Civil Engineering Technical Project for an existing T intersection needing to be updated. Plans submitted to NCDOT, City of Asheville, and to Wilbur Smith Engineering company over the Wilma Dykeman Riverway Project in Asheville North Carolina. This was submitted by the Senior Project Class Spring 2011
Okeechobee Road (US 27/SR 25) from Krome Avenue (SR 997) to NW 79 Avenue PD&E Study presentation to the Citizens Transportation Advisory Committee (CTAC), July 23, 2014.
Walton Boulevard Reconstruction, APWA Project of the YearOHM Advisors
http://www.ohm-advisors.com. An APWA award-winning project, reconstructing Walton Boulevard, in the City of Auburn Hills, was no easy task. Start with 1.5 miles of road, an old bridge over a major freeway, and three government owners. Then, throw in high priority federal and state funding deadlines and a five month schedule to complete. No problem. If you're OHM, and you're committed to Advancing Communities!
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Fairfax County
A virtual meeting about the project will be held on August 19, 2020 at 6:00 p.m. Please see a how to sign in on slide 2. A 2019 study evaluated several alternatives for replacement. Those alternatives will be discussed with the community at the virtual meeting.
This project included rehabilitation of four sanitary sewer metering vaults. These meter vaults included Dukes Car Wash, Lower Holmes Run, Tod Street, and Scotts Run. The Dukes Car Wash and Lower Holmes Run Meters are in the City of Alexandria, the Tod Street Meter is in Falls Church in the Providence District, and the Scotts Run Meter is in the Scotts Run Nature Preserve in the Dranesville District. Work included removal of existing control panels, conduits and metering equipment, rehabilitation of the interior of the vaults with a cementitious coating and epoxy liner system, installation of new control panels and conduit, and reinstallation of flow metering devices. This project was substantially complete on August 30, 2021.
Civil Engineering Technical Project for an existing T intersection needing to be updated. Plans submitted to NCDOT, City of Asheville, and to Wilbur Smith Engineering company over the Wilma Dykeman Riverway Project in Asheville North Carolina. This was submitted by the Senior Project Class Spring 2011
Okeechobee Road (US 27/SR 25) from Krome Avenue (SR 997) to NW 79 Avenue PD&E Study presentation to the Citizens Transportation Advisory Committee (CTAC), July 23, 2014.
Walton Boulevard Reconstruction, APWA Project of the YearOHM Advisors
http://www.ohm-advisors.com. An APWA award-winning project, reconstructing Walton Boulevard, in the City of Auburn Hills, was no easy task. Start with 1.5 miles of road, an old bridge over a major freeway, and three government owners. Then, throw in high priority federal and state funding deadlines and a five month schedule to complete. No problem. If you're OHM, and you're committed to Advancing Communities!
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Fairfax County
A virtual meeting about the project will be held on August 19, 2020 at 6:00 p.m. Please see a how to sign in on slide 2. A 2019 study evaluated several alternatives for replacement. Those alternatives will be discussed with the community at the virtual meeting.
This project included rehabilitation of four sanitary sewer metering vaults. These meter vaults included Dukes Car Wash, Lower Holmes Run, Tod Street, and Scotts Run. The Dukes Car Wash and Lower Holmes Run Meters are in the City of Alexandria, the Tod Street Meter is in Falls Church in the Providence District, and the Scotts Run Meter is in the Scotts Run Nature Preserve in the Dranesville District. Work included removal of existing control panels, conduits and metering equipment, rehabilitation of the interior of the vaults with a cementitious coating and epoxy liner system, installation of new control panels and conduit, and reinstallation of flow metering devices. This project was substantially complete on August 30, 2021.
Lakevale Estates Collection Improvements Community MeetingFairfax County
Short-term: Install Backflow Devices
Devices installed
Regular system maintenance is ongoing
Mid-term: Temporary modifications to the Lakevale Pump Station
Updated pump operating strategy
Replaced pump impeller to reduce pump station capacity
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementFairfax County
This project included removal and replacement of fuel storage tanks for stand by generators at the Long Branch Sanitary Sewer Pump Station and New Alexandria Stormwater Pump Station. Existing underground storage tanks were replaced with new above ground fuel tanks. The project included installation of piping, valves, fuel polishing systems, day tanks, and appurtenances, as well as associated site work. This project was substantially complete on October 29, 2021.
June 26, 2020 -- PEC seeks to secure contracted professional engineering services to complete (1) a Geotechnical Report and (2) a Final Design for fish-friendly and flood-resilient structures to replace culverts at ONLY the Piney River (VA Rt. 653) pilot project site in Rappahannock County, VA.
Presentation slides from Community Workshop 1 for the Park Lawn Lake Shore Transportation Master Plan, that took place on November 24 and December 3 2016.
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingFairfax County
Design Phase includes:
Finalize sewer alignment
Manhole locations and material selection
Construction phasing plan
Final restoration for former pump station site/access
Existing utility coordination
Easement acquisition (if applicable)
By-pass water & sewer locations
Temporary service outage plan – water/sewer/gas
Traffic control plans
Phasing
Detour and closure plan
The report presents and describes in detail the suggested alternative street light replacement program that will best address all of the critical issues associated with the ultimate goal of continuous lighting and enhanced safety for pedestrians and bicyclists along Belcrest after dark.
Lakevale Estates Collection Improvements Community MeetingFairfax County
Short-term: Install Backflow Devices
Devices installed
Regular system maintenance is ongoing
Mid-term: Temporary modifications to the Lakevale Pump Station
Updated pump operating strategy
Replaced pump impeller to reduce pump station capacity
Long Branch & New Alexandria Pump Station Fuel Tank ReplacementFairfax County
This project included removal and replacement of fuel storage tanks for stand by generators at the Long Branch Sanitary Sewer Pump Station and New Alexandria Stormwater Pump Station. Existing underground storage tanks were replaced with new above ground fuel tanks. The project included installation of piping, valves, fuel polishing systems, day tanks, and appurtenances, as well as associated site work. This project was substantially complete on October 29, 2021.
June 26, 2020 -- PEC seeks to secure contracted professional engineering services to complete (1) a Geotechnical Report and (2) a Final Design for fish-friendly and flood-resilient structures to replace culverts at ONLY the Piney River (VA Rt. 653) pilot project site in Rappahannock County, VA.
Presentation slides from Community Workshop 1 for the Park Lawn Lake Shore Transportation Master Plan, that took place on November 24 and December 3 2016.
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingFairfax County
Design Phase includes:
Finalize sewer alignment
Manhole locations and material selection
Construction phasing plan
Final restoration for former pump station site/access
Existing utility coordination
Easement acquisition (if applicable)
By-pass water & sewer locations
Temporary service outage plan – water/sewer/gas
Traffic control plans
Phasing
Detour and closure plan
The report presents and describes in detail the suggested alternative street light replacement program that will best address all of the critical issues associated with the ultimate goal of continuous lighting and enhanced safety for pedestrians and bicyclists along Belcrest after dark.
Foundation Design For the abutment and footing design, soil anal.docxbudbarber38650
Foundation Design
For the abutment and footing design, soil analysis was required to determine allowable design loads. Our geotechnical engineers have provided a thoroughly soil reports and calculations for the abutment and is located in Appendix XX. With our design constraints, our structural engineers have come to concluded that spread footing design is best for our pedestrian bridge.
Design Criteria
Based on the geotechnical reports, our structural engineers have designed our abutment and footing to transfer the loads from the pedestrian bridge to the underlying soil and to prevent the soil from tipping the abutment over. Our structural team have worked closely with our geotechnical team to design an abutment that capable to support a 144 Kips (Dead + Live) loads coming from the bridge, and to not exceed the bearing capacity of 4000 psf. With the vertical depth of the abutment and footing of 26 ft, our teams already take into consideration that our footing need to be 3 ft below the channel to prevent the soil erosion below the footing. Our abutment and footing will be design for overturning moment and shear coming from soil pushing into the abutment wall. All stresses have been accounted for and designed to be able to handle the above mentioned stresses, all calculations are included in Appendix XX. Both abutment and footing are the same on both end span of the bridge.
Our structural engineers will use 4000 psi concrete, and 60000 psi steel for the abutment and footing design. The abutment dimensions will be 15 ft wide by 24 ft height and thickness of 4 ft. The footing will have dimensions of 15 ft wide by 2 ft depth a thickness of 12 ft.
With the dimensions of abutment and footing calculated, the righting moment created by reinforced concrete is much larger than the overturning moment pushing against it and is adequate for the bridge support.
Table of Contents
1. Executive Summary
2. Project Personnel
3. Preliminary Design Analysis
4. Appendices
a. Overall Plans and Exhibits
b. Traffic Study
c. Geotechnical Evaluation
d. Site – Civil & Utilities
e. Structural Calculations
f. Construction
g. Summary of Assumptions
MFilanc_FIL
Note
MFilanc_FIL
Text Box
The table of contents should be broken down more. For example: 1.1. Introduction
1.2. Background of project
1.3. purpose and Objective
Each one should also list which page and the entire report should have pagination.
Executive Summary
Introduction
Donovan & Associates looks forward to providing professional engineering services to
the City of Escondido for the design and construction of the new Escondido Pure Water
Pipeline.
Donovan & Associates prides itself in offering the most cost-effective and sustainable
solutions for
public infrastructure improvements and land development. The new Escondido Pure
Water Pipeline will be located on Washington Avenue and Spruce Street in the City of
Escondido. This
project will include the evaluati.
Proposal to reclaim Chicago's lakefront from the highway using immersed tunnelsJames Chuck
My exploration (and proposal) of how to improve Chicago's North Lake Shore Drive as a multi-modal transportation facility and reclaim the shoreline for the City and its Citizens.
A thoughtful and sustainable strategy to give urban shores and coasts a second chance
The work on this project included investigation and repair to an 8-inch sewer line in Waterway Drive which had been previously lined with a plastic liner system. The project location was in Waterway Drive from Cavalier Court to the vicinity of Half Moon Circle. The project involved setting up a bypass system to remove sewage from the line so the pipe could be properly cleaned and inspected. Following this process, it was determined the plastic liner was causing capacity issues. It was determined that the liner could be repaired using internal methods and no excavation was needed. In addition, the five manholes associated with the segments of pipe in the project area were also rehabilitated. This project was substantially complete on June 25, 2021.
Getting the Lead Out: How Lansing, Michigan Replaced 13,500 Lead Service Line...Environmental Initiative
Lansing is one of only two cities in the United States to have completely replaced their lead service lines and is advising Flint, Michigan in the wake of their drinking water crisis. Scott Hamelink talked about how and why Lansing replaced their lead pipes, focusing on the methods that allowed them to cut the cost of replacement by more than half.
Congress Parkway Construction Overview, January 2010Daniel X. O'Neil
Congress Parkway improvement project
Michigan Avenue to Wells Street.
Includes history, background, project goals & scope, as well as schedule and public outreach tactics
1. TA-T3-02
WATER, SEWER AND TRAFFIC IT’S ALL ABOUT THE FLOW
Mark Oberschmidt, P.E., Stantec, Fort Collins, Colorado
Robin Dornfest, P.G., Brierley Associates, Fort Collins, Colorado
Matt Fater, P.E., Fort Collins Utilities, Fort Collins, Colorado
Owen Randall, P.E., Fort Collins Utilities, Fort Collins, Colorado
Don Silar, P.E., Stantec, Fort Collins Colorado
Dan Giesler, Connell Resources Inc., Fort Collins, Colorado
1. ABSTRACT
When the City of Fort Collins (City) Utilities (Utilities) decided they needed to replace an existing 4-inch
Cast Iron Pipe (CIP) waterline in College Avenue (State Highway 287) to increase flow capacity, they knew
that they would have to get creative in order to reduce impacts to third parties and streamline the
construction. Replacing a 90-year old waterline under one of the busiest thoroughfares in the City and
replacing an 8-inch sewer line running under a very busy intersection would require extensive coordination
and planning. The utility department put this project into their Alternative Project Delivery System (APDS)
and put together the APDS team of Engineers (Stantec & Brierley Associates) and Contractors (Connell
Resources &Temple Construction) to develop a design and a construction plan that would
• Minimize third party impacts to traffic and pedestrians, local businesses, and Colorado State
University
• Share project risks between the City, Design Engineer(s), and Contractors
• Maintain traffic flow- vehicular and pedestrian
• Meet a tight construction schedule
• Reduce pavement replacement costs
• Improve water distribution capacity and increase sewer flow capacity
• Provide a safe work zone
The team, supported by TT Technologies and Underground Solutions, decided to replace the pipe in situ
using a combination of Pipe Bursting and Horizontal Directional Drilling (HDD) with Fusible PVC pipe
(FPVC) and Certa-Lok® pipe. Pipe Bursting was used where new pipe followed existing pipe alignments
and HDD was used to relocate waterline for easier future maintenance and on side streets where there was
no existing pipe.
North American Society for Trenchless Technology (NASTT)
NASTT’s 2015 No-Dig Show
Denver, Colorado
March 15-19, 2015
Paper TA-T3-02 - 1
2. 2. INTRODUCTION
In the spring of 2013 The Colorado Department of Transportation (CDOT) informed the City of Fort Collins (City)
that they would be doing a mill and overlay project during the summer of 2015 on College Avenue (State Highway
287) from Harmony Road at the south end of town to Mulberry Street at the entrance into the downtown area of Fort
Collins known as Old Town. College Avenue is the main north-south thoroughfare through Fort Collins passing
10,000’s of vehicles a day. In general when an existing road is improved, it is also important to look at the underground
infrastructure to assess whether it will require maintenance or repair in the near future post road improvement so as
not to have to cut in to new asphalt right after it has been placed.
Roads and underground infrastructure in the Old Town area date back to the early 1920’s. Parts of Old Town have
redeveloped in the past 20-years increasing the demands on this aging infrastructure. The condition of the existing
cast iron pipe limited fire flows and created water quality problems. These were some of the reasons the City decided
to completely replace this section of waterline in addition to wanting new waterlines under the roadway before CDOT
paved College.
Figure 1: Cast Iron Pipe with holes
Figure 2: Tuberculation in existing Cast Iron Pipe
Two parallel lines extending south from Mulberry Street servicing buildings on the east and west sides of College
Avenue were considered for replacement or abandonment.
• from Mulberry Street south to Buckeye Street on the east side of College (4350 LF 4-inch CIP) and
• from Mulberry Street south to Laurel Street on the west side of College (1350 LF 6-inch CIP)
Paper TA-T3-02 - 2
3. The first questions to be answered were what size of waterline was needed along the route to meet domestic and fire
demands and were the two parallel lines required. The City, together with Stantec, modeled the existing and expected
development in the area and determined that both lines could be replaced with a single 8-inch line along the east side
of College with services connecting across the street to the properties on the west. Additional fire hydrants were also
placed along the route to improve coverage and better meet fire code requirements.
3. HOW TO
BUILD IT
With that question out of
the way, Fort Collins now
needed to determine how
to build it. The Utilities
department has developed
a process to design and
manage all of their
projects called the
Alternative Project
Delivery System (APDS)
that brings together
Utilities and other City
departments, the Design
Engineer(s) and the
General Contractor at the
outset of the design
process to evaluate all
aspects of the project from
design to construction.
Utilities put together the
APDS project team of
Stantec, Brierley
Associates and Connell
Resources (Connell) in
the summer of 2013.
The APDS system has
several advantages over
the traditional Design –
Bid – Build method of
municipal construction
projects including;
• Introducing the
Contractor at the
outset of design
rather than
weeks before
bids are due provides them with a better understanding of project costs, schedules and impacts and thus
reduces their risk for the project. In this case, the design process took 7-8 months with regular design progress
meeting including the entire APDS team.
• Allowing the Engineer and Contractor to work through the design with means and methods in mind along
with the engineering aspects.
• Taking into account other aspects of the project including public outreach, planning for traffic control (crucial
for this project) as part of the means and methods and coordinating with other City departments, the project
team developed a better understanding of the soft and hard costs and schedule for the project.
Figure 3: Map of Project Area
Paper TA-T3-02 - 3
4. • Allows the team to look at alternative methods of construction, such as trenchless installation, with time to
look at the pros and cons of each method and without the issues relating to low bids from contractors who
might not have the experience with newer technology.
• Eliminates as many unknowns as possible, thus reducing risk to all parties.
• Shares risk between the City, Design Engineer(s), and Contractor.
Survey of field conditions was the first step along with determining the number, size and location of all existing water
services along the route. Once the locations of everything where known, the APDS team got together to look at means
and methods of construction with consideration for traditional open cut and trenchless methods.
The APDS team looked at traditional open cut methods of replacing the water line but determined that there were a
lot of disadvantages. The biggest disadvantage to the open cut method was third party impacts associated with having
to shut down the entire north bound (NB) stretch of College Avenue for about one mile from Prospect Road on the
south to Mulberry Street on the north. Shutting down the NB stretch of College Avenue would have had significant
impacts to vehicular flow along the corridor. The City Streets Department made a very strong argument that this could
not be done given the daily vehicular volume along College and the nearest comparable north-south streets being 1-
mile east and west of College.
Additionally the open cut method would have required significantly more asphalt replacement versus trenchless
installation alternatives. If an open cut method was utilized to install the waterline, Connell Resources estimated 3,100
tons of asphalt would be required to patch the roadway. Approximately 5,800 LF of waterline was installed under
roadways with this project utilizing trenchless installation methods reducing the asphalt requirement to 1,300 tons. In
addition to more asphalt, there would have also been the additional cost and time associated with replacing curb, gutter
and sidewalk given the proximity of the waterline to the curb. Installing the lines using trenchless technology resulted
in a small amount of curb, gutter and sidewalk being replaced where new services or fire hydrant installation required
it.
Finally, the construction duration for the project would have been significantly longer using open cut methods. It is
estimated that waterline (installation only) production along the College portion of the project would have been 60-
70 feet per day not including setting up the temporary water or reconnecting services back in (62 working days @ 70
feet per day just to install 4340 LF of waterline). As an example, the waterline installation including temporary water
and services tied over from Mulberry to Laurel began on 5/27/14 and was completed on 6/25/14 including two side
street installations for a total production (temporary water, pipe installation and testing, services, and patching) of
1800 LF of pipe in 24 days or 75 feet per day. Several more weeks would have been added to this section of the project
if open cut methods had been used.
The contractor also replaced an 8-inch sewer main through the Laurel and College intersection, which could have
possibly taken a month to complete using open cut methods given the traffic load at that intersection. The 400 LF of
8-inch sewer line was burst up to a 12-inch line with construction only taking a week from start to finish including
five deep service tie-ins.
The other issue relating to College Avenue and open cut methods was that there are a mixture of asphalt pavement
sections and asphalt over concrete sections in College and there were areas of widely varying thicknesses of asphalt.
This posed a problem as current City policy requires that patching pavement thicknesses be the existing pavement
thickness plus one inch. This has led to pavement thicknesses in excess of 18-inches where the letter of the law was
followed. Also the City has in the past required concrete be replaced in kind extending the project duration due to the
time required for concrete placement and curing. This was resolved as a result of the APDS system and is the subject
of another discussion.
Based on the project constraints discussed above, the APDS team opted to look at trenchless methods of installing the
new waterline and sewer line. Brierley Associates was tasked with determining the subsurface conditions under
College to ascertain whether or not they would be suitable for trenchless installation methods. They concluded that
the trenchless installation of new pipelines was a suitable method given the existing ground conditions under
College Avenue and the adjoining side streets.
Paper TA-T3-02 - 4
5. Initially, the APDS team looked at pipe bursting for the entire length of the project as it would eliminate the
need to change technology mid-stream. The alignment of the existing 4-inch CIP waterline caused the team to
rethink this idea. The existing 4-inch CIP was located approximately 3-ft off the eastern curb line of College
from Mulberry south to Elizabeth Street (2750 LF). From Elizabeth south to Buckeye Street the waterline
moved further out into the middle lanes of College caused by the widening and realignment of College back in
the 1950’s. The city preferred that the entire line be closer to the eastern curb line along the entire route for
maintenance reasons and so that the two lanes of NB traffic could be maintained during construction. This
required creating a new alignment for the waterline south of Elizabeth, which brought Horizontal Direction
Drilling (HDD) into the planning discussions.
Figure 4: HDD Pipe Sling
The next task for Brierley Associates was to determine if Pipe Bursting and HDD were both viable options for
the project with the limits of the project as follows. Pipe bursting essentially installs a new pipe using the
existing pipe as a conduit. Two pits, receiving and pulling, are excavated at the ends of the pipe being replaced.
Rods are inserted in the pipe at the receiving pit and pushed to the pulling pit where a pipe bursting head larger
than the existing pipe (upsized from 4-inches to 8-inches) is attached to the new pipe and the rods and pipe are
pulled back bursting/breaking the old pipe in-situ while filling the resultant cavity with new pipe. The new pipe
is then reconnected to the existing services and the exposed areas are backfilled and paved if under roadways.
Pipe bursting reduces the amount of excavation required to replace old waterlines and more pipe can be installed
per day than using open trench construction methods. Approximately 700 LF was installed in less than 2-hours
with the first pipe bursting operation after a little over 1 week of preparation including exposing existing
services, installing temporary waterline and connecting the services. As noted earlier in the report the contractor
estimated that they would complete approximately 60-70 feet of pipe installation per day using open cut
methods or 350-500 feet in a little over a week.
HDD is similar to pipe bursting except that a machine creates a new opening underground for the waterline
using an augur and drilling fluids. A pilot hole is initially drilled along the alignment and at the required depth
and then the hole is enlarged to accommodate the new pipe by pulling a reamer back through the hole. That and
the drilling fluids reduce the pressure required to pull the pipe back through the hole in the final step of the
Paper TA-T3-02 - 5
6. process. The length of the pull takes into account the allowable pulling forces on the pipe in comparison to the
resistive forces generated against the pipe by the soils as well as the size of the pipe. The first HDD operation
took about 3 days to set up and execute with 300 LF of pipe being pulled in about 1-hour.
Brierley Associates determined that both trenchless methods were viable in their report (Brierley Associates (2014).
They concluded that the soft Lean Clay (CL) at the elevation of the proposed pipe were sufficiently displaceable,
based on blow counts to allow for a successful pipe bursting operation. Along with this they noted that the existing
depth of the pipe was sufficient to minimize the chance of pavement movement at the surface during bursting
operations.
The also concluded based on the existing soils conditions at the southern end of the project that had blow counts in
the 4-17 bpf (blows per foot) range were soils that could be excavated using a mud motor, which is used in HDD.
Testing determined the unconfined compressive strength of the subsurface to generally range from 1,510 to 5,740
pounds per square foot (psf) near the proposed depth of installation. Therefore from a geotechnical perspective both
HDD and pipe bursting were considered suitable methods to install the waterline in College Avenue.
Figure 5: Connell Team on site
Based on the results of the Brierley Associates report and discussions amongst the APDS team, it was decided that
Pipe Bursting and HDD would be used to install the new waterline and sewer line for this project. This project was
divided into sections of pipe bursting and HDD installation methods as follows.
• Pipe Bursting where the existing pipe alignment is being maintained – waterline from Mulberry to
Elizabeth and across the intersection of Laurel and College for both water and sewer lines
• HDD from Elizabeth south to Buckeye where a new alignment was defined closer to the eastern curb
line as required by the City.
• HDD several side laterals at crossing streets to provide additional looping to existing waterlines in
Remington Street, one block east of College Avenue.
o Buckeye – 300 LF
o Garfield – 300 LF
o Myrtle – 500 LF
• 100 LF of replacement waterline was installed using pipe bursting at the intersection of Laurel Street
and College Avenue.
• 400 LF of replacement sewer line was installed using pipe bursting at the intersection of Laurel Street
and College Avenue.
The APDS team also verified the pull forces for the HDD portion of the project based on decisions made as to the
locations of the pulling and receiving pits in order to determine the type of pipe used in the installation. For the HDD
installation and the given lengths of each drill, Brierley Associates determined a maximum pull force of 14 kips or a
maximum pulling stress of 978 psi which was significantly lower than the allowable pull strength of 35.7 kips for the
Fusible PVC (FPVC) pipe.
Paper TA-T3-02 - 6
7. Fusible HDPE and Fusible PVC (FPVC) were considered for both portions of the project and it was decided that
FPVC would be the pipe used based on the following.
• The City currently uses PVC for all their new waterline and they can use the same fittings whether working
with PVC or FPVC
The APDS team also worked out the potential issue of inadvertent drill fluid loss or frack-out with this project by
planning to use the service pits installed at the onset of each section of pipe installation with the temporary water
service as relief wells, allowing for collection of drill fluids that might be released during the HDD process. This was
accomplished as the service pits were excavated at the beginning of each section and the services tied over to a
temporary water service. The pits remained open during construction allowing any fluids a point of release that would
not spill out onto the road or into a storm sewer system.
Figure 6: HDD Machine at Buckeye Street
4. WHEN TO BUILD IT
The other planning decision made by the APDS team was the timing of the construction. Fort Collins is the home of
Colorado State University (CSU) with a student population of 32,000 and growing. CSU fronts on College Avenue
and has 3 points of access to their campus off College Avenue within the project limits. With this in mind the City
opted to plan for construction during the summer (mid May – mid August) when the majority of students would be
gone reducing the amount of traffic on this section of College Avenue. However, this placed a burden on Connell and
their subcontractors to be able to install this much waterline and reconnect all the services in this short of a time frame
(75 working days). The APDS team worked out the sequencing of the following.
• Installing and connecting temporary water services
• Turning off and isolating individual line sections for replacement
• Installing the new lines and testing
• Reconnecting the service lines and any side laterals
• Patching the service holes and any other excavating areas.
• Other work as needed
• Project clean up
Paper TA-T3-02 - 7
8. Figure 7: Pipe Bursting Rod going in
5. INSTALLATION
The final plans worked out the following installation sections and phasing to limit the amount of time in College
Avenue by completing a lot of the side street work ahead of the end of the CSU semester (May 15th
) and not closing
any lanes in College until after the May 15th. Phase 1 included
• Buckeye Street Waterline (HDD) 300 LF
• Edwards Street Waterline (Open Cut) 150 LF
• Garfield Street Waterline (HDD) 300 LF
Construction on the side streets began on 5/5/14 and was completed by 5/23/14 (15 working days). Phase 2 work in
College Avenue began after Memorial Day and was phased as follows.
1. Mulberry to Myrtle – Pipe Burst 500 LF Waterline – also included a 500 LF HDD waterline portion on
Myrtle Street
2. Myrtle to Laurel – Pipe Burst 700 LF Waterline
3. Laurel and College Intersection– Pipe Burst 100 LF Waterline
4. Laurel to Locust – Pipe Burst 1000LF Waterline
5. Laurel and College Intersection– Pipe Burst 400 LF Sanitary Sewer Line
6. Laurel to Elizabeth – Pipe Burst 400 LF Waterline
7. Elizabeth to Buckeye – HDD in 3 reaches from north to south
a. Elizabeth to Garfield 500LF Waterline
b. Garfield to Pitkin 540 LF Waterline
c. Pitkin to Buckeye 345 LF Waterline
8. Mulberry Street Tie in – 80 LF waterline burst set up and completed in one long night
The lengths of the HDD reaches were based on reasonable drill lengths and logical tie-in places for the side street
laterals installed earlier in the project. These locations could also be used as pulling and receiving pits minimizing
the number of mobilizations required for each drill (i.e. spin the machine around and drill the other direction).
Water services on the west side of the road were installed using a Grundopit machine supplied by TT Technology.
This proved to be quite efficient and kept traffic moving on the south bound side of College with very minimal
interruptions. As the project continued the crew was able to complete as many as five services across the road per day.
Paper TA-T3-02 - 8
9. Figure 8: Bursting machine on College Figure 9: Pipe ready to be pulled back into existing
pipe to be burst
Additional trenchless work on the project included Pipe Bursting 400 LF of 8-inch sewer up to a 12-inch across the
Laurel and College intersection using Certa Lok® pipe and HDD installation of a 12-inch storm sewer under the
sidewalk between Edwards and Garfield Street (300 LF) so as to abandon an existing irrigation/storm line that was
failing but inaccessible for open cut replacement.
6. TRAFFIC FLOW
Traffic flow was maintained during the installation of the waterline. It was thought that two lanes of NB traffic could
be maintained along the entire length of the project. However, when it came down to closing the section from Laurel
Street North to Mulberry (2 blocks), it was decided to limit traffic to one lane as this allowed for more efficient
movement of construction equipment along this section speeding up the installation. Jersey Barriers were used to line
the limits of the construction keeping the construction crew safe. Continuous coordination with City traffic control
personnel and their prompt responses were critical to keeping the project moving smoothly. Short term soft closures
were scheduled during off peak hours when the pipe had to be pulled into place for either bursting or HDD installation.
From Laurel south only one lane was closed and this did slow down the progress somewhat. In hind sight, the team
should have considered additional soft lane closures during certain phases such as flo-filling of excavated holes to
allow easier access to those locations reducing the time spent completing these tasks and maintaining adequate traffic
flow. This is one of the lessons learned post project that will be included in future trenchless projects.
Paper TA-T3-02 - 9
10. 7. RESULTS
The project succeeded in meeting the demands outlined at the beginning of this paper.
• Project risks and unknowns were identified early in the design stage and planned for,
• Traffic flow was maintained with minimal disruption.
• The construction schedule was maintained even with the additional work that was added to the project
• There was a reduction in cost of asphalt required.
• Services were installed to the west side of the road without having major lane closures in the SB lanes
• There was minimal construction impact to adjoining properties
• Safety was maintained for the construction crew, pedestrian and vehicular traffic.
• Additional waterline capacity was created for the surrounding users as well as increased ability to handle
fires with the installation of additional fire hydrants along the route.
• An important piece of sewer line was upsized to handle additional flows coming from recently redeveloped
upstream areas.
8. CONCLUSION
The City Fort Collins Utilities was pleased with the results of this project and will continue to make use of trenchless
technology as they replace and rehabilitate underground pipes in Old Town and other locations throughout the City.
As with every project, lessons were learned including the following:
• Trenchless methods for pipeline replacement are cost effective and can significantly minimize third party impacts
and make a project flow smoothly with proper planning.
• With proper planning, trenchless methods can save time for waterline installations.
• Plan for short lane closures to facility easier placement of flo-fill in the holes at service and lateral connections as
well as sending and receiving pits along the construction route. Backing concrete trucks into the area to place the
flo-fill was difficult and time consuming.
• Connecting smaller diameter pipe into large diameter pipe needs to be considered as well since there is a
possibility of additional fittings near the connection. We encountered this at the connection between the 4-inch
and the 16-inch line in Mulberry. A vertical bend stopped the burst and required open cut and removal.
• We used 40-ft sticks of FPVC on this project and may consider shorter sticks in the future to speed up the pipe
transport around the site.
• Reflective flags will be used on the Jersey barriers for future projects to improve visibility and safety of workers
and vehicular public.
• Build a more realistic schedule for future trenchless projects based on the results of this project
9. REFERENCES
Brierley (2014) - Geotechnical Investigation Report South College Avenue Water Line Replacement, Fort
Collins, Colorado January 15, 2014
Paper TA-T3-02 - 10