SlideShare a Scribd company logo
1 of 20
Presented By,
FAISAL RAHMAN P (OET-2021-31-04)
M. Tech CHE, KUFOS
QUAY FAILURE
IN BARCELONA
HARBOUR
1
TABLE
OF
CONTENTS
What Happened?
03
Introduction
01
Project Overview
02
WHY?
04
Conclusions
05
2
INTRODUCTION
● The Port of Barcelona Southern expansion project aimed at doubling of it’s capacity, in both
quantitative terms (wharves, breakwaters, cranes, accesses) and qualitatively (new shipping
lines, more services and more connections).
● The southern breakwater, already completed, is 4.8 km long and divided into three sections.
● The extension of the eastern breakwater, also completed, reaches a length of 2.1 km.
● At the El Prat wharf, a wharf is being built measuring 1.5 km in length, with a depth of 16.50
m, generating a surface area of 100 hectares.
3
Barcelona Harbour Extension Projects, 2005-15
(/Researchgate)
The main actions for the southern
expansion of the Port are;
a. The construction of the
southern breakwater
a. The extension of the
eastern breakwater and
a. The construction of the El
Prat wharf.
PROJECT OVERVIEW
4
A 1,500m long prat quay was constructed in two phases;
● Phase 1:
○ Prat I was built after mud dredging from 16 to 25 m bsl and the placement of a 9 m thick
rock fill blanket.
○ The wall itself consisted of four caissons on granular foundations.
○ Phase 1 act as a breakwater.
● Phase 2:
○ Phase 2 was protected by the extension to the sloping breakwater.
○ Following dredging to 24 m bsl, the 11.5 m wide caisson was placed on a 8 m thick rock
blanket at a level of 16.5 m bsl.
○ Since the second phase was protected by the breakwater and hence was designed as a
gravity structure.
5
On 1 January 2007,
the quay collapsed, and
the caisson slid.
WHAT HAPPENED?
State of Prat Quay after the collapse(/Researchgate)
6
WHY?
State of Prat Quay after the collapse(/Researchgate)
7
1
The first phase was to act as a breakwater while the
second phase was protected by the breakwater and
hence was designed as a gravity structure.
8
2
The phases and the transformation from breakwater
to quay, filling, consolidation and paving were put
out to tender separately, with a slight time lag.
The caisson and fill works were undertaken by different
companies and there were different site managers.
9
3
The nature of the hydraulically placed fill was not
adequately studied and it was placed very quickly to
meet operational requirements.
10
4
The fills were placed commencing at the landward
side, such that a lake was created inside the new
structure.
Drain spillways were not provided.
11
5
In the initial phase, when the structure was built as
a breakwater, there was no rear rubble mound,
consequently the loading on the monolithic
structure was greater than anticipated in the design.
12
6
The caisson acted as a dam, hence the pressures
were higher than anticipated at design stage.
13
7
The tidal environment, as well as the variable
pressure imposed on the structure by waves, was
difficult to model.
The balance of effective and neutral stresses may
cause ground liquefaction and siphoning.
14
With these limitations, the quay was prone to sliding as
a consequence of only a slight environmental, geotechnical or
structural disturbance and it collapsed on 1 January 2007.
After debris removal, blasting and caisson refloating,
repair works were undertaken during 2008 and 2009
15
State of the caissons after the quay slid(/Researchgate)
16
● Before using gravity structures in this marine environment, the ground requires improvement or
consolidation to ensure adequate geotechnical parameters.
● The soft material should be removed by dredging and replaced with adequately compacted
material.
● Care must be taken if rapid construction is undertaken as loading too quickly may cause short
term stability problems. The construction works should not be compromised by the client’s desire
to utilise the facility at the earliest possible date.
● Where gravity walls are used, a rear rubble mound of granular material should be constructed with
a slope angle < 37.
CONCLUSIONS
17
● An inner construction is interdependent with the linear structure. The
containment wall and yard fills cannot be addressed separately.
● Provision should be made for the removal of water as the fill operation
takes place.
● Analyses should be made not only prior to construction but during all
phases of the works.
CONCLUSIONS
18
Jose ́ Marı ́a del Campo, Vicente Negro, 2010, “Failures of harbour walls at Malaga and
Barcelona”, Bull Eng Geol Environ (2011) 70:1–6 DOI 10.1007/s10064-010-0313-z
REFERENCE
19
THANK YOU…
20

More Related Content

What's hot

NOH3 Launching Girder Assembly and Erection VSL
NOH3  Launching Girder Assembly and Erection VSLNOH3  Launching Girder Assembly and Erection VSL
NOH3 Launching Girder Assembly and Erection VSLIan Kelly
 
training report on pwd
training report on pwdtraining report on pwd
training report on pwdAjay Upadhyay
 
Structural analysis of a road bridge using ansys
Structural analysis of a road bridge  using ansysStructural analysis of a road bridge  using ansys
Structural analysis of a road bridge using ansysSubham kumar
 
Analysis and design of multi-storey building using staad.Pro
Analysis and design of multi-storey building using staad.ProAnalysis and design of multi-storey building using staad.Pro
Analysis and design of multi-storey building using staad.Progsharda123
 
Railway engineering (CIVIL ENGINEERING)
Railway engineering (CIVIL ENGINEERING)Railway engineering (CIVIL ENGINEERING)
Railway engineering (CIVIL ENGINEERING)comsats
 
Earth retaining structures
Earth retaining structuresEarth retaining structures
Earth retaining structuresJNTUK
 
Concrete and steel bridges
Concrete and steel bridgesConcrete and steel bridges
Concrete and steel bridgesMadujith Sagara
 
Staad Pro Intro
Staad Pro IntroStaad Pro Intro
Staad Pro IntroSolai Raja
 
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGEAELC
 
Geometric desing of railway track
Geometric desing of railway trackGeometric desing of railway track
Geometric desing of railway trackmohitjain123
 
3.4 pushover analysis
3.4 pushover analysis3.4 pushover analysis
3.4 pushover analysisNASRIN AFROZ
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEsrinivas cnu
 
Design & Analysis of G+2 Residential Building Using STAAD Pro
Design & Analysis of G+2 Residential Building Using STAAD ProDesign & Analysis of G+2 Residential Building Using STAAD Pro
Design & Analysis of G+2 Residential Building Using STAAD ProPARAS TANEJA
 
Railway engineering By T.Ravi Prakash/Kongu Engineering College
Railway engineering By T.Ravi Prakash/Kongu Engineering CollegeRailway engineering By T.Ravi Prakash/Kongu Engineering College
Railway engineering By T.Ravi Prakash/Kongu Engineering Collegeravicivil
 

What's hot (20)

NOH3 Launching Girder Assembly and Erection VSL
NOH3  Launching Girder Assembly and Erection VSLNOH3  Launching Girder Assembly and Erection VSL
NOH3 Launching Girder Assembly and Erection VSL
 
training report on pwd
training report on pwdtraining report on pwd
training report on pwd
 
Structural analysis of a road bridge using ansys
Structural analysis of a road bridge  using ansysStructural analysis of a road bridge  using ansys
Structural analysis of a road bridge using ansys
 
Analysis and design of multi-storey building using staad.Pro
Analysis and design of multi-storey building using staad.ProAnalysis and design of multi-storey building using staad.Pro
Analysis and design of multi-storey building using staad.Pro
 
Railway engineering (CIVIL ENGINEERING)
Railway engineering (CIVIL ENGINEERING)Railway engineering (CIVIL ENGINEERING)
Railway engineering (CIVIL ENGINEERING)
 
Earth retaining structures
Earth retaining structuresEarth retaining structures
Earth retaining structures
 
Concrete and steel bridges
Concrete and steel bridgesConcrete and steel bridges
Concrete and steel bridges
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Rail bridge and composite girder bridge analysis
Rail bridge and composite girder bridge analysisRail bridge and composite girder bridge analysis
Rail bridge and composite girder bridge analysis
 
Staad Pro Intro
Staad Pro IntroStaad Pro Intro
Staad Pro Intro
 
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE4.	STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
4. STUDY ONVARIATION OF JOINT FORCES IN STEEL TRUSS BRIDGE
 
Geometric desing of railway track
Geometric desing of railway trackGeometric desing of railway track
Geometric desing of railway track
 
3.4 pushover analysis
3.4 pushover analysis3.4 pushover analysis
3.4 pushover analysis
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Design & Analysis of G+2 Residential Building Using STAAD Pro
Design & Analysis of G+2 Residential Building Using STAAD ProDesign & Analysis of G+2 Residential Building Using STAAD Pro
Design & Analysis of G+2 Residential Building Using STAAD Pro
 
Bearing
BearingBearing
Bearing
 
Presentation on bridges
Presentation on bridgesPresentation on bridges
Presentation on bridges
 
Railway engineering By T.Ravi Prakash/Kongu Engineering College
Railway engineering By T.Ravi Prakash/Kongu Engineering CollegeRailway engineering By T.Ravi Prakash/Kongu Engineering College
Railway engineering By T.Ravi Prakash/Kongu Engineering College
 
Bridge introduction
Bridge introductionBridge introduction
Bridge introduction
 

Similar to Quay failure in barcelona harbour

ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptxAditya Mane
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationAmir Amdani
 
Case Study Brighton Pier 2012
Case Study   Brighton Pier 2012Case Study   Brighton Pier 2012
Case Study Brighton Pier 2012gavinrixon
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Angelo Indelicato
 
20150421031337318
2015042103133731820150421031337318
20150421031337318James Prs
 
2008-05 International Water Power & Dam Construction_ ROGUN 2400MW
2008-05 International Water Power & Dam Construction_ ROGUN 2400MW2008-05 International Water Power & Dam Construction_ ROGUN 2400MW
2008-05 International Water Power & Dam Construction_ ROGUN 2400MWRoland Schmidt
 
Nikhil Gopi.doc.pptx
Nikhil Gopi.doc.pptxNikhil Gopi.doc.pptx
Nikhil Gopi.doc.pptxitech2017
 
Bahrain - Half Moon Bay Project - Project Manager
Bahrain - Half Moon Bay Project - Project ManagerBahrain - Half Moon Bay Project - Project Manager
Bahrain - Half Moon Bay Project - Project ManagerNiels Asjee
 
Leaning Tower of Pisa.pptx
Leaning Tower of Pisa.pptxLeaning Tower of Pisa.pptx
Leaning Tower of Pisa.pptxVISHVACHAUDHARY2
 
Submerged floating tunnel
Submerged floating tunnelSubmerged floating tunnel
Submerged floating tunnelShaikh Ismail
 

Similar to Quay failure in barcelona harbour (20)

ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Body corctd
Body corctdBody corctd
Body corctd
 
BHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentationBHUSAN GEOJE FIXED LINK presentation
BHUSAN GEOJE FIXED LINK presentation
 
Busan Geoje
Busan GeojeBusan Geoje
Busan Geoje
 
Think Outside The Box
Think Outside The BoxThink Outside The Box
Think Outside The Box
 
Case Study Brighton Pier 2012
Case Study   Brighton Pier 2012Case Study   Brighton Pier 2012
Case Study Brighton Pier 2012
 
South Jetty
South JettySouth Jetty
South Jetty
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...
 
KIX
KIXKIX
KIX
 
20150421031337318
2015042103133731820150421031337318
20150421031337318
 
Yumesaki Tunnel
Yumesaki TunnelYumesaki Tunnel
Yumesaki Tunnel
 
2008-05 International Water Power & Dam Construction_ ROGUN 2400MW
2008-05 International Water Power & Dam Construction_ ROGUN 2400MW2008-05 International Water Power & Dam Construction_ ROGUN 2400MW
2008-05 International Water Power & Dam Construction_ ROGUN 2400MW
 
Pecker aci2003
Pecker aci2003Pecker aci2003
Pecker aci2003
 
Nikhil Gopi.doc.pptx
Nikhil Gopi.doc.pptxNikhil Gopi.doc.pptx
Nikhil Gopi.doc.pptx
 
DP0901.pdf
DP0901.pdfDP0901.pdf
DP0901.pdf
 
Bahrain - Half Moon Bay Project - Project Manager
Bahrain - Half Moon Bay Project - Project ManagerBahrain - Half Moon Bay Project - Project Manager
Bahrain - Half Moon Bay Project - Project Manager
 
Leaning Tower of Pisa.pptx
Leaning Tower of Pisa.pptxLeaning Tower of Pisa.pptx
Leaning Tower of Pisa.pptx
 
Submerged floating tunnel
Submerged floating tunnelSubmerged floating tunnel
Submerged floating tunnel
 

Recently uploaded

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 

Recently uploaded (20)

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 

Quay failure in barcelona harbour

  • 1. Presented By, FAISAL RAHMAN P (OET-2021-31-04) M. Tech CHE, KUFOS QUAY FAILURE IN BARCELONA HARBOUR 1
  • 3. INTRODUCTION ● The Port of Barcelona Southern expansion project aimed at doubling of it’s capacity, in both quantitative terms (wharves, breakwaters, cranes, accesses) and qualitatively (new shipping lines, more services and more connections). ● The southern breakwater, already completed, is 4.8 km long and divided into three sections. ● The extension of the eastern breakwater, also completed, reaches a length of 2.1 km. ● At the El Prat wharf, a wharf is being built measuring 1.5 km in length, with a depth of 16.50 m, generating a surface area of 100 hectares. 3
  • 4. Barcelona Harbour Extension Projects, 2005-15 (/Researchgate) The main actions for the southern expansion of the Port are; a. The construction of the southern breakwater a. The extension of the eastern breakwater and a. The construction of the El Prat wharf. PROJECT OVERVIEW 4
  • 5. A 1,500m long prat quay was constructed in two phases; ● Phase 1: ○ Prat I was built after mud dredging from 16 to 25 m bsl and the placement of a 9 m thick rock fill blanket. ○ The wall itself consisted of four caissons on granular foundations. ○ Phase 1 act as a breakwater. ● Phase 2: ○ Phase 2 was protected by the extension to the sloping breakwater. ○ Following dredging to 24 m bsl, the 11.5 m wide caisson was placed on a 8 m thick rock blanket at a level of 16.5 m bsl. ○ Since the second phase was protected by the breakwater and hence was designed as a gravity structure. 5
  • 6. On 1 January 2007, the quay collapsed, and the caisson slid. WHAT HAPPENED? State of Prat Quay after the collapse(/Researchgate) 6
  • 7. WHY? State of Prat Quay after the collapse(/Researchgate) 7
  • 8. 1 The first phase was to act as a breakwater while the second phase was protected by the breakwater and hence was designed as a gravity structure. 8
  • 9. 2 The phases and the transformation from breakwater to quay, filling, consolidation and paving were put out to tender separately, with a slight time lag. The caisson and fill works were undertaken by different companies and there were different site managers. 9
  • 10. 3 The nature of the hydraulically placed fill was not adequately studied and it was placed very quickly to meet operational requirements. 10
  • 11. 4 The fills were placed commencing at the landward side, such that a lake was created inside the new structure. Drain spillways were not provided. 11
  • 12. 5 In the initial phase, when the structure was built as a breakwater, there was no rear rubble mound, consequently the loading on the monolithic structure was greater than anticipated in the design. 12
  • 13. 6 The caisson acted as a dam, hence the pressures were higher than anticipated at design stage. 13
  • 14. 7 The tidal environment, as well as the variable pressure imposed on the structure by waves, was difficult to model. The balance of effective and neutral stresses may cause ground liquefaction and siphoning. 14
  • 15. With these limitations, the quay was prone to sliding as a consequence of only a slight environmental, geotechnical or structural disturbance and it collapsed on 1 January 2007. After debris removal, blasting and caisson refloating, repair works were undertaken during 2008 and 2009 15
  • 16. State of the caissons after the quay slid(/Researchgate) 16
  • 17. ● Before using gravity structures in this marine environment, the ground requires improvement or consolidation to ensure adequate geotechnical parameters. ● The soft material should be removed by dredging and replaced with adequately compacted material. ● Care must be taken if rapid construction is undertaken as loading too quickly may cause short term stability problems. The construction works should not be compromised by the client’s desire to utilise the facility at the earliest possible date. ● Where gravity walls are used, a rear rubble mound of granular material should be constructed with a slope angle < 37. CONCLUSIONS 17
  • 18. ● An inner construction is interdependent with the linear structure. The containment wall and yard fills cannot be addressed separately. ● Provision should be made for the removal of water as the fill operation takes place. ● Analyses should be made not only prior to construction but during all phases of the works. CONCLUSIONS 18
  • 19. Jose ́ Marı ́a del Campo, Vicente Negro, 2010, “Failures of harbour walls at Malaga and Barcelona”, Bull Eng Geol Environ (2011) 70:1–6 DOI 10.1007/s10064-010-0313-z REFERENCE 19