKOUT METHODS Electricity power transmission lines; machine power, motors; solenoids; capacitors, interlock ram blocks
  • 3.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 3 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23 LOCKOUT / TAGOUT PROCEDURE DIE SETUP AND DIE CHANGES DIE CHANGE-OVER / DIE SETUP STEPS 1. Run out material. 2. Park transfer, TURN OFF POWER TO DRIVES AND LOGOUT HMI (LINEAR Lockout) 3. *SHUT DOWN PRESS USING MASTER STOP -WAIT UNTIL FLYWHEEL HAS COME TO A FULL STOP 4. *RAISE THE RAM AND LOCK OUT THE PRESS USING SAFETY BLOCKS, and lock out the plug with your lock (see next page ) ----1min per ram block 5. Unclamp & open die, clean die , inspect it for wear 6. REMOVE SAFETY BLOCKS AND LOCK FROM BOLSTER 7. Move Bolster up and out. 8. Recipe & Ram adjust. 9. Clean tracks on bolster part. 10. Bolster in and clamp. 11. *RAISE THE RAM AND LOCK OUT THE PRESS USING RAM BLOCKS (same as # 4) 12. Close die & clamp, connect sensor and lube cable. 13. REMOVE SAFETY BLOCKS AND LOCK FROM BOLSTER (same as # 6) 14. Hook up transfer bar 15. Login into HMI Linear, turn on drives and UN-Park transfer 16. Line fill through manual hits - set to continuous NOTE: ITEMS WITH * ARE LOTO POINTS SPECIFIED ON LOTO PLACARD DIE SETUP
  • 4.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 4 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23 BOLSTER ENTRY AND E-STOP LOCK OUT Before entering the bolster from either the rear or front the opeprator must push the the E-stop button and must lock out using hius/her lockout device. LIGHT CURTAIN AREA When the person remains in the light curtain area, the person is protected from accidental restarting of the press and all hazardous energy are contained. However the area outside light curtain, specifically the bolster is not detected by the light curtain and not safe without locking out. Therefore before the person steps foot onto the bolter that person MUST lock out the ESTOP by placing a cover over it, twisting the cover onto it PROTECTED AREA BY LIGHT CURTAIN
  • 5.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 5 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23 STOPPING THE MOTOR AND FLYWHEEL Before stopping the press notify everyone affected , i.e. supervisor, lead hand, operators and maintenance if needed . The flywheel generates kinetic energy that drives the press ram in the downward stroke, To stop the press drive motor and flywheel press the MASTER STOP BUTTON which will stop the motor and flywheel. It is critically important to ensure that the flywheel has stopped before continuing Wait for the flywheel light to come on before inserting the ram blocks. Master stop button Flywheel Stopped Light Flywheel Stopped Light
  • 6.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 6 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23 As per section CSA z142- “the press is not considered locked out until the flywheel has stopped” If the flywheel has not stopped within 2 minutes apply the brakes and continue applying the brakes until the flywheel has come to a full stop.
  • 7.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 7 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23 LOCKING OUT THE MASTER STOP Alternative lockout method LOCKED PLUG ON THE SAFETY BLOCK
  • 8.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 8 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23 Section 7.4 CSA Z460 permits other types of lock out /control of hazardous energy other than traditional lock out tag out. The Master Stop is the only control that shuts off the motor and stops the flywheel. In some cases where the die is setup, clamped in position, but there are material feed issues, multiple minor quick adjustments required or when changing grippers on the transfer is required , locking out using safety blocks may not be effective and may create more hazardous conditions for the operators. Specifically in situations where operator exposure time in the die< 30 seconds and 2 T-stands are being used to cycle the press, locking out with safety blocks will increase the exposure under the die from 30 seconds to 2 min and may not permit the resolution of the material ejection / feed issues. In those cases alternative safer way is to lock out the master stop after the flywheel has stopped make the quick adjustment remove the lock and restart the press, The 2 hand trip controls by both operators is required in all circumstances LOCKOUT PROCEDURE FOR DIE REMOVAL “ZERO KINETIC ENERGY STATE”.
  • 9.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 9 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23 1. Identify Lockout Situations and Energy Sources Assess equipment energy sources (figure 1.0), either potential or kinetic and determine the most effective method to achieve a “ZERO ENERGY STATE”. Contact Safety Engineer to help identify system shutdown procedures. 2. Notify Persons Affected Once energy sources have been isolated, notify affected personnel of the shutdown. 3. Shutdown Procedure Stop the press motor by pressing the master stop button, and selecting the OFF condition. Place a lock cover over the master stop and lock it out. Disconnect the interlocked RAM block by removing the RAM block connector. 4. Verify Flywheel Complete Stop –CRITICAL STEP Verify that the flywheel has come to a full stop before placing the ram block into the press. The light at the press control will turn on when the flywheel stopped. Also check the rear of the press and see if it has stopped, Use a flywheel brake to stop the flywheel WARNING : DO NOT PERFORM DIE CHANGES WHILE THE FLYWHEEL IS RUNNING, 5. Install Ram blocks Raise the ram and Lock Out the press using ram safety blocks. Wait for the flywheel to stop, and install Ram Blocks in place on the bolster. 6. Verify Effectiveness of Lockout—ZERO ENERGY Try starting the press by pushing the start button, and 2 hand trip controls Try starting the hydraulic pump and see if the bolster will move. Press coil feed and try to cycle the feeder. If the feeder does not move, flywheel stopped light is on and the press lights remain off and press will not start then you have achieved ZERO ENERGY STATE and can perform die change RESCUE AND RECOVERY
  • 10.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 10 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23 IF A PERSON BECOMES TRAPPED IN THE PTC 1000 TON PRESS # 23: Do not start motor. Assess the problem and do the following : Call maintenance and senior press shop personnel to Press Crank will not move with light curtain blocked. Switch key switch for Ram/Slide adjustment to 'ON' and reactivate power Move Ram/Slide to free person: If a person is trapped BELOW the Ram/Slide, use Ram/Slide adjust UP to raise the Ram/Slide If a person is trapped ABOVE the Ram/Slide, Use Ram/Slide adjust DOWN to lower the Ram/Slide If Ram/Slide adjust is not enough to free the person, maintenance must make changes to further move the Ram/Slide Remove the trapped person and provide first aid Call 911 if required Safety Standards: ANSI B11.0-2010 – Safety of Machinery – General Requirements and Risk Assessment
  • 11.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 11 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23 ANSI B11.TR3-2000 – Risk Assessment and Risk Reduction – A Guide to Estimate, Evaluate and Reduce Risks Associated with Machine Tools ANSI/RIA R15.06-1999 (R2009) – For Industrial Robots and Robot Systems – Safety Requirements ANSI/PMMI B155.1-2011 – Standard for Packaging Machinery and Packaging-Related Converting Machinery – Safety Requirements for Construction, Care, and Use SEMI S10-0307 – Safety Guideline for Risk Assessment and Risk Evaluation Process CSA Z432-04 – Safeguarding of Machinery – Occupational Health and Safety CSA Z434-03 – Industrial Robots and Robot Systems – General Safety Requirements CSA Z460-05 – Control of Hazardous Energy – Lockout and Other Methods ISO 12100:2010 – Safety of machinery – General principles for design – Risk assessment and risk reduction X Safety Manager X DEPARTMENT MANAGER X GENERAL MANAGER
  • 12.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 12 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23
  • 13.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 13 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23
  • 14.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 14 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23
  • 15.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 15 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23
  • 16.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 16 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23
  • 17.
    June 27, 2018PRESS 23 DIE SETUP / CHANGEOVER LOCKOUT TAGOUT 17 SAFE WORK PROCEDURE PRESS 23 WITH LINEAR TRANSFER DIE REMOVAL/SETUP/CHANGEOVER LOTO Created by : Julian Kalac Approved by AGM Department Press Shop Date Created June 25 2018 Revision Date: N/A Press No. 23 SAFETY BLOCKS REQUIREMENT The CSA standard Z142-10 requires that Safety Blocks be used whenever dies are being repaired in a press or when work of any kind is being performed between the slide and bolster. Safety Blocks are placed between the die punch and holder and must be rated to support the combined static load of the slide and associated components. Correct Usage Safety Blocks must be used when anyone is working in and around the die area of a press. An electrical interlock must be attached to the Safety Block so that the press cannot be operated when the blocks are in place. When not being used the blocks must be stored in a location where the electrical interlock can be interfaced with the press controls ensuring the press can only be started when the block is in the stored position, i.e. not in the press.