SlideShare a Scribd company logo
XCE 703 - COST ESTIMATION
AND VALUATION
UNIT – 1
ESTIMATION OF BUILDINGS
PREPARED BY
Dr.B.ANUPRIYA
Associate Professor/CIVIL
• Estimation
Estimating is the technique of Computing the
various quantities and the expected
Expenditure on a particular work or project.
• Need for estimation and costing
– Estimate give an idea of the cost of the work
– Estimate gives an idea of time required for the completion
of the work.
– Estimate is required to invite the tenders and Quotations
ESTIMATION OF BUILDINGS
Method of Estimating
• Detail Estimate: It consists of working out
quantities of different items of work and then
working out the cost.
Item
No.
Particulars of
Items of work
No. L( m) B( m) D( m) Q
• Abstract of Estimated cost: Cost under item of
work is calculated from the quantities already
computed at workable rate.
Item
no.
Description
/Particulars
Quantity Unit Rate Amount
• Earth work excavation
• Concrete in foundation
• Soling ( when the soil is soft one layer of dry brick is applied below the
foundation concrete)
• Damp Proof Course
• Masonry
• Deduction for openings ( doors & Windows)
• Lintel over openings
• R.C.C work
• Flooring & Roofing
• Plastering & Pointing
• White washing & colour washing
• Painting
MAIN ITEMS OF WORK
S.No Particulars of Item Units
1. Earth work Excavation M3
2. Concreting M3
3. D.P.C M2
4. Brick Work in Foundation,
Plinth & Superstructure
M3
5. Roofing M3
6. Plastering & Pointing M2
UNITS OF MEASUREMENTS
METHODS OF BUILDING ESTIMATES
Individual wall method ( Long wall Short wall
method)
Centre Line method
Q= Total c/c distance X Breadth X Depth
PROBLEM 1
For the given plan of super structure of a
single room building 5 m X 4 m, estimate the
quantities of
I. Earth work excavation in foundation
II. Concrete in foundation
III. Brick work in foundation & Plinth
IV. Brick Work in superstructure
Particulars of Item No L( m) B(m) H( m) Q ( m3 )
Earth work Excavation
in foundation
Long wall
Short wall
2
2
6.2
3.4
0.9
0.9
0.9
0.9
Total
10.04
5.51
15.55 m3
Long wall- short wall method
Note
L = 5.3 +0.9/2 +0.9/2
= 6.2 m
B= 4.3-0.9 = 3.4 m
1.
Particulars of Item No L( m) B(m) H( m) Q ( m3 )
Concrete in foundation
Long wall
Short wall
2
2
6.2
3.4
0.9
0.9
0.3
0.3
Total
3.35
1.83
5.18 m3
Note
L = 5.3 +0.9/2 +0.9/2= 6.2 m
B= 4.3-0.9 = 3.4 m
2.
Particulars of Item No L( m) B(m) H( m) Q ( m3 )
Brick Work in
foundation & Plinth
Long Wall
I st Footing
2nd Footing
Plinth
2
2
2
5.9
5.8
5.7
0.6
0.5
0.4
0.3
0.3
0.6
2.13
1.74
2.74
3.
Note
L = 5.3 +0.6= 5.9 m
L = 5.3 +0.5= 5.8 m
L = 5.3 +0.4= 5.7 m
Particulars of Item No L( m) B(m) H( m) Q ( m3 )
Short Wall
I st Footing
2nd Footing
Plinth
2
2
2
3.7
3.8
3.9
0.6
0.5
0.4
0.3
0.3
0.6
1.33
1.14
1.87
Total 10.95 m3
3.
Note
L = 4.3 - 0.6= 3.7 m
L = 4.3 -0.5= 3.8 m
L = 4.3 -0.4= 3.7 m
Particulars of Item No L( m) B(m) H( m) Q ( m3 )
Brick Work in Super
structure
Long wall
Short wall
2
2
5.6
4.0
0.3
0.3
3.5
3.5
11.76
8.40
Total 20.16 m3
4.
Note
L = 5.3+0.3= 5.6 m
L = 4.3 +0.3= 4.0 m
CENTRE LINE METHOD
Total Centre Length of wall = 5.3 +4.3 +5.3 +4.3 = 19.20 m
No Particulars of Item No L( m) B(m) H( m) Q ( m3 )
1. EWE in foundation 1 19.20 0.9 0.9 15.55 m3
2. Concrete in
foundation
1 19.20 0.9 0.3 5.18 m3
3. Brick Work
I st footing
2 nd footing
Plinth
1
1
1
19.20
19.20
19.20
0.6
0.5
0.4
0.3
0.3
0.6
Total
3.46
2.88
4.61
10.95 m3
4. B.W in super
structure
1 19.20 0.3 3.5 20.16 m3
CENTRE LINE METHOD
PROBLEM 2
For the given plan of super structure of a single room
building 5 m X 4 m, estimate the quantities of
I. Earth work excavation in foundation
II. Concrete in foundation
III. Brick work in foundation & Plinth
IV. Brick Work in superstructure
PROBLEM 2
Estimate the quantities of the following items of a two
roomed building from the given plan
Total Centre length of wall = 2 X 10.60 + 3 X 6.3 = 40.10 m
DOOR: D- 1.20 m x 2.10 m
WINDOW: W- 1.0 m X 1.5 m
SHELVES: S – 1.0 m X 1.5 m
C/S of wall on AA
CENTRE LINE METHOD
Total Centre length of wall = 2 X 10.60 + 3 X 6.3 = 40.10 m
CENTRE LINE METHOD
No Particulars of Item No L( m) B(m) D( m) Q ( m3 )
1. EWE in foundation 1 39 1.10 1.0 42.9 m3
2. Lime Concrete in
foundation
1 39 1.10 0.3 12.87 m3
Earth work Excavation Length L= 40.10 – 2 X ( 1.10 /2) = 39.0 m
Note
Total Centre length of wall = 2 X 10.60 + 3 X 6.3 = 40.10 m
3. Brick Work
I st footing
2 nd footing
3 rd footing
4 th footing
Plinth wall above
footing
1
1
1
1
1
39.30
39.40
39.50
39.60
39.70
0.8
0.7
0.6
0.5
0.4
0.20
0.10
0.10
0.10
0.80
Total
6.29
2.76
2.37
1.98
12.70
26.10 m3
Note
L= 40.10 – 2X ( 0.80 / 2) = 39.30
L= 40.10 – 2X ( 0.70 / 2) = 39.40
L= 40.10 – 2X ( 0.60 / 2) = 39.50
L= 40.10 – 2X ( 0.50 / 2) = 39.60
L= 40.10 – 2X ( 0.40 / 2) = 39.70
No Particulars of Item No L( m) B(m) D( m) Q ( m3 )
4. Damp Proof Course
2.5 cm c/c
Deduct door sill
1
2
39.70
1.20
0.40
0.40
-
-
Net
15.88
0.96
14.92 m2
Note
L= 40.10 – 2X ( 0.40 / 2) = 39.70
DOOR: D- 1.20 m x 2.10 m
No Particulars of Item No L( m) B(m) D( m) Q ( m3 )
4. I st class B.W in super
structure
1 39.80 0.30 4.2 50.15
Deduct
L= 40.10 – 2 X ( 0.30/2)= 39.80m
Door Openings 2 1.20 0.30 2.10 1.51
Window Openings 4 1.0 0.30 1.50 1.80
Shelves( Back of the wall 10
cm thick wall)
2 1.0 0.20 1.50 0.60
Lintel over door
( Bearing 15 cm)
2 1.50 0.30 0.15 0.14
Lintel over window
( Bearing 15 cm)
4 1.30 0.30 0.15 0.23
Lintel over shelves
( Bearing 15 cm)
2 1.30 0.30 0.15 0.12
Total Deduction 4.40 m3
Net Total 45.75 m3
PROBLEM 3
For the given plan calculate the detail and abstract
estimate by centre line method.
Door D = 1000 X 2000
Window W = 1200X 1500
CENTRE LINE METHOD
Total length = 2 X (3.3+3.8+3.8+4.3) + 3.8+3.3+3.8= 41.3
Door D = 1000 X 2000
Window W = 1200X 1500
No Particulars of Item No L( m) B(m) D( m) Q ( m3 )
1. EWE in foundation 1 39.5 0.9 1.0 35.55 m3
2. Concreting in
foundation
1 39.5 0.9 0.3 10.66 m3
CENTRE LINE METHOD
Note:
L= 41.3 – 4 X 0.9/2 = 39.5
No Particulars of Item No L( m) B(m) D( m) Q ( m3 )
3. R.R Masonry in C.M
I st Footing
II nd Footing
Basement
1
1
1
40.1
40.3
40.5
0.6
0.5
0.4
0.3
0.4
0.6
Total
7.21
8.06
9.72
25.0 m3
Note:
L= 41.3 – 4 X 0.6/2 = 40.1
L= 41.3 – 4 X 0.5/2 = 40.3
L= 41.3 – 4 X 0.4/2 = 40.5
No Particulars of Item No L( m) B(m) D( m) Q ( m2 )
4. D.P.C ( 1: 2 : 4)
Deduct for door sills
1
3
40.5
1.0
0.4
0.3
-
-
Net
16.2
0.9
15.3 m2
L= 41.3 – 4 X 0.4/2 = 40.5 Door D = 1000 X 2000 mm
No Particulars of Item No L( m) B(m) D( m) Q ( m3 )
5. First class B.W in
superstructure
Parapet wall
1
1
40.7
30.4
0.3
0.3
3.
0.6
Total
36.63
5.472
42.10 m3
Note: L= 41.3 – 4 X 0.3/2 = 40.7 L= 2( 7.1 + 8.1) = 30.4
Deduction:
Doors 3 1.0 0.3 2.0 1.80
Windows 8 1.2 0.3 1.5 4.32
Lintel openings over
Doors 3 1.2 0.3 0.1 0.108
Windows 8 1.4 0.3 0.1 0.336
Total 6.564 m3
Net Total 35.53 m3
No Particulars of Item No L( m) B(m) H( m) Q ( m2 )
6. Plastering with 12
mm in C.M 1:5
Plastering for Parapet
wall - Sides
Top
Deduction for
opening Doors
Windows
1X2
1X2
1
3X2
8X2
40.1
30.4
30.4
1.0
1.2
-
-
0.3
-
-
3.0
0.6
-
Total
2.0
1.5
Total
240.6m2
36.48
9.12
45.60 m2
12.0
28.8
40.8 m2
Net Plastering = 240.6 + 45.60 – 40.8 = 245.4 m2
No Particulars of Item No L( m) B(m) H( m) Q ( m2 )
7. Flooring with 25 mm
C.C( 1: 2:4)
Kitchen
Bed
Hall
Sills of Doors
1
1
1
3
3.0
3.5
6.8
1.0
3.5
3.5
4.0
0.3
-
-
-
-
Total
10.5
12.25
27.20
0.9
50.85 m2
8. Celling ( same as
flooring
50.85 m2
9. White washing ( Same as plastering for walls & celling)
= 245.4 +50.85 = 296.25 m2
No Particulars of Item No L( m) B(m) H( m) Q ( m3 )
10. R.C.C ( 1: 2: 4) for
slabs
Lintel over doors
Lintel over windows
Lintel over beams
1
3
8
1
7.4
1.2
1.4
40.7
8.4
0.3
0.3
0.3
1.5
0.1
0.1
0.3
9.324
0.108
0.336
3.663
Total 13.431m3
Note:
L= 41.3- (4 X 0.3/2) = 40.7
S.No Abstract Estimate Quantity UNIT Rate Per Amount
1. Earth work excavation 35.33 m3 465 10m3 1653.00
2. C.C ( 1:4:8) 10.66 m3 1545 1m3 16477.50
3. R.R Masonry 25.0 m3 1391 m3 34775.00
4. Sand Filling in basement 23.22 m3 195 10m3 464.00
5. Brick Masonry 35.53 m3 2291 m3 81417.60
6. R.C.C ( 1:2:4) for lintel ,
Beam
4.107 m3 6030 m3 24765.20
7. R.C.C for Slab 9.324 m3 6030 m3 56223.70
8. C.C for Flooring 5.085 m3 1452 m3 7383.40
9. Supplying & fixing wood
for doors
6.0 m2 1650 m2 9900.00
10. Supplying & fixing wood
for windows & ventilators
14.40 m2 1650 m2 33120.0
ABSTRACT ESTIMATE
S.No Abstract Estimate Quantity UNIT Rate Per Amount
11. Plastering to all exposed
surfaces
245.40 m2 582 10m2 14282.30
12. White washing 296.25 m2 116 10m2 3436.50
13. Flooring with tiles 50.85 m2 4230 10m2 21509.50
14. Painting 45.90 m2 335 10m2 1537.65
Total 3,06945.35
Provision for water supply & sanitary arrangements @12.5% 38,368.20
Provision for electrification @7.5% 23,020.90
Provision for architectural appearance @2% 6138.90
Provision for unforeseen items @ 2% 6138.90
Provision for contingencies @ 4% 12,277.80
Total Amount 3,928,90.00
Exercise Problem
PROBLEM 1
Estimate the quantities of the
following items of a two roomed
building from the given plan
(i) Earth work Excavation (ii) C.C ( 1:4:8)
(iii) Brick Masonry.
D- 1X2.1
W-1.5X1.2
Part A Questions
1. Define Estimate.
2. What are the different types of estimate?
3. Describe centre line method.
4. What are the methods of estimate?
5. Define separate or individual wall method.
6. Define centre line method.
7. Define abstract estimate.
8. Explain about preliminary estimate.
9. Explain about revised estimate.
10. Briefly explain about bay method.
Part B
1. Briefly explain various types of estimate in detail.
2. Differentiate abstract and detail estimate.
3. Estimate in detail the quantities of the following
items of work for an industrial building using centre
line method. (i) Earth work excavation in
foundation. (ii) concrete in foundation. (iii) Brick
work in foundation. (IV) Brick work in
superstructure.
( Hint)
Centre to centre length of inclined wall:
=
= 2.46 m
Total centre line length of wall= 4.80 +(2X4.15)+(2X2.46)+2.25
= 20.27m
1. UNIT -I ESTIMATION OF BUILDINGS.pdf

More Related Content

What's hot

Combined footing 1-1-18
Combined footing 1-1-18Combined footing 1-1-18
Combined footing 1-1-18
SubhashPatankar2
 
HOLLOW CORE SLABS
HOLLOW CORE SLABSHOLLOW CORE SLABS
HOLLOW CORE SLABS
MohdAbdulMujeeb5
 
Footing design
Footing designFooting design
Footing design
Shubham .
 
One way slab load calculation
One way slab load calculation One way slab load calculation
One way slab load calculation
udhayasankar Ramasamy
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Building
ppt_master
 
Lassing and Battering system
Lassing and Battering systemLassing and Battering system
Lassing and Battering system
9033124117
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
Kailash Chander
 
Design of footing as per IS 456-2000
Design of footing as per IS 456-2000Design of footing as per IS 456-2000
Design of footing as per IS 456-2000
PraveenKumar Shanmugam
 
Tension members
Tension membersTension members
Tension members
sky hawk
 
Bar bending schedule
Bar bending scheduleBar bending schedule
Bar bending schedule
civilengineeringfreedownload
 
Water tank design ppt
Water tank design pptWater tank design ppt
Water tank design ppt
Vibhanshu Singh
 
Prestressed composite beams
Prestressed composite beamsPrestressed composite beams
Prestressed composite beams
PraveenKumar Shanmugam
 
workability test of concrete
workability test of concreteworkability test of concrete
workability test of concrete
Karan Patel
 
Design of rcc structures
Design of rcc structuresDesign of rcc structures
Design of rcc structures
R VIJAYAKUMAR
 
Singly Reinforce Concrete
Singly Reinforce ConcreteSingly Reinforce Concrete
Singly Reinforce Concrete
guest00bb06
 
Slabs -Design steps
Slabs -Design steps Slabs -Design steps
Slabs -Design steps
rohinibjn
 
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
Make Mannan
 
Design of One-Way Slab
Design of One-Way SlabDesign of One-Way Slab
Design of One-Way Slab
Mohotasimur Anik
 
Methods of rcc design
Methods of rcc designMethods of rcc design
Methods of rcc design
Selvakumar Palanisamy
 
Two way slab
Two way slabTwo way slab
Two way slab
Priodeep Chowdhury
 

What's hot (20)

Combined footing 1-1-18
Combined footing 1-1-18Combined footing 1-1-18
Combined footing 1-1-18
 
HOLLOW CORE SLABS
HOLLOW CORE SLABSHOLLOW CORE SLABS
HOLLOW CORE SLABS
 
Footing design
Footing designFooting design
Footing design
 
One way slab load calculation
One way slab load calculation One way slab load calculation
One way slab load calculation
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Building
 
Lassing and Battering system
Lassing and Battering systemLassing and Battering system
Lassing and Battering system
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Design of footing as per IS 456-2000
Design of footing as per IS 456-2000Design of footing as per IS 456-2000
Design of footing as per IS 456-2000
 
Tension members
Tension membersTension members
Tension members
 
Bar bending schedule
Bar bending scheduleBar bending schedule
Bar bending schedule
 
Water tank design ppt
Water tank design pptWater tank design ppt
Water tank design ppt
 
Prestressed composite beams
Prestressed composite beamsPrestressed composite beams
Prestressed composite beams
 
workability test of concrete
workability test of concreteworkability test of concrete
workability test of concrete
 
Design of rcc structures
Design of rcc structuresDesign of rcc structures
Design of rcc structures
 
Singly Reinforce Concrete
Singly Reinforce ConcreteSingly Reinforce Concrete
Singly Reinforce Concrete
 
Slabs -Design steps
Slabs -Design steps Slabs -Design steps
Slabs -Design steps
 
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
Numerical problem on bearing capacity is code terzaghi water table (usefulsea...
 
Design of One-Way Slab
Design of One-Way SlabDesign of One-Way Slab
Design of One-Way Slab
 
Methods of rcc design
Methods of rcc designMethods of rcc design
Methods of rcc design
 
Two way slab
Two way slabTwo way slab
Two way slab
 

Similar to 1. UNIT -I ESTIMATION OF BUILDINGS.pdf

E.C.V detail estimate By centre line and Long wall short wall method
E.C.V detail estimate By centre line and Long wall short wall methodE.C.V detail estimate By centre line and Long wall short wall method
E.C.V detail estimate By centre line and Long wall short wall method
Yusuf Challawala
 
estimation of structure
estimation of structureestimation of structure
estimation of structure
kamariya keyur
 
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Nafisa Nazneen Choudhury
 
Center line method 6
Center line method 6Center line method 6
Center line method 6
SAIYYED AKABARALI MOHAMMAD
 
SMM7 Cost Summary Report
SMM7 Cost Summary ReportSMM7 Cost Summary Report
SMM7 Cost Summary Report
Natalie Reid
 
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdfFarm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Avin Kharel
 
tpp3k
tpp3ktpp3k
Long wall and short wall method 4
Long wall and short wall method 4Long wall and short wall method 4
Long wall and short wall method 4
SAIYYED AKABARALI MOHAMMAD
 
LONG WALL AND SHORT WALL METHOD-6
LONG WALL AND SHORT WALL METHOD-6LONG WALL AND SHORT WALL METHOD-6
LONG WALL AND SHORT WALL METHOD-6
SAIYYED AKABARALI MOHAMMAD
 
SANDIN.pptx
SANDIN.pptxSANDIN.pptx
SANDIN.pptx
John Ajish
 
DESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGDESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDING
Anjneya Srivastava
 
Deduction of opening , Number of bars and Bar Bending Scheduling
Deduction of opening , Number of bars and Bar Bending SchedulingDeduction of opening , Number of bars and Bar Bending Scheduling
Deduction of opening , Number of bars and Bar Bending Scheduling
Yash Patel
 
Analysis and Design of Residential building.pptx
Analysis and Design of Residential building.pptxAnalysis and Design of Residential building.pptx
Analysis and Design of Residential building.pptx
DP NITHIN
 
Report costing
Report costingReport costing
Report costing
SamarthDevangamath
 
Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)
hlksd
 
Structural Analysis of SIRI House
Structural Analysis of SIRI HouseStructural Analysis of SIRI House
Structural Analysis of SIRI House
Carmen Chan
 
Chap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfChap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdf
AberaMamoJaleta
 
EC Unit 002 new (1).pdf
EC  Unit 002 new (1).pdfEC  Unit 002 new (1).pdf
EC Unit 002 new (1).pdf
mohsin mohammad
 
Cost estimation of a Building
Cost  estimation of a BuildingCost  estimation of a Building
Cost estimation of a Building
ARAVINDBORRA1
 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal
ashleyyeap
 

Similar to 1. UNIT -I ESTIMATION OF BUILDINGS.pdf (20)

E.C.V detail estimate By centre line and Long wall short wall method
E.C.V detail estimate By centre line and Long wall short wall methodE.C.V detail estimate By centre line and Long wall short wall method
E.C.V detail estimate By centre line and Long wall short wall method
 
estimation of structure
estimation of structureestimation of structure
estimation of structure
 
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
Double Storeyed Building Estimation and Costing by Nafisa Nazneen Choudhury (...
 
Center line method 6
Center line method 6Center line method 6
Center line method 6
 
SMM7 Cost Summary Report
SMM7 Cost Summary ReportSMM7 Cost Summary Report
SMM7 Cost Summary Report
 
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdfFarm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
Farm Survey Assignment, Avin Kharel (16, IAAS Lamjung Campus)..pdf
 
tpp3k
tpp3ktpp3k
tpp3k
 
Long wall and short wall method 4
Long wall and short wall method 4Long wall and short wall method 4
Long wall and short wall method 4
 
LONG WALL AND SHORT WALL METHOD-6
LONG WALL AND SHORT WALL METHOD-6LONG WALL AND SHORT WALL METHOD-6
LONG WALL AND SHORT WALL METHOD-6
 
SANDIN.pptx
SANDIN.pptxSANDIN.pptx
SANDIN.pptx
 
DESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDINGDESIGN OF G+20 MULTISTOREY BUILDING
DESIGN OF G+20 MULTISTOREY BUILDING
 
Deduction of opening , Number of bars and Bar Bending Scheduling
Deduction of opening , Number of bars and Bar Bending SchedulingDeduction of opening , Number of bars and Bar Bending Scheduling
Deduction of opening , Number of bars and Bar Bending Scheduling
 
Analysis and Design of Residential building.pptx
Analysis and Design of Residential building.pptxAnalysis and Design of Residential building.pptx
Analysis and Design of Residential building.pptx
 
Report costing
Report costingReport costing
Report costing
 
Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)Ce1402 estimationandquantitysurveying (1)
Ce1402 estimationandquantitysurveying (1)
 
Structural Analysis of SIRI House
Structural Analysis of SIRI HouseStructural Analysis of SIRI House
Structural Analysis of SIRI House
 
Chap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdfChap-5-T-Girder Example-1.pdf
Chap-5-T-Girder Example-1.pdf
 
EC Unit 002 new (1).pdf
EC  Unit 002 new (1).pdfEC  Unit 002 new (1).pdf
EC Unit 002 new (1).pdf
 
Cost estimation of a Building
Cost  estimation of a BuildingCost  estimation of a Building
Cost estimation of a Building
 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal
 

Recently uploaded

Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
rpskprasana
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
nooriasukmaningtyas
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
IJECEIAES
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
VICTOR MAESTRE RAMIREZ
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
Divyam548318
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
ClaraZara1
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
Dr Ramhari Poudyal
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
Rahul
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 

Recently uploaded (20)

Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
CSM Cloud Service Management Presentarion
CSM Cloud Service Management PresentarionCSM Cloud Service Management Presentarion
CSM Cloud Service Management Presentarion
 
Low power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniquesLow power architecture of logic gates using adiabatic techniques
Low power architecture of logic gates using adiabatic techniques
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
Embedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoringEmbedded machine learning-based road conditions and driving behavior monitoring
Embedded machine learning-based road conditions and driving behavior monitoring
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student MemberIEEE Aerospace and Electronic Systems Society as a Graduate Student Member
IEEE Aerospace and Electronic Systems Society as a Graduate Student Member
 
bank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdfbank management system in java and mysql report1.pdf
bank management system in java and mysql report1.pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)6th International Conference on Machine Learning & Applications (CMLA 2024)
6th International Conference on Machine Learning & Applications (CMLA 2024)
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Literature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptxLiterature Review Basics and Understanding Reference Management.pptx
Literature Review Basics and Understanding Reference Management.pptx
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024ACEP Magazine edition 4th launched on 05.06.2024
ACEP Magazine edition 4th launched on 05.06.2024
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 

1. UNIT -I ESTIMATION OF BUILDINGS.pdf

  • 1. XCE 703 - COST ESTIMATION AND VALUATION UNIT – 1 ESTIMATION OF BUILDINGS PREPARED BY Dr.B.ANUPRIYA Associate Professor/CIVIL
  • 2. • Estimation Estimating is the technique of Computing the various quantities and the expected Expenditure on a particular work or project. • Need for estimation and costing – Estimate give an idea of the cost of the work – Estimate gives an idea of time required for the completion of the work. – Estimate is required to invite the tenders and Quotations ESTIMATION OF BUILDINGS
  • 3. Method of Estimating • Detail Estimate: It consists of working out quantities of different items of work and then working out the cost. Item No. Particulars of Items of work No. L( m) B( m) D( m) Q
  • 4. • Abstract of Estimated cost: Cost under item of work is calculated from the quantities already computed at workable rate. Item no. Description /Particulars Quantity Unit Rate Amount
  • 5. • Earth work excavation • Concrete in foundation • Soling ( when the soil is soft one layer of dry brick is applied below the foundation concrete) • Damp Proof Course • Masonry • Deduction for openings ( doors & Windows) • Lintel over openings • R.C.C work • Flooring & Roofing • Plastering & Pointing • White washing & colour washing • Painting MAIN ITEMS OF WORK
  • 6. S.No Particulars of Item Units 1. Earth work Excavation M3 2. Concreting M3 3. D.P.C M2 4. Brick Work in Foundation, Plinth & Superstructure M3 5. Roofing M3 6. Plastering & Pointing M2 UNITS OF MEASUREMENTS
  • 7. METHODS OF BUILDING ESTIMATES Individual wall method ( Long wall Short wall method)
  • 8. Centre Line method Q= Total c/c distance X Breadth X Depth
  • 9. PROBLEM 1 For the given plan of super structure of a single room building 5 m X 4 m, estimate the quantities of I. Earth work excavation in foundation II. Concrete in foundation III. Brick work in foundation & Plinth IV. Brick Work in superstructure
  • 10.
  • 11. Particulars of Item No L( m) B(m) H( m) Q ( m3 ) Earth work Excavation in foundation Long wall Short wall 2 2 6.2 3.4 0.9 0.9 0.9 0.9 Total 10.04 5.51 15.55 m3 Long wall- short wall method Note L = 5.3 +0.9/2 +0.9/2 = 6.2 m B= 4.3-0.9 = 3.4 m 1.
  • 12. Particulars of Item No L( m) B(m) H( m) Q ( m3 ) Concrete in foundation Long wall Short wall 2 2 6.2 3.4 0.9 0.9 0.3 0.3 Total 3.35 1.83 5.18 m3 Note L = 5.3 +0.9/2 +0.9/2= 6.2 m B= 4.3-0.9 = 3.4 m 2.
  • 13. Particulars of Item No L( m) B(m) H( m) Q ( m3 ) Brick Work in foundation & Plinth Long Wall I st Footing 2nd Footing Plinth 2 2 2 5.9 5.8 5.7 0.6 0.5 0.4 0.3 0.3 0.6 2.13 1.74 2.74 3. Note L = 5.3 +0.6= 5.9 m L = 5.3 +0.5= 5.8 m L = 5.3 +0.4= 5.7 m
  • 14. Particulars of Item No L( m) B(m) H( m) Q ( m3 ) Short Wall I st Footing 2nd Footing Plinth 2 2 2 3.7 3.8 3.9 0.6 0.5 0.4 0.3 0.3 0.6 1.33 1.14 1.87 Total 10.95 m3 3. Note L = 4.3 - 0.6= 3.7 m L = 4.3 -0.5= 3.8 m L = 4.3 -0.4= 3.7 m
  • 15. Particulars of Item No L( m) B(m) H( m) Q ( m3 ) Brick Work in Super structure Long wall Short wall 2 2 5.6 4.0 0.3 0.3 3.5 3.5 11.76 8.40 Total 20.16 m3 4. Note L = 5.3+0.3= 5.6 m L = 4.3 +0.3= 4.0 m
  • 16. CENTRE LINE METHOD Total Centre Length of wall = 5.3 +4.3 +5.3 +4.3 = 19.20 m
  • 17. No Particulars of Item No L( m) B(m) H( m) Q ( m3 ) 1. EWE in foundation 1 19.20 0.9 0.9 15.55 m3 2. Concrete in foundation 1 19.20 0.9 0.3 5.18 m3 3. Brick Work I st footing 2 nd footing Plinth 1 1 1 19.20 19.20 19.20 0.6 0.5 0.4 0.3 0.3 0.6 Total 3.46 2.88 4.61 10.95 m3 4. B.W in super structure 1 19.20 0.3 3.5 20.16 m3 CENTRE LINE METHOD
  • 18. PROBLEM 2 For the given plan of super structure of a single room building 5 m X 4 m, estimate the quantities of I. Earth work excavation in foundation II. Concrete in foundation III. Brick work in foundation & Plinth IV. Brick Work in superstructure
  • 19. PROBLEM 2 Estimate the quantities of the following items of a two roomed building from the given plan Total Centre length of wall = 2 X 10.60 + 3 X 6.3 = 40.10 m
  • 20. DOOR: D- 1.20 m x 2.10 m WINDOW: W- 1.0 m X 1.5 m SHELVES: S – 1.0 m X 1.5 m C/S of wall on AA
  • 21. CENTRE LINE METHOD Total Centre length of wall = 2 X 10.60 + 3 X 6.3 = 40.10 m
  • 22. CENTRE LINE METHOD No Particulars of Item No L( m) B(m) D( m) Q ( m3 ) 1. EWE in foundation 1 39 1.10 1.0 42.9 m3 2. Lime Concrete in foundation 1 39 1.10 0.3 12.87 m3 Earth work Excavation Length L= 40.10 – 2 X ( 1.10 /2) = 39.0 m Note Total Centre length of wall = 2 X 10.60 + 3 X 6.3 = 40.10 m
  • 23. 3. Brick Work I st footing 2 nd footing 3 rd footing 4 th footing Plinth wall above footing 1 1 1 1 1 39.30 39.40 39.50 39.60 39.70 0.8 0.7 0.6 0.5 0.4 0.20 0.10 0.10 0.10 0.80 Total 6.29 2.76 2.37 1.98 12.70 26.10 m3 Note L= 40.10 – 2X ( 0.80 / 2) = 39.30 L= 40.10 – 2X ( 0.70 / 2) = 39.40 L= 40.10 – 2X ( 0.60 / 2) = 39.50 L= 40.10 – 2X ( 0.50 / 2) = 39.60 L= 40.10 – 2X ( 0.40 / 2) = 39.70
  • 24. No Particulars of Item No L( m) B(m) D( m) Q ( m3 ) 4. Damp Proof Course 2.5 cm c/c Deduct door sill 1 2 39.70 1.20 0.40 0.40 - - Net 15.88 0.96 14.92 m2 Note L= 40.10 – 2X ( 0.40 / 2) = 39.70 DOOR: D- 1.20 m x 2.10 m
  • 25. No Particulars of Item No L( m) B(m) D( m) Q ( m3 ) 4. I st class B.W in super structure 1 39.80 0.30 4.2 50.15 Deduct L= 40.10 – 2 X ( 0.30/2)= 39.80m Door Openings 2 1.20 0.30 2.10 1.51 Window Openings 4 1.0 0.30 1.50 1.80 Shelves( Back of the wall 10 cm thick wall) 2 1.0 0.20 1.50 0.60 Lintel over door ( Bearing 15 cm) 2 1.50 0.30 0.15 0.14 Lintel over window ( Bearing 15 cm) 4 1.30 0.30 0.15 0.23 Lintel over shelves ( Bearing 15 cm) 2 1.30 0.30 0.15 0.12 Total Deduction 4.40 m3 Net Total 45.75 m3
  • 26. PROBLEM 3 For the given plan calculate the detail and abstract estimate by centre line method. Door D = 1000 X 2000 Window W = 1200X 1500
  • 27. CENTRE LINE METHOD Total length = 2 X (3.3+3.8+3.8+4.3) + 3.8+3.3+3.8= 41.3 Door D = 1000 X 2000 Window W = 1200X 1500
  • 28. No Particulars of Item No L( m) B(m) D( m) Q ( m3 ) 1. EWE in foundation 1 39.5 0.9 1.0 35.55 m3 2. Concreting in foundation 1 39.5 0.9 0.3 10.66 m3 CENTRE LINE METHOD Note: L= 41.3 – 4 X 0.9/2 = 39.5
  • 29. No Particulars of Item No L( m) B(m) D( m) Q ( m3 ) 3. R.R Masonry in C.M I st Footing II nd Footing Basement 1 1 1 40.1 40.3 40.5 0.6 0.5 0.4 0.3 0.4 0.6 Total 7.21 8.06 9.72 25.0 m3 Note: L= 41.3 – 4 X 0.6/2 = 40.1 L= 41.3 – 4 X 0.5/2 = 40.3 L= 41.3 – 4 X 0.4/2 = 40.5
  • 30. No Particulars of Item No L( m) B(m) D( m) Q ( m2 ) 4. D.P.C ( 1: 2 : 4) Deduct for door sills 1 3 40.5 1.0 0.4 0.3 - - Net 16.2 0.9 15.3 m2 L= 41.3 – 4 X 0.4/2 = 40.5 Door D = 1000 X 2000 mm
  • 31. No Particulars of Item No L( m) B(m) D( m) Q ( m3 ) 5. First class B.W in superstructure Parapet wall 1 1 40.7 30.4 0.3 0.3 3. 0.6 Total 36.63 5.472 42.10 m3 Note: L= 41.3 – 4 X 0.3/2 = 40.7 L= 2( 7.1 + 8.1) = 30.4 Deduction: Doors 3 1.0 0.3 2.0 1.80 Windows 8 1.2 0.3 1.5 4.32 Lintel openings over Doors 3 1.2 0.3 0.1 0.108 Windows 8 1.4 0.3 0.1 0.336 Total 6.564 m3 Net Total 35.53 m3
  • 32. No Particulars of Item No L( m) B(m) H( m) Q ( m2 ) 6. Plastering with 12 mm in C.M 1:5 Plastering for Parapet wall - Sides Top Deduction for opening Doors Windows 1X2 1X2 1 3X2 8X2 40.1 30.4 30.4 1.0 1.2 - - 0.3 - - 3.0 0.6 - Total 2.0 1.5 Total 240.6m2 36.48 9.12 45.60 m2 12.0 28.8 40.8 m2 Net Plastering = 240.6 + 45.60 – 40.8 = 245.4 m2
  • 33. No Particulars of Item No L( m) B(m) H( m) Q ( m2 ) 7. Flooring with 25 mm C.C( 1: 2:4) Kitchen Bed Hall Sills of Doors 1 1 1 3 3.0 3.5 6.8 1.0 3.5 3.5 4.0 0.3 - - - - Total 10.5 12.25 27.20 0.9 50.85 m2 8. Celling ( same as flooring 50.85 m2 9. White washing ( Same as plastering for walls & celling) = 245.4 +50.85 = 296.25 m2
  • 34. No Particulars of Item No L( m) B(m) H( m) Q ( m3 ) 10. R.C.C ( 1: 2: 4) for slabs Lintel over doors Lintel over windows Lintel over beams 1 3 8 1 7.4 1.2 1.4 40.7 8.4 0.3 0.3 0.3 1.5 0.1 0.1 0.3 9.324 0.108 0.336 3.663 Total 13.431m3 Note: L= 41.3- (4 X 0.3/2) = 40.7
  • 35. S.No Abstract Estimate Quantity UNIT Rate Per Amount 1. Earth work excavation 35.33 m3 465 10m3 1653.00 2. C.C ( 1:4:8) 10.66 m3 1545 1m3 16477.50 3. R.R Masonry 25.0 m3 1391 m3 34775.00 4. Sand Filling in basement 23.22 m3 195 10m3 464.00 5. Brick Masonry 35.53 m3 2291 m3 81417.60 6. R.C.C ( 1:2:4) for lintel , Beam 4.107 m3 6030 m3 24765.20 7. R.C.C for Slab 9.324 m3 6030 m3 56223.70 8. C.C for Flooring 5.085 m3 1452 m3 7383.40 9. Supplying & fixing wood for doors 6.0 m2 1650 m2 9900.00 10. Supplying & fixing wood for windows & ventilators 14.40 m2 1650 m2 33120.0 ABSTRACT ESTIMATE
  • 36. S.No Abstract Estimate Quantity UNIT Rate Per Amount 11. Plastering to all exposed surfaces 245.40 m2 582 10m2 14282.30 12. White washing 296.25 m2 116 10m2 3436.50 13. Flooring with tiles 50.85 m2 4230 10m2 21509.50 14. Painting 45.90 m2 335 10m2 1537.65 Total 3,06945.35 Provision for water supply & sanitary arrangements @12.5% 38,368.20 Provision for electrification @7.5% 23,020.90 Provision for architectural appearance @2% 6138.90 Provision for unforeseen items @ 2% 6138.90 Provision for contingencies @ 4% 12,277.80 Total Amount 3,928,90.00
  • 37. Exercise Problem PROBLEM 1 Estimate the quantities of the following items of a two roomed building from the given plan (i) Earth work Excavation (ii) C.C ( 1:4:8) (iii) Brick Masonry. D- 1X2.1 W-1.5X1.2
  • 38. Part A Questions 1. Define Estimate. 2. What are the different types of estimate? 3. Describe centre line method. 4. What are the methods of estimate? 5. Define separate or individual wall method. 6. Define centre line method. 7. Define abstract estimate. 8. Explain about preliminary estimate. 9. Explain about revised estimate. 10. Briefly explain about bay method.
  • 39. Part B 1. Briefly explain various types of estimate in detail. 2. Differentiate abstract and detail estimate. 3. Estimate in detail the quantities of the following items of work for an industrial building using centre line method. (i) Earth work excavation in foundation. (ii) concrete in foundation. (iii) Brick work in foundation. (IV) Brick work in superstructure.
  • 40.
  • 41. ( Hint) Centre to centre length of inclined wall: = = 2.46 m Total centre line length of wall= 4.80 +(2X4.15)+(2X2.46)+2.25 = 20.27m