SlideShare a Scribd company logo
1 of 2
Download to read offline
Forth Replacement Crossing
relocation of the Port Edgar long sea outfall
by Marcus Black B.Eng (Hons) C.Eng MICE
A
s part of their Forth Replacement Crossing project, Transport Scotland requested that Scottish Water relocate
their infrastructure outwith the construction area for the new Forth Road bridge pier, to mitigate the potential
for damage during construction. Scottish Water approached Grontmij in late 2009 to assist in the investigation,
and undertake the detailed design of a replacement long sea outfall for the existing headworks at Port Edgar, South
Queensferry.
At an early meeting, Transport Scotland indicated their desire that
all works should be completed by the end of December 2010, to
tie in with the bridge construction programme. This milestone
necessitated design completion by the end of December 2009, with
a construction site start planned for summer 2010.
Scottish Water acted as client for the design and construction
works. The scope of the project was fixed to require a ‘like for like
replacement of the existing pipeline, and to ensure no impact on flow,
or detriment to the Port Edgar Marina’.
Background
The existing headworks and long sea outfall at Port Edgar were
constructed in the early 1990s. Through implementation of the
Urban Wastewater Treatment Regulations, Scottish Water later
constructed a new wastewater treatment works outwith the town,
transferring flows from Port Edgar.
Design investigations & development
Prior to undertaking the design of the replacement outfall, Grontmij
undertook substantial investigations to determine and review the
original design parameters. Through review of existing records,
discussions with Scottish Water and former employees of Lothian
Regional Council who had been engaged in the original outfall’s
construction supervision, the following was determined:
•	 The pipe material was a high specification armoured pipeline.
•	 During construction, the installation of the pipeline diffuser
proved onerous, due to the depth of installation, strong
currents and low visibility for divers.
Investigation by the design team indicated that the supply cost of
the armoured pipeline was estimated to be in excess of £1 million. In
addition,duetothespecialistnatureofthepipematerial,therewere
a limited number of vessels available which could undertake the
installation works. With respect to the diffuser end, the limitations
imposed on dive times at the working depth and the information
obtained on the previous construction works, indicated that health
and safety would play a significant part in the development of the
design to mitigate risks to construction operatives.
Further investigations were carried out with Scottish Water to
understand the reasons behind the original material selection,
however these proved inconclusive. Text books which contained
sections on the original installation and individual recollections
were at times conflicting.
Wastewater Treatment & Sewerage
Page 132	 UK Water Projects 2011
Concrete block mattress on barge prior to installation		 Courtesy of Scottish Water
Wastewater Treatment & Sewerage
UK Water Projects 2011 										 Page 133
The design team later determined that a combination of the
original method of installation (reel barge), which induces high
tensile forces, and the relatively untested nature of HDPE pipelines
in the early 1990s, were the most likely reasons for their selection.
As such, it was considered that a replacement pipeline constructed
from HDPE would yield significant costs savings, and leave the
installation methodology open, thereby reducing the risk of lack of
availability of installation vessels.
Single pipe solution
Following review of the existing twin pipeline and diffuser
arrangement and, with health and safety at the forefront, the design
team reviewed the pipeline hydraulics and proposed a single pipe
solution, as this would result in minimal diving requirements, and
in improved buildability.
From a review of bathymetric survey information, beyond 400m
from the shoreline the ground profile drops substantially, from
MLWS at -2.15m AOD to the discharge point at -30m AOD. At the
discharge point the profile remains relatively steep, however the
design incorporated a localised rock platform to flatten this section
and elevate the diffuser above the seabed, thereby reducing the
risk of sediment deposition.
The result of the change to the single pipe solution, and removal
of the complex diffuser arrangement, led to a reduced need for
potentially dangerous diving operations, and thereby substantially
mitigated health and safety risks during construction.
Following agreement from key Scottish Water stakeholders to the
single pipe option, the design progressed with the following key
activities being carried out:
•	 Geotechnical desk study utilising historical data and data
obtained from the bridge investigation works.
•	 Hydrodynamic modelling to prove no detriment in water
quality.
•	 Pipeline hydraulics. An existing hydraulic profile was not
available, therefore the system design was undertaken to
match an assessment made of existing system losses.
•	 Calculation of wave forces in the intertidal zone to consider
suitable pipeline protection.
•	 Development of the pipeline profile and backfill specification.
Undertakings
The tender design was completed in December 2009 and, following
approvalofcostestimatesbyScottishWaterandTransportScotland,
the contract was awarded to Farrans Construction in spring 2010.
Farrans engaged Grontmij to undertake finalisation of the detail
design. Through the incorporation of early Value Engineering,
Farrans identified further potential costs savings and programme
efficiencies through the use of concrete mattress protection below
the intertidal zone, and optimisation of excavations and backfill.
Construction works progressed through the summer, with the
pipeline being installed using conventional lay barge techniques.
The works was undertaken by AMC Subsea, a subcontractor
experienced in outfall construction, and completion was achieved
on programme in September 2010.
Despite the challenging design and construction programme,
the project highlighted the benefits of developing a thorough
understanding of the historical context, and the development
of the existing works, which when allied with appropriate Value
Engineering and scope challenge, can produce substantial cost
savings.
The Editor & Publishers wish to thank Marcus Black, Technical
Manager with Grontmij, for preparing the above article for
publication.
Installation of concrete block mattress to pipeline below MLWS		 Courtesy of Scottish Water

More Related Content

What's hot

Dubaidib Wellfield Sdc Presentation July2011
Dubaidib Wellfield Sdc Presentation July2011Dubaidib Wellfield Sdc Presentation July2011
Dubaidib Wellfield Sdc Presentation July2011Shammy Puri
 
modeling and analysis of subsea pipeline by fem
modeling and analysis of subsea pipeline by femmodeling and analysis of subsea pipeline by fem
modeling and analysis of subsea pipeline by fem9845097705
 
Marange Resources Water Supply System Design-Odzi to Concession Pipeline
Marange Resources Water Supply System Design-Odzi to Concession PipelineMarange Resources Water Supply System Design-Odzi to Concession Pipeline
Marange Resources Water Supply System Design-Odzi to Concession PipelineAugustine Marume
 
Design of an Export Pipeline
Design of an Export Pipeline Design of an Export Pipeline
Design of an Export Pipeline Sarah Busef
 
General Flood Resistant Bridge Design Guidelines
General Flood Resistant Bridge Design GuidelinesGeneral Flood Resistant Bridge Design Guidelines
General Flood Resistant Bridge Design GuidelinesGibson Ali Holemba
 
Exploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well TechnologyExploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well TechnologyAbhinav Bisht
 
2016-07-28 Martin Jacobs
2016-07-28 Martin Jacobs2016-07-28 Martin Jacobs
2016-07-28 Martin JacobsMartin Jacobs
 
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGSEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGDEEPAK MALLICK
 
Flood Resistant Bridge Design in PNG rev0117 draft
Flood Resistant Bridge Design in PNG rev0117 draftFlood Resistant Bridge Design in PNG rev0117 draft
Flood Resistant Bridge Design in PNG rev0117 draftGibson Ali Holemba
 
Case study on underwater pipieline leaks and its environmental impacts
Case study on underwater pipieline leaks and its environmental impactsCase study on underwater pipieline leaks and its environmental impacts
Case study on underwater pipieline leaks and its environmental impactsssuser8fec94
 
Michael J. Arnold's Resume (NACE CIP Level 2 Coating Inspector)
Michael J. Arnold's Resume (NACE CIP Level 2 Coating Inspector)Michael J. Arnold's Resume (NACE CIP Level 2 Coating Inspector)
Michael J. Arnold's Resume (NACE CIP Level 2 Coating Inspector)Michael Arnold
 
Flood alleviationbrief170214
Flood alleviationbrief170214Flood alleviationbrief170214
Flood alleviationbrief170214Naoise
 
BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015Blase Townsing
 
Nuts and Bolts of Restoration Implementation
Nuts and Bolts of Restoration ImplementationNuts and Bolts of Restoration Implementation
Nuts and Bolts of Restoration ImplementationBuzzards Bay Coalition
 

What's hot (20)

Dubaidib Wellfield Sdc Presentation July2011
Dubaidib Wellfield Sdc Presentation July2011Dubaidib Wellfield Sdc Presentation July2011
Dubaidib Wellfield Sdc Presentation July2011
 
modeling and analysis of subsea pipeline by fem
modeling and analysis of subsea pipeline by femmodeling and analysis of subsea pipeline by fem
modeling and analysis of subsea pipeline by fem
 
Contech DuroMaxx Steel Reinforced Polyethylene
Contech DuroMaxx Steel Reinforced PolyethyleneContech DuroMaxx Steel Reinforced Polyethylene
Contech DuroMaxx Steel Reinforced Polyethylene
 
Marange Resources Water Supply System Design-Odzi to Concession Pipeline
Marange Resources Water Supply System Design-Odzi to Concession PipelineMarange Resources Water Supply System Design-Odzi to Concession Pipeline
Marange Resources Water Supply System Design-Odzi to Concession Pipeline
 
OGJ Nordstream
OGJ NordstreamOGJ Nordstream
OGJ Nordstream
 
Doug Thiessen Outlook 2012
Doug Thiessen Outlook 2012Doug Thiessen Outlook 2012
Doug Thiessen Outlook 2012
 
Ellis Sess14 102009
Ellis Sess14 102009Ellis Sess14 102009
Ellis Sess14 102009
 
Design of an Export Pipeline
Design of an Export Pipeline Design of an Export Pipeline
Design of an Export Pipeline
 
General Flood Resistant Bridge Design Guidelines
General Flood Resistant Bridge Design GuidelinesGeneral Flood Resistant Bridge Design Guidelines
General Flood Resistant Bridge Design Guidelines
 
Exploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well TechnologyExploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well Technology
 
2016-07-28 Martin Jacobs
2016-07-28 Martin Jacobs2016-07-28 Martin Jacobs
2016-07-28 Martin Jacobs
 
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGSEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
 
Flood Resistant Bridge Design in PNG rev0117 draft
Flood Resistant Bridge Design in PNG rev0117 draftFlood Resistant Bridge Design in PNG rev0117 draft
Flood Resistant Bridge Design in PNG rev0117 draft
 
Case study on underwater pipieline leaks and its environmental impacts
Case study on underwater pipieline leaks and its environmental impactsCase study on underwater pipieline leaks and its environmental impacts
Case study on underwater pipieline leaks and its environmental impacts
 
Cv of mr.Jefferson Tomas Tulabot
Cv of mr.Jefferson Tomas TulabotCv of mr.Jefferson Tomas Tulabot
Cv of mr.Jefferson Tomas Tulabot
 
Michael J. Arnold's Resume (NACE CIP Level 2 Coating Inspector)
Michael J. Arnold's Resume (NACE CIP Level 2 Coating Inspector)Michael J. Arnold's Resume (NACE CIP Level 2 Coating Inspector)
Michael J. Arnold's Resume (NACE CIP Level 2 Coating Inspector)
 
Flood alleviationbrief170214
Flood alleviationbrief170214Flood alleviationbrief170214
Flood alleviationbrief170214
 
2000_Charleston_cement
2000_Charleston_cement2000_Charleston_cement
2000_Charleston_cement
 
BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015BLASE TOWNSING CV 2015
BLASE TOWNSING CV 2015
 
Nuts and Bolts of Restoration Implementation
Nuts and Bolts of Restoration ImplementationNuts and Bolts of Restoration Implementation
Nuts and Bolts of Restoration Implementation
 

Viewers also liked

Medikamenten Einnahme von Jugendlichen mit einer Herzerkrankung – eine Heraus...
Medikamenten Einnahme von Jugendlichen mit einer Herzerkrankung – eine Heraus...Medikamenten Einnahme von Jugendlichen mit einer Herzerkrankung – eine Heraus...
Medikamenten Einnahme von Jugendlichen mit einer Herzerkrankung – eine Heraus...kalaidos-gesundheit
 
Farmprojectslidehsow
FarmprojectslidehsowFarmprojectslidehsow
Farmprojectslidehsowtmlolsen
 
World of Creative Designer & Front-end-Developer
World of Creative Designer & Front-end-DeveloperWorld of Creative Designer & Front-end-Developer
World of Creative Designer & Front-end-DeveloperCatch Themes
 

Viewers also liked (9)

SlideShow
SlideShowSlideShow
SlideShow
 
Class #04
Class #04Class #04
Class #04
 
Class #05
Class #05Class #05
Class #05
 
Medikamenten Einnahme von Jugendlichen mit einer Herzerkrankung – eine Heraus...
Medikamenten Einnahme von Jugendlichen mit einer Herzerkrankung – eine Heraus...Medikamenten Einnahme von Jugendlichen mit einer Herzerkrankung – eine Heraus...
Medikamenten Einnahme von Jugendlichen mit einer Herzerkrankung – eine Heraus...
 
English, a l'educació infantil
English, a l'educació infantilEnglish, a l'educació infantil
English, a l'educació infantil
 
Farmprojectslidehsow
FarmprojectslidehsowFarmprojectslidehsow
Farmprojectslidehsow
 
World of Creative Designer & Front-end-Developer
World of Creative Designer & Front-end-DeveloperWorld of Creative Designer & Front-end-Developer
World of Creative Designer & Front-end-Developer
 
Pakaagee
PakaageePakaagee
Pakaagee
 
Marine structures
Marine structuresMarine structures
Marine structures
 

Similar to Scottish_Forth_Crossing_2011

Melbourne Channel Deepening
Melbourne Channel DeepeningMelbourne Channel Deepening
Melbourne Channel DeepeningSikko Krol
 
Marine_Brochure_For_Web
Marine_Brochure_For_WebMarine_Brochure_For_Web
Marine_Brochure_For_WebMike Bisland
 
Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Soumalya Bag
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012Mike Vernon
 
Fib2010 article263 concrete durability_rev_a
Fib2010 article263 concrete durability_rev_aFib2010 article263 concrete durability_rev_a
Fib2010 article263 concrete durability_rev_agefyra-rion
 
G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15Greg Clifford
 
15.2.2 bored pile wall - method statement
15.2.2   bored pile wall - method statement15.2.2   bored pile wall - method statement
15.2.2 bored pile wall - method statementNECB
 
Hoover dam bypass bridge
Hoover dam bypass bridgeHoover dam bypass bridge
Hoover dam bypass bridgeBismillah Arif
 
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...Michal Krzeminski
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15ADAM DUKE
 
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015Harry Holland
 
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015Harry Holland
 
2014_BRMCA_Award_Excellence_in_Customer_Service_Concrete_Nov_2014
2014_BRMCA_Award_Excellence_in_Customer_Service_Concrete_Nov_20142014_BRMCA_Award_Excellence_in_Customer_Service_Concrete_Nov_2014
2014_BRMCA_Award_Excellence_in_Customer_Service_Concrete_Nov_2014Wendy Ling
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16Leo Youngman
 

Similar to Scottish_Forth_Crossing_2011 (20)

03_WP-CPL_0704_LR
03_WP-CPL_0704_LR03_WP-CPL_0704_LR
03_WP-CPL_0704_LR
 
Melbourne Channel Deepening
Melbourne Channel DeepeningMelbourne Channel Deepening
Melbourne Channel Deepening
 
Marine_Brochure_For_Web
Marine_Brochure_For_WebMarine_Brochure_For_Web
Marine_Brochure_For_Web
 
Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891Hooverdambypassbridge 151003030959-lva1-app6891
Hooverdambypassbridge 151003030959-lva1-app6891
 
Libya & TERRA ROSSA
Libya & TERRA ROSSALibya & TERRA ROSSA
Libya & TERRA ROSSA
 
Virginia
VirginiaVirginia
Virginia
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012
 
Fib2010 article263 concrete durability_rev_a
Fib2010 article263 concrete durability_rev_aFib2010 article263 concrete durability_rev_a
Fib2010 article263 concrete durability_rev_a
 
ECS Food For Thought_ presentation Final2
ECS Food For Thought_ presentation Final2ECS Food For Thought_ presentation Final2
ECS Food For Thought_ presentation Final2
 
G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15G_Clifford_resume_Feb 15
G_Clifford_resume_Feb 15
 
Curricula Vitae - NVB
Curricula Vitae - NVBCurricula Vitae - NVB
Curricula Vitae - NVB
 
15.2.2 bored pile wall - method statement
15.2.2   bored pile wall - method statement15.2.2   bored pile wall - method statement
15.2.2 bored pile wall - method statement
 
Hoover dam bypass bridge
Hoover dam bypass bridgeHoover dam bypass bridge
Hoover dam bypass bridge
 
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...
(2012) - Fok N, Vincent P, Qiu T, Krzeminski M - A Case Study of Ground Impro...
 
RA_CV - October 2016
RA_CV - October 2016RA_CV - October 2016
RA_CV - October 2016
 
UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15UKWP Case study - Mauchline Final copy 23 06 15
UKWP Case study - Mauchline Final copy 23 06 15
 
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
 
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015Harry Holland CV Update Water Infrastructure & Pipelines August 2015
Harry Holland CV Update Water Infrastructure & Pipelines August 2015
 
2014_BRMCA_Award_Excellence_in_Customer_Service_Concrete_Nov_2014
2014_BRMCA_Award_Excellence_in_Customer_Service_Concrete_Nov_20142014_BRMCA_Award_Excellence_in_Customer_Service_Concrete_Nov_2014
2014_BRMCA_Award_Excellence_in_Customer_Service_Concrete_Nov_2014
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16
 

Scottish_Forth_Crossing_2011

  • 1. Forth Replacement Crossing relocation of the Port Edgar long sea outfall by Marcus Black B.Eng (Hons) C.Eng MICE A s part of their Forth Replacement Crossing project, Transport Scotland requested that Scottish Water relocate their infrastructure outwith the construction area for the new Forth Road bridge pier, to mitigate the potential for damage during construction. Scottish Water approached Grontmij in late 2009 to assist in the investigation, and undertake the detailed design of a replacement long sea outfall for the existing headworks at Port Edgar, South Queensferry. At an early meeting, Transport Scotland indicated their desire that all works should be completed by the end of December 2010, to tie in with the bridge construction programme. This milestone necessitated design completion by the end of December 2009, with a construction site start planned for summer 2010. Scottish Water acted as client for the design and construction works. The scope of the project was fixed to require a ‘like for like replacement of the existing pipeline, and to ensure no impact on flow, or detriment to the Port Edgar Marina’. Background The existing headworks and long sea outfall at Port Edgar were constructed in the early 1990s. Through implementation of the Urban Wastewater Treatment Regulations, Scottish Water later constructed a new wastewater treatment works outwith the town, transferring flows from Port Edgar. Design investigations & development Prior to undertaking the design of the replacement outfall, Grontmij undertook substantial investigations to determine and review the original design parameters. Through review of existing records, discussions with Scottish Water and former employees of Lothian Regional Council who had been engaged in the original outfall’s construction supervision, the following was determined: • The pipe material was a high specification armoured pipeline. • During construction, the installation of the pipeline diffuser proved onerous, due to the depth of installation, strong currents and low visibility for divers. Investigation by the design team indicated that the supply cost of the armoured pipeline was estimated to be in excess of £1 million. In addition,duetothespecialistnatureofthepipematerial,therewere a limited number of vessels available which could undertake the installation works. With respect to the diffuser end, the limitations imposed on dive times at the working depth and the information obtained on the previous construction works, indicated that health and safety would play a significant part in the development of the design to mitigate risks to construction operatives. Further investigations were carried out with Scottish Water to understand the reasons behind the original material selection, however these proved inconclusive. Text books which contained sections on the original installation and individual recollections were at times conflicting. Wastewater Treatment & Sewerage Page 132 UK Water Projects 2011 Concrete block mattress on barge prior to installation Courtesy of Scottish Water
  • 2. Wastewater Treatment & Sewerage UK Water Projects 2011 Page 133 The design team later determined that a combination of the original method of installation (reel barge), which induces high tensile forces, and the relatively untested nature of HDPE pipelines in the early 1990s, were the most likely reasons for their selection. As such, it was considered that a replacement pipeline constructed from HDPE would yield significant costs savings, and leave the installation methodology open, thereby reducing the risk of lack of availability of installation vessels. Single pipe solution Following review of the existing twin pipeline and diffuser arrangement and, with health and safety at the forefront, the design team reviewed the pipeline hydraulics and proposed a single pipe solution, as this would result in minimal diving requirements, and in improved buildability. From a review of bathymetric survey information, beyond 400m from the shoreline the ground profile drops substantially, from MLWS at -2.15m AOD to the discharge point at -30m AOD. At the discharge point the profile remains relatively steep, however the design incorporated a localised rock platform to flatten this section and elevate the diffuser above the seabed, thereby reducing the risk of sediment deposition. The result of the change to the single pipe solution, and removal of the complex diffuser arrangement, led to a reduced need for potentially dangerous diving operations, and thereby substantially mitigated health and safety risks during construction. Following agreement from key Scottish Water stakeholders to the single pipe option, the design progressed with the following key activities being carried out: • Geotechnical desk study utilising historical data and data obtained from the bridge investigation works. • Hydrodynamic modelling to prove no detriment in water quality. • Pipeline hydraulics. An existing hydraulic profile was not available, therefore the system design was undertaken to match an assessment made of existing system losses. • Calculation of wave forces in the intertidal zone to consider suitable pipeline protection. • Development of the pipeline profile and backfill specification. Undertakings The tender design was completed in December 2009 and, following approvalofcostestimatesbyScottishWaterandTransportScotland, the contract was awarded to Farrans Construction in spring 2010. Farrans engaged Grontmij to undertake finalisation of the detail design. Through the incorporation of early Value Engineering, Farrans identified further potential costs savings and programme efficiencies through the use of concrete mattress protection below the intertidal zone, and optimisation of excavations and backfill. Construction works progressed through the summer, with the pipeline being installed using conventional lay barge techniques. The works was undertaken by AMC Subsea, a subcontractor experienced in outfall construction, and completion was achieved on programme in September 2010. Despite the challenging design and construction programme, the project highlighted the benefits of developing a thorough understanding of the historical context, and the development of the existing works, which when allied with appropriate Value Engineering and scope challenge, can produce substantial cost savings. The Editor & Publishers wish to thank Marcus Black, Technical Manager with Grontmij, for preparing the above article for publication. Installation of concrete block mattress to pipeline below MLWS Courtesy of Scottish Water